49453-001: south tarawa water supply project...melad ministry of environment, lands and agricultural...
TRANSCRIPT
Environmental Impact Assessment Report
February 2018
KIR: South Tarawa Water Supply Project
Prepared by Ministry of Infrastructure and Sustainable Energy for the Asian Development Bank.
This environmental impact assessment report is a document of the borrower. The views
expressed herein do not necessarily represent those of ADB's Board of Directors, Management,
or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making
any designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
February 2018
Kiribati: South Tarawa Water Supply
Project
Environmental Impact Assessment
Report*
* This environmental impact assessment (EIA) report complies with the country safeguard
system requirements of Kiribati with additional elements as required to also comply with the
safeguard requirements of the Asian Development Bank and World Bank. This report does not
constitute an EIA for category A projects as per the ADB Safeguard Policy Statement 2009 or
World Bank OP 4.01. For this project the EIA is an assessment commensurate with the risks and
impacts of a category B project.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | ii
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | i
Table of Contents
EXECUTIVE SUMMARY
ABBREVIATIONS
1. INTRODUCTION 1
2. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK 3
2.1 Kiribati Constitution and Environment Act 3
2.2 Other Relevant Legislation 3
2.3 Administrative framework for safeguards implementation 4
2.4 Develop e t Pa t e s’ Safegua d Re ui e e ts 5
3. DESCRIPTION OF THE PROJECT 8
3.1 Need for the Project 8
3.2 Project Components 11
3.3 Proposed Implementation Schedule and Workforce Component 21
4. DESCRIPTION OF THE ENVIRONMENT 26
4.1 Physical Environment 26
4.2 Biological Environment 29
4.3 Socio-Economic Environment 36
5. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 40
5.1 Design and Pre-construction phase 40
5.2 Construction Phase 44
5.3 Operation Impacts 52
5.4 Positive Impact on Health 58
5.5 Cumulative Effects 58
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | ii
6. ANALYSIS OF ALTERNATIVES 59
6.1 Alternative to the SWRO 59
6.2 Alternative Location of Desalination Plant and Brine Disposal 59
6.3 Alternative to Desalination Design 61
6.4 Alternative to Feed-water Sources 61
6.5 Alternative to Brine Delivery Pipeline 62
6.6 Location Alternatives for PV Solar System 63
6.7 The No Project Alternative 63
7. INFORMATION DISCLOSURE, CONSULTATION, AND GRIEVANCE REDRESS 64
7.1 Public Consultations 64
7.2 Summary of Issues Raised 64
7.3 Means of Addressing Issues Raised 66
7.4 Consultation and Disclosure during Implementation 66
7.5 Grievance Redress Mechanism 67
8. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN 69
8.1 ESMP - Mitigation Measures 69
8.2 Monitoring and Reporting 69
8.3 Capacity of Proponent and Operator - Monitoring 82
9. CONCLUSION 83
APPENDICES 84
Appendix 1: MELAD response to Environmental License Application 85
Appendix 2: Land Options for Desalination Plant 90
Appendix 3: Minutes of Community Consultations 110
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | iii
Abbreviations
ADB Asian Development Bank
CESMP construction environmental and social management plan
CSS country safeguards system
ECD Environment and Conservation Division (within MELAD)
EIA environmental impact assessment report (as per the CSS)
EHSG Environmental Health and Safety Guidelines (of the World Bank Group)
ESMP environmental and social management plan
ENSO El Nino Southern Oscillation
GCF Green Climate Fund
GOK Government of Kiribati
HDD horizontal direct drilling
KAPII Kiribati Adaptation Project Phase II
KAPIII Kiribati Adaptation Project Phase III
MELAD Ministry of Environment, Lands and Agricultural Development
MFED Ministry of Economic and Finance Development
MHMS Ministry of Health and Medical Services
MISE Ministry of Infrastructure and Sustainable Energy
NIWA New Zealand Institute of Water and Atmosphere
PEO Principal Environment Officer (of ECD)
PMU Project Management Unit
PPTA Project Preparatory Technical Assistance
PUB Public Utilities Board
PV Photovoltaic
PVC Polyvinyl chloride
RO Reverse Osmosis
STSISP South Tarawa Sanitation Improvement Sector Project
SWRO Salt Water Reverse Osmosis
USEPA United State Environmental Protection Agency
UXO Unexploded Ordnance
WASH Water, Sanitation, and Health
WHO World Health Organisation
WWII World War Two
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | iv
Units and Measurements
% percentage
C° Degrees Celsius
ft Feet
kg Kilograms
kg/day Kilograms per day
kL Kilolitres
kL/day Kilolitres per day
L/c/day Litres per capita per day
LSI Langelier saturation index
m/h Metres per hour
m2 Square metres
m3 Cubic metres
m3/day Cubic metres per day
mg/L Milligrams per Litre
mL/hr Millilitres per hour
mm millimetres
MPN Most probable number
ND nominal diameter
NTU Nephelometric Turbidity Unit
pH potential of hydrogen (acidity/alkalinity)
ppt Part per thousandth
SDI silt density index
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | v
EXECUTIVE SUMMARY
Introduction
The proposed South Tarawa Water Supply Project (the project) is committed to supplementing
existing water shortages and infrastructure improvements, by offering an opportunity for all
residents on South Tarawa access to safe water. The physical work components of the project
involve the installation of a salt water reverse osmosis (SWRO) desalination facility that will
supplement existing water shortages, installation of a solar photo-voltaic (PV) system that will
provide extra energy to the existing power grid to compensate for the energy consumed by the
desalination plant and the rehabilitation and renewal of the water supply network and
associated infrastructure on South Tarawa. The proposed desalination facility will be designed
to accommodate the seawater reverse osmosis system to produce up to 6000 m3/day,
sufficient to meet the estimated water demand in 2031. The project will install four x
1000 m3/day capacity systems to meet projected demand in 2020.
The Asian Development Bank (ADB) and World Bank (WB) are supporting the Government of
Kiribati (GOK) by providing technical assistance through the Ministry of Infrastructure and
Sustainable Energy (MISE), and Public Utilities Board (PUB) to prepare in implementing the
project. Part of this assistance is to address environmental and social safeguard issues. In
addition, both ADB (through the Asian Development Fund) and the World Bank have each
committed US$15.0 million. Furthermore, the pending submission for additional financing from
the Green Climate Fund (GCF) is hoping to provide access to a further US$20 million. This will
further strengthen the GOK s positio to e a le to i ple e t this i po ta t p oje t.
The environmental impact assessment report (EIA) has been prepared following the Kiribati
environmental safeguard procedure, with additional elements to meet the requirements of the
development partners environment and social safeguards. Potential project impacts at pre-
construction, construction and post construction phases are predicted and the quality of the
impacts are assessed. Concomitant potential risks of the implementation are evaluated, and
mitigation measures proposed.
Potential impacts and mitigation measures
The project includes installation of a desalination plant and upgrading and/or replacement of
existing water distribution infrastructure – the environmental impacts will be site-specific and
largely limited to the construction period. The environmental and social management plan
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | vi
(ESMP) prepared as part of this EIA identifies measures to manage and mitigate the impacts.
Most important in the pre-construction phase is to identify the location of the main
infrastructure so it does not affect any heritage and culturally important sites and is not
affected by seawater flooding and inundation due to climate change. Sustainability results from
proper design and contractors providing training on the operation and maintenance (preventive
and corrective) of the systems and producing an operation manual and maintenance plan. The
contractor is also obliged to produce a construction environmental and social management
plan (CESMP) that is based on the EIA report and ESMP.
During the construction period, environmentally responsible construction practices and
management of all wastes will be mandatory. Likewise, social issues will be addressed
appropriately, and it is obligatory that consultation is made with people concerned, specifically
where private land access/usage and livelihood are involved.
Throughout the operation phase the integrity of the Betio outfall should be monitored to
ensure maximum dilution of wastewater effluent. It is recommended that monitoring of salinity
level at and adjacent areas to the outfall is carried out monthly. Regular testing on the quality
of water produced by the RO desalination and pumped from the water reservoirs is also
recommended. Maintenance of the installed and upgraded infrastructure should be ongoing.
Consultation and Disclosure
Issues raised at meetings related to the existing situation caused by the poor state of the water
supply system, to impacts of construction, and some further concerns. The lack of a reticulated
water supply system in some areas, and increased salinity of the well-water in Bonriki, were the
main concerns with the existing water supply system. Concerns with construction impacts
were:
(i) effects of excavation on trees/permanent structures, and the newly completed
tar-sealed road;
(ii) effect of drilling boreholes on ground stability; and
(iii) labor recruitment process.
Further concerns raised were:
(i) effects of brine disposal on the marine ecosystem;
(ii) effect of pumping feed water from boreholes on the freshwater lens;
(iii) concern for cost of water produced by the desalination plant; and
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | vii
(iv) community participation in maintenance, and the poor repair and hence
sustainability of infrastructure.
Conclusion
The EIA has found that no significant environmental impacts are likely to occur from this
development, particularly with the mitigation and monitoring strategies in place to ensure that
the environment is adequately protected, the SWRO desalination plant, solar PV system, and
water supply infrastructures are adequately managed, and the safety of workers as well as the
public are addressed.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 1
1. INTRODUCTION
Kiribati, an island republic in the central Pacific, comprises three island groups (Gilbert, Phoenix
and Line) with 33 coral atolls and islands stretching along the equator (Figure 1-1). South
Tarawa the ou t s apital comprises a series of isolates, oriented east-west and connected
by causeways. It adjoins North Tarawa, which similarly, comprises a series of islets, oriented
approximately north-east to form Tarawa atoll (Gilbert Islands group). It lies at a latitude of
120o20o north and 1720 – 1730 east, approximately 150km north of the equator.
This environmental impact assessment report (EIA)1 has been prepared for the South Tarawa
Water Supply Project comprising physical works including (i) the installation of a seawater
reverse osmosis desalination plant (SWRO) at Betio, (ii) the rehabilitation of the existing water
supply infrastructure on South Tarawa, and (iii) the installation of the solar photo-voltaic (PV)
system at Bonriki water reservation area to offset the energy consumed by the SWRO. The
project also includes non-physical works to improve the management of the water supply
network and increase health and hygiene awareness of the community through a Water,
Sanitation and Health (WASH) program. The Project aims to provide additional supply of water
to augment the water shortage problem on South Tarawa, an essential part of the solution to
the growing and intense problem of public health related to water and sanitation.
This EIA examines the potential impacts of proposed project activities and identifies mitigation
measures to avoid adverse impacts. It is prepared to assist the Ministry of Infrastructure and
Sustainable Energy (MISE) in preparing for the South Tarawa Water Supply Project. The Project
will be handed-over and managed by the Public Utilities Board (PUB), once the infrastructure is
fully installed and rehabilitation works are completed. The executing agency for the project is
the Ministry of Finance and Economic Development (MFED) and the implementing agency is
the MISE. The EIA has been prepared in accordance with the requirements of the development
partners (Asian Development Bank [ADB] and World Bank ([WB]), as found in Appendix 1 and
with the country safeguards system (CSS) as per Environment Act 1999, Environment Act,
Amended, 2007, and other requirements of the Republic of Kiribati.
1 This EIA report has been prepared to conform to the requirements of the Kiribati country safeguard system
with additional elements as required to also comply with ADB and WB safeguards. This EIA report is not an EIA
within the meaning of the ADB Safeguard Policy Statement 2009 or WB OP 4.01.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 2
Figure 1-1 Location Map of Kiribati and South Tarawa
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 3
2. LEGAL, ADMINISTRATIVE AND POLICY FRAMEWORK
2.1 Kiribati Constitution and Environment Act
The constitution of the Republic of Kiribati vests the natural resources of Kiribati in the
people and Government, who through various ministries and agencies provide the
protection to public health, the health of animals and plants and the conservation of
the environment. The country safeguard system (CSS) requires compliance with the
environmental assessment regulations for all projects is embodied in the Environment Act 1999
(No. 9 of 1999), which states it is an A t to P o ide fo the P ote tio I p o e e t a d Conservation of the Environment of the Republic of Kiribati… . The E i o e t A t as amended in 2007 to better reflect the needs of better appraising, monitoring and to provide
the means for the inclusion of the Environmental (General) Regulations of 2009 (which repeals
previous regulations to the Act). Activities are scheduled' according to their environmental
significance, activities considered to create significant environmental impact require application
for environmental license and some activities further require an EIA report. The decision to
grant the license and the provision of conditions are set out in Section 38 of the Environment
Act 2007, are made according to the principles of sustainable development and with any
international obligations or agreements to which Kiribati is bound, and any other prescribed
requirements (the process is further described in Section 2.3).
Following review of the application submission, an EIA report is required by the Principal
Environment Officer (PEO) of the Ministry of Environment, Lands and Agricultural Development
(MELAD) for the project (Appendix 1). The EIA requested is similar in content to the previous
CSS requirement of a Basic EIA which o espo ds to the ADB s lassifi atio of a category B
project where the impacts of a project are site-specific, few (if any) are irreversible and
mitigation measures can be designed more readily. 2
2.2 Other Relevant Legislation
Other legislation that is relevant to this Project include: (i) the Public Utilities Ordinance of
1977, which vests responsibility for the protection and security of water resources in the
Public Utilities Board, and includes regulations for the protection of water reserves, (ii) the
Public Health Ordinance of 1926, (iii) Public Health Regulations of 1926, both of which provide
for public health measures including sanitation, solid waste collection and drainage, (iv) the
2 Government of Kiribati & ADB. 2012. South Tarawa Water Supply Options Assessment Desalination Feasibility
Study. STSISP TA-7359(KIR). Volume 1: South Tarawa Desalination Plants Environment Assessment Appendix E
of South Tarawa Desalination Plants Environment Assessment in Fraser Thomas Partners.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 4
Foreshore and Land Reclamation Ordinance of 1969, which regulates extraction of material
such as sand, gravel, reef mud and rock, (v) Land Planning Ordinance 1972 (amended 1973,
1974, 1977, 1979, 1980 (2), 2000), the objective of which is to apply controls over land use and
developments within designated areas; (vi) the Local Government Act, 1984 which empowers
local government bodies to issue bylaws relating to environmental protection, and (vii) Penal
codes (Cap 76 1977) having some offences in the Code that are relevant to environmental
protection and enforcement.
Additionally, the following conventions, protocols and regional agreements are relevant and to
Kiribati: (i) Convention on Biological Diversity, (ii) Cartagena Protocol, (iii) World Heritage
Convention, (iv) Framework Convention on Climate Change, (v) Regional Seas Convention, (vi)
Convention to Combat Desertification, (vii) The Vienna Convention and Montreal Protocol on
Ozone Depleting Substances, (viii) Basel Convention and Waigani Convention to control the
trans-boundary movements and disposal of hazardous wastes, (ix) CITES (International trade in
endangered species), (x) Stockholm Convention International, (xi) Convention for the Protection
of World Cultural and National Heritage.
2.3 Administrative Framework for Safeguards Implementation
Requirements of the CSS are set out in the Environment Act of 2007 and Environment (General)
Regulations, 2009. The act assigns primary responsibility for undertaking environmental
assessment of projects to the project developer. The Ministry of Environment, Lands and
Agricultural Development (MELAD), under the direction of the Principal Environment Officer
(PEO), is responsible for review and approval of environmental assessment reports, prescription
of requirements for publication and disclosure environmental assessment reports, issuance of
environment licenses, and prescription of any conditions to the licenses.
Environment licenses are required from the MELAD, for all activities that are deemed
environmentally significant. These include activities to be undertaken by the Project, including
installment and operation of a desalination systems and solar PV system, and rehabilitation of
the existing water supply system that may require land clearance and excavating activities. The
Act requires the applicant for the environment license (in this case the MISE) submit an
application with an application fee to the PEO.
On consideration of the application, the PEO determines whether to issue an environment
license or require an EIA, or refuse the application. Appendix 1 provides the PEO decision and
what is required in the EIA report for this project.
If an EIA report is required, the applicant undertakes the assessment according to the required
format and is required to hold public consultations. This is compatible with the development
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 5
partners requirements, which requires that consultation is meaningful, commences early in the
project preparation cycle, provides timely disclosure of relevant and adequate information that
is understandable and readily accessible to affected people, is inclusive of the views of women,
men, and vulnerable groups, and is carried out in a non-coercive manner.
Once the EIA report is received by MELAD, the PEO will determine the appropriate form of its
publication and disclosure to interested parties, and the deadline for receipt of comments.
Comments received must be shown to the applicant and taken into consideration. Concurrently
the report is also being review by the Environment and Conservation Division (ECD), where
regional and international expert views may be sorted. In accordance with ADB policy, revisions
should be made in response to comments.
On receipt of comments, the PEO decides whether to grant a license and if a license is to be
granted, whether it will include any conditions. Conditions may include duration, location,
prescribed methods, emission limits, monitoring and reporting requirements, lodgment of
bonds and payment of fees, and preparation of plans and specific mitigations.
The ECD is responsible to monitor the a ti it s progress to ensure compliance with the license
conditions.
2.4 Develop e t Pa t e s’ Safeguard Requirements
The project is being co-financed by the ADB and WB and therefore in addition to the CSS the
safeguard requirements of the ADB and WB will also be complied with.
Asian Development Bank. The o je ti es of ADB s safegua ds a e to: i avoid adverse impacts
of projects on the environment and affected people, where possible; (ii) minimize, mitigate,
and/or compensate for adverse project impacts on the environment and affected people when
avoidance is not possible; and (iii) help borrowers/clients to strengthen their safeguard systems
and develop the capacity to manage environmental and social risks. Through its Safeguard
Policy Statement 2009 (SPS) ADB establishes policy objectives, scope and triggers, and
principles for three key safeguard areas of environment, involuntary resettlement, and
Indigenous People. The SPS sets out the process to be applied from screening, through due
diligence and assessment to monitoring and reporting.
The SPS requires project screening and categorization at the earliest stage of project
preparation. Screening and categorization is undertaken to (i) reflect the significance of
potential impacts or risks that a project might present; (ii) identify the level of assessment and
institutional resources required for the safeguard measures; and (iii) determine disclosure
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 6
requirements. ADB uses a lassifi atio s ste to efle t the sig ifi a e of a p oje t s pote tial e i o e tal i pa ts. A p oje t s atego is dete i ed y the category of its most
environmentally sensitive component. Each proposed project is scrutinized as to its type,
location, scale, and sensitivity and the magnitude of its potential environmental impacts.
Projects are assigned to one of four categories.3 The category determines the level of
assessment required.
ADB's safeguard due diligence emphasizes planning, environmental and social impact
assessments and safeguard documentation. Through such due diligence and review, ADB will
confirm (i) that all key potential social and environmental impacts and risks of a project are
identified; (ii) that effective measures to avoid, minimize, mitigate, or compensate for the
adverse impacts are incorporated into the safeguard plans and project design; (iii) that the
o o e / lie t u de sta ds ADB s safeguard policy principles and requirements and has the
necessary commitment and capacity to manage the risks adequately; (iv) that, as required, the
role of third parties is appropriately defined in the safeguard plans; and (v) that consultations
with affected people are conducted in accordance with ADB's requirements.
World Bank. The WB has operational policies relating to environmental and social safeguards.
OP 4.01 states that the WB requires environmental assessment of projects proposed for WB
financing to help ensure that they are environmentally sound and sustainable. Like ADB SPS,
OP4.01 sets out the process to be applied and commences with environmental screening which
is undertaken to determine the appropriate extent and type of environmental assessment. WB
uses the same classification system for projects as the ADB with Category A projects having the
greatest potential for significant environmental impacts (i.e. that are sensitive, diverse or
unprecedented) and an environmental assessment report must be prepared by the borrower.
Category B projects having potential impacts that are minor (i.e. site-specific with few, if any,
irreversible impacts) and mitigation can be provided readily. The scope of environmental
assessment for Category B projects is less than Category A (but the level of detail will vary from
project to project based on what is potentially at risk). Category C projects are unlikely to have
any adverse environmental impact and no further environmental assessment is required.
3 Category A if it is likely to have significant adverse environmental impacts that are irreversible, diverse, or
unprecedented, and impacts may affect an area larger than the sites or facilities subject to physical works.
Category B if its potential adverse environmental impacts are less adverse than those of Category A projects,
impacts are site-specific, few if any of them are irreversible, and in most cases mitigation measures can be
designed readily. A project is Category C if it is likely to have minimal or no adverse environmental impacts.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 7
WB appraises and, if necessary, includes components to strengthen the capabilities of the
implementing agency to a) screen sub-projects, b) obtain the necessary expertise to carry out
EIA, c) review all findings and results of EIA for individual sub-projects, d) ensure
implementation of mitigation measures and e) monitor environmental conditions during
project implementation.
Common safeguards approach. For this project, ADB and WB have developed a common
approach to safeguards and social dimensions to e applied. It is ased o Ki i ati s C““ supplemented by additional elements, as required, to also o pl ith “P“ a d WB s operational policies. The approach provides direction on the preparation of documents,
including environmental assessments, poverty and social assessment, land acquisition and
resettlement plans.
Government and the development partners have separate monitoring responsibilities. The
extent of monitoring activities, including their scope and periodicity, will be commensurate
with the p oje t s isks a d i pa ts. Go e e ts, th ough the i ple e ti g age , a e required to implement safeguard measures and relevant safeguard plans, as provided in the
legal agreements, and to submit periodic monitoring reports on their implementation
performance. Monitoring and supervising of social and environmental safeguards is integrated
into the project performance management system. ADB and WB will monitor projects on an
ongoing basis until a project completion report is issued.
Public consultation. For all projects the borrower consults affected groups and local non-
go e e tal o ga isatio s NGOs du i g the EIA p o ess a out the p oje t s e i o e tal aspects and takes into account their views. Consultation is initiated as early as possible.
