PRODUCTIVITY RATES FOR ALL PROJECT WORKS: (Rev 0, May 2000) Item No. CREW SIZE Hourly Production Production Rate Per 10 hrs. SM FW FORMWORK FW01 Formwork to footings 2 CARPENTERS, 1 HELPER 1.2 12 FW02 Formwork to isolated footings 2 CARPENTERS, 1 HELPER 1.6 16 FW03 Formwork to rafts 2 CARPENTERS, 1 HELPER 1.4 14 FW04 Formwork to rafts D>0.75m 2 CARPENTERS, 1 HELPER 1.8 18 FW05 Formwork to tie beams 2 CARPENTERS, 1 HELPER 1 10 FW06 Formwork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 12 FW07 Formwork to Neck Columns 2 CARPENTERS, 1 HELPER 4 FW08 Formwork to U/G Water tank 2 CARPENTERS, 1 HELPER 6 FW09 Formwork to basement retaining walls 2 CARPENTERS, 1 HELPER 9 FW10 Formwork to columns (small size) 2 CARPENTERS, 1 HELPER 7 FW11 Formwork to Columns (large size) 2 CARPENTERS, 1 HELPER 9 FW12 Formwork to D/S beam internal (shallow) 2 CARPENTERS, 1 HELPER 6 FW13 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 7 FW14 Formwork to D/S beam external (Shallow) 2 CARPENTERS, 1 HELPER 4 FW15 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 6 FW16 Formwork to lift walls single core 2 CARPENTERS, 1 HELPER 6 FW17 Formwork to lift walls multi core 2 CARPENTERS, 1 HELPER 8 FW18 Formwork to slab decking (10ft) hourdi 2 CARPENTERS, 1 HELPER 1.6 16 FW19 Formwork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 12 FW20 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.2 12 FW21 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1 10 FW22 Formwork to staircase (non spiral) 2 CARPENTERS, 1 HELPER 4 FW23 Formwork to balcony parapets 2 CARPENTERS, 1 HELPER 6 FW24 Formwork to roof parapets 2 CARPENTERS, 1 HELPER 8 D = DEPTH Page 1 of 7 U. GR. = UNDERGROUND D/S = DECK - SLAB > = GREATER THAN < = LESS THAN

Upload: george-israel

Post on 01-Dec-2015

1.262 views

Category:

Documents


100 download

TRANSCRIPT

Page 1: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE Hourly Production

Production Rate Per 10 hrs.

SM

FW FORMWORK

FW01 Formwork to footings 2 CARPENTERS, 1 HELPER 1.2 12

FW02 Formwork to isolated footings 2 CARPENTERS, 1 HELPER 1.6 16

FW03 Formwork to rafts 2 CARPENTERS, 1 HELPER 1.4 14

FW04 Formwork to rafts D>0.75m 2 CARPENTERS, 1 HELPER 1.8 18

FW05 Formwork to tie beams 2 CARPENTERS, 1 HELPER 1 10

FW06 Formwork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 12

FW07 Formwork to Neck Columns 2 CARPENTERS, 1 HELPER 4

FW08 Formwork to U/G Water tank 2 CARPENTERS, 1 HELPER 6

FW09 Formwork to basement retaining walls 2 CARPENTERS, 1 HELPER 9

FW10 Formwork to columns (small size) 2 CARPENTERS, 1 HELPER 7

FW11 Formwork to Columns (large size) 2 CARPENTERS, 1 HELPER 9

FW12 Formwork to D/S beam internal (shallow) 2 CARPENTERS, 1 HELPER 6

FW13 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 7

FW14 Formwork to D/S beam external (Shallow) 2 CARPENTERS, 1 HELPER 4

FW15 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 6

FW16 Formwork to lift walls single core 2 CARPENTERS, 1 HELPER 6

FW17 Formwork to lift walls multi core 2 CARPENTERS, 1 HELPER 8

FW18 Formwork to slab decking (10ft) hourdi 2 CARPENTERS, 1 HELPER 1.6 16

FW19 Formwork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 12

FW20 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.2 12

FW21 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1 10

FW22 Formwork to staircase (non spiral) 2 CARPENTERS, 1 HELPER 4

FW23 Formwork to balcony parapets 2 CARPENTERS, 1 HELPER 6

FW24 Formwork to roof parapets 2 CARPENTERS, 1 HELPER 8

D = DEPTH Page 1 of 7

U. GR. = UNDERGROUNDD/S = DECK - SLAB> = GREATER THAN< = LESS THAN

Page 2: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE Hourly Production

Production Rate Per 10 hrs.

