Social Monitoring Report This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Director, Management or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 48102-002 November 2020 PRC: Qinghai Haidong Urban-Rural Eco Development Project Prepared by National Research Center for Resettlement, Hohai University

Upload: others

Post on 06-Nov-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

Social Monitoring Report

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Director, Management or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Number: 48102-002 November 2020

PRC: Qinghai Haidong Urban-Rural Eco Development Project

Prepared by National Research Center for Resettlement, Hohai University

Page 2: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

External EMDP M&E Report (No.3)

National Research Center for Resettlement, Hohai University Nanjing, Jiangsu, China

September 2020

ADB-financed Qinghai Haidong Urban-Rural Eco Development Project

Page 3: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

II

Contents

1 Summary ......................................................................................................................................................... 1

1.1 Introduction to the Project .................................................................................................................................. 1

1.2 External EMDP M&E ............................................................................................................................................ 1

1.2.1 Scope ......................................................................................................................................................... 1

1.2.2 Purpose and Key Points .......................................................................................................................... 2

1.2.3 Methods ..................................................................................................................................................... 2

2 Identification of Local Minority Population .............................................................................................. 4

3 EMDP Implementation M&E ......................................................................................................................... 6

3.1 Overview of the EMDP ........................................................................................................................................ 6

3.1.1 Impacts on Minority Population .............................................................................................................. 7

3.1.2 Sampling Survey on Minority Households ............................................................................................ 7

3.2 EMDP Implementation Progress ......................................................................................................................... 8

3.2.1 Alleviation Measures .................................................................................................................... 8

3.2.2 Supporting Measures of Local Governments ............................................................................ 10

3.2.3 Project Management .................................................................................................................. 10

3.3 Issues and Suggestions ...................................................................................................................................... 11

3.3.1 Key Issues and Challenges ........................................................................................................ 11

3.3.2 Suggestions and Subsequent Measures .................................................................................... 11

4 SGAP Implementation Monitoring .............................................................................................................14

4.1 SGAP Overview .................................................................................................................................................. 14

4.2 SGAP Implementation Progress ........................................................................................................................ 14

4.2.1 Output 1: River Rehabilitation .................................................................................................... 14

4.2.2 Output 2: Eco-environment Protection and Restoration ............................................................ 14

4.2.3 Output 3: Rural Water Supply and MSW Management Infrastructure Construction ................. 14

4.2.4 All Outputs.................................................................................................................................. 15

5 Sampling Survey ..........................................................................................................................................19

Page 4: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

III

5.1 Methods ............................................................................................................................................................. 19

5.2 Results ................................................................................................................................................................ 19

5.2.1 Population ............................................................................................................................................... 19

5.2.2 Age Structure .......................................................................................................................................... 19

5.2.3 Education ................................................................................................................................................. 19

5.2.4 Employment ............................................................................................................................................ 20

5.2.5 Annual Income and Expenditure .......................................................................................................... 20

6 Grievance Redress .......................................................................................................................................21

6.1 Channels and Procedure .................................................................................................................................... 21

6.2 Recording and Feedback .................................................................................................................................... 22

6.3 Evaluation........................................................................................................................................................... 22

7 Findings and Suggestions ..........................................................................................................................24

7.1 Findings .............................................................................................................................................................. 24

7.2 Suggestions ........................................................................................................................................................ 25

Appendix 1 Interview Minutes .............................................................................................................................26

Appendix 2 Fieldwork Photos .............................................................................................................................27

Page 5: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

IV

List of Tables Table 2-1 Minority Population in the Project Area ...................................................................... 4 Table 3-1 Distribution of Minority Population ............................................................................. 7 Table 3-2 Participation in AIDS Prevention Publicity .................................................................. 9 Table 3-3 Are you satisfied with AIDS prevention publicity? ...................................................... 9 Table 3-4 Summary of Local Jobs Generated by the Project in 2019 ....................................... 9 Table 3-5 EMDP M&E Matrix ................................................................................................... 12 Table 4-1 Local Jobs Generated during Construction and Women’s Employment ................. 16 Table 4-2 SGAP ....................................................................................................................... 17 Table 5-1 Distribution of Minority Population ................................................................................... 19 Table 5-2 Demographics of Minority APs ......................................................................................... 19 Table 5-3 Household Income and Expenditure of Minority APs ................................................... 20 Table 6-1 Contact Information for Grievance Redress .................................................................. 22 Table 6-2 Grievance Registration Form ........................................................................................... 22

List of Figures

Figure 1-1 Key Informant Interview and Questionnaire Survey in Minority Village .................... 3 Figure 3-1 Provisions on Work Safety ....................................................................................... 8 Figure 3-2 Guidance on EMDP Implementation by Project Consultants ................................. 11 Figure 4-1 Exchange and Training on MSW Recycling ........................................................... 15 Figure 4-2 Disclosure of Employment Information ................................................................... 15 Figure 6-1 Grievance Redress Flowchart ................................................................................ 21

Page 6: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

V

Abbreviations ADB - Asian Development Bank AH - Affected Household AP - Affected Person DMS - Detailed Measurement Survey EMDP - Ethnic Minority Development Plan FGD - Focus Group Discussion HD - House Demolition IA - Implementing Agency LA - Land Acquisition M&E - Monitoring and Evaluation MSW - Municipal Solid Waste NRCR - National Research Center for Resettlement PMO - Project Management Office PRC - People’s Republic of China RP - Resettlement Plan SGAP - Social and Gender Action Plan WWTP - Wastewater Treatment Plant

Units

Currency unit = Yuan (CNY) USD1.00 = CNY6 1 hectare = 15 mu

Page 7: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

1

1 Summary 1.1 Introduction to the Project

The Qinghai Municipal Government has used an ADB loan of $150 million and domestic counterpart funds of about $72 million to implement the Qinghai Haidong Urban-Rural Eco Development Project (hereinafter, the “Project”). The Project aims to promote urban-rural eco development, including: 1) expanding water supply, wastewater treatment and solid waste management capacity; 2) conserving water through wetland rehabilitation; 3) promoting the integrated management of river rehabilitation and flood risk control; and 4) improving integrated water resources management and institutional capacity.

The Project consists of the following components: 1) Component 1: River Rehabilitation: The objective of this component is to reduce flood risks,

maintain and improve the ecological environment, and beautify the landscape. This component includes: 1) Ping’an segment; 2) Ledu urban segment; 3) Ledu non-urban segment; 4) Riverfront shelter forest; and 5) Yizhou wetland.

2) Component 2: Eco-environment Protection and Restoration: The objective of this component is to prevent water loss and soil erosion, alleviate flood risks, reinforce embankments, and increase vegetation coverage (planting a variety of tree species on riverbanks and mountain boundary). This component includes: 1) Mountain boundary shelter forest construction in Ping’an District; and 2) Ping’an WWTP Water Reclamation Work (Phase 2).

3) Component 3: Rural Water Supply and MSW Management Infrastructure Construction: The objective of this component is to realize wastewater reclamation in Ping’an District, and MSW management in Ledu District. This component includes: 1) Urban-rural water supply; and 2) Ledu landfill reconstruction and expansion.