Disclosure. To facilitate meaningful consultation, the borrower provides relevant materials in a
timely manner and in a form and language that are understandable and accessible to groups
being consulted.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 8
3. DESCRIPTION OF THE PROJECT
3.1 Need for the Project
Water management in Kiribati is amongst the most complex and challenging in the world.
Water resources are fragile, vulnerable to drought, over-extraction and contamination. This is
further complicated by issues of land ownership and water rights, and in the urban area of
South Tarawa (Figure 3-1), a rapidly increasing population.
Figure 3-1 Tarawa Atoll and South Tarawa
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 9
Many of the issues related to WASH in Kiribati are centered on South Tarawa. The population in
South Tarawa is projected to continue to increase at a rate between 1.1-2.3%, which for a high
growth scenario, represents approximately 160% increase between 2015 to 2040 to almost
90,000 people. Even without the projected population growth, as a result of high physical losses
in the system (estimated at 67%), the average available per capita water supply from the piped
water system operated by the PUB is 11 L/day. This is far less than the actual estimated
demand of between 57 and 112 L/day and, in the context of disaster response, is considered
the absolute minimum quantity required for basic drinking, cooking and personal hygiene
needs. Consequently, people are required to use unsafe alternative water sources, with a high
proportion of the South Tarawa population using contaminated well-water for bathing (82% in
2015 census).
The existing water supply in South Tarawa is sourced from infiltration galleries located at
Bonriki and Buota, from which water is abstracted and treated with a chlorination and aeration
system and distributed along the island. Due to high production and non-revenue water (NRW)
losses and the limited supply, customers are provided with water intermittently – for a few
hours every 2-3 days. This inadequate water supply is compounded by other challenges of
climate change and variability, urban encroachment, poor infrastructure management, high
non-revenue water, little-no cost recovery, low institutional capacity and funds. South Tarawa
is strongly influenced by the El Nino Southern Oscillation (ENSO) cycles and during La Nina
periods often experiences dry or drought conditions.
There are 7,877 number of households on South Tarawa with the number of persons per
household averaging 7.4 As illustrated in Table 3-1, in 2015 36% of the households get their
drinking water from the PUB reticulated water, 49.5% depend on rainwater, and about 12% are
still relying on groundwater, where 6% of these households are in Betio.
Table 3-1 Number of households on South Tarawa and source of drinking water
Area Total number
of
Households
PUB Pipe system
(undefined)
Well or
Ground
Water
Rainwater Other
Sth Tarawa 5,584 1,672 28 895 2,949 40
Betio 2,293 1,252 12 60 952 17
Source: GOK: 2015 Population and Housing Census Vol 1
4 GOK, 2016. 2015 Population and Housing census. Volume 1: Management report and basic tables.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 10
The future availability of water supply and the demand for water is also influenced by climate
change. Previous studies had indicated that the main impact of climate change on South
Tarawa water supply would be a 20% reduction in the size and sustainable yield of the Bonriki
and Buota lenses from approximately the year 2030. Further analysis as part of this project
preparation (see Climate Risk Vulnerability Study as part of the Green Climate Fund application
for the project) determined a more nuanced situation: that future sea overtopping and/or
droughts, rendered far more probable by climate change, could lead to a sudden, significant
but temporary reduction in the freshwater available from the lenses.
Sea overtopping alone could lead to a 54% or more temporary reduction in freshwater yield. If
the sea overtopping occurs in combination with drought, the freshwater available from the lens
could be close to zero. The duration of such an event would vary and cannot be accurately
forecasted, but it is reasonable to estimate it would be between 3 and 5 years duration. The
return period for such an event is unknown, but it is reasonable to estimate that the return
period lies between 10 and 50 years.
The analysis as part of this study also validated two pathways through which projected climate
change affects water demand:
• Rising temperatures will lead to higher per capita demand, rising by an estimated 2
liters per capita per day;
• Climate change will contribute to projected higher population growth on South
Tarawa (relative to the national average growth), contributing an estimated
incremental increase of 2,114 persons by 2040.
An additional source of water for South Tarawa is urgently needed at an affordable cost and
needs to have the capacity to expand to meet population increases. Both the Tarawa Water
Master Plan 2010-20305 and the Tarawa Water and Sanitation Roadmap 2011-2030 concluded
that SWRO is the most practical and affordable long-term option for supplementing the water
supply.
The main activities involved in the project include:
(i) installation of a SWRO desalination plant
(ii) installation of a solar PV system with a capacity of 2.5 MW of photovoltaic
power generation to offset the energy consumption of the desalination plant,
(iii) rehabilitation of the water supply network infrastructure,
5 White, I. 2011. Tarawa Water Master Plan 2010-2030. Ministry of Public Works and Utilities/Kiribati Adaptation
Programmes Phase II Water Component 3.2.1, World Bank. AusAID, NZAID.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 11
(iv) engagement of the private sector to improve management of water supply
infrastructure and to improve capacity of key institutions in program
management, and non-revenue water management; and
(v) implementation of a WASH awareness program to improve hygiene practices
a o g “outh Ta a a s populatio .
3.2 Project Components
3.2.1 Desalination Plant
Capacity and installation. The proposed desalination facility will be designed to accommodate
the seawater reverse osmosis system to produce 6000 m3/day, sufficient to meet the estimated
water demand in 2031. The Project will install four, 1000 m3/day capacity, systems to meet
projected demand in 2020. It is estimated that normal daily production of the plant will be 3000
m3/day, however, the plant will be able to produce a maximum of 4000 m3/day to meet peak
demand.
The location of the facility is shown in
Figure 3-2 and Figure 3-3, shows the layout plan for the system. The dimensions of the area
needed for the desalination system are 36.4 m by 23 m, as shown in Figure 3-2 desalination
plan (within red dashed lines) and borehole locations (red dots) can be easily accommodated
within an area that is currently used by Dai Nippon Construction Company (Betio-Bairiki
causeway contractor).
12 different sites (Table 6-1 and Appendix 3) were proposed and considered for the location of
the desalination plant. The lands with private ownership (Sites 1 and 2) were eliminated due to
complications with land procurement. The preferred location is site 9, shown below in Figure 3-
2. It is located more than 100 meters from the shoreline and therefore will not be exposed to
coastal wave events which might cause local inundation. The ocean outfall pump station that
can provide a means of brine disposal is located across the road, saving approximately US$2
million from the cost of constructing an independent outfall system for the plant.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 12
Figure 3-2 Proposed location of desalination plant
The water produced at the SWRO plant will be pumped to the Betio main water reservoir
where it will be distributed using the existing water supply network.
Figure 3-3 Site Plan for the Desalination Plant
Bores within
property
boundary
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 13
Source of feed water and conveyance. The feed water to the plant will be sourced from 12
constructed wells to be located within the proposed boundary of the desalination plant (
Figure 3-2). Each well will be drilled approximately 20 - 30 meters apart and to a depth of
approximately 35 meters. The depth is within the Pleistocene limestone with high salinity
groundwater (see Section 4). Sourcing the feed water at this depth will not impose adverse
impact on the overlying freshwater lens that is used by the local community. There will be
seven wells needed for the initial four desalination reverse osmosis systems with two
additional wells that will provide spare pumping capacity. Another three wells will be required
to allow for two future SWRO systems planned.
Each well will be 200mm in diameter with 150mm polyvinyl chloride (PVC) internal casings with
screens equipped with 100mm submersible pump. The wells will be installed as follows;
• The bottom 15 m of the borehole will be fitted with 3 m lengths of 150 mm PVC
screwed-end, machine-slotted screens and fitted with a 150 mm screwed end cap
at the base.
• The suggested slot pattern for the 150 mm PVC screens is five rows of 1.5 mm wide
x 50 mm long radial slots with 40 mm gap between rows of slots. There will be a
spacing of 8 mm between slots along the full length of the screen, except near
screwed ends.
• Above the 15 m screen section will consist of five 3 m screens. Seven 3 m lengths
of 150 mm PVC casing should be installed, giving 21 m total length, the casing
terminating about 1 m above ground. The end should be temporarily fitted with a
150 mm screwed end cap.
The above slot pattern will enable a continuous flow rate of 17 L/s to be drawn through the 15
lo g s ee at a elo it elo the sta da d elo it . Based o pu pi g tests a ied out at Buariki on North Tarawa and Ebeye (Kwajalein Atoll, Marshall Islands) the drawdown at the
wells from a pumping rate of 17L/s is likely to be less than about 0.3 to 0.5m and diminishes
with distance from the well. Although there are differences between wells referenced above
and the ones proposed in this project, drawdown will be undetectable beyond a distance of 15-
20m from each well.
The expected salinity of the groundwater pumped from 35 m below ground level would be very
saline and close to seawater salinity. The feed water obtained from wells below the aquifer are
naturally filtered and has more constant solute and impurity levels. The quality of feed water
adopted for the preparation of SWRO concept design is shown in Table 3-1. Water quality
testing is required during the next stage of the project to verify actual water quality.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 14
Table 3-1 Feed water quality
Parameter Units High salinity Low salinity
pH 8.2 8.2
Sodium mg/L 11,002 9,169
Potassium mg/L 399 333
Calcium mg/L 426 355
Magnesium mg/L 1,325 1,104
Strontium mg/L 13 11
Chloride mg/L 19,796 16,496
Sulphate mg/L 2,764 2,303
Bromide mg/L 68 56
Carbonate mg/L 30 25
Bicarbonate mg/L 148 124
Fluoride mg/L 1 1
Borate mg/L 28 23
TDS mg/L 36,000 30,000
Source: STWP PPTA Design for Desalination Plant
Prior to the use of each well, the end 150mm casing located above ground will be fitted with a
150mm heavy duty plastic lockable well-plug. The lid would stay locked until the pump and
associated electrical and safety cables and delivery pipe work are ready to be installed.
Pre-treatment. Media filtration is proposed to attain a quality of feed water with turbidity less
than 1 nephelometric turbidity unit (NTU) or as close to 0.1NTU as possible, and silt density
Index (SDI) of less than 5. The media essentially has dual media beds with anthracite as the top
layer and silica sand as the lower layer. Ten filters are proposed so that the full production of
4,000m3/day can be achieved with one filter out of service.
To contain filtered feed-water it is proposed that a 50m3 filtrate tank is installed downstream of
the media filter and a low pressure forwarding pumps is installed upstream of the high-pressure
reverse osmosis pumps. Thus, the filtrate tank isolates the bore pump operation from the
reverse osmosis plant. To allow for the tank overflow, an overflow pipe is proposed to run in
parallel to the brine line and the sewage outfall pipe and terminate at the tidal reef flat close to
the beach.
Regular backwash occurring once every 24 hours to remove captured suspended solids from
the filters is essentially required. It is proposed that one filter should be backwashed at a time.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 15
To achieve the backwash process two backwash pumps are required operating at duty/standby
configuration.
Cartridge filter. From the low pressure forwarding pump, the filtered water then passes
through the cartridge filter (nominal filtration to 5 microns) to remove any fine contaminants
that might be present downstream of the media filtration system. The cartridge filters are to be
installed on each of the reverse osmosis skid.
Reverse osmosis system. All equipment associated with a 1000m3/day reverse osmosis system
will be installed on a skid that can be easily transported by a 40ft container and installed on a
plinth constructed as part of the floor slab in the building. Each skid will have the following; low
pressure forwarding pump, cartridge filter, anti-scaling dosing pump, high pressure pump,
pressure vessel rack containing reverse osmosis elements, energy recovery device, booster
pump for the energy recovery device, high pressure and low-pressure piping, manual and
automated valves, instrumentation and remote IO cubicle.
The water is fed into the reverse osmosis system after the filtration process by the high-
pressure pump. To maintain the setpoint permeate production of 1,000m3/day and system
recovery of 43% an automated control system will be installed to automatically adjust pump
speed and hence the inlet pressure to the reverse osmosis membrane. The energy requirement
to operate the RO system is considerably high, however there are currently available
technologies that are being used to conserve energy in the reverse osmosis operation. An
energy recovery device known as pressure exchanger will be incorporated in the RO system.
The device recovers the hydraulic energy from the rejected brine stream; by incorporating the
device the size of the high-pressure pump can be reduced (further contributing to the energy
efficiency of the system). Some of the pressure exchanger devices, PX device for instance is
known to reduce energy usage up to 60%.
In seawater reverse osmosis, the formation of calcium carbonate scales over the membrane is
inevitable reducing its performance over time. For this project, it is proposed that a central
storage tank housing the anti-scalant with a dosing pump be installed on each reverse osmosis
skid. The anti-scalant is a phosphate-based chemical used on a continuous basis for injection
into the feed stream to the reverse osmosis system. The estimated dose rate is 2 mg/L.
Additionally, regular chemical cleaning of each reverse osmosis system is also required three
times per year to maintain high performance. The chemical to be used depends on the type of
fouling and therefore cleaning that is required:
• Citric acidic cleaning to remove metals and salts (carbonates) precipitates. Usually
the concentration used is 2%;
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 16
• Alkaline detergent cleaning to remove fouling caused by organics, colloids or
biofouling. The chemical used is sodium lauryl sulfate and usually applied at 0.025%
concentration; and,
• Biocide cleaning to remove fouling from bacteria, yeast and fungi. Usually this
cleaning is very unlikely to be applied.
The final selection of chemicals will be decided by the supplier of the reverse osmosis systems.
Flushing of the membrane by fresh water produced from the system is also required for normal
shutdown to displace saline feed water and to flush cleaning solution from the system after the
chemical cleaning process. Where the RO system will not be required due to low demand,
recirculating of a 1% sodium bisulphite solution within the system is needed to preserve the
membrane.
The waste from the chemical cleaning process will be discharged to a 40m3 sump to be located
within the desalination plant compound (exact site to be determined in detail design by
contractor). is the waste will be neutralized in the sump before it is discharged by a submersible
pump to the main disposal pipeline. The pump will also be used to provide a mixing
environment for the neutralization process required.
Post-treatment. Based on the Concept Design Report6, the quantity of the chemicals required
in the re-mineralisation process is considerably high, 90 kg of 90% purity hydrated lime and 96
kg/day of carbon dioxide and are not readily available in the Country and must be imported on
a continuous basis. Further, the above quantity will add 37 mg/l of total dissolved solids (TDS)
to the final drinking water. Additionally, the corrosiveness characteristics of the permeate on
the concrete will not be an issue as the reticulation system are predominantly plastics,
therefore any form of re-mineralisation will not be pursued. However, treating the permeate
with chlorine will still be applied. Chlorination of water will be based on the use of gases
chlorination as currently practiced on South Tarawa. The recommended dose is 3 mg/L.
Brine disposal. The maximum volume of brine flow rate for each of the reserve osmosis rack is
7,953 m3 per day (Table 3-2) when all the six racks are installed. For the four racks that will be
installed in the proposed Project, the maximum flow rate is 5,302 m3 per day or 61.37 L/s.
6 GHD, 2017. Report for ADB and Government of Kiribati – TA-9200 KIR: South Tarawa Water Supply Project
(49453-001)-Project Preparatory Technical Assistance (PPTAA), Output 8 – Concept Design for Desalination
Plant
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 17
Table 3-2 Brine flow rate
Number of
operating racks
Volume of brine produced
per day (m3)
Brine Flow (L/s)
1 1326 15.34
2 2651 30.68
3 3977 46.03
4 5302 61.37
5 6628 76.71
6 7953 92.05
Source: STWP PPTA Output 8 Design for Desalination Plant
At a recovery of 43% the brine will be 1.75 times the concentration of the feed water. Beside
the brine as the major component of the total waste flow from the desalination system, the
other components include;
• Backwash and maturation flow from the filter backwash sequence with an
estimated daily volume of 290 m3.
• Neutralized water from chemical cleaning sump which will be discharged
intermittently at approximately monthly interval. The expected quantity is about
20 m3 per cleaning operation.
• Seawater flush in the final stage of chemical cleaning operation. The flow rate is
about 27m/s for a period of about 10 minutes.
Table 3-3 shows the expected salinity level of the combine effluent once the brine is combined
with the raw sewage.
Table 3-3 Combined brine and sewage discharge volume and salinity
Operation Drinking water
production
m3/day
Brine flow rate
m3/day
Brine salinity
mg/L
Normal 3000 5,705 54,800
Peak 4000 7,030 56,350
Future 6000 9,681 58,200
Source: STWP PPTA Output 8 Design for Desalination Plant
The total waste to be disposed will be routed from the desalination facility directly to the
existing outfall pipeline at the outfall pump station (Figure 3-4). This is located across the road
where it will be combined with raw sewage and subsequently discharged to the ocean through
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 18
the existing DN 300 PE outfall pipeline. To allow the brine to be discharged through the sewage
outfall pipeline the existing gravity flow system will be converted to a pressurized system. The
works required to change the system include:
• Installation of a new sump downstream of the existing screen to accept screened
effluent
• Procurement of two additional submersible pumps that will pressurized the system
• Mechanical and electrical installation of the submersible pumps in the new sump
• Control system to maintain controlled flow from new pumps, irrespective of the
brine flow rate
• Modification of existing outfall piping to accept sewage inflow from pumping
station and brine from desalination plant
• Connection of brine into the modified outfall pipeline
Figure 3-4 - Direction of brine from desalination plant
The figure shows brine from desalination plant (blue arrow) and the additional work (enclosed
in green box) required at the outfall pump station to change the system from gravity to
pressure feed. The outfall is equipped with a diffuser system that has 12 outlet ports located at
a depth of between 25 to 30 meters.
Power supply. The desalination plant will run on the exiting PUB power grid with a backup
generator provided. It is expected that PUB will install two additional high speed electrical
generators at its PUB sites in Betio with constant power supply adding more stability to
electricity source.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 19
Summary. The following is a summary of the activities involved in construction of the
desalination plant.
• Construction of building that will house the desalination plant and raised platform
within the building for each of 1000 m3 RO skid
• Drilling of boreholes and well construction
• Construction of a 40m3 sump to store the wastewater from the chemical cleaning
process;
• Installation of chlorination and chemical cleaning facility as part of the desalination
plant.
• Installation of standby generator and electrical components of the desalination
system
• Pipe connection between the different components of the desalination system
• Trenching activities for construction of transmission pipe of permeate to the storage
tank located at the existing PUB water storage tank in Betio
• Trenching activities for construction of transmission pipe of brine to the existing
outfall pipeline;
• Upgrading work on the existing outfall system.
3.2.2 PV Solar System
The power supply to the desalination facility when it is operating at peak production will be
around 500 kW. It is proposed to offset the energy consumption with 2.5MW of PV power
generation, which will be installed at the Bonriki water reserve area (Figure 3-5) and to be
connected to the electricity power grid. The total land area required is approximately
3 hectares. The area is under a long-term lease agreement by the Government as part of the
National Water Reserve.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 20
Figure 3-5 Proposed site of the PV Solar system
3.2.3 Water Supply Infrastructure
Table 3-2 provides a list of the water supply infrastructure within the supply network on South
Tarawa and Betio that requires upgrading and Figure 3-6 illustrates supply network and existing
water storage infrastructure along the island. Note that some of the upgrading works will be
undertaken through Kiribati Adaptation Program Phase Three (KAP III) which is addressing non-
revenue water in South Tarawa.
The activities involved include;
(i) upgrading of the chlorination storage facility from an open ventilated facility to
an international compliance standard and the chlorination gas cylinder from the
existing direct injection to flow paced;
(ii) renewal of a water transmission main at Temwaiku village from the existing
DN100 to DN200 PE100 capacity;
(iii) installation of a new DN160 PE100 transmission main at Buota village;
(iv) installation of new 22kl ground tank at Buota with a booster pump;
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 21
(v) installation of new ground water tanks of varying capacities (refer to Table 3-2)
with appropriate booster pumps to serve 2040 demand at existing locations of
overhead storage tanks on South Tarawa;
(vi) installation of a new water reticulation network at Buota and expansion of the
network at Bonriki to area that currently has no reticulated supply;
(vii) Installation of new PE pipelines and meters to replace the existing reticulation
network at Temwaiku, Hospital at Nawerewere, Bangantebure, Eita, Tebunia,
Ambo, Banraeaba, Antemai, Teaoraereke and Bairiki.
Figure 3-6: Existing Water Network Diagram
3.3 Proposed Implementation Schedule and Workforce Component
Follo i g the app o al of the p oje t s detail desig a d the o pletio of iddi g do u e ts toward mid-2019, implementation of construction is expected to commence shortly after the
contractor/s is or are identified. The workforce will be small-scale. It is expected that most of
the skilled labor force (90%) will be sourced locally, with expatriates filling the supervisory,
skilled plant operation and management positions.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 22
Table 3-2 Water Supply Infrastructure - Summary of Proposed Upgrades
Infrastructure Description Existing
Size/Capacity
Proposed Upgrade
HEADWORKS - BUOTA AND BONRIKI
Bonriki - chlorination Gas cylinder direct injection 300 g/hr 3.7 mg/L (av.) Upgrade so that the dosing rate is flow paced
Bonriki – chlorine storage Open ventilated storage of cylinders New compliant storage facility
HEADWORKS – BETIO DESALINATION PLANT (PROPOSED)
Betio – on-ground storage Concrete tank split into two portions 2 320 kL KAPIII project proposed rehabilitation spot repairs as required
Betio headworks – pumping
station (PS)
N.A. (new) New pumping facility (desal. water to transmission main)
PIPELINES
Temaiku distribution main –
transmission main
Existing pipeline too small for future
requirements
DN100 DN200 PE100
Buota distribution main –
transmission main
New – to provide water to an area that currently
has no reticulated supply
N.A. (new) DN160 PE100
CHLORINE DOSING STATIONS
Betio - chlorination Gas cylinder direct injection 1.1 mg/L Replaced by new disinfection process part of desalination plant
DISTRIBUTION AREAS – STORAGES AND BOOSTER PUMPING STATIONS
Buota - tank New – area currently has no reticulated supply N.A. (new) 22 kL on ground tank to serve 2040 demands
Buota - booster PS New – area currently has no reticulated supply N.A. (new) Booster Pumps No. and configuration to be determined
Bonriki - elevated tank Existing - reinforced concrete tank 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Bonriki – on-ground tank Storage to meet peak demand of distribution area N.A. (new) 158 kL on ground tank to serve 2040 demands
Bonriki – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Temaiku – on-ground tank Storage to meet peak demand of distribution area N.A. (new) 158 kL on ground tank to serve 2040 demands
Temaiku – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 23
Infrastructure Description Existing
Size/Capacity
Proposed Upgrade
Hospital – on-ground tank Storage to meet peak demand of distribution area N.A. (new) 148 kL on ground tank to serve 2040 demands
Hospital – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
McKenzie – on-ground tank Storage to meet peak demand of distribution area N.A. (new) 84 kL on ground tank to serve 2040 demands
McKenzie – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Bikenibeu KGV - elevated tank Existing - reinforced concrete tank 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Bikenibeu KGV – on-ground Existing - concrete roofed structure 210 kL KAP III proposed rehabilitation of existing tank.
