5/f, western magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… ·...

94

Upload: others

Post on 09-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 2: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

20/F Two Landmark East, 100 How Ming Street, Kwun Tong, Kowloon, Hong Kong

T +852 2828 5757 F +852 2827 1823 W www.mottmac.com.hk

Mott MacDonald Hong Kong Limited

Attn: Mr. Danny Tang

Dear Sir,

Agreement No. CE 8/2009(EP)

Harbour Area Treatment Scheme (HATS) Stage 2A

Independent Environmental Checker for Construction Phase – Investigation

Contract No. DC/2009/05

Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station

at Stonecutters Island Sewage Treatment Works

Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14)

I refer to the Monthly EM&A Report for January 2011 (Version 0) received on 14 February 2011 via email.

Pursuant to Condition 4.4 of Environmental Permit No. EP-322/2008/E, I hereby verify the captioned report.

Yours faithfully

for MOTT MACDONALD HONG KONG LIMITED

Dr. Anne F Kerr

Independent Environmental Checker

c.c. ARUP Mr. Gamini Ananda Fax: 2370 4377

AECOM Ms. Edith Ng Fax: 2891 0305

CSSTJV Mr. Y L Chan Fax: 2370 2086

Our ref KMY/AFK/FY/TK/T261332/22.01/L-0159

T 2828 5757

E [email protected]

Your ref -

CE/Harbour Area Treatment Scheme

Drainage Services Department

Sewage Services Branch

Harbour Area Treatment Scheme Division

5/F, Western Magistracy,

2A Pokfulam Road, Hong Kong

16 February 2011

By Fax (2833 9162) and Post

Page 3: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. i February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

Table of Content

Page

EXECUTIVE SUMMARY ........................................................................................................................ 1

1 INTRODUCTION ........................................................................................................................ 3

1.1 Background ................................................................................................................... 3 1.2 Scope of Report ............................................................................................................ 4 1.3 Project Organization...................................................................................................... 4 1.4 Summary of Construction Works .................................................................................. 4 1.5 Summary of EM&A Programme Requirements ............................................................ 5

2 AIR QUALITY MONITORING .................................................................................................... 6

2.1 Monitoring Requirements .............................................................................................. 6 2.2 Monitoring Equipment ................................................................................................... 6 2.3 Monitoring Location ....................................................................................................... 6 2.4 Monitoring Parameters, Frequency and Duration ......................................................... 7 2.5 Monitoring Methodology ................................................................................................ 7 2.6 Monitoring Schedule for the Reporting Month ............................................................ 10 2.7 Monitoring Results ...................................................................................................... 10

3 NOISE MONITORING .............................................................................................................. 11

3.1 Monitoring Requirements ............................................................................................ 11 3.2 Monitoring Equipment ................................................................................................. 11 3.3 Monitoring Location ..................................................................................................... 11 3.4 Monitoring Parameters, Frequency and Duration ....................................................... 12 3.5 Monitoring Methodology .............................................................................................. 13 3.6 Monitoring Schedule for the Reporting Month ............................................................ 14 3.7 Monitoring Results ...................................................................................................... 14

4 LANDSCAPE AND VISUAL .................................................................................................... 15

4.1 Monitoring Requirements ............................................................................................ 15 4.2 Background ................................................................................................................. 15 4.3 Summary of Inspection – 25 January 2011 ................................................................ 15 4.4 Next Landscape and Visual Audit Schedule ............................................................... 15

5 ENVIRONMENTAL SITE INSPECTION AND AUDIT ............................................................. 16

5.1 Site Inspection ............................................................................................................. 16 5.2 Advice on the Solid and Liquid Waste Management Status ....................................... 18 5.3 Environmental Licenses and Permits.......................................................................... 19 5.4 Implementation Status of Environmental Mitigation Measures ................................... 20 5.5 Summary of Exceedances of the Environmental Quality Performance Limit ............. 20 5.6 Summary of Complaints, Notification of Summons and Successful Prosecutions ..... 21

6 FUTURE KEY ISSUES ............................................................................................................ 22

6.1 Construction Programme for the Coming Two Months ............................................... 22 6.2 Key Issues for the Coming Month ............................................................................... 22 6.3 Monitoring Schedule for the Coming Month ............................................................... 22

7 CONCLUSIONS AND RECOMMENDATIONS ....................................................................... 23

7.1 Conclusions ................................................................................................................. 23 7.2 Recommendations ...................................................................................................... 24

Page 4: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. ii February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

List of Tables Table 1.1 Contact Information of Key Personnel Table 2.1 Air Quality Monitoring Equipment Table 2.2 Locations of Air Quality Monitoring Station Table 2.3 Air Quality Monitoring Parameters, Frequency and Duration Table 2.4 Summary of 1-hour TSP Monitoring Results in the Reporting Period Table 2.5 Summary of 24-hour TSP Monitoring Results in the Reporting Period Table 3.1 Noise Monitoring Equipment Table 3.2 Locations of Impact Noise Monitoring Station Table 3.3 Noise Monitoring Parameters, Frequency and Duration Table 3.4 Summary of Impact Noise Monitoring Results During Daytime on Normal Weekdays in

the Reporting Period Table 3.5 Summary of Impact Noise Monitoring Results During Evening time on Normal

Weekdays in the Reporting Period Table 5.1 Summary of Environmental Licensing and Permit Status List of Figures Figure 1.1 General Layout Plan of the Project Site Figure 2.1 Location of Air Quality Monitoring Station During Impact Monitoring Figure 3.1 Location of Noise Monitoring Station During Impact Monitoring List of Appendices Appendix A Project Organization Structure Appendix B Construction Programme Appendix C Implementation Schedule of Environmental Mitigation Measures (EMIS) Appendix D Summary of Action and Limit Levels Appendix E Calibration Certificates of Equipments Appendix F EM&A Monitoring Schedules Appendix G Air Quality Monitoring Results and their Graphical Presentations Appendix H Noise Monitoring Results and their Graphical Presentations Appendix I Meteorological Data for January 2011 Appendix J Event Action Plan Appendix K Detailed Landscape and Visual Monitoring Report Appendix L Cumulative Statistics of Exceedances, Complaints, Notification of Summons and

Successful Prosecutions

Page 5: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 1 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

EXECUTIVE SUMMARY

The proposed construction of interconnection tunnel and diaphragm wall for main pumping station at Stonecutters Island Sewage Treatment Works (SCISTW) (the Project) is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is governed by an Environmental Permit (EP-322/2008/E). The Project comprises the construction of interconnection tunnel between the inlet chamber of the main pumping station and the existing riser shaft and diaphragm wall for the main pumping station. China State - Shanghai Tunnel Joint Venture was commissioned as the Contractor of the Project. AECOM Asia Co. Ltd. was employed by China State - Shanghai Tunnel Joint Venture as the Environmental Team to undertake the EM&A works for the Project. The construction phase of the Project commenced on 10 December 2009. The impact environmental monitoring and audit (EM&A) programme of the Project, which includes air quality, noise and landscape and visual monitoring and environmental site inspections, was commenced on 10 December 2009. This report documents the findings of EM&A works conducted in the period between 1 and 31 January 2011. As informed by the Contractor, major construction activities in the reporting period were: Construction of diaphragm wall for the main pumping station and its inlet chamber and at

launching shaft region of interconnection tunnel; Carrying out toe grouting at the main pumping station and its inlet chamber; Drainage works; and Construction of utility diversion.

Breaches of Action and Limit Levels for Air Quality

No exceedance of Action and Limit Level was recorded for both 1-hour TSP and 24-hour TSP monitoring in the reporting month.

Breaches of Action and Limit Levels for Noise

According to the information provided by the Contractor, no Action Level exceedance was recorded since no noise related complaint was received in the reporting month.

No Limit Level exceedance of noise was recorded at all monitoring station in the reporting month.

Complaint, Notification of Summons and Successful Prosecution

According to the information provided by the Contractor, no complaint, notification of summons and successful prosecution was received in the reporting month.

Page 6: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 2 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

Reporting Changes

As informed by the Officer from FSD Diving Rescue and Diving Rescue Centre, the trainings will be conducted during the daytime period in Year 2011. According to the EIA report, no other noise sensitive receiver was identified near the Project site area, except for the FSD Diving Rescue and Diving Training Centre. Thus, the noise monitoring during the night-time period (from 2300 to 0700) was considered not necessary for Year 2011.

With the approval from IEC & ER, the noise monitoring at monitoring station (NM6) during night-time period (from 2300 to 0700) was suspended in Year 2011. The necessity of conducting noise monitoring at this station from Year 2012 will be subject to the class arrangement by FSD and will be reviewed in the end of Year 2011.

According to the information from Hong Kong Observatory, the Hong Kong Observatory anemometer station at Cheung Sha Wan was stopped from 17 December 2010. With approval from IEC & ER, the wind direction and wind speed data were obtained from another Hong Kong Observatory anemometer station located close to the Project site, which is located in Shell Oil Depot at Tsing Yi, with effective from December 2010.

Future Key Issues

Key issues to be considered in the coming month include:

- Properly store and label oil drums and chemical containers placed on site; - Proper chemical, chemical waste and waste management; - Segregation and recycling of general refuse and construction wastes should be properly

implemented; - Collection of general refuse and construction wastes should be carried out properly and

regularly; - Site runoff should be properly collected and treated prior to discharge; - Regular review and maintenance of drainage systems and desilting facilities; - Accumulation of slurry and stagnant water within site area should be avoided; - Suppress dust generated from bentonite slurry treatment plant, excavation/earth movement

activities, soil stockpiles and haul road traffic; - Regular inspection and maintenance of machineries operated on site to avoid any dark smoke

emission and oil leakage; - Quieter powered mechanical equipment should be used; - Noise control measures, such as erection of movable noise barrier, should be properly

maintained on site; and - Proper tree protection works should be provided when carry out works near existing trees.

Page 7: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 3 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

1 INTRODUCTION

1.1 Background

1.1.1 The proposed construction of interconnection tunnel and diaphragm wall for main pumping station at Stonecutters Island Sewage Treatment Works (SCISTW) (the Project) is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is governed by an Environmental Permit (EP-322/2008/E).

1.1.2 The Project site is located in the Sham Shui Po District. It is located within the existing Stonecutters Island Sewage Treatment Works (SCISTW), which is bounded by Ngong Shung Road to the north and the west. The general layout plan of the Project site showing the contract area is shown in Figure 1.1.

1.1.3 The objective of the Project “Harbour Area Treatment Scheme (HATS) Stage 2A - Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at Stonecutters Island Sewage Treatment Works (SCISTW)” under Contract DC/2009/05 is to provide interconnection tunnel between the inlet chamber of the main pumping station and the existing riser shaft and diaphragm wall for the main pumping station.

1.1.4 The scope of the Project comprises mainly:

Construction of interconnection tunnel with concrete lining between the inlet chamber of the main pumping station and the existing riser shaft;

Construction of diaphragm wall, base slab and pile cap for the main pumping station and its inlet chamber;

Excavation within the diaphragm walls for the main pumping station and its inlet chamber to founding levels;

Piling works for the main pumping station; Utilities upgrading and diversion works; Temporary launching shaft to be handed over to main pumping station

Contractor; Carrying out ground monitoring and instrumentation works; Carrying out pumping test; Miscellaneous building, civil and electrical and mechanical works; and Landscape works.

1.1.5 The Project is anticipated to complete in mid 2012.

1.1.6 According to the Environmental Permit (EP-322/2008/E) and the EM&A Manual of the Project, there is a need of an EM&A programme including air quality and noise monitoring and landscape and visual audits and environmental site inspections.

1.1.7 AECOM Asia Co. Ltd. was employed by the Contractor, China State - Shanghai Tunnel Joint Venture, as the Environmental Team (ET) to undertake the EM&A works for the Project. In accordance with the EM&A Manual of the Project, environmental monitoring of air quality, noise and landscape and visual impacts and environmental site inspections would be required for this Project.

1.1.8 The construction phase of the Project commenced on 10 December 2009. The impact environmental monitoring and audit (EM&A) programme of the Project, which includes air quality, noise and landscape and visual monitoring and environmental site inspections, was commenced on 10 December 2009.

Page 8: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 4 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

1.2 Scope of Report

1.2.1 This is the fourteenth monthly Environmental Monitoring and Audit (EM&A) Report under the Contract DC/2009/05 – Harbour Area Treatment Scheme (HATS) Stage 2A - Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at Stonecutters Island Sewage Treatment Works (SCISTW). This report presents a summary of the environmental monitoring and audit works, list of activities and mitigation measures proposed by the ET for the Project in January 2011.

1.3 Project Organization

1.3.1 The project organization structure is shown in Appendix A. The key personnel contact names and numbers are summarized in Table 1.1

Table 1.1 Contact Information of Key Personnel

Party Position Name Telephone Fax

ER (Ove Arup)

The Engineer S.Y. Chan 2528 3031 2865 6493

Principal Resident Engineer/ Engineer’s

Representative Ted Tang 2370 4311 2370 4377

Senior Resident Engineer M.P. Gamini Ananda 2370 4311 2370 4377

Resident Engineer (Environmental, Safety and

Material) William Yu 2370 4311 2370 4377

IEC (Mott MacDonald)

Independent Environmental Checker

Anne Kerr 2828 5793 2827 1823

Contractor (China State –

Shanghai Tunnel Joint Venture)

Site Agent Ben Siu 2370 3166 2370 2086

Environmental Officer Holmes Wong 2370 3166 2370 2086

ET (AECOM) Environmental Team

Leader Edith Ng 3105 8525 2891 0305

1.4 Summary of Construction Works

1.4.1 As informed by the Contractor, the Contractor has carried out the following major activities in the reporting month:

Construction of diaphragm wall for the main pumping station and its inlet chamber and at launching shaft region of interconnection tunnel;

Carrying out toe grouting at the main pumping station and its inlet chamber; Drainage works; and Construction of utility diversion.

1.4.2 The Construction Programme is shown in Appendix B.

1.4.3 The mitigation measures implementation schedule (EMIS) are presented in Appendix C.

Page 9: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 5 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

1.5 Summary of EM&A Programme Requirements

1.5.1 The EM&A programme required environmental monitoring for air quality, noise and landscape and visual impacts, environmental site inspections for air quality, water quality, noise and waste management. The EM&A requirements for each parameter described in the following sections include:

- All monitoring parameters; - Monitoring schedules for the reporting month and forthcoming months; - Action and Limit levels for all environmental parameters; - Event / Action Plan; - Environmental mitigation measures, as recommended in the Project EIA study final report;

and - Environmental requirement in contract documents.

Page 10: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 6 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

2 AIR QUALITY MONITORING

2.1 Monitoring Requirements

2.1.1 In accordance with the EM&A Manual, 1-hour and 24-hour TSP levels at 4 air quality monitoring stations should be established. As accesses to some of the proposed monitoring stations as stipulated in the EM&A manual have been rejected by other parties or found to be not suitable, a Monitoring Proposal, presenting the alternative monitoring stations, requirements and methodologies for the monitoring, had been submitted.

2.1.2 Moreover, monitoring station at Block A of Government Dockyard mentioned in the Monitoring Proposal will be established by the other contract (Contract DE/2009/02: Provision of Covers and Deodourisation Facilities to the Existing Sedimentation Tanks at SCISTW), so impact monitoring details at this station are not mentioned in this report.

2.1.3 Impact monitoring of air quality at 1 monitoring station, West Kowloon No. 2 Sewage Pumping Station (AM7), as described in the Monitoring Proposal, was established.

2.1.4 Impact 1-hour TSP monitoring was conducted for at least three times every 6 days, while impact 24-hour TSP monitoring was carried out for at least once every 6 days. The Action and Limit level of the air quality monitoring is provided in Appendix D.

2.2 Monitoring Equipment

2.2.1 24-hour TSP air quality monitoring was performed using High Volume Sampler (HVS) located at the designated monitoring station. The HVS meets all the requirements of the EM&A Manual. Portable direct reading dust meters were used to carry out the 1-hour TSP monitoring. Brand and model of the equipment is given in Table 2.1.

Table 2.1 Air Quality Monitoring Equipment

Equipment Brand and Model

Portable direct reading dust meter (1-hour TSP)

Sibata Digital Dust Monitor (Model No. LD-3 and LD-3B)

High Volume Sampler (24-hour TSP)

Graseby Andersen Total Suspended Particulate Mass Flow Controlled Sampling System

(Model No.GMWS2310)

2.3 Monitoring Location

2.3.1 Monitoring station (AM7), was set up at the proposed location in accordance with the Monitoring Proposal submitted, as agreed by the ER and IEC. Figure 2.1 shows the location of air quality monitoring station during impact phase. Table 2.2 describes the details of the monitoring station.

Table 2.2 Locations of Air Quality Monitoring Station

ID Location Monitoring Station

AM7 West Kowloon No. 2

Sewage Pumping Station Roof top of the premise

Page 11: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 7 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

2.4 Monitoring Parameters, Frequency and Duration

2.4.1 Table 2.3 summarizes the monitoring parameters, frequency and duration of impact TSP monitoring.

Table 2.3 Air Quality Monitoring Parameters, Frequency and Duration

Monitoring Station

Parameter Frequency and Duration

AM7 1-hour TSP At least 3 times every 6 days

24-hour TSP At least once every 6 days

2.5 Monitoring Methodology

2.5.1 24-hour TSP Monitoring

(a) The HVS was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the installation of the HVS:

(i) A horizontal platform with appropriate support to secure the sampler against

gusty wind was provided. (ii) The distance between the HVS and any obstacles, such as buildings, was at

least twice the height that the obstacle protrudes above the HVS. (iii) A minimum of 2 meters separation from walls, parapets and penthouse for

rooftop sampler. (iv) A minimum of 2 meters separation from any supporting structure, measured

horizontally is required. (v) No furnace or incinerator flues nearby. (vi) Airflow around the sampler was unrestricted. (vii) Permission was obtained to set up the samplers and access to the monitoring

station. (viii) A secured supply of electricity was obtained to operate the samplers. (ix) The sampler was located more than 20 meters from any dripline. (x) Any wire fence and gate, required to protect the sampler, did not obstruct the

monitoring process. (xi) Flow control accuracy was kept within ±2.5% deviation over 24-hour sampling

period.

(b) Preparation of Filter Papers

(i) Glass fibre filters, G810 were labelled and sufficient filters that were clean and without pinholes were selected.

(ii) All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C; the relative humidity (RH) was < 50% and not variable by more than ±5%. A convenient working RH was 40%.

(iii) All filter papers were prepared and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality assurance and quality control programmes.

Page 12: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 8 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

(c) Field Monitoring

(i) The power supply was checked to ensure the HVS works properly. (ii) The filter holder and the area surrounding the filter were cleaned. (iii) The filter holder was removed by loosening the four bolts and a new filter, with

stamped number upward, on a supporting screen was aligned carefully. (iv) The filter was properly aligned on the screen so that the gasket formed an

airtight seal on the outer edges of the filter. (v) The swing bolts were fastened to hold the filter holder down to the frame.

The pressure applied was sufficient to avoid air leakage at the edges. (vi) Then the shelter lid was closed and was secured with the aluminium strip. (vii) The HVS was warmed-up for about 5 minutes to establish run-temperature

conditions. (viii) A new flow rate record sheet was set into the flow recorder. (ix) On site temperature and atmospheric pressure readings were taken and the

flow rate of the HVS was checked and adjusted at around 1.3 m3/min, and

complied with the range specified in the EM&A Manual (i.e. 0.6-1.7 m3/min).

(x) The programmable digital timer was set for a sampling period of 24 hrs, and the starting time, weather condition and the filter number were recorded.

(xi) The initial elapsed time was recorded. (xii) At the end of sampling, on site temperature and atmospheric pressure

readings were taken and the final flow rate of the HVS was checked and recorded.

(xiii) The final elapsed time was recorded. (xiv) The sampled filter was removed carefully and folded in half length so that only

surfaces with collected particulate matter were in contact. (xv) It was then placed in a clean plastic envelope and sealed. (xvi) All monitoring information was recorded on a standard data sheet. (xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.

(d) Maintenance and Calibration

(i) The HVS and its accessories were maintained in good working condition,

such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.

(ii) HVSs were calibrated using TE-5025A Calibration Kit upon installation and thereafter at bi-monthly intervals.

(iii) Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in Appendix E.

Page 13: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 9 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

2.5.2 1-hour TSP Monitoring

(a) Measuring Procedures

The measuring procedures of the 1-hour dust meter were in accordance with the Manufacturer’s Instruction Manual as follows: (i) Turn the power on. (ii) Close the air collecting opening cover. (iii) Push the “TIME SETTING” switch to [BG] (iv) Push “START/STOP” switch to perform background measurement for 6

seconds. (v) Turn the knob at SENSI ADJ position to insert the light scattering plate. (vi) Leave the equipment for 1 minute upon “SPAN CHECK” is indicated in the

display. (vii) Push “START/STOP” switch to perform automatic sensitivity adjustment. This

measurement takes 1 minute. (viii) Pull out the knob and return it to MEASURE position. (ix) Push the “TIME SETTING” switch the time set in the display to 3 hours. (x) Lower down the air collection opening cover. (xi) Push “START/STOP” switch to start measurement.