4) Component 4: Project Management and Capacity Building: The objective of this component is to ensure the effective operation of the EA and IAs, e.g., flood management basin planning, water conservation, sponge city practice, water quality control, response to climate change, and wetland management. 1.2 External EMDP M&E

The external resettlement M&E work of the Project is undertaken by the National Research Center for Resettlement (NRCR).

NRCR is responsible for external M&E on EMDP implementation by supervising the implementation compliance of the EMDP submitted by the Project Leading Group to ADB in June 2016, and performing a social survey and a data analysis in order to identify issues and potential risks. NRCR will also provide training that meets ADB’s safeguard requirements to stakeholders, review project progress and EMDP implementation, confirm the actual impacts of the EMDP, ensure the relevance and effectiveness of target monitoring, propose solutions, and submit M&E reports to the Haidong PMO and ADB.

By the end of July 2020, the task force conducted the third round of EMDP M&E with the aid of the Haidong PMO and local agencies concerned, held FGDs and interviews with their staff, and conducted a door-to-door survey in the project area to learn EMDP implementation.

1.2.1 Scope This M&E mainly covers:

Page 8: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

2

1) Local minority population and poverty; 2) EMDP implementation progress, key findings and suggestions on further work; 3) GAP implementation progress, key findings and suggestions on further work; 4) Information disclosure, and grievances and appeals during EMDP implementation; 5) Ensuring the relevance and effectiveness of target monitoring, and proposing solutions

1.2.2 Purpose and Key Points This report is the No.3 external EMDP M&E report of the Project, aiming to: i) ensuring that the

PMO and the IAs implement the EMDP properly, and meet its overall objectives; ii) collecting data and information to ensure implementation progress; iii) analyzing data to describe the impacts of the EMDP measures; iv) ensuring that appropriate participatory methods are used; v) monitoring indicative actions and evaluating their impacts during project implementation; and vi) ensuring that the grievance redress mechanism is effective, and updating the monitoring indicators when necessary for follow-up M&E.

By the end of July 2020, project activities had been conducted for all components, and EMDP and GAP implementation, public participation, resettlement, etc. were in progress. Therefore, the key points of this report are:

1) Checking EMDP implementation for compliance routinely; 2) Reviewing project progress and EMDP implementation, and confirming the actual impacts

of the EMDP; 3) Performing a social survey and a data analysis to identify issues and potential risks; 4) Ensuring the relevance and effectiveness of target monitoring, and proposing solutions; 5) GAP implementation progress, key findings and suggestions on further work; 6) Information disclosure, and grievances and appeals during EMDP implementation

1.2.3 Methods The task force conducted a field survey on the Lincang PMO, IAs and sample villages to learn

EMDP, GAP and public participation implementation progress, etc. using such methods as literature review, FGD, questionnaire survey and interview. In this survey, 7 FGDs and 24 key informant interviews were held, and the questionnaire survey covered 70 minority households with 198 persons.

Literature review: Documents, agreements and statistical reports on EMDP and GAP implementation progress were referred to and verified.

FGD: 7 FGDs were held with officials of the Lincang PMO, IAs and village committees, minority residents, women, etc. to learn project, EMDP, GAP, resettlement and public participation implementation progress.

Questionnaire survey: To learn different groups’ needs for and attitudes to the Project, the task force sampled 70 minority households with 198 persons, including 64 households with 175 persons in the 3 beneficiary minority villages, accounting for 47.3% of the beneficiary minority population.

Page 9: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

3

Figure 1-1 Key Informant Interview and Questionnaire Survey in Minority Village

Page 10: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

4

2 Identification of Local Minority Population According to the RP, no minority population is affected by LA and/or HD. Only the Urban-Rural

Water Supply subcomponent involves a minority population living centrally of 370 in 3 Tibetan villages in Shihuiyao Xiang (Yima, Shiguasi and Shihuiyao); the other 8 subcomponents involve scattered minority population in Nianbo, Yurun, Hongshui and Gaomiao Towns in Ledu District, and Ping’an, Xiaoxia and Sanhe Towns in Ping’an District. The project area has an affected population of 217,000, including 195,109 Han people, accounting for 89.91%. 10,054 Hui people, accounting for 4.63%; 4,192 Tibetans, accounting for 1.93%; and 3,378 Tu people, accounting for 1.56%.

In the direct beneficiary population: 1) Only the Urban-Rural Water Supply subcomponent involves a minority population living

centrally of 370 in 3 Tibetan villages in Shihuiyao Xiang (Yima, Shiguasi and Shihuiyao), in which Mayi Village has 83 households with 231 persons, including 94 Tibetans, accounting for 40.69%; Shihuiyao Village has 76 households with 343 persons, including 118 Tibetans, accounting for 34.40%; and Shiguasi Village has 40 households with 185 persons, including 158 Tibetans, accounting for 85.41%.

2) The remaining minority population involved in the Project lives in a scattered manner in Nianbo, Gaodian, Yurun, Hongshui and Gaomiao Towns in Ledu District, and Ping’an, Xiaoxia and Sanhe Towns in Ping’an District. See Table 2-1.

Table 2-1 Minority Population in the Project Area

District

Township Minority township or not

Gross populati

on

Tu Hui Tibetan Han

Component(s) involved

Population

Percent

Population

Percent

Population

Percent

Population

Percent

Ledu

Nianbo Town No 69522 1188 1.71 3369 4.85 1252 1.80 61843 88.95

Eco-environment Protection and

Restoration, River Rehabilitation

Gaodian Town No 8918 215 2.41 73 0.82 64 0.72 8496 95.27 River Rehabilitation Yurun Town No 17056 354 2.08 199 1.17 257 1.51 15076 88.39 River Rehabilitation

Hongshui Town No 19251 108 0.56 91 0.47 91 0.47 18889 98.12 River Rehabilitation Gaomiao Town No 25063 248 0.99 1480 5.91 104 0.41 228952 91.35 River Rehabilitation

Ping

’an Ping’an Town No 51770 1022 1.97 2644 5.11 1414 2.73 46033 88.92

River Rehabilitation, Eco-environment Protection and

Restoration, Urban Water Reclamation

Xiaoxia Town No 13230 156 1.18 1033 7.81 63 0.48 11886 89.84

River Rehabilitation, Eco-environment Protection and

Restoration Sanhe Town: Sanhe,

Xinzhuang, Binglingshan, Dongcun,

Xicun, Luotuobao, Zhangqizhai, Zhuangke,

Sitai, Wanzi, Xin’an, Zhongjia and Tiaoling

Villages

No 9978 76 0.76 73 0.73 577 5.78 9252 92.72 Urban-Rural Water Supply

Shihuiyao Xiang: Liming, Yes 2212 11 0.44 1092 49.31 370 16.73 739 33.41 Urban-Rural Water

Page 11: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

5

Yima, Shihuiyao, Yaozhuang and Shiguasi

Villages

Supply

Total / 217000 3378 1.56 10054 4.63 4192 1.93 195109 89.91 \ Source: data of the sixth national census in 2010, and statistics of ethnic and religious affairs bureaus

Page 12: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

6

3 EMDP Implementation M&E 3.1 Overview of the EMDP

The local minority communities have their own culture and customs. At the preparation, implementation and operation stages, the design and implementing agencies learned local minority customs and needs, and conducted project activities in a manner accepted by minority residents, ensuring the Project’s sustainability in minority areas.