FW 25 shutter Manufacture for pile caps 1 CARPENTER + 1 HELPER 2.00 20

FW 26 shutter Fix for pile caps I CARPENTER + 1 HELPER 1.50 30

FW 27 Deshutter footings/pile caps 1 HELPER 6.00 60

FW 28 Shutter make column necks 1 CARPENTER + 1 HELPER 1.50 15

FW 29 Shutter fix column necks 1 CARPENTER + 1 HELPER 1.20 12

FW 30 Deshutter Column necks 1 HELPER 4.80 48

FW 31 Shutter make tie beams 1 CARPENTER + 1 HELPER 1.20 12

FW 32 shutter fix tie beams 1 CARPENTER + 1 HELPER 1.00 10

FW 33 Column shutter making 1 CARPENTER + 1 HELPER 1.20 12

FW 34 Column shutter fixing 1 CARPENTER + 1 HELPER 1.00 10

FW 35 Column deshuttering 1 HELPER 4.00 40

FW 36 Walls shutter making 1 CARPENTER + 1 HELPER 1.50 15

FW 37 Walls shutter fixing 1 CARPENTER + 1 HELPER 0.80 80

FW 38 De shutter Tie beam shutter 1 HELPER 4.00 40

FW 39 Wall formwork deshuttering 1 HELPER 3.20 32

FW 40 Staircase formwork making 1 CARPENTER + 1 HELPER 0.80 8

FW 41 staircase formwork fixing 1 CARPENTER + 1 HELPER 0,8 8

FW 42 Staircase formwork deshuttering 1 HELPER 1,6 16

FW 43 Drop beams formwork making 1 CARPENTER + 1 HELPER 1.00 10

FW 44 Drop beams formwork fixing 1 CARPENTER + 1 HELPER 0.80 8

FW 45 Drop beams formwork stipping 1 HELPER 3.20 32

FW 46 suspended slab formwork fixing 1 CARPENTER + 1 HELPER 1.20 12

FW 47 suspended slab formwork deshutter 1 HELPER 5.00 50

FW 48 Formwork fixing for sunshades 1 CARPENTER + 1 HELPER 0.70 7

FW 49 Parapet formwork making 1 CARPENTER + 1 HELPER 1.20 12

FW 50 Parapets formwork fixing 1 CARPENTER + 1 HELPER 1.00 10

FW 51 Parapets formwork stripping 1 HELPER 4.00 40

FW 53 Fixing of lintle formwork 1 CARPENTER + 1 HELPER 0.50 5

FW 54 Deshutter lintle formwork 1 HELPER 2.00 20

FW 55 Deck formwork fixing 1 CARPENTER + 1 HELPER 1.50 15

FW 56 Deck Formwork deshuttering 1 HELPER 6.00 60

FW 57 Pipe scaffolding erection for slab 1 SCAFFOLDER 0.85 85

FW 58 inverted beam shutter fixing 1 CARPENTER + 1 HELPER 1.00 10

FW 59 De-Shuttering Manholes, square - circular (Timber) 1 CARPENTER + 1 HELPER

FW 60 Manhole Shutter erection - square or circular(Timber) 1 CARPENTER + 1 HELPER

FW 61 Metal Shutter for Manholes 1 CARPENTER + 1 HELPER

FW 62 Metal Shutter for Precast Beams 2 CARPENTERS + 2 HELPERS

FW 63 Metal Shutter for Pile caps 2 CARPENTERS + 2 HELPERS

FW 64 Metal Shutters for Pile cap Beams 2 CARPENTERS + 2 HELPERS

4m2 40m2

1,5 m2 15m2

1m2 10m2

3M2 30M2

3M2 27M2

3M2 30M2

Page 3: 59413838 Labour Productivity Chart in Uae

Page 2 of 7

Page 4: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE Hourly Production

Production Rate Per 10 hrs.

