5a - boiler construction continued -internals - superheaters locked

Upload: ganeshan

Post on 14-Apr-2018

236 views

Category:

Documents


2 download

TRANSCRIPT

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    1/29

    MainPlant

    Boilers

    MainPlant

    Boilers

    Feed water in

    Economiser

    Steamdrum

    Waterdrum

    Superheater

    Downcomers

    Risers

    Risers

    Furnace

    Casing

    Superheated

    steam out

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    2/29

    Steam DrumSteam Drum

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    3/29

    The steam drum is designed to separate the steam from the

    steam/water emulsion produced in the riser tubes.

    It is important to ensure that no water is carried over into

    the superheater. Separation is carried out by:-

    Horizontal perforated plates acting as baffles.

    A dry pipe situated at the top of the drum with slots

    cut in to help prevent the passage of water. The dry

    pipe carries the steam away from the drum to the

    superheater.

    The feed water pipe is submerged below the normal

    working water level of the boiler.

    Steam Drum InternalsSteam Drum Internals

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    4/29

    CycloneSeparators

    CycloneSeparators

    Used in some makes

    of boiler to give

    improved separation of

    steam/water.

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    5/29

    Cyclone SeparatorsCyclone Separators

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    6/29

    Steam DrumSteam Drum

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    7/29

    Steam DrumSteam Drum

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    8/29

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    9/29

    Super-heatersSuper-heaters

    The ESD III boiler

    has an external

    superheater that

    uses the thermalenergy of the

    combustion gasses

    after passing

    through the screen

    wall

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    10/29

    Superheater tubes are subject to very high temperatures

    (510C) and full boiler pressure (65 bar) and are, therefore,

    highly stressed.

    Materials: Chrome/molybdenum steel.

    Tube Diameter 53mmThe superheater tubes are welded on to stub pipes on the

    headers, which are external to the gas passage.

    The tube bends are supported by lugs which are welded tothe screen wall riser tubes in order to remove heat.

    SuperheatersSuperheaters

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    11/29

    The superheater is set up as three separate banks of tubes.

    The two top banks (furthest from the furnace) are set up asthe primary superheater.

    The lower bank (closest to the furnace) is the secondary

    superheater.ALL steam flow from the boiler drum must pass through

    ALL sections of the superheater continuously.

    It is important to maintain maximum flow through thesuperheater at all times in order to prevent overheating.

    SuperheatersSuperheaters

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    12/29

    SuperheatersSuperheaters

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    13/29

    SuperheatersSuperheaters

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    14/29

    SuperheatersSuperheaters

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    15/29

    Steam Temperature ControlSteam Temperature Control

    Air Attemporation

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    16/29

    Steam Temperature ControlSteam Temperature Control

    ESD II

    Gas Flow Control

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    17/29

    Steam Temperature ControlSteam Temperature Control

    ((AttemporationAttemporation))

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    18/29

    Superheat

    Flow

    SuperheatSuperheat

    FlowFlow

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    19/29

    Superheat FlowSuperheat Flow

    Primary Superheater Contra flow

    Secondary Superheater Parallel Flow

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    20/29

    AttemporatorAttemporator

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    21/29

    AttemporatorAttemporator

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    22/29

    Water SprayWater Spray AttemporationAttemporation

    Feed water sprayed into steam path

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    23/29

    Some of the superheated steam is de-superheated in order

    to supply cooled saturated steam for lower quality heatingpurpose e.g.

    Steam/steam generators. Evaporators. De-aerators. Air

    heaters. etc.

    There are two main ways of de-superheating:-

    Via a cooling coil in the water drum of the boiler.

    Via a water spray de-superheater.

    De-superheatersDe-superheaters

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    24/29

    Spray De-superheaterSpray De-superheater

    De-superheatedoutlet

    Superheatedinlet

    Drain

    Feed

    water inlet

    Feed

    water flow

    control

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    25/29

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    26/29

    In order to improve the efficiency of the combustion

    process and the overall efficiency of the boiler the

    combustion air is pre-heated. This can be done in threeways:-

    A tube type air heater using de-superheated steam.

    A rotary heat exchanger (Ljungstrom)

    A double casing fitted round the boiler.

    Air HeaterAir Heater

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    27/29

    The combustion air is passed from the forced draught fan

    into a double casing surrounding the furnace and

    superheater.

    The air is first heated by waste heat passing through the

    riser tube wall and the refractory.

    The air then passes through a tube type heat exchanger that

    uses de-superheated steam to increase the temperature to

    about 120C before the air passes to the burner registers.

    Note that monowall boilers do not normally have double

    casings.

    Double Casing & Air HeaterDouble Casing & Air Heater

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    28/29

    Ljungstrom Air HeaterLjungstrom Air Heater

  • 7/27/2019 5a - Boiler Construction Continued -Internals - Superheaters Locked

    29/29