The EMDP submitted by the Project Leading Group to ADB for approval in June 2016 was prepared in consultation with meaningful consultation with the minority APs, covering the Project’s positive and negative impacts to learn their attitudes to and opinions on the Project. The EMDP includes beneficiary measures to ensure that minority residents receive the benefits identified in the project impact assessment and aligned with minority cultures, and mitigation measures for the Project’s negative impacts on them.

The key points of the EMDP are: 1) Mitigation measures • Mitigation of construction impacts and safe construction Construction may affect living or cultural activities of local residents and minority residents. To

mitigate such impacts, the EMDP requires that:1) using noise reduction techniques to control noise; 2) strengthening construction site management, and establishing entry registration and parking management systems; 3) avoiding minority religious activities or festivals (e.g., not conducting construction within 500m from a mosque during Friday worships); 4) setting up relevant signs in nearby communities; and 5) including construction safety provisions in construction contracts.

• AIDS and other infectious diseases According to the EMDP, the tender documents should include provisions on the prevention and

treatment of AIDS and other infectious diseases, publicity and education on public health and AIDS prevention conducted for the construction staff, health protection measures developed for the construction staff, and brochures, posters, books, etc. on AIDS prevention and sexual harassment distributed.

• Jobs generated by the Project 135 skilled and 404 unskilled jobs will be generated at the construction stage, and 162 skilled

and 331 unskilled jobs at the operation stage (maintenance, cleaning, landscaping, etc.). According to the EMDP, 15% of these jobs will be first made available to minority residents and the poor.

• Publicity and education on employment, labor protection, environmental protection and water conservation

The EMDP requires that inclusive public participation be conducted during project implementation to protect the interests, and rights of information and participation of local residents, and improve their environmental awareness, including ensuring that local residents participate in publicity and education on environmental protection and water conservation, conducting publicity on environmental protection and water conservation at communities and schools, producing publicity materials and distributing them at communities, and holding a public hearing on the water supply and solid waste treatment rates.

• Establishing CESTs According to the EMDP, CESTs will be established to improve the environmental and public

health awareness of beneficiaries, especially minority residents. In addition, the ADB mission in October 2019 required that CESTs be established by July 30, 2020. The Haidong PMO will appoint

Page 13: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

7

a qualified social development and community participation expert to ensure that all tasks are performed as planned. This expert is being recruited.

2) Local Supporting Measures • Skills training Local handicrafts training has been offered to minority women in Yima, Shiguasi and Shihuiyao

Villages. The district women’s federation, minority and religious affairs committee, and labor and social security bureau would offer various skills training courses locally to increase job opportunities.

• Supporting measures for 3 minority villages According to the EMDP, characteristic cultivation will be supported in the 3 minority villages,

including a sea buckthorn cultivation base in Shiguasi Village, and modern garden base in Shihuiyao Village, and vegetable greenhouses in Yima Village.

3) Project Management The Haidong PMO and the IA have appointed one person to supervise implementation for each

component, including EMDP implementation. 3.1.1 Impacts on Minority Population

According to the RP, no minority population is affected by LA and/or HD. Only the Urban-Rural Water Supply subcomponent involves a minority population living centrally of 370 in 3 Tibetan villages in Shihuiyao Xiang (Yima, Shiguasi and Shihuiyao); the other 8 subcomponents involve scattered minority population in Nianbo, Yurun, Hongshui and Gaomiao Towns in Ledu District, and Ping’an, Xiaoxia and Sanhe Towns in Ping’an District. The project area has an affected population of 217,000, including 195,109 Han people, accounting for 89.91%. 10,054 Hui people, accounting for 4.63%; 4,192 Tibetans, accounting for 1.93%; and 3,378 Tu people, accounting for 1.56%.

In the direct beneficiary population: 1) Only the Urban-Rural Water Supply subcomponent involves a minority population living

centrally of 370 in 3 Tibetan villages in Shihuiyao Xiang (Yima, Shiguasi and Shihuiyao), in which Mayi Village has 83 households with 231 persons, including 94 Tibetans, accounting for 40.69%; Shihuiyao Village has 76 households with 343 persons, including 118 Tibetans, accounting for 34.40%; and Shiguasi Village has 40 households with 185 persons, including 158 Tibetans, accounting for 85.41%.

2) The remaining minority population involved in the Project lives in a scattered manner in Nianbo, Gaodian, Yurun, Hongshui and Gaomiao Towns in Ledu District, and Ping’an, Xiaoxia and Sanhe Towns in Ping’an District.

3.1.2 Sampling Survey on Minority Households 70 households with 198 persons were sampled, including 64 households with 175 persons in

the 3 beneficiary minority villages, accounting for 47.3% of the beneficiary minority population, covering 7 villages in two townships. See Table 3-1.

Table 3-1 Distribution of Minority Population Type of impact City District Township Village Minority

households Minority

population

Directly benefiting minority villages

Haidong Ledu

Sanhe Town

Sanhe 1 4 Xinzhuang 2 7

Binglingshan 1 5 Dongcun 2 7

Shihuiyao Xiang

Yima 16 36 Shihuiyao 21 47 Shiguasi 27 92

Page 14: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

8

Total 70 198 Source: door-to-door survey in July 2020

3.2 EMDP Implementation Progress

3.2.1 Alleviation Measures 1) Mitigation of construction impacts and safe construction Construction may affect living or cultural activities of local residents and minority residents. To

mitigate such impacts, the EMDP requires that:1) using noise reduction techniques to control noise; 2) strengthening construction site management, and establishing entry registration and parking management systems; 3) avoiding minority religious activities or festivals (e.g., not conducting construction within 500m from a mosque during Friday worships); 4) setting up relevant signs in nearby communities; and 5) including construction safety provisions in construction contracts.

Appropriate measures have been taken for the subcomponents that broke ground in 2019, and no appeal in this respect has been received to date.

Figure 3-1 Provisions on Work Safety

2) AIDS and other infectious diseases Construction tender documents and contracts include provisions on the prevention and

treatment of AIDS and other infectious diseases. Labor safety and disease prevention are always stressed in routine project management, such as daily meetings. Each employee has been trained on health and safety, and signed a letter of safety commitment.

The local governments would conduct publicity on AIDS prevention and treatment at all communities on World AIDS Day (December 1). In December 2019, all local governments in Haidong City conducted online and offline AIDS prevention publicity at communities, squares, stations and schools, and distributed over 500 copies of the publicity materials.

Page 15: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

9

Table 3-2 Participation in AIDS Prevention Publicity

District All participants Women (>40%) Minority residents (>50%)

N Percent N Percent N Percent Ledu 1500 100% 650 43.33% 260 17.33%

Ping’an 400 100% 180 45.0% 160 40.0% Total 1900 100% 830 43.68% 420 22.10%

It can be seen from the satisfaction survey on AIDS prevention publicity among 70 minority

respondents (including 28 women) that 100% of the respondents are satisfied with such publicity.

Table 3-3 Are you satisfied with AIDS prevention publicity?

