56-61_as432411995 standardseptoct12

Upload: spnaik

Post on 13-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 56-61_AS432411995 standardSeptOct12

    1/656 Australian Bulk Handling Review: September/October 2012

    IntroductionAS4324.1 Mobile equipment for continu-

    ous handling of bulk materials Part 1-

    General requirements for the design of

    steel structureswas introduced in 1995.

    The Standard had a long gestation period

    [5], with work commencing in 1978. Its

    release in 1995 was timely in response

    to a number of failures of bulk materials

    handling machines in Australia in the ear-

    ly 1990s. This Standard applies to mobile

    equipment for continuous handling of

    bulk materials, e.g. excavators, stackers,

    reclaimers, shiploaders, and ship unload-ers. It was intended that AS4324: Part 1,

    which deals with steel structures, would

    be followed by other parts addressing

    mechanical, electrical and other aspects.

    However this has not occurred.

    The International Organization forStandardization (ISO) has published a de-

    sign standard for bulk materials handl ing

    machines, ISO5049.1 [3] which has been

    widely used internationally and was used

    in Austral ia prior to 1995. There are signif-

    icant differences between AS4324.1 and

    ISO5049.1; generally speaking, machines

    designed according to AS4324.1 are heav-

    ier than similar machines designed to

    ISO5409.1. German Standard DIN 2226

    [2] has been written specifically for ma-

    chines working in large brown coal open

    cut mines, including bucket wheel ex-cavators. AS4324.1 has adopted material

    from DIN 22261 and its predecessors in

    addition to material from ISO5049.1.

    Protective or load limiting devices in

    the electrical, control, mechanical and

    hydraulic systems are very importantin determining the load imposed on a

    machine. This is an area which requires

    close attention both in the design phase

    and on site to ensure that the installed

    devices perform the correct function.

    AS4324.1 adopts a philosophy of not

    overly relying on electrical protection

    devices for structural integrity.

    Application of AS4324.1 totypes of machinesAS4324.1 is intended to apply to both

    rail-mounted yard machines and contin-uous mining machines which are usually

    mounted on crawlers. Appendix E in the

    Standard gives illustrations of the types

    of machines for which the Standard is in-

    tended to apply. A description of some

    AS4324.1-1995 standard for design of bulk

    materials handling machines

    The increasing level of mineral exports from Australia has resulted in the need for expansions to existing

    facilities and new export facilities. Rail-mounted materials handling machines such as shiploaders,

    stackers and reclaimers are significant investment items for the ports and mines involved in the supply

    chain for export of these commodities. Australia is one of the few countries to have its own standard for

    such equipment: AS4324.1.

    Figure 1 - Stacker Reclaimer

    By Richard Morgan, Aspec Engineering

    ENGINEERING SERVICES

  • 7/27/2019 56-61_AS432411995 standardSeptOct12

    2/657Australian Bulk Handling Review: September/October 2012

    of the more common types of rail-mounted machines follows

    below.

    Stacker reclaimersFigure 1 shows the components on an older style of stacker

    reclaimer. The machine has a long travel motion along tracks

    propelled by driven wheels on the bogie system. In the stack-

    ing mode, bulk material is fed onto the machine from the yardbelt via a tripper which discharges onto the elevator. Material

    travels on a conveyor up the elevator and discharges through a

    chute onto the boom conveyor. The bulk material discharges

    onto the stockpile from the end of the boom.

    In reclaiming mode the boom conveyor reverses direction.

    Bulk material is reclaimed from the stockpile by the bucket

    wheel which rotates via a driven shaft. The buckets dig ma-

    terial from the stockpile and discharge them onto the boom

    conveyor. The boom conveyor discharges material through a

    central chute onto the yard conveyor.

    The boom can pivot in a vertical plane about a central bear-

    ing to follow the stockpile terrain. This motion is driven by hy-

    draulic cylinders and is termed luffing. The boom can also

    rotate in the horizontal plane about a circular bear ing. This mo-tion is dr iven by a gear system and is termed slewing.

    Machines of this type are sensitive to changes in balance

    about the luffing pivot. Changes in weight and weight distribu-

    tion need to be carefully monitored and controlled. The repeti-

    tive loading due to the bucket wheel motion requires considera -

    tion for metal fatigue of the structure and slew bearing. Other

    machine configurations are used, e.g. a C frame configuration

    can slew to both sides of the rail tracks without the need to ex-

    tend the elevator away from the machine with the tow bridge.

