http://slidepdf.com/reader/full/5-x-8-flashcards 1/37
4.0 Integration 5.0 Scope 6.0 Time
4.1 Develop Project Charter
4.2 Develop PreliminaryScope Statement
4.3 Develop Project
Management Plan
4.4 Direct and Manage
Project Execution
4.5 Monitor and Control
Project Work
4.6 Integrated Change
Control
4.7 Close Project
5.1 Scope Planning
5.2 Scope Definition
5.3 Create WBS
5.4 Scope Verification
5.5 Scope Change Control
6.1 Activity Definition
6.2 Activity Sequencing
6.3 Activity Resource
Estimating
6.4 Activity Duration
Estimating
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 2/37
7.0 Cost 8.0 Quality 9.0 Human
Resources
7.1 Cost Estimation
7.2 Cost Budgeting
7.3 Cost Control
8.1 Quality Planning
8.2 Perform Quality
Assurance
8.3 Perform Quality Control
9.1 Human ResourcesPlanning
9.2 Acquire Project Team
9.3 Develop Project Tea
9.4 Manage Project Team
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 3/37
10.0Communication
11.0 Risk 12.0 Procurem
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 4/37
10.1 Communication
Planning
10.2 Information
Distribution
10.3 Performance Reporting
10.4 Manage Stakeholders
11.1 Risk Management
Planning
11.2 Risk Identification
11.3 Qualitative Risk
Analysis
11.4 Quantitative Risk
Analysis
11.5 Risk Response Planning
11.6 Risk Monitoring &
Controlling
12.1 Plan Purchases &
Acquisitions
12.2 Plan Contracting
12.3 Request Seller
Responses
12.4 Select Sellers
12.5 Contract Administr
12.6 Contract Closure
4.1 Develop Project Charter
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 5/37
Knowledge Area: Integration
Process Group: Initiating
* Process necessary for documenting thebusiness needs & requirements* PC links to ongoing work of the organizatand authorize the project* Project is charted by org or program or
portfolio bodyInputs Tools & Techniques Outputs1. Contract
2. SOW (includes businessneed, scope description,
strategic plan)3. Enterprise environmental
factors
4. Organizational processassets (templates,
procedures)
1. Project selection methods
2. Project managementmethodology
3. Project managementinformation system
4. Expert judgment
1. Project Charter
4.2 Develop Preliminary Project Scope StatementKnowledge Area: Integration
Process Group: Initiating
* Produces preliminary high level definitionthe project* contains deliverable requirements, produc
requirements, boundaries of the project,methods of acceptance and high level scope
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 6/37
control
Inputs Tools & Techniques Outputs
1. Project Charter2. Statement Of Work
(SOW)3. Enterprise environmental
factors4. Organizational process
Assets
1. Project managementmethodology
2. Project managementinformation system
3. Expert judgment
1. Prelimnary Project ScStatement
4.3 Develop Project Management PlanKnowledge Area: IntegrationProcess Group: Planning
* Process for defining, prepating, integratin
and coordinating all subsidiary plans into aproject management plan* Project mgmt plan becomes primary scouof info for how the project will be planned,executed, monitored and controlled and clo
Inputs Tools & Techniques Outputs1. Preliminary project scope
statement
2. Project managementprocesses
1. Project management
methodology
2. Project managementinformation system
1. Project management
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 7/37
3. Enterprise environmental
factors4. Organizational process
Assets
(configuration management
system, change controlsystem)
3. Expert judgment
4.4 Direct and Manage Project ExecutionKnowledge Area: Integration
Process Group: Executing
* Process for directing technical & org interto work defined in project management pla* Deliverables are outputs of processes defin project management plan* Deliverable status and work performed isfurther used as input to performance reportprocess
Inputs Tools & Techniques Outputs1. Project management plan
2. Approved correctiveactions
3. Approved preventiveactions
4. Approved changerequests
5. Approved defect repair6. Validated defect repair
1. Project management
methodology2. Project management
information system
1. Deliverables
2. Requested changes3. Implemented change
requests4. Implemented correcti
actions5. Implemented prevent
actions6. Implemented defect
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 8/37
7. Administrative closure
procedure
repair
7. Work performanceinformation (status, bud
% complete)
4.5 Monitor and Control Project WorkKnowledge Area: Integration
Process Group: Monitoring andControlling