District Very satisfied Satisfied Neither, nor Dissatisfied Very dissatisfied N Percent N Percent N Percent N Percent N Percent

Ledu 12 70.59 5 29.41 0 0.0 0 0.0 0 0.0 Ping’an 8 72.73 3 27.27 0 0.0 0 0.0 0 0.0 Total 20 71.43 8 28.57 0 0.0 0 0.0 0 0.0 Source: door-to-door survey in July 2020

3) Jobs generated by the Project 135 skilled and 404 unskilled jobs will be generated at the construction stage, and 162 skilled

and 331 unskilled jobs at the operation stage (maintenance, cleaning, landscaping, etc.). According to the EMDP, 15% of these jobs will be first made available to minority residents and the poor.

By the end of July 2020, two subcomponents had broken ground, and 60 jobs had been offered to local residents, including 57 skilled and 3 unskilled jobs, including two minority residents.

In addition, the contractors will release information on these jobs timely by various means, including without limitation WeChat public account, job fair, brochure, on-site publicity, bulletin, electronic screen, referral, etc. The contractors will also give priority to APs in employment.

Table 3-4 Summary of Local Jobs Generated by the Project in 2019

Subcomponent Job type Local jobs

Minority laborers employed Percent Daily pay

Ping’an WWTP Water Reclamation Work (Phase 2)

Unskilled 11 2 20% 150-180 yuan Skilled 3 0 0 380-400 yuan

Ledu non-urban segment Unskilled 40 0 0 130 yuan Skilled 10 0 0 240 yuan

Total 64 2

4) Publicity and education on employment, labor protection, environmental protection and water conservation

The EMDP requires that inclusive public participation be conducted during project implementation to protect the interests, and rights of information and participation of local residents, and improve their environmental awareness, including ensuring that local residents participate in publicity and education on environmental protection and water conservation, conducting publicity on environmental protection and water conservation at communities and schools, producing publicity materials and distributing them at communities, and holding a public hearing on the water supply and solid waste treatment rates

In this round of M&E, 1) The Ping’an District Water Bureau conducted publicity on environmental protection and water conservation several times in 2019 by means of media, banner, display board, brochure, souvenir, etc., with over 1,000 copies of the brochure and poster distributed;

Page 16: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

10

2) In 2019, the Ping’an District Water Bureau installed water conservation equipment and posted water conservation signs at schools; 3) In December, the Ping’an District Water Bureau gave publicity on laws and regulations on water conservation, pollution control, environmental improvement, and sustainable development, with over 2,000 of the brochure, over 1,000 copies of the brochure and poster, and over 150 souvenirs distributed; 4) In July 2016, the RP and the EMDP were disclosed in the affected townships in Ping’an and Ledu Districts; 5) The district water bureaus conducted publicity on environmental protection and water conservation in Ping’an District by means of media, banner, billboard, brochure, etc. in January 2020, with over 500 copies of the brochure and poster distributed in total; 6) The PMO conducted publicity and education on solid waste recovery in Qilidian Village, Nianbo Town in January 2020, involving 22 community residents, including 20 women.

5) Establishing CESTs According to the EMDP, CESTs will be established to improve the environmental and public

health awareness of beneficiaries, especially minority residents. In addition, the ADB mission in October 2019 required that CESTs be established by July 30, 2020. The Haidong PMO will appoint a qualified social development and community participation expert to ensure that all tasks are performed as planned. This expert is being recruited.

3.2.2 Supporting Measures of Local Governments 1) Skills training Local handicrafts training has been offered to minority women in Yima, Shiguasi and Shihuiyao

Villages. The district women’s federation, minority and religious affairs committee, and labor and social security bureau would offer various skills training courses locally to increase job opportunities. However, relevant information is unavailable because urban-rural water supply has not broken ground.

2) Supporting measures for 3 minority villages According to the EMDP, characteristic cultivation will be supported in the 3 minority villages,

including a sea buckthorn cultivation base in Shiguasi Village, and modern garden base in Shihuiyao Village, and vegetable greenhouses in Yima Village. These measures had not been implemented by the end of July 2020. According to the Haidong Municipal Ethnic and Religious Affairs Commission, these measures have been cancelled, and new measures will be planned but have not been finalized.

3.2.3 Project Management The Haidong PMO and the IA have appointed one person to supervise implementation for each

component, including EMDP implementation. In June 2019, the social development and resettlement expert trained 7 staff members of the PMO and the IA on social development and resettlement to ensure successful EMDP implementation.

The international and domestic experts were in place in May 2019 to monitor SGAP and EMDP implementation progress timely. They collected relevant information, and submitted a quarterly and semiannual progress report to ADB.

Page 17: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

11

Figure 3-2 Guidance on EMDP Implementation by Project Consultants

During the ADB mission in October 2019, the PMO appointed a coordinator (preferably a female

or minority member) to coordinate SGAP and EMDP monitoring under the direction of the project leader and consultants, including: a) conducting required activities; b) keeping records of all relevant activities; and c) ensuring effective communication between the PMO contact, consultants and contractors.

The coordinator Zhang Wenbin was appointed at the end of October 2019. Fan Lijuan (female, Han) was appointed as Deputy Director in February 2020, responsible for resettlement, EMDP and SGAP implementation.

In addition, gender and ethnic minority indicators have been included in the project performance monitoring system with the assistance of the experts. 3.3 Issues and Suggestions

3.3.1 Key Issues and Challenges 1) According to the approved EMDP, some actions will be taken at the implementation stage.

By the end of July 2020, only the Ping’an WWTP Water Reclamation Work (Phase 2), and Ledu Landfill Reconstruction and Expansion had broken ground among the 5 subcomponents that had not been adjusted. Therefore, most of the actions under the EMDP have not been started.

2) The persons responsible for EMDP implementation all subcomponents have been appointed, but are not familiar with the ADB policy and EMDP implementation enough.

3.3.2 Suggestions and Subsequent Measures 1) The PMO staff should gain relevant information through pertinent training and learning in

order to fulfill their duties and tasks properly. 2) The EMDP progresses slowly, and has been partly implemented only. The task force

suggests that with the successive construction of the subcomponents, the EMDP should be implemented successively.

3) Publicity on public health and AIDS prevention should be conducted in the project area in various forms, such as brochure, poster and book, covering epidemics and infectious diseases (including COVID-19, AIDS, influenza, etc.), and a physical checkup performed for non-local workers (e.g., setting up a temporary infirmary, taking full advantage of local medical resources), where only healthy workers can participate in project construction.

Page 18: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

12

Table 3-5 EMDP M&E Matrix Proposed action Monitoring indicator Monitoring result

1. A. Mitigation of construction impacts and safe construction Using noise reduction techniques to control

noise; Techniques used during construction, and relevant standards Frequency of overnight construction

The Ping’an WWTP Water Reclamation Work (Phase 2) is located in a hill, and has minimum impacts.

No overnight construction has been conducted.

Strengthening construction site management, and establishing entry registration and parking management systems;

Construction safety management Isolation facilities, entry registration and parking management are adequate.

Avoiding minority religious activities or festivals (e.g., not conducting construction within 500m from a mosque during Friday worships);

Comments of local residents, especially minority residents, on contractors and workers

The IA and contractors respect minority religious and cultural activities, and comply with ethnic and religious policies.

Setting up relevant signs in nearby communities

Number of signs Non-horn signs have been erected in nearby villages.

Including construction safety provisions in construction contracts

Inclusion of such provisions in contracts

Each employee has been trained on health and safety, and signed a letter of safety commitment.