    StackersStackers predominately long travel with limited slewing mo-

    tions in order to lay the stockpiles for subsequent reclaiming bya slewing or bridge type reclaimers. On modern designs luffing

    is carried out by means of hydraulic cylinders. Stackers with

    longer spans are often articulated to provide less variation in

    load during the luffing motion.

    ReclaimersBucket wheel boom type reclaimers are similar to a bucket

    wheel stacker reclaimer (see Figure 1) but without the stacking

    function, so they do not include a tripper and elevator. Bridge

    reclaimers of the bucket wheel type are often used for reclaim-

    ing on the face of a blended stockpile. Such machines have

    rakes which are used to loosen material on the active face.

    ShiploadersLong travelling shiploaders with a wheelbase up to approxi-

    mately 20 metres commonly have a portal structure spanning

    the rails and a fixed boom gantry set at 90 degrees to the rail

    track. The boom conveyor and shiploading chute shuttle in and

    out to load the hatches and due to geometry, there are limita-

    tions on the length of in-board travel of the shuttle. The shuttle

    mechanism may vary the length of the boom or the boom may

    be of fixed length with the shuttle within the boom. Another

    configuration is the bridge type which has a large travelling

    bridge spanning from the seaward rail to a second rail or pivot

    point some distance behind the berth. A shuttling trolley sys-

    tem, which supports the boom, tower, and luffing winch sys-

    tem, travels along the bridge.The portal slewing type shiploader is suitable for ships with-

    out masts and cargo gear. Trimming of hatches is accomplished

    by a combination of slewing and long travel motions. The portal

    slewing and shuttling type shiploader allows for greater flexibil-

    ity in loading di fferent ship types than the portal slewing type.

    ENGINEERING SERVICES

  • 7/27/2019 56-61_AS432411995 standardSeptOct12

    3/658 Australian Bulk Handling Review: September/October 2012

    LoadsThe following section describes some

    of the important load conditions which

    have been expanded or covered in more

    detail in AS4324.1 than in the ISO or DIN

    Standards.

    Digging Resistance U and AbnormalDigging Resistance UUThe calculation procedure for digging

    resistance requires this load to be based

    on drive motor torque. In the authors

    experience site measurements generally

    show that machines are driven to the

    limits of the drive system.

    Lateral Digging Resistance Sand Abnormal Lateral DiggingResistance SSAS4324.1 requires lateral digging resist-

    ance to be based on available slew or

    long travel drive capacity. Site measure-ments generally support this approach,

    even for bucket wheel reclaimers or oth-

    er yard machines.

    Permanent Dynamics DThe treatment of permanent dynamics

    uses dynamic effects factors which mul-

    tiply the appropriate dead and live loads.

    The factors used in AS4324.1 include

    additional values to cover rail-mounted

    machines as well as crawler mounted

    equipment.

    Wind Loads Operating W and WindWhile Idle WWWind loads, either for operating condi-

    tions or for extreme winds with the

    machine out of operation, are referred

    to the Australian Standard AS1170.2. Ad-

    ditional requirements are included for

    gust effects on the superstructure and

    for wind at a 45 degree angle to the main

    structure axes.

    Travel Skew Forces LSFor rail-mounted machines, AS4324.1

    nominates a calculation procedure fortravel skew forces which is similar to

    that in the Crane Standard AS1418. This

    includes consideration of asymmetrical

    traction forces on each rail, commonly

    encountered on bridge-type shiploaders.

    Travel Device Obstructed LLIn AS4324.1, the approach adopted is to

    assume that these loads are generated

    where one side of a travel ling machine

    is suddenly obstructed and brought to

    rest in 300 mm. Consideration of the dy-

    namics of the event, including inertialeffects, is required.

    Boom Collision Loads FS, FTAS4324.1 considers the combined effect

    of both inertia and drive torques for a

    stopping distance of 300 mm. AS4324.1

    includes load cases to address such acci-

    dents for both slewing and non-slewing

    machines. In the latter case, the limiting

    long travel drive force rather than slew

    torque will determine impact loads.

    AS4324.1 includes a longitudinal boom

    impact case, representing the situationfor a slewable boom machine, where the

    impact might occur while the boom is

    facing forward at a shallow angle to the

    long travel direction.