* Process for collecting, measuring anddisseminating performance information andassessing measurements and trends to effeprocess improvements* Process includes risk monitoring (identifystatus reporting risk plan executing)* Also includes status reporting, progress
measurement and forecasting* performance reporting with regards to scoschedule, cost, resources, quality and risk
Inputs Tools & Techniques Outputs
1. Project management plan2. Work performance
information3. Rejected change requests
1. Project managementmethodology
2. Project managementinformation system
3. Earned valuemanagement
1. Recommended correcactions
2. Recommended preveactions
3. Forecasts4. Recommended defect
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 9/37
4. Expert judgment repair
5. Requested changes
4.6 Integrated Change ControlKnowledge Area: Integration
Process Group: Monitoring andControlling
* Process for controlling factors that create
changes, determining wether change hasoccured and measuring approved changes.* This process is performed throught theproject.(intiating to closure)
Inputs Tools & Techniques Outputs
1. Project management plan2. Requested changes
3. Work performance
information4. Recommended preventive
actions5. Recommended corrective
actions6. Recommended defect
repair7. Deliverables
1. Project managementmethodology
2. Project management
information system3. Expert judgment
1. Approved changerequests
2. Rejected change requ
3. Project management (updates)
4. Project scopemanagement (updates)
5. Approved correctiveactions
6. Approved preventiveactions
7. Approved defect repa8. Validated defect repa
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 10/37
9. Deliverables
4.7 Close ProjectKnowledge Area: IntegrationProcess Group: Closing
* Process to finalize all activities across all oprocess groups to formally close the project
phaseInputs Tools & Techniques Outputs
1. Project management plan2. Contract documentation
3. Enterprise environmentalfactors
4. Organizational processassets
5. Work performanceinformation
6. Deliverables
1. Project managementmethodology
2. Project managementinformation system
3. Expert judgment
1. Administrative closurprocedure
2. Contract closureprocedure
3. Final product, serviceresult
4. Organizational procesassets (updates)
(acceptance doc, projec
files, closure doc, historinfo update)
5.1 Scope PlanningKnowledge Area: Scope
Process Group: Planning
* Process necessory for creating a project s
management plan.* It documents how scope will be defined,
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 11/37
verified and controlled and how WBS will becreated and defined
Inputs Tools & Techniques Outputs
1. Enterprise environmentalfactors
2. Organizational processassets
3. Project Charter4. Preliminary project scope
statement5. Project management plan
1. Expert judgment2. Templates, forms,
standards (WBS templates,scope management plan
templates, project scopecontrol forms)
1. Project scopemanagement plan
5.2 Scope DefinitionKnowledge Area: ScopeProcess Group: Planning
* Process for developing detailed project scstatement as the basis for future projectdecisions
Inputs Tools & Techniques Outputs1. Organizational process
assets2. Project charter
3. Preliminary project scopestatement
4. Project scope
1. Product analysis [Value
Analysis]2. Alternative identification
(brainstorming & lateralthinking)
3. Expert judgment (SME)
1. Project Scope Statem
2. Requested changes3. Project scope
management plan (upda(include approved chang
requests)
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 12/37
management plan
5. Approved changerequests
2. Stakeholder analysis
5.3 Create WBS
Knowledge Area: ScopeProcess Group: Planning
* Process for subdividing the major projectdeliverables and project work into smaller, manageable components (work packages)
Inputs Tools & Techniques Outputs
1. Organizational processassets
2. Project scope statement3. Project scope
management plan4. Approved change
requests
1. WBS templates2. Decomposition
1. Project scope stateme(updates) (approved cha
requests)2. WBS
3. WBS dicitionary4. Scope baseline
5. Project scope
management plan (upda(approved change reque
6. Requested changes
5.4 Scope Verification
Knowledge Area: ScopeProcess Group: Monitoring and
* Process for formalizing acceptance of thecomplete project deliverables
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 13/37
Controlling
Inputs Tools & Techniques Outputs
1. Project scope statement2. WBS directory
3. Project scope mgmt plan4. Deliverables
1. Inspection 1. Accepted deliverables(supporting documents
acknowledgement)2. Requested changes
3. Recommended correcactions