B. AIDS and other infectious diseases Including provisions on the prevention and

treatment of AIDS and other infectious diseases in the tender documents

Inclusion of such provisions in tender documents

Such provisions have been included in the tender documents.

Conducting publicity and education on public health and AIDS prevention for the construction staff

Frequency of such activities and number of participants

8 public health and AIDS prevention publicity and training activities have been organized, with 290 participants in total, including 26 women.

Developing health protection measures for the construction staff

Induction physical checkup for workers;

Establishment of health files

Each employee has been trained on health and safety, signed a letter of safety commitment, and taken a health checkup; a COVID-19 contingency plan was established at the construction site during the pandemic.

Distributing brochures, posters, books, etc. on AIDS prevention and sexual harassment

Relevant publicity activities of the center for disease control

Publicity on AIDS prevention and sexual harassment has been conducted by various means, with 1,000 copies of the material distributed.

C. Publicity and education on employment, labor protection, environmental protection and water conservation 135 skilled and 404 unskilled jobs will be

generated at the construction stage, and 162 skilled and 331 unskilled jobs at the operation stage (maintenance, cleaning, landscaping, etc.).

Proportion of APs doing unskilled jobs under the Project

Men-times of vulnerable groups (women and the poor) doing unskilled jobs under the Project

60 jobs have been offered to local residents (66.67% of all jobs), including two minority residents.

Releasing employment information timely by various means

Mode of release of job opportunities

Employment information is released by various means, such as job fair, WeChat account and referral.

Complying with state and local regulations and policies

Compliance with state and local regulations and policies

A supervising agency has been appointed for on-site project management, including labor management.

D. Inclusive public participation

Page 19: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

13

Ensuring that local residents participate in publicity and education on environmental protection and water conservation

Frequency of such activities, number of participants, and percentage of minority residents and women

5 publicity and education activities have been conducted, involving 3,522 participants in total, including 2,200 women and 400 minority residents.

Conducting publicity on environmental protection and water conservation at communities and schools

Number and types of schools involved, and number of participants, where not less than 50% should be minority residents and women

One publicity and education activity on environmental protection and water conservation has been conducted at schools.

Producing publicity materials and distributing them at communities

Frequency of such activities, number of participants, and percentage of minority residents and women

4,650 copies of the poster, brochure, banner and souvenir have been distributed in total.

Holding a public hearing on the water supply and solid waste treatment rates

Frequency of public hearing, number of participants, and percentage of minority residents and women

Not started

E. Establishing CESTs Establishing 6 exemplary community

environmental supervision and education teams (two urban and 4 rural), running for 3 years, and conducting public awareness development activities in environmental management, forest protection, water conservation and waste recycling

Frequency of such activities, number of participants, and percentage of minority residents and women

The Haidong PMO has begun to recruit an expert, which had not been completed by the date of this report.

2. Local Supporting Measures: skills training Offering local handicrafts training to

minority women in Yima, Shiguasi and Shihuiyao Villages

Frequency of training, number of participants, and percentage of minority residents and women

Cancelled

Establishing a cyclic income generation pattern

Frequency of such activities, number of participants, and percentage of minority residents and women

Not started

3. Project management Training the PMO and IA staff on the EMDP

and SGAP Types and frequency of training,

and number of participants The staff of the PMO and IA was

trained twice on the EMDP in June 2019, and further training will be offered at the implementation stage.

Appointing international and domestic social development and gender experts

Number of experts, and activities The experts were in place in May 2019.

The PMO and IA should appoint dedicated staff members to implement and report EMDP, SGAP and RP implementation.

Availability of such staff members Two staff members have been appointed to implement and report on the EMDP, SGAP and RP.

Collecting data by gender and ethnic group to monitor, evaluate and report EMDP and SGAP implementation.

If data is collected as required Ongoing

Page 20: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

14

4 SGAP Implementation Monitoring 4.1 SGAP Overview

The SGAP involves 4 outputs, which are: 1) River Rehabilitation; 2) Eco-environment Protection and Restoration; 3) Rural Water Supply and MSW Management Infrastructure Construction; 4) all outputs, including jobs generated by the Project, publicity on public health and AIDS prevention, establishing CESTs, and project management.

The scope of SGAP implementation M&E is the 5 subcomponents that are still within the Project and 100% funded by ADB, namely the Ping’an segment, Yizhou wetland, the Ping’an WWTP Water Reclamation Work (Phase 2), urban-rural water supply, and Ledu Landfill Reconstruction and Expansion, excluding the 4 subcomponents that are still within the Project but have been completed, namely the Ledu urban segment, Ledu non-urban segment, riverfront shelter forest, and mountain boundary shelter forest construction in Ping’an District. 4.2 SGAP Implementation Progress

4.2.1 Output 1: River Rehabilitation During implementation, public participation activities should be conducted in the communities

along the Ping’an segment to select suitable sludge disposal and transfer sites to reduce negative impacts, and improve the public awareness of wetland conservation.

The above public participation activities will begin when the Ping’an segment and the Yizhou wetland break ground, and be conducted together with activities organized by community education and supervision teams (CESTs).

4.2.2 Output 2: Eco-environment Protection and Restoration According to the SGAP, forest protection and fire control training will be offered to residents in

Ping’an Town, and a forest protection handbook prepared. This will be implemented under the direction of the Ping’an District Forest and Grass Bureau,

which has fire control and pest control offices. 1) During the forest fire control period (November 1 to May 30), the fire control office would

conduct various publicity and training activities. 2) During the technology, culture, health and law publicity campaign in January 2019, and

Technology Publicity Day in May 2019, the Ping’an District Forest and Grass Bureau conducted publicity and education on forest protection, fire control, pest control, laws and regulations, etc. in Ping’an Town by means of media, banner, display board, brochure, souvenir, etc. Most participants were women. Over 2,000 copies of the brochure and over 5,000 copies of the leaflet were distributed.

3) In addition, forest rangers, and village and township officials have also been trained on forest protection, in which 10% of participants are women.

4) The Ping’an District Forest and Grass Bureau has also prepared a fire and pest control handbook.

4.2.3 Output 3: Rural Water Supply and MSW Management Infrastructure Construction Public consultation on Ledu Landfill Reconstruction and Expansion, and dustbin placement will

be conducted in March 2020. The Haidong Municipal and Ping’an District Water Bureaus have conducted publicity on water

conservation at communities and schools many times, and will conduct publicity on solid waste recycling in 2020 together with activities organized by CESTs.

The public hearing on the water supply and solid waste treatment rates does not apply for the

Page 21: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

15

moment, because there is no plan to collect such charges. A public hearing will be organized if such charges are to be collected or the rates are to be increased in the future.

Figure 4-1 Exchange and Training on MSW Recycling

4.2.4 All Outputs

1) Jobs generated by the Project 135 skilled and 404 unskilled jobs will be generated at the construction stage, and 162 skilled

and 331 unskilled jobs at the operation stage (maintenance, cleaning, landscaping, etc.). According to the EMDP, 30% of these jobs will be first made available to women, and 15% to minority residents and the poor.

By the end of July 2020, two subcomponents had broken ground, and 14 jobs had been offered to local residents, including 3 skilled and 11 unskilled jobs, including 3 women.