    Buffer Loads OOThe principle adopted is that rail-mount-

    ed machines should be equipped with

    buffers, and that the machine structure

    should be capable of surviving a buffer

    impact situation where the machine

    is driven into the buffers at full long

    travel speed. With this impact case as

    well, both iner tia and drive forces arerequired to be considered concurrently.

    Bucket Wheel Loss BLAS4324.1 a lso includes a requirement to

    design bucket wheel machines for the

    situation following loss of the bucket

    wheel, shaft and associated gearbox

    from the boom, as a result of a bucket

    wheel shaft failure or similar accident.

    Inclusion of this load case was a result of

    several failures of this type.

    Non-Permanent Dynamic Effects DDThis applies to inertia forces due to dy-namic load effects, such as abnormal ac-

    celeration and braking of moving parts

    occurring less than 20,000 times during

    the life of the machine (e.g. emergency

    braking). Allowance needs to be made

    during the design phase for these ef-

    fects. During the commissioning phase,

    care needs to be taken in testing the

    emergency stops on the machine. When

    emergency stopping is via the braking

    system, rather than via controlled elec-

    trical stopping, severe forces can be im-

    parted into the structure if the brakes orrail clamps are not adjusted correctly and

    are applied too quickly following power

    deactivation of the electrical system.

    Burying (ZZ)This load case is for where collapse

    of a stockpile or slippage of the bank

    could cause the reclaiming or excavat-

    ing component of an operating machine

    to become partially or fully buried. The

    Standard allows for the need for any such

    appropriate loading to be addressed in

    the procurement specification and g ivessuggestions on how this may be covered.

    Load combinationsAS4324.1 shows how dif ferent load

    components should be considered in

    combination. These are summarised

    in Table 3.7 of AS4324.1, together with

    safety factors and stability margins.

    Loads are grouped according to their fre-

    quency of occurrence, i.e. main loads,

    additional loads and special loads. The

    frequency of occurrence of these load

    groups are similar to those stated in thecrane standard, AS1418.1 [8].

    Stability against overturningIn order to check safety against over-

    turning, AS43241.1 requires the stabil-

    ity ratio, (Ms/M

    o) to be calculated for the

    prescribed load case combinations. Ms

    is the minimum stabilising moment due

    to the total permanent load referred to

    a possible axis of tipping and Mo is the

    maximum overturning moment due to

    the prescribed load case combination of

    vertical and horizontal non-permanent

    overturning forces referred to the sameaxis of tipping.

    The Standard nominates minimum

    stability ratios against overturning to be

    applied to load case combinations vary-

    ing between 1.5 and 1.1, being higher

    (1.5) for more frequent operational load-

    ing conditions, lower (1.33) for less fre-

    quent operational loading conditions,

    and lower again (1.2 or 1.1) for much less

    frequent abnormal loading conditions.

    Fatigue

    AS4324.1 refers to AS4100 [7] for fatiguedesign. AS4100 reflects current practice

    for the design of welded steel structures

    subject to fatigue loads. There are im-

    portant differences between AS4324.1

    and ISO5049.1. AS4324.1 is prescriptive

    and gives detailed guidance on how to

    calculate the load cases and which load

    combinations to consider. ISO5049.1 uses

    an outdated mean stress approach to

    fatigue design which is not adapted to

    modern standards. It should also be noted

    that structures affected by fatigue must

    be regularly inspected for fatigue damage

    for design code rules such as AS4100 toapply.

    For combining the effects of cyclical

    load components, the AS4324.1 approach

    is to consider the fatigue damage result-

    ing from the cyclical stresses produced by

    each component of the loading spectrum

    and carrying out a cumulative damage

    assessment by miners rule summation.

    AS4100 requires a capacity factor of 0.7 to

    be applied for non-redundant load paths

    and inaccessible areas for inspection.

    Strength assessmentAS4324.1 allows for the use of either thepermissible stress method (also termed

    working stress) to AS3990 [9] or limit

    states method to AS4100 to be used for

    strength design.