5.5 Scope Change ControlKnowledge Area: ScopeProcess Group: Monitoring andControlling
* Process for controlling changes to the proscope
Inputs Tools & Techniques Outputs
1. Project scope statement2. WBS
3. WBS dictionary4. Project scope
management plan
5. Performance reports6. Approved change
1. Change control system2. Variance analysis
3. Replanning4. Configuration
management system
1. Project scope stateme(updates)
2. WBS (updates)3. WBS dictionary (upda
4. Scope baseline (upda
5. Requested changes6. Recommended correc
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 14/37
requests
7. Work performanceinformation
action
7. Organizational procesassets (updates) (varian
learnings & lessons lear
8. Project management(updates)
6.1 Activity DefinitionKnowledge Area: Time
Process Group: Planning
* Process for identifying the specific activitithat need to be performed to produce thevarious project deliverables
Inputs Tools & Techniques Outputs1. Enterprise environmental
factors2. Organizational process
assets
3. Project scope statement4. WBS
5. WBS dictionary
6. Project management plan
1. Decomposition
(Work package --> scheduleactivities)
2. Templates
3. Rolling wave planning4. Expert judgement
5. Planning component
1. Activity list
2. Activity attributes3. Milestone list
4. Requested changes
6.2 Activity Sequencing
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 15/37
Knowledge Area: Time
Process Group: Planning
* Process for identifying and documenting lrelationships among schedule activities andlogically sequencing them accordingly
Inputs Tools & Techniques Outputs
1. Project scope statement
2. Activity list3. Activity attributes
4. Milestone list5. Approved change
requests
1. Precedence diagramming
method (PDM)2. Arrow diagramming
method (ADM)3. Schedule network
templates
4. Dependencydetermination
5. Applying leads & lags
1. Project schedule netw
diagrams2. Activity list (updates)
3. Activity attributes(updates)
4. Requested changes
6.3 Activity Resources EstimatingKnowledge Area: Time
Process Group: Planning
* Process for estimating the type and quantof resources required to perform each scheactivity
Inputs Tools & Techniques Outputs
1. Enterprise environmentalfactors
2. Organizational processassets
1. Expert judgment2. Alternate analysis (make-
or-buy decision,automation)
1. Activity resourcerequirements
2. Activity attributes(updates)
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 16/37
3. Activity list
4. Activity attributes5. Resource availability
6. Project management plan
3. Published estimating data
(rates & cost data)4. Project management
software
5. Bottom-up estimating
3. Resource breakdown
structure4. Resource calendars
(updates)
5. Requested changes
6.4 Activity Duration EstimatingKnowledge Area: Time
Process Group: Planning
* Process for estimating the number of worperiods that will be needed to completeindividual schedule activities
Inputs Tools & Techniques Outputs
1. Enterprise environmentalfactors
2. Organizational processassets
3. Project scope statement
4. Activity list5. Activity attributes
6. Activity resource
requirements7. Resource calendars
8. Project management plan(Risk register, Activity cost
1. Expert judgment2. Analogous estimating
3. Parametric estimating4. Three point estimating
5. Reserve analysis
1. Activity durationestimates
2. Activity attributes(updates)
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 17/37
estimates)
6.5 Schedule DevelopmentKnowledge Area: TimeProcess Group: Planning
* Iterative process and determines plannedand finish dates for the project activities
Inputs Tools & Techniques Outputs1. Organizational process
assets2. Project scope statement
(imposed dates & imposedmilestones by sponsor)
3. Activity list4. Activity attributes
5. Project schedule networkdiagrams
6. Activity resourcerequirements
7. Resource calendars8. Activity duration
estimates
1. Schedule network
analysis2. Critical path method
3. Schedule compression(crashing, fast-tracking)
4. What-if scenario analysis5. Resource leveling
6. Critical chain method7. Project management
software8. Applying calendars
9. Adjust leads & lags10. Schedule model
1. Project schedule
2. Schedule model data3. Schedule baseline
4. Resource requiremen(updates)
5. Activity attributes(updates)
6. Project calendar(updates)
7. Requested changes8. Project management
(updates, including schemanagement plan)
6.6 Schedule Control
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 18/37
Knowledge Area: Time
Process Group: Monitoring andControlling
* Process for controlling changes to projectschedule
Inputs Tools & Techniques Outputs
