A endaDefine Master Production Schedule (MPS) and
Discuss Some Key Issues Managing Master
MPS & competitive environments [MTS, ATO MTO]
Structuring of Bill of Materials (BOM)Lead Time and Time fences
Creating Master Schedule
,Available to Promise
Rough Cut Capacity Planning
-
7/29/2019 5.MasterProdScheduling
2/31
Manufacturin Resource Plannin - MRP-II
MATERIAL PLAN(PRODUCTION
CAPACITY PLAN(RESOURCE USE PLAN)PLANNING
HORIZON
Input from Higher Level Business Plan
Production Resource RequirementL ong Term
Master Plan
Sales Planning
ann n
Rough Cut Capacity
Planning (RCCP)
an
M aster Production
Scheduling (MPS)M edium Term
DemandM anagement
Aggregate Planing
M aterial RequirementPlanning (mrp)
Capacity RequirementPlanning (CRP)
Production ActivityControl/Shop Floor CtrlShort Term
Execution Plan
Hierarchy of Planning in MRP-I I
-
7/29/2019 5.MasterProdScheduling
3/31
Relationship between Aggregate Plan (Overall
- family total quantity of mattress in production plan is disaggregated to plannedproduction quantities of three models or end items in MPS for first 9 weeks
Month 1 2 3 4 5 6Matress Production 1000 900 950 950 900 900
ggrega e ro uc on an or Mattress Famil Pseudo Part Name
Week 1 2 3 4 5 6 7 8 9
Model-327 200 200 100 100
-Model-749 200 100 100 250Total 200 200 200 200 200 200 200 250 250
Master Production Schedule (MPS) for
Mattress Models Real Parts
-
7/29/2019 5.MasterProdScheduling
4/31
Master Production Schedule (MPS)
-
what the company plans to produce expressedin specific configurations, quantities, and dates.
Master Production Schedule (MPS) is definedlikely to be build] for those items assigned tomaster scheduler. It drives material
.
-
7/29/2019 5.MasterProdScheduling
5/31
[Although term MS is used interchangeably with MPS sometime it
The master schedule (MS) is a time-phased,
including the forecast and the backlog
(customer orders received), the masterpro uc on sc e ue e suppy pan , eprojected on hand (POH) inventory, and theavailable-to- romise ATP uantit .
It helps the master scheduler creating masterproduction schedule (MPS).
-
7/29/2019 5.MasterProdScheduling
6/31
An Example Master Schedule [MS]Week
0 1 2 3 4 5Month
Total
Aggregate forecast 100 200 150 150 200 800
Production 150 150 150 150 150 750Aggregate inventory 400 450 400 400 400 450Item AForecast 60 120 90 90 120 480Production (MPS) 150 150 150 450
Inventory 300 390 420 480 390 270Item BForecast 40 80 60 60 80 320Production (MPS) 150 150 300Inventory 100 60 -20 -80 10 80
Total Production 150 150 150 150 150
Aggregate plan capacity 150 150 150 150 150Deviation 0 0 0 0 0
Total Inventory 400 450 420 480 400 350
Deviation 0 -20 -80 0 0
-
7/29/2019 5.MasterProdScheduling
7/31
Manufacturing Environments and MPS
The competitive strategy of an organization may be
any of the following:MTS: Make finished items to stock (sell fromns e goo s nvenory
ATO: Assemble final products to order and make, ,
MTO: Custom design and make-to-order
It is not unusual for an organization to havedifferent strategies for different product lines and,t us, use erent approac es.
-
7/29/2019 5.MasterProdScheduling
8/31
MPS in Make-to-Stock Environment
Limited number of end items assembled from relatively largenumber of components. e compe ve s raegy o ma e- o-soc emp aszes
immediate delivery of reasonably priced off-the-shelf standarditems. In this environment the MPS is the anticipated buildschedule of the items required to maintain the finished goods at
the desired level. Note that the MPS is the same as the final.
