696 CONSTRUCTION PROJECT
Cities of Warren, Centerline, Roseville: 75 to 94
and
Oakland County: 75 to 275
April - November 2018
P R O J E C T L I M I T S
I M P R O V E M E N T S
C O S T
OVERVIE W
A N T I C I PAT E D S C H E D U L E
M A I N T E N A N C E O F T R A F F I C
WHY IS IT HAPPENING NEXT YEAR?
I-75 Mega Project in 2019
Poor Pavement ConditionsGood
Fair
Poor
Michigan Roads Ratings
PROJECT LIMITS
East of 75 to 94• Replace all pavement• WB direction closed completely• EB open and shifted during project• Repair service drives in 2019
West of 75 to 275• Pavement repairs in both directions• Closures evenings and weekends• Maintenance to drainage systems
PAVEMENT SELECTION
Concrete is proposed
Public Act 79 (1997) Pavement
analysis must be done when
pavement costs exceed $1Mil
Costs based on material prices and
overall costs of the life cycle of the
road
*MDOT Pavement Design and Selection (2012)
Construction is anticipated to begin
April 2018 through November 2019
(mainline completed in 2018)
COST & SCHEDULE
Preliminary budget of $100M
Open to traffic November 2018
East of 75 to 94
Closed: WB 696 traffic for the duration of mainline
Open: 696 EB throughout project
When WB lanes are completed, EB traffic will be
placed onto newly constructed WB lanes
I-696 EB lanes closed for reconstruction (late July)
Project Construction April - November 2018
MAINTENANCE OF TRAFFIC
ANTICIPATED MILESTONE DATES
Apr
2018Mar
2018Nov
2018Jan
2018Nov
2019
Plan Submittal Job Letting Construction Start
Open to Traffic Construction Completion
Engaging Stakeholders
✓ Distributing information
✓ Public Meetings
✓ Community Partnerships
Media
✓ Digital and traditional
✓ www.MovingMacomb.org
✓ Twitter and Facebook
COMMUNICATIONS PLAN
CONTACT US/QUESTIONS
Spiro Kotsonis, P.E.696 Project [email protected]