Per Unit

M MASONARY WORKS

MBW 01 Hollow Blockwork (100, 150 & 200 mm) 1 MASON, 1 HELPER 12 Nos 120 NR

MBW 02 Hollow Blockwork (large panels) 1 MASON, 1 HELPER 14 Nos. 140 NR

MBW 03 Solid blockwork 1 MASON, 1 HELPER 9,5 95 NR

MBW 04 Solid Blockwork as Raft forms 1 MASON, 1 HELPER 11 110 NR

MPL PLASTERWORK 1.2

MPL 01 Plaster (internal), walls final coat 1 MASON, 1 HELPER 1.6 16 SM

MPL 02 Plaster (internal), walls rush coat 2 HELPER 1.4 150 SM

MPL 03 Plaster (internal), walls mesh 1 HELPER 1.8 100 SM

MPL 04 Plaster (internal), walls hacking 1 HELPER 1 100 SM

MPL 05 Plaster (internal), walls guide point 1 MASON, 1 HELPER 1.2 100 SM

MPL 06 Plaster (internal), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM

MPL 07 Plaster (external), walls with grooves 1 MASON, 1 HELPER 10 SM 10 SM

MPL 08 Plaster (external), walls without grooves 1 MASON, 1 HELPER 1,2 12 SM

MPL 09 Plaster (external), walls rush coat 2 HELPER 15 SM 150 SM

MPL 10 Plaster (external), walls mesh 1 HELPER 10 SM 100 SM

MPL 11 Plaster (external), walls hacking 1 HELPER 10 SM 100 SM

MPL 12 Plaster (external), walls guide points 1 MASON, 1 HELPER 10 SM 100 SM

MPL 13 Plaster (external), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM

MPL 14 Plastering of Arches/Mullians 1 MASON, 1 HELPER 0.8 80

MPL 15 Floor screed 50mm thick 1 MASON, 1 HELPER 2 20

MPL 16 Roof screed 100 mm thick 1 MASON, 1 HELPER 1.5 15

MPL 17 Mosiac floor Tiles fixing 1 MASON, 1 HELPER 1.6 1.5

MPL 18 Floor Screed 25mm thick 1 Mason + 1 Helper 0,6 6

MCR CERAMIC WORKS

MCR 01 Ceramic tiles to walls by mortar 1 MASON, 1 HELPER 1.2 8 SM

MCR 02 Ceramic tiles to walls, mortar to corridors 1 MASON, 1 HELPER 1 9 SM

MCR 03 Ceramic tiles to walls, cut pieces 1 MASON 2 20 SM

MCR 04 Ceramic tiles to walls grouting 1 HELPER 5 50 SM

MCR 05 Ceramic tiles to walls, by glue 1 MASON, 1 HELPER 1,2 12 SM

MCR 06 Ceramic tiles to walls, corridors, by glue 1 MASON, 1 HELPER 1,3 13 SM

MCR 07 Ceramic tiles to walls, by glue, cut pieces 1 MASON 2 20 SM

MCR 08 Ceramic tiles to walls, by glue, grouting 1HELPER 5 50 SM

MCR 09 Ceramic tiles to floors 1 MASON, 1 HELPER 1 10 SM

MCR 10 Ceramic tiles to floors in halls 1 MASON, 1 HELPER 1,2 12 SM

MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM

MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM

MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60

Page 5: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE Hourly Production

Production Rate Per 10 hrs.

Per Unit

MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM

MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM

MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60

Page 3 of 7

Page 6: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE Hourly Production

Production Rate Per 10 hrs.

Per Unit

MCR CERAMIC WORKS

MCR 13 Ceramic skirting by glue 1 MASON, 1 HELPER 2,5 M 25 METRE

MCR 14 Ceramic skirting by glue to halls, corridors 1 MASON, 1 HELPER 3 M 30 METRE

