Stakeholder MeetingDecember 16th, 20141:30 pm to 2:30 pm
Interstate 229 Major Investment StudyExit 3 – Minnesota
Avenue
Benson Road
60th Street N.
Benson Road
60th Street N.
![Page 2: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/2.jpg)
Study Area Map
I-229 Corridor Study
Additional StudiesExit 3 – Minnesota AveExit 6 – 10th StreetExit 9 – Benson Road
Solberg Avenue Overpassto60th Street N. Overpass
![Page 3: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/3.jpg)
Study Advisory PartnersSouth Dakota Department of Transportation (SDDOT)
South Dakota Highway Patrol
City of Sioux Falls
Sioux Falls Metropolitan Planning Organization (MPO)
Federal Highway Administration (FHWA)
![Page 4: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/4.jpg)
Exit 3 (Minnesota Avenue) Crossroad
Study Goals• Reduce traffic congestion • Evaluate interchange options• Integrate plans for the 49th Street
Extension with the interchange options developed
• Improve pedestrian and bike access to the Big Sioux River Pathway
• Improve safety for corridor users• Improve vehicle safety to Yankton Trail
Park
![Page 5: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/5.jpg)
Minnesota Avenue Corridor Overview
Intersection projected to be over capacity by 2035.
43 Crashes in 4 year period (rear end and
angle crashes).
Stop-controlled approach projected to be over capacity by 2018.
![Page 6: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/6.jpg)
Minnesota Avenue Corridor Overview
Park Entrance difficult to enter/exit during peak hours (mostly related to
soccer season).
6 Crashes in 4 year period (rear end crashes
near gore area).
Stop-controlled approach projected to be over capacity by 2018.
Intersection projected to be at capacity by 2035.
![Page 7: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/7.jpg)
Minnesota Avenue Corridor Overview
57 Crashes in 4 year period (rear end and
angle crashes).
Traffic backs up north from I-229; numerous driveways increase
potential for conflict.
Intersection projected to be over capacity by 2035.
Stop-controlled approach is over capacity.
![Page 8: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/8.jpg)
Preliminary local street extensions, interchange concepts, and traffic impact analyses in the vicinity of I-229 & Minnesota Avenue were identified in the following studies:
41st Street Corridor Study
Sioux Falls Major Street and Access Management Plan
2000 and 2010 Decennial Interstate Corridor Studies
49th Street Extension Study
Traffic Impact Studies – Costco, Scheels, and Walmart
Relevant Previous Studies
![Page 9: 60 Street N. Benson Road MIS Stakeholder Meetings_Mi… · Benson Road 60th Street N. Benson Road 60th Street N. Thanks for Attending!!!!! PROJECT CONTACTS: Jason Kjenstad – HDR](https://reader033.vdocuments.us/reader033/viewer/2022060904/609fd19296fb285c366494ad/html5/thumbnails/9.jpg)
© 2014 HDR, all rights reserved.
Interstate 229 Major Investment StudyExit 3 – Minnesota
Avenue
Benson Road
60th Street N.
Benson Road
60th Street N.
Thanks for Attending!!!!!
PROJECT CONTACTS:Jason Kjenstad – HDR Engineering, Inc.605-977-7740 or [email protected]
Ross Harris– HR Green, Inc.515-657-5263 or [email protected]
Shannon Ausen – City of Sioux Falls605-367-8607 or [email protected]
Steve Gramm – SDDOT Project Development605-773-6641 or [email protected]