Bikenibeu KGV – tank (disused) Existing - concrete tank in-ground 220 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Bikenibeu KGV – booster PS Boosts supply pressure within distribution area N.A. (New) Booster pumps number and configuration to be determined
Bikenibeu OH - elevated tank Existing - reinforced concrete tank 22 kL KAPIII proposed rehabilitation of existing tank to rectify leakage
Bikenibeu OH – in-ground tank Existing - concrete tank in-ground 220 kL KAPIII proposed rehabilitation of existing tank to rectify leakage
Bikenibeu OH – tank (disused) Existing - concrete tank in-ground 220 kL KAPIII proposed rehabilitation of existing tank to rectify leakage
Bikenibeu OH – booster PS Boosts supply pressure within distribution area N.A. (New) Booster pumps number and configuration to be determined
Bangantebure - elevated tank Existing - reinforced concrete tank 22 kL KAPIII proposed rehabilitation of existing tank to rectify leakage
Bangantebure – on ground tank Storage to meet peak demand of distribution area N.A. (new) 130 kL on ground tank to serve 2040 demands
Bangantebure – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Eita - elevated tank Existing - reinforced concrete tank 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Eita – on-ground (three) tanks Existing - concrete tanks 3 x 22 kL (66 kL) KAP III proposed rehabilitation of existing tank to rectify leakage.
Eita – on ground tank Storage to meet peak demand of distribution area N.A. (new) 42 kL on ground tank to serve 2040 demands
Eita – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Tebunia – on ground tank Storage to meet peak demand of distribution area N.A. (new) 111 kL on ground tank to serve 2040 demands
Tebunia – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Ambo - elevated tank Existing - Reinforced concrete tank 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 24
Infrastructure Description Existing
Size/Capacity
Proposed Upgrade
Ambo – on ground tank Storage to meet peak demand of distribution area N.A. (new) 127 kL on ground tank to serve 2040 demands
Ambo – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Banraeaba - elevated tank Existing - reinforced concrete tank 22 kL KAPIII proposed rehabilitation of existing tank to rectify leakage
Banraeaba – on ground tank Storage to meet peak demand of distribution area N.A. (new) 94 kL on ground tank to serve 2040 demands
Banraeaba – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Antemai - elevated tank Existing - reinforced concrete tank 22 kL KAPIII proposed rehabilitation of existing tank to rectify leakage
Antemai – on ground tank Storage to meet peak demand of distribution area N.A. (new) 152 kL on ground tank to serve 2040 demands
Antemai – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Teaoraereke - elevated tank Existing - reinforced concrete tank 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Teaoraereke – on-ground ( Existing - concrete tanks 5 x 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Teaoraereke – on ground tank Storage to meet peak demand of distribution area N.A. (new) 39 kL on ground tank to serve 2040 demands
Teaoraereke – booster PS Boosts supply pressure within distribution area N.A. (new) Booster pumps number and configuration to be determined
Nanikaai - elevated tank Existing - reinforced concrete tank 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Nanikaai – on ground tank Storage to meet peak demand of distribution area N.A. (new) 67 kL on ground tank to serve 2040 demands
Nanikaai – booster PS Boosts supply pressure within distribution area N.A. (New) Booster pumps number and configuration to be determined
Bairiki - elevated tank Existing - reinforced concrete tank 22 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Bairiki – in-ground tank Existing - concrete tank in-ground 220 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Bairiki – in-ground tank Existing - concrete tank in-ground 220 kL KAP III proposed rehabilitation of existing tank to rectify leakage
Bairiki – booster PS Boosts supply pressure within distribution area N.A. (New) KAP III - booster pumps proposed as part of upgrade.
Betio – booster PS Boosts supply pressure within distribution area N.A. (New) KAP III - booster pumps proposed as part of upgrade.
DISTRIBUTION AREAS - RETICULATION NETWORK
Buota New – area currently has no reticulated supply N.A. (New) New PE pipelines and service connections and meters
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 25
Infrastructure Description Existing
Size/Capacity
Proposed Upgrade
Bonriki New – expand to none-reticulated supply area New reticulation in the north/north east of the island
Temaiku Existing reticulation New PE pipelines, service connections and meters (replace existing)
Hospital Existing reticulation (installed in 1986) New PE pipelines, service connections and meters (replace existing)
McKenzie Existing reticulation (installed in 1986) Detailed design part of KAP III
Bikenibeu KGV Existing reticulation (installed in 1986) Detailed design part of KAP III
Bikenibeu OH Existing reticulation (installed in mid 1980s) Detailed design part of KAP III
Bangantebure Existing reticulation New PE pipelines, service connections and meters (replace existing)
Eita Existing reticulation New PE pipelines, service connections and meters (replace existing)
Tebunia Existing reticulation New PE pipelines, service connections and meters (replace existing)
Ambo Existing reticulation New PE pipelines, service connections and meters (replace existing)
Banraeaba Existing reticulation New PE pipelines, service connections and meters (replace existing)
Antemai Existing reticulation (minor installation 2004) New PE pipelines, service connections and meters (replace existing)
Teaoraereke Existing reticulation (minor installation 2004) New PE pipelines, service connections and meters (replace existing)
Bairiki Existing reticulation (installed in mid 1980s) Detailed design part of KAP III
Betio Existing reticulation. Detailed design part of KAP III
Note: Kiribati Adaptation Program - Phase Three (KAP III), under the auspices of the Office of Beretitenti, is addressing non-revenue
water in South Tarawa.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 26
4. DESCRIPTION OF THE ENVIRONMENT
4.1 Physical Environment
4.1.1 Geology and Soils
The Tarawa atoll developed from a volcano which appeared between 55 million and 65 million
years ago (during the Paleocene geologic epoch). Over time, the peak of the volcano sank
below sea level due to subsidence of the ocean floor. The island surface is formed by
successive coral deposits around the old and now submerged volcano. Atolls originate as coral
reef formations at the tidal level at the rim of the original volcano, these formations rise in
successive layers of dead coral. When the reef rises above sea level, coral ceases to grow. Coral
growth will resume if the atoll drops below the surface of the sea. The vertical growth from this
process keeps the reefs at or near the surface of the ocean as the volcano subsides. The atolls
of North and South Tarawa, and surrounding reef delineate the edges of the lagoon which
occupies the site of the former volcanic core. The atolls and lagoon cover the peak of the
former volcano, which rises sharply from the seabed.
Like other coral atolls and islands, the nature of the soil is derived from limestone which has
been formed due to coral formation over thousands of years. The soil is alkaline and therefore
it does not support the growth of certain plants and trees. The soil is porous and lacks essential
elements which makes it unable to support plant life. The topsoil which comprises decaying or
composted organic matter mainly decaying leaves and plant materials is thinly spread over
most of the area with plant cover and other areas covered with wild bushes.
4.1.2 Climate and Climate Change
Tarawa has a maritime tropical climate.7 Two seasons occur, characterised mainly by the
wind patterns but also by rainfall. Between October and March, easterly trade-winds
predominate and rainfall is generally higher, while between April and September, more
variable winds occur including westerlies, which can be strong and rainfall is lower.
Temperatures generally vary between 28°C and 32°C, averaging 31°C, though monthly
averages remain very constant between 26°C (February) and 28°C (September). Rainfall
averages 2,027 mm annually; however this varies widely, between 398mm and 4,333mm.
The main reason for this variability is the El Niño–Southern Oscillation (ENSO).
7 GOK 2014. Kiribati Joint Implementation Plan for Climate Change and Disaster Risk Management / developed
by the Government of Kiribati. SPC Noumea.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 27
Many Kiribati islands lie within the equatorial waters that warm significantly during an El Niño
event and cool during a La Niña event. As a result, rainfall is much higher than normal during an
El Niño event and much lower during a La Niña event. Maximum air temperatures tend to be
higher than normal during El Niño years, driven by the warmer oceans surrounding the islands,
while in the dry season minimum air temperatures in El Niño years are below normal.
El Niño is generally associated with above-normal rainfall and strong westerly winds, while La
Niña is associated with below-normal rainfall and the risk of drought. Prolonged drought
periods were encountered in 1988 to early 1989 and followed by another in 1998 extending
into mid-1999 and resulting in the loss of many valuable food crops including coconuts (Cocos
nucifera) and breadfruits (Artocarpus sp.). Unlike many other Pacific islands, Tarawa rarely
experiences cyclones.
Climate change is a longer-term phenomenon and will result in landform changes which may
become unstable or untenable for communities. Using the 18 Global Climate Model data
obtained from the International Coupled Model Inter-Comparison Project phase 3 (CMIP3)
experiments, Pacific Climate Change Science Program reports that over the course of the 21st
century, mean rainfall, air temperature, sea surface temperature and the frequency and
strength of extreme events are likely to increase.8 Mean sea-level is also projected to continue
to increase during the 21st century. According to a study carried out under Kiribati Adaptation
Project Phase Two (KAPII) in 2008 the groundwater yields from Bonriki and Buota reserves are
expected to be reduced by about 19% by 2030.9 With the increase in mean sea level South
Tarawa could loss 25 to 54% of its land mass by 2050.10
4.1.3 Water Resources
Ground water. Shallow groundwater is the principal source of fresh water in Kiribati. South
Tarawa s water supply originates from the water reserve areas in the villages of Bonriki and
Buota where water is extracted and reticulated through a water supply system. Climatic
conditions have a major influence on fresh water resources in Kiribati. Underground freshwater
lenses are recharged by rainfall and households frequently use rainwater catchments to
supplement other water sources. Thus, for many reasons, prolonged periods of low rainfall or
even droughts have had serious implications in the past. The droughts associated with well-
8 BoM and CSIRO. 2011. Climate Change in the Pacific: Scientific Assessment and New Research - Vol. 2: Country
Reports) produced by the Pacific Climate Change Science Program
9 GOK & ADB. 2012. South Tarawa Water Supply Options Assessment Desalination Feasibility Study Volume 1 –
Appendix E: South Tarawa Desalination Plants Environment Assessment. (STSISP TA-7359-KIR). 10 World Bank. 2000. Cities, Seas and Storms: Managing Change in Pacific Island Economies. Vol IV. Adapting to
Climate Change, World Bank, Washington.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 28
developed La Niña conditions are evident. The provision of a desalination plant in this proposed
project will supplement the shortage of water envisaged.
Marine water. The coastal area of South Tarawa is polluted and littered with rubbish due to
illegal rubbish disposal, open defecating practices, and animal wastes. Also, effluent from the
remaining sewage outfalls that have not been rehabilitated will continue to pollute the
intertidal zone. The coastal water quality on South Tarawa tested by the New Zealand Institute
of Water and Atmosphere (NIWA) in 2014 shows varying degrees of pollution (Figure 4-1).11
Figure 4-1 Pollution level along the coastal areas of South Tarawa
Source: NIWA 2014
11 NIWA 2014. Water Quality Report Card Kiribati 2014. NZAID/GOK
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 29
Through the South Tarawa Sanitation Improvement Sector Project, the sewerage outfalls at
Bikenibeu, Bairiki and Betio have been extended beyond the surf zone to a depth of 30 meters
and with a 10 m diffuser connected to each. Prompt dilution of the effluent is expected once
discharged due to presence of diffuser ports and how the ports are oriented to the direction of
the current. The new outfall construction was completed in 2017.
A 2015 study shows that the direction of the nearshore ocean current changes to an eastward
direction according to the tide, but currents are generally moving in a westward direction.12
The currents velocity measured at different depth, 15m, 25m and 30m was variable, depending
upon tidal conditions, the velocity ranges between 0.2 – 1.0 m/s. Wind driven set-up on the
windward ocean reef and wind stress on the surface are also the driving mechanism of water
circulation and flushing.13 The dredged ship and boat channels over the reef also contribute to
the magnitude of water movement at the reef intertidal zone around the atoll islands.14 The
main shipping channel at Betio is located about 6.5 km from the outfall pipeline.
The Environmental Health and Laboratory Units under the Ministry of Health and Medical
Services have facilities to test water quality. Currently they have a program established to
undertake water quality measurements. The capacity of the Water Division under the MISE is
limited to some features of water quality only such as salinity, by the type of machine and
testing probes currently available on hand.
4.2 Biological Environment
4.2.1 Marine Resources
Mangrove and coral ecosystems have significant ecological significance. Mangroves occur on
reef mud flats at the lagoon margins at certain areas and provide a coastal protection function
as well as an important habitat for marine organisms. Mangroves have been subject to
depletion, but mangrove forest areas are being rehabilitated by the government under the
World Bank funded Kiribati Adaptation Program – Phase 3 (KAP III). Seagrass beds, which
provide an important habitat for shellfish and other organisms, occur extensively within the
lagoon particularly toward the southeast. No mangroves or seagrass are located within the
vicinity of the sewerage outfall to be used for Brine Disposal, as the outfall is located on the
ocean side reef flat.
12 SMEC 2015. ICB-02 Rehabilitation and Upgrading of Ocean Outfalls at Betio, Bairiki and Bikenibeu Ocean
Outfalls Concept and Options Report. (ADB Grant-0263 STSISP)
13 Callaghan, D.P. etal (2006). Atoll lagoon flushing forces by waves. Coastal Engineering 53, 691-704.
14 Lelaurin, J. 2000. Hydrodynamic simulation with MIKE21 of Abaiang atoll, Kiribati. SOPAC Training Report 87.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 30
Coral reefs surrounding the atoll and within the lagoon provide habitat to reef fish species and
other marine species, including turtles, supporting a complex and bio-diverse community.
Common fish species found at the site include surgeon fish (Acanthurus lineatus, A.triostegus,
A.xanthopterus), soldier fish (Myripristis species) parrot fish (Scarrus species). Red snapper
(Lutjanus gibbus) and L.bohar (known to be ciguatoxic) are also commonly caught by local
residents fishing in the area. Figure 4-2 provides a perspective view of the reef/intertidal
platform to the reef slope, typical of reef front in Kiribati atoll islands. 15 The reef/intertidal
platform is the section located between the beach shoreline to the reef margin with the
distance ranging between less than 10 meters to more than a kilometer.
Figure 4-2 Seaward reef front perspective
The alignment of the Betio outfall is shown on Figure 4.3.
15 Zann, L.P.1986. The Marine Ecology of Betio Island, Tarawa Atoll, Republic of Kiribati. Coastal Zone Surveys on
Sedimentation, Erosion, Pollution Problems in Kiribati. CCOP/SOPAC Technical Report 23.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 31
Figure 4-3 Betio sewage outfall pipeline route
Source: Fellenius Consultants 201716
Coral and micro-algae. On the reef flat adjacent to the Betio outfall pipeline route (where brine
from the desalination plant is to be discharged) the odoriferous and fast growing red macro-
algae, Hypnea sp. is predominant. The algae proliferate under nutrient-loading conditions from
the sewage effluent discharge. It occurs as both attached and unattached mats.17 For that
reason, it is omnipresent when exposed or caught in pools at low tide, but partly washes away
16 Fellenius Consultants/Maritime Constructions Inc., 2017. STSISP Betio Outfall Post-Installation Survey Report 17 Fellenius,K. and Hess,D.2015. Benthic morphology and marine life assessment for the siting of ocean outfalls on
South Tarawa. STSISP, MPWU Kiribati
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 32
when the tide rises. They produce bad odor and are a nuisance when the dead algae
accumulate on the beach.
The marine life assessment survey completed at the Betio Outfall site in 2015 found the
substrate and algae that is representative of the outer 100 m of the intertidal reef flat is
comprised of negligible sand, with about 70% cover of turf algae. 18 Roughly half of the turf
algae are red cyanobacteria microalgae, and half are fleshy green microalgae. Both arise from
high nutrient and high energy conditions with enough sunlight. Figure 4-4, extracted from the
marine life assessment survey report completed at the Betio Outfall site, gives the average
percent cover for substrate and benthic categories on the subtidal reef flat. All invertebrates
other than coral and zoanthids are absent. The survey found that whilst there is no baseline
comparison available for this outfall, it is likely that the low coral cover, lack of coralline algae,
high turf algae, and the high rubble, debris, and rock cover across the reef flat, crest, and slope
can be attributed to both the 2009 Crown-of-Thorns sea star infestation and to nutrient loading
conditions since the outfall pipes broke in the shallows a half decade ago. The heavy siltation
combined with limited variety in coral growth forms is consistent with the transition towards an
algae-dominated reef.
Figure 4-4 Betio Subtidal Reef Flat Substrate and Benthic Categories
Source: STSISP - Fellenius Consultants 2017 (after footnote 18)
The marine life assessment survey also found that coral cover on the outer reef crest is less
than 5% to the east and about 15% to the west of point 14 (refer to Figure 4-3). It is mainly H.
coerulea with some encrusting varieties. There was also less silt than was observed on the
subtidal reef flat.
18 Ibid
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 33
There are slightly less turf algae at 50% cover, consistent with lower energy on the crest than
on the subtidal reef flat yet with a significant nutrient load. Fleshy coralline algae are present at
15%. Crustose coralline algae are absent.
Figure 4-5 and Figure 4-6 extracted from the post-installation survey report completed at the
Betio Outfall site19 give the average percent cover for substrate and benthic categories on the
reef crest and reef slope, respectively. The crest has the same 65% undesirable algae and 10%
coral cover as for the subtidal reef flat. The slope has less of both, although blue-green algae
are at 10%. In contrast with the subtidal reef flat, the positive attributes of the reef crest are
that it has less turf algae and more coralline algae, albeit the fleshy variety. It has more
submassive coral, but with limited species richness beyond H. coerulea. The negatives are that
it has less rock and more rubble, and therefore less stable surfaces available for re-growth.
Figure 4-5 Betio reef crest substrate and benthic categories
Source: Fellenius Consultants 2017 (after footnote 19)
In contrast with the reef crest, the positive attributes of the reef slope are that it has less turf
algae. The negatives are that it has less rock and more debris, and therefore minimal stable
surfaces available for re-growth. This is in part mitigated by the lower energy environment.
19 Ibid
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 34
Figure 4-6 Betio reef slope substrate and benthic categories
Source: Fellenius Consultants 2017 (after footnote 19)
The nearest diffuser (discharge point) for the sewage, that will also be used for brine disposal, is
located at a depth of 30 meters and is about 47 meters away (south) from the shallower and
nearest live coral (Hypnea coerulea).
Corals near the ocean outfalls on South Tarawa. including Betio outfall, were studied more
specifically by a monitoring team in 2005. The team used a line intercept transect methodology,
which involves placing a tape along a contour on the sea floor, and noting the substrates
beneath the tape and length at which they change. Transects were taken 100 m either side of
each outfall opening and at a control site. The results showed a greater coverage of dead coral
and of macro algae at the sites near the outfalls, compared with the control site. Nearer the
outfalls themselves, reduced diversity of coral species was observed.20
Pelagic fish form an important part of the local economy, both through commercial fishing
activities and game fishing, focusing on tuna. Fishing activity focuses on areas known to be
abundant and these occur throughout Kiribati waters and include several favored sites around
Tarawa, usually distant to the coast. For lagoon and coastal fisheries, overpopulation pressures
in South Tarawa are threatening the sustainability of these fisheries through overfishing.21
20 Tonganibeia, K. 2005. Impacts assessment of Betio, Bairiki and Bikenibeu Sewage Outfalls on Coral Reef. Report
prepared for PMO and Steering Committee, SAPHE.
21 Campbell B, Hanich Q. 2014. Fish for the future. Fisheries development and food security for Kiribati in an era
of global climate change. Project Report 2014-47. Worldfish. Penang, Malaysia.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 35
Protected and conservation areas. While Kiribati has several protected areas, there are
currently no actively managed conservation areas in the Gilbert Islands. There have, however,
been efforts in the recent past, including the North Tarawa Conservation Area which was
officially established in 1996 and the North Tarawa lagoon was also proposed as a key
biodiversity area due to its habitat for endangered species; Green Turtles (Chelonia mydas), Big
Eye Tuna (Thunnus obesus), Humphead Wrasse (Cheilinus undulates), Giant clam (Tridacna
gigas). Mangrove, coral, and sea-grass ecosystems, which occur around South Tarawa, are of
conservation significance. Mangroves of the species Rhizophora stylosa, and Brugulera
gymnorhiza occur predominantly at the eastern corner of South Tarawa lagoon. Replanting of
the mangroves along the coastal areas in Kiribati including South Tarawa is on-going as part of
KAP III. Corals occur adjacent to the Betio outfall.