(b) Maintenance and Calibration

(i) The 1-hour TSP meter was calibrated at 1-year intervals against a continuous

particulate TEOM Monitor, Series 1400ab. Calibration certificates of the Laser Dust Monitors are provided in Appendix E.

Page 14: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 10 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

2.6 Monitoring Schedule for the Reporting Month

2.6.1 The schedule for environmental monitoring in January 2011 is provided in Appendix F.

2.7 Monitoring Results

2.7.1 The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Table 2.4 and 2.5 respectively. Detailed air quality monitoring results are presented in Appendix G.

Table 2.4 Summary of 1-hour TSP Monitoring Results in the Reporting Period

Average (g/m3) Range (g/m

3)

Action Level

(g/m3)

Limit Level

(g/m3)

AM7 87 82 – 98 322 500

Table 2.5 Summary of 24-hour TSP Monitoring Results in the Reporting Period

Average (g/m3) Range (g/m

3)

Action Level

(g/m3)

Limit Level

(g/m3)

AM7 127 93 – 179 207 260

2.7.2 All 1-hour TSP and 24-hour TSP results were below the Action and Limit Level at all monitoring location in the reporting month.

2.7.3 The event action plan is annexed in Appendix J.

2.7.4 Major dust sources observed during the dust monitoring in the reporting period included construction dust from the Project site, nearby traffic emission and construction dust from other construction sites.

2.7.5 Weather information including prevailing wind speed and wind direction is annexed in Appendix I. According to the information from Hong Kong Observatory, the Hong Kong Observatory anemometer station at Cheung Sha Wan was stopped from 17 December 2010. With approval from IEC & ER, the wind direction and wind speed data were obtained from another Hong Kong Observatory anemometer station located close to the Project site, which is located in Shell Oil Depot at Tsing Yi, with effective from December 2010.

Page 15: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 11 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

3 NOISE MONITORING

3.1 Monitoring Requirements

3.1.1 In accordance with the EM&A Manual, impact noise levels should be obtained at 2 noise monitoring stations. As accesses to some of the proposed monitoring stations as stipulated in the EM&A manual have been rejected by other parties or found to be not suitable, a Monitoring Proposal, presenting the alternative monitoring stations, requirements and methodologies for the monitoring, had been submitted.

3.1.2 Impact monitoring of construction noise at 1 monitoring station, Customs’ Marine Base (NM6) (which serves as alternative location for FSD Diving Rescue and Diving Training Centre), as described in the Monitoring Proposal, was established.

3.1.3 Impact noise monitoring was conducted for at least once per week during the construction phase of the Project. The Action and Limit level of the noise monitoring is provided in Appendix D.

3.2 Monitoring Equipment

3.2.1 Noise monitoring was performed using sound level meter at the designated monitoring station. The sound level meters deployed comply with the International Electrotechnical Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level. Brand and model of the equipment is given in Table 3.1.

Table 3.1 Noise Monitoring Equipment

Equipment Brand and Model

Integrated Sound Level Meter B&K (Model No. 2238; 2250L; 2270)

Acoustic Calibrator B&K (Model no. 4231)

3.3 Monitoring Location

3.3.1 Monitoring station (NM6) serves as an alternative location for FSD Diving Rescue and Diving Training Centre which is regarded as a Noise Sensitive Receiver (NSR) as it is an institution.

3.3.2 Monitoring station (NM6), was set up at the proposed location in accordance with the Monitoring Proposal submitted, as agreed by the ER and IEC. Figure 3.1 shows the location of noise monitoring station during impact phase. Table 3.2 describes the details of the monitoring station.

Table 3.2 Locations of Impact Noise Monitoring Station

ID Location Monitoring Station

NM6 Customs’ Marine Base 1m from the exterior of the roof top façade of

Block H of Government Dockyard

Page 16: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 12 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

3.4 Monitoring Parameters, Frequency and Duration

3.4.1 Table 3.3 summarizes the monitoring parameters, frequency and duration of impact noise monitoring.

Table 3.3 Noise Monitoring Parameters, Frequency and Duration

Monitoring Station

Parameters and Duration Frequency

NM6

30-min measurement at monitoring station between 0700 and 1900 on

normal weekdays.

3 times of 5-min measurement at monitoring station during restricted hours if construction works were

carried out.

Leq, L10 and L90 would be recorded.

At least once per week

3.4.2 As informed by the Contractor, the construction works had extended to include works during the evening time period (1900 to 2300) on all weekdays and during daytime and evening time period (0700 to 2300) on all Sundays and Public Holidays in the reporting month. Moreover, construction works had been further extended to the night-time period (2300 to 0700 of next day) on all days, except for 1 January 2011. The construction works were conducted in accordance with the granted Construction Noise Permit (CNP) under NCO.

3.4.3 As informed by the Officer from FSD Diving Rescue and Diving Rescue Centre, the trainings will be conducted during the daytime period in Year 2011. According to the EIA report, no other noise sensitive receiver was identified near the Project site area, except for the FSD Diving Rescue and Diving Training Centre. Thus, the noise monitoring during the night-time period (from 2300 to 0700) was considered not necessary for Year 2011.

3.4.4 With the approval from IEC & ER, the noise monitoring at monitoring station (NM6) during night-time period (from 2300 to 0700) was suspended in Year 2011. The necessity of conducting noise monitoring at this station from Year 2012 will be subject to the class arrangement by FSD and will be reviewed in the end of Year 2011.

3.4.5 According to the requirement stipulated in Clause 3.16 of EM&A Manual, additional weekly noise impact monitoring was carried out during restricted hours on the scheduled day as stated in Appendix F.

Page 17: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 13 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

3.5 Monitoring Methodology

3.5.1 Monitoring Procedure

(a) The sound level meter was set on a tripod at a height of 1.2 m above the ground.

(b) Façade measurements were made at all monitoring locations.

(c) The battery condition was checked to ensure the correct functioning of the meter.

(d) Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

(i) frequency weighting: A (ii) time weighting: Fast (iii) time measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00 – 1900

on normal weekdays; Leq(5-minutes) x3 during restricted hours i.e. 19:00 – 23:00 and 23:00 – 07:00 of normal weekdays, whole day of Sundays and Public Holidays

(e) Prior to and after each noise measurement, the meter was calibrated using the acoustic calibrator for 94dB(A) at 1000 Hz. If the difference in the calibration level before and after measurement was more than 1 dB(A), the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

(f) During the monitoring period, the Leq, L10 and L90 were recorded. In addition, site conditions and noise sources were recorded on a standard record sheet.

(g) Noise measurement was paused during periods of high intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations were recorded when intrusive noise was unavoidable.

(h) Noise monitoring was cancelled in the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind with gusts exceeding 10m/s.

3.5.2 Maintenance and Calibration

(a) The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.

(b) The meter and calibrator were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.

(c) Calibration certificates of the sound level meters and acoustic calibrators are provided in Appendix E.

Page 18: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 14 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

3.6 Monitoring Schedule for the Reporting Month

3.6.1 The schedule for environmental monitoring in January 2011 is provided in Appendix F.

3.7 Monitoring Results

3.7.1 The monitoring results for noise are summarized in Table 3.4 to 3.5 and the monitoring data is provided in Appendix H.

Table 3.4 Summary of Impact Noise Monitoring Results During Daytime on Normal Weekdays in the reporting period

Average, dB(A),

Leq (30 mins)

Range, dB(A),

Leq (30 mins)

Limit Level, dB(A),

Leq (30 mins)

NM6 70.8 70.6 – 71.0 75

Table 3.5 Summary of Impact Noise Monitoring Results During Evening time on Normal Weekdays in the reporting period

Average, dB(A),

Leq (5 mins)

Range, dB(A),

Leq (5 mins)

Limit Level, dB(A),

Leq (5 mins)

NM6 63.4 60.7 – 65.4 70

3.7.2 According to the information provided by the Contractor, no noise complaint was received in the reporting month; hence, no Action Level exceedance was recorded.

3.7.3 No Limit Level exceedance of noise was recorded at all monitoring station in the reporting month.

3.7.4 The event action plan is annexed in Appendix J.

3.7.5 Major noise sources observed during the noise monitoring in the reporting period included construction noise from the Project site, nearby traffic noise and construction noise from other construction sites.

Page 19: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 15 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

4 LANDSCAPE AND VISUAL

4.1 Monitoring Requirements

4.1.1 In accordance with the EM&A Manual, during the construction phase of the Project, landscape and visual monitoring should be carried out monthly with supervision by a Registered Landscape Architect (RLA). The landscape and visual monitoring is to check if the design, implementation and maintenance of the landscape and visual mitigation measures are fully effectuated.

4.1.2 A detailed report is annexed in Appendix K.

4.2 Background

4.2.1 A Baseline Review was conducted prior to the commencement of the construction contracts. The Baseline Review is to review the landscape and visual baseline conditions associated with the Project. Based on the findings given in the Baseline Review Report, the baseline landscape resources, landscape character areas and visually sensitive receivers originally identified within the EIA study area are generally unchanged and remain valid. Changes to the landscape and visual baseline are thus judged to be Insignificant.

4.3 Summary of Inspection – 25 January 2011

Matters Arising from Previous Inspections: 4.3.1 No particular observation was made from previous inspection.

Protection of Existing Trees and Tree Works:

4.3.2 It was observed that the lower branches of the retained trees and the tree protection zone area were covered with splashed mud slurry. The Contractor was requested to clean up by hosing down the tree branches and to install plastic sheets at the base of the tree protection zone area to prevent further splashing of mud slurry, which would affect the health of the trees.

Recommendations:

4.3.3 The Contractor was recommended to clean up the tree branches and tree protection zone area, and to install plastic sheets to prevent the splashing of mud slurry.

4.3.4 The event action plan is annexed in Appendix J.

4.4 Next Landscape and Visual Audit Schedule

4.4.1 The landscape and visual audits in the next reporting month was tentatively scheduled to 23rd

February 2011.

Page 20: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 16 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

5 ENVIRONMENTAL SITE INSPECTION AND AUDIT

5.1 Site Inspection

5.1.1 Site Inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. In the reporting month, 4 site inspections were carried out on 4, 11, 18 and 25 January 2011. Particular observations are described below.

5.1.2 The Contractor has rectified several observations as identified during environmental site inspection in the reporting month within agreed time frame. Rectifications of remaining identified items are undergoing by the Contractor, which included implementation of proper mitigation measures for collection of surface run-off at site boundaries, oil drums stored and protection of existing trees in launching shaft works area (Portion 2) and clearance of oil stain and provision of proper drip tray in main pumping station works area. Follow-up inspections will be conducted to ensure all identified items are mitigated properly.

5.1.3 Air Quality

Nil.

5.1.4 Noise

No Noise Emission Label (NEL) was affixed to an air compressor employed in main pumping station works area. The Contractor should ensure NELs were affixed to air compressors employed within the works area.

5.1.5 Water Quality

No proper measure was provided at the part of the site boundaries at main pumping station works area and at launching shaft works area (Portion 2) to collect/confine the surface run-off from main pumping station and launching shaft works area. The Contractor was recommended to provide bunds/sand bags/channels at the site boundaries of the works area to avoid any surface run-off or wastewater from construction works flowing outside the works area.

Page 21: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 17 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

5.1.6 Chemical and Waste Management

Stockpile of general refuse and wooden boards were found in the works area in launching shaft works area (Portion 2). The Contractor should clear the general refuse and C&D wastes accumulated on site properly and regularly to maintain the housekeeping within the works area.

Oil drums placed within works area at launching shaft (Portion 2) were still found stored without provision of drip trays. The Contractor is advised to provide drip trays to the oil drums placed within the works area as soon as possible to retain any oil leakage.

Oil stains were observed on the ground in main pumping station works area and in launching shaft works area (Portion 2). The Contractor should clear the oil mixture and disposed of them as chemical waste. Also, the Contractor is reminded to provide proper measures (like provision of drip trays or temporarily with tarpaulin sheets) if works with potential oil leakage (e.g. oil filling) was carried out.

The drain hole of a drip tray placed for a generator placed in main pumping station works area was found plugged improperly. Drain hole of the drip tray employed within the works area should be plugged properly to avoid any oil leakage.

5.1.7 Landscape

It was observed that the high level nettings installed for screening of the existing trees at launching shaft works area (Portion 2) was not well maintained. Also, the barriers demarcating the tree protection zone at the Portion 2 area was broken down by construction equipments / materials placed next by. The Contractor was reminded to rectify the nettings and properly re-instate the barriers for proper demarcation of the tree protection zone to prevent possible damage to the retained trees.

Page 22: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 18 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

5.2 Advice on the Solid and Liquid Waste Management Status

5.2.1 The Contractor is registered as a chemical waste producer for this Project. C & D material and waste sorting was carried out on site. Receptacles were available for general refuse and C&D wastes collection.

5.2.2 As advised by the Contractor, a total of 7,608.75 tonnes of inert C&D materials were

generated on site in the reporting month. 4,081.49 tonnes of soil and slurry, 61.35 tonnes of

mixed rock and soil, 13.95 tonnes of broken concrete and 10.47 tonnes of building debris were generated on site and disposed of at Public Fill (Tuen Mun Area 38 Fill Bank). 3,441.49 tonnes were used bentonite slurry and were disposed of at Public Fill (Tseung Kwan O Area 137 Fill Bank).

11,910 kg of metals was generated and collected by registered recycling collector. No paper cardboard packing and plastic were generated on site and collected by registered recycling collector. No chemical waste was generated and collected by licensed chemical waste collector. 13.59 tonnes of other types of wastes (e.g. general refuse) were generated on site and disposed of at North East New Territories (NENT) Landfill.

5.2.3 The Contractor is advised to properly maintain on site C&D material and waste sorting, collection and recording system and maximize reuse / recycle of C&D material and waste. The Contractor is reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

Page 23: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 19 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

5.3 Environmental Licenses and Permits

5.3.1 The environmental licenses and permits for this Project and valid in the reporting month is summarized in Table 5.1.

Table 5.1 Summary of Environmental Licensing and Permit Status

Statutory Reference Description Permit No.

Valid Period Remarks

From To

EIAO Environmental

Permit EP-322/2008/E 24/11/10 --

- Harbour Area Treatment Scheme (HATS) Stage 2A

APCO NA notification -- 09/11/09 19/12/11 - Whole Construction

Site for Contract DC/2009/05

WPCO Discharge License

WT00005755-2010 27/04/10 31/01/15

- Discharge of Construction Runoff

from Contract DC/2009/05

WDO Chemical Waste

Producer Registration

WPN5213-269-C3572-01

23/10/09 -- - Whole Construction

Site for Contract DC/2009/05

WDO Waste Charges

Account 7009440 -- --

- Whole Construction Site for Contract

DC/2009/05

NCO Construction Noise Permit

GW-RW0386-10 04/08/10 01/02/11

- Construction Site at Portion 2 (launching shaft) for Contract

DC/2009/05

NCO Construction Noise Permit

GW-RW0505-10 07/10/10 05/04/11 - Construction Site at

Portion 2, 3 and 4 for Contract DC/2009/05

NCO Construction Noise Permit

GW-RW0556-10 01/11/10 30/04/11 - Construction Site at

Portion 3 and 4 for Contract DC/2009/05

NCO Construction Noise Permit

GW-RW0007-11 11/01/11 04/04/11 - Construction Site at

Portion 3 and 4 for Contract DC/2009/05

Page 24: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 20 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

5.4 Implementation Status of Environmental Mitigation Measures

5.4.1 In response to the site audit findings, the Contractor carried out corrective actions.

5.4.2 A summary of the Implementation Schedule of Mitigation Measures (EMIS) is presented in Appendix C. Most of the necessary mitigation measures were implemented properly.

5.5 Summary of Exceedances of the Environmental Quality Performance Limit

5.5.1 All 1-hour TSP and 24-hour TSP results were below the Action and Limit level at all monitoring location in the reporting month.

5.5.2 Referring to the information provided by the Contractor, there was no noise related complaint received in the reporting month; hence, no Action Level exceedance was recorded.

5.5.3 No Limit Level exceedance of noise was recorded at all monitoring station in the reporting month.

5.5.4 Cumulative statistics of exceedances is provided in Appendix L.

Page 25: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 21 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

5.6 Summary of Complaints, Notification of Summons and Successful Prosecutions

5.6.1 Complaints shall be referred to the ET Leader for action. The ET Leader shall undertake the following procedures upon receipt of any complaint:

Log complaint and date of receipt onto the complaint database and inform the IC(E) immediately;

Investigate the complaint to determine its validity, and assess whether the source of the problem is due to works activities;

Identify mitigation measures in consultation with the IC(E) if a complaint is valid and due to works;

Advise the Contractor and the ER if additional mitigation measures are required; Review the Contractor’s response to identified mitigation measures, and the updated

situation; If the complaint is transferred from EPD, submit interim report to EPD on status of the

complaint investigation and follow-up action within the time frame assigned by EPD; Undertake additional monitoring and audit to verify the situation if necessary, and review that

circumstances leading to the complaint to not recur; Report investigation results and subsequent actions to complainant (if the source of

complaint is EPD, the results should be reported within the time frame assigned by EPD); and

Record the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.

5.6.2 During any complaint investigation work, the Contractor and the ER shall cooperate with the

ET Leader in providing all necessary information and assistance for completion of the investigation. If mitigation measures are identified in the investigation, the Contractor shall promptly carry out the mitigation. The ER shall ensure that all necessary measures have been carried out by the Contractor.

5.6.3 Referring to the information provided by the Contractor, no environmental complaint, notification of summons and successful prosecution was received in the reporting month.

5.6.4 Cumulative statistics of complaints, notification of summons and successful prosecutions is provided in Appendix L.

Page 26: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 22 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

6 FUTURE KEY ISSUES

6.1 Construction Programme for the Coming Two Months

6.1.1 As advised by the Contractor, the major construction works in February and March 2011 will be:

Construction of diaphragm wall for the inlet chamber and at launching shaft region of interconnection tunnel;

Carrying out toe grouting at the main pumping station and its inlet chamber; Drainage works; Capping beam construction at the main pumping station and its inlet chamber; and Open excavation for the main pumping station and its inlet chamber and at launching shaft

region of interconnection tunnel.

6.2 Key Issues for the Coming Month

6.2.1 Key issues to be considered in the coming month include:

- Properly store and label oil drums and chemical containers placed on site; - Proper chemical, chemical waste and waste management; - Segregation and recycling of general refuse and construction wastes should be properly

implemented; - Collection of general refuse and construction wastes should be carried out properly and

regularly; - Site runoff should be properly collected and treated prior to discharge; - Regular review and maintenance of drainage systems and desilting facilities; - Accumulation of slurry and stagnant water within site area should be avoided; - Suppress dust generated from bentonite slurry treatment plant, excavation/earth

movement activities, soil stockpiles and haul road traffic; - Regular inspection and maintenance of machineries operated on site to avoid any dark

smoke emission and oil leakage; - Quieter powered mechanical equipment should be used; - Noise control measures, such as erection of movable noise barrier, should be properly

maintained on site; and - Proper tree protection works should be provided when carry out works near existing trees.

6.3 Monitoring Schedule for the Coming Month

6.3.1 The tentative schedule for environmental monitoring in February 2011 is provided in Appendix F.

Page 27: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 23 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

7 CONCLUSIONS AND RECOMMENDATIONS

7.1 Conclusions

7.1.1 The construction phase of the project commenced in December 2009.

7.1.2 1-hour TSP, 24-hour TSP and noise monitoring were carried out in the reporting month.

7.1.3 All 1-hour TSP and 24-hour TSP monitoring results complied with the Action / Limit Level.

7.1.4 According to the Contractor’s information, no noise complaint was received in the reporting month. Hence, no Action Level exceedance was recorded.

7.1.5 No Limit Level exceedance of noise was recorded at all monitoring station in the reporting month.

7.1.6 One landscape and visual audit was carried out in the reporting month. Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the landscape and visual audit.

7.1.7 Environmental site inspections were carried out 4 times in January 2011. Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

Page 28: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05

HATS Stage 2A,

Construction of Interconnection Tunnel and Diaphragm Wall for

Main Pumping Station at SCISTW

China State – Shanghai Tunnel Joint Venture Monthly EM&A Report for January 2011

AECOM Asia Co. Ltd. 24 February 2011 P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\rev.0 (January 2011).doc

7.2 Recommendations

7.2.1 According to the environmental site inspections performed in the reporting month, the following recommendations were provided:

Air Quality Impact

Nil.

Construction Noise Impact

Noise Emission Label (NEL) should be affixed to air compressors employed within the works area.

Water Quality Impact

Proper bunds/sand bags/channels at the site boundaries, cover the gullies or other means should be provided to avoid any surface run-off or wastewater from construction works flowing outside the works area.

Chemical and Waste Management

Housekeeping within the works area should be properly maintained. General refuse and C&D wastes accumulated within the site area should be removed regularly and properly.

All oil drums placed within site areas should be properly stored with provision of drip tray in order to retain any oil leakage. Regular inspection on the site condition should be conducted to ensure all oil drums are properly stored.

Drain hole of the drip tray employed within the works area should be plugged properly to avoid any oil leakage.

Drip trays or temporarily with tarpaulin sheets should be provided when works with potential oil leakage (like oil filling) were carrying out within the works area.

Any oil mixed material, like oil stains, found within the works area should be cleared and disposed of properly as chemical wastes.