End Item/Product
RawMaterial/Components
-
7/29/2019 5.MasterProdScheduling
9/31
Product Structure Tree or Bill of Material
THE BILL OF MATERIAL (BOM): An inclusivedefinition of a final roduct includes a list of the items,
ingredients, or materials needed to assemble, mix, orproduce that end product. This list is called a bill of material.
Table
. .,in Make-to-Stock environment.
-
7/29/2019 5.MasterProdScheduling
10/31
MPS in Assemble-to-Order
In this environment, options, subassemblies and components are.
to be able to supply a large variety of final product configurationsfrom standard components and subassemblies within a relativelyshort lead time.
End Item/Product
FASExample: automobile may
MPS Assemblies/options
be ordered with or withoutair conditioning, an option.
MPS for the options,accessories, and common
Raw Material/Components
componens as we as na
assembly schedule (FAS).
-
7/29/2019 5.MasterProdScheduling
11/31
MPS in Make-to-Order Environment
on customer orders.In many situations the final design of an item is part of what ispurchased. The final product is usually a combination of standarditems and items custom designed to meet the special needs of thecustomerExample, special trucks for off-the-road work on utility lines and
facilities are another. Thus, there is one MPS for the raw material
End Item/Product
, ,stock and another MPS for the custom engineering, fabrication,and final assembly.
FAS
Raw Material/ComponentsMPS
-
7/29/2019 5.MasterProdScheduling
12/31
Structuring of Bills of Material forn envronmen s
Requires forecast of options as well as totaldemand.
or op ons, accessores commoncomponents developed based on anticipated orforecast demand.
FAS for end item should be developed based onbooked orders.
Modular Bill of Material, a planning bills ofmaterial is used for this purpose
-
7/29/2019 5.MasterProdScheduling
13/31
Modular BOM(A type of planning BOM)
Modular billsModular bills--Product assembled from ma orProduct assembled from ma or
subassemblies & customer optionssubassemblies & customer options
--Modular bil l kept for each majorModular bill kept for each majorsu assem ysu assem y
--Simplif ies forecasting & planningSimplif ies forecasting & planning
slide)slide)Total: 3 x 8 x 3 x 8 x 4 = 2 304Total: 3 x 8 x 3 x 8 x 4 = 2 304
configurationsconfigurations
Only: 3 + 8 + 3 + 8 + 4 = 26 modular billsOnly: 3 + 8 + 3 + 8 + 4 = 26 modular bills
-
7/29/2019 5.MasterProdScheduling
14/31
Modular Bills of Material
-Disa re ate the rou total to the to module/o tion total based onproportion factors shown in modular BOM
-Safety stocks for options to absorb variations in mix can be included
X-10 Automobile
Engine(1 of 3)
Exterior color
(1 of 8)
Interior
(1 of 3)
Interior color
(1 of 8)
Body
(1 of 4)
44--Cylinder (.40+.1)Cyl inder (.40+.1) Br ight red (.10)Bright red (.10) Leather (.20)Leather (.20) Grey (.10)Grey (.10) Sports coupe (.20)Sports coupe (.20)
66--Cylinder (.50)Cylinder (.50) White linen (.10)White linen (.10) Tweed (.40)Tweed (.40) Light blue (.10)Light blue (.10) TwoTwo--door (.20)door (.20)
-- y n er .y n er . u p ur ye ow .u p ur ye ow . us .us . ose .ose . our our-- oor .oor .