The 90 species in Kiribati that are classified on the IUCN Red List as threatened species include
72 corals, nine marine fish, two turtles, a giant clam and a mammal.
4.2.2 Terrestrial Resources
Flora. Indigenous flora and vegetation of Kiribati is among the least diverse and poorest on
earth.22 In the Gilbert Islands, including Tarawa, and some locations in other inhabited islands,
this flora has been severely modified or removed. Generally, terrestrial vegetation in Kiribati is
limited to coastal strand vegetation, mangroves and coastal marsh vegetation (limited), inland
forest, and pinnacle vegetation on limestone escarpments. The vegetation on South Tarawa is
substantially influenced by human habitation and has little biodiversity conservation
significance. The selected sites for the proposed the project are located at areas with varying
degrees of disturbance to natural vegetation but is dominated by ferns, coconut palm, saltbush,
breadfruit and te ango (Permna serratifolia), pandanus (Pandanus fanning enosis) and starbuck
island daisy (Bidens kiribatiensis).
Terrestrial fauna. There are no endemic mammals or avifauna on Tarawa.23 Two avifauna
species are included in the 90 species classified on the IUCN Red List as threatened species.
Species of seabird that are commonly sighted on South Tarawa include a black tern (Anous
minutus morcusi) and white tern (Gygis microrhyncha). The sparse number of avifauna may be
influenced by the high population on South Tarawa and probably the impact of the invasive
ship rat (Rattus rattus). The rat is a nuisance in almost every household on the island.
22 GOK - MELAD. 2013. Kiribati Biodiversity Area Report (South Tarawa, Kiribati). 23 Two endemic avifauna species exist on Kiritimati (Christmas) Island.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 36
4.3 Socio-Economic Environment
4.3.1 Population
South Tarawa is densely populated, with inhabitants originating from islands throughout the
group as well as South Tarawa itself. Even between the main urban areas of Bonriki, Bikenibeu,
Bairiki and Betio, land is almost entirely taken up by residential, commercial and communal
buildings and their surrounding compounds. According to the 2015 census the population
stands at some 56,388 people representing an average population density of around 2,772
people per square kilometer (km2) over less than 15 km2 of land area. Within the urban areas,
such as Betio, it reaches 10,377 people/km2 which is very high among Pacific capitals (c.f. Apia
- 6,534 people/km2, Majuro - 2,628 people/km2, Nuku alofa - 2,073 people/km2 and Funafuti -
1,872 people/km2 ). While measures were taken in the past to encourage migration to outlying
atolls, at present extensive in-migration occurs and the population of South Tarawa is growing
by 4.4% per year (Figure 4-7). In 2015, at the time of the last census, the population of South
Tarawa represented some 51.2% of the total population of Kiribati. The average household size
is large, at seven people per household and households with 15 or more inhabitants are not
uncommon.
Figure 4-7 Population of Kiribati and South Tarawa 1930 – 2010
Source: GOK-MFED - Kiribati 2010 Census. Volume 2: Analytical Report (2012)
Due to this overcrowding effect, South Tarawa faces serious environmental and social
problems, pollution of ground water, polluted lagoon and beaches due to open defecating,
scarcity of freshwater and high unemployment.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 37
4.3.2 Economy
The economy of Kiribati features the extreme distances between its islands (the two gaps
between the three island groups are both approximately 1,000 km), paucity of natural
resources and distances to international markets. Fishing licenses, copra and seaweed provide
some international revenue, and many Kiribati families are reliant on remittances from family
members working offshore, often in international merchandised and fishing vessels. Some
tourism takes place. Competition is high among Pacific nations to market traditional attractions
such as secluded beach locations, and culture, and Kiribati is not well located in terms of
proximity to the major markets of the United States, Japan, Australia and New Zealand and
therefore does not compete easily with other tourist destinations in the Pacific. However, war
relicts from World War II (WWII) on South Tarawa in particular Betio, game fishing and the
millennium islands, (whose proximity to the international dateline provides them with the
distinction of being the first to celebrate each New Year) encourage some visitors. Visitors
number between 3,000 and 4,000 each year and bring some significant revenue.
The economy of South Tarawa reflects its fu tio oth as the atio s apital a d the ai sea and international airport. The service sector accounts for most employment and 80% of jobs
are with the public sector.
4.3.3 Infrastructure, Public Services and Utilities
Transport. There are only two paved roads on South Tarawa and Kiritimati. A program to
construct causeways between North and South Tarawa was completed in the mid-1990s. The
road throughout South Tarawa except Tanaea has been rehabilitated to a quality standard with
funding support from ADB and World Bank. The causeway connecting the rest of South Tarawa
to the main shipping port located at Betio is being rehabilitated with completion scheduled to
beginning of 2019.
Kiribati has 21 airports; two of them (Bonriki and Kiritimati) served by international flights, only
four of them with paved runways. The country has domestic fleets to serve the outer islands.
Water supply. The existing public water supply system is operated by Public Utilities Board
(PUB) for the entire population on South Tarawa. Overall the water supply infrastructure is in
poor condition with numerous water leakages in the reticulated system. Fresh water is supplied
from fresh groundwater reserves extracted from a total of 28 galleries in Bonriki and Buota,
with a total sustainable yield from the groundwater lenses of 2,010 m3/day. An estimated fresh
water demand for South Tarawa by 2020 is 3,735 m3/day projected under the high population
growth and conservative leakage control scenario. Although rainwater is harvested by
residents, this is not enough to augment supplies from the reticulated system in South Tarawa.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 38
Supplementing water supply by Seawater Reverse Osmosis as proposed in this project will
provide a sustainable freshwater supply to meet the growing demand.
Electricity supply. PUB is responsible for the electrical power supply on South Tarawa. There
are approximately 6,331 households connected to grid with a contracted power per household
of about 500 to 700 watts. The average monthly consumption of electricity lays between 150
and 200kWh; with monthly bills for electricity of AUD 60 to 80 per household. The number of
illegally connected households is not known; PUB is just planning an investigation. Beside the
domestic connections, there are 897 commercials and 408 industrial companies connected to
the grid. Yearly there are 10 to 12 black-outs, caused by technical problems and with an
average duration of 1-2 hours.24 In addition, costumers suffer eventual short shutdowns of the
energy supply, caused by failures of the distribution system, the poor state of wiring or the
deficient internal electrical installation. The addition of a solar PV system in this project will
have a positive impact on the energy supply in South Tarawa to increase general grid stability.
4.3.4 Health Services and Profile
In Kiribati, health services are provided by the Ministry of Health and Medical Services. The
Ministry has three core departments, the Health (Curative) Services, Public Health and Nursing
Services. On South Tarawa there are several clinics and two hospitals, Tungaru Central Hospital
and Betio Hospital providing health services to the public. Amongst several duties of the Public
Health Department one of its responsibility under it Environment Health Section is to monitor
the quality of water from the well-water, rain water, PUB reticulated water, ocean water and
lagoon water. Samples of the above water sources are collected and tested once every 8 weeks
from the specified established sites. PH, Conductivity, Dissolved Oxygen, Salinity, Turbidity,
Temperature, Chemical test (nitrate/nitrite, chlorine, lead) are tested on site or at the mini lab
while micro-biological testing (Coliform and Faecal Coliform) is done in the hospital laboratory.
Testing of water from private water sources can also be arranged.25
Over the period 2014–2016 there were 80,000 reported cases relating to deficiencies in water
supply and poor sanitation on South Tarawa. The cases include diarrhea, dysentery,
conjunctivitis, and fungal infections including ringworm. In 2016 alone, there was an excess of
10,000 reported cases across South Tarawa. Also, numerous cases of other water related
disease such as scabies, tinea corpis, tinea versicolor and worm infections have been reported
and have continued to increase over the 2014 – 2016 indicating people are using unsafe water
24 Trama Tecnoambiental TTA. 2012. Kiribati Grid Connected Solar PV Power Station Project Environmental
Impact Assessment (prepared for MPWU and WB)
25 www.health.gov.ki (visited November 2017)
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 39
for bathing. However, the actual number of cases could be more as many cases are estimated
to go unreported.
To address this situation, a range of interventions focusing on the immediate water supply
infrastructure improvements, improvement of a water treatment system, and a continuous
awareness to encourage practice change to better hygiene and sanitation practices and
management of free roaming animals (dogs and pigs) are required. The p oje t s WASH
program will contribute to an improvement in the health of South Tarawa community.
4.3.5 Education
Education is free and compulsory for children between the ages of 6 and 14. I-Kiribati receive
seven years of primary education and five years of secondary education. On South Tarawa, 9
primary schools and 10 secondary schools provide primary and secondary education. Being the
capital of Kiribati, South Tarawa is the home of several tertiary institutions. In the Kiribati
Institute of Technology, (formerly known as Tarawa Technical Institute), offers courses in
technical and vocational subjects for more than 200 fulltime students, that finish their studies
with a certificate.26 The Marine Training Centre runs 18-month courses in deck, engine-room
and catering work on merchant-shipping lines; it trains about 200 students each year.27 There is
also the Kiribati Teachers College based in South Tarawa, offering training for primary teachers.
Kiribati is a partner in the regional University of the South Pacific, which has its main campus in
Suva, Fiji Islands, and a campus in Tarawa, Kiribati, with some 3,000 students, enrolled for a
wide range of courses using the university's distance learning facilities.
4.3.6 Cultural Resources and Historic sites
Ancestral shrines and te maneaba (meeting house) are the two important cultural resources on
land. Fishing traps, typically built on the reef flat on the ocean side of the island, by overlaying
reef boulders and stones, are of equal importance. None of these structures are present at the
project sites.
Tarawa was the scene of significant combat between Japanese and American forces during
WWII. The large guns and bunkers installed by Japanese forces remain in place and provide a
strident reminder of the events in the 1940s. Unexploded ordinance (UXO) is a public concern
as several UXO have been found buried underground at several locations on South Tarawa (i.e.
Betio).
26 http://kit.edu.ki/about.html
27 http://www.mtc-tarawa.edu.ki
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 40
5. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
The potential environmental and social impacts of the proposed project have been assessed in
line with the C““ a d de elop e t pa t e s safeguard requirements, including assessment of
the possible benefits and impacts with regards to (i) sustainable natural resource management;
(ii) pollution prevention and abatement; (iii) health and safety; and (iv) climate change. Like
previous ADB initiatives that improved water and sanitation services in South Tarawa, the
project will generate significant environmental and health benefits that more than outweigh
the adverse environmental impacts incurred during construction.
The project will rehabilitate existing water and electrical infrastructure, in an environmental
setting where habitat has been highly modified by the built environment, and the densely
populated community.
The following sections outline the potential negative impacts and risks associated with the main
project works:
• Sub-project 1: Construction and operation of a Salt Water Reverse Osmosis (SWRO)
water plant
• Sub-project 2: Rehabilitation of water supply infrastructure
• Sub-project 3: Construction and operation of a Photo-Voltaic (PV) power system
5.1 Design and Pre-construction phase
In addition to the identification of risks and impacts and required mitigations, during pre-
construction, measures to facilitate compliance with environmental regulations and provide
environmental and social protection and monitor the same will be implemented.
Environmentally responsible procurement. Proper implementation will promote continuously
improving environmental protection activities during design, construction, and operation to
prevent, reduce, or mitigate adverse impacts. Inclusion of mitigation measures in contract
documents for all subprojects, and assurance that the Project Management Unit (PMU) has
adequate capacity to implement the ESMP, including training of contractor personnel in the
requirements of the ESMP, will eliminate or minimize anticipated impacts. The ESMP will
require updating following the detailed design phase.
Management measures include:
• All land acquisition and resettlement issues to be resolved following the
requirements of the social safeguard due diligence reports. Provisions for land
access and compensation mechanisms to clearing of fruit bearing trees, vegetables
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 41
and if permanent structures are damaged or removed should be addressed
adequately.
• All subprojects will pass through the CSS. The EIA report will be prepared on behalf
of the executing agency and reviewed by the ECD within MELAD and the
development partners.
• Obtaining plans from the PUB showing the locations of utilities and infrastructure
(power, telecom, other) and consultation with residents and/or landowners on the
relocation of utilities prior to commencing excavation operations.
• The project ESMP will be updated based on the detail design and integrated into the
bidding documents.
• The contractor will designate a full-time experienced/qualified Environment Officer
to prepare the construction ESMP (CESMP) and implement all environmental
management and mitigations measures.
Appropriate environmental mitigation and monitoring measures are included in the
environmental and social management plan (ESMP). The proposed environmental mitigation
measures will form part of the design documents for the project and will be adequately
budgeted and included in the contracts for procurement of goods and services. All contractors
and subcontractors will be required to follow the project ESMP.
Contract tender documents will direct the contractor to provide qualified staff for
environmental, safety and health, management and monitoring, to prepare and implement the
CESMP.
Prior to commencement of any works, the CESMP will be prepared by the contractor, following
the project ESMP, and providing details related to their construction methodologies (including
site specific plans and drawings and sub-plans as required). The CESMP will be reviewed and
cleared by the PMU and development partners. The CESMP will address erosion and
sedimentation control (for land based, and marine works), health and safety, waste and
materials management (for land based, and marine works), control plans for traffic, noise, and
dust. The CESMP will also address all conditions on the environmental license as issued by ECD.
5.1.1 Impacts on Physical Environment
These impacts relate to topography, geology, and soils impacts and consideration of climate
change requirements during the design and pre-construction stage.
Climate change/natural hazard considerations. Planning for the potential impacts of climate
variability, and natural hazards, will help to mitigate against potential impacts which may
include sea water inundation resulting in failure of water and electrical systems infrastructure,
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 42
and subsequent loss of public water supply. The risks that are associated with climate change
and variability are related to sea level rise, sea surge risks, temperature rise, decreases in
rainfall (whether long term or in terms of extreme dry years or season) and storm
severity. The main vulnerabilities faced by the people of Tarawa can be summarized as:
• Sea-level rise which exacerbates the severity of sea surges, increased rates of
coastal erosion and heightened risks to public and private infrastructure;
• More intense and more frequent storms which increase risks of damage from sea
surges, high winds and strong inundation on public and private infrastructure; and
• More frequent and longer periods of drought: which cause both intense short term
difficulty and, of greater concern, long term damage to the freshwater lenses that
exist beneath the islets.
In addition, the energy consumption from the desalination facility presents a risk to enhancing
climate change through increased energy consumption and resulting increased greenhouse gas
emissions.
Mitigation measures include:
• Planning new infrastructure at a suitable elevation above the current high tide level
(utilizing accurate topographic survey);
• Ensuring new infrastructure is designed to withstand extreme weather events, such
as sea water inundation;
• Selection of renewable system (solar PV) in the design of power supply to support
desalination facility; and
• Design system to provide treated, safe water to reduce the requirement for
consumers to boil water for treatment using green-house gas emitting heating
sources.
Survey and clearance of UXO. Prior to commencement of any construction activities, a survey
for UXO will be undertaken. The TOR for the survey (and disposal) will be prepared by the
supervision consultant supporting the PMU. Should UXO be identified, these will be disposed of
following established government and police protocols and procedure.
Specific sub-project impacts. Subproject 1 will include boring and construction of 12 wells, in
phases, for water plant feed water has the potential to contaminate the fresh water lens with
high saline water. Adequate planning for well-depths below the freshwater lens, and proper
procedures for well-casing installation, will prevent lens contamination. Monitoring of
freshwater lens salinity levels, near the well-field should be planned for. Erosion and
sedimentation control plans should be developed for the plant site and for pipeline
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 43
construction alignment to the pump station, to avoid impacts to marine waters. For sub-project
2, erosion and sedimentation control plans should be developed for the alignment of water
reticulation to be rehabilitated, and water storage tanks sites, to avoid impact to terrestrial
habitat and marine waters.
5.1.2 Impacts on Ecological Environment
Terrestrial Ecology. As stated above, land-based earthworks for the subprojects, will not have
significant impacts on the existing topography, geology, and soils, or significant terrestrial
habitat. The project design proposes that site works will be in the same footprint as the existing
water, and electrical infrastructure. The terrestrial ecology has been extensively modified by
the built environment, and introduced species, in all areas. There are no protected sites in the
project area.
Marine Ecology. Project design for the discharge of brine from the SWRO plant via the newly
constructed wastewater outfall pipeline at Betio, considered the recommendations of the
marine benthic habitat surveys, of the existing and proposed wastewater outfall pipelines,
conducted for the prior wastewater improvements project. The surveys determined that overall
reef health is impacted by sedimentation, macroalgae cover, and lack of suitable substrate for
coral recruitment.
Specific sub-project impacts. For sub-project 1, the brine discharge as per sewer outfall
pipeline route will follow the recommended alignment to minimize impacts to the lagoon
marine ecology.28 For sub-project 2, erosion and sedimentation control plans should be
developed for the alignment of water reticulation to be rehabilitated, and water storage tanks
sites, considering the vicinity of works near marine waters. For sub-project 3, vegetation
clearing should be kept to the minimum required for PV plant construction and operation, to
avoid additional impact to terrestrial habitat.
5.1.3 Impacts on Socio-Economic Environment
Land access. There are two main types of land tenure in Kiribati – private ownership and state
ownership. 95% of land is under traditional private ownership, while 5% is State-owned. The
project is expected to have minimal involuntary resettlement (IR) impacts. There is no
requirement for an Indigenous Peoples Plan as the majority (98%) of the South Tarawa
population is indigenous to the country. The desalination plant will be constructed on
government long-term lease land, leased until 2040. In all cases government land has been
28 Fellenius,K. and Hess,D.2015. Benthic morphology and marine life assessment for the siting of ocean outfalls on South
Tarawa. STSISP, MPWU Kiribati
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 44
sought for location of the storage tanks and booster pump stations. Where government land
was not available, private lands have been identified as potential sites for some of the storage
tanks and booster pumps. No relocation of housing or settlements or income restoration will
be required.
Planning for operations. The building contractor should be obligated to provide a relevant
training program to the operators. The training will ensure that the infrastructure is operated
according to the intended safe procedure, and that preventive and corrective maintenances are
undertaken appropriately.
Health and safety. The CESMP will include a health and safety plan which will address both
worker and community health and safety risks. Workers sanitation at worksites and any
facilities accommodating workers has to be accounted for prior mobilization to ensure that
no raw sewage is released directly into the soil or into lagoon or coastal water. These
arrangements will be either (i) arrangements with nearby homes or institutions that are
connected to the sewer system or (ii) use of portable toilets which are emptied daily into
manholes within the sewer system.
Negotiating working areas. Available space on South Tarawa is limited and laydown sites
to store containerized building materials may be required outside the project sites. In such
event, the use of GOK-leased land or state land should be arranged, or negotiation with
land owners if private land is to be utilized. Separate approval may be required by the ECD
and needs to be sorted and cleared prior usage of any land.
5.2 Construction Phase
5.2.1 Impacts on Physical Environment
Impacts associated with brine disposal pipe, permeate delivery and upgrading of the
reticulated system. The installation of pipeline requires excavation work and may
potentially affect underground power cables, tar sealed main road, concrete private
driveways, permanent structures and living plants.
Impacts will be mitigated by:
• Contractor to appoint experienced site supervisor for each works site;
• Contractor to undertake a condition survey prior to any works and planning works
to avoid damage to property and plant to the extent practicable. At the start of
works the contract supervisor will file a checklist confirming that necessary pre-
planning was completed;
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 45
• Refurbishing of road and disturbed ground to original status. Apart from the road,
disturbed ground resulting from earth works will be refilled, vegetation and trees
removed along the trenching route will be replaced where necessary.
Impacts associated with hazardous materials. Fuels, paints and lubricants will be used,
which pose a soil contamination risk if leaked or spilled accidentally. Existing asbestos
concrete pipelines may be encountered during excavation works and pose a hazard to
human health.
• All fuels or other potentially hazardous materials will be stored at secure and
managed sites (bunded and concreted floor and walls), identified by the contractor
and approved by the PMU/supervision consultant;
• Fuel and oil to be stored in bunded and concreted areas with 110% capacity.
• All hazardous chemicals will be clearly labelled;
• Spill kit, appropriate to the hazardous materials being used, to be kept on-site and
workers to be trained in its deployment;
• Regular checks for leaking oil or fuel from machinery;
• Ensuring that any leaks are promptly repaired and/or parts replaced within two
days as part of maintenance of vehicles and equipment to international standards;
• Any surplus hazardous materials shall be removed from the island when the
contractor demobilizes. The co t a to s o kshop ill ha e clearly marked waste
disposal bins to store filters, rags and waste oil, for disposal at the landfills; and
• All asbestos concrete pipe disposal will be supervised by a competent person,
trained in asbestos abatement. Pipe sections will be wrapped and marked with the
cautionary statement Da ge Asbestos-Containing Material . The pipe sections
will be buried at an authorized location.
Climate change/natural hazard considerations. Construction vehicles, equipment, and
generators will emit greenhouse gases during the period of construction but will not be a
significant contributor to overall greenhouse gases. Construction vehicles, equipment, and
generators will be serviced regularly to reduce emissions. Furthermore, locating construction
plant and equipment inland away from the shoreline is required to minimise risk of loss or
damage from ocean inundation.
Need for aggregate and construction materials. The pipes that are associated with the
desalination plant will be prefabricated and purchased by the project and will be either
stainless steel or plastic, to be decided by the contractor. However, the plant will require
some concrete for the pouring of a facility based and the plinth needed for all the reverse
osmosis skids.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 46
Depe di g o the desig spe ifi atio a d o t a to s de isio the lo al agg egates if required can be sourced from Te Atinimarawa Company Limited, the GOK aggregate
company. Imported aggregated if needed will require clearance from the Agriculture
quarantine office.
No additional mining for aggregate will be conducted by the project.