MTW TILING WORKS

MTW 01 Mosiac / Terrazo tiles to roofs 1 MASON, 1 HELPER 1,6 16 SM

MTW 02 Mosiac / Terrazo tiles to floors 1 MASON, 1 HELPER 1,4 14 SM

MTW 03 Mosiac skirting to halls 1 MASON, 1 HELPER 2,5 25 METRE

MTW 04 Mosiac skirting flush / recessed 1 MASON, 1 HELPER 1,4 14 METRE

MTW 05 Grouting / sealing to roof / floor tiles 1 HELPER 2,5 25 METRE

MKP KERBING / BLOCK PAVING WORKS

MKP00 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE

MKP01 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE

MKP02 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 METRE

MKP03 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 METRE

MKP04 Interlock paving on pre prepared sub - base 1 MASON, 1 HELPER 2 SM

MKP05 Screed works including preparation 1 MASON, 1 HELPER 1,5 15 SM

MKP06 Haunching ot Kerb Base (Mixing Truck) 1 MASON, 1 HELPER 10 M 100M

DRW MANHOLE/ DRAINAGE CONSTRUCTION

DRW 01 Excavation for drains / manholes 1 HELPER 5 CM

DRW 02 Backfill to drains / manholes 1 HELPER 10 CM

DRW 03 Blockwork to manholes 1 MASON, 1 HELPER 2 NOS

DRW 04 Plaster to manholes 1 MASON, 1 HELPER 2 NOS

DRW 05 Benching to manholes 1 MASON, 1 HELPER 4 NOS

DRW 06 Fix covers to manholes 1 MASON, 1 HELPER 2 NOS

DRW 07 Fix gulley traps 1 MASON, 1 HELPER 1 NO

DRW 08 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240M

MLW MISCELLANEOUS LABOUR WORKS

MLW01 Bitumen paint to concrete blockwork surfaces 1 HELPER 4 40 SM

MLW02 Bitumin painting Bases / piles 1 HELPER 7.00 70

MLW03 Hacking of concrete surfaces 1 HELPER 5 50 SM

MLW04 fixing of flexcell sheets 1 HELPER 6 SM

MLW05 pile cutting/dressing 1 HELPER 1 NO

MLW06 pile cutting/dressing (small diameter) 1 HELPER 2 NOS

MLW07 Vertical sealant (12 mm) 1 HELPER 2,5 25 METRE

MLW08 Horizontal sealant (12 mm) 1 HELPER 5 50 EMTRE

MLW09 Roof preparation for lw concrete 1 MASON, 1 HELPER 5 50 SM

MLW10 Angle fillet fixing 1 MASON, 1 HELPER 4 40 EMTE

MLW11 Hourdi block shifting and fixing to slab 2 HELPER 20 200 NOS

MLW12 Polythene sheet fixing 1 HELPER 3m 30

MLW13 Shaping of Soil Blinding 1 MASON + 1 HELPER 1 M 10M

MLW14 Protection Board installation 1 CARPENTER + 1 HELPER 8M2

MCW MISCELLANEOUS CARPENTARY WORKS

MCW 01 A/C subframe manufacture / fixing 1 CARPENTER 5 NOS

MCW 02 Door subframe manufacture / fixing 1 CARPENTER 4 NOS

MCW 03 Water bar fixing 1 CARPENTER 2 M 20 METRE

Page 4 0f 7

80M2

Page 7: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE Hourly Production

Production Rate Per 10 hrs.

Per Unit

CPW CONCRETE PLACEMENT WORKS

CPW01 Concrete to pile caps by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM

Standard rate 1 man 1 hr. 10m3

CPW02 Concrete to PCC blinding (100 mm thick) 1 MASON, 10 HELPERS 27 CM

CPW03 Concrete to slabs/beams, by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM

CPW04 Concrete to slabs / beams by crane 1 MASON, 6 HELPERS, 0.5 OPERATOR 8,10 27 CM

CPW05 Concrete to walls / columns, by pump 4 MASONS, 16 HELPERS, 2 CARPENTERS 1.2 81 CM

CPW06 Concrete by site mix 1 MASON, 12 HELPERS , 0.5 CARPENTER 1.6 9 CM

CPW07 Concrete Columns 8 HELPERS 1.40 10

CPW08 Concrete suspended slab (pump) 3 MASONS + 6 HELPERS 1.80 150

CPW09 Concrete parapets/staircases 8 HELPERS 1.00 7

CPW10 Blinding concrete 50 mm (readymix) 1 MASON + 4 HELPER 8,0 80

CPW11 Blinding concrete 50 mm (sitemix) 1 MASON + 8 HELPER 1.00 10

CPW12 Concrete footings & pile caps 1 MASON + 4 HELPER 12.00 120

CPW13 Concrete tiebeams, ground beams 1 MASON + 5 HELPER 6.00 60

CPW14 Concrete column necks 8 HELPER 1.50 15

CPW15 Concrete Ground slab 3 MASONS + 6 HELPER 1,5 15

CPW16 Concrete to precast slabs, beams 2 MASONS + 1 HELPER 3m3

GLW GENERAL LABOUR WORKS

GLW01 Unloading reinforcement ((Flat Bed Truck) 4 HELPERS 2 Nos

GLW02 Loading reinforcement to slab (With Crane) 4 HELPERS (Flat Bed Truck loads) 40 Nos. 2 Nos