Neon orange (.10)Neon orange (.10) Off Off--white (.20)white (.20) Station wagon (.30)Station wagon (.30)
Metalli c blue (.10)Metallic blue (.10) Cool green (.10)Cool green (.10)
Emerald green (.10)Emerald green (.10) Black (.20)Black (.20)
Jet black (.20)Jet black (.20) Brown (.10)Brown (.10)
Champagne (.20)Champagne (.20) B/W checked (.10)B/W checked (.10)
-
7/29/2019 5.MasterProdScheduling
15/31
Plannin Horizon of MPS The planning horizon is the amount of time the master schedule extends into
the future. A rinci le of lannin is that a lan must cover a eriod at least e ual to the
time required to accomplish it. This means that the MS planning horizon must
be at least as long as the lead time required to fabricate the MS items. Thisincludes production and procurement time as well as engineering time in acustom design environment. This is normally set to cover a minimum of
-
-
7/29/2019 5.MasterProdScheduling
16/31
o c es: me ences MPS is a link between operations (production) and sales.
Hence need to have some policies in maintaining MPS,
otherwise it may cause confusions. Many organizations divide the planning horizon into periods
with different controls on schedule chan es. The closer aperiod is to the present, the tighter are the controls onschedule changes.
Varying lead times, market condit ions, and processing.execution and manufacturing approaches, labor and materialare committed. A change in the schedule can be disruptive andcostly, and the costs must be compared with the benefits of the
- -. ,realistic lead time constraints and competitive factors, willresult in an MPS that promotes manufacturing stability andproductivity while providing reasonable flexibility in meeting
.
-
7/29/2019 5.MasterProdScheduling
17/31
Demand Time Fence (DTF): DTF is future master schedule period inside towhich chan es to MPS are t icall not acce ted due to excessive cost caused b theschedule disruption.
Planning Time Fence (PTF): PTF is future master schedule period inside towhich chan es to MPS are evaluated to revent costl schedule disru tion. Outside PTFplanned can be freely changes by computer logic.
-
7/29/2019 5.MasterProdScheduling
18/31
Must recognize all sources of the demand
um o saggrega e gures s ou ma cwith aggregate figures of production, inventory
Disaggregation over time should be efficient
(i.e., optimize cost etc.) Avoid overloading or underloading the
production facility so that production capacity
result.
considering environment MTS, ATO, MTO
-
7/29/2019 5.MasterProdScheduling
19/31
Techni ues for Develo inan MS
Cut and Fit Methods: Try out variousallocations of ca acit to roducts in agroup until a satisfactory combination is
determined. Linear Programming: Can write LP model
constraints, factors and relevant costs.
-
7/29/2019 5.MasterProdScheduling
20/31
An Example Master Schedule generated usingCut and Fit Method
Week0 1 2 3 4 5
MonthTotal
Aggregate forecast 100 200 150 150 200 800
Production 150 150 150 150 150 750Aggregate inventory 400 450 400 400 400 450Item AForecast 60 120 90 90 120 480Production (MPS) 150 150 150 450Inventory 300 390 420 480 390 270Item BForecast 40 80 60 60 80 320Production (MPS) 150 150 300Inventory 100 60 -20 -80 10 80
Total Production 150 150 150 150 150
Aggregate plan capacity 150 150 150 150 150Deviation 0 0 0 0 0
Total Inventory 400 450 420 480 400 350
Deviation 0 -20 -80 0 0
-
7/29/2019 5.MasterProdScheduling
21/31
Customer Order Bookin & MPS Interactions between demand management and MPS is frequent.
The projected available balance (PAB) and available-to-promiseATP are two techni ues used b the master scheduler to ro ect
available inventory or capacity and to promise future production
against customer orders. The PAB considers the availability of goods based on consuming
. , ,PAB uses the forecast while in the near future periods, customerorders are used as a statement of demand.
Available to promise (ATP) is found to determine if future customer.people. The ATP uses customer orders alone as a basis of itscomputation. We will consider three methods of calculations of ATPfigures.
scre e Cumulative ATP (without lookahead) Cumulative ATP (with lookahead)
-
7/29/2019 5.MasterProdScheduling
22/31
Available to Promise ATP : DPAB CALCULATIONS: It is based on a concept called
consumption of forecast by actual orders.