Solid waste management. The contractor is required to minimize the environmental impact of
its work by adopting respectful waste management behavior and fulfilling national norms and
regulations. The Contractor is required to:
• Prepare a solid waste management plan as part of the CESMP;
• Separate and store wastes with respect for health and environment. Identify any
waste that can be reused or recycled;
• Contain all stored wastes in secure receptacles within construction sites and the
compound, avoiding littering and runoff;
• No waste is to be burned;
• Workers will be advised that littering will not be permitted. Waste generated
construction activities at sites will be cleared and disposed of as per the above;
• Use recycled or renewable building materials (e.g. timber) where possible; and
• Optimize and reduce waste production. Avoid mix of different waste and minimize
waste disposal into the approved dumping area or landfill.
5.2.2 Impacts on Ecological Environment
Impacts associated with upgrading of outfall for disposal of brine. The existing sewage
outfall pipeline will be utilized for brine disposal, therefore no impacts to the coral reef,
fish, and other marine fauna and flora are anticipated from the Project construction phase.
Likewise upgrading the sewage system at the outfall pump station from gravity feed to a
pressurized system will pose no effect on the biological environment around the pumping
station as there are no fruit bearing trees on the site. However, overflow and spillage of
raw sewage from the sump at the outfall pump station could occur during the upgrading
work when the brine pipeline is linked with the sewage outfall pipe. This can be minimized
by:
• Accounting for the likely overflow and spillage problems in the CESMP; and
• Having qualified personnel on site to oversee the upgrading work.
Impacts associated with construction of SWRO plant, Solar PV system and excavation
work. While there are no trees at the proposed location for the desalination plant, some
trees will be affected when installing the solar PV system at that site. A few coconut and
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 47
pandanus trees will be cleared to make space for the PV module array. To minimize the
effect, tree clearing will be marked on survey drawing or plan and removal will be
restricted to the identified trees/vegetation. All trees that are affected will be
compensated for in accordance with local policy.
Earthworks associated with the project have the potential to result in increased sediment
runoff entering the coastal marine environment, impacting marine water quality. Earthworks
will be required for the construction of the water plant and rehabilitation and replacement of
pipeline sections for water systems. Minor earthworks will be associated with the PV electrical
system improvements, such as possible power pole replacement.
Water quality impacts from earthworks can be mitigated as follows:
• Use of sediment retention fencing, berms, and sandbags around excavations to
restrict the release of sediment from the construction site;
• Use of siltation curtains to contain the site area around trenching works on the
near shore reef to prevent the release of sediment onto the surrounding reef area;
• Immediately re-vegetate and/or stabilize exposed surfaces and stockpiles of
excavated materials; and
• Monitor water quality for near shore waters adjacent to land base earthworks
Terrestrial ecology. The majority South Tarawa community area is built environment, which has
displaced any former natural habitat. Observed fauna consists mainly of introduced species
such as dogs, cats, and rats. Resident and migratory shorebirds are common along the fringing
reef, though typically found away from the residential areas. No surface water resources, or
associated flora and fauna, exist on South Tarawa. Construction noise and dust will not have
impact on any terrestrial habitat of value, and no mitigation is necessary. Clearing planting sites
may cause permanent or temporary disturbances to vegetation. While no known protected
flora species have been identified on the project sites, disturbance of vegetation should be
minimized.
The project will not introduce any alien species that are not yet established in the region of the
Project or promote species that are known to be invasive in the given environments. All vessels
carrying equipment and materials to the Project will be subject to inspection by agriculture
quarantine inspectors, and may be refused entry into Kiribati if they are known or suspected of
being infected or infested with disease or pests.
Mitigation measures include:
• Prohibition of burning vegetation and residual bushes and grasses when clearing
planting sites;
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 48
• Only cutting flora which are a direct obstacle to project infrastructure works; and
• All vessels carrying equipment and materials for the project will be subject to
inspection by agriculture quarantine inspectors.
Ecological impacts associated with spillage of hazard materials. The underground
freshwater lens at the project sites can be contaminated from fuel and lubricants leakages.
The effect can be mitigated by:
• Regular checks for leaking oil or fuel from machinery;
• Ensuring that any leaks are promptly repaired and/or parts replaced within two
days as part of maintenance of vehicles and equipment to international standards;
and
• Contractor will implement the measures identified to mitigate the impacts from
storage and spillage of hazardous substances and other chemicals and materials.
5.2.3 Impacts on Socio-Economic Environment
Materials and plant haulage. The haulage of plant and materials to and from works sites and
need to relocate services/utilities (and therefore dig up roads and accessways) will create
temporary traffic disruptions and pose a risk to pedestrian safety. These risks will be mitigated
by:
• Contractor to prepare a traffic management plan as part of the CESMP; and
• Advance notification (through radio and newspaper) to advise road closures,
detours and the like to facilitate work activities.
Noise. Noise will be generated from all constructions sites (desalination plant, upgraded
water supply infrastructure, solar PV) during site preparation, delivery, trenching, and work
procedures that are required for each component such as metal works, welding, and
general carpentry work. Impacts can be mitigated by:
• Restricting the working hours to between 0800 hrs and 1700 hrs from Monday to
Friday, or Saturday if there is a need to work on the weekend, this is important,
especially in areas where residential dwellings are located adjacent to the
construction area, as in the desalination construction area and the upgraded water
supply infrastructure;
• Use of vehicles, plant and equipment, that comply with international standards for
construction equipment noise emission, such as Part 204 of US Federal Regulations-
Noise Emission Standards for Construction Equipment (40 CFR 204)). Verification of
such compliance from the country of origin is required;
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 49
• The CE“MP ill i lude easu es to eet the e ui e e ts of the WB s Environmental Health and Safety Guidelines (EHSG); and
• Maintenance repair should also be routinely performed during the construction
phase and making the record available whenever needed to the concerned
authority.
Dust generation and nuisance. Dust will be generated during the hauling, delivery,
excavation operations, trench refilling and compaction works. This can be mitigated by:
• Daily spraying/wetting of the access roads, sites (including excavated trenches for
water supply network upgrades) material and stockpiles;
• Locations for stockpiles of materials or waste materials will be approved by the
PMU/supervision consultant and by the ECD if required;
• Loose materials hauled to/from sites will be secured with a tarpaulin to prevent
debris;
• Ensure emissions are minimal through standardized site management such as dust
watering or stockpile covers;
• Removal of spoil to stockpile sites or use as refill material; and
• Contractor will provide equipment that conforms to international emission
standards, verified by emission test certificates and maintenance records, as in the
case of control of black smoke emissions.
To ensure that emissions from diesel generators, vehicles and other machinery are kept
within acceptable measures, the Contractor will be required to provide equipment that
conforms to international emission standards, verified by emission test certificates and
maintenance records, as in the case of control of noise emissions.
Social conflict. Social conflict between expatriate and local workers could arise due to cultural
differences. It is essential that expatriates are provided with information on Kiribati culture,
including dressing code, sexually transmitted diseases, and other essential social factors. A
code of conduct will be agreed between the contractor and the community (facilitated by
PMU/supervision consultant). The agreed code of conduct will be applied at all times. The
code of conduct will cover:
• How and when information will be communicated between the contractor and the
community;
• Schedule of activities and works (days and times) and if night-time or Sunday work
will be required;
• Conduct of the building and asset condition survey;
• Negotiations for access to land for temporary works, laydown areas and the like;
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 50
• Conduct and behavior while working in community, villages or close to churches or
schools etc;
• Identification of community leaders and appropriate ways to address them;
• Appropriate ways to address women;
• Avoidance of fraternization of workers with local people;
• Avoidance of use of inappropriate language or cursing when working close to
residences and shops;
• No differences in wages paid to men and women for similar work;
• No use of trafficked or child labor;
• Prohibitions on use of illegal drugs and alcohol and sanctions to be imposed;
• Implementation of the health and safety plan (including communicable diseases
awareness and prevention training); and
• Implementation of the grievance redress mechanism (GRM) and process for
resolving conflicts between workers and community members.
Occupational and community health and safety. All health and safety requirements will
comply with the EHSG. Work on the desalination plant, upgrade of water supply
infrastructure and installation of the Solar PV system will pose some potential hazards to
both workers and the public, resulting from construction works, excavation, vehicle
movements and the use of electrical power. The contractor will be required to:
• Prepare health and safety plan, complying with the EHSG, as part of CESMP;
• Works sites and contra to s offi e a d o pou d to e se u el fe ed a d a ess only permitted to workers and authorized people;
• For i-Kiribati workers, comply with Kiribati laws on employment and health and
safety and observe Kiribati statutory holidays;
• Under no circumstances, allow hild e to e te the o ks sites, o t a to s offi e and compound;
• Provide sufficient light coverage during night construction. Any light used during
night construction is not to affect neighboring residences;
• Designate a full-time, experienced/qualified Health and Safety Officer within
o t a to s staff; • Allocate responsibility for safety inspections to Health and Safety Officer;
• Regularly training of workers in safety precautions, for themselves and others and
for implementing emergency procedures;
• Engage an approved service provider to deliver a communicable diseases
awareness and prevention program including sexually transmitted infections (STI)
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 51
and HIV/AIDS. The program will be conducted regularly for works and the
community;
• Provide protective clothing and equipment (PPE) to workers appropriate to the
activities they undertake (including any activities at height);
• Ensure that vehicle and equipment operators are properly licensed and trained;
• Arrange for provision of first aid kits in all vehicles and facilities with trained staff
o all at the o t a to s offi e o o pou d/ o ks a d;
• Illegal drugs and alcohol will not be permitted on any works site and any worker
intoxicated while at work will be dismissed;
• Establish emergency and medical evacuation procedures and provide time for
workers to undertake training and drills in the procedures;
• Provide regular safety checks of vehicles and equipment;
• Identify hazard zones and provision of hazard warning signs at the construction
sites;
• Provide temporary fencing/barriers around potential hazards such as pipe trenches
and any excavations 1m or deeper to ensure there is no hazard to the workers or
public;
• Maintain a register of incidents and accidents detailing date, circumstances,
severity, action taken at the time or subsequently, outcomes and
actions/measures to prevent future incidents/accidents; and
• Implement the relevant elements of the GRM and maintain a complaints/grievance
registry.
• Munitions and explosives and UXO are a concern to the public and workers, given
the war history of South Tarawa. The following procedure will be put in place by
the contractor: The construction sites will be scanned by a qualified
munitions/explosives/UXO field support team to evaluate the presence of
munitions/explosives and determine the appropriate level of munitions/explosives
support requirements. UXO monitoring would be performed concurrent with
ongoing construction works. The primary method of support would be provided by
a UXO Technician in the field during construction works who would scan ahead of
the clearing/grubbing and excavations to identify areas of avoidance containing
potential munitions/explosives. Supervisors will conduct a munitions/explosives
awareness safety briefing for all construction personnel.
• All asbestos concrete pipe disposal will be supervised by a competent person,
trained in asbestos abatement. Pipe sections will be wrapped and marked with the
autio a state e t Da ge As estos-Containing Material. The pipe sections will
be buried at an authorized location.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 52
Impact on underground service utilities and other disruptions. During construction, service
outages may be necessary or occur due to accidental damage of underground service utilities
and disruptions to the public due to impacts to local traffic. Whilst accidental damage cannot
be entirely controlled the risk can be mitigated by ensuring the contractor has access to all
information from PUB on underground service locations. Furthermore, any planned
interruptions where services are required to be relocated or temporarily stopped during
construction for safety of workers, consultation of local residents is required prior to
commencing works. The contractor must also put in place measures to control traffic
movement to avoid congestion.
Impacts associated with encroaching onto private property and permanent use of site .
Work on upgrading the reticulated water supply network will take place within the existing
alignments and will not therefore encroach significantly on private property, however,
excavation work and the installation of components as well as vehicle movements, present
some risk where access is restricted. The locations of permanent ground water tanks could
also encroach on private properties. These risks will be mitigated by
• Consultation with and written approval from land owners for access when intrusion
on to private properties is inevitable; and
• Formulation of lease agreements in cases where the sites are not leased by
Government.
5.3 Operation Impacts
5.3.1 Impact on Physical Environment
Effect of greenhouse gas emissions. Desalination plants are energy intensive process and
hence contribute to global warming due to the use of fossil fuel that drives the system. The
generators running on diesel fuel will still be utilized in the proposed desalination plants,
however to compensate for the energy used, a solar PV system will be installed, for
supplemental electrical power. The use of solar PV system will reduce dependence on fossil fuel
and contribute to the reduction of greenhouse gas emission. Furthermore, provision of safe,
treated water to customers also reduces greenhouse gas emissions by reducing the
requirement for boiling water using greenhouse gas emitting fuels as the energy source.
Generated waste disposal. The operator of the desalination facility is required to minimize the
environmental impact of its work by adopting respectful waste management behavior and
fulfilling national norms and regulations. Spent filter cartridge and other solid wastes from the
desalination plant will be disposed at the Betio landfill through routine collection by the Betio
Town Council or by PUB whenever needed. On-site waste bins will be provided.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 53
5.3.2 Impacts on Ecological Environment
Effect of brine disposal on marine ecosystem. Brine effluent is known to have adverse effect
on benthic ecosystem. Due to higher concentration of salt levels the effluent is denser and
tends to sink to the bottom when discharged, directly impacting the benthic organisms around
the discharged location. Brine discharge, associated with SWRO plants, has been found to alter
the benthic community and reduce the diversity of organisms, including sea grass.
High salinity can also influence water turbidity, disrupting primary production through the
extinction of plankton species.29 The results of experimental exposure of corals to high salinity
varies widely depending on the species, the ambient salinity in experimental settings from
which they were collected and the exposure period. Available information suggests that salinity
tolerances in coral species depend on several factors including the speed, magnitude and
duration of salinity increase, ambient salinities before the change, individual species tolerance
levels, acclimatization abilities and whether salinity changes are occurring simultaneously to
other stressors such as temperature and turbidity fluctuations.30
Beyond the demersal environment, concentrations of nutrients and particulate organic matter
progressively decrease although the brine effluent with sewage plume provides a localized zone
where salinity is higher and concentrations of nutrient from plume are higher than in
surrounding waters. Fish are known to have acute chemical sensing capabilities and are
therefore likely to perceive concentrations of soluble nutrients and higher salinity water. While
it is not possible to predict what behavioral responses to these will be, fish can avoid the plume
and saline water if it is perceived as harmful. At the depth of the outfall opening, 30 m, coral
cover was found to be less than 5%, and most of the surface is comprised of sand and rock
outcrop. No seagrass habitat is present.31
Under the South Tarawa Improvement Sector Project the upgrading work on the Betio sewage
outfall will be completed mid-2018. Part of the upgrading is the addition of 12 diffuser ports at
30 m depth. The ports will alter the way in which the effluent is introduced into the ocean
water and level of dilution. The relevant changes include: (i) more rapid mixing of effluent from
the outfall with seawater, and (ii) introduction of effluent from the sewer systems at depth so
29 Munke, Frank: Ecological and economic analysis of seawater desalination plants - Diploma Thesis. Matri. No.:
1157140 Karlsruhe, April 2008
30 RPS Environment & Planning Pty Ltd. 2009. Effects of a Desalination Plant Discharge on the Marine
Environment of Barrow Islands. WA, Australia. Report # N09504. 31 Fellenius,K. and Hess,D.2015. Benthic morphology and marine life assessment for the siting of ocean outfalls on
South Tarawa. STSISP, MPWU Kiribati
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 54
there is lower levels of nutrients and organic matter close to the surface that will prompt
eutrophication.
Marine water quality. The proposed outfall discharge, at 30m depth, will provide for rapid
dilution of effluent with ocean water, immediately on release and incrementally as the effluent
disperses in the form of an expanding plume. The Project s use of the e outfall pipeli e fo brine discharge is not expected to impact coastal marine water quality, especially in the near
shore.
The dilution of effluent will be maximized by ensuring that release occurs at a depth of 30
meters beneath the water surface (compared to the previous situation where release of
sewage occurs near the surface, within the intertidal zone), the fitting of a diffuser at the outfall
opening which causes effluent to be released in a series of small jets, increases near field
dilution. Salinity testing of marine waters in proximity to the brine outfall discharge could
define the influence of the brine discharge, and distance required for waters to reach ambient
levels.
Collection, dilution and dispersal of discharge from RO desalination plant. Effluent from
the desalination plant is a combination of brine representing about 99% of the effluent,
while the rest is backwash water, maturation rinse, and the neutralised waste from the
chemical cleaning process. The waste brine will be combined with the sewage effluent
immediate after the outfall pump station prior to discharging. There is no sewage treatment
facility at the pump station so the brine will not interfere with any biological treatment process
as the sewage is raw. The combined effluent will exhibit an estimated salinity greater than
seawater, thus making the effluent discharged at the Betio outfall denser than the ambient
seawater level. The effect of brine and associated sewage plume on the marine environment
depends on the dilution factors attained when discharged.
Dilution of the waste discharge has been measured at desalination plants in the Canary
Islands32 and north-west Mediterranean Spain.33 The volume of waste brine from the Canary
Islands is 17,000 m3 per day and 75,000 m3 per day for the latter. Samples taken 20 m from the
Canary Island outfalls show rapid near-field dilution of waste brine to near ambient levels. A
similar investigation of dilution rates was completed at a RO plant in the north-west
Mediterranean. That study also found rapid dilution of brine with ambient salinity achieved at
32 Talavera,J.L.P. & Ruiz, J.J.Q. 2001. Identification of the mixing process in brine discharges carried out in
Barranco del Toro Beach, South Gran Canaria (Canary Islands). Desalination, 139, 277 – 286
33 Raventos, N., Macpherson, E. & Garcia-Rubies, A. 2006. Effect of brine discharge from a desalination plant on
macrobenthic communities in the NW Mediterranean. Marine Environmental Research, 62, 1-14.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 55
10 m from the outlets. For the latter, salinity level decline rapidly close to the outfall. The
measurement of salinity level from the above outfalls, in general, suggested that elevated
salinity declines rapidly close to the outfall even where simple diffusers are employed.34
The brine waste from the proposed SWRO plant is predicted at 7,030 m3 per day and peak
operation at 9,681 m3 per day in future operation, however it is expected that there will be very
rapid dilution due to the small volume of output and use of diffusers. The United States
Environmental Protection Agency effluent plume model UM3 was run to define plume
movement and decay in relation to high salinity effluent, for the design of this sewer outfall.
The performance of the model has been tested by comparing model predictions against actual
measurements using Laser Induced Fluorescence, which makes three dimensional
measurements of contaminant concentrations. UM3 was found to provide reliable estimates
for plume movement, as well as near and far field dilution.35 A further feature of UM3 is that it
supports the analysis of different levels of salinity, which is important for this situation. Finally,
the model enabled the estimation of effluent dilution both immediately on release (near field)
and at distance (far field). The following parameters (Table 5-1) were used in the UM3 model.
Table 5-1 Model parameters
Parameter Value Justification
Port Diameter 100mm Diameter of each diffuser port
Number of ports 12 Betio outfall has 12 diffuser ports elevated at 30
degree angle.
Depth of outfall 30m Maximum depth of end of diffuser pipe
Current speed 0.2m/s Current speed at Betio outfall at 30m, 25m and 15m
according to 2015 SMEC study ranges between 0.2
m/s to 1m/s. Lowest velocity is used. Even in calm
water, current speed at the outfall is within that range
due to tidal movement which is further influenced by
the adjacent ship channel.
Effluent discharge rate Value for producing
6,000 m3 is used
Based on projected combined discharge from Betio
sewerage system
Concentration of fecal
coliform
100,000 MPN/ 100 mL Based on tests undertaken for preparation of the
SAPHE project and used in the STSISP project
34 RPS Environment & Planning Pty Ltd. 2009. Effects of a Desalination Plant Discharge on the Marine
Environment of Barrow Islands. WA, Australia. Report # N09504.
35 Philip JW, Roberts PJ and Tian X (2004). New experimental techniques for validation of marine discharge
models. Environmental Modelling & Software 19 (7-8): 691-699.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 56
Parameter Value Justification
Effluent Salinity
Value for producing
6,000 m3 is used
The salinity level at maximum capacity of Desalination
plant is used
Ambient seawater
salinity
35 ppt Typical value for seawater
Effluent temperature 30oC Assumed
Ambient seawater
temperature
29oC Measured temperature of seawater at 30m depth
Based on the parameters used an indication of plume elevation and dilution are shown in
Figure 5-1. A dilution factor of about 100 is attained 6 meters from the point of discharge when
the current velocity used in the UM3 model is 0.2m/s. The point of discharge of effluent at
Betio outfall is a well mix area prone to wave surge and currents providing a good environment
for diluting the high salinity effluent.
Figure 5-1 Plume elevation profile and dilution
Other wastes from the desalination plant. The other wastes to be considered from the
desalination plant include spent filters and general office wastes. A provision of appropriate
waste bins and regular disposal at the Betio is required.
Risk associated with the failure of the desalination plant. Failure of the desalination plant,
especially the desalination membranes or post treatment system, will result in the discharge of
seawater and chemicals entering the water distribution system. Also, the failure of the brine
disposal transfer pipeline will affect the local salinity of the aquifer in the area directly affecting
the local plants especially fruit bearing plants.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 57
The failure of chlorination system can also affect the quality of reticulated water. Water leakage
is another long-term problem that is often associated with the water supply system on South
Tarawa. These risks can be reduced with regular inspection and maintenance.
Risks of failure can also be reduced if proper protection of the installations are adopted to avoid
accidents, and the damaging, or unauthorized removal of the technical equipment. It is
proposed that unauthorized access to the RO plant, PV modules structures, and exposed water
supply infrastructures is prohibited by means of fences with lockable gates, lockable manholes
for underground water valves, and that visible signs indicating danger and no-go-areas are
displayed visibly to the public.