1. Schedule managementplan
2. Schedule baseline3. Performance reports
4. Approved change
requests
1. Progress reporting2. Schedule change control
system3. Performance
measurement
4. Project managementsoftware
5. Variance analysis
6. schedule comparison barcharts
1. Schedule model data(updates)
2. Schedule baseline(updates)
3. Performance
measurements4. Requested changes
5. Recommended correc
actions6. Organizational procesAssets
7. Activity list (updates)8. Activity attributes
(updates)9. Project management
(updates)
7.1 Cost Estimation
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 19/37
Knowledge Area: Cost
Process Group: Planning
* Process for developing an approximation the costs of the resources needed to complproject activities
Inputs Tools & Techniques Outputs
1. Enterprise environmental
factors2. Organizational process
Assets3. Project scope statement
4. WBS
5. WBS dictionary6. Project management plan
(schedule mgmt plan & staffing mgmt plan, risk
register)
1. Analogous estimating
2. Determine resource costrates
3. Bottom-up estimating4. Parametric estimating
5. Project management
software6. Vendor bid analysis
7. Reserve analysis8. Cost of quality
1. Activity cost estimate
2. Activity cost estimatesupporting detail
(description, basis of estimate, constraint, RO
3. Requested changes
4. Cost management pla(updates)
7.2 Cost BudgetingKnowledge Area: Cost
Process Group: Planning
* Process for aggregating the estimated cosindividual activities or work packages toestablish a cost baseline
Inputs Tools & Techniques Outputs
1. Project Scope Statement2. WBS
1. Cost aggregation2. Reserve Analysis
1. Cost baseline2. Project funding
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 20/37
3. WBS Dictionary
4. Activity cost estimates5. Activity cost estimate
supporting detail
6. Project schedule
7. Resource calendars8. Contract9. Cost management plan
3. Parametric estimating
4. Funding limitreconcillation
requirements
3. Cost management pla(updates)
4. Requested changes
7.3 Cost ControlKnowledge Area: Cost
Process Group: Monitoring andControlling
* Process for infleuncing the factors that crvariances and controlling changes to the prbudget
Inputs Tools & Techniques Outputs1. Cost baseline
2. Project fundingrequirements
3. Performance reports
4. Work performanceinformation
5. Approved changerequests
1. Cost change control
system2. Performance
measurement analysis
3. Forecasting4. Project performance
reviews5. Project management
1. Cost estimate (update
2. Cost baseline (update3. Performance
measurements
4. Forecasted completio5. Requested changes
6. Recommended correcactions
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 21/37
6. Project management plan software
6. Variance management
7. Organizational proces
assets (updates)8. Project management
(updates)
8.1 Quality PlanningKnowledge Area: Quality
Process Group: Planning
* Process for identifying which quality standare relevent to the project and determiningto satisfy them
Inputs Tools & Techniques Outputs1. Enterprise environmental
factors (govt regulations,standards)
2. Organizational processAssets (Quality policies,
historical database, lessons
learned)3. Project scope statement
4. Project management plan
1. Cost benefit analysis
2. Benchmarking3. Design of
experiments[TaguchiMethod]
4. Cost of Quality (COQ)
5. Additional qualityplanning tools
1. Quality management
2. Quality metrics3. Quality checklists
4. Process improvementplan(steps to analyze
processes to identify wa
& non-value added item5. Quality baseline
6. Project management
(updates)
8.2 Perform Quality Assurance
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 22/37
Knowledge Area: Quality
Process Group: Executing
* Process for applying the planned, systemquality activities to ensure that the projectemploys all processes needed to meetrequirements
Inputs Tools & Techniques Outputs
1. Quality management plan2. Quality metrics3. Process improvement
plan4. Work performance
information5. Approved change
requests
6. Quality controlmeasurements7. Implemented change
requests8. Implemented corrective
actions9. Implemented defect
repair10. Implemented preventive
1. Quality planning tools andtechniques2. Quality audits
3. Process analysis4. Quality control tools and
techniques
1. Requested changes2. Recommended correcactions
3. Organizational procesassets (updates)
4. Project management (updates)
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 23/37
actions
8.3 Perform Quality ControlKnowledge Area: QualityProcess Group: Monitoring and
Controlling