    ENGINEERING SERVICES

  • 7/27/2019 56-61_AS432411995 standardSeptOct12

    4/6

    Buckling assessmentAS4324.1 permits buckl ing assessment, either to the limit state

    procedures of AS4100 or to the permissible stress procedures

    of AS3990. This is directly applicable to design of beams and

    columns. Design of plate work structures for the base and oth-

    er major components to resist buckling and to accommodate

    shear lag effects is not well covered in the steel design stand-

    ards AS4100 or AS3990. AS4324.1 covers this to some extent insection 5.4 and Appendix J.

    Machine procurement specificationThe standard method for procuring bulk materials handling

    machines is a design and construct contract with the contrac-

    tor having responsibility for design, manufacture, supply and

    instal lation. The procurement specification needs to be written

    to ensure that the configuration and performance parameters

    upon which the requirements for the machine were determined

    can be met realistically in practice. Appendix B in AS4324.1

    gives guidance on issues which should be covered specifically

    in the purchase specification.

    Design auditAppendix K in AS4324.1 gives guidance for design auditing and

    certification by an independent third party engineering con-

    sultant. This may be by means of independent calculations or

    by checking and reviewing the original design calculations and

    by computer analysis.

    WeighingAS4324.1 requires that after a machine has been constructed,

    the mass and centre of gravity of the machine as built should

    be accurately determined. The final weight of a machine is of-

    ten greater than that advised at the time of tender even when

    the supplier has carried out an upfront concept design phase.

    AS4324.1 stipulates that if the construction mass exceeds themass used in the calculation of static loads by more than five

    percent, the stresses in the machine should be re-checked.

    Experience with AS4324.1 and suggestedchangesThe following section covers some of the areas where the

    authors organisation has found issues in the application of

    AS4324.1 that required resolution. Areas that may need to be

    addressed in revisions to AS4324.1 are also identif ied.

    Fatigue Non-Redundant Load PathsThe requirement in AS4100 to allow for a capacity factor of

    0.7 for non-redundant load paths or for areas which cannot be

    readily inspected has caused difficulties and can be subject toquite different interpretation by different parties. Procurement

    specifications should be specific in this respect to avoid differ-

    ing interpretations.

    Treatment of Burying Load CaseThe burying load case is applicable to reclaimers and particular-

    ly covers the situation where material from the bank or stock-

    pile slumps onto the end of the boom. One way of handling

    this, as suggested in AS4324.1, is to assume that the boom can

    support the full weight of this material. Another way this has

    been handled is to allow the luffing hydraulic system to relieve

    and the boom to be partially supported by the stockpile. Pro-

    curement specifications should be specific in this respect.

    Blocked Chute Flooded BeltThe case of blocked chutes and conveyor-flooded belts happen-

    ing concurrently can be onerous and there is a temptation by

    designers to try to relax requirements to design for a flooded

    ENGINEERING SERVICES

    Our global family of industry-leading power brands, extensive

    application knowledge and award-winning design advantages

    provide proven product performance and reliability. Thousands

    of Altra backstops, couplings, clutches, brakes, torque limiters,

    and belted drives are hard at work in mining applications

    including conveyors, shovels, draglines, ball and sag mills,

    winders and hoists, crushers, compressors, fans, stackers/

    reclaimers, sizers, and vehicles.

    Many major mining equipment OEMs and end users partner

    with Altra to access the latest power transmission technologies.

    www.warnerelectric.com.au

    www.AltraMining.com

    Altra products help keep

    material moving at mines

    throughout Australia

    For the distributor nearest

    you, contact us at:

    (02) 9894-0133

    [email protected]

  • 7/27/2019 56-61_AS432411995 standardSeptOct12

    5/660 Australian Bulk Handling Review: September/October 2012

    belt by measures such as installing a

    profile plate in the feed chute. This ap-

    proach should be treated with caution

    as the machine can easily be modified in

    service to remove the profile plate with-

    out reference to the designer. Similarly,

    designers may tend to rely on blocked

    chute cut-off switches to limit the loadfrom material overflowing from the top

    of a clogged chute. In practice, these

    cut-offs are not instantaneous or may

    malfunction, causing greater loadings

    than assumed.

    Design AuditQualifications of the design audit engi-

    neer and the need to audit mechanical

    and electrical items are not covered in

    AS4324.1. Where the audit engineers

    function is provided as part of the con-

    tract for the machine, the purchase spec-

    ifications should be specific in this re-spect to avoid differing interpretations.