PRIOR TO DTF:
PAB = PRIOR PERIOD PAB OR ONHAND INVENTORY + MPS CUSTOMER ORDERS
PAB = PRIOR PERIOD PAB + MPS MAX(CUSTOMER ORDERS,FORECAST)
ATP = ON-HAND INVENTORY APPLICABLE ONLY FOR PERIOD 1 +MPS (TOTAL ORDERS BOOKED UNTIL NEXT MPS).
Production Capacity or Inventory
Firm customerorders (consuming
Available to promise
Time
-
7/29/2019 5.MasterProdScheduling
23/31
ATP: CalculationsLead Time:1 Lot Size: 300 DTF: 2ON Hand:140 PTF: 4
Week 1 2 3 4 5 6
ORDERS 110 80 50 20 0 0-
MPS
ATP
- -
-
7/29/2019 5.MasterProdScheduling
24/31
ATP: CalculationsLead Time:1 Lot Size: 300 DTF: 2ON Hand:140 PTF: 4
Week 1 2 3 4 5 6
ORDERS 110 80 50 20 0 0
-
MPS 300
-
-
7/29/2019 5.MasterProdScheduling
25/31
ATP: CalculationsLead Time:1 Lot Size: 300 DTF: 2ON Hand:140 PTF: 4
Week 1 2 3 4 5 6
ORDERS 110 80 50 20 0 0
5 5 5 5 5
MPS 300 300
- -
-
7/29/2019 5.MasterProdScheduling
26/31
ATP: CalculationsLead Time:1 Lot Size: 300 DTF: 2ON Hand:140 PTF: 4
Week 1 2 3 4 5 6
ORDERS 110 80 50 20 0 0
MPS 300 300
ATP 30 150 300
[140-110] [300-(80+50+20)]-
-
7/29/2019 5.MasterProdScheduling
27/31
Cumulative ATP with and without lookaheadATP from previous period is added while computing next
.
Without lookahead does not take into consideration those
Week
, .
Item AForecast 60 120 90 90 120Production (MPS) 150 150 150 0 0
nven orOrders 60 55 50 40 30ATP(discrete) 120 95 30
ATP(with lookahead) 120 215 245 245 245
-
7/29/2019 5.MasterProdScheduling
28/31
Rou h-Cut Ca acit Plannin As orders are slotted in the MPS, the effects on the
Rough cut capacity planning (RCCP) identifies
resources.
, ,Resources approach and overall factors.
o esource: s gves e num er o oursrequired at each critical resource to build a particular enditem.
-
7/29/2019 5.MasterProdScheduling
29/31
Example: Rough-Cut Capacity
Suppose, work center WC21 is a critical resource. There are twoend items A and B are master scheduled. The bill of resources for
.
Work Center Part A Part BWC21 2.5 h 2.0 h
Week 1 2 3 4 5 6 7 8
Part A 10 10 10 10 20 20 20 10
Part B 5 25 5 15 10 25 15 10
Then RCCP calculations will appear as follows.Week 1 2 3 4 5 6 7 8 Total
Part A (hours) 25 25 25 50 50 50 50 25 300
Part B (hours) 10 50 10 30 20 50 30 10 210Total (hours) 35 75 35 80 70 100 80 35 510
Available 65 65 65 65 65 65 65 65 520
- - - - - -
-
7/29/2019 5.MasterProdScheduling
30/31
Example: Rough-Cut Capacity
annng If we had considered only the sum (as in aggregate
,sufficient capacity (520 hours) versus a requirementof 510 hours. However, after performing RCCP wesee that several eriods have insufficient ca acitwhile others have an excess.
Planners o tions to make MPS feasible: 1 ad ustthe MPS by changing due dates; or (2) adjustcapacity by adding or taking away resources, usingovertime, or subcontracting of the work .
RCCP can be very rough sometime. A more refinedapproach capacity requirement planning (CRP) isdone during material requirement planning (MRP)p ase o p ann ng.
-