Landscape and Visual Impact

Proper tree protection measures should be provided to the existing trees located within the works area to avoid accidental damage of the existing trees by the works.

Page 29: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

FIGURES

Page 30: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

FIGURE 1.1

General Layout Plan of the Project Site

Page 31: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 32: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 33: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 34: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX A

Project Organization Structure

Page 35: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Employment RelationshipWorking Relationship

SCALE DATE

CHECK DRAWN

JOB NO. APPENDIX Rev.

Project Organization Structure

Contract No. DC/2009/05HATS Stage 2A

Construction of Interconnection Tunnel and DiaphragmWall for

Main Pumping Station at SCISTW

N.T.S. Dec-09

60143571A -

ENFL LCHC

Environmental ProtectionDepartment (EPD)

Project Proponent

Drainage Services Department(DSD)

Independent EnvironmentalChecker (IEC))

Mott MacDonaldHong Kong Ltd.

Environmental Team (ET)

AECOM Asia Company Ltd.

Engineer / Engineer'sRepresentative (ER)

Ove Arup & Partners HongKong Ltd.

Contractor

China State – Shanghai TunnelJoint VentureMonitoring + Audit + Recommendation

Liaision

Liaison

Liaison

Recommendation & Improvements

Recommendation&

Improvements

Liaison

Liaison,Recommendation& Improvements

Supervision

app_a - Project Organization Structure

Page 36: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX B

Construction Programme

Page 37: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

Key DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey Dates

( For All Wor( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )

GeneralGeneralGeneralGeneralGeneralGeneralGeneralGeneral

KD-1000 Letter of Acceptance 03-Sep-09 03-Sep-09 A 0

KD-2000 Contract Commencement 17-Sep-09 17-Sep-09 A 0

KD-2500 Revised Contract Completion 19-Dec-11 18-Feb-12* 0 0

KD-2600 Revised End of Maintenance Period 19-Dec-12 18-Feb-13 0 0

Portion HandPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion Handover

KD-6000 Portion 2 (1 day) 17-Sep-09 17-Sep-09 A 0

KD-6100 Portion 3 (1 day) 17-Sep-09 17-Sep-09 A 0

KD-6200 Portion 4 (1 day) 17-Sep-09 17-Sep-09 A 0

KD-6400 Portion 6 (1 day) 17-Sep-09 17-Sep-09 A 0

KD-6500 Portion A (1 day) 17-Sep-09 17-Sep-09 A 0

KD-6600 Portion B (1 day) 17-Sep-09 17-Sep-09 A 0

KD-6700 Portion C (1 day) 17-Sep-09 17-Sep-09 A 0

KD-6300 Portion 5 (Latest Possession 549 days) 19-Mar-11 19-Mar-11* 0 0

Section I of thSection I of the Works (387 days)Section I of the Works (387 days)Section I of the Works (387 days)Section I of the Works (387 days)Section I of the Works (387 days)Section I of the Works (387 days)Section I of the Works (387 days)

KD-3010 Extension of Time (EOT1) granted for Claims 1,3,4,6, 8 & 9 08-Oct-10 A 20-Oct-10 A 0

KD-3020 Extension of Time (EOT2) granted for Claim 12,14, 17&18 21-Oct-10 A 06-Dec-10 A 0

KD-3000 Section I of the Works (Extended) 09-Oct-10 31-Jan-11* 0 -55

Section II of tSection II of the Works (730 days)Section II of the Works (730 days)Section II of the Works (730 days)Section II of the Works (730 days)Section II of the Works (730 days)Section II of the Works (730 days)Section II of the Works (730 days)

KD-4010 Extension of Time (EOT1) granted for Claims 1,3,4,6, 8&9 16-Sep-11* 27-Sep-11 10 0

KD-4020 Extension of Time (EOT2) granted for Claim 12,14, 17 & 18 28-Sep-11 15-Nov-11 49 0

KD-4000 Section II of the Works (Extended) 17-Sep-11 15-Nov-11* 0 0

Section III of tSection III of the Works (823 days)Section III of the Works (823 days)Section III of the Works (823 days)Section III of the Works (823 days)Section III of the Works (823 days)Section III of the Works (823 days)Section III of the Works (823 days)

KD-5010 Extension of Time (EOT1) granted for Claims 1,3,4,6, 8&9 19-Dec-11* 30-Dec-11 11 0

KD-5020 Extension of Time (EOT2) granted for Claim 12,14, 17&18 31-Dec-11 18-Feb-12 50 0

KD-5000 Section III of the Works (Extended) 19-Dec-11 18-Feb-12* 0 0

Section IV (1)Section IV (1) of the Additional Works (131 daysSection IV (1) of the Additional Works (131 daysSection IV (1) of the Additional Works (131 daysSection IV (1) of the Additional Works (131 daysSection IV (1) of the Additional Works (131 daysSection IV (1) of the Additional Works (131 daysSection IV (1) of the Additional Works (131 days

KD-5030 Section IV (1) - Part of Section Hand Over to ST 25-Aug-10 A 0

Section IV (2)Section IV (2) of the Additional Works (199 daysSection IV (2) of the Additional Works (199 daysSection IV (2) of the Additional Works (199 daysSection IV (2) of the Additional Works (199 daysSection IV (2) of the Additional Works (199 daysSection IV (2) of the Additional Works (199 daysSection IV (2) of the Additional Works (199 days

KD-5040 Section IV (2) - Part of Section Hand Over to ST 15-Oct-10 A 0

Section IV (3)Section IV (3) of the Addtional Works (199 days)Section IV (3) of the Addtional Works (199 days)Section IV (3) of the Addtional Works (199 days)Section IV (3) of the Addtional Works (199 days)Section IV (3) of the Addtional Works (199 days)Section IV (3) of the Addtional Works (199 days)Section IV (3) of the Addtional Works (199 days)

KD-5050 Section IV (3) Completion of Additional Works 30-Dec-10 A 0

PreliminariPreliminaries and General RequirementPreliminaries and General RequirementPreliminaries and General RequirementPreliminaries and General RequirementPreliminaries and General RequirementPreliminaries and General RequirementPreliminaries and General Requirement

General ReqGeneral RequirementGeneral RequirementGeneral RequirementGeneral RequirementGeneral RequirementGeneral RequirementGeneral Requirement

GeneralGeneralGeneralGeneralGeneralGeneralGeneralGeneral

PG/00020 General Site Clearance 17-Sep-09 30-Sep-09 17-Sep-09 A 30-Sep-09 A 0

PG/00030 Establish Cont & Eng's Temp Site Office 17-Sep-09 30-Sep-09 17-Sep-09 A 30-Sep-09 A 0

PG/00040 Initial Survey of Site 17-Sep-09 07-Oct-09 17-Sep-09 A 07-Oct-09 A 0

PG/00050 Construction of Steel Fencing & Gates 17-Sep-09 14-Oct-09 17-Sep-09 A 14-Oct-09 A 0

PG/00060 Construction of Contractor Accommodation 17-Sep-09 26-Nov-09 17-Sep-09 A 26-Nov-09 A 0

PG/00070 Provision of Interim Engineer Office 17-Sep-09 30-Sep-09 17-Sep-09 A 30-Sep-09 A 0

PG/00080 Submit Engineer Accommodation Proposal 17-Sep-09 18-Oct-09 17-Sep-09 A 18-Oct-09 A 0

PG/00110 Take Over Control Gate No.2 from ADF Contractor 15-Oct-09 15-Oct-09 15-Oct-09 A 15-Oct-09 A 0

PG/00090 Approval for Engineer's Accommodation Proposal 19-Oct-09 31-Dec-09 19-Oct-09 A 31-Dec-09 A 0

PG/00100 Construction of Engineer Accommodation 22-Oct-09 11-Feb-10 22-Oct-09 A 11-Feb-10 A 0

PG/00120 Handover Portion 3 to MPS Contractor 24-Oct-11 24-Oct-11 24-Feb-12 24-Feb-12 1 -101

PG/00130 Handover Control Gate No2 to 4 to MPS Contractor 25-Jan-12 25-Jan-12 18-Apr-12 18-Apr-12 1 306

PG/00140 Handover Portions 2 & 4 to MPS Contractor 25-Jan-12 25-Jan-12 18-Apr-12 18-Apr-12 1 -60

PG/00150 Handover Portions A & D to MPS Contractor 25-Jan-12 25-Jan-12 18-Apr-12 18-Apr-12 1 306

PG/00160 Handover Eng Accommodation to MPS Contractor 25-Jan-12 25-Jan-12 18-Apr-12 18-Apr-12 1 306

PG/00170 Handover Switchboard to MPS Contractor(deleted) 25-Jan-12 25-Jan-12 18-Apr-12 18-Apr-12 0 307

Submission,Submission, Approvals and PermitsSubmission, Approvals and PermitsSubmission, Approvals and PermitsSubmission, Approvals and PermitsSubmission, Approvals and PermitsSubmission, Approvals and PermitsSubmission, Approvals and Permits

GeneralGeneralGeneralGeneralGeneralGeneralGeneralGeneral

PG/00220 Submission of Initial Works Programme 03-Sep-09 21-Sep-09 03-Sep-09 A 21-Sep-09 A 0

PG/00260 Submission of Draft Safety Plan 03-Sep-09 16-Sep-09 03-Sep-09 A 16-Sep-09 A 0

PG/00270 Submission of Final Safety Plan 03-Sep-09 07-Oct-09 03-Sep-09 A 07-Oct-09 A 0

PG/00290 Submission of Subcontractor Management Plan 03-Sep-09 02-Oct-09 03-Sep-09 A 02-Oct-09 A 0

PG/00300 Submit Draft Environmental Management Plan 03-Sep-09 23-Sep-09 03-Sep-09 A 23-Sep-09 A 0

PG/00310 Submit Final Environmental Management Plan 03-Sep-09 17-Oct-09 03-Sep-09 A 17-Oct-09 A 0

PG/00250 Submission of 1st 3Mths Rolling Programme 17-Sep-09 17-Sep-09 17-Sep-09 A 17-Sep-09 A 0

PG/00280 Submission of Staff/ Organisation Chart 17-Sep-09 30-Sep-09 17-Sep-09 A 30-Sep-09 A 0

PG/00330 Submission of WaterProofing Concrete 17-Sep-09 30-Sep-09 17-Sep-09 A 30-Sep-09 A 0

PG/00350 Establish Site Liaison Group SLG 17-Sep-09 16-Oct-09 17-Sep-09 A 16-Oct-09 A 0

PG/00230 Engineer's Approval of Works Programme 22-Sep-09 22-Oct-09 22-Sep-09 A 22-Oct-09 A 0

PG/00320 Submission of Initial Survey Records 01-Oct-09 14-Oct-09 01-Oct-09 A 14-Oct-09 A 0

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

Letter of Acceptance

Contract Commencement

Revised Contract Completion

Portion 2 (1 day)

Portion 3 (1 day)

Portion 4 (1 day)

Portion 6 (1 day)

Portion A (1 day)

Portion B (1 day)

Portion C (1 day)

Portion 5 (Latest Possession 549 days)

Extension of Time (EOT1) granted for Claims 1,3,4,6, 8 & 9

Extension of Time (EOT2) granted for Claim 12,14, 17&18

Section I of the Works (Extended)

Extension of Time (EOT1) granted for Claims 1,3,4,6, 8&9

Extension of Time (EOT2) granted for Claim 12,14, 17 & 18

Section II of the Works (Extended)

Extension of Time (EOT1) granted for Claims 1,3,4,6, 8&9

Extension of Time (EOT2) granted for Claim 12,14, 17&18

Section III of the Works (Extended)

Section IV (1) - Part of Section Hand Over to ST

Section IV (2) - Part of Section Hand Over to ST

Section IV (3) Completion of Additional Works

General Site Clearance

Establish Cont & Eng's Temp Site Office

Initial Survey of Site

Construction of Steel Fencing & Gates

Construction of Contractor Accommodation

Provision of Interim Engineer Office

Submit Engineer Accommodation Proposal

Take Over Control Gate No.2 from ADF Contractor

Approval for Engineer's Accommodation Proposal

Construction of Engineer Accommodation

Handover Portion 3 to MPS Contractor

Handover Control Gate No2 to 4 to MPS Contractor

Handover Portions 2 & 4 to MPS Contractor

Handover Portions A & D to MPS Contractor

Handover Eng Accommodation to MPS Contractor

Handover Switchboard to MPS Contractor(deleted)

Submission of Initial Works Programme

Submission of Draft Safety Plan

Submission of Final Safety Plan

Submission of Subcontractor Management Plan

Submit Draft Environmental Management Plan

Submit Final Environmental Management Plan

Submission of 1st 3Mths Rolling Programme

Submission of Staff/ Organisation Chart

Submission of WaterProofing Concrete

Establish Site Liaison Group SLG

Engineer's Approval of Works Programme

Submission of Initial Survey Records

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 1 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 38: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

PG/00340 Engineer's Approval of W.P Concrete 01-Oct-09 04-Jan-10 01-Oct-09 A 04-Jan-10 A 0

PG/00240 Submission of Detailed Works Programme 23-Oct-09 24-Mar-10 23-Oct-09 A 24-Mar-10 A 0

Section 1Section 1Section 1Section 1Section 1Section 1Section 1Section 1

( For All Wor( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )

Key DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey Dates

KD3000 Achievement of Section I 16-Nov-10 06-Mar-11 0 -89

Portion HandPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion Handover

KD6200 Portion 4 (1 day) 17-Sep-09 17-Sep-09 A 0

Inlet ChambeInlet ChamberInlet ChamberInlet ChamberInlet ChamberInlet ChamberInlet ChamberInlet Chamber

Diaphragm WDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm Wall

S1/02040 Mobilization of Plant and Labours 06-Oct-09 22-Mar-10 06-Oct-09 A 22-Mar-10 A 0

S1/02050 Establishment of Slurry Treatment Plant 06-Oct-09 14-Dec-09 06-Oct-09 A 14-Dec-09 A 0

S1/02070 Inlet Chamber: Preparation for DW construction 22-Mar-10 22-Mar-10 22-Mar-10 A 22-Mar-10 A 0

S1/02060 C1-C13,P1-P3&P41-P42 (18 nos. Panels) 23-Mar-10 28-Sep-10 23-Mar-10 A 10-Feb-11 7 -91

S1/02080 Inlet Chamber: DW Panel P42 23-Mar-10 03-May-10 23-Mar-10 A 03-May-10 A 0

S1/02090 Inlet Chamber: DW Panel P2 04-May-10 17-May-10 04-May-10 A 17-May-10 A 0

S1/02100 Inlet Chamber: DW Panel C3 18-May-10 29-May-10 18-May-10 A 29-May-10 A 0

S1/02110 Inlet Chamber: DW Panel C11 19-May-10 04-Jun-10 19-May-10 A 04-Jun-10 A 0

S1/02120 Inlet Chamber: DW Panel C7 04-Jun-10 10-Jul-10 04-Jun-10 A 10-Jul-10 A 0

S1/02130 Inlet Chamber: DW Panel P1 07-Jun-10 19-Jun-10 07-Jun-10 A 19-Jun-10 A 0

S1/02140 Inlet Chamber: DW Panel P41+C1 11-Jul-10 02-Aug-10 11-Jul-10 A 02-Aug-10 A 0

S1/02150 Inlet Chamber: DW Panel C9 23-Jul-10 10-Aug-10 23-Jul-10 A 22-Oct-10 A 0

S1/02170 Inlet Chamber: DW Panel P3+C13 22-Aug-10 03-Sep-10 05-Aug-10 A 31-Aug-10 A 0

S1/02160 Inlet Chamber: DW Panel C5 10-Aug-10 22-Aug-10 06-Aug-10 A 08-Sep-10 A 0

S1/02180 Inlet Chamber: DW Panel C2 04-Sep-10 07-Sep-10 25-Sep-10 A 11-Feb-11 8 -91

S1/02210 Inlet Chamber: DW Panel C12 16-Sep-10 19-Sep-10 27-Sep-10 A 29-Nov-10 A 0

S1/02190 Inlet Chamber: DW Panel C10 08-Sep-10 11-Sep-10 29-Oct-10 A 22-Nov-10 A 0

S1/02220 Inlet Chamber: DW Panel C4 20-Sep-10 23-Sep-10 03-Nov-10 A 09-Dec-10 A 0

S1/02200 Inlet Chamber: DW Panel C6 12-Sep-10 15-Sep-10 19-Nov-10 A 26-Nov-10 A 0

S1/02230 Inlet Chamber: DW Panel C8 25-Sep-10 28-Sep-10 27-Nov-10 A 11-Feb-11 3 -91

S1/02260 Carry Out Toe Grouting 29-Sep-10 15-Nov-10 10-Dec-10 A 05-Mar-11 30 -85

S1/02270 Submission of As-built Record of Diaphragm Wall 29-Sep-10 26-Oct-10 12-Feb-11 11-Mar-11 28 344

S1/02262 Dummy for Toe Grouting 06-Mar-11 06-Mar-11 0 -85

S1/02280 Access Date to penetrate Dwall by SCS Contractor 16-Nov-10 16-Nov-10 06-Mar-11 08-Mar-11 2 348

Initial Works /Initial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated Submission

S1/01020 Site Clearance (Portion 4) 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S1/01030 Precondition Survey of Existing Structures 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S1/01040 Erection of Steel Fencing & Entrance Gate 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S1/01070 Submission of Diaphragm Wall M.S. 17-Sep-09 05-Oct-09 17-Sep-09 A 05-Oct-09 A 0

S1/01090 Submission of Ground Treatment M.S. 17-Sep-09 05-Oct-09 17-Sep-09 A 05-Oct-09 A 0

S1/01080 Engineer's Review of Diaphragm Wall M.S. 06-Oct-09 21-Oct-09 06-Oct-09 A 21-Oct-09 A 0

S1/01100 Engineer's Approval of Ground Treatment M.S. 06-Oct-09 21-Oct-09 06-Oct-09 A 21-Oct-09 A 0

S1/01050 Pre-drilling Works of Diaphragm Wall 14-Oct-09 16-Nov-09 14-Oct-09 A 16-Nov-09 A 0

S1/01120 Installation of Geotechnical Instruments 14-Oct-09 30-Nov-09 14-Oct-09 A 30-Nov-09 A 0

S1/01110 Construction of Guide Wall 22-Oct-09 02-Nov-09 22-Oct-09 A 02-Nov-09 A 0

S1/01060 Confirm Founding Level of Diaphragm Wall 17-Nov-09 04-Aug-10 17-Nov-09 A 30-Nov-10 A 0

Utilities and Utilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and Services

GeneralGeneralGeneralGeneralGeneralGeneralGeneralGeneral

S1/01000 Underground Utilities Detection & Trial Holes 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

Section 2Section 2Section 2Section 2Section 2Section 2Section 2Section 2

( For All Wor( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )

Key DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey Dates

KD4000 Achievement of Section II 24-Oct-11 23-Feb-12 0 -101

Portion HandPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion Handover

KD6100 Portion 3 (1 day) 17-Sep-09 17-Sep-09 A 0

Main PumpinMain Pumping StationMain Pumping StationMain Pumping StationMain Pumping StationMain Pumping StationMain Pumping StationMain Pumping Station

Diaphragm WDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm WallDiaphragm Wall

S2/03550 P4 to P40 (37 nos. Panels) 15-Dec-09 19-Sep-10 15-Dec-09 A 31-Dec-10 A 0

S2/03560 Main Pumping Station: DW Panel P24 15-Dec-09 04-Jan-10 15-Dec-09 A 04-Jan-10 A 0

S2/03570 Main Pumping Station: DW Panel P36 23-Dec-09 12-Jan-10 23-Dec-09 A 12-Jan-10 A 0

S2/03580 Main Pumping Station: DW Panel P26 05-Jan-10 23-Jan-10 05-Jan-10 A 23-Jan-10 A 0

S2/03590 Main Pumping Station: DW Panel P16 14-Jan-10 27-Jan-10 14-Jan-10 A 27-Jan-10 A 0

S2/03600 Main Pumping Station: DW Panel P30 20-Jan-10 04-Feb-10 20-Jan-10 A 04-Feb-10 A 0

S2/03610 Main Pumping Station: DW Panel P40 28-Jan-10 09-Feb-10 28-Jan-10 A 09-Feb-10 A 0

S2/04030 All Test including Sonic Test to completed Dwall 01-Feb-10 29-Sep-10 01-Feb-10 A 15-Dec-10 A 0

S2/03620 Main Pumping Station: DW Panel P22 02-Feb-10 23-Feb-10 02-Feb-10 A 23-Feb-10 A 0

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

Engineer's Approval of W.P Concrete

Submission of Detailed Works Programme

Achievement of Section I

Portion 4 (1 day)

Mobilization of Plant and Labours

Establishment of Slurry Treatment Plant

Inlet Chamber: Preparation for DW construction

C1-C13,P1-P3&P41-P42 (18 nos. Panels)

Inlet Chamber: DW Panel P42

Inlet Chamber: DW Panel P2

Inlet Chamber: DW Panel C3

Inlet Chamber: DW Panel C11

Inlet Chamber: DW Panel C7

Inlet Chamber: DW Panel P1

Inlet Chamber: DW Panel P41+C1

Inlet Chamber: DW Panel C9

Inlet Chamber: DW Panel P3+C13

Inlet Chamber: DW Panel C5

Inlet Chamber: DW Panel C2

Inlet Chamber: DW Panel C12

Inlet Chamber: DW Panel C10

Inlet Chamber: DW Panel C4

Inlet Chamber: DW Panel C6

Inlet Chamber: DW Panel C8

Carry Out Toe Grouting

Submission of As-built Record of Diaphragm Wall

Dummy for Toe Grouting

Access Date to penetrate Dwall by SCS Contractor

Site Clearance (Portion 4)

Precondition Survey of Existing Structures

Erection of Steel Fencing & Entrance Gate

Submission of Diaphragm Wall M.S.