    Boom Collision on Non-SlewingMachinesOn non-slewing machines such as ship-

    loaders and stackers where the boom is

    fixed at right angles to the long travel

    tracks, it is usually not practical to de-

    sign for the boom collision load case

    and it may be necessary to rely on anti-

    collision systems. It is suggested that

    further guidance be given in revisions to

    AS4324.1.

    Travel Device Obstructed On BridgeMachinesOn long span bridge machines such as

    shiploaders and reclaimers it is usually

    not practical to design for the travel de-

    vice-obstructed load case and it is nec-

    essary to rely on anti-collision and skew

    control systems. It is suggested that fur-

    ther guidance be given in revisions to

    AS4324.1.

    Digging Cut-Off Settings and

    Protection SystemsTypically, bucket wheel drives are sized

    to provide sufficient power to dig and

    lift the stockpile material. The drive is

    sized to operate at about 100% of motor-

    rated torque for the majority of its op-

    erating time. During operation the dig-

    ging torque will vary based on a number

    of factors, such as the type of material

    being reclaimed and stockpile slumps.

    The primary and secondary protection

    settings are provided so that the load on

    the machine is not excessive and the ma-

    chine can continue to operate withouttoo many overload stoppages. The nor-

    mal digging resistance (U) is calculated

    based on 1.1 times the first protection

    setting but not less than 1.1 times the mo-

    tor-rated torque. The abnormal digging

    resistance (UU) is calculated based on

    1.1 times the greatest protection setting

    but not less than 1.5 times the motor-rate

    torque. Diversity for protection systems

    is particularly beneficial. For example,

    a protection system implemented using

    one mechanical protective device and

    one electrical protective device has ahigh diversity component.

    Fluid couplings of any type on the

    bucket wheel drive train are not general-

    ly suitable as a torque limiting device for

    normal digging or associated lateral dig-

    ging and it is suggested that the Standard

    be revised so as not to refer to f luid cou-

    plings as a load limiting device.

    Permanent Dynamics DIn general more guidance on the ap-

    plication of permanent dynamic ef-

    fects would be a useful addition to the

    standard.For stability calculations, a uni-

    form dynamic multiplier as adopted in

    AS4324.1 can produce non-conservative

    results. A triangular-distributed accel-

    eration as shown in Figure 2 is more

    appropriate.

    Redundancy of Stays, Ropes andHydraulic CylindersIn cases where an operators cab is lo-

    cated on a boom, there is a requirement

    for the boom support to be redundant,

    with two total ly independent support

    systems. The design of ropes or stays is

    required to consider the dynamic load-

    ing which would occur following failureof one of the support systems. The mag-

    nitude of the dynamic load multiplier

    and the need to have this on top of the

    safety factors is an area which can be

    subject to quite different interpretation

    by different parties. It is suggested that

    further guidance be given in revisions to

    AS4324.1.

    Loss of Bucket WheelThis load case was introduced primarily

    for situations where the bucket wheel is

    on a cantilevered section of shaft. Wherethe bucket wheel is not cantilevered

    but held captive by the boom support

    structure and the discharge/circular

    chute in case of shaft failure, this load

    event may not be applicable. It would be

    appropriate to revise the Standard to re-

    flect this.

    Wind LoadsThe Standard is written with reference

    to the 1989 edition of AS1170.2 and uses

    wind forces for permissible stress de-

    sign, Vp rather than wind forces for ul-timate design Vu. Subsequent editions of

    the wind load standard, AS1170.2 pub-

    lished in 2002 and 2011 only include Vu

    and do not include Vp. specifically. This

    is an area where revision would be ap-

    propriate. It may be necessary to define

    an intermediate wind speed for reloca-

    tion to the storm park position and for

    parking with rail clamps. Care needs to

    be taken in cyclonic areas where wind is

    a controlling load case, as use of permis-

    sible stress design wind speed may be

    non-conservative.

    Plate BucklingThe AS4324.1 assessment method for

    plate bucking can be difficult to apply.

    In practice, plate bucking is generally

    handled by finite element analysis and

    alternative design standards such as

    BS5400 [1] or the Merrison Committee

    recommendations [4] are used. It is sug-

    gested that revisions to AS4324.1 should

    address this.

