5.2 preparation of the inventory for new building ships r2
TRANSCRIPT
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
1/19
for New Buildin Shi s
December 2009
The Shipbuilders Association of Japan
1
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
2/19
Preparation of the Inventory
for New Building Ships
1. Procedure of Inventory Preparation
2. Trial Results of Inventory Preparation
3. Inventory Preparation from now on
2
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
3/19
1. Procedure of Inventory Preparation
(1) Collection of Hazardous Materials Information(2) Check of Hazardous Materials Information
repara on o e nven ory ar
(4) Submission of the Inventory Part I for the Certification
3
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
4/19
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
5/19
(2) Check of Hazardous Materials Information
Because of long period of construction after purchase, following itemsshould be checked at the time of receiving the Materials DeclarationMD and Su liers Declaration of Conformit SDoC .
- SDoC ID No. described in Materials Declaration (MD) coincides
with the ID No. of Suppliers Declaration of Conformity (SDoC).- To check the hazardous materials on the Materials Declaration (MD)
The products containing table A materials over the threshold level are
pro e . xcep on: y roc oro uorocar ons s- All information available to calculate the amount of hazardous.
5
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
6/19
(2) Check of Hazardous Materials Information
6
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
7/19
(3) Preparation of the Inventory Part I
ass ca on o nven oryTo classify the products containing the materials listed in table A andB in three cate ories.
Category Products
1.1 Paints and Coatin S stems Paint used for Shi buildin
1.2 Equipment and Machinery Machinery, equipment, parts, pipes,
electric cables, etc.
1.3 Structure and Hull Construction materials, joiner workssuch as interior walls, floors, etc.
e at on etween t e contents o nventory an ater a s ec arat on(MD) information
, . .
4) To calculate the amount of hazardous materials.
5 The location of hazardous materials on board to be described with the
7name of location used in General Arrangement, MachineryArrangement, Cabin Plans, etc.
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
8/19
(3) Preparation of the Inventory Part I
(A),(B) Copy
(C) Calculate quantitya n name norma y use
(E) Location onthe ship
8(F) Number
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
9/19
(4) Submission of the Inventory Part I
or e er ca onShipbuilders prepare the Inventory Part I based on Materials
ec ara on rom pro uc s supp ers, an su m o e agadministration or Recognized Organizations (RO) to get certification.
Shi builders rovide on board with the International Certificate onInventory of Hazardous Materials together with the Inventory Part I.
Drawings and documents requested for verifying the Inventory;- Materials Declaration (MD)
- Suppliers Declaration of Conformity (SDoC)
- Reference drawings (General Arrangement, Machinery, .
- Other drawings or documents requested by the flag administrationor Reco nized Or anizations RO
9
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
10/19
2. Trial Results of Inventory Preparation
The Shipbuilders Association of Japan (SAJ) conducted trials forInventory preparation two times according to the drafts of the
onven on an u e ne.
First time: from Oct. 2007 to Feb. 2008 , .
Second time: from Jan. 2009 to Dec.2009 (currently ongoing)Inventory of 10 vessels prepared by using the PrimeShip-
INVENTORY (NK software)
Rate of Materials declaration MDobtained
First time: 75 to 85% Second time: 80 to 99%Problem: Materials declaration MDand Suppliers Declaration of
Conformity (SDoC) were found not correctly described.
10Following points are important check points of MD and SDoC fromthe trial results.
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
11/19
(1) Preparation of MD and SDoC
Shipbuilders should obtain the Materials Declaration (MD) andSuppliers Declaration of Conformity (SDoC) from productssu liers.
Supplier: A company such as manufacturer, trader or agency who
provides products and has responsibility for the productsater a s ec arat on :
Document identifying whether the material contained in table A
(specific chemical substance) designated in accordance with theConvention and Guidelines
The document assuring that the product and its related MD conforms
to the law and is suitable for the management and control of then ormat on on c em ca su stances conta ne , an w o sresponsible for the product and MD
11
existence of materials listed in table A and table B.
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
12/19
(2) Description in Materials Declaration (MD)
One MD should be prepared for one product in principle.Attention to be paid:
- o escr e t e o o.
- To specify the content of the hazardous materials (HM) in case ofexceedin the threshold level.
- To be able to calculate the total amount of the HM.
- To enter No for materials not exceeding the threshold level.
Threshold level means the concentration value in homogeneousmaterials (mg/kg).
, ,theoretical, controlled or measured figures.
- In case the same material is contained in many parts or portions,suc names o e par s or por ons o e escr e .
In case the parts of product contain the HM above the threshold
12
,
of the parts should be prepared separately.
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
13/19
(2) Description in Materials Declaration (MD)
Homogeneous materialsElectric cable: Sheath, intervention, insulator and conductor are all
n v ua omogeneous ma er a s.
Platin : Base metal and latin la er to be treated as not mechanicallseparable.(Base metal and plating layer consist of one homogeneous material.)
13
a n : a n se cons s s o one omogeneous ma er a .
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
14/19
(3) Object of MD Investigation
Materials Declarations (MDs) should be collected for all the productsthat consist of hull, machinery, equipment and material.
- Materials listed in table B that are inherent in solid metals or metal
allo s, rovided the are used in eneral construction, such as hull,superstructure, pipes, or equipment.
For example:
Hull construction, superstructure and other structure such as rudderplate
, ,stainless steel
Lar e fittin s such as masts tanks etc.However, MD should be obtained in case the above steel plates andpipes being coated or plated.
14
- Products listed in table C and table D
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
15/19
(3) Object of MD Investigation
Relation between Table A, B, C and DProducts (hull, machinery, equipment, Products loaded
Table D
MD InvestigationTable C
Potentially
Regular
consumableProduct(Investigate contained materials
listed in Table A and B)
azar ous
Items
goo s
potentially
containing
MD Investigation not to be required
Materials listed in Table B that are
Hazardous
Materials
n eren n so me a s or me a a oys,
provided they are used in general
construction, such as hull, superstructure,
pipes, or equipment.
Table A Controls of Hazardous Materials
(Appendix 1 of the Annex to the Convention)Material
15
.
(Appendix 2 of the Annex to the Convention)
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
16/19
(3) Object of MD Investigation
: o en a y azar ous emsThe products listed in table C are those which are loaded on board andthe amount changes during the ship operation.To be listed in the Inventory Part II or Part III before the ship
recycling as waste generating during operation.Table D: Regular consumable goods potentially containing Hazardous
Materials
Inventory Part III.Example for items requiring MD:- nter or uorescent amp oc et requ re
Lamp MD not required
- Refri erator Lar e refri erator on the market MD not re uiredRefrigerator composed of part of MD requiredhull construction
16
s ou e co ec e n genera , n case s no c ear w e er
MD is required or not.
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
17/19
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
18/19
3. Inventory Preparation from now on
At the earliest case, the Convention may enter into force in 2012.New building ships before entry into force will be treated as existing
s ps accor ng to t e onvent on.
18
-
8/6/2019 5.2 Preparation of the Inventory for New Building Ships R2
19/19
Proposal from Japan
Japan had some trials for development of inventory of hazardous
ma er a s or new y- u s ps.
To avoid potential confusion after the Convention entry into force,
a discussion among experts is needed to develop a manual.
y on we ave a vo un ary scuss on
Japan is ready for coordinating the discussion.
Those who are interested, please e-mail to
19