Milestone Chart (Planned) Months D uration S tart End W1 W2 W3 W4 W5 W6 W7 W8 W9 W 10 W 11 W 12 W 13 W 14 W 15 W 16 W 17 1 W eek W1 W1 1 W eek W1 W1 1 W eek W2 W2 1 W eek W2 W2 1 W eek W3 W3 1 W eek W3 W3 3 W eeks W3 W5 1 W eek W3 W3 3 W eeks W4 W6 1 W eek W7 W7 9 W eeks W8 W 16 1 W eek W 17 W 17 1 W eek W 17 W 17 Aug M ay Total 5S Im plem entation (Area) Photographs ofarea before im plem entation of5S Selection ofotherArea m em bers Selection of Evaluators July June Form ation ofAreas and selection of Area Leader/C oordinator AC TIV ITIES AuditafterTrial im plementation Finalisation ofAuditform at Photographs ofarea after im plem entation of5S Auditing Training Program forArea Leaders Auditbefore im plementation Training ofotherTeam m em bers Trial Im plementation

Upload: arnab-mallick

Post on 26-Nov-2015

8 views

Category:

Documents


1 download

DESCRIPTION

5S Road Map Template

TRANSCRIPT

  • Milestone Chart (Planned)

    Sheet1

    MonthsMayJuneJulyAug

    ACTIVITIESResourceDurationStartEndW1W2W3W4W5W6W7W8W9W10W11W12W13W14W15W16W17

    Formation of Areas and selection of Area Leader/Coordinator

    1 WeekW1W1

    Photographs of area before implementation of 5S

    1 WeekW1W1

    Selection of other Area members

    1 WeekW2W2

    Selection of Evaluators

    1 WeekW2W2

    Training Program for Area Leaders

    1 WeekW3W3

    Finalisation of Audit format

    1 WeekW3W3

    Training of other Team members

    3 WeeksW3W5

    Audit before implementation

    1 WeekW3W3

    Trial Implementation

    3 WeeksW4W6

    Audit after Trial implementation

    1 WeekW7W7

    Total 5S Implementation (Area)

    9 WeeksW8W16

    Auditing

    1 WeekW17W17

    Photographs of area after implementation of 5S

    1 WeekW17W17