Impacts associated with lack of water quality test. The quality of water produced from the
desalination plant and extracted from the water reserve still must be routinely tested for
consumption suitability, to assure public health. In Kiribati, the salinity of the drinking water
should not exceed 600 mg/L and should be free of pathogens as per the World Health
Organisation guideline for pathogens36 that is normally adopted as a national guideline.
Samples from all storage tanks should be taken monthly for testing. PUB should also liaise
regularly with the Ministry of Health and Medical Services on their routine water sampling and
testing program to ensure that the results are shared. Where negative results are attained, PUB
should promptly provide remedy to rectify the salinity of the reticulated water. Further, the
public should be promptly informed to boil water when the chlorination system fails and the
presence of pathogen is detected.
5.3.3 Impacts on Socio-economic Environment
Risk associated with solid/waste disposal. Although the project will improve the supply of
water to the public, contamination of ground freshwater lens will persist and worsen overtime
if open defecating practices, animals (dogs and pigs) are still allowed to roam around, and
illegal rubbish dumping. The WASH community consultation program incorporated in the
project to encourage community participation in solving the problem will assist to address and
p o ide e ed to this o ti ui g a d u ge t issue du i g a d e o d the p oje t s life.
Health and safety risks associated with mishandling of chemicals. Anti-scaling agents and
cleaning chemicals will be used in the desalination plant and chlorine gas will be used to treat
water from the Bonriki water reserve and desalination plant. Although the chemicals to be used
are applied in small doses when applied into the system proper, handling should be practiced to
36 WHO. 2008. Drinking Water Guideline - 3rd Edition (incorporating the first and second addenda, Vol 1
Recommendations). Geneva.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 58
minimize health risks to workers and the public. Hazardous chemicals should be adequately
labelled, stored safely and handling procedures should be visibly displayed at appropriate
locations. Staff should be trained on how the chemicals are handled safely, specifically chlorine
gas cylinders.
Noise impact. Noise associated with the high-pressure pump in the desalination plant will be a
nuisance to nearby residence if noise is not contained within the plant. Noise reduction or
acoustic packages is recommended and should be installed to reduce noise emitted from the
plant. Workers will be required to wear proper hearing protection.
5.4 Positive Impact on Health
The additional clean water from the desalination plan and rehabilitated water infrastructure
proposed in this project will ensure that the wider community have access to safer water and
that the recommended 50 liters per person benchmark for ensuring low levels of health
concern is achieved, limiting negative health issues that are related to poor water quality and
insufficient quantity. Improvement in health of individuals will result in improved economic
situation through being more productive. This can also lead to a wider economic benefit.
However, achieving that level will be impractical unless there is a change in attitude of people
toward good sanitation practices, and that the existing sanitation infrastructure is adequately
improved throughout the island. The WASH Awareness Program along with sanitation
improvement projects such as STSISP will contribute towards improvement to that end.
5.5 Cumulative Effects
The effect of this proposed project depends on the dilution of brine water discharge. The
predicted result from the UM3 model indicates suitable dilution is attainable at the lowest
current velocity noted in the area.
There will be no cumulative effect on the local aquifer at the desalination project site due to
the use of seawater extracted from below the freshwater lens.
Training on the operation and maintenance of the systems installed will also add to the
technical capacity of PUB.
The use of the PV solar system in this project in combination with the previously installed PV
solar system under the Kiribati Grid Connected PV Solar Power Station Project will increase the
capacity of green energy. This could lessen the overall demand for fossil fuel over time thus
increasing the probability of reducing tariff costs.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 59
6. ANALYSIS OF ALTERNATIVES
6.1 Alternative to the SWRO
The alternative supplementary sources of water were assessed in the Tarawa Water Master
Plan 2010-203037 report and were also addressed in the environmental assessment that
accompanied the South Tarawa Water Supply Options Assessment Desalination Feasibility
Study.38 The water sources included: bulk importation by ship, constructed rainwater
catchment, recycling, the construction of island for groundwater collection and pumping, and
construction of a SWRO water plant. The Master Plan assessment concluded the following:
• Bulk importation is extremely expensive and might only be suitable to emergency
only,
• Rainwater catchment is constrained by vulnerability to prolonged drought,
shortage of space, high costs, and difficulties with keeping the water free of
contamination.
• The scope of water recycling is limited as extensive recycling of water sourced from
household wells already occurs throughout Tarawa.
• The construction of an island for ground water collection is capital intensive and
would pose several environmental problems associated with the substantial
amount of aggregates needed to create such an island
• The saltwater reverse osmosis option was adopted as the most economical means
to argument water supply on South Tarawa, provided it can be effectively
maintained throughout 10 years and more. The system can be containerized and
hence tested for workability according to design preference and performance
before shipment, located in area of highest demand and direct connection to the
existing water supply network, limited land area requirement, producing high
quality of water, and that the system can incorporate an energy recovery system
that reduces the amount of energy used by the plant.
6.2 Alternative Location of Desalination Plant and Brine Disposal
Twelve different sites (Table 6-1 and Appendix 3) were proposed and considered for the
location of the desalination plant. The lands with private ownership (sites 1 and 2) were
37 White, I. 2010. Tarawa Water Master Plan 2010 – 2030. GOK. 38 GOK & ADB. South Tarawa Desalination Plants Environment Assessment in Fraser Thomas Partners. 2012.
South Tarawa Water Supply Options Assessment Desalination Feasibility Study. STSISP TA-7359(KIR). Volume 1.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 60
eliminated due to complications with land procurement. Identification of landowners involves
court proceeding that can last for more than a year. Sites 3 and 5 are zoned as open space and
therefore are eliminated based on social sensitivity of the area. A transmission tower is located
on Site 4 and will create limitations on land area with significant impact on site layout. Also, the
site is not ideal for sourcing feed water from the bores. Site 10 at Bonriki is not ideal as major
portion of the land is swampy and not ideal for construction, bores will be remote from
desalination plant and require their own electrical power system, a new water transmission
pipeline from Bonriki will be required possibly connecting to the existing pipeline around Ambo,
and strategically it is preferable to have two water supply systems locate at either end of South
Tarawa with the SWRO plant located at Betio where population density is highest and located
furthest from the Bonriki groundwater reserve. Site 12 at Bairiki was considered as it is also
close to Betio. The site however is too sandy and there may be a need to improve soil bearing
capacity. It is located in close proximity to residential area and the church so noise level has to
be considered. Additionally, the area is prone to destructive waves during extreme westerly
bad weather event thus coastal protection structure may be needed bearing additional cost.
Site 6, 7, 8, 9 and 11 are all located at Betio and mostly suitable for the desalination plant. Site
11 was eliminated as PUB will be relocated to the site. Even if the site is available the total
length of pipeline required for brine discharge is around 2.8 km running through the residential
area. Site 6, 7 and 8 are also ideal locations but extra distance is needed to run the brine
discharge to the ocean to miss the cemetery and residential buildings.
The preferred location is site 9. It is located more than 100 meters from the shoreline and
therefore will not be exposed to coastal wave events which might cause local inundation. The
ocean outfall pump station that can provide a means of brine disposal is located across the
road, saving approximately more than US$2 million from building an independent outfall
system for the plant.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 61
Table 6-1 Proposed sites for the Desalination Plant
Site #
Description
1 Vacant land opposite the Parliament in Ambo
2 Abaokoro on the ocean side in Ambo
3 Land to the west of the Nanikai landfill site
4 Land on the eastern end of the Bairiki causeway
5 Land in Betio, on the ocean side between the WW2 heritage artifacts and Taiwan Park
6 Land in Betio, eastern area used by Nippon Causeway contractor, Betio
7 Some of the land currently occupied by the meteorological office, Betio
8 Land currently occupied for container storage, Betio
9 Land in Betio, western area used by Nippon Causeway contractor
10 Location on Bonriki Water Reserve
11 PUB Water Yard up to and including McConnell Dowell site/MPWU Civil yard
12 Bairiki end of Dai Nippon Causeway (South) currently occupied by Ferris wheel
6.3 Alternative to Desalination Design
Seawater desalination can be achieved through reverse osmosis and distillation. Distillation is a
phase separation method whereby saline water is heated to produce water vapor, which is
then condensed to produce freshwater. The various distillation processes used to produce
potable water, including Multi-Stage-Flash, Multiple Effect, Vapor Compression, and Waste-
Heat Evaporators, all generally operate on the principle of reducing the vapor pressure of water
within the unit to permit boiling to occur at lower temperatures, without the use of additional
heat. Distillation units routinely use designs that conserve as much thermal energy as possible
by interchanging the heat of condensation and heat of vaporization within the units. The major
energy requirement in the distillation process thus becomes providing the heat for vaporization
to the feed water. However, the methods require high levels of technical input for operation
and maintenance.
Reverse osmosis, a preferred design, does not require the need to vaporize the water, but only
the use of membranes with controlled pore size, separating water from the saline solution.
6.4 Alternative to Feed-water Sources
The alternative feed water sources are the underground blackish water and the coastal
seawater. Although the underground blackish water has lower salinity and therefore reduced
energy requirements for desalination, it is polluted with variable concentration of solutes that
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 62
can lead to operational difficulties. The coastal seawater on the other hand tends to contain
variable solutes and it is a highly turbid environment requiring more efforts to filter. The feed
water obtained from bore holes below aquifer are naturally filtered and has more constant
solute and impurity levels.
6.5 Alternative to Brine Delivery Pipeline
Apart from the preferred alternative, where a simple excavation across the road is done to
provide sufficient work space to lay the transfer pipeline for brine discharge from the
desalination plant to sump at the ocean outfall pump station, construction using horizontal
directional drilling (HDD) is another option.
The HDD is used to bore through the ground and involves a GPS-guided drill head creating a
bore hole from the surface at the outlet of the desalination, to a few meters below the surface
under the road to the desire location at the pump station. The technique can maneuver the
drill head horizontally and vertically to maintain the required angle and route. The technique
will enable the placement of the borehole through the ground and feeding the brine transfer
pipe through the borehole, avoiding the need to dig trenches which would damage the newly
completed tar sealed road surface at which the pipe can be laid.
Horizontal directional drilling is done with the help of a viscous fluid known as drilling fluid. It is
a mixture of water and, usually, bentonite or polymer continuously pumped to the cutting head
or drill bit to facilitate the removal of cuttings, stabilize the bore hole, cool the cutting head,
and lubricate the passage of the product pipe. The drilling fluid is sent into a machine called a
reclaimer which removes the drill cuttings and maintains the proper viscosity of the fluid.
Drilling fluid holds the cuttings in suspension to prevent them from clogging the bore. A clogged
bore creates back pressure on the cutting head, slowing production. For environmental
compliance, the viscous fluid must be recovered for proper disposal.
The method is constrained by the availability of freshwater, a scarce resource on the island. The
use of HDD is further constrained by the fact that it works best with solid rock or sedimentary
material and that soils with cobblestone are not recommended. Most of the ground materials
on the atoll island few meters below surface is sand. The existing underground utilities are also
subjected to damage and repair may require trenching.
Excavating across the road is preferred as compacting and resurfacing of the small excavated
road surface area is only required. The existing machinery used on the road project which will
be used by Dai Nippon Construction to rehabilitate the Bairiki-Betio causeway can be used for
the work.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 63
6.6 Location Alternatives for PV Solar System
The proposed site is located within the Bonriki water reserve area away from the public and
therefore there will be no social disturbance during the construction and operation of the
installment. Clearing of trees (coconut trees, pandanus trees and scrubs) will be minimal and
should be contained within the recommended area to install the PV modules and other
appurtenances required. The area is accessible by unpaved dirt road.
An alternative to this site is the use of roof tops of several, GOK and Church owned, high school
buildings. This alternative will mean that the system will be installed in small units due to the
area restrictions of the roof top adding to the complication of installation, operation and future
maintenance.
6.7 The No Project Alternative
The main implications of the no project alternative are that the current water shortage problem
will worsen in the immediate future with the status of the existing water supply system.
Additional demand on the existing water reserves will increase to the level that it will no longer
be able to sustainably supply potable water, if the current extraction rate continues, from the
freshwater lens source. The health risks that are related to insufficient and poor quality of
water will increase. Additional climate change associated increases in sea level rise and the
frequency of inundation events, may catastrophically impact the present system of infiltration
galleries, where groundwater is extracted for the current water system, as seawater inundation
would render the shallow groundwater non-potable.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 64
7. INFORMATION DISCLOSURE, CONSULTATION, AND GRIEVANCE REDRESS
7.1 Public Consultations
During project preparation, formal consultations took place with participants from Betio,
Bonriki and few other villages on South Tarawa. The consultation told placed at community
halls (maneabas). Meetings at each of the community halls to disclose information on the
project, including descriptions of the project, potential environmental impacts, and to seek
feedback relating to the project and any concerns, were held between 3rd and 11th February
2018. Minutes of meeting, highlighting key questions raised is included as Appendix 4 and
attendance records show a total of 190 people attended ranging from 15 people in Bairiki
through to 50 people in Bangantebure (Table 7-1).
Table 7-1: Summary of Meeting Participants
Village Date No. of participants
Male Female Total
Betio (Temanoku) 3 Feb 2018 8 10 18
Betio (Temakin) 6 Feb 2018 15 30 45
Bairiki 9 Feb 2018 9 6 15
Teaoraereke 7 Feb 2018 13 18 31
Bangantebure 11 Feb 2018 15 35 50
Bonriki 11 Feb 2018 21 10 31
Total 81 109 190
Source: STWSP PPTA consultations (2018)
7.2 Summary of Issues Raised
At the consultation meetings, the public were informed of the main components of the project
that includes installation and operation of a RO desalination plant and solar PV system, and the
upgrading of the water supply system on South Tarawa. The activities involved and proposed
locations for each component were presented including the reasons why these locations were
chosen. For the desalination plant information on the production capacity, source of feed
water, how the brine will be disposed, potential environmental impacts of brine on the marine
and terrestrial ecosystem were disclosed. Other environmental and social issues that could
arise during the construction were discussed specific issues related to (i) land access, (ii) effect
of encroaching onto private properties, (iii) excavation works and related impacts on trees and
permanent structures removals, noise, dust, increased traffic that would cause nuisance during
construction, destruction of the newly completed tar-sealed road and impacts on traffic.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 65
Mitigation measures for each impact, and the benefits associated with the implementation of
the project, formed parts of the discussion during the consultation meeting.
Issues raised at these meetings, related to the existing situation caused by the poor state of the
water supply system, to impacts of construction, and some further concerns. Issues relating to
the state of water supply system were (i) some areas in Bonriki and along the lagoon side at
Bangatebure and Eita are not connected to the reticulated water supply system, and (ii)
freshwater extraction from Bonriki water reservoir has increased the salinity level of water in
the village and could worsen if the existing extraction rate continues.
Concerns over construction were (i) removal of trees/permanent structures and destruction of
the newly completed tar-sealed road where excavation took place to lay pipes and other
components of the reticulated water supply system, (ii) effect of drilling boreholes on the
ground stability, and (iii) labor recruitment has been observed with the on-going and past
p oje ts as ased o ho k o s ho ithout follo i g atio al guideli e fo e uit e t –
there were element of favoritisms observed by the community. It was suggested that the
number of laborers needed should be divided equally between and recruited from all
communities on South Tarawa.
Further concerns raised were (i) effects of brine disposal on the marine ecosystem, (ii) effect of
pumping feed water from boreholes on the freshwater lens, (iii) concern of cost increase for
water to compensate high production cost from the desalination plant and request that cost of
reticulated water be kept at minimum level, (iv) fabricating water pipe connections by
individuals causing damage to the reticulated system, poor repair and hence sustainability of
infrastructure.
No concern was expressed over temporary effects of construction.
The effect of brine disposal on the marine ecosystem and pumping feed water from boreholes
on the freshwater lens were also the two major issues raised during the WASH consultation
meetings for undertaken as part of other PPTA activities.39
A few suggestions were raised during the meeting and include; (i) the production of salt from
the brine wastes, (ii) Government to create a reserve fund that can be used to compensate
landowners for having their land disturbed during the excavation work to lay pipelines, and (iii)
increase the compensation amount per tree (trees supporting livelihood) from the current
level.
39 South Tarawa Water Supply Project PPTA WASH Output report
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 66
7.3 Means of Addressing Issues Raised
The issues of main concern, namely the effects of the current state of the infrastructure, will be
addressed by the proposed infrastructure improvements. The water reticulation system will be
installed at Bonriki and other areas not connected to the system. Salinity level of wells in
Bonriki is anticipated to improve as water extraction will remain unchanged overtime. Concern
over the removal of vegetation and structures during construction will be limited to sites where
individual items of equipment or damaged sections of pipe need to be replaced. However, the
need to avoid the removal of or damage to trees during excavation, and replanting as required,
is included in the ESMP. Likewise, a resettlement plan is in place to address issues on removal
of structures. The effect of feed water extraction on ground stability and freshwater lens is
negligible. Effects on fish populations and coral reef were examined and was also found to be
negligible, as dilution of the brine effluent is expected over a short distance from the point of
discharge. The ESMP includes a monitoring process that will track changes the salinity level over
and adjacent to the point of discharge. Risks of damage to vegetation and salinity level of
ground freshwater lens from leaks in the brine disposal system and failure of the desalination
plant will remain, but will be mitigated by improvements in the management and
implementation of improved maintenance that is expected to result from capacity building and
maintenance support components of the project. The government is to deal with labor issues
and compensation to land owners over disturbed land. The production of salt from the brine is
an option, however chemical wastes associated with the brine would render the salt unsafe for
consumption.
7.4 Consultation and Disclosure during Implementation
During construction, the contractor will disclose information on the location and duration of
construction operations, as well as the GRM. The contractor will assign a liaison officer at each
site, who will be responsible for receiving, and acting on complaints.
The p oje t s o u i atio s a d o sultatio pla ill e updated the PMU/supe isio consultant during the design and pre-construction stage, this plan will guide the process
(means, methods, frequency, documentation etc) for all communications about the project.
Disclosure will follow the requirements of the ADB Public Communications Policy 2011 and any
laws of GOK. This will include uploading of the environmental assessment and other safeguard
due diligence documents on the ADB website and local disclosure.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 67
7.5 Grievance Redress mechanism
Members of the public may perceive risks to themselves or their property, or have concerns
about the environmental performance of the project. These issues may relate to construction
and operation and therefore they will have rights to file complaints for the contractor, PUB and
the MISE to address promptly and sensitively, and for complaints to be made without
retribution.
During construction, the contractor will be required to comply with the Project ESMP and the
approved CESMP, including any issues relating to noise, dust nuisance, accidental damage to
property/utilities and exhaust emissions. The contractor will appoint one staff member as a
liaison officer for each worksite to receive complaints and initiate corrective action as
appropriate. This name will be made available to the Supervising Engineer. Further, the name
and contact details of the contact person for each site will be presented on a notice board at
work sites and at the MISE. The notice board will also state (i) that members of the public with
a grievance or concern have the right to register complaints (verbally or in written form) and for
appropriate and reasonable action to be taken to address any valid complaint and (ii) that
complaints can be made to the individuals concerned either verbally, in person, or in written
form and that (iii) a written response will be provided within 48 hours.
The contractor will maintain a complaints book on site, containing complaint forms that are
filled out in duplicate, with one copy provided to the complainant. The forms will record date,
time and nature of the complaint and information on the rights of the complainant and process
to be followed for assessing and acting on the complaint. Registering and resolving a complaint
will be at no cost to the complainant.
The contractor will then address the complaint and take corrective action agreed to with the
complainant. For minor complaints, such as noise or dust nuisance, or disregard of safety
procedures, immediate corrective action will be taken. For more serious issues requiring
guidance or further discussions, the contractor will raise the issue with the Supervising
Engineer. A written response will be prepared, stating either (i) the nature and duration of
action that has been taken, (ii) where an issue is not readily addressed by direct action on site,
the steps that have been taken for resolution or (iii) complaint is considered invalid, an
explanation as to why. In each case, the complainant will be informed as to their rights for the
next step. The response will be handed to the complainant or made available for them to
collect, within 48 hours of the complaint being received.
Should the complainant remain dissatisfied with the action taken or the explanation received,
the matter/complaint file will be forwarded to the Supervising Engineer.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 68
The Supervising Engineer will have assigned a member of staff with the role of community
liaison. The name of this individual will be provided on the complaints registration form, with
contact details and notice that this individual can be approached for follow up in respect of the
complaint and that this may be done in person, by phone or in written form.
The Supervising Engineer will consult with MISE and on their behalf review the complaint and
the response of the contractor, then make a decision to be referred to the complainant within a
a i u of t o eeks. If the o plai a t e ai s dissatisfied ith the “upe isi g E gi ee s de isio , the g ie a e a e filed ith the Magist ate s Cou t, hi h u de o al
o ditio s i ol es a egist atio fee. The Magist ate s uli g ill e i di g o all pa ties.
O o pletio of the o ks, a d he the o t a to s defe ts lia ilit pe iod has passed, the infrastructure is handed over to MISE and PUB. The PUB, is responsible for infrastructure
service delivery, will be required to receive and act on complaints relating to the operation and
maintenance of the desalination plant, water supply infrastructure and solar PV system. A
complaints register will be maintained.
The contractor will maintain a register of all complaints and grievances received either on site
or at the office. The register will include: date of the complaint, the name of the complainant
(and their contact details), name/title of person receiving the complaint, nature of complaint,
any actions taken to immediately resolve the complaint and any future actions required, and
close-out date when the complaint was satisfactorily resolved.
The register will be subject to inspections during audits and monitoring.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 69
8. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
The mitigation and monitoring activities defined and recommended in this EIA are summarized
in the environmental and social management plan (ESMP) which includes the mitigation and
monitoring requirements (Table 8.1).