In addition, the contractors will release information on these jobs timely by various means, including without limitation WeChat public account, job fair, brochure, on-site publicity, bulletin, electronic screen, referral, etc. The contractors will also give priority to APs in employment.

Figure 4-2 Disclosure of Employment Information

Page 22: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

16

Table 4-1 Local Jobs Generated during Construction and Women’s Employment

Subcomponent Job type Local jobs Female laborers

employed Percent Daily pay

This period Cumulative This

period Cumulative This period Cumulative

Ping’an WWTP Water Reclamation

Work (Phase 2)

Unskilled 0 11 0 3 27% 150-180 yuan

Skilled 0 3 0 0 0 380-400 yuan

Ledu non-urban segment

Unskilled 0 40 0 1 2.5% 130 yuan Skilled 0 10 0 0 0 240 yuan

Total 0 64 0 4

2) Publicity on public health and AIDS prevention Construction tender documents and contracts include provisions on the prevention and

treatment of AIDS and other infectious diseases. Labor safety and disease prevention are always stressed in routine project management, such as daily meetings. Each employee has been trained on health and safety, and signed a letter of safety commitment, including 26 female employees.

The local governments would conduct publicity on AIDS prevention and treatment at all communities on World AIDS Day (December 1). In December 2019, all local governments in Haidong City conducted online and offline AIDS prevention publicity at communities, squares, stations and schools, and distributed over 500 copies of the publicity materials, in which over 350 were distributed to women.

3) Establishing CESTs CESTs will be established to improve the environmental and public health awareness of

beneficiaries, especially minority residents. In addition, the ADB mission in October 2019 required that CESTs be established by July 30, 2020. The Haidong PMO will appoint a qualified social development and community participation expert to ensure that all tasks are performed as planned. This expert will be in place by the specified date.

4) Project Management The Haidong PMO and the IA have appointed one person to supervise implementation for each

component, including SGAP implementation. In June 2019, the social development and resettlement expert trained 7 staff members of the PMO and the IA on social development and resettlement to ensure successful SGAP implementation.

The international and domestic experts were in place in May 2019 to monitor SGAP and EMDP implementation progress timely. They collected relevant information, and submitted a quarterly and semiannual progress report to ADB.

During the ADB mission in October 2019, the PMO appointed a coordinator (preferably a female or minority member) to coordinate SGAP and EMDP monitoring under the direction of the project leader and consultants, including: a) conducting required activities; b) keeping records of all relevant activities; and c) ensuring effective communication between the PMO contact, consultants and contractors. The coordinator Zhang Wenbin was appointed at the end of October 2019.

Fan Lijuan (female, Han) was appointed as Deputy Director in February 2020, responsible for resettlement, EMDP and SGAP implementation. In addition, gender and ethnic minority indicators have been included in the project performance monitoring system with the assistance of the experts.

Page 23: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

17

Table 4-2 SGAP Action Monitoring indicator Monitoring result

1. Output 1: River Rehabilitation Public consultation on the selection of

sludge disposal and transport sites to minimize negative impacts on nearby communities

Number of participants, in which not less than 50% are women

Not started

Public awareness development on wetland conservation

Activity type, frequency, number of participants (gender, ethnic group)

Not started

2. Output 2: Eco-environment Protection and Restoration Publicity and skills training on forest

protection and fire protection for residents in Ping’an District

Activity type, frequency, number of participants, in which not less than 50% are women

At least two training courses on fire control, pest control, forest protection, etc. have been offered, involving 3,200 persons in total, including 2,073 women, accounting for 64.7%.

Public participation and consultation for residents in Ping’an District, and preparation of a community forest protection handbook

Residents’ feedback collected, in which not less than 50% are women

The Ping’an District Forest and Grass Bureau has prepared a fire and pest control brochure.

3. Output 3: Rural Water Supply and MSW Management Infrastructure Construction Consultation with local residents on Ledu

landfill reconstruction and expansion Number of participants, in which

not less than 50% are women Not started

Consultation with residents in Ping’an and Ledu Districts on waste bin positions

Number and type of schools, number of participants, in which not less than 50% are women

Not started

Publicity on water conservation and solid waste recycling at communities and schools

Training material prepared for all groups and age groups

5 education activities have been conducted, involving 3,522 participants, with 4,650 copies of the material distributed.

Public hearing on water supply, cleaning and solid waste disposal charges

Number of participants, in which not less than 50% are women and not less than 40% are low-income residents

Not started

4. All Outputs Jobs generated 135 skilled and 404 unskilled jobs at the

construction stage 30% of jobs first made available to

women, and 15% to poor and minority residents (baseline data for women: 15%)

In the Ping’an WWTP Water Reclamation Work (Phase 2), 88.33% of the jobs (53) are offered to local residents, including 14 women; in Ledu Landfill Reconstruction and Expansion, 23.33%% of the jobs (7) are offered to local residents, including no woman.

162 skilled and 331 unskilled jobs at the operation stage (maintenance, cleaning, landscaping, etc.)

30% of jobs first made available to women, and 15% to poor and minority residents (baseline data for women: 20%)

Not started

Publicity on public health and AIDS prevention Public health and AIDS prevention

publicity for construction workers Training course, number of

participants (by gender and target 8 public health and AIDS

prevention publicity and training

Page 24: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

18

group) activities have been organized, with 290 participants in total, including 26 women.

Distribution of brochure, poster, etc. on AIDS prevention and sexual harassment

Brochure type and number of copies distributed

The local governments would conduct publicity on AIDS prevention and treatment at all communities on December 1 every year.

Establishing CESTs Establishing 6 exemplary community

environmental supervision and education teams (two urban and 4 rural), running for 3 years, and conducting public awareness development activities in environmental management, forest protection, water conservation and waste recycling

At least 5 members per team, in which 50% are women; frequency and type of training, number of participants (gender)

The Haidong PMO has begun to recruit an expert, which had not been completed by the date of this report.

Evaluating effects of communications on awareness development and behavior change

Investigated and evaluated by social and gender experts, and included in project progress reports

The Haidong PMO has begun to recruit an expert, which had not been completed by the date of this report.

Project Management Training the PMO and IA staff on the

EMDP and SGAP All staff of the PMO and IA should

be trained on the EMDP and SGAP (including not less than 40% should be women and ethnic minorities) (baseline: 20%).

The staff of the PMO and IA has been trained twice on the EMDP and SGAP, with 10 participants in total.

Appointing international and domestic social development and gender experts

2 men-months for international expert and 12 men-months for domestic expert

The experts are in place.

The PMO and IA should appoint dedicated staff members to implement and report SGAP implementation.

Number of staff members appointed

The PMO and IA have appointed one staff member to be responsible for the SGAP each.

The PPMS will collect data by gender and ethnic group to monitor, evaluate and report EMDP and SGAP implementation.

Social development and gender indicators included in the PPMS

Social development and gender indicators have been included in the PPMS.

Page 25: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

19

5 Sampling Survey 5.1 Methods

The task force conducted a sampling survey in 8 villages in Sanhe Town and Shihuiyao Xiang, Ledu District benefiting directly from the Project, including FGDs and key informant interviews.

70 households with 198 persons were sampled, including 64 households with 175 persons in the 3 beneficiary minority villages, accounting for 47.3% of the beneficiary minority population, covering 7 villages in two townships. See Table 5-1.