    Limit States Code Calibration

    Table 3.7 of AS4324.1 gives load multi-plying factors to be used with the limit

    states method to AS4100. Normally, the

    limit states design method uses partial

    load factors vP, which differ for each

    type of load and range generally between

    1.2 and 1.5 depending on the statistical

    variabil ity of the load type. However, for

    AS4324.1 this factor is taken as the same

    for all load components. In AS1418.1 for

    cranes, the standard notes that where

    the limit states design method is used,

    care needs to be taken so that the design

    gives a degree of safety not less than that

    for the permissible stress design methodto AS3990. Such a cautionary note could

    be included in a revision to AS4324.1 in

    the short term. Ultimately a full code

    calibration of the load multipliers should

    be carried out in a similar manner to that

    carried out by Warren et al [11] for crane

    girders.

    ConclusionsAS4324.1 has been in use for over 16 years

    and major machine suppliers and design

    audit engineers operating in Australia

    are now familiar with the document.Since the introduction of AS4324.1, the

    majority of new machines in Australia

    have been subject to a third party de-

    sign audit. Its application in the procure-

    ment of bulk handling equipment for

    Figure 2 - Triangular Distribution of Acceleration.

    ENGINEERING SERVICES

  • 7/27/2019 56-61_AS432411995 standardSeptOct12

    6/6

    Australian ports and mines has genera lly resulted in robust and

    reliable machines which are expected to offer long-term ben-

    efits. Some areas in the Standard have caused issues and pend-

    ing revisions to the Standard, this has generally been covered

    in purchase specifications. Now that most industry participants

    are famil iar with the Standard, revisions would be appropriate as

    part of continuous improvement in the industry.

    References1. British Standards Institute (1982). BS5400: Steel, Concrete

    and Composite Bridges.

    2. German Institute for Standardization (2006), DIN 22261-2

    Excavators, Stackers and Ancil lary Equipment in Brown Coal

    Open Cut Mines Part 2 Calculation Principals

    3. International Organization for Standardization (1994).

    ISO5049.1: Mobile Equipment for the Continuous Handling of

    Bulk Materials Par t 1 Rules for the Design of Steel Structures.

    4. Merrison, A. W., Flint, A. R., Harper, W. J., Horne, M. R. and

    Scruby, G. F. B. (1973). HMSO Merrison Committee Report

    on the Design and Erection of Steel Box Girder Bridges, Par t

    1 to Part 4.

    5. Morgan, R. C. (2011) Design of Materials Handling Machinesto AS4324.1-1995, Australasian Structural Engineering Con-

    ference, Perth, 12 July 2012

    6. Morrison, W. R. B. et al. (1996). A New Australian Standard

    for Continuous Bulk Materials Handling Machines, National

    Conference on Bulk Materials Handling 30 September - 2 Oc-

    tober 1996, Melbourne.

    7. Standards Australia (2008). AS4100: Steel Structures.

    8. Standards Austra lia (2002). AS1418.1: Cranes, hoists and

    winches - General requi rements.

    9. Standards Australia (1993). AS3990: Mechanical Equipment

    Steelwork.

    10. Standards Australia (1995). AS4324.1: Mobile equipment for

    continuous handling of bulk materials Part 1 - General re-quirements for the design of steel structures.

    11. Warren, J. S. et al. (2005). Reliability models of overhead

    traveling crane loading for code calibration, ICOSSAR, Mill-

    press, Rotterdam.

    Every effort has been made to ensure that the information contained in this

    article is correct. However, Aspec Engineering Pty Ltd or its employees take no

    responsibility for any errors, omissions or inaccuracies.

    SGS expands Australianminerals processing facilities

    SGS has expanded its Australian mineral processing test-work facilities, including a new mineral processing labora-tory complex adjacent to its existing Perth operation.

    SGS says the expansion, now completed, will allow it to

    increase its focus from hydrometallurgical testing to include

    services for comminution, flotation, magnetic and gravity sep-

    aration, filtration, thickening and iron ore characterisation.

    The expansion involved:

    A continuous three stage crushing plant with a capacity of

    approximately 3tph.

    A 20m fully instrumented iron ore drop-tower.

    A continuous pilot comminution and flotation plant includ-

    ing conventional, f lash and column f lotation.

    Pilot hi-rate and paste thickening. Pilot fi ltration equipment. Pilot wet magnetic separation equipment (LIMS, REMS,

    WHIMS and Slon).

    Contact: Richard Morgan, [email protected]

    Contact: www.sgs.com

    ENGINEERING SERVICES