8.1 ESMP - Mitigation Measures
In Table 8.1, the required mitigation measures are listed, starting with the actions required
during the design or pre-construction period, then the construction period, and finally the
operating period of the desalination plant, water supply infrastructures, and solar PV system.
The pre-construction period measures all relate to planning items to prevent impacts to marine
and terrestrial ecosystems, the community, longevity of infrastructure, and cultural and
heritage important sites.
During the construction period, mitigation actions should be undertaken, all related to the
construction and installment of the SWRO desalination plant and solar PV system, trench for
the main pipelines and large storage tank and waste management. The safety of workers and
the public is also address.
In the operation stage, the environmental management obligations become the responsibility
of the proponent, MISE, and the operator, PUB.
8.2 Monitoring and Reporting
Monitoring. The ESMP table also lists the actions to be undertaken to monitor effectiveness of
the proposed mitigation measures and to record compliance by the contractor. The monitoring
actions are aligned with the mitigations. The process is important to ensure safeguards are
implemented and any unexpected impacts are responded to swiftly and appropriately.
Monitoring during construction will focus on inspecting work sites to confirm construction,
waste and fuel management is according to specifications and acceptable standards specified in
the o t a to s ou t of o igi if Ki i ati sta da ds do ot e ist , a d that the safet of the workers and the public is upheld.
Both compliance and effects monitoring actions as defined in Table 8-1 should take place as
part of day to day construction supervision, and will be the primary responsibility of the
contractor, supervised by the Supervising Engineer.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 70
During the operation phase, monitoring is the responsibility of PUB, the operator of the newly
installed and upgraded infrastructure. The objectives of monitoring are to (i) quantify that
sufficient dilution of the disposed waste brine is attained through a well maintained and
functioning diffuser after construction and over time, (ii) maintain the performance of the
infrastructures at prime level to reduce potential environments impacts and safeguard issues
that could arise from the failing systems, (iii) ensure workers adhere to correct and safety
operation procedures (iv) ensure wastes generated during the operation are disposed safety (v)
water generated from the desalination plant and pumped from the water reservoirs is safe for
consumption and (vi) understand the contribution of the improved water quality to waterborne
diseases, and trends in relations to reduce use of unsafe water.
The salinity level should be monitored monthly to take account of variation in season, tides,
currents and any other factors that affect the performance of the outfall. The salinity level
should be taken at seabed level and mid depth, at point of discharge, 10m, 20m and 50m on
either side of the point of discharge parallel to the reef edge and identified as offshore sites; at
5m from the reef edge at mid- depth perpendicular to the offshore sites; and two locations
mid-way between the shore and the reef edge along the outfall pipeline route. Obtaining
feedback from local communities on fishing catch from and adjacent to the outfall site will form
the baseline data on fishing effort and catch of the area. The Fisheries Department has done a
lot of work on social economic surveys related to arsenal fisheries, their involvement will be
paramount in the success of data collection and analysis.
Reporting. The reporting will be undertaken at all levels. The contractor will prepare monthly
reports and these will be submitted to the PMU; these reports will contain a summary of
CESMP implementation and corrective action requests issued by the Supervising Engineer. The
PMU will prepare quarterly progress reports (QPR) which will include a section on safeguards
implementation. The PMU will also prepare and sub it to DNPM and ADB/WB the semi-annual
safeguards monitoring reports which will summarize contractor monthly reports and the QPR.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 71
Table 8-1 Environmental and Social Management and Monitoring Plan
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Design and Pre-construction Stage
Environmentally
responsible
procurement
Land acquisition and lease issues resolved and
agreements reached;
Ensure EIA and updated ESMP incorporated into bid and
contract documents. Require Project ESMP as basis for
CESMP to be prepared by contractor and reviewed and
cleared by PMU;
ECD issues environmental license for the project;
Contractor to recruit environmental specialist/officer
(ES/EO) and prepare CESMP for PMU clearance prior to
commencement of works;
Contractor will appoint an experienced site supervisor at
each works site;
If required, PMU to provide support to contractor during
CESMP preparation.
PMU/GOK
(compensation/
lease payment and
ECD);
Supervising
engineer;
Contractor
Land DDR cleared;
Environmental
license;
Bid & contract
documents;
Co t a to s staff contracts – full-
ti e o ks supervisors and
ES/EO recruited;
Approved CESMP
Prior to works
commencing -
once
PMU MISE,
ADB/WB
Climate change and
natural hazards
considerations
Planning new infrastructure at a suitable elevation above
the current high tide level (utilizing accurate topographic
survey);
Ensuring new infrastructure is designed to withstand
extreme weather events, such as sea water inundation;
Selection of renewable system (solar PV) in the design of
power supply to support desalination facility; and
Design system to provide treated, safe water to reduce
the requirement for consumers to boil water for
treatment using green-house gas emitting sources.
PMU Surveys;
Design reports
During detail
design period
PMU (specialists
as required)
MISE,
ADB/WB
Use of land
(temporary) outside
lease area – working
and laydown areas
Laydown sites to store containerized building materials
may be required outside the project sites - use of GOK-
leased land or state land should be arranged, or
negotiation with land owners if private land to be
utilized;
PMU/GOK
(compensation/
lease payment and
ECD);
Land DDR cleared;
Environmental
license;
Signed
lease/agreements
Prior to works
commencing
– as required
PMU;
Contractor
MISE,
ADB/WB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 72
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Separate approval may be required by the ECD and
needs to be sorted and cleared prior usage of any land.
Supervising
engineer;
Contractor
UXO survey and
clearance/disposal
Survey for UXO will be undertaken. The TOR for the
survey (and disposal) will be prepared by the supervision
consultant supporting the PMU;
Should UXO be identified, these will be disposed of
following established government and police protocols
and procedure;
The construction sites will be scanned by a qualified
munitions/UXO field support team to evaluate the
presence of MEC and determine the appropriate level
of MEC support requirements;
UXO monitoring performed concurrent with ongoing
construction works. The primary method of support
would be provided by a UXO technician in the field
during construction works who would scan ahead of
the clearing/grubbing and excavations to identify areas
of avoidance containing potential
munitions/explosives;
Supervisors will conduct a munitions/explosives
awareness safety briefing for all construction
personnel.
PMU + UXO
specialist team as
required
Survey;
TOR;
Results of UXO
monitoring;
Records of
munitions/
explosives
awareness safety
briefing
Prior to any
works
commencing
– as required
PMU (specialists
as required);
Police
MISE,
ADB/WB
Earthworks and
vegetation clearance
- impact on
terrestrial
ecosystems
Ensure survey of proposed locations of desalination plant,
solar PV system and water supply infrastructure identifies
and avoids important sites and minimizes footprint to
reduce requirement for vegetation clearing (vegetation to
be retained/protected clearly marked)
PMU/supervision
consultant;
Contractor
Approved report;
Marked survey
plan and trees to
be retained clearly
marked on site
Prior to works
commencing
– as required
PMU/supervision
consultants
MISE,
ADB/WB
Impacts on marine
environment
Brine discharge as per sewer outfall pipeline route will
follow the recommended alignment to minimize impacts
to the lagoon marine ecology;
PMU;
Contractor;
Supervising Engineer
Design report;
CESMP
During detail
design period
– prior to
installation
PMU/supervision
consultants
MISE,
ADB/WB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 73
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Erosion and sedimentation control plans should be
developed for the three sub-projects as part of CESMP;
Construction Stage
Obtaining
construction
materials and need
for aggregates –
risk of introduced
alien species
Local aggregates if required can be sourced from Te
Atinimarawa Company Limited;
Quarantine clearance to be obtained from the concerned
authority for any imported aggregates and plant;
Pipes that are associated with the desalination plant
will be prefabricated and purchased by the project and
will be either stainless steel or plastic;
No additional mining for aggregate or other materials
will be conducted by the project.
Contractor;
Supervising Engineer
Contract for local
materials;
Phytosanitary
clearances for
imported materials
and plant
As required
throughout
works period
PMU/supervision
consultants
MISE,
ADB/WB
Installation of brine
disposal, permeate
delivery, and
upgrading of the
reticulated system
causing damage to
property and plant
and disturbing
residents
Contractor will appoint an experienced site supervisor at
each works site;
Undertaking condition survey prior to any works and
planning to avoid damage to property and plant;
At the start of the works the contractor will file a checklist
confirming that necessary pre-planning was completed;
Site rehabilitation upon completion - refurbishing of road
and disturbed ground to original status. Apart from the
road, disturbed grounds resulting from earth works will
be refilled, vegetation and trees removed along the
trenching route will be replaced where appropriate.
Contractor;
Supervising Engineer
Works supervisors
appointed;
Condition survey;
Completed
checklists;
Sites rehabilitated
to agreed standard
During
installation
PMU/supervision
consultants
MISE,
ADB/WB
Transport, storage
and use of
hazardous materials
Contractor prepare plan as part of CESMP;
All fuels or other potentially hazardous materials will be
stored at secure and managed sites (bunded and
concreted floor and walls), identified by the contractor
and approved by the PMU/supervision consultant.
Fuel and oil to be stored in bunded and concreted areas
with 110% capacity;
All hazardous chemicals will be clearly labelled.
Contractor,
Supervising Engineer
CESMP;
Secured storage
area (concerted
and bunded);
Spill kit and worker
training records;
Records of safety
briefings
Throughout
works period
PMU/supervision
consultants
MISE,
ADB/WB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 74
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Spill kit, appropriate to the hazardous materials being
used, to be kept on-site and workers to be trained in its
deployment;
Regular checks for leaking oil or fuel from machinery,
Ensuring that any leaks are promptly repaired and/or
parts replaced within two days as part of maintenance of
vehicles and equipment to international standards;
Any surplus hazardous materials shall be removed from
the island when the contractor demobilizes. The
co t a to s o kshop ill ha e clearly marked waste
disposal bins to store filters, rags and waste oil, for
disposal at the landfills;
All asbestos concrete pipe disposal will be supervised by a
competent person, trained in asbestos abatement. Pipe
sections will be wrapped and marked with the cautionary
statement Da ge Asbestos-Containing Material . The
pipe sections will be buried at an authorized location.
Generation of
wastes and waste
management
Prepare a solid waste management plan as part of the
CESMP;
Separate and store wastes with respect for health and
environment. Identify any waste that can be reused or
recycled;
Contain all stored wastes in secure receptacles within
construction sites and the compound, avoiding littering
and runoff;
No waste is to be burned;
Workers will be advised that littering will not be
permitted. Waste generated construction activities at
sites will be cleared and disposed of as per the above;
Use recycled or renewable building materials (e.g. timber)
where possible;
Contractor Solid waste
management plan
as part of CESMP;
Throughout
works
PMU/Supervising
Engineer
MISE,
ADB/WB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 75
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Optimize and reduce waste production. Avoid mix of
different waste and minimize waste disposal into the
approved dumping area or landfill.
Use of outfall for
brine disposal -
overflow and
spillage of raw
sewage from sump
at the outfall pump
Installing a by-pass pipe to allow continuous outflow of
the sewage while desalination waste pipeline is
connected to the sewage outfall;
Accounting for the likely overflow and spillage problems
in the CESMP;
Having qualified personnel on site to oversee the
upgrading work.
PMU;
Contractor
Design report and
technical
specifications for
pipe upgrading;
CESMP
Prior to and
during works
PMU/Supervising
Engineer
MISE,
ADB/WB
Earthworks
affecting water
quality - impact of
sediment runoff on
coastal marine
environment
Use of sediment retention fencing, berms, and sandbags
around excavations to restrict the release of sediment
from the construction site;
Use of siltation curtains to contain the site area around
trenching works on the near shore reef to prevent the
release of sediment onto the surrounding reef area;
Immediately re-vegetate and/or stabilize exposed
surfaces and stockpiles of excavated materials; and
Monitor water quality for near shore waters adjacent to
land base earthworks.
Contractor;
Supervising Engineer
On-site sediment
control measures;
CESMP;
Re-vegetation;
Records of water
quality monitoring
(visual)
During works PMU/Supervising
Engineer
MISE,
ADB/WB
Localized impacts
on terrestrial
ecology -
vegetation cleared
and/or affected
during construction
Identify trees and vegetation to be removed on survey
plan, plan will be approved by Supervising Engineer;
Mark trees and vegetation to be removed (with
fluorescent paint or tags) as per plan;
Only trees and vegetation marked on plan to be
removed. All trees and vegetation removed and any
others affected during the installation of the solar PV
system and excavation work will be compensated in
accordance with GOK schedules;
Prohibition of burning vegetation and residual bushes and
grasses when clearing planting sites;
Contractor
Supervising Engineer
Phytosanitary
clearances for
imported materials
and plant;
Survey plan and
protected trees
marked on-site;
Compensation paid
for productive
trees removed
Prior to and
during
clearance
works and
earthworks
PMU/Supervising
Engineer
MISE,
ADB/WB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 76
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Only cutting flora which are a direct obstacle to project
infrastructure works;
All vessels carrying equipment and materials for the
project will be subject to inspection by agriculture
quarantine inspectors.
Ecological impacts
associated with
spillage of hazards
material during
construction
Regular checks for leaking oil or fuel from machinery,
ensuring that any leaks are promptly repaired and/or
parts replaced within two days as part of maintenance of
vehicles and equipment to international standards; and
Contractor will implement the measures identified to
mitigate the impacts from storage and spillage of
hazardous substances and other chemicals and materials.
Contractor CESMP;
Secured storage
area (concerted
and bunded);
Spill kit and worker
training records
Throughout
construction
PMU/Supervising
Engineer
MISE,
ADB/WB
Materials and plant
haulage - traffic
disruption and
pedestrian safety
risk
Contractor to prepare a traffic management plan as part
of the CESMP;
Advance notification (through radio and newspaper) to
advise road closures, detours and the like to facilitate
work activities.
Traffic
management plan
as part of approved
CESMP;
Traffic control
measures
implemented;
Signage and
barriers installed as
required
Throughout
construction
PMU/Supervising
Engineer
MISE,
ADB/WB
Noise nuisance from
construction
Restricting the working hours to between 0800 hrs and
1700 hrs from Monday to Friday, or Saturday if there is a
need to work on the weekend, this is important,
especially in areas where residential dwellings are located
adjacent to the construction area, as in the desalination
construction area and the upgraded water supply
infrastructure.
Use of vehicles, plant and equipment, that comply with
international standards for construction equipment noise
emission, such as Part 204 of US Federal Regulations-
Contractor Workers allocated
and wearing PPE;
Complaints
register;
Vehicle and plant
maintenance
records
Throughout
construction
PMU/Supervising
Engineer
MISE,
ADB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 77
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Noise Emission Standards for Construction Equipment (40
CFR 204)). Verification of such compliance from the
country of origin is required.
The CESMP will include measures to meet the
e ui e e ts of the WB s E i o e tal Health a d Safety Guidelines (EHSG).
Maintenance repair should also be routinely performed
during the construction phase and making the record
available whenever needed to the concerned authority.
Dust generation and
nuisance
Daily spraying/wetting of the access roads, sites (including
excavated trenches for water supply network upgrades)
material and stockpiles;
Locations for stockpiles of materials or waste materials
will be approved by the PMU/supervision consultant and
by the ECD if required;
Loose materials hauled to/from sites will be secured with
a tarpaulin to prevent debris;
Ensure emissions are minimal through standardized site
management such as dust watering or stockpile covers.
Removal of spoil to stockpile sites or use as refill material;
Contractor will provide equipment that conforms to
international emission standards, verified by emission
test certificates and maintenance records, as in the
case of control of black smoke emissions.
Contractor Designated
stockpile areas
approved;
Workers allocated
and wearing PPE;
Dust plumes;
Complaints
register;
Vehicle and plant
maintenance
records
Throughout
construction
PMU/Supervising
Engineer
MISE,
ADB
Foreign and non-
Tarawa workers -
social conflict
Contractor to provide information on Kiribati culture
(obtained from PMU) to the expatriate workers;
Code of conduct to be agreed and implemented at all
times. Code of conduct to include:
How and when information will be communicated
between the contractor and the community;
Contractor Agreed code of
conduct;
GRM register;
Meetings and
information
brochures to
community;
Throughout
construction
PMU/Supervising
Engineer
MISE,
ADB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 78
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Schedule of activities and works (days and times) and
if night-time or Sunday work will be required;
Conduct of the building and asset condition survey;
Negotiations for access to land for temporary works,
laydown areas and the like;
Conduct and behavior while working in community,
villages or close to churches or schools etc;
Identification of community leaders and appropriate
ways to address them;
Appropriate ways to address women;
Avoidance of fraternization of workers with local
people;
Avoidance of use of inappropriate language or cursing
when working close to residences and shops;
No differences in wages paid to men and women for
similar work;
No use of trafficked or child labor;
Prohibitions on use of illegal drugs and alcohol and
sanctions to be imposed;
Implementation of the health and safety plan
(including communicable diseases awareness and
prevention training); and
Implementation of the grievance redress mechanism
(GRM) and process for resolving conflicts between
workers and community members.
Records of workers
– hours and wages
paid (by aged and
sex);
Records of delivery
of STI/HIV/AIDS
awareness and
prevention training
Occupational and
community health
and safety impacts
Contractor to prepare health and safety plan,
complying with the EHSG, as part of CESMP;
Wo ks sites a d o t a to s offi e a d o pou d to be securely fenced and access only permitted to
workers and authorized people;
Contractor Health and safety
plan as part of
approved CESMP;
Site and works
yard security and
fencing;
Throughout
construction
PMU/Supervising
Engineer
MISE,
ADB
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 79
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
For i-Kiribati workers, comply with Kiribati laws on
employment and health and safety and observe Kiribati
statutory holidays;
Under no circumstances, allow children to enter the
o ks sites, o t a to s offi e a d o pou d;
Provide sufficient light coverage during night
construction. Any light used during night construction
is not to affect neighboring residences;
Designate a full-time, experienced/qualified Health and
Safety Offi e ithi o t a to s staff. Allocate
responsibility for safety inspections to Health and
Safety Officer;
Regularly training of workers in safety precautions, for
themselves and others and for implementing
emergency procedures;
Engage an approved service provider to deliver a
communicable diseases awareness and prevention
program including sexually transmitted infections (STI)
and HIV/AIDS. The program will be conducted
regularly for works and the community;
Provide PPE (at no cost) to workers appropriate to the
activities they undertake (including any activities at
height);
Ensure that vehicle and equipment operators are
properly licensed and trained;
Arrange for provision of first aid kits in all vehicles and
fa ilities ith t ai ed staff o all at the o t a to s office or compound/works yard;
Illegal drugs and alcohol will not be permitted on any
works site and any worker intoxicated while at work
will be dismissed;
PPE provided to
workers;
Meetings and
information
brochures to
community;
Records of workers
– hours and wages
paid (by aged and
sex);
Records of worker
training;
Records of delivery
of STI/HIV/AIDS
awareness and
prevention
training;
GRM register;
First aid kits in
vehicles and at
work sites;
Signage and traffic
control measures;
Accidents/
incidents register
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 80
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Establish emergency and medical evacuation
procedures and provide time for workers to undertake
training and drills in the procedures;
Provide regular safety checks of vehicles and
equipment;
Identify hazard zones and provision of hazard warning
signs at the construction sites;
Provide temporary fencing/barriers around potential
hazards such as pipe trenches and any excavations 1m
or deeper to ensure there is no hazard to the workers
or public;
Maintain register of incidents and accidents detailing
date, circumstances, severity, action taken at the time
or subsequently, outcomes and actions/measures to
prevent future incidents/accidents; and
Implement the relevant elements of the GRM and
maintain a complaints/grievance registry.
Impact on
underground service
utilities and services
relocation
Obtain plans from the PUB showing the location of
underground service utilities (power, telecom, other)
and consultation with residents and/or landowners on
the relocation of utilities prior to commencing
excavation operation
Contractor Service and utility
location plans;
Relocation plans
agreed with PUB
Throughout
construction
as required
PMU/Supervising
Engineer
MISE,
ADB
Encroachment on
private property or
use of private
lands=
Consultation with and written approval from land
owners for access when intrusion on to private
properties is inevitable;
Formulation of lease agreements in cases where the
sites are not leased by GOK.
Contractor Signed agreements
and/or leases as
required
Throughout
construction
as required
PMU/Supervising
Engineer
MISE,
ADB
Operation Stage
Use of fossil fuel and
greenhouse gas
emission
Installation of solar PV system to compensate for the
energy used by the desalination system;
PUB/MISE Records of
performance
During
operations
ECD (MELAD) GOK
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 81
Project activity or
environmental
issues
Mitigation and Management Monitoring
Mitigation Measures/Parameter Implementation
Responsibility Verification
Timing/
Frequency
Responsibility
Implementation Oversight
Provision of safe, treated water to customers that reduces
requirement for boiling water and associated greenhouse
gas emissions.
levels, e-coli and
chlorine residuals
Generated waste Spent filter cartridge and other solid wastes from the
desalination plant will be disposed at the Betio landfill
through routine collection by the Betio Town Council or
by PUB whenever needed.
On site waste bins will be provided.