Table 5-1 Distribution of Minority Population Type of impact City District Township Village Minority

households Minority

population

Directly benefiting minority villages

Haidong Ledu

Sanhe Town

Sanhe 1 4 Xinzhuang 2 7

Binglingshan 1 5 Dongcun 2 7

Shihuiyao Xiang

Yima 16 36 Shihuiyao 21 47 Shiguasi 27 92

Total 70 198 Source: door-to-door survey in July 2020

5.2 Results

5.2.1 Population The 70 sample households have 198 persons in total, including 128 laborers, 86 women

(accounting for 43.43%), with 2.8 persons per household on average. 5.2.2 Age Structure

Among the 198 samples, 32 are aged 16 years or less, accounting for 16.16%; 77 aged 17-39 years, accounting for 38.89%; 45 aged 40-59 years, accounting for 22.73%; and 44 aged above 60 years, accounting for 22.22%. See Table 5-2.

5.2.3 Education Among the 198 samples, 92 have received primary school or below education, accounting for

46.46%; 77 have received junior high school education, accounting for 38.89%; 16 have received senior high or secondary technical school education, accounting for 8.08%; and 13 have received junior college or above education, accounting for 6.57%. See Table 5-2.

Table 5-2 Demographics of Minority APs

Item Male Female Total N Percent (%) N Percent (%) N Percent (%)

Age ≤16 years 19 16.96% 13 15.11% 32 16.16%

17-39 years 46 41.07% 31 36.05% 77 38.89% 40-59 years 22 19.64% 23 26.74% 45 22.73% ≥60 years 25 22.32% 19 22.09% 44 2.22% Subtotal 112 100% 86 100% 198 100%

Educational level (adults) Primary school or below 52 46.43% 40 46.51% 92 46.46%

Junior high school 42 37.5% 35 40.70% 77 38.89% Senior high school /

secondary technical school 10 8.93% 6 6.98% 16 8.08%

Junior college or above 8 7.14% 5 5.81% 13 6.57%

Page 26: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

20

Subtotal 112 100% 86 100% 198 100% Source: door-to-door survey in July 2020

5.2.4 Employment

Among the 70 sample households, 58 deal with farming mainly, and 12 with nonagricultural operations mainly. Most young people work outside and deal with physical labor mainly. The percentage of nonagricultural employment is 17.1%.

5.2.5 Annual Income and Expenditure The per capita annual income of the sample households is 21,573.33 yuan, per capita annual

expenditure 8,311.63 yuan, and per capita annual net income 17,766.4 yuan. See Table 5-3.

Table 5-3 Household Income and Expenditure of Minority APs

Item Average per household (yuan)

Per capita (yuan)

Percent (%)

Household income

Cultivation income 12797 4570.36 21.19 Operating income 10375 3705.36 17.18

Wage income 773.33 276.19 1.28 Property income 28500 10178.57 47.18

Other income 4960 1771.43 8.21 Subtotal (A) 60405.33 21573.33 100

Household expenditure

Agricultural productive expenditure (B) 5789.63 2067.73 24.88 Nonagricultural productive expenditure (C) 4869.77 1739.20 20.92

Nonproductive expenditure (D) 10623.43 3794.08 45.65

Item Daily expenses 1976.53 1106.86

Educational expenses 1146.80 683.19 Medical expenses 670.75 375.62

Other expenses (E) 1989.73 710.62 8.55 Subtotal (B+C+D+E) 12649.13 8311.63 100

Per capita net income (A-B-C) 17766.4 Source: door-to-door survey in July 2020

Page 27: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

21

6 Grievance Redress 6.1 Channels and Procedure

According to the survey, the existing grievance redress channels in the project area are: 1) Minority residents may reflect complaints and suggestions to their village committees, which is the main grievance redress channel; 2) Minority residents may reflect complaints and suggestions to their township governments; 3) Minority residents may reflect complaints and suggestions to the complaint handling office of the county government. All APs may maintain their rights and interests through the above channels.

A smooth grievance redress mechanism has been established to ensure the successful implementation of the EMDP.

Stage 1: If any right of AP minority resident is infringed on in terms of LA, HD, resettlement or project implementation, he/she may file an appeal to the village group or committee. If the village group or committee cannot solve such appeal, it will be referred to the township government, which should give a disposition within two weeks.

Stage 2: If the AP is dissatisfied with the disposition of Stage 1, he/she may file an appeal to the district PMO within one month after receiving such disposition, which shall make a disposition within two weeks.

Stage 3: If the AP is still dissatisfied with the disposition of Stage 2, he/she may file an appeal to the Haidong PMO within one month after receiving such disposition, which shall make a disposition within two weeks.

Stage 4: If the AP is dissatisfied with the disposition of Stage 3, he/she file an appeal with the competent authorities level by level in accordance with the Administrative Procedure Law of the PRC for arbitration after receiving such disposition.

Stage 5: If the AP is still dissatisfied with the arbitration award of Stage 4, he/she may file a suit in a civil court in accordance with the Civil Procedure Law of the PRC after receiving such disposition.

In addition, the APs may file grievances and appeals directly with the external M&E agency, or the legal, disciplinary inspection and complaint handling departments of Ping’an and Ledu Districts.

During the COVID-19 pandemic, grievance redress channels for minority residents are kept unobstructed, including such noncontact means as telephone, WeChat and the Internet.

If on-site handling is inevitable, the health checkup procedure should be observed strictly, including temperature taking and face mask wearing.

Figure 6-1 Grievance Redress Flowchart

AHs / village committees

Township t

District PMOs

Haidong PMO

Municipal / district l i t h dli

Municipal / district di i li i ti

External M&E agency

Municipal / district legal d t t

Page 28: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

22

The resettlement agencies will appoint staff members to collect and accept grievances and

appeals from the minority APs specifically. See Table 6-1.

Table 6-1 Contact Information for Grievance Redress City / district Agency Name Address Tel

Haidong City Haidong PMO Zhou Ling No.205 Ping’an Avenue, Ping’an District 15202561243

Ping’an District

Ping’an District Housing Construction Bureau Wang Xurong Junction of Ping’an Avenue and

Minhe Road, Ping’an District 13709734054

Ping’an District Water Bureau Zhong Hailin No.14 Huangyuan Street, Ping’an

District 18697212798

Ledu District

Ledu District Housing Construction Bureau Yuan Youxia No.11 Binhe South Street,

Ping’an District 18997022369

Ledu District Water Bureau Zhou Bin No.25 Wenhua Street, Ledu

District 15709822634

6.2 Recording and Feedback During implementation, the IAs have prepared a registration form to record grievances and

appeals of minority residents, as shown in Table 6-2. The task force will register and handle grievances and appeals during EMDP implementation

using this form.

Table 6-2 Grievance Registration Form Appellant Time

Accepting agency: Location Appeal

Expected solution Suggestion of the

M&E agency

Proposed solution Actual handling

Appellant (signature) Person responsible

(signature) Recorder (signature)

Notes: 1. The recorder should record the appeal and request of the appellant factually. 2. The appeal process should not be interfered with or hindered whatsoever. 3. The proposed solution should be notified to the appellant within the specified time.

6.3 Evaluation

The task force has found that information disclosure and public participation under the Project are adequate.

