4.4 design flood discharge - jica · 2014. 7. 8. · river, design flood discharge of these...
TRANSCRIPT
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-30
4.4 Design Flood Discharge
With examining the alternatives of flood management facility plan, optimal design flood discharge allocation and its flood management plan is proposed.
Since flood control works for 1/30 years flood have been conducted in Pasig and Lower Marikina River, design flood discharge of these sections shall be set considering the previous works.
Design flood water levels will be checked with the design water level of the JICA Study.
4.4.1 Evaluation of Conditions for Pasig-Marikina River Channel Improvement Project (PMRCIP)
(1) Design Flood Discharge for PMRCIP
PMRCIP can be divided as the following 4 phases.
Phase I : Detailed Design Works for Whole Section
Phase II : River Improvement Works from River Mouth to Confluence of Napindan Channel
Phase III : River Improvement Works from Confluence of Napindan Channel to Diversion of Manggahan Floodway without MCGS
Phase IV : River Improvement Works from Diversion of Manggahan Floodway to Marikina Bridge with MCGS
In the detailed design conducted in 2002, the design flood discharge allocation of 1/30 years flood was formulated as shown in Figure 4.29, and river improvement works and construction of MCGS was planned.
Source: Preparatory Study for Pasig-Marikina Channel Improvement Project (Phase III)
Figure 4.27 H-Q Curve Formulated in JICA M/P Study
(2) Operation of NHCS The JICA Study planned that NHCS should be closed during flood to block inflow from Laguna Lake to Pasig River while the WB Study planned that NHCS should be open during flood to expect reverse flow from Pasig River to Laguna Lake.
Advantages and disadvantages of operation of NHCS are summarized in Table 4.15. With the following reasons, it is judged as appropriate that NHCS shall be closed during flood to avoid uncertain phenomena in flood management plan.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-31
Diversion through Napindan Channel to Laguna Lake is uncertain since reverse flow will happen depending on water level in Laguna Lake.
If NHCS would open during flood, channel improvement of Napindan Channel is inevitable to protect surrounding dense urbanized area resulting difficulty of land acquisitions.
Table 4.15 Comparison of NHCS Operation
Open during Flood Close during Flood
Advantage Gate operation is not required. Inflow from Laguna Lake to Pasig River can be prevented.
Disadvantage
In case WL of Laguna Lake is higher than Pasig River, flood risk in the center of Metro Manila increases due to inflow from Laguna Lake to Pasig River.
Diversion of flood discharge to Laguna Lake through Napindan Channel is uncertain depending of water levels of Laguna Lake and Pasig River.
If diversion to Laguna Lake through Napindan Channel is included in the discharge allocation plan, discharge of Lower Marikina becomes large resulting increase of flood risk and heightening of dyke is required.
Napindan Channel also requires improvement works such as dyke heightening.
Gate operation is required.
Evaluation Not Favorable Favorable Source: JICA Study Team
(3) Necessity of MCGS The JICA Study planned to fully utilize Laguna Lake with sure diversion through Manggahan Floodway controlled by MCGS. On the other hand, the WB Study recommended that MCGS is not necessary and flood control is planned with diversion through Napindan Channel. Advantages and disadvantages of MCGS are summarized in Table 4.16.
MCGS is necessary for sure diversion of design discharge to Laguna Lake. Besides, excess flood also can be diverted to Manggahan Floodway by MCGS resulting mitigation of flood risk at the center of Metro Manila.
Without MCGS, re-improvement of channel downstream of Rosario Weir since HWL increases. Rise of HWL leads to increase of flood disaster potentials.
Table 4.16 Comparison of With/Without MCGS
Without MCGS With MCGS
Advantage WL of Upper Marikina decrease.
Sure diversion is available. Excess flood also can be diverted resulting
mitigation of flood risk at the center of Metro Manila.
Disadvantage
Flood risk for excess flood increase. HWL in Pasig-Lower Marikina increases
leading to increase of flood disaster potentials
Gate operation is required. WL in Upper Marikina rise.
Evaluation Not Favorable Favorable Source: JICA Study Team
The basic specifications and operation rule of MCGS designed in the detailed design in 2002 are summarized in Table 4.17.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-32
Table 4.17 Comparison of With/Without MCGS Item Specifications
Design Discharge 500m3/s (Lower Marikina River) Design HWL Upstream Side: EL. 17.40m
Downstream Side: EL. 14.74m Design Section Riverbed Width: 43.5m
Riverbed Elevation: EL.8.0m Gate Dimensions: W20m x H11m x 2 units
Type: Roller Gate Operation Rule MCGS Gate shall be operated together with Rosario Weir with monitoring of levels of Manila
Bay, Laguna Lake and Sto.Nino for secure diversion of design discharge. Source: JICA Study Team
Discharge allocations to Manggahan Floodway and Lower Marikina, and influence to downstream with/without MCGS is simulated with following conditions. Diversion volumes of the both case, 1/20 years flood discharge allocation, and longitudinal flow profile of it are summarized in Table 4.18, Figure 4.30 and 4.31, respectively.
Design discharge at Sto.Nino is 2,900 m3/s which equivalent to 1/20 years flood with natural retarding function is applied.
NHCS is closed not to divert to Laguna Lake through Napindan Channel.
Manggahan Floodway has designed capacity without illegal residents in the river course.
Without MCGS, the following disadvantage occurs.
Design diversion discharge to Manggahan Floodway of 2,400 m3/s is not secured.
Water levels in Pasig-Lower Marikina River rise higher than the design HWL about 1 m as maximum resulting increase of flood risk. RE-improvement such as heightening of dyke is required.