* Process for monitoring specific project resto determine whether they comply with relequality standards and identifying ways toeliminate causes of unsatisfactory performa
Inputs Tools & Techniques Outputs1. Quality management plan
2. Quality metrics3. Quality checklists
4. Organizational processassets
5. Work performanceinformation
6. Approved changerequests
7. Deliverables
1. Cause and effect diagram
2. Control charts3. Flowcharting
4. Histogram5. Pareto chart
6. Run chart7. Scatter diagram
8. Statistical sampling9. Inspection
10. Defect repair review
1. Quality control
measurements2. Validated defect repa
3. Quality baseline (upd4. Recommended correc
actions5. Recommended preve
actions6. Requested changes
7. Recommended defectrepair
8. Organizational procesAssets
9. Validated deliverables10. Project managemen
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 24/37
plan (updates) (complet
checklists, lessons learn
9.1 Human Resource PlanningKnowledge Area: Human Resource
Process Group: Planning
* Process for identifying and documentingproject roles, responsibilities and reportingrelationships as well as creating the staffingmanagement plan
Inputs Tools & Techniques Outputs
1. Enterprise environmentalfactors (organizational,
technical, interpersonal,logistical, political)
2. Organizational processassets (templates,
checklists)3.Project management plan
(activity resourcerequirements)
1. Organization charts andposition descriptions[RAM
Using RACI]2. Networking
3. Organizational theory
1. Roles and responsibil(role, authority,
responsibility, competenrequired)
2. Project organizationcharts
3. Staffing managementplan
9.2 Acquire Project Team
Knowledge Area: Human ResourceProcess Group: Executing* Process for obtaining the human resourceneeded to complete the project
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 25/37
Inputs Tools & Techniques Outputs
1. Enterprise environmentalfactors(Availability, ability,
experience, interest, cost)
2. Organizational process
assets3. Roles and responsibilities4. Project organization
charts5. Staffing management
plan
1. Pre-assignment2. Negotiation
3. Acquisition
4. Virtual teams
1. Project staff assignme2. Resource availability
3. Staffing management
plan (updates)
9.3 Develop Project TeamKnowledge Area: Human ResourceProcess Group: Executing
* Process for improving the competencies ainteraction of team members to enhace properformance
Inputs Tools & Techniques Outputs1. Project staff assignments
2. Staffing management
plan3. Resource availability
1. General management
skills (interpersonal skills)
2. Training3. Team-building activities
4. Ground rules5. Co-location[War Room]
1. Team performance
assessment (includes i.
improvements in skills findividuals ii. improvem
in competencies for thegroup as a whole iii. red
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 26/37
6. Recognition and rewards staff turnover rate)
9.4 Manage Project TeamKnowledge Area: Human ResourceProcess Group: Monitoring and
Controlling
* Process for tracking team memberperformance, providing feedback, resolvingissues and coordinating changes to enhanceproject performance
Inputs Tools & Techniques Outputs1. Organizational process
assets2. Project staff assignments
3. Roles and responsibilities4. Project organizational
charts5. Staffing management
plan6. Team performance
assessment7. Work performance
information8. Performance reports
1. Observation and
conversation2. Project performance
appraisals3. Conflict management
4. Issue log
1. Requested changes
2. Recommended correcactions
3. Recommended preveactions
4. Organizational procesAssets (updates)
5. Project management (updates)
10.1 Communication Planning
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 27/37
Knowledge Area: Communication
Process Group: Planning
* Process for determining the info andcommunication needs of the projectstakeholders
Inputs Tools & Techniques Outputs
1. Enterprise environmental
factors2. Organizational process
assets3. Project scope statement
4. Project management plan
(Constraints & assumptions)
1. Communications
requirements analysis2. Communications
technology
1. Communication
management plan[provides:
(i)stakeholder requirem(ii)info to be communica
(iii)responsibility
(iv)methods(v) escalation
(vi)updating]
10.2 Information DistributionKnowledge Area: Communication
Process Group: Executing
* Process for making information available project stakeholders in a timely manner
Inputs Tools & Techniques Outputs1. Communications
management plan
1. Communications skills
2. Information gatheringand retrieval system
3. Information distribution
1. Organizational proces