Submission of Ground Treatment M.S.

Engineer's Review of Diaphragm Wall M.S.

Engineer's Approval of Ground Treatment M.S.

Pre-drilling Works of Diaphragm Wall

Installation of Geotechnical Instruments

Construction of Guide Wall

Confirm Founding Level of Diaphragm Wall

Underground Utilities Detection & Trial Holes

Achievement of Section II

Portion 3 (1 day)

P4 to P40 (37 nos. Panels)

Main Pumping Station: DW Panel P24

Main Pumping Station: DW Panel P36

Main Pumping Station: DW Panel P26

Main Pumping Station: DW Panel P16

Main Pumping Station: DW Panel P30

Main Pumping Station: DW Panel P40

All Test including Sonic Test to completed Dwall

Main Pumping Station: DW Panel P22

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 2 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 39: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

S2/03630 Main Pumping Station: DW Panel P14 04-Feb-10 01-Mar-10 04-Feb-10 A 01-Mar-10 A 0

S2/03640 Main Pumping Station: DW Panel P28 19-Feb-10 05-Mar-10 19-Feb-10 A 05-Mar-10 A 0

S2/03810 Main Pumping Station: DW Panel P4 23-Feb-10 17-Jul-10 23-Feb-10 A 17-Jul-10 A 0

S2/03820 Main Pumping Station: P4 Excavation 23-Feb-10 19-Mar-10 23-Feb-10 A 19-Mar-10 A 0

S2/03650 Main Pumping Station: DW Panel P34 02-Mar-10 11-Mar-10 02-Mar-10 A 11-Mar-10 A 0

S2/03660 Main Pumping Station: DW Panel P18 03-Mar-10 17-Mar-10 03-Mar-10 A 17-Mar-10 A 0

S2/03780 Main Pumping Station: DW Panel P10 05-Mar-10 06-Jun-10 05-Mar-10 A 06-Jun-10 A 0

S2/03782 Main Pumping Station: P10 Panel Excavation 1 05-Mar-10 19-Mar-10 05-Mar-10 A 19-Mar-10 A 0

S2/03670 Main Pumping Station: DW Panel P38 09-Mar-10 22-Mar-10 09-Mar-10 A 22-Mar-10 A 0

S2/04020 Sonic Test to P14 and P30 17-Mar-10 17-Mar-10 17-Mar-10 A 17-Mar-10 A 0

S2/03680 Main Pumping Station: DW Panel P25 23-Mar-10 30-Mar-10 23-Mar-10 A 30-Mar-10 A 0

S2/03690 Main Pumping Station: DW Panel P17 23-Mar-10 02-Apr-10 23-Mar-10 A 02-Apr-10 A 0

S2/03700 Main Pumping Station: DW Panel P29 26-Mar-10 09-Apr-10 26-Mar-10 A 09-Apr-10 A 0

S2/03830 Main Pumping Station: P4 Backfill with Agg /Conc 27-Mar-10 29-Mar-10 27-Mar-10 A 29-Mar-10 A 0

S2/03720 Main Pumping Station: DW Panel P6 02-Apr-10 16-Apr-10 02-Apr-10 A 16-Apr-10 A 0

S2/03730 Main Pumping Station: DW Panel P15 07-Apr-10 19-Apr-10 07-Apr-10 A 19-Apr-10 A 0

S2/03710 Main Pumping Station: DW Panel P23 08-Apr-10 13-Apr-10 08-Apr-10 A 13-Apr-10 A 0

S2/03740 Main Pumping Station: DW Panel P27 15-Apr-10 26-Apr-10 15-Apr-10 A 26-Apr-10 A 0

S2/03750 Main Pumping Station: DW Panel P35 18-Apr-10 06-May-10 18-Apr-10 A 06-May-10 A 0

S2/03760 Main Pumping Station: DW Panel P20 23-Apr-10 08-May-10 23-Apr-10 A 08-May-10 A 0

S2/03770 Main Pumping Station: DW Panel P39 27-Apr-10 25-May-10 27-Apr-10 A 25-May-10 A 0

S2/03784 Main Pumping Station: P10 Panel Excavation 2 30-Apr-10 05-Jun-10 30-Apr-10 A 05-Jun-10 A 0

S2/03890 Main Pumping Station: DW Panel P37 02-May-10 09-Jun-10 02-May-10 A 09-Jun-10 A 0

S2/03790 Main Pumping Station: DW Panel P32 04-May-10 24-Jun-10 04-May-10 A 24-Jun-10 A 0

S2/03840 Main Pumping Station: P4 Submit Method Statement 10-May-10 09-Jul-10 10-May-10 A 09-Jul-10 A 0

S2/03910 Main Pumping Station: DW Panel P21 12-May-10 30-Jun-10 12-May-10 A 30-Jun-10 A 0

S2/03860 Main Pumping Station: P4 Reconstruction 04-Jun-10 17-Jul-10 04-Jun-10 A 17-Jul-10 A 0

S2/03786 Main Pumping Station: P10 Concrete 10-Jun-10 10-Jun-10 10-Jun-10 A 10-Jun-10 A 0

S2/03870 Main Pumping Station: DW Panel P12 12-Jun-10 09-Aug-10 12-Jun-10 A 19-Aug-10 A 0

S2/03900 Main Pumping Station: DW Panel P31 02-Jul-10 14-Jul-10 02-Jul-10 A 14-Jul-10 A 0

S2/03850 Main Pumping Station: P4 Engineer Approval on MS 10-Jul-10 13-Jul-10 10-Jul-10 A 13-Jul-10 A 0

S2/03880 Main Pumping Station: DW Panel P33 16-Jul-10 28-Jul-10 16-Jul-10 A 28-Jul-10 A 0

S2/03930 Main Pumping Station: DW Panel P5 29-Jul-10 06-Aug-10 29-Jul-10 A 09-Aug-10 A 0

S2/03800 Main Pumping Station: DW Panel P8 12-Aug-10 26-Aug-10 16-Aug-10 A 28-Sep-10 A 0

S2/04050 Carry out Toe Grouting 07-Aug-10 20-Oct-10 19-Aug-10 A 10-Feb-11 7 -96

S2/03960 Main Pumping Station: DW Panel P11 06-Sep-10 13-Sep-10 13-Sep-10 A 06-Nov-10 A 0

S2/03950 Main Pumping Station: DW Panel P9 01-Sep-10 08-Sep-10 06-Oct-10 A 16-Dec-10 A 0

S2/03940 Main Pumping Station: DW Panel P7 27-Aug-10 03-Sep-10 07-Oct-10 A 04-Dec-10 A 0

S2/03970 Main Pumping Station: DW Panel P13 11-Sep-10 18-Sep-10 01-Nov-10 A 16-Nov-10 A 0

S2/04080 Install PumpWells,Recharge&Observation Wells 30-Sep-10 20-Oct-10 14-Dec-10 A 15-Feb-11 6 -101

S2/03920 Main Pumping Station: DW Panel P19 07-Aug-10 14-Aug-10 21-Dec-10 A 30-Dec-10 A 0

S2/03980 Main Pumping Station: Demobilization of Plant 15-Sep-10 19-Sep-10 27-Dec-10 A 31-Jan-11 1 -101

S2/04070 Capping Beam (Inlet Chamber Inclusive) 21-Oct-10 10-Nov-10 11-Feb-11 03-Mar-11 21 -96

S2/04100 Submission of As-built Record of Diaphragm Wall 21-Oct-10 10-Nov-10 11-Feb-11 03-Mar-11 21 39

S2/04090 Pumping Test (Inlet Chamber Inclusive) 21-Oct-10 10-Nov-10 16-Feb-11 08-Mar-11 21 -101

Initial Works /Initial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated Submission

S2/03120 Site Clearance (Portion 3) 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S2/03130 Tree Survey 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S2/03160 Precondition Survey of Existing Structures 17-Sep-09 23-Oct-09 17-Sep-09 A 23-Oct-09 A 0

S2/03170 Erection of Steel Fencing & Entrance Gates 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S2/03150 Demolition of Existing Storage Shed 02-Oct-09 03-Nov-09 02-Oct-09 A 03-Nov-09 A 0

S2/03230 Reprovision of Store Shed 05-Oct-09 16-Nov-09 05-Oct-09 A 16-Nov-09 A 0

S2/03140 Assign a Location for Trees Transplant 14-Oct-09 30-Oct-09 14-Oct-09 A 30-Oct-09 A 0

S2/03180 Predrilling Works of Diaphragm Wall 14-Oct-09 16-Nov-09 14-Oct-09 A 16-Nov-09 A 0

S2/03200 Construction of Guild Wall 14-Oct-09 14-Dec-09 14-Oct-09 A 14-Dec-09 A 0

S2/03210 Installation of Geotechnical Instruments 14-Oct-09 30-Nov-09 14-Oct-09 A 30-Nov-09 A 0

S2/03220 Relocation of Materials Possessed by ST2/DSD 17-Nov-09 24-Nov-09 17-Nov-09 A 24-Nov-09 A 0

S2/03190 Confirm Founding level of Diaphragm Wall 19-Nov-09 20-Nov-09 19-Nov-09 A 20-Nov-09 A 0

S2/03250 Predrilling for Mini-piles (at Ground Level) 19-Nov-09 18-Nov-10 19-Nov-09 A 19-Mar-11 40 58

S2/03260 Predrilling for Mini-piles (9 nos) 19-Nov-09 20-Jan-10 19-Nov-09 A 20-Jan-10 A 0

S2/03240 Transplant of Existing Trees 05-Feb-10 27-Feb-10 05-Feb-10 A 27-Feb-10 A 0

S2/03270 Predrilling for Mini-piles (24 nos) 02-Jul-10 14-Oct-10 02-Jul-10 A 28-Feb-11 23 23

S2/03280 Confirm Founding level of Mini-piles 19-Nov-10 02-Dec-10 01-Mar-11 14-Mar-11 12 23

Other WorksOther WorksOther WorksOther WorksOther WorksOther WorksOther WorksOther Works

S2/05020 Excavation +5.5mPD to -16mPD 11-Nov-10 25-Nov-10 09-Mar-11 23-Mar-11 15 -101

S2/05030 Construction of 1st Layer Ringbeam at -14.5mPD 26-Nov-10 12-Dec-10 24-Mar-11 09-Apr-11 17 -101

S2/05040 Excavation down to -24mPD 13-Dec-10 30-Dec-10 10-Apr-11 27-Apr-11 18 -101

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

Main Pumping Station: DW Panel P14

Main Pumping Station: DW Panel P28

Main Pumping Station: DW Panel P4

Main Pumping Station: P4 Excavation

Main Pumping Station: DW Panel P34

Main Pumping Station: DW Panel P18

Main Pumping Station: DW Panel P10

Main Pumping Station: P10 Panel Excavation 1

Main Pumping Station: DW Panel P38

Sonic Test to P14 and P30

Main Pumping Station: DW Panel P25

Main Pumping Station: DW Panel P17

Main Pumping Station: DW Panel P29

Main Pumping Station: P4 Backfill with Agg /Conc

Main Pumping Station: DW Panel P6

Main Pumping Station: DW Panel P15

Main Pumping Station: DW Panel P23

Main Pumping Station: DW Panel P27

Main Pumping Station: DW Panel P35

Main Pumping Station: DW Panel P20

Main Pumping Station: DW Panel P39

Main Pumping Station: P10 Panel Excavation 2

Main Pumping Station: DW Panel P37

Main Pumping Station: DW Panel P32

Main Pumping Station: P4 Submit Method Statement

Main Pumping Station: DW Panel P21

Main Pumping Station: P4 Reconstruction

Main Pumping Station: P10 Concrete

Main Pumping Station: DW Panel P12

Main Pumping Station: DW Panel P31

Main Pumping Station: P4 Engineer Approval on MS

Main Pumping Station: DW Panel P33

Main Pumping Station: DW Panel P5

Main Pumping Station: DW Panel P8

Carry out Toe Grouting

Main Pumping Station: DW Panel P11

Main Pumping Station: DW Panel P9

Main Pumping Station: DW Panel P7

Main Pumping Station: DW Panel P13

Install PumpWells,Recharge&Observation Wells

Main Pumping Station: DW Panel P19

Main Pumping Station: Demobilization of Plant

Capping Beam (Inlet Chamber Inclusive)

Submission of As-built Record of Diaphragm Wall

Pumping Test (Inlet Chamber Inclusive)

Site Clearance (Portion 3)

Tree Survey

Precondition Survey of Existing Structures

Erection of Steel Fencing & Entrance Gates

Demolition of Existing Storage Shed

Reprovision of Store Shed

Assign a Location for Trees Transplant

Predrilling Works of Diaphragm Wall

Construction of Guild Wall

Installation of Geotechnical Instruments

Relocation of Materials Possessed by ST2/DSD

Confirm Founding level of Diaphragm Wall

Predrilling for Mini-piles (at Ground Level)

Predrilling for Mini-piles (9 nos)

Transplant of Existing Trees

Predrilling for Mini-piles (24 nos)

Confirm Founding level of Mini-piles

Excavation +5.5mPD to -16mPD

Construction of 1st Layer Ringbeam at -14.5mPD

Excavation down to -24mPD

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 3 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 40: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

S2/05050 Construction of 2nd Layer Ringbeam at -23.5mPD 31-Dec-10 16-Jan-11 28-Apr-11 14-May-11 17 -101

S2/05060 Excavation Down to -30mPD 17-Jan-11 30-Jan-11 15-May-11 28-May-11 14 -101

S2/05070 Construction of 3rd Layer Ringbeam, at -28.5mPD 31-Jan-11 25-Feb-11 29-May-11 19-Jun-11 22 -101

S2/05080 Excavation to Final Formation Level -35mPD 26-Feb-11 11-Mar-11 20-Jun-11 03-Jul-11 14 -101

S2/05410 2nd Stage of Pre-drilling 30-Jun-11 21-Jul-11 22 -101

S2/05100 Mobilization of Piling Rig 08-Mar-11 13-Mar-11 30-Jun-11 05-Jul-11 6 -79

S2/05090 Mini-piles Installation (453 nos.) 08-Mar-11 23-Aug-11 22-Jul-11 06-Jan-12 169 -101

S2/05110 Mini-Pile Rig 1: 39 Piles 10-Mar-11 26-May-11 22-Jul-11 29-Sep-11 70 -96

S2/05130 Mini-Pile Rig 2: 39 Piles 10-Mar-11 26-May-11 22-Jul-11 29-Sep-11 70 -96

S2/05150 Mini-Pile Rig 3: 39 Piles 10-Mar-11 26-May-11 22-Jul-11 29-Sep-11 70 -96

S2/05170 Mini-Pile Rig 4: 37 Piles 14-Mar-11 26-May-11 22-Jul-11 27-Sep-11 68 -95

S2/05190 Mini-Pile Rig 5: 36 Piles 14-Mar-11 24-May-11 22-Jul-11 24-Sep-11 65 -95

S2/05210 Mini-Pile Rig 6: 39 Piles 14-Mar-11 30-May-11 22-Jul-11 29-Sep-11 70 -92

S2/05200 Mini-Pile Rig 5: 37 Piles 25-May-11 06-Aug-11 25-Sep-11 01-Dec-11 68 -95

S2/05180 Mini-Pile Rig 4: 36 Piles 27-May-11 06-Aug-11 28-Sep-11 01-Dec-11 65 -95

S2/05120 Mini-Pile Rig 1: 39 Piles 27-May-11 12-Aug-11 30-Sep-11 08-Dec-11 70 -96

S2/05140 Mini-Pile Rig 2: 39 Piles 27-May-11 12-Aug-11 30-Sep-11 08-Dec-11 70 -96

S2/05160 Mini-Pile Rig 3: 39 Piles 27-May-11 12-Aug-11 30-Sep-11 08-Dec-11 70 -96

S2/05220 Mini-Pile Rig 6: 34 Piles 31-May-11 06-Aug-11 30-Sep-11 28-Nov-11 60 -92

S2/05240 Loading Test(10nos.) & Proof Drilling(5 nos.) 24-Jun-11 11-Sep-11 19-Oct-11 06-Jan-12 80 -101

S2/05250 Proof Drilling 6 nos 04-Jul-11 01-Sep-11 29-Oct-11 27-Dec-11 60 -95

S2/05230 Demobilization of Rig 4 to 6 07-Aug-11 08-Aug-11 02-Dec-11 03-Dec-11 2 -95

S2/05260 Loading Test 1 to 3 09-Aug-11 18-Aug-11 05-Dec-11 14-Dec-11 10 -96

S2/05270 Loading Test 4 to 6 19-Aug-11 28-Aug-11 15-Dec-11 24-Dec-11 10 -96

S2/05280 Loading Test 7 and 8 29-Aug-11 07-Sep-11 25-Dec-11 03-Jan-12 10 -96

S2/05290 Loading Test 9 and 10 29-Aug-11 07-Sep-11 25-Dec-11 03-Jan-12 10 -96

S2/05310 Construction of Pile Cap 02-Sep-11 16-Oct-11 03-Jan-12 16-Feb-12 45 -101

S2/05320 Formation and Blinding 02-Sep-11 21-Sep-11 03-Jan-12 22-Jan-12 20 -101

S2/05300 Demobilization of Loading Equipment 08-Sep-11 09-Sep-11 04-Jan-12 05-Jan-12 2 -96

S2/05330 Main Pumping Station Pilecap Bay 1 05-Sep-11 11-Sep-11 06-Jan-12 12-Jan-12 7 -101

S2/05340 Main Pumping Station Pilecap Bay 2 12-Sep-11 18-Sep-11 13-Jan-12 19-Jan-12 7 -101

S2/05350 Main Pumping Station Pilecap Bay 3 19-Sep-11 25-Sep-11 20-Jan-12 26-Jan-12 7 -101

S2/05360 Main Pumping Station Pilecap Bay 4 26-Sep-11 02-Oct-11 27-Jan-12 02-Feb-12 7 -101

S2/05400 Handover Section II Works to MPS Contractor 24-Oct-11 24-Oct-11 02-Feb-12 02-Feb-12 1 -79

S2/05370 Main Pumping Station Pilecap Bay 5 03-Oct-11 09-Oct-11 03-Feb-12 09-Feb-12 7 -101

S2/05380 Main Pumping Station Pilecap Bay 6 10-Oct-11 16-Oct-11 10-Feb-12 16-Feb-12 7 -101

S2/05390 Reinstatement of Wall Openings of Base Slab 10-Oct-11 23-Oct-11 10-Feb-12 23-Feb-12 14 -101

Utilities and Utilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and Services

GeneralGeneralGeneralGeneralGeneralGeneralGeneralGeneral

S2/03010 MPS:Underground Utilities Detection &Trial Holes 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S2/03020 MPS: Diversion of Existing CLP Cables(By Others) 17-Sep-09 31-Oct-09 17-Sep-09 A 31-Oct-09 A 0

S2/03040 MPS: Demolish Existing Abandoned Sewerage 11-Nov-10 01-Dec-10 09-Mar-11 29-Mar-11 18 -48

Section 3Section 3Section 3Section 3Section 3Section 3Section 3Section 3

( For All Wor( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )( For All Works Under the Contract )

Key DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey Dates

KD5000 Achievement of Section III 25-Jan-12 17-Apr-12 0 -60

Portion HandPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion HandoverPortion Handover

KD6000 Portion 2 (1 day) 17-Sep-09 17-Sep-09 A 0

KD6300 Portion 5 (Latest Possession 549 days) 19-Mar-11 19-Mar-11* 0 0

General ReqGeneral RequirementGeneral RequirementGeneral RequirementGeneral RequirementGeneral RequirementGeneral RequirementGeneral Requirement

GeneralGeneralGeneralGeneralGeneralGeneralGeneralGeneral

S3/06010 IC: Ground Stabilization Works at Inlet Chamber 11-Nov-10 22-Feb-11 09-Mar-11 16-Jun-11 100 -34

S3/06020 Handover Section III Works to MPS Contractor 25-Jan-12 25-Jan-12 18-Apr-12 18-Apr-12 1 -60

Inlet ChambeInlet ChamberInlet ChamberInlet ChamberInlet ChamberInlet ChamberInlet ChamberInlet Chamber

GeneralGeneralGeneralGeneralGeneralGeneralGeneralGeneral

S3/06120 Excavation down to Formation -30mPD 12-Mar-11 06-Jun-11 04-Jul-11 28-Sep-11 87 -51

S3/06130 Inlet Chamber: Excavate Down to +2.5mpd 12-Mar-11 15-Mar-11 04-Jul-11 07-Jul-11 4 -51

S3/06140 Inlet Chamber: Install Temp Strut at +3 mpd 16-Mar-11 17-Mar-11 08-Jul-11 09-Jul-11 2 -51

S3/06150 Inlet Chamber: Excavate Down to -4 mpd 18-Mar-11 27-Mar-11 10-Jul-11 19-Jul-11 10 -51

S3/06160 Inlet Chamber: Install Temp Strut at -3.5mpd 28-Mar-11 29-Mar-11 20-Jul-11 21-Jul-11 2 -51

S3/06170 Inlet Chamber: Excavate Down to -10 mpd 30-Mar-11 10-Apr-11 22-Jul-11 02-Aug-11 12 -51

S3/06180 Inlet Chamber: Install Temp Strut at -9.5mpd 11-Apr-11 12-Apr-11 03-Aug-11 04-Aug-11 2 -51

S3/06190 Inlet Chamber: Excavate Down to -14.5 mpd 13-Apr-11 22-Apr-11 05-Aug-11 14-Aug-11 10 -51

S3/06200 Inlet Chamber: Install Temp Strut at -14mpd 23-Apr-11 24-Apr-11 15-Aug-11 16-Aug-11 2 -51

S3/06210 Inlet Chamber: Excavate Down to -19mpd 25-Apr-11 03-May-11 17-Aug-11 25-Aug-11 9 -51

S3/06220 Inlet Chamber: Install Temp Strut at -18.5mpd 04-May-11 05-May-11 26-Aug-11 27-Aug-11 2 -51

S3/06230 Inlet Chamber: Excavate Down to -24.5mpd 06-May-11 17-May-11 28-Aug-11 08-Sep-11 12 -51

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

Construction of 2nd Layer Ringbeam at -23.5mPD

Excavation Down to -30mPD

Construction of 3rd Layer Ringbeam, at -28.5mPD

Excavation to Final Formation Level -35mPD

2nd Stage of Pre-drilling

Mobilization of Piling Rig

Mini-piles Installation (453 nos.)