GLW03 Loading blockwork to site (with Wheel Burrow) 1 HELPER 400 Nos.

GLW04 Loading mortar to site location

GLW05 Mixing mortar for distribution 0, 3 L mixer 4 HELPER 6M3

GLW06 Site mixing of ready mix for distribution Hand mix 3M3

GLW07 Loading ready mix to site location

NTRA NON TARGET RELATED ACTIVITES

NTRA01 Stacking of formwork 2 HELPERS

NTRA02 Curing of Substructure works 2 HELPERS

NTRA03 Curing of beams / slabs Hessiant Water 2 HELPERS

NTRA04 Curing of columns (Hessiant Water) 1 MASON + 2 HELPERS 1.6 (L.M) 36 M

NTRA05 Builders work make good chases 1.2 (L.M)

NTRA06 Site cleaning 1 HELPER 25

NTRA07 Repairs to finished works 1

30 M3

250 M2

Page 8: 59413838 Labour Productivity Chart in Uae

Page 5 of 7

Page 9: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE NON MEASURABLE

NTRA08 Maintenance of site services 2 HELPERS

NTRA09 Operators for mixers 2/MIXER

NTRA10 Operators for compaction equipment 1 UNIT

NTRA11 Office boy ARABTEC 1 / CONSULTANT 1

NTRA12 Watchman 2 MIN

NTRA13 Storekeeper 1/SHIFT

Page 6 of 7

Page 10: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:(Rev 0, May 2000)

Item No. CREW SIZE Hourly

Production Rate

RF REINFORCEMENT

RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 25

RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 20

RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 18

RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15

RF 05 Fix rebar to hidden beams 1 STEEL FIXER 20

RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 78

RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 38

RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 35

RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15

RF 05 Fix rebar to hidden beams 1 STEEL FIXER

RFC 01 Steel cutting and bending 18.25 mm 1 STEEL FIXER 50.00

RFC 02 Steel cutting and bending 8 - 16 mm 1 STEEL FIXER 40.00

EXCAVATION

EX 1 1 HELPER

EX 2 Backfill + levelling 1HELPER

EX 3 Shaping of sloped earth for blinding for bases including compaction 1 MASON + 2 HELPER

Manual Excavation

Page 11: 59413838 Labour Productivity Chart in Uae

PRODUCTIVITY RATES (Rev 0, May 2000)

Productivity Rates for Tilling

Size. (Cms) Location Area Manpower Production Rate Remarks

(Sqm. Per day)

30 X 30 Floor Kitchen 1 Mason, 1 Helper 14 Residential Area by Sub-Contractor

30 X 30 Floor with pattern Corridor 1 Helper, 2 Masons 10 Residential Area by Sub-Contractor

40 X 40 Floor Bed room 1 Mason, 1 Helper 22-25 Residential Area by Sub-Contractor

20 X 20 Floor Store (small area) 1 Mason, 1 Helper 10 Residential Area by Sub-Contractor

30 X 60 Floor Bathroom 2 Mason, 1 Helper 6 Residential Area by Sub-Contractor

30 X 30 Floor + Wall Bathroom 2 Mason, 1 Helper 5

10 X 10 Wall Kitchen 1 Mason, 1 Helper 8-9 Residential Area by Sub-Contractor

30 X 60 Wall Corridor 1 Mason, 1 Helper 14-15 Residential Area by Sub-Contractor

30 X 30 Wall Bathroom 2 Mason, 1 Helper 7 Residential Area by Sub-Contractor

Residential Area by Sub-Contractor

Notes:

1. 1 Day = 10 hrs.

2. Gang Size:

1 Mason + 1 Helper for Kitchen and Bedroom.