PUB
Record of disposal
date and volume
per waste category
During
operations
PUB/MISE
Impacts associated
with the failure of
the desalination
plant
Fences with lockable gates, lockable manhole for
underground water valves and visible signs indicating
danger and restricted areas are displayed visibly to the
public;
Regular maintenance (preventive and corrective)
PUB/MISE Lacks of failure and
complaint from the
public
During
operations
PUB/MISE GOK
Quality of drinking
water produced
through desalination
Water testing for salinity and harmful pathogens;
Inform the public to boil water when chlorination system
fails or presence of harmful level of pathogens is detected
in the system
PUB/MISE Reduce trend in
disease related to
unsafe water
During
operations
PUB/MISE GOK
Impact of brine
disposal on marine
ecosystem
Salinity level monitoring at the outfall location to detect
possible loss of performance of the diffuser fitting and
leakage
PUB/MISE Ambient salinity
level is attained
near the reef and
on the reef flat
During
operations
PUB/MISE GOK
Impact of
solid/waste disposal
WASH program incorporated in the project will assist to
address and provide remedy to this continuing and urgent
p o le du i g a d e o d the p oje t s life
PUB Trends of pollution
level on coastal
and ground water
During
operations
MISE/MELAD/OB/
Min. of Health
and Medical
Services
GOK
Health and safety
risks associated with
handling of
chemicals
Chemicals are labelled accordingly;
Safety instructions on chemical use are visibly displayed;
Operators are trained on chemical handling
PUB/MISE Number of
accidents
During
operations
PUB/MISE GOK
Nuisance noise Desalination warehouse is installed with acoustic
packages (noise reducing materials)
PUB/MISE Record of public
complaints
During
operations
PUB/MISE GOK
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 82
8.3 Capacity of Proponent and Operator - Monitoring
PUB and MISE are obligated to ensure all monitoring needs are undertaken as expected in
accordance to the assigned schedule. Thus establishing a safeguard post within PUB to
implement all safeguard measures, or assigning the duty to an existing staff member that will
implement the measures after the construction phase and beyond is essential. Training should
be incorporated as part of the project.
The proposed monitoring plans identified and summarized in Table 8-2 are within the capacity
of PUB except for the visual inspection of the outfall and diffuser ports which requires SCUBA
diving for inspection. There are several certified SCUBA divers on the island who can carry out
the inspection work with a cost ranging from $6,000 - $8,000 per year. The cost includes boat
hire, fuel cost, hire of SCUBA gears, and inspection fee. The indicative cost of water quality
monitoring by PUB and MHMS is provided in Table 8-2.
Whilst a capacity needs assessment for ECD/MELAD has not been conducted as part of this EIA,
as ECD is responsible for monitoring the work progress to ensure compliance with the license
conditions it is recommended that any monitoring capacity development activities for
monitoring for the PUB are also extended to include ECD and ensure collaboration between the
ECD and PUB.
Table 8-2 Summary of the water quality monitoring cost
Impact to be
monitored
Means of
Monitoring
Operation
Frequency Responsible Agency Indicative annual
cost (USD)
Water Quality Laboratory testing
of water quality in
the distribution
network
12 tests annually PUB but testing to
be undertaken by
MHMS
13,200
Salinity test for
brine dilution and
drinking water.
Cost of testing
machine and probe
Regular for drinking
water and monthly
for testing of brine
dilution at outfall
monitoring sites
PUB 5,000
Socio-economic
survey on arsenal
fisheries impacts
Annual PUB in
collaboration with
Fisheries
Department
2,000
Implementation of
safeguards
Recruitment of new
staff and training
PUB 10,000
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 83
9. CONCLUSION
In conclusion, the EIA has found that no significant or residual environmental impacts are likely
to occur provided that the ESMP is updated, implemented and monitored. The ESMP (which
will be updated and further developed as a CESMP by the contractor) addresses the impacts
and risks associated with construction and operation of the SWRO desalination plant, solar PV
system, and water supply infrastructure.
The project will provide significant environmental benefits such as consistent service of potable
public water, reduced public health risks associated with inadequate water supply, and will
incorporate a renewable energy component. Additional benefits include, improved planning,
management, and sustainability of future water supply, improved development planning, and
increased tourism potential.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 84
APPENDICES
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 85
Appendix 1: MELAD response to Environmental License Application
.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 86
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 87
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 88
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 89
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 90
Appendix 2: Land Options for Desalination Plant
Current Situation. Drinking water supply in South Tarawa is currently limited to water pumped
through the PUB distribution system which is augmented with collected rainfall, when
available. The source of potable water is from the fresh water lens at Bonriki. The volume of
water pumped from Bonriki to supply all consumers in South Tarawa is approximately
2 ML/day.
The direction that government is taking towards future water supply is based upon having a
pressurised water supply to consumers that will be available 24 hours per day. This will require
another source of drinking water to be established. Previous studies have identified that the
only viable means of supplying large quantities of additional drinking water is desalination of
seawater.
Desalination System. The expected capacity of the desalination plant to meet current demand
is approximately 3 ML/day, ultimate capacity is expected to be approximately 6 ML/day.
Hydraulic Considerations. Preliminary hydraulic studies on the capacity of the existing water
transmission line that runs from Bonriki to Betio have shown that the pipeline does not have
the capability to transfer this additional water from a desalination facility located at Bonriki. To
maintain future water supply throughout South Tarawa in the existing pipeline will require a
desalination facility located in the Western end of South Tarawa, preferably in Betio which has
a large bulk storage tank and a large population centre.
A desalination facility located at Bonriki will require a new larger pipeline running the majority
of the length of South Tarawa will be required which will incur very high cost and cause
considerable disruption. A possible connection point to the existing pipeline is around Ambo.
Strategically it is preferable to have a water source at either end of South Tarawa.
Operational Considerations. The desalination plant will be a strategic asset for supply of
additional drinking water to South Tarawa to meet current and future water demand. From an
operational consideration, there are significant benefits to the PUB in locating the desalination
facility on a single site, as opposed to having multiple small sites located in the western portion
of South Tarawa. A single site would allow the capacity of the plant to be upgraded without
future land issues.
Area Requirements. The area required for a desalination plant located on a single site to meet
current and future water demand is 2400 m2, preferably a site with dimensions approximating
80 m by 30 m. The overall land requirements if multiple sites for desalination plants are
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 91
required would be significantly greater than 2400 m2. This is because balance of plant
requirements, such as water storage tanks, are required at each plant site.
Water Supply. Saline water will be supplied to the desalination plant from a series. It is
anticipated that nine bores will be required at 25 to 30 metre spacing. Land will be required for
the bore headworks.
Brine Discharge. The environmental and social constraints relating to brine discharge are
common throughout South Tarawa and are not specific to a specific plant site.
Potential Sites. The potential sites identified are shown in Table A2.1.
Table A2.1 – Potential Sites for Desalinization Plant
Site Description
1 Vacant land opposite the Parliament in Ambo
2 Abaokoro on the ocean side in Ambo
3 Land to the west of the Nanikai landfill site
4 Land on the eastern end of the Bairiki causeway
5 Land in Betio, on the ocean side between the WW2 heritage artifacts and Taiwan Park
6 Land in Betio, eastern area used by Nippon Causeway contractor, Betio
7 Some of the land currently occupied by the meteorological office, Betio
8 Land currently occupied for container storage, Betio
9 Land in Betio, western area used by Nippon Causeway contractor
10 Location on Bonriki Water Reserve
11 PUB Water Yard up to and including McConnell Dowell site/MPWU Civil yard
12 Bairiki-end of Dai Nippon Causeway (south) currently occupied by Ferris wheel
Table A2.2 sets out the existing ownership and use and identifies any issues.
An image of each location with the land required for the desalination plant is shown in the
following plates. The desalination plant boundary and bores are also shown for indication
purposes only. The actual position may be changed to suit any specific requirements.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 92
Table A2.2 – Description of Potential Sites and Issues
Site Land Issues
Tenure/Ownership Use/status Social Environmental Engineering
1 Assumed to be
residential
Vacant site
Close to population center in active
community.
Bores will have to be installed outside
this area within residential areas
Potential noise issue to local
residences but this can be
managed by building design
Not ideal from hydraulic
consideration because the site is
not on the western end of South
Tarawa
Close to water transmission line
Close to 11 kV power line
Brine discharge close to the reef
Minimal area for construction
laydown will make construction
difficult
Not ideal from consideration of
water supply from bores
2 Unknown, land use
assumed to be
residential
No residential or
industrial activity
Remote from residential centres
Land occasionally used by community
groups
Undisturbed site in highly
modified area
Will require construction of a
causeway for vehicle access
Considerable disturbance to land
in construction phase
Not ideal from hydraulic
consideration because the site is
not close to the western end of
South Tarawa
Not close to water or
transmission line
Brine discharge close to ocean,
will need to cross road
Will require construction of a
causeway for vehicle access
Area available for construction
laydown
Site acceptable for installation
of a series of bores
3 Unknown, land use
assumed to be Open
Space - Recreation
Site currently
occupied by shipping
containers
Remote from residential centres
No social amenity activity, apart from
landfill, nearby
Disturbed site
Environmental noise not a major
issue
Reclaimed land, will require
geotechnical investigation
Close to water transmission line
Close to 11 kV power line
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 93
Site Land Issues
Tenure/Ownership Use/status Social Environmental Engineering
Brine discharge close to ocean,
will need to cross road
Area for construction laydown
available
Long site that is acceptable for
installation of a series of bores
Not ideal, but workable site,
from hydraulic consideration of
continuous pressurised water
supply
4 land use assumed to
be Non-residential
institutions –
Government
Buildings
Transmission tower is
present on the site
Close to a residential area
Some bores might need to encroach
into residential areas
Disturbed site
Potential noise issue to local
residences but this can be
managed by building design.
Close to water transmission line
and 11 kV power line
Brine discharge close to ocean
Presence of transmission tower
will probably create limitations
with significant impact on site
layout
Construction laydown area
available
Not ideal from consideration of
water supply from bores
5 assumed to be Open
Space - Recreation
Vacant but vegetated
Close to Taiwan Park and WWII
heritage artifacts
Bores will be presents in Taiwan Park
and WWII heritage area.
Industrial building close to used social
amenity
Vegetated site
Need to reduce community noise
levels because of proximity to
Taiwan Park
A preferred location for
discharge of drinking water into
the transmission line from a
hydraulic consideration
Close to water transmission line
and 11 kV power line
Limited area for construction
laydown
Some bores would have to be
installed outside this area,
possibly encroaching onto
adjacent areas or sourced from
land on lagoon side
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 94
Site Land Issues
Tenure/Ownership Use/status Social Environmental Engineering
6 land use assumed to
be Non-residential
institutions –
Government
Buildings
Currently used by
Contractor for
causeway/road
project
Residential area around the site
Most of the site is required for the
desalination plant
Disturbed site
Need to consider community
noise levels because of proximity
to residential area
Bores will have to be installed
outside this area in non-
residential area
Ideal location for plant control,
desalination plant will interface
with Betio main storage tank
Route for drinking water
pipeline to Betio main storage
tank needs to be considered
through residential areas
Brine discharge to ocean side,
will need to run along the road
to miss the cemetery
Close to 11 kV power line
Minimal area for construction
laydown
Remote borefield
7 Non-residential
institutions –
Government
Buildings
Currently used by
Office of Meteorology
Residential area around the site
Brine discharge to ocean side,
will need to run along road to
miss the cemetery
Vegetated site currently being
used by a government agency
Need to consider community
noise levels because of proximity
to residential area
Borefield could possibly affect
local groundwater table
Ideal location for plant control,
desalination plant will interface
with Betio main storage tank
Route for drinking water
pipeline to Betio main storage
tank needs to be considered
through residential areas
Brine discharge to ocean side,
will need to run along the road
Close to 11 kV power line
Area for construction laydown,
but considerable interface
issues with Office of
Meteorology
Potential to install all bores
within this area
8 Assumed to be
industrial
Currently used for
storage of shipping
containers
Residential area to the north of the
site
Not all of the site is required for the
desalination plant
Disturbed site
Need to consider community
noise levels because of proximity
to residential area
Ideal location for plant control,
desalination plant will interface
with Betio main storage tank
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 95
Site Land Issues
Tenure/Ownership Use/status Social Environmental Engineering
Borefield could possibly affect
local groundwater table
Route for drinking water
pipeline to Betio main storage
tank needs to be considered
Large site available, not all of
which is required for final
installation
Good area for construction
laydown
Site sufficient to possibly install
all bores
9 Assumed to be
industrial
Currently used by
Contractor for
Causeway Contract
Residential area to the north of the
site
Not all of the site is required for the
desalination plant
Disturbed site
Need to consider community
noise levels because of proximity
to residential area
Borefield could possibly affect
local groundwater table
Ideal location for plant control,
desalination plant will interface
with Betio main storage tank
Route for drinking water
pipeline to Betio main storage
tank needs to be considered
Large site available, not all of
which is required for final
installation
Good area for construction
laydown
Site sufficient to possibly install
all bores
Area not ideal unless some of
the existing building on site are
removed
10 Unknown Currently used for
multiple activities
Large portions of land
are not available
because of other
activities, for example
fish farming
Residential area
Not all of the available land is required
for the desalination plant
Desalination plant might encroach on
land being considered for future
residential requirements
Environmental assessment will
be required when site identified
Major portion of the land is
swampy and not ideal for
construction, this limited
available areas
Bores will be remote from
desalination plant and require
their own electrical power
system
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 96
Site Land Issues
Tenure/Ownership Use/status Social Environmental Engineering
New water transmission
pipeline from Bonriki will be
required, possibly connecting to
the existing pipeline around
Ambo
Strategically it is preferable to
have two water supply systems
locate at either end of South
Tarawa
From water quality
consideration, it is
advantageous to blend reverse
osmosis water with Bonriki
ground water
11 Assumed to be
industrial
Currently used by PUB
for 2 ML reservoir,
elevated tank for
water reticulation,
storage for pipes and
the site offices.
MPWU use part of the
area for heavy plant
storage, soil
laboratory and site
offices.
Currently surrounded
by residential areas,
school and site offices.
Surrounded by Residential areas and
the school
Not all of the available land is required
for the desalination plant
Desalination plant might encroach on
land being considered for future
residential requirements
Disturbed site
Need to consider community
noise levels because of proximity
to residential area
Borefield could possibly affect
local groundwater table
Ideal location for plant control,
desalination plant will interface
with Betio main storage tank
Large site available, not all of
which is required for final
installation
Good area for construction
laydown
Site sufficient to possibly install
all bores if Macdow area can be
made available
Area not ideal unless some of
the existing building on site are
removed
12 Assumed to be
industrial
Currently used by
overseas contractor
and the Ferris wheel
There are residential buildings to the
south and the church to the east.
The land is thought to be owned by
private landowners but these need to
be confirmed by Lands Management
Division of MELAD.
Disturbed site
Need to consider community
noise levels because of proximity
to residential area
Bore-wells could be located on
the beach.
The current site is too sandy and
there may be a need to improve
soil bearing capacity.
Large site available, not all of
which is required for final
installation
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 97
Site Land Issues
Tenure/Ownership Use/status Social Environmental Engineering
Desalination plant will prevent viewing
of the causeway from the Church site.
Good area for construction
laydown
Site sufficient to possibly install
all bores along the beach.
Area not ideal unless some of
the existing building on site are
removed
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 98
Site 1- Opposite Parliament building in Ambo
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 99
Site 2 – Abaokoro (ocean-side in Ambo)
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 100
Site 3 - Land to the west of the Nanikai landfill site
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 101
Site 4 - Land on the eastern end of the Bairiki causeway
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 102
Site 5 - Land in Betio (ocean side - east of WWII heritage artifacts)
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 103
Site 6 - Land in Betio, Eastern area used by Nippon Causeway contractor
Bores will need to be located remote from this site with bore
collector main and independent power supply.
Communication with plant site required.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 104
Site 7 - Land in Betio, meteorological site
Bores within
property boundary
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 105
Site 8 - Land in Betio, currently used for shipping container storage
Bores within property
boundary
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 106
Site 9 - Land in Betio, Western area used by Nippon Causeway contractor
Bores within
property
boundary
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 107
Site 10 – Bonriki Water Reserve Area
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 108
Site 11 – PUB Water Yards to McConell Dowell area
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 109
Site 12 – South of Bairiki end of Dai Nippon Causeway
Site 12
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 110
Appendix 3: Minutes of Community Consultations
Member of consultation team; Iannang Teaioro, Environment Safeguards, Taboia Metutera,
Water Engineer and Deputy Team Leader
Venue and attendance; meeting with the communities is arranged prior every meeting through
the community or church leaders.
Six maneaba (meeting halls) were visited between 3rd and 11th February 2018 during the
disclosure and consultation meetings. Two at Betio and one at Bairiki, Teaoraereke,
Bangantebure and Bonriki. Summary of the attendance is provided in Table A3.1.
Table A3.1. Summary of attendance
Village Date of meeting Male Female Total
Betio (Temanoku) 3 Feb 2018 8 10 18
Betio (Temakin) 6 Feb 2018 15 30 45
Bairiki 9 Feb 2018 9 6 15
Teaoraereke 7 Feb 2018 13 18 31
Bangantebure 11 Feb 2018 15 35 50
Bonriki 11 Feb 2018 21 10 31
Total 81 109 190
The participants were informed of the main components of the project that includes
installation and operation of a RO desalination plant and solar PV system, and the upgrading of
the water supply system on South Tarawa. The activities involved and proposed locations for
each component were presented including the reasons why these locations were chosen. For
the desalination plant information on the production capacity, source of feed water, how the
brine will be disposed, potential environmental impacts of brine on the marine and terrestrial
ecosystem were disclosed. Other environmental and social issues that could arise during the
construction were discussed in particular: (i) land access, (ii) effect of encroaching onto private
properties, (iii) excavation works and related impacts on trees and permanent structures
removals, noise, dust, increased traffic that would cause nuisance during construction,
destruction of the newly completed tar-sealed road and impacts on traffic. Mitigation
measures for each and the benefits associated with the implementation of the projects formed
parts of the discussion during the meeting.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 111
Table A3-2 Feedback from each community and response.
Feedback Response from PPTA Team
1. Betio - Temanoku
1.1 Effect of drilling on ground stability
1.2 Effect of feed water extraction n
freshwater lens
1.3 Effect of brine on marine ecosystem.
1.1 Ground stability will not be affected
1.2 Freshwaters will not be affected as the water will be pumped
from a depth of 30-35m, well below the freshwater lens
1.3 Dilution of brine will be attained within 10 m from the point
of discharge.
2. Betio - Temakin
2.1 Effect of drilling on ground stability
2.2 Effect of feed water extraction on
freshwater lens and level of underground
water
2.3 Effect of brine on marine ecosystem
2.4 Location – why the desalination plant is
not located over the seawater instead of on
land
2.1 Ground stability will not be affected
2.2 Freshwaters will not be affected as the water will be pumped
from a depth of 30-35m, well below the freshwater lens. A
drawback on underground water level of about 10-30 mm will be
noticeable at the extraction point but diminishes to zero once
you reach 20 meters away from the borehole.
2.3 Dilution of brine will be attained within 10 m from the point
of discharge.
2.4 Cost to construction seawall or separate island over the reef
is not feasible due to costs and vulnerability to storms waves
3. Bairiki
3.1 Effect of excavation on vegetation and
structure
3.2 Convert brine to salt instead of
disposing it
3.3 Sourcing feed water from the ocean
3.4 Government to create a reserve fund
that can be used to compensate
landowners for having their land disturbed
during the excavation work
3.5 Community to have equal share of labor
recruited to the project during construction.
Favoritism has been observed in the past
and ongoing project where recruitment is
based on whom you know.
3.1 Effect should be minimized where possible. However,
replanting, resettlement plan to address the issue, and
compensation are the mitigation measures provided.
3.2 Not feasible due to chemicals used in the desalination
process and would contaminate the salt if produced from the
brine
3.3 Ocean water has more suspended solids in it and would
require more effort and hence cost to remove
3.4 Will raise the matter to Government through MISE
3.5 Will raise the matter to Government through MISE
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 112
Feedback Response from PPTA Team
4. Teaoraereke
4.1 Cost of water, will it be increased after
the completion of project?
4.2 Suggested that a study should be
undertaken to ensure there is no impact of
desalination on the marine and terrestrial
ecosystem.
4.1 Government is considering different options
4.2 Study is underway and there will be monitoring activities to
be undertaken to ensure impacts are minimized.
5. Bangantebure
5.1 Are the water consumers expected to
pay for the water after completion of
project
5.2 IF paying for water then request that
cost is kept at minimum level
5.3 Effects of pipe installation on the newly
completed tar-sealed road
5.4 Fabricating water pipe connections by
individual causing damage to the reticulated
system. Concern over poor repair and
hence sustainability of infrastructure
5.5 No reticulated water supply system on
the lagoon side of the road. Will the project
installed the system for the concerned
residences.
5.1 It is expected that the consumers will be charged
5.2 Yes Government is considering different options
5.3 Efforts will be taken to ensure the newly tar-sealed road is
not affected. However, if affected the contractor is responsible
to resurface the excavated road to original status
5.4 WASH will address the issue with the community the
importance of having the system and effects when damage and
encourage the community to participate in maintaining the
system. Management and implementation of improved
maintenance that is expected to result from capacity building
and maintenance support components of the project
5.5 This will be addressed by the project
6. Bonriki
6.1 Rely on expert to provide appropriate
mitigation measures towards impact on the
marine ecosystem as most of them are not
expert and would not have any clues on
what will happen except that there will be
happy with more water from the project
6.2 Concern that trees will be affected
during the installation of solar PV system,
and therefore requesting if the amount of
compensation can be increased from the
current level
6.1 Impacts on the marine is expected to be minimal
6.2 Will raised the matter to Government through MISE
6.3 This will be address by the project
6.4 It is expected that current extraction rate will be maintained
and expected to decrease overtime due to the installation of a
desalination plant.
K i r i b a t i : S o u t h T a r a w a W a t e r S u p p l y P r o j e c t P a g e | 113
Feedback Response from PPTA Team
6.3 No reticulated water supply system in
Bonriki village. Request for one.
6.4 Freshwater extraction from Bonriki
water reservoir has increased the salinity
level of water in the village and could
worsen if the existing extraction rate
continues