Mini-Pile Rig 1: 39 Piles

Mini-Pile Rig 2: 39 Piles

Mini-Pile Rig 3: 39 Piles

Mini-Pile Rig 4: 37 Piles

Mini-Pile Rig 5: 36 Piles

Mini-Pile Rig 6: 39 Piles

Mini-Pile Rig 5: 37 Piles

Mini-Pile Rig 4: 36 Piles

Mini-Pile Rig 1: 39 Piles

Mini-Pile Rig 2: 39 Piles

Mini-Pile Rig 3: 39 Piles

Mini-Pile Rig 6: 34 Piles

Loading Test(10nos.) & Proof Drilling(5 nos.)

Proof Drilling 6 nos

Demobilization of Rig 4 to 6

Loading Test 1 to 3

Loading Test 4 to 6

Loading Test 7 and 8

Loading Test 9 and 10

Construction of Pile Cap

Formation and Blinding

Demobilization of Loading Equipment

Main Pumping Station Pilecap Bay 1

Main Pumping Station Pilecap Bay 2

Main Pumping Station Pilecap Bay 3

Main Pumping Station Pilecap Bay 4

Handover Section II Works to MPS Contractor

Main Pumping Station Pilecap Bay 5

Main Pumping Station Pilecap Bay 6

Reinstatement of Wall Openings of Base Slab

MPS:Underground Utilities Detection &Trial Holes

MPS: Diversion of Existing CLP Cables(By Others)

MPS: Demolish Existing Abandoned Sewerage

Achievement of Section III

Portion 2 (1 day)

Portion 5 (Latest Possession 549 days)

IC: Ground Stabilization Works at Inlet Chamber

Handover Section III Works to MPS Contractor

Excavation down to Formation -30mPD

Inlet Chamber: Excavate Down to +2.5mpd

Inlet Chamber: Install Temp Strut at +3 mpd

Inlet Chamber: Excavate Down to -4 mpd

Inlet Chamber: Install Temp Strut at -3.5mpd

Inlet Chamber: Excavate Down to -10 mpd

Inlet Chamber: Install Temp Strut at -9.5mpd

Inlet Chamber: Excavate Down to -14.5 mpd

Inlet Chamber: Install Temp Strut at -14mpd

Inlet Chamber: Excavate Down to -19mpd

Inlet Chamber: Install Temp Strut at -18.5mpd

Inlet Chamber: Excavate Down to -24.5mpd

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 4 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 41: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

S3/06240 Inlet Chamber: Install Temp Strut at -24mpd 18-May-11 19-May-11 09-Sep-11 10-Sep-11 2 -51

S3/06250 Inlet Chamber: Excavate Down to -27.5mpd 20-May-11 26-May-11 11-Sep-11 17-Sep-11 7 -51

S3/06260 Inlet Chamber: Install Temp Strut at -27mpd 27-May-11 28-May-11 18-Sep-11 19-Sep-11 2 -51

S3/06270 Inlet Chamber: Excavate Down to -30mpd 29-May-11 06-Jun-11 20-Sep-11 28-Sep-11 9 -51

S3/06280 Construction of Base Slab 07-Jun-11 02-Jul-11 29-Sep-11 24-Oct-11 26 -51

S3/06290 Inlet Chamber: Formation and Blinding Layer 07-Jun-11 09-Jun-11 29-Sep-11 01-Oct-11 3 -51

S3/06300 Inlet Chamber: Steel Fixing to Base 10-Jun-11 16-Jun-11 02-Oct-11 08-Oct-11 7 -51

S3/06310 Inlet Chamber: Install Thermal Couple 17-Jun-11 20-Jun-11 09-Oct-11 12-Oct-11 4 -51

S3/06320 Inlet Chamber: Steel Fixing 21-Jun-11 27-Jun-11 13-Oct-11 19-Oct-11 7 -51

S3/06330 Inlet Chamber: Cleaning 28-Jun-11 28-Jun-11 20-Oct-11 20-Oct-11 1 -51

S3/06340 Inlet Chamber: Cast the Base 29-Jun-11 29-Jun-11 21-Oct-11 21-Oct-11 1 -51

S3/06350 Inlet Chamber: Concrete Curing 30-Jun-11 02-Jul-11 22-Oct-11 24-Oct-11 3 -51

S3/06400 Dismantle Temp Shoring&Cast R.C. Beams 03-Jul-11 28-Sep-11 25-Oct-11 20-Jan-12 88 -51

S3/06410 IC: Remove Temp Strut at -27 and -18.5mpd 03-Jul-11 05-Jul-11 25-Oct-11 27-Oct-11 3 -51

S3/06420 IC: Construct Waling Beam at -17mpd 06-Jul-11 23-Jul-11 28-Oct-11 14-Nov-11 18 -51

S3/06430 IC: Curing for Waling Beam at -17mpd 24-Jul-11 26-Jul-11 15-Nov-11 17-Nov-11 3 -51

S3/06440 IC: Remove Temp Strut at -24mpd 27-Jul-11 28-Jul-11 18-Nov-11 19-Nov-11 2 -51

S3/06450 IC: Cast the 1m Thick Wall Below Bottom Waling 29-Jul-11 06-Aug-11 20-Nov-11 28-Nov-11 9 -51

S3/06460 IC: Construct Waling Beam at -12.5mpd 07-Aug-11 20-Aug-11 29-Nov-11 12-Dec-11 14 -51

S3/06470 IC: Curing for Waling Beam at -12.5mpd 21-Aug-11 23-Aug-11 13-Dec-11 15-Dec-11 3 -51

S3/06480 IC: Remove Temp Strut at -14mpd 24-Aug-11 25-Aug-11 16-Dec-11 17-Dec-11 2 -51

S3/06490 IC: Construct Waling Beam at -6mpd 26-Aug-11 06-Sep-11 18-Dec-11 29-Dec-11 12 -51

S3/06500 IC: Curing for Waling Beam at -6mpd 07-Sep-11 09-Sep-11 30-Dec-11 01-Jan-12 3 -51

S3/06510 IC: Remove Temp Strut at -9.5mpd 10-Sep-11 11-Sep-11 02-Jan-12 03-Jan-12 2 -51

S3/06520 IC: Construct Waling Beam at +1.5mpd 12-Sep-11 23-Sep-11 04-Jan-12 15-Jan-12 12 -51

S3/06530 IC: Curing for Waling Beam at +1.5mpd 24-Sep-11 26-Sep-11 16-Jan-12 18-Jan-12 3 -51

S3/06540 IC: Remove Temp Strut at -3.5 and +3mpd 27-Sep-11 28-Sep-11 19-Jan-12 20-Jan-12 2 -51

S3/06600 Reinstate Openings at Base Slab 29-Sep-11 12-Oct-11 21-Jan-12 03-Feb-12 14 -51

InterconnectInterconnection TunnelInterconnection TunnelInterconnection TunnelInterconnection TunnelInterconnection TunnelInterconnection TunnelInterconnection Tunnel

Detail DesignDetail DesignDetail DesignDetail DesignDetail DesignDetail DesignDetail DesignDetail Design

S3/07320 TBM Submittals Group A Preliminary Design 19-Jan-10 29-Apr-10 19-Jan-10 A 29-Apr-10 A 0

S3/07360 TBM Submittals Group B Preliminary Design 19-Jan-10 29-Apr-10 19-Jan-10 A 29-Apr-10 A 0

S3/07400 TBM - Preliminary Design for Choice of TBM 19-Jan-10 10-Apr-10 19-Jan-10 A 10-Apr-10 A 0

S3/07420 TBM Submittals Group C Preliminary Design 19-Jan-10 06-Aug-10 19-Jan-10 A 27-Aug-10 A 0

S3/07410 TBM - Design of Proposed TBM 27-Mar-10 06-Aug-10 27-Mar-10 A 27-Aug-10 A 0

S3/07325 Re-submit Group A Preliminary Design 30-Apr-10 02-Jun-10 30-Apr-10 A 02-Jun-10 A 0

S3/07365 TBM Submittals Group B Engineer's Review 30-Apr-10 14-May-10 30-Apr-10 A 14-May-10 A 0

S3/07370 TBM Submittals Group B Engineer's Review 30-Apr-10 14-May-10 30-Apr-10 A 14-May-10 A 0

S3/07380 TBM Submittals Group B Resubmission 15-May-10 02-Jun-10 15-May-10 A 02-Jun-10 A 0

S3/07330 TBM Submittals Group A Engineer's Review 03-Jun-10 09-Jun-10 03-Jun-10 A 09-Jun-10 A 0

S3/07390 TBM Submittals Group B Engineer Approval 03-Jun-10 28-Jun-10 03-Jun-10 A 28-Jun-10 A 0

S3/07340 TBM Submittals Group A Resubmission 09-Jun-10 09-Jun-10 09-Jun-10 A 09-Jun-10 A 0

S3/07350 TBM Submittals Group A Engineer Approval 09-Jun-10 09-Jun-10 09-Jun-10 A 09-Jun-10 A 0

S3/07850 Tunnel Lining Detail Design 28-Jan-10 13-Sep-10 25-Aug-10 A 15-Nov-10 A 0

S3/07430 TBM Submittals Group C Engineer's Review 07-Aug-10 11-Sep-10 27-Aug-10 A 27-Sep-10 A 0

S3/07460 TBM - Manufacturing of TBM & Delivery 22-Aug-10 17-Apr-11 01-Sep-10 A 03-Jun-11 70 -9

S3/07470 Submit Tunnel Layout/Procedure/Equipment to FSD 17-Aug-10 15-Oct-10 08-Sep-10 A 18-Oct-10 A 0

S3/07510 Submit Temp Ventilation System for Tunnel 17-Aug-10 15-Oct-10 08-Sep-10 A 15-Oct-10 A 0

S3/07610 TBM Submittals Group D Work Plan / Training Prog 06-Sep-10 04-Nov-10 08-Sep-10 A 02-Nov-10 A 0

S3/07730 Submit Temp Work Design for Tunnel 01-Oct-10 29-Nov-10 15-Sep-10 A 27-Oct-10 A 0

S3/07650 TBM Submittals Group E Tunnel Safety Programme 06-Sep-10 04-Nov-10 23-Sep-10 A 14-Nov-10 A 0

S3/07440 TBM Submittals Group C Resubmission 12-Sep-10 30-Sep-10 28-Sep-10 A 07-Dec-10 A 0

S3/07450 TBM Submittals Group C Engineer Approval 01-Oct-10 16-Oct-10 04-Oct-10 A 06-Jan-11 A 0

S3/07520 Engineer Review on Temp Ventilation System 16-Oct-10 12-Nov-10 18-Oct-10 A 27-Oct-10 A 0

S3/07690 Submit Segment Annulus Grouting Design 01-Oct-10 29-Nov-10 18-Oct-10 A 15-Nov-10 A 0

S3/07480 FSD Review ofTunnel Layout/Procedure/Equipment 16-Oct-10 12-Nov-10 19-Oct-10 A 29-Oct-10 A 0

S3/07740 Engineer Review on Temp Work Design for Tunnel 30-Nov-10 27-Dec-10 28-Oct-10 A 05-Dec-10 A 0

S3/07490 Re-submit Tunnel Layout/Procedure/Equipment 13-Nov-10 03-Dec-10 30-Oct-10 A 15-Mar-11 40 -8

S3/07530 Resubmit Temp Ventilation System 13-Nov-10 03-Dec-10 01-Nov-10 A 13-Jan-11 A 0

S3/07620 TBM Submittals Group D Engineer Review 05-Nov-10 02-Dec-10 03-Nov-10 A 08-Dec-10 A 0

S3/07660 TBM Submittals Group E Engineer Review 05-Nov-10 02-Dec-10 15-Nov-10 A 06-Dec-10 A 0

S3/07700 Engineer Review on Segment Annulus Grouting 30-Nov-10 27-Dec-10 16-Nov-10 A 27-Nov-10 A 0

S3/07860 Engineer's Approval on Lining Design 14-Sep-10 01-Oct-10 16-Nov-10 A 30-Nov-10 A 0

S3/07710 Resubmit Segment Annulus Grouting 28-Dec-10 10-Jan-11 29-Nov-10 A 10-Feb-11 7 47

S3/07870 Address Engineer's Comments 02-Oct-10 21-Oct-10 30-Nov-10 A 30-Nov-10 A 0

S3/07750 Resubmit Temp Work Design for Tunnel 28-Dec-10 10-Jan-11 07-Dec-10 A 03-Jan-11 A 0

S3/07670 TBM Submittals Group E Re-submission 03-Dec-10 16-Dec-10 07-Dec-10 A 16-Feb-11 13 32

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

Inlet Chamber: Install Temp Strut at -24mpd

Inlet Chamber: Excavate Down to -27.5mpd

Inlet Chamber: Install Temp Strut at -27mpd

Inlet Chamber: Excavate Down to -30mpd

Construction of Base Slab

Inlet Chamber: Formation and Blinding Layer

Inlet Chamber: Steel Fixing to Base

Inlet Chamber: Install Thermal Couple

Inlet Chamber: Steel Fixing

Inlet Chamber: Cleaning

Inlet Chamber: Cast the Base

Inlet Chamber: Concrete Curing

Dismantle Temp Shoring&Cast R.C. Beams

IC: Remove Temp Strut at -27 and -18.5mpd

IC: Construct Waling Beam at -17mpd

IC: Curing for Waling Beam at -17mpd

IC: Remove Temp Strut at -24mpd

IC: Cast the 1m Thick Wall Below Bottom Waling

IC: Construct Waling Beam at -12.5mpd

IC: Curing for Waling Beam at -12.5mpd

IC: Remove Temp Strut at -14mpd

IC: Construct Waling Beam at -6mpd

IC: Curing for Waling Beam at -6mpd

IC: Remove Temp Strut at -9.5mpd

IC: Construct Waling Beam at +1.5mpd

IC: Curing for Waling Beam at +1.5mpd

IC: Remove Temp Strut at -3.5 and +3mpd

Reinstate Openings at Base Slab

TBM Submittals Group A Preliminary Design

TBM Submittals Group B Preliminary Design

TBM - Preliminary Design for Choice of TBM

TBM Submittals Group C Preliminary Design

TBM - Design of Proposed TBM

Re-submit Group A Preliminary Design

TBM Submittals Group B Engineer's Review

TBM Submittals Group B Engineer's Review

TBM Submittals Group B Resubmission

TBM Submittals Group A Engineer's Review

TBM Submittals Group B Engineer Approval

TBM Submittals Group A Resubmission

TBM Submittals Group A Engineer Approval

Tunnel Lining Detail Design

TBM Submittals Group C Engineer's Review

TBM - Manufacturing of TBM & Delivery

Submit Tunnel Layout/Procedure/Equipment to FSD

Submit Temp Ventilation System for Tunnel

TBM Submittals Group D Work Plan / Training Prog

Submit Temp Work Design for Tunnel

TBM Submittals Group E Tunnel Safety Programme

TBM Submittals Group C Resubmission

TBM Submittals Group C Engineer Approval

Engineer Review on Temp Ventilation System

Submit Segment Annulus Grouting Design

FSD Review ofTunnel Layout/Procedure/Equipment

Engineer Review on Temp Work Design for Tunnel

Re-submit Tunnel Layout/Procedure/Equipment

Resubmit Temp Ventilation System

TBM Submittals Group D Engineer Review

TBM Submittals Group E Engineer Review

Engineer Review on Segment Annulus Grouting

Engineer's Approval on Lining Design

Resubmit Segment Annulus Grouting

Address Engineer's Comments

Resubmit Temp Work Design for Tunnel

TBM Submittals Group E Re-submission

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 5 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 42: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

S3/07630 TBM Submittals Group D Re-submission 03-Dec-10 16-Dec-10 09-Dec-10 A 16-Feb-11 13 32

S3/07680 TBM Submittals Group E Approval 17-Dec-10 30-Dec-10 02-Jan-11 A 02-Mar-11 14 32

S3/07540 Engineer Approval on Temp Ventilation System 04-Dec-10 17-Dec-10 14-Jan-11 A 25-Jan-11 A 0

S3/07760 Engineer Approval on Temp Work Design for Tunnel 11-Jan-11 24-Jan-11 31-Jan-11 17-Feb-11 14 54

S3/07770 Submit Method for Tunnel Movement Monitoring 01-Oct-10 29-Nov-10 31-Jan-11 04-Apr-11 60 -48

S3/07810 Submit Method to Control Infiltration 01-Oct-10 29-Nov-10 31-Jan-11 04-Apr-11 60 -48

S3/07720 Engineer Approval on Segment Annulus Grouting 11-Jan-11 24-Jan-11 11-Feb-11 24-Feb-11 14 47

S3/07640 TBM Submittals Group D Approval 17-Dec-10 30-Dec-10 17-Feb-11 02-Mar-11 14 32

S3/07500 FSD Approval Tunnel Layout/Procedure/Equipment 04-Dec-10 31-Dec-10 16-Mar-11 12-Apr-11 28 -8

S3/07780 Eng Review Method for Tunnel Movement Monitoring 30-Nov-10 27-Dec-10 05-Apr-11 02-May-11 28 -48

S3/07820 Eng Review on Method to Control Infiltration 30-Nov-10 27-Dec-10 05-Apr-11 02-May-11 28 -48

S3/07790 Re-submit Method for Tunnel Movement Monitoring 28-Dec-10 10-Jan-11 03-May-11 16-May-11 14 -48

S3/07830 Re-submit Method to Control Infiltration 28-Dec-10 10-Jan-11 03-May-11 16-May-11 14 -48

S3/07800 Approval Method for Tunnel Movement Monitoring 11-Jan-11 24-Jan-11 17-May-11 30-May-11 14 -48

S3/07840 Eng Approval on Method to Control Infiltration 11-Jan-11 24-Jan-11 17-May-11 30-May-11 14 -48

Launching ShLaunching Shaft ConstructionLaunching Shaft ConstructionLaunching Shaft ConstructionLaunching Shaft ConstructionLaunching Shaft ConstructionLaunching Shaft ConstructionLaunching Shaft Construction

S3/08020 Mobilisation of Plant & Equipments 25-Mar-10 24-Apr-10 25-Mar-10 A 24-Apr-10 A 0

S3/08030 Erection of Silo System 01-Apr-10 05-May-10 01-Apr-10 A 05-May-10 A 0

S3/08038 Preparation work to commence D-wall 31-Jul-10 13-Aug-10 03-May-10 A 16-Aug-10 A 0

S3/08035 Ground Improvement 14-Jun-10 31-Jul-10 14-Jun-10 A 31-Jul-10 A 0

S3/08040 Diaphragm Wall Installation 14-Aug-10 11-Dec-10 16-Aug-10 A 13-Mar-11 38 -60

S3/08160 Launching Shaft: DW Panel L17 15-Oct-10 19-Oct-10 16-Aug-10 A 01-Sep-10 A 0

S3/08120 Launching Shaft: DW Panel L13 25-Sep-10 29-Sep-10 02-Sep-10 A 17-Sep-10 A 0

S3/08180 Launching Shaft: DW Panel L19 25-Oct-10 29-Oct-10 20-Sep-10 A 05-Oct-10 A 0

S3/08070 Launching Shaft: DW Panel L9 31-Aug-10 04-Sep-10 06-Oct-10 A 30-Oct-10 A 0

S3/08140 Launching Shaft: DW Panel L15 05-Oct-10 09-Oct-10 31-Oct-10 A 12-Nov-10 A 0