1) At different stages of the Project, the PMOs and the IAs have collected opinions on project design and implementation from minority residents by means of FGD, in-depth interview, stakeholder discussion, key informant interview, etc., and given feedback, and disclosed project information by means of village committee publicity, broadcast, TV, the Internet, etc. Under the leadership of the Haidong PMO, the local PMOs, township governments and village committees have established a sound grievance redress mechanism, and disclosed the contact information.

2) A transparent and effective grievance redress channel has been established, and notified to the AHs through the village committees.

3) No lawsuit arising from the infringement on the rights of minority residents has occurred to

Page 29: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

23

date. The task force thinks that the public participation and grievance redress mechanisms have

played a good role during project implementation.

Page 30: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

24

7 Findings and Suggestions 7.1 Findings

1) Organizational structure The organizational structure of the Project is well established, the roles and responsibilities of

all agencies well defined, and all agencies well equipped. However, in the resettlement agencies, some staff and jobs have been adjusted, and the newly appointed staff lacks understanding in the Project and ADB’s social safeguard policies. The Haidong Municipal Government ensures successful project preparation and EMDP implementation by way of organizational setup and capacity building. In addition, the owners, land and resources bureaus, housing construction bureaus, affected township governments and village committees also participate in resettlement.

2) Construction and resettlement progress The baseline survey was conducted in June 2019. 680 mu of collective land has been acquired,

25.76 mu of state-owned land (roads, river flats, etc.), and 128.8 mu of land occupied temporarily for the Project, involving 49 villages in 8 townships in two districts, Haidong City. 341 households with 1,420 persons have been affected by LA, and 131 households with 535 persons by temporary land occupation. The Project also affects 29 households with 53 persons, and ground attachments such as scattered trees and telegraph poles. The urban-rural water supply subcomponent involves the demolition of the properties of two entities (Wenzukou and Fatai Reservoir Management Stations) of 722 m2, including 572 m2 in simple structure and 150 m2 in masonry timber structure, affecting 27 workers. These two entities will not be relocated, and will be subject to cash compensation.

By the end of July 2020, the progress was as follows: 1) LA compensation for 9.74 mu of land for the Ping’an WWTP Water Reclamation Work

(Phase 2) had been completed, including 2.61 mu of acquired collective land and 7.13 mu of reclaimed state-owned land, affecting 3 households with 12 persons in 3 villages in Ping’an Town.

2) LA compensation agreements had been signed, and the compensation paid for Ledu Landfill Reconstruction and Expansion. 11.44 mu of collective land had been acquired, affecting 5 households with 18 persons.

3) The DMS for the Ping’an segment began in December 2019 and was underway. 4) The DMS for the Yizhou wetland and urban-rural water supply had been completed in

October 2018, LA not begun, no LA compensation agreement signed, and no compensation paid. 3) Alleviation and supporting measures under the EMDP The external M&E agency has disclosed the EMDP, and established an EMDP monitoring

network. Among the 23 activities under the EMDP, 4 have been completed, 16 are ongoing and 3 have not been started. The key issues are as follows:

a) Among the 5 unadjusted subcomponents, only the Ping’an WWTP Water Reclamation Work (Phase 2), and Ledu Landfill Reconstruction and Expansion have broken ground, so most of the measures under the EMDP have not been started or progress slowly.

b) The persons responsible for EMDP implementation for all subcomponents have been appointed, but are not familiar with the ADB policy and EMDP implementation enough.

c) Among supporting measures of local governments, skills training and knowledge enhancement has not been started. According to the EMDP, characteristic cultivation will be supported in the 3 minority villages, including a sea buckthorn cultivation base in Shiguasi Village, and modern garden base in Shihuiyao Village, and vegetable greenhouses in Yima Village. These measures had not been implemented by the end of July 2020. According to the Haidong Municipal Ethnic and Religious Affairs Commission, these measures have been cancelled, and new measures

Page 31: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

25

will be planned but have not been finalized. 4) SGAP implementation According to the approved SGAP, some actions will be taken at the implementation stage. By

the end of July 2020, only the Ping’an WWTP Water Reclamation Work (Phase 2), and Ledu Landfill Reconstruction and Expansion had broken ground among the 5 subcomponents that had not been adjusted. Therefore, most of the actions under the SGAP have not been started.

The resettlement agencies are understaffed and therefore unable to handle day-to-day work properly. In addition, in the resettlement agencies, some staff and jobs have been adjusted, and the newly appointed staff lacks understanding in the Project and ADB’s social safeguard policies.

Local women’s overall educational level is low, and lower than men. As a result, most people (including women themselves) think that women are incompetent to handle family and public affairs, and women’s needs and suggestions are often neglected at all stages.

The two components that have broken ground are under construction, and the proportion of local women employed, below the 30% target specified in the SGAP.

5) Information disclosure and grievance redress By the end of July 2020, few information disclosure and public participation activities had been

conducted, but a sound grievance redress mechanism had been established and disclosed in the project area. No appeal in this respect has been received to date. 7.2 Suggestions

1) Organizational structure The staff of the agencies concerned should further be trained on resettlement policies and

implementation, and strengthen communication and coordination by means of theoretical learning and exchange, especially visiting and learning from completed or ongoing ADB-financed projects, to further improve their efficiency and capacity.

2) EMDP implementation The PMO staff should gain relevant information through pertinent training and learning in order

to fulfill their duties and tasks properly. The EMDP progresses slowly, and has been partly implemented only. The task force suggests that with the successive construction of the subcomponents, the EMDP should be implemented successively. Publicity on public health and AIDS prevention should be conducted in the project area, covering epidemics and infectious diseases (including COVID-19, AIDS, influenza, etc.).

3) Information disclosure and grievance redress The resettlement agencies, affected township governments and village committees lack

awareness of public participation and information disclosure, and should conduct disclosure, publicity and mobilization properly, and keep minutes of meetings.

Page 32: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

26

Appendix 1 Interview Minutes Date June 16, 2020 Venue Ms Li’s home in Haidong Organizer Haidong PMO Participants Engineer Zhang of the Haidong Municipal Water Bureau, task force Topics Public participation, socioeconomic survey, EMDP implementation Key points and results

This family has 6 members. Her daughter’s two sons are at school. Her husband, daughter and son-in-law work outside. She stays at home. She is a Han resident, while his husband and daughter are Tu residents but have been assimilated by the Han people. This family formerly had 2 mu of land, all of which has been acquired. Such land was used to grow wheat and corn, with annual income of 700-800 yuan/mu. The LA compensation is 53,200 yuan, which has been paid. This family knew about LA in November 2019, and had a land ownership dispute with another group. Such dispute has been settled through coordination by the local government and the village committee.

Photo

Page 33: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

27

Appendix 2 Fieldwork Photos

Interview at the Haidong PMO

Interview at the construction site of Ledu Landfill Reconstruction and Expansion

Interview with an AH by the Ping’an District Water Bureau

Publicity on pandemic prevention and control

LA announcement

RP and EMDP disclosure

Page 34: 48102-002: Qinghai Haidong Urban-Rural Eco Development Project · 2020. 11. 3. · Project Number: 48102-002 . November 2020 . PRC: Qinghai Haidong Urban-Rural Eco Development Project

28

Safety instructions on construction site

Publicity on AIDS prevention

Exchange and training on MSW recycling

Resettlement training