assets (updates)2. Requested changes
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 28/37
methods
4. Lessons learned process
10.3 Performance ReportingKnowledge Area: Communication
Process Group: Monitoring andControlling
* Process for collecting and distributingperformance information* Includes status reporting, progressmeasurement and forecasting
Inputs Tools & Techniques Outputs
1. Work performanceinformation
2. Performancemeasurements
3. Forecasted completion4. Quality control
measurements5. Project management plan
(performance measurementbaseline)
6. Approved changerequests
7. Deliverables
1. Information presentationtools
2. Performance informationgathering and compilation
3. Status review meetings4. Time reporting systems
5. Cost reporting systems
1. Performance reports2. Forecasts
3. Requested changes4. Recommended correc
actions5. Organizational proces
assets (updates)
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 29/37
10.4 Manage StakeholdersKnowledge Area: CommunicationProcess Group: Monitoring and
Controlling
* Process for managing communications tosatisfy the requirements of and resolve issuwith project stakeholders
Inputs Tools & Techniques Outputs1. Communicationsmanagement plan
2. Organizational processassets
1. Communication methods2. Issue logs
1. Resolved issues2. Approved change
requests3. Approved corrective
actions4. Organizational proces
assets (updates)
5. Project management (updates)
11.1 Risk Management PlanningKnowledge Area: RiskProcess Group: Planning
* Process for deciding how to approach, plaand execute the risk management activitiesproject
Inputs Tools & Techniques Outputs
1. Enterprise environmentalfactors
1. Project meetings andanalysis
1. Risk management pla
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 30/37
2. Organizational process
assets3. Project scope statement
4. Project management plan
11.2 Risk IdentificationKnowledge Area: Risk
Process Group: Planning
* Process for determining which risks mightaffect the project and documenting theircharacteristics
Inputs Tools & Techniques Outputs1. Enterprise environmental
factors2. Organizational process
assets3. Project scope statement
4. Risk management plan
5. Project management plan
1. Documentation reviews
2. Information gatheringtechniques
3. Checklist analysis4. Assumptions analysis
5. Diagramming techniques
1. Risk register (include
of risks, potential responroot causes, and update
risk categories)
11.3 Qualitative Risk AnalysisKnowledge Area: Risk
Process Group: Planning
* Process for prioratizing risks for subsequefurther analysis or action by assessing andcombining their probability of occurance an
impact* SUBJECTIVE analysis
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 31/37
Inputs Tools & Techniques Outputs
1. Organizational processassets
2. Project scope statement
3. Risk management plan
4. Risk register
1. Risk probability andimpact assessment
2. Probability and impact
matrix
3. Risk data qualityassessment4. Risk categorization
5. Risk urgency assessment
1. Risk register (updates
11.4 Quantitative Risk AnalysisKnowledge Area: Risk
Process Group: Planning
* Process for numerically analysing the effeoverall project objectives of indentified risk
* Objective or Numerical analysisInputs Tools & Techniques Outputs
1. Organizational process
assets2. Project scope statement
3. Risk management plan
4. Risk register5. Project management plan
(project schedule,management plan, project
1. Data gathering and
presentation techniquesA)Interviewing B) Probability
Distribution C) Expert
Judgement2. Quantitative risk analysis
and modeling techniques
1. Risk register(updates
includes1)probabilistic analysis o
project for schedule & co
outcomes 2)prioritized lquantified risks 3)trends
quantitative risk results
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 32/37
cost mgmt plan)
11.5 Risk Response PlanningKnowledge Area: RiskProcess Group: Planning
* Process for developing options and actionenhance opportunities and to reduce threatproject objectives
Inputs Tools & Techniques Outputs1. Risk management plan2. Risk register
1. Strategies for negativerisks or threats
2. Strategies for positiverisks or opportunities
3. Strategy for both threatsand opportunities
4. Contingency responsestrategy
1. Risk register(updates2. Project management
plan(updates)3. Risk-related contractu
agreements
11.6 Risk Monitoring and ControllingKnowledge Area: RiskProcess Group: Monitoring and
Controlling
* Process for tracking identified risks,monitoring residual risks, identifying new riexecuting risk response plans, and evaluatitheir effectiveness throughout the project licycle