S3/08200 Launching Shaft: DW Panel L21 04-Nov-10 08-Nov-10 14-Nov-10 A 24-Nov-10 A 0

S3/08090 Launching Shaft: DW Panel L7 10-Sep-10 14-Sep-10 17-Nov-10 A 20-Dec-10 A 0

S3/08080 Launching Shaft: DW Panel L3 05-Sep-10 09-Sep-10 26-Nov-10 A 07-Dec-10 A 0

S3/08100 Launching Shaft: DW Panel L11 15-Sep-10 19-Sep-10 26-Nov-10 A 28-Dec-10 A 0

S3/08050 Launching Shaft: DW Panel L1 14-Aug-10 25-Aug-10 20-Dec-10 A 24-Dec-10 A 0

S3/08240 Launching Shaft: DW Panel L20 24-Nov-10 28-Nov-10 26-Dec-10 A 17-Jan-11 A 0

S3/08060 Launching Shaft: DW Panel L5 26-Aug-10 30-Aug-10 28-Dec-10 A 07-Jan-11 A 0

S3/08210 Launching Shaft: DW Panel L12 09-Nov-10 13-Nov-10 04-Jan-11 A 14-Jan-11 A 0

S3/08250 Launching Shaft: DW Panel L16 29-Nov-10 03-Dec-10 10-Jan-11 A 21-Jan-11 A 0

S3/08170 Launching Shaft: DW Panel L8 20-Oct-10 24-Oct-10 15-Jan-11 A 20-Jan-11 A 0

S3/08110 Launching Shaft: DW Panel L2 20-Sep-10 24-Sep-10 19-Jan-11 A 22-Jan-11 A 0

S3/08130 Launching Shaft: DW Panel L4 30-Sep-10 04-Oct-10 31-Jan-11 08-Feb-11 5 -46

S3/08150 Launching Shaft: DW Panel L6 10-Oct-10 14-Oct-10 09-Feb-11 13-Feb-11 5 -46

S3/08190 Launching Shaft: DW Panel L10 30-Oct-10 03-Nov-10 14-Feb-11 18-Feb-11 5 -46

S3/08220 Launching Shaft: DW Panel L18 14-Nov-10 18-Nov-10 19-Feb-11 23-Feb-11 5 -46

S3/08230 Launching Shaft: DW Panel L14 19-Nov-10 23-Nov-10 24-Feb-11 28-Feb-11 5 -46

S3/08260 Launching Shaft: DW Panel L22 04-Dec-10 08-Dec-10 01-Mar-11 05-Mar-11 5 -46

S3/08270 Launching Shaft: Demobilization of Plant 09-Dec-10 11-Dec-10 06-Mar-11 08-Mar-11 3 -46

S3/08280 All Test including Sonic Test to completed Dwall 09-Dec-10 01-Jan-11 14-Mar-11 06-Apr-11 24 -60

S3/08320 Excavation & Construction of Temp Base Slab 09-Dec-10 17-Mar-11 14-Mar-11 11-Jun-11 90 -60

S3/08330 LS: Excavation to 500mm Below Top Ring Beam 09-Dec-10 10-Dec-10 14-Mar-11 15-Mar-11 2 -57

S3/08340 LS: Construct Top Ring Beam at +5.5mpd 11-Dec-10 20-Dec-10 16-Mar-11 25-Mar-11 10 -57

S3/08350 LS: Excavation to 500mm Below Top Ring Beam 21-Dec-10 09-Jan-11 26-Mar-11 14-Apr-11 20 -57

S3/08360 LS: Construct Middle Ring Beam at -16.45mpd 10-Jan-11 24-Jan-11 15-Apr-11 29-Apr-11 15 -57

S3/08370 LS: Excavation to 500mm Below Middle Ring Beam 25-Jan-11 07-Feb-11 30-Apr-11 09-May-11 10 -57

S3/08380 LS: Construct Middle Ring Beam at -23.05mpd 08-Feb-11 22-Feb-11 10-May-11 24-May-11 15 -57

S3/08390 LS: Excavation Below Bottom Ring Beam 23-Feb-11 27-Feb-11 25-May-11 29-May-11 5 -57

S3/08400 LS: Formation and Blinding 28-Feb-11 05-Mar-11 30-May-11 04-Jun-11 6 -57

S3/08410 LS: Construct Base Slab 06-Mar-11 17-Mar-11 05-Jun-11 11-Jun-11 7 -57

S3/08420 Dummy 18-Mar-11 18-Mar-11 12-Jun-11 12-Jun-11 0 -57

Bored TunnelBored TunnelBored TunnelBored TunnelBored TunnelBored TunnelBored TunnelBored Tunnel

S3/08520 Production of Lining Form 22-Oct-10 20-Dec-10 15-Sep-10 A 02-Feb-11 3 -24

S3/08530 Inspection and modification of Lining Form 21-Dec-10 03-Jan-11 07-Feb-11 20-Feb-11 14 -24

S3/08540 Initial Casting for Precast Segment Lining 04-Jan-11 16-Feb-11 21-Feb-11 01-Apr-11 40 -24

S3/08600 Soil Improvement for TBM Retrieving 13-Dec-10 25-Feb-11 14-Mar-11 28-May-11 60 33

S3/08550 Casting for Pre-cast Segment Lining 17-Feb-11 30-Sep-11 29-Mar-11 09-Nov-11 226 -24

S3/08560 Precast Segment Lining for ch0 to ch90 17-Feb-11 03-May-11 29-Mar-11 12-Jun-11 76 -12

S3/08640 Soil Improvement for TBM Launch/ Ground freezing 25-Mar-11 10-Jun-11 11-Apr-11 07-Sep-11 150 -60

S3/08610 Surface Preparation (Muck Pit&Crawler Crane) 01-Mar-11 25-Apr-11 03-Jun-11 08-Aug-11 67 -60

S3/08620 Dome,Ringbeam&Backthrust Wall Construction 18-Mar-11 26-Apr-11 12-Jun-11 21-Jul-11 40 -57

S3/08630 Preparation inside Launching Shaft 10-Mar-11 23-May-11 12-Jun-11 25-Aug-11 75 -60

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

TBM Submittals Group D Re-submission

TBM Submittals Group E Approval

Engineer Approval on Temp Ventilation System

Engineer Approval on Temp Work Design for Tunnel

Submit Method for Tunnel Movement Monitoring

Submit Method to Control Infiltration

Engineer Approval on Segment Annulus Grouting

TBM Submittals Group D Approval

FSD Approval Tunnel Layout/Procedure/Equipment

Eng Review Method for Tunnel Movement Monitoring

Eng Review on Method to Control Infiltration

Re-submit Method for Tunnel Movement Monitoring

Re-submit Method to Control Infiltration

Approval Method for Tunnel Movement Monitoring

Eng Approval on Method to Control Infiltration

Mobilisation of Plant & Equipments

Erection of Silo System

Preparation work to commence D-wall

Ground Improvement

Diaphragm Wall Installation

Launching Shaft: DW Panel L17

Launching Shaft: DW Panel L13

Launching Shaft: DW Panel L19

Launching Shaft: DW Panel L9

Launching Shaft: DW Panel L15

Launching Shaft: DW Panel L21

Launching Shaft: DW Panel L7

Launching Shaft: DW Panel L3

Launching Shaft: DW Panel L11

Launching Shaft: DW Panel L1

Launching Shaft: DW Panel L20

Launching Shaft: DW Panel L5

Launching Shaft: DW Panel L12

Launching Shaft: DW Panel L16

Launching Shaft: DW Panel L8

Launching Shaft: DW Panel L2

Launching Shaft: DW Panel L4

Launching Shaft: DW Panel L6

Launching Shaft: DW Panel L10

Launching Shaft: DW Panel L18

Launching Shaft: DW Panel L14

Launching Shaft: DW Panel L22

Launching Shaft: Demobilization of Plant

All Test including Sonic Test to completed Dwall

Excavation & Construction of Temp Base Slab

LS: Excavation to 500mm Below Top Ring Beam

LS: Construct Top Ring Beam at +5.5mpd

LS: Excavation to 500mm Below Top Ring Beam

LS: Construct Middle Ring Beam at -16.45mpd

LS: Excavation to 500mm Below Middle Ring Beam

LS: Construct Middle Ring Beam at -23.05mpd

LS: Excavation Below Bottom Ring Beam

LS: Formation and Blinding

LS: Construct Base Slab

Dummy

Production of Lining Form

Inspection and modification of Lining Form

Initial Casting for Precast Segment Lining

Soil Improvement for TBM Retrieving

Casting for Pre-cast Segment Lining

Precast Segment Lining for ch0 to ch90

Soil Improvement for TBM Launch/ Ground freezing

Surface Preparation (Muck Pit&Crawler Crane)

Dome,Ringbeam&Backthrust Wall Construction

Preparation inside Launching Shaft

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 6 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 43: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

S3/08570 Precast Segment Lining for ch90 to ch170 04-May-11 22-Jul-11 13-Jun-11 31-Aug-11 80 -12

S3/08645 Establish Plant for TBM Excavation 27-Apr-11 10-Jun-11 22-Jul-11 04-Sep-11 45 -57

S3/08650 TBM Assembly 27-Apr-11 10-Jun-11 25-Jul-11 07-Sep-11 45 -60

S3/08580 Precast Segment Lining for ch170 to ch236 23-Jul-11 30-Sep-11 01-Sep-11 09-Nov-11 70 -12

S3/08710 Initial Drive (50m) 11-Jun-11 14-Jul-11 08-Sep-11 11-Oct-11 34 -60

S3/08720 Convert to Main Drive 15-Jul-11 04-Aug-11 12-Oct-11 01-Nov-11 21 -60

S3/08730 Main Drive (34m) 05-Aug-11 24-Aug-11 02-Nov-11 21-Nov-11 20 -60

S3/08740 Main Drive (102m) 25-Aug-11 14-Oct-11 22-Nov-11 31-Dec-11 40 -60

S3/08750 Main Drive (50m) 15-Oct-11 07-Nov-11 01-Jan-12 24-Jan-12 24 -60

S3/08760 Preparation Works for TBM Breakthrough 15-Oct-11 02-Nov-11 16-Jan-12 03-Feb-12 19 -51

S3/08770 Post Condition Survey for Bored Tunnel 08-Nov-11 28-Nov-11 25-Jan-12 14-Feb-12 21 3

S3/08780 Dismantle TBM 08-Nov-11 22-Dec-11 25-Jan-12 23-Feb-12 30 -60

S3/08790 Removing Sleeper&Rail,Cleaning Works 16-Nov-11 06-Dec-11 24-Feb-12 15-Mar-12 21 -48

S3/08800 Connection Joints with Inlet Chamber 18-Dec-11 07-Jan-12 07-Mar-12 27-Mar-12 21 -60

S3/08810 Final Touching Up&Cleaning of Inlet Chamber 04-Jan-12 24-Jan-12 28-Mar-12 17-Apr-12 21 -60

S3/08820 Submission of As-built Record for Bored Tunnel 23-Dec-11 21-Jan-12 28-Mar-12 26-Apr-12 30 298

Initial Works /Initial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated SubmissionInitial Works / Associated Submission

S3/07020 Site Clearance (Portion 2) 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S3/07030 Relocation of Existing Car Park 17-Sep-09 23-Oct-09 17-Sep-09 A 23-Oct-09 A 0

S3/07060 Erection of Chain Link Fence 17-Sep-09 13-Oct-09 17-Sep-09 A 13-Oct-09 A 0

S3/07080 Submission of Launching Shaft Design 17-Sep-09 15-Mar-10 17-Sep-09 A 15-Mar-10 A 0

S3/07110 Proposed TTM for Gate No.4 17-Sep-09 23-Oct-09 17-Sep-09 A 23-Oct-09 A 0

S3/07040 Underground Utilities Detection&Trial Holes 08-Oct-09 02-Nov-09 08-Oct-09 A 02-Nov-09 A 0

S3/07120 Approval of Proposal for Gate No.4 24-Oct-09 19-Feb-10 24-Oct-09 A 19-Feb-10 A 0

S3/07070 Ground Investigation Works 19-Nov-09 26-Nov-09 19-Nov-09 A 26-Nov-09 A 0

S3/07050 Transplant of Existing Trees 01-Feb-10 04-Feb-10 01-Feb-10 A 04-Feb-10 A 0

S3/07090 Approval of Launching Shaft Design 16-Mar-10 26-May-10 16-Mar-10 A 26-May-10 A 0

S3/07100 Construction of Guide Wall 26-Mar-10 03-May-10 26-Mar-10 A 03-May-10 A 0

S3/07130 Construction of Gate No.4 02-Nov-10 25-Nov-10 12-Jul-10 A 31-Jul-10 A 0

S3/07140 Obtain As-built Pile Record from STDF Contractor 19-Mar-11 25-Mar-11 19-Mar-11 25-Mar-11 6 61

S3/07150 Review Piling Record Against Tunnel Alignment 26-Mar-11 01-Apr-11 26-Mar-11 01-Apr-11 6 61

Mined TunnelMined TunnelMined TunnelMined TunnelMined TunnelMined TunnelMined TunnelMined Tunnel

S3/09020 Vertical Jet Grout for Mined Tunnel Construction 18-Mar-11 28-Jun-11 13-Jun-11 19-Sep-11 80 417

S3/09060 Vertical Drill at D-Wall 21-Mar-11 19-Apr-11 15-Jun-11 14-Jul-11 30 -59

S3/09030 Drill Horizontal Freezing \ Jet Grout 27-Apr-11 26-May-11 21-Jun-11 20-Jul-11 30 -28

S3/09070 Set Up Station for Freezing\ Jet Grout at D-Wall 20-Apr-11 14-Jun-11 15-Jul-11 08-Sep-11 56 -59

S3/09080 Ground Freezing \ Jet Grout at D-Wall 15-Jun-11 13-Aug-11 09-Sep-11 07-Nov-11 60 -59

S3/09040 Set Up Station for Freezing\ Stabilization 18-Jul-11 15-Sep-11 11-Sep-11 09-Nov-11 60 -28

S3/09050 Ground Freezing \ Stabilization 16-Sep-11 14-Nov-11 10-Nov-11 08-Jan-12 60 -28

S3/09090 Stabilize Ground at Existing Riser Shaft Wall 16-Sep-11 14-Nov-11 11-Dec-11 08-Feb-12 60 -59

S3/09110 Construct Mined Tunnel 15-Nov-11 06-Jan-12 09-Feb-12 01-Apr-12 53 -59

S3/09120 Make Good & Final Cleaning Works 07-Jan-12 24-Jan-12 02-Apr-12 16-Apr-12 15 -59

S3/09130 Submission of As-built Record for Mined Tunnel 07-Jan-12 21-Jan-12 02-Apr-12 01-May-12 30 293

S3/09140 Post Condition Survey for Mined Tunnel 07-Jan-12 27-Jan-12 02-Apr-12 22-Apr-12 21 302

SupplemenSupplementary AgreementSupplementary AgreementSupplementary AgreementSupplementary AgreementSupplementary AgreementSupplementary AgreementSupplementary Agreement

Utilities and Utilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and ServicesUtilities and Services

Cable WorksCable WorksCable WorksCable WorksCable WorksCable WorksCable WorksCable Works

V1/02020 Cable Trough 16-Apr-10 30-Oct-10 16-Apr-10 A 31-Dec-10 A 0

V1/02030 Mobilization 16-Apr-10 21-Apr-10 16-Apr-10 A 21-Apr-10 A 0

V1/02035 Detect Existing Utilities 16-Apr-10 21-Apr-10 16-Apr-10 A 21-Apr-10 A 0

V1/02040 Phase A: TTA for Cable Trough ch0 to 20 22-Apr-10 22-Apr-10 22-Apr-10 A 22-Apr-10 A 0

V1/02050 Phase A: Excavation and Blinding ch0 to 15 23-Apr-10 05-May-10 23-Apr-10 A 05-May-10 A 0

V1/02055 Phase A: Sheet Piling / Exc ch15 to 80 06-May-10 02-Aug-10 06-May-10 A 18-Jun-10 A 0

V1/02060 Phase A: Base Slab ch0 to 20 13-May-10 05-Jun-10 13-May-10 A 05-Jun-10 A 0

V1/02070 Phase A: Wall Stem ch0 to 20 13-May-10 05-Jun-10 13-May-10 A 05-Jun-10 A 0

V1/02190 Phase B: TTA for Cable Trough ch220 to 260 18-May-10 18-May-10 18-May-10 A 18-May-10 A 0

V1/02200 Phase B: Sheet Piling / Exc ch220 to 260 31-May-10 15-Jun-10 31-May-10 A 15-Jun-10 A 0

V1/02210 Phase B: Single Cell Cable Trough ch220 to 260 01-Jun-10 03-Aug-10 01-Jun-10 A 19-Oct-10 A 0

V1/02080 Phase A: Base Slab ch20 to 40 04-Jun-10 14-Jun-10 04-Jun-10 A 14-Jun-10 A 0

V1/02090 Phase A: Wall Stem ch20 to 40 04-Jun-10 14-Jun-10 04-Jun-10 A 14-Jun-10 A 0

V1/02215 Phase B: Single Cell Cable Trough ch260 to 300 05-Jun-10 03-Aug-10 05-Jun-10 A 19-Oct-10 A 0

V1/02110 Phase A: Single Cell Cable Trough ch40 to 80 07-Jun-10 03-Aug-10 07-Jun-10 A 18-Sep-10 A 0

V1/02100 Phase A: Backfill and Reinstatement ch0 to 40 10-Jun-10 03-Jul-10 10-Jun-10 A 03-Jul-10 A 0

V1/02220 Phase E: Single Cell Cable Trough ch300 to 340 12-Jun-10 03-Aug-10 12-Jun-10 A 31-Dec-10 A 0

V1/02250 Phase C: TTA for Cable Trough ch420 to 460 28-Jun-10 28-Jun-10 28-Jun-10 A 28-Jun-10 A 0

V1/02260 Phase C: Single Cell Cable Trough ch420 to 460 29-Jun-10 19-Aug-10 29-Jun-10 A 22-Oct-10 A 0

V1/02230 Phase E: Single Cell Cable Trough ch340 to 380 19-Jul-10 03-Aug-10 19-Jul-10 A 31-Dec-10 A 0

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

Precast Segment Lining for ch90 to ch170

Establish Plant for TBM Excavation

TBM Assembly

Precast Segment Lining for ch170 to ch236

Initial Drive (50m)

Convert to Main Drive

Main Drive (34m)

Main Drive (102m)

Main Drive (50m)

Preparation Works for TBM Breakthrough

Post Condition Survey for Bored Tunnel

Dismantle TBM

Removing Sleeper&Rail,Cleaning Works

Connection Joints with Inlet Chamber

Final Touching Up&Cleaning of Inlet Chamber

Submission of As-built Record for Bored Tunnel

Site Clearance (Portion 2)

Relocation of Existing Car Park

Erection of Chain Link Fence

Submission of Launching Shaft Design

Proposed TTM for Gate No.4

Underground Utilities Detection&Trial Holes

Approval of Proposal for Gate No.4

Ground Investigation Works

Transplant of Existing Trees

Approval of Launching Shaft Design

Construction of Guide Wall

Construction of Gate No.4

Obtain As-built Pile Record from STDF Contractor

Review Piling Record Against Tunnel Alignment

Vertical Jet Grout for Mined Tunnel Construction

Vertical Drill at D-Wall

Drill Horizontal Freezing \ Jet Grout

Set Up Station for Freezing\ Jet Grout at D-Wall

Ground Freezing \ Jet Grout at D-Wall

Set Up Station for Freezing\ Stabilization

Ground Freezing \ Stabilization

Stabilize Ground at Existing Riser Shaft Wall

Construct Mined Tunnel

Make Good & Final Cleaning Works

Submission of As-built Record for Mined Tunnel

Post Condition Survey for Mined Tunnel

Cable Trough

Mobilization

Detect Existing Utilities

Phase A: TTA for Cable Trough ch0 to 20

Phase A: Excavation and Blinding ch0 to 15

Phase A: Sheet Piling / Exc ch15 to 80

Phase A: Base Slab ch0 to 20

Phase A: Wall Stem ch0 to 20

Phase B: TTA for Cable Trough ch220 to 260

Phase B: Sheet Piling / Exc ch220 to 260

Phase B: Single Cell Cable Trough ch220 to 260

Phase A: Base Slab ch20 to 40

Phase A: Wall Stem ch20 to 40

Phase B: Single Cell Cable Trough ch260 to 300

Phase A: Single Cell Cable Trough ch40 to 80

Phase A: Backfill and Reinstatement ch0 to 40

Phase E: Single Cell Cable Trough ch300 to 340

Phase C: TTA for Cable Trough ch420 to 460

Phase C: Single Cell Cable Trough ch420 to 460

Phase E: Single Cell Cable Trough ch340 to 380

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 7 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 44: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Activity ID Activity Name Target Start Target Finish

Start Finish RemDur

TotalFloat

V1/02280 Phase F: TTA for Cable Trough ch280 to 300 31-Jul-10 31-Jul-10 13-Aug-10 A 13-Aug-10 A 0

V1/02290 Phase F: Single Cell Cable Trough ch280 to 300 01-Aug-10 30-Aug-10 16-Aug-10 A 31-Dec-10 A 0

