Milestone Chart (Planned)
Sheet1
MonthsMayJuneJulyAug
ACTIVITIESResourceDurationStartEndW1W2W3W4W5W6W7W8W9W10W11W12W13W14W15W16W17
Formation of Areas and selection of Area Leader/Coordinator
1 WeekW1W1
Photographs of area before implementation of 5S
1 WeekW1W1
Selection of other Area members
1 WeekW2W2
Selection of Evaluators
1 WeekW2W2
Training Program for Area Leaders
1 WeekW3W3
Finalisation of Audit format
1 WeekW3W3
Training of other Team members
3 WeeksW3W5
Audit before implementation
1 WeekW3W3
Trial Implementation
3 WeeksW4W6
Audit after Trial implementation
1 WeekW7W7
Total 5S Implementation (Area)
9 WeeksW8W16
Auditing
1 WeekW17W17
Photographs of area after implementation of 5S
1 WeekW17W17