Inputs Tools & Techniques Outputs1. Risk management plan 1. Risk reassessment 1. Risk register (updates
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 33/37
2. Risk register
3. Approved changerequests
4. Work performance
information
5. Performance reports
2. Risk audits
3. Variance and trendanalysis
4. Technical performance
measurement
5. Reserve analysis6. Status meetings
2. Requested changes
3. Recommended correcactions
4. Recommended preve
actions
5. Organizational procesassets (updates)6. Project management
(updates)
12.1 Plan Purchases and AcquisitionsKnowledge Area: Procurement
Process Group: Planning
* Process for determining what to purchaseacquire, and determining when and how
Inputs Tools & Techniques Outputs1. Enterprise environmental
factors2. Organizational process
assets3. Project scope statement
4. WBS
5. WBS dictionary6. Project management plan
1. Make-or-buy analysis
2. Expert judgment3. Contract types
1. Procurement
management plan2. Contract SOW
3. Make or buy decision4. Requested changes
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 34/37
* Risk regiter
* Risk relatedcontractual agreements
* Resouce
requirements
* Project schedule* Activity cost
estimates
12.2 Plan ContractingKnowledge Area: Procurement
Process Group: Planning
* Process for documenting proucts, serviceresults requirements and identifying potentsellers
Inputs Tools & Techniques Outputs1. Procurement
management plan
2. Contract statement of work
3. Make or buy decisions
4. Project management plan* Risk register
* Risk relatedcontractual agreements
1. Standard forms
2. Expert judgment
1. Procurement docume
2. Evaluation criteria (ca
include cost, technicalcapability, financial capa
business type, reference
etc…)3. Contract SOW (updat
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 35/37
* Resouce
requirements* Project schedule
* Activi
12.3 Request Seller ResponseKnowledge Area: Procurement
Process Group: Executing
* Process for obtaining information, quotatibids, offers or proposals as appropriate
Inputs Tools & Techniques Outputs
1. Organizational processassets
2. Procurementmanagement plan
3. Procurement documents
1. Bidder conferences2. Advertising
3. Develop qualified sellerslist
1. Qualified sellers list2. Procurement docume
package3. Proposals
12.4 Select SellerKnowledge Area: ProcurementProcess Group: Executing
* Process for reviewing offers, choosing froamong potential sellers and negotiating awritten contact with the seller
Inputs Tools & Techniques Outputs
1. Organizational process
assets2. Procurement
1. Weighting system
2. Independent estimates[Should-cost]
1. Selected sellers
2. Contract3. Contract managemen
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 36/37
management plan
3. Evaluation criteria4. Procurement document
package
5. Proposals
6. Qualified sellers list7. Project management plan(risk register, risk-related
contractual agreements)
3. Screening system
4. Contract negotitaion5. Seller rating system
6. Expert judgement
7.Proposal evaluation
techniques
plan
4. Resource availability5. Procurement
management plan (upda
6. Requested changes
12.5 Contract AdministrationKnowledge Area: Procurement
Process Group: Monitoring and
Controlling
* Process for managing contract & relationsbetween buyer and seller, reviewing and
documenting how a seller is performing andmanaging contactual relationship * IdentifyTriggers
Inputs Tools & Techniques Outputs
1. Contract2. Contract management
plan3. Selected sellers
4. Performance reports5. Approved change
1. Contract change controlsystem
2. Buyer conductedperformance review
3. Inspections and audits4. Performance reporting
1. Contract documentat2. Requested changes
3. Recommended correcactions
4. Organizational procesassets (updates)
8/8/2019 5 x 8 Flashcards
http://slidepdf.com/reader/full/5-x-8-flashcards 37/37
requests
6. Work performanceinformation
5. Payment system
6. Claims administration7. Records management
system
8. Information technology
5. Project management
(updates)(procurementmgmt plan & contract m
plan)
12.6 Contract ClosureKnowledge Area: Procurement
Process Group: Closing
* Process for completing and settling eachcontract, including resolution of any open itand closing each contract applicable
Inputs Tools & Techniques Outputs
1. Procurementmanagement plan
2. Contract managementplan
3. Contract documentation
4. Contract closureprocedure
1. Procurement audits2. Records management
system
1. Closed contracts2. Organizational proces
assets (update contract deliverable acceptance,
lessons learned