V1/02300 Phase F: Single Cell Cable Trough ch200 to 280 14-Sep-10 30-Oct-10 16-Aug-10 A 30-Nov-10 A 0

V1/02270 Phase C: Single Cell Cable Trough ch460 to 510 20-Aug-10 13-Sep-10 18-Aug-10 A 22-Oct-10 A 0

V1/02120 Phase D: Single Cell Cable Trough ch80 to 120 04-Aug-10 27-Aug-10 28-Sep-10 A 29-Dec-10 A 0

V1/02140 Phase D: Single Cell Cable Trough ch160 to 200 11-Sep-10 04-Oct-10 28-Sep-10 A 29-Dec-10 A 0

V1/02340 Phase G: TTA for Cable Trough ch220 to 180 31-Jul-10 31-Jul-10 18-Oct-10 A 18-Oct-10 A 0

V1/02350 Phase G: Sheet Piling / Exc ch220 to 180 01-Aug-10 14-Aug-10 19-Oct-10 A 12-Nov-10 A 0

V1/02130 Phase D: Single Cell Cable Trough ch120 to 160 28-Aug-10 10-Sep-10 28-Oct-10 A 29-Dec-10 A 0

V1/02360 Phase G: Single Cell Cable Trough ch220 to 180 11-Aug-10 24-Aug-10 30-Oct-10 A 22-Dec-10 A 0

V1/02370 Phase G: Single Cell Cable Trough ch180 to 140 20-Aug-10 02-Sep-10 30-Oct-10 A 22-Dec-10 A 0

V1/02240 Phase E: Single Cell Cable Trough ch380 to 420 04-Aug-10 24-Aug-10 01-Nov-10 A 31-Dec-10 A 0

V1/02380 Phase G: Single Cell Cable Trough ch140 to 135 03-Sep-10 16-Sep-10 22-Dec-10 A 22-Dec-10 A 0

V1/02390 Phase G: Single Cell Cable Trough ch135 to 95 17-Sep-10 30-Sep-10 22-Dec-10 A 22-Dec-10 A 0

V1/02400 Phase G: Single Cell Cable Trough ch95 to 80 01-Oct-10 14-Oct-10 22-Dec-10 A 22-Dec-10 A 0

Key DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey DatesKey Dates

KD7000 Commencement for Section IV (Variation Order) 16-Apr-10 16-Apr-10 A 0

KD7100 Completion of Section IV (1) : 120 days 14-Aug-10 25-Aug-10 A 0

KD7200 Completion of Section IV (2) : 150 days 13-Sep-10 31-Dec-10 A 0

KD7300 Completion of Section IV (3) : 150 days 13-Sep-10 31-Dec-10 A 0

Pipe WorksPipe WorksPipe WorksPipe WorksPipe WorksPipe WorksPipe WorksPipe Works

V1/01120 Pipe Drain / Sludge Feed Pipe for Section IV (1) 16-Apr-10 26-Aug-10 16-Apr-10 A 07-Aug-10 A 0

V1/01125 Detect Existing Utilities 16-Apr-10 21-Apr-10 16-Apr-10 A 21-Apr-10 A 0

V1/01130 Sewer bet F10 to F9 and Manhole (Part 1) 16-Apr-10 26-Jun-10 16-Apr-10 A 26-Jun-10 A 0

V1/01200 TTA for F10 to F9 (Part 2) 16-Apr-10 16-Apr-10 16-Apr-10 A 16-Apr-10 A 0

V1/01210 Sewer bet F10 to F9 (Part 2) 16-Apr-10 28-Jun-10 16-Apr-10 A 28-Jun-10 A 0

V1/01235 Pipe Drain / Sludge Feed Pipe for Section IV (2) 16-Apr-10 20-Oct-10 16-Apr-10 A 07-Aug-10 A 0

V1/01300 Storm Drain bet S1D to S1E & Manhole (Part 1) 16-Apr-10 31-Jul-10 16-Apr-10 A 31-Jul-10 A 0

V1/01240 Sewer bet F7 to F4 & Manhole 20-Apr-10 16-Jul-10 20-Apr-10 A 16-Jul-10 A 0

V1/01140 Sewer bet F9 to F7 05-May-10 03-Jul-10 05-May-10 A 03-Jul-10 A 0

V1/01150 Storm Drain bet S1B to S1C 05-Jun-10 10-Jul-10 05-Jun-10 A 10-Jul-10 A 0

V1/01250 Sewer bet F4 to F3 & Manholes 30-Jun-10 08-Sep-10 30-Jun-10 A 30-Nov-10 A 0

V1/01170 DN400 Sludge Feed Pipe (SF1) - 70m 05-Jul-10 17-Jul-10 05-Jul-10 A 17-Jul-10 A 0

V1/01180 Storm Drain bet S1B to S13 13-Jul-10 19-Aug-10 13-Jul-10 A 18-Aug-10 A 0

V1/01160 DN600 Sludge Feed Pipe (SF2) - 70m 14-Jul-10 03-Aug-10 14-Jul-10 A 07-Aug-10 A 0

V1/01220 Storm Drain bet S1A to S1B and Manholes 20-Jul-10 19-Aug-10 20-Jul-10 A 19-Aug-10 A 0

V1/01260 12DN600 Sludge Feed Pipe (SF2) - 10m 23-Jul-10 09-Aug-10 23-Jul-10 A 07-Aug-10 A 0

V1/01190 Reinstatement of Area / Access 20-Aug-10 26-Aug-10 09-Aug-10 A 23-Aug-10 A 0

V1/01290 Storm Drain bet S1C to S1D & Manholes S1C/S1C2 31-Jul-10 24-Sep-10 20-Aug-10 A 12-Oct-10 A 0

V1/01270 Sewer bet F3 to F2 09-Sep-10 02-Oct-10 23-Aug-10 A 30-Oct-10 A 0

V1/01330 Storm Drain bet S7 to S7A & Manhole S7 (Part 1) 31-Jul-10 18-Sep-10 23-Aug-10 A 15-Oct-10 A 0

V1/01320 Storm Drain bet S6 to S7A & Manhole S7A 06-Sep-10 20-Oct-10 26-Aug-10 A 15-Dec-10 A 0

V1/01340 Storm Drain bet S7 to S7A & Manhole S7 (Part 2) 03-Sep-10 20-Oct-10 13-Oct-10 A 05-Nov-10 A 0

V1/01305 Storm Drain bet S1D to S1E (Part 2) 31-Jul-10 24-Sep-10 25-Oct-10 A 31-Dec-10 A 0

V1/01310 Storm Drain bet S1E to S6 & Manholes S1E / S6 31-Jul-10 20-Sep-10 30-Oct-10 A 31-Dec-10 A 0

V1/01350 Sewer bet F2 to F1 27-Sep-10 20-Oct-10 20-Nov-10 A 15-Dec-10 A 0

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

2010 2011 2012

Phase F: TTA for Cable Trough ch280 to 300

Phase F: Single Cell Cable Trough ch280 to 300

Phase F: Single Cell Cable Trough ch200 to 280

Phase C: Single Cell Cable Trough ch460 to 510

Phase D: Single Cell Cable Trough ch80 to 120

Phase D: Single Cell Cable Trough ch160 to 200

Phase G: TTA for Cable Trough ch220 to 180

Phase G: Sheet Piling / Exc ch220 to 180

Phase D: Single Cell Cable Trough ch120 to 160

Phase G: Single Cell Cable Trough ch220 to 180

Phase G: Single Cell Cable Trough ch180 to 140

Phase E: Single Cell Cable Trough ch380 to 420

Phase G: Single Cell Cable Trough ch140 to 135

Phase G: Single Cell Cable Trough ch135 to 95

Phase G: Single Cell Cable Trough ch95 to 80

Commencement for Section IV (Variation Order)

Completion of Section IV (1) : 120 days

Completion of Section IV (2) : 150 days

Completion of Section IV (3) : 150 days

Pipe Drain / Sludge Feed Pipe for Section IV (1)

Detect Existing Utilities

Sewer bet F10 to F9 and Manhole (Part 1)

TTA for F10 to F9 (Part 2)

Sewer bet F10 to F9 (Part 2)

Pipe Drain / Sludge Feed Pipe for Section IV (2)

Storm Drain bet S1D to S1E & Manhole (Part 1)

Sewer bet F7 to F4 & Manhole

Sewer bet F9 to F7

Storm Drain bet S1B to S1C

Sewer bet F4 to F3 & Manholes

DN400 Sludge Feed Pipe (SF1) - 70m

Storm Drain bet S1B to S13

DN600 Sludge Feed Pipe (SF2) - 70m

Storm Drain bet S1A to S1B and Manholes

12DN600 Sludge Feed Pipe (SF2) - 10m

Reinstatement of Area / Access

Storm Drain bet S1C to S1D & Manholes S1C/S1C2

Sewer bet F3 to F2

Storm Drain bet S7 to S7A & Manhole S7 (Part 1)

Storm Drain bet S6 to S7A & Manhole S7A

Storm Drain bet S7 to S7A & Manhole S7 (Part 2)

Storm Drain bet S1D to S1E (Part 2)

Storm Drain bet S1E to S6 & Manholes S1E / S6

Sewer bet F2 to F1

DC2009/05 Monthly Report for January 2011 Harbour Area Treatment Scheme Stage 2A Construction of Interconnection Tunnel & D. Wall - Main Pumping Station at Stonecutters 07-Feb-11 15:24

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Revised Works Programme (Version 3) - Updated on 31 January 2011

Page 8 of 8

Date Revision Checked Approved

01-Feb-11 Monthly Progress Update - January 2011 BS CL

MR16

Page 45: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX C

Implementation Schedule of Environmental Mitigation Measures (EMIS)

Page 46: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

1

APPENDIX C IMPLEMENTATION SCHEDULE OF ENVIRONMENTAL MITIGATION MEASURES (EMIS)

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

A Air Quality

3.74 Skip hoist for material transport should be totally enclosed by impervious sheeting.

All construction sites

V

Vehicle washing facilities should be provided at every vehicle exit point. V

The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcore.

V

Where a site boundary adjoins a road, streets or other areas accessible to the public, hoarding of not less than 2.4 m high from ground level should be provided along the entire length except for a site entrance or exit.

N/A

Use of regular watering, with complete coverage, to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather.

V

Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.

V

Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty material storage piles near ASRs

V

Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations. V

Imposition of speed controls for vehicles on unpaved site roads. Ten kilometers per hour is the recommended limit. V

Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the 3 sides.

V

Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.

V

Page 47: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

2

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

3.74 Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.

All construction sites

V

B Airborne Noise

4.56– 4.61

Use of quiet PME, movable barriers and acoustic mats. All construction

sites

V

4.67 Only well-maintained plant shall be operated on-site and plant shall be serviced regularly during the construction program.

V

Silencers or mufflers on construction equipment shall be utilized and shall be properly maintained during the construction program.

V

Mobile plant, if any, shall be sited as far away from NSRs as possible. V

Machines and plant (such as trucks) that may be in intermittent use shall be shut down between works periods or shall be throttled down to a minimum.

V

4.67 Plant known to emit noise strongly in one direction shall, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

V

Material stockpiles and other structures shall be effectively utilized, wherever practicable, in screening noise from on-site construction activities.

V

C Water Quality

6.349 to 6.375

Construction Site Runoff and General Construction Activities

The mitigation measures as outlined in the ProPECC PN 1/94 Construction Site Drainage should be adopted where applicable.

All construction sites

@

Page 48: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

3

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

6.376 Effluent Discharge

There is a need to apply to EPD for a discharge licence for discharge of effluent from the construction site under the WPCO. The discharge quality must meet the requirements specified in the discharge licence. If monitoring of the treated effluent quality from the works areas is required during the construction phase of the Project, the monitoring should be carried out in accordance with the WPCO license which is under the ambit of regional office (RO) of EPD. Minimum distances of 100 m should be maintained between the discharge points of construction site effluent and the existing saltwater intakes.

All construction sites

V

6.377 Accidental Spillage of Chemicals Contractor must register as a chemical waste producer if chemical wastes would be produced from the construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes.

V

6.378 Any service shop and maintenance facilities should be located on hard standings within a bunded area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment involving activities with potential for leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.

@

6.379 Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:

Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.

Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents.

Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area.

V

Page 49: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

4

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

6.380 Construction Works in Close Proximity of Storm Drains or Seafront

To minimize the potential water quality impacts from the construction works located at or near any watercourse, the practices outlined below should be adopted where applicable.

The use of less or smaller construction plants may be specified to reduce the disturbance to the storm water courses or marine environment.

Temporary storage of materials (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction materials should be located well away from any water courses during carrying out of the construction works.

Stockpiling of construction materials and dusty materials should be covered and located away from any water courses.

Construction debris and spoil should be covered up and/or disposed of as soon as possible to avoid being washed into the nearby water receivers.

Construction activities, which generate large amount of wastewater, should be carried out in a distance away from the waterfront, where practicable.

Proper shoring may need to be erected in order to prevent soil/mud from slipping into the storm culvert or sea.

All construction sites

V

D Waste Management

9.107 Reusable steel or concrete panel shutters, fencing and hoarding and signboard should be used as a preferred alternative to items made of wood, to minimise wastage of wood. Attention should be paid to WBTC No. 19/2001 - Metallic Site Hoardings and Signboards to reduce the amount of timber used on construction sites. Metallic alternatives to timber are readily available and should be used rather than new timber. Precast concrete units should be adopted wherever feasible to minimize the use of timber formwork.

All construction sites

V

Page 50: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

5

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

9.109 All waste materials should be segregated into categories covering:

excavated materials suitable for reuse on-site; excavated materials suitable for public filling facilities; remaining C&D waste for landfill; chemical waste; and general refuse for landfill.

All construction sites

V

9.113 Sort C&D waste from demolition of existing facilities to recover recyclable portions such as metals;

N/A

Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.

V

Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force.

V

Any unused chemicals or those with remaining functional capacity shall be recycled. V

Proper storage and site practices to minimise the potential for damage or contamination of construction materials. @

9.115 Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.

V

Training of site personnel in proper waste management and chemical waste handling procedures. V

9.115 Develop and provide toolbox talk for on-site sorting of C&D materials to enhance worker’s awareness in handling, sorting, reuse and recycling of C&D materials.

V

Provision of sufficient waste disposal points and regular collection of waste. @

Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors. V

Page 51: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

6

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

9.125 Bentonite slurries used in diaphragm wall construction should be reconditioned and reused wherever practicable. The disposal of residual used bentonite slurry should follow the good practice guidelines stated in ProPECC PN 1/94 “Construction Site Drainage”

All construction sites

V

9.131 Adequate number of portable toilets at temporary works areas or the PTWs to ensure that sewage from site staff would be properly collected.

V

9.133 General refuse should be stored in enclosed bins, skips or compaction units separating from C&D material and disposed of at designated landfill.

V

9.135 The recyclable component of the municipal waste generated by the workforce, such as aluminium cans, paper and cleansed plastic containers should be separated from other waste. Provision and collection of recycling bins for different types of recyclable waste should be set up by the Contractor. The Contractor should also be responsible for arranging recycling companies to collect these materials.

V

9.137 If chemical wastes are produced at the construction site, the Contractor would be required to register with the EPD as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. The Contractor shall use a licensed collector to transport and dispose of the chemical wastes, to either the approved Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

V

9.142 Prior to excavation of the marine deposit layer, the deposit should be tested in accordance with the ETWB TC(W) No. 34/2002 and the results should be presented in a Preliminary Sediment Quality Report. The marine deposit should be disposed of at the disposal site designated by the Marine Fill Committee (MFC) or Director of Environmental Protection (DEP) depending on the test results.

V

Page 52: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

7

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

E Terrestrial Ecology

10.93 To implement effective noise mitigation measures as recommended in Section 4 of EIA.

All construction sites

V

10.94 Dust control practices such as regular watering, complete coverage of any aggregate or dusty material storage piles, and re-schedule of dusty activities during high-wind conditions as well as other measures recommended in Section 3 of EIA, should be implemented.

V

10.95 Fences/hoardings should be erected and installed along the boundary of the works areas.

V

10.96 Standard good site practices as suggested in Section 10 of EIA should be implemented.

@

10.97 Provision of proper drainage system and runoff control measures such as use of sand/silt traps, oil/grease separators, sedimentation tanks, etc.

@

F Landscape and Visual

Table 13.7

Topsoil, where identified, should be stripped and stored for re-use in the construction of the soft landscape works, where practical.

All construction sites

N/A

Existing trees to be retained on site should be carefully protected during construction. @

Trees unavoidably affected by the works should be transplanted where practical. V

Compensatory tree planting should be provided to compensate for felled trees. N/A

Control of night-time lighting. V

Page 53: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Contract No. DC/2009/05 Harbour Area Treatment Scheme (HATS) Stage 2A Construction of Interconnection Tunnel and Diaphragm of Main Pumping Station at SCISTW Appendix C - EMIS

January 2011

8

EIA Ref. Recommended Mitigation Measures Location of the measure

Implementation Status

Table 13.7

Erection of decorative screen hoarding compatible with the surrounding setting. All construction

sites

N/A

G Marine Ecology

11.135 To minimize the potential indirect impacts on water quality from construction site runoff and various construction activities, the practices outlined in ProPECC PN 1/94 Construction Site Drainage should be adopted.

All construction sites

@

H Hazard to Life

14A.201 Limiting use of cranes in terms of locations, lifting height, swing angle and setting up safety zone.

Exact location will be

determined on construction site by the engineer

V

Legend: V = implemented;

x = not implemented; @ = partially implemented; N/A = not applicable

Page 54: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX D

Summary of Action and Limit Levels

Page 55: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Appendix D - Summary of Action and Limit Levels

Table 1 – Action and Limit Levels for 1-hour TSP

Monitoring Station Action Level ( g/m3) Limit Level ( g/m3)

AM7 322 500

Table 2 – Action and Limit Levels for 24-hour TSP

Monitoring Station Action Level ( g/m3) Limit Level ( g/m3)

AM7 207 260

Table 3 – Action and Limit Levels for Construction Noise

Time Period MonitoringStation

Action Level Limit Level

0700-1900 hrs on

normal weekdays

NM6

When one documented

complaint is received

from any one of the

sensitive receivers

75 dB(A)

1900-2300 hrs on

normal weekdays,

0700-2300 hrs on

General Holidays and

70 dB(A)

2300-0700 hrs of next

day on all days 55 dB(A)

Page 56: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX E

Calibration Certificates of Equipments

Page 57: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 58: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 59: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 60: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 61: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 62: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 63: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 64: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 65: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 66: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 67: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 68: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 69: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX F

EM&A Monitoring Schedules

Page 70: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

As informed by

Contractor, no

construction work

was carried out during

the night-time period.

15-Jan

24-hour TSP

Noise

6-Jan

18-Jan

Noise

21-Jan

DC/2009/05 - HATS Stage 2A Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at SCISTW

Impact Air Quality and Noise Monitoring Schedule for January 2011 (Ver. 0)

14-Jan

7-Jan5-Jan 8-Jan2-Jan 3-Jan 4-Jan

Noise

1-hour TSP

12-Jan

24-hour TSP

16-Jan 17-Jan

9-Jan 10-Jan

24-hour TSP

11-Jan

1-hour TSP

20-Jan19-Jan

1-hour TSP

29-Jan26-Jan 27-Jan23-Jan 28-Jan

24-hour TSP

1-hour TSP

24-Jan 25-Jan

Sunday Monday Tuesday Wednesday Thursday Friday Saturday

1-Jan

1-hour TSP

22-Jan

13-Jan

24-hour TSP

Public Holiday

Noise

30-Jan 31-Jan

Noise (Evening time)

Page 71: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

The schedule is subject to change due to unforeseeable circumstances (like adverse weather, etc)

4-Feb

24-hour TSP

1-hour TSP

24-hour TSP

20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb

9-Feb

Sunday

7-FebAs informed by

Contractor, no

construction work will

be carried out.

24-hour TSP

13-Feb 15-Feb 16-Feb

6-Feb

5-Feb3-Feb1-Feb 2-Feb

24-hour TSP

8-Feb

Noise

14-Feb

1-hour TSP

Noise

1-hour TSP

19-Feb

12-Feb

Public Holiday

As informed by Contractor, no construction work will be carried out.

24-hour TSP

11-Feb

17-Feb 18-Feb

10-Feb

Wednesday

1-hour TSP

Noise (Daytime)

26-Feb

1-hour TSP

Noise

27-Feb 28-Feb

DC/2009/05 - HATS Stage 2A Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at SCISTWTentative Impact Air Quality and Noise Monitoring Schedule for February 2011 (Ver. 0)

Monday Tuesday Thursday Friday Saturday

Page 72: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX G

Air Quality Monitoring Results and their Graphical Presentations

Page 73: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Appendix G Air Quality Monitoring Results

1-hour TSP Monitoring Results at Station AM7 (Rooftop of West Kowloon No.2 Sewage Pumping Station)

Start Finish Weather

TSP

Concentration

Action

Level Limit Level Site Conditions /

Mean

Temperature

Mean Wind

Speed Sampler Filter

Date Time Time (µg/m3) (µg/m

3) (µg/m

3) Observations / Remarks (°C) (km/h) ID ID

13:08 14:08 Cloudy 95

14:08 15:08 Cloudy 96

15:08 16:08 Cloudy 98

13:30 14:30 Sunny 85

14:30 15:30 Sunny 88

15:30 16:30 Sunny 90

14:44 15:44 Sunny 83

15:44 16:44 Sunny 84

16:44 17:44 Sunny 82

10:15 11:15 Sunny 87

11:15 12:15 Sunny 87

13:15 14:15 Sunny 87

13:00 14:00 Sunny 82

14:00 15:00 Sunny 82

15:00 16:00 Sunny 83

Min. 82

Max. 98

Average 87

500Dust from Project site, traffic emission and dust

from other construction sites12.9 11.9 A005-09a -29-Jan-11 322

-

A005-11a -

322 500 Dust from Project site and traffic emission 15.0 6.4 A005-08a -

500Dust from Project site, traffic emission and dust

from other construction sites11.8 7.1

A005-12a500Dust from Project site, traffic emission and dust

from other construction sites15.7 7.0

-322 500Dust from Project site, traffic emission and dust

from other construction sites11.2 13.0 A005-12a

5-Jan-11

11-Jan-11

17-Jan-11

23-Jan-11

322

322

Page 74: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

CHECK DRAWN

Rev.Graphical Presentation of 1-hour TSP MonitoringResults

N.T.S.SCALEHATS Stage 2A - Construction of Interconnection Tunneland Diaphragm Wall for Main Pumping Station at

SCISTW ENFL

60143571

DATE

JOB NO. APPENDIX No.

G

Feb-11

LCHC

-

0

100

200

300

400

500

600

Conc

entr

atio

n µ

g/m

3

AM7

1st Hour

2nd Hour

3rd Hour

Action Level: 322µg/m3

Limit Level: 500µg/m3

Page 75: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Appendix G

24-hour TSP Monitoring Results at Station AM7 (Rooftop of West Kowloon No.2 Sewage Pumping Station)

Weather

Sampling

Time

TSP

Conc.

Action

Level Limit Level Observations / Remarks Sampler Filter

Date Time Date Time Initial Final Initial Final (hrs) Initial Final Average (µg/m3) (µg/m

3) (µg/m

3) ID ID

4-Jan-11 16:00 5-Jan-11 16:00 Cloudy 2.8115 2.9924 7268.86 7292.86 24.00 1.3470 1.3470 1.3470 93 207 260

Dust from Project site, traffic emission and dust

from other construction sites A.001.53T 12028

10-Jan-11 16:00 11-Jan-11 16:00 Sunny 2.7855 3.1310 7292.86 7316.86 24.00 1.3440 1.3440 1.3440 179 207 260

Dust from Project site, traffic emission and dust

from other construction sites A.001.53T 12035

16-Jan-11 16:00 17-Jan-11 16:00 Sunny 2.7927 3.0256 7316.86 7340.86 24.00 1.3370 1.3370 1.3370 121 207 260

Dust from Project site, traffic emission and dust

from other construction sites A.001.53T 12067

22-Jan-11 16:00 23-Jan-11 16:00 Sunny 2.8369 3.0411 7340.86 7364.86 24.00 1.3470 1.3470 1.3470 105 207 260

Dust from Project site, traffic emission and dust

from other construction sites A.001.53T 12097

28-Jan-11 16:00 29-Jan-11 16:00 Sunny 2.7881 3.0542 7364.86 7388.86 24.00 1.3370 1.3370 1.3370 138 207 260

Dust from Project site, traffic emission and dust

from other construction sites A.001.53T 12122

Min. 93

Max. 179

Average 127

Flow Rate (m3/min)

Air Quality Monitoring Results

Start Finish Filter Weight (g)

Elapsed Time

Reading

Page 76: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

CHECK DRAWN

Rev.

G

Feb-11ENFL LCHC

60143571 -

DATE

APPENDIX No.Graphical Presentation of 24-hour TSP MonitoringResults

N.T.S.SCALEHATS Stage 2A - Construction of Interconnection Tunneland Diaphragm Wall for Main Pumping Station at

SCISTWJOB NO.

0

50

100

150

200

250

300

Con

cent

ratio

n µg

/m3

AM7

Conc.

Action Level:207µg/m3

Limit Level: 260µg/m3

Page 77: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX H

Noise Monitoring Results and their Graphical Presentations

Page 78: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Appendix H Noise Monitoring Results

Location : NM6 Customs' Marine Base (Block H of Government Dockyard) Rooftop

Daytime (07:00-19:00 hrs) Noise Monitoring Results on Normal Weekdays

Leq L10 L90

5-Jan-11 9:33 10:03 Cloudy 70.6 72.8 68.1

excavation and

drilling in process

and crane in

operation

other construction

site nearby- 15.7 <5 m/s B&K 2270 B&K 4231

11-Jan-11 15:19 15:49 Sunny 71.0 72.5 68.5

excavation and

drilling in process

and crane in

operation

other construction

site nearby- 11.2 <5 m/s B&K 2238 B&K 4231

17-Jan-11 16:15 16:45 Sunny 70.6 69.0 68.5

excavation and

piling in process

and crane in

operation

other construction

site nearby- 11.8 <5 m/s B&K 2238 B&K 4231

29-Jan-11 13:30 14:00 Sunny 70.8 73.5 65.5

excavation in

process and crane

in operation

other construction

site nearby- 12.9 <5 m/s B&K 2238 B&K 4231

Min. 70.6

Max. 71.0

+ - Façade measurement

Other Noise

Source(s)

Observed

Calibrator

Model / IDRemarks

Mean

Temp.

(°C)

Mean

Wind

Speed

(m/s)

Noise Meter

Model / IDDate Start Time End Time Weather

Noise level (dB(A)), 30 min+ Major

Construction

Noise Source(s)

Observed

Page 79: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

CHECK DRAWN

Rev.APPENDIX No.

H -

DATE Feb-11LCHC

SCALE N.T.S.

Graphical Presentation of Daytime Noise MonitoringResults on Normal Weekdays

JOB NO.60143571

ENFL

HATS Stage 2A - Construction of Interconnection Tunneland Diaphragm Wall for Main Pumping Station at

SCISTW

0

20

40

60

80

100

120

Leq(

30m

in),

dB(A

)

NM6

NM6

Limit Level: 75 dB(A)

Baseline : 76.5 dB(A)

Date

Page 80: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Appendix H Noise Monitoring Results

Location : NM6 Customs' Marine Base (Block H of Government Dockyard) Rooftop

Evening time (19:00-23:00 hrs) Noise Monitoring Results on Normal Weekdays

Leq L10 L90

20:07 20:12 62.2 62.7 61.7

20:12 20:17 62.8 63.7 62.1

20:17 20:22 62.5 63.0 62.0

19:32 19:37 64.2 64.8 63.5

19:37 19:42 64.0 64.6 63.2

19:42 19:47 64.5 65.8 63.1

21:54 21:59 61.2 61.8 60.5

21:59 22:04 61.0 61.6 60.4

22:04 22:09 60.7 61.2 60.2

20:13 20:18 65.1 66.2 64.6

20:18 20:23 65.4 65.9 64.9

20:23 20:28 65.3 65.9 64.8

20:57 21:02 62.8 63.4 62.2

21:02 21:07 62.8 63.3 62.2

21:07 21:12 62.8 63.8 61.9

Min. 60.7

Max. 65.4

+ - Façade measurement

B&K 4231<5 m/s

B&K 4231

B&K

2270

- 11.2 <5 m/sB&K

2250L

- 11.8

Mean

Wind

Speed

(m/s)

Noise

Meter

Model /

ID

Calibrator

Model / ID

- 15.7 <5 m/s B&K 4231B&K

2270Fine

Cloudy

Mean

Temp.

(°C)

Remarks

excavation in

process

Fine

other construction

site nearby; traffic

noise from nearby

pier

5-Jan-11

Other Noise

Source(s)

Observed

Major

Construction

Noise Source(s)

Observed

Date Start Time End Time Weather

Noise level (dB(A)), 5 min+

excavation in

process

traffic noise from

nearby pier

17-Jan-11

Fineexcavation in

process

other construction

site nearby; traffic

noise from nearby

pier

-

11-Jan-11

excavation in

process

traffic noise from

nearby pier

31-Jan-11

29-Jan-11 fineexcavation in

process

other construction

site nearby; traffic

noise from nearby

pier

- 12.9 <5 m/sB&K

2250LB&K 4231

13.1 <5 m/sB&K

2250LB&K 4231

Page 81: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

CHECK DRAWN

Rev.APPENDIX No.

H -

DATE Feb-11LCHC

SCALE N.T.S.

Graphical Presentation of Evening Noise MonitoringResults on Normal Weekdays

JOB NO.60143571

ENFL

HATS Stage 2A - Construction of Interconnection Tunneland Diaphragm Wall for Main Pumping Station at

SCISTW

0

20

40

60

80

100

120

Leq(

5 m

in),

dB(A

)

NM6

NM6 1st dataset

NM6 2nd dataset

NM6 3rd dataset

Limit Level: 70 dB(A)

Baseline: 60.4 dB(A)

Date

Page 82: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX I

Meteorological Data for January 2011

Page 83: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 84: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX J

Event Action Plan

Page 85: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Appendix J – Event Action Plan

Event and Action Plan for Construction Air Quality

Event ACTION

ET IEC ER Contractor

ACTION LEVEL

Exceedance for

one sample

1. Identify source, investigate thecauses of exceedance andpropose remedial measures;

2. Inform IEC and ER;3. Repeat measurement to confirm

finding;4. Increase monitoring frequency to

daily.

1. Check monitoring datasubmitted by ET;

2. Check Contractor’s workingmethod.

1. Notify Contractor. 1. Rectify any unacceptablepractice;

2. Amend working methods ifappropriate.

Exceedance for

two or more

consecutive

samples

1. Identify source;2. Inform IEC and ER;3. Advise the ER on the effectiveness

of the proposed remedialmeasures;

4. Repeat measurements to confirmfindings;

5. Increase monitoring frequency todaily;

6. Discuss with IEC and Contractor onremedial actions required;

7. If exceedance continues, arrangemeeting with IEC and ER;

8. If exceedance stops, ceaseadditional monitoring.

1. Check monitoring datasubmitted by ET;

2. Check Contractor’s workingmethod;

3. Discuss with ET and Contractoron possible remedial measures;

4. Advise the ET on theeffectiveness of the proposedremedial measures;

5. Supervise Implementation ofremedial measures.

1. Confirm receipt ofnotification of failure inwriting;

2. Notify Contractor;3. Ensure remedial

measures properlyimplemented.

1. Submit proposals for remedial toER within 3 working days ofnotification;

2. Implement the agreed proposals;3. Amend proposal if appropriate.

Page 86: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Event and Action Plan for Construction Air Quality

Event ACTION

ET IEC ER Contractor

LIMIT LEVEL

Exceedance for

one sample

1. Identify source, investigate thecauses of exceedance andpropose remedial measures;

2. Inform ER, Contractor and EPD;3. Repeat measurement to confirm

finding;4. Increase monitoring frequency to

daily;5. Assess effectiveness of

Contractor’s remedial actions andkeep IEC, EPD and ER informed ofthe results.

1. Check monitoring datasubmitted by ET;

2. Check Contractor’s workingmethod;

3. Discuss with ET and Contractoron possible remedial measures;

4. Advise the ER on theeffectiveness of the proposedremedial measures;

5. Supervise implementation ofremedial measures.

1. Confirm receipt ofnotification of failure inwriting;

2. Notify Contractor;3. Ensure remedial

measures properlyimplemented.

1. Take immediate action to avoidfurther exceedance;

2. Submit proposals for remedialactions to IEC within 3 workingdays of notification;

3. Implement the agreedproposals;

4. Amend proposal if appropriate.

Exceedance for

two or more

consecutive

samples

1. Notify IEC, ER, Contractor andEPD;

2. Identify source;3. Repeat measurement to confirm

findings;4. Increase monitoring frequency to

daily;5. Carry out analysis of Contractor’s

working procedures to determinepossible mitigation to beimplemented;

6. Arrange meeting with IEC and ERto discuss the remedial actions tobe taken;

7. Assess effectiveness ofContractor’s remedial actions andkeep IEC, EPD and ER informed ofthe results;

8. If exceedance stops, ceaseadditional monitoring.

1. Check monitoring datasubmitted by ET;

2. Check Contractor’s workingmethod;

3. Discuss amongst ER, ET, andContractor on the potentialremedial actions;

4. Review Contractor’s remedialactions whenever necessary toassure their effectiveness andadvise the ER accordingly;

5. Supervise the implementation ofremedial measures.

1. Confirm receipt ofnotification of failure inwriting;

2. Notify Contractor;3. In consolidation with the

IEC, agree with theContractor on theremedial measures tobe implemented;

4. Ensure remedialmeasures properlyimplemented;

5. If exceedancecontinues, considerwhat portion of the workis responsible andinstruct the Contractorto stop that portion ofwork until theexceedance is abated.

1. Take immediate action to avoidfurther exceedance;

2. Submit proposals for remedialactions to IEC within 3 workingdays of notification;

3. Implement the agreed proposals;4. Resubmit proposals if problem

still not under control;5. Stop the relevant portion of

works as determined by the ERuntil the exceedance is abated.

Page 87: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Event and Action Plan for Construction Noise

Event Action

ET IEC ER Contractor

Exceedance forAction Level

1. Notify ER, IEC and Contractor;2. Carry out investigation;3. Report the results of investigation to

ER, IEC and Contractor;4. Discuss with IEC and Contractor on

remedial measures required;5. Increase monitoring frequency to

check mitigation effectiveness.

1. Review the investigation resultssubmitted by ET;

2. Review the proposed remedialmeasures by Contractor andadvise ER accordingly;

3. Advise ER on the effectiveness ofthe proposed remedial measures.

1. Confirm receipt ofnotification of failure inwriting;

2. Notify Contractor;3. In consolidation with IEC,

agree with Contractor onremedial measures to beimplemented;

4. Supervise theimplementation ofremedial measures.

1. Submit noise mitigation proposalsto IEC and ER;

2. Implement noise mitigationproposals.

Exceedance forLimit Level

1. Inform IEC, ER, Contractor andEPD;

2. Repeat measurements to confirmfindings;

3. Increase monitoring frequency;4. Identify source and investigate the

cause of exceedance;5. Carry out analysis of Contractor’s

working procedures;6. Discuss with IEC, Contractor and

ER on remedial measures required;7. Assess effectiveness of

Contractor’s remedial actions andkeep IEC, EPD and ER informed ofthe results;

8. If exceedance stops, ceaseadditional monitoring.

1. Discuss amongst ER, ET, andContractor on the potentialremedial actions;

2. Review Contractor’s remedialactions whenever necessaryto assure their effectivenessand advise ER accordingly.

1. Confirm receipt ofnotification of failure inwriting;

2. Notify Contractor;3. In consolidation with IEC,

agree with Contractor onthe remedial measures tobe implemented;

4. Supervise theimplementation ofremedial measures;

5. If exceedance continues,consider stoppingContractor to continueworking on that portion ofwork which causes theexceedance until theexceedance is abated.

1. Take immediate action to avoidfurther exceedance;

2. Submit proposals for remedialactions to IEC and ER within 3working days of notification;

3. Implement the agreed proposals;4. Submit further proposal if problem

still not under control;5. Stop the relevant portion of works

as instructed by ER until theexceedance is abated.

Page 88: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Event and Action Plan for Landscape and Visual Impact during Construction Phase

Event Action

ET IEC ER Contractor

Non-conformityon one occasion

1. Identify source;2. Inform IEC and ER;3. Discuss remedial actions with IEC,

ER and Contractor;4. Monitor remedial action until

rectification has been completed.

1. Check report;

2. Check Contractor’s working

method;

3. Discuss with ER and Contractor on

possible remedial measures;

4. Advise ER on effectiveness of

proposed remedial measures.

1. Notify Contractor;

2. Ensure remedial

measures are properly

implemented.

1. Amend working methods;

2. Rectify damage and undertake

remedial measures or any

necessary replacement.

Repeated

Non-conformity

1. Identify source;2. Inform IEC and ER;3. Increase monitoring (site audit)

frequency;4. Discuss remedial actions with IEC,

ER and Contractor;5. Monitor remedial actions until

rectification has been completed;6. If exceedance stops, cease

additional monitoring (site audit).

1. Check report;2. Check Contractor’s working

method;3. Discuss with ER and Contractor

on possible remedial measures;4. Advise ER on effectiveness of

Proposed remedial measures;5. Supervise implementation

of remedial.

1. Notify Contractor;

2. Ensure remedial

measures are properly

implemented.

1. Amend working methods;

2. Rectify damage and undertake

remedial measures or any

necessary replacement.

Page 89: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX K

Detailed Landscape and Visual Monitoring Report

Page 90: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer
Page 91: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Drainage Services Department

Contract No. DC/2009/05

Harbour Area Treatment Scheme Stage 2A –

Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at Stonecutters Island

Sewage Treatment Works

P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\Landscape and Visual Report\LVA & M Inspection Report No._13a.docx

1.0 INTRODUCTION

The Landscape and Visual Audit & Monitoring are conducted to fulfill the requirements of the EIA

Report during the Construction and Operational Phases of the project, and are based on the

procedures and requirements as set out in the Agreement No. CE 43/2005 (EP) Harbour Area

Treatment Works (HATS) Stage 2A EIA Study – Final Environmental Monitoring and Audit Manual.

As stated in section 11.7 and 11.08 of the EM&A Manual, all landscape and visual mitigation

measures undertaken by the Contractor during the Construction Phase and the first 12 months of the

Operational Phase shall be audited on a monthly basis to ensure compliance with the intended aims

of the mitigation measures as stated in section 11.10.

2.0 SCOPE OF AUDIT and MONITORING

The broad scope of landscape and visual monitoring and audit on mitigation measures is as detailed

below:

2.1 Construction Phase

Indentify any potential conflicts between the proposed landscape measures and any other project

works or operation requirements, and recorded for the contractor to resolve in early stage, without

compromising the intention of the mitigation measures. Also, the followings shall be monitored:

Identify topsoil where suitable to be stripped and stored for re-use in the construction of soft

landscape works;

Regular review of the progress of engineering works to identify the earliest practical opportunity

for the landscape works;

Monitoring of tree transplanting and planting operations;

Monitoring of works around the area of existing trees to be retained and protected;

Monitoring of protection works for existing trees;

Ensure planting works are carried out in accordance with the Specification and within the right

planting season;

Ensure decorative screen hoarding erected on site are compatible with the surrounding setting;

Monitoring of night-time lighting to avoid light pollution and glare.

2.2 Operation Phase

Ensure the effectiveness of the landscape and visual mitigations measures during the Operation

Phase, including:

Monitoring of the maintenance operations during the Establishment Period to ensure all plants

are well established;

Ensure the aesthetic design of the façade of PTW and associated structures are harmonized with

the surroundings;

Ensure buffer tree and shrub plantings provides adequate screening to structures, including

rooftop greening and vertical greening.

Page 92: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Drainage Services Department

Contract No. DC/2009/05

Harbour Area Treatment Scheme Stage 2A –

Construction of Interconnection Tunnel and Diaphragm Wall for Main Pumping Station at Stonecutters Island

Sewage Treatment Works

P:\60143571\1.01\Deliverables\Monthly EM&A Report\1101\Landscape and Visual Report\LVA & M Inspection Report No._13a.docx

3.0 INSPECTION

3.1 Summary of Inspection – 25th

January 2011

3.1.1 Matters Arising from Previous Inspections

Nil.

3.1.2 Protection of Existing Trees and Tree Works

It was observed that the lower branches of the retained trees and the tree protection zone area

were covered with splashed mud slurry. The Contractor was requested to clean up by hosing

down the tree branches and to install plastic sheets at the base of the tree protection zone area to

prevent further splashing of mud slurry, which would affect the health of the trees.

3.1.3 Recommendations

The Contractor was recommended to clean up the tree branches and tree protection zone area,

and to install plastic sheets to prevent the splashing of mud slurry.

4.0 AUDIT SCHEULE

4.1 Audit Schedule for February 2011

The next monthly audit is schedule to be conducted on 23rd

February 2011.

Page 93: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

APPENDIX L

Cumulative Statistics of Exceedances, Complaints, Notification of Summons and Successful Prosecutions

Page 94: 5/F, Western Magistracy,hats2a-ema.com/rp_ema/dc200905/0111/rev.0 (january 2011) full set 1… · Condition 4.4 – Submission of Monthly EM&A Report for January 2011 (no. 14) I refer

Appendix L - Cumulative Statistics on Exceedances,Complaints, Notification of Summons and SuccessfulProsecutions

Cumulative statistics on Exceedances

Total no. recorded in this

month

Total no. recorded since

project commencement

1-Hour TSP Action 0 0

Limit 0 0

24-Hour TSP Action 0 0

Limit 0 0

Noise Action 0 0

Limit 0 0

Remarks: Exceedances which are not project-related are not presented in this table.

Cumulative statistics on Complaints, Notifications of Summons andSuccessful Prosecutions

Date

Received

Subject Status Total no.

recorded in

this month

Total no.

recorded since

project

commencement

Environmental

complaints

- - - 0 0

Notification of

summons

- - - 0 0

Successful

Prosecutions

- - - 0 0