Table 4.18 Diversion Discharge With/Without MCGS
Marikina (Before Diversion)
Lower Marikina (After Marikina) Manggahan Floodway
Without MCGS 2,900 m3/s 1,000 m3/s 1,900 m3/s With MCGS 2,900 m3/s 500 m3/s 2,400 m3/s
Source: JICA Study Team
2,900
2,900
1,600 1,000 1,000 1,000
0 1,900
650
Laguna Lake
Ma
ng
ah
an
F
loo
dw
ay
Na
pin
da
n
Ch
an
ne
l
Marikina River (Lower)Pasig River M
ari
kin
a R
ive
r
Sto.Nino
Pasig River
Sa
n J
ua
n R
ive
r
NHCS
Rosario Weir
PPManila Bay
2,900
2,900
1,200 600 500 500
0 2,400
650
Laguna Lake
Ma
nga
han
F
loo
dw
ay
Na
pin
dan
C
ha
nn
el
Marikina River (Lower)Pasig River M
ari
kin
a R
ive
r
Sto.Nino
Pasig River
Sa
n J
uan
Riv
er
MCGS
NHCS
Rosario Weir
PPManila Bay
Source: JICA Study Team
Figure 4.28 Discharge Allocation With/Without MCGS (1/20 years, with Natural Retarding Function)
Without MCGS With MCGS
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
33
So
urce
: JIC
A St
udy
Team
Fi
gure
4.2
9 Fl
ow P
rofil
e With
/With
out M
CG
S
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-34
(4) Consideration of Urban Development along Marikina River
At near Rosario Weir, urban development program is on-going by private developers as shown in Figure 4.32. Influence of this development is calculated based on the design drawings of development program. As shown in Figure 4.33, rise of water level due to the urban development is just 20 cm which can be adjusted in the Phase IV Project.
Figure 4.30 H-Q Curve Formulated in WB Study
Source: JICA Study Team
Figure 4.31 Flow Profile of Influence of Urban Development Program
(5) Evaluation of Probability of Design Flood Discharge by PMRCIP Based on the review of hydrological analysis referring the observed flood in recent years, probable flood discharge of 1/30 years return period is estimated at 3,100 m3/s which is 200 m3/s larger than the design discharge of 2,900 m3/s. Table 4.19 shows the probable discharges at Sto.Nino with natural retarding function. According to Table 4.19, the design flood discharge of PMRCIP of 2,900 m3/s is reevaluated as 1/20 years flood.
Table 4.19 Reviewed Probable Discharge at Sto.Nino
Return Period Sto.Nino (With Inundation) Return Period Sto.Nino (With Inundation) 2 1,620 30 3,030 5 2,290 50 3,220
10 2,670 100 3,580 20 2,860
Source: JICA Study Team
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-35
4.4.2 Flood Management Plan for 1/30 Years Flood
(1) Conditions for Examination The following conditions were applied to examine the flood management plan for 1/30 years flood.
Change of HWL at the section where PMRCIP has been conducted or on-going since the social infrastructures have been developed based on the designed HWL. Therefore, HWL at the section where PMRCIP has conducted including Phase III Section shall remain same. For Phase IV Section, minor change is considered acceptable.
Diversion through Napindan Channel to Laguna Lake is uncertain since reverse flow will happen depending on water level in Laguna Lake. As discussed in Section 4.4.1, NHCS is closed during flood and inflow from Pasig River to Laguna Lake through Napindan Channel is not considered.
MCGS is to be constructed.
Flood management plan is examined for 1/30 years flood with natural retarding function as shown in Figure 4.34.
3,100
3,100
1,300 600 500 500
0 2,600
700
Laguna Lake
Mang
ahan
Flo
odwa
y
Napin
dan
Chan
nel
Marikina River (Lower)Pasig River
Nangka River
Marik
ina Ri
ver
Sto.Nino
Pasig River
San Ju
an Ri
ver
MCGS
NHCS
Rosario Weir
Montalban
PP
Natural Retarding Basin
Source: JICA Study Team
Figure 4.32 Discharge Allocation of 1/30 Years Flood
(2) Alternatives of Flood Management Plan for 1/30 Flood Since the discharge allocation downstream of MCGS is already fixed, flood management plan can be considered upstream of MCGS such as following 2 alternatives.
A: To retain flood discharge in Laguna Lake through Manggahan Floodway.
B: To retain flood discharge at retarding basin upstream of Sto.Nino.
Thus the following 2 alternatives for countermeasure are examined adding to the Phase IV components consisting channel improvement from MCGS to Marikina Bridge and construction of MCGS.
Alternative-a: Phase IV with Dyke Heightening + Improvement of Manggahan Floodway
Alternative-b: Phase IV without Dyke Heightening + Construction of Retarding Basin
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-36
(3) Alternative-a: Phase IV with Dyke Heightening + Improvement of Manggahan Floodway
1) Discharge Allocation 3,100 m3/s between Risario Weir to Sto.Nino with Channel Improvement
2,600 m3/s to Manggahan Floodway and 500 m3/s to Lower Marikina River
2) Improvement Plan In Upper Marikina River, heightening of dyke such as parapet is required since HWL rise about
50 cm of the flow sections designed in the detailed design in 2002.
Since required discharge of Manggahan Floodway is 2,600 m3/s which is 200 m3/s larger than design discharge of 2,400 m3/s, improvement works is required.
Source: JICA Study Team
Figure 4.33 Alternative-a: Phase IV with Dyke Heightening + Improvement of Manggahan Floodway (1/30 Years)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-37
(4) Alternative-b: Phase IV without Dyke Heightening + Construction of Retarding Basin
1) Discharge Allocation 2,900 m3/s between Risario Weir to Sto.Nino with control of 200 m3/s at the retarding basins
upstream of Sto.Nino.
2,400 m3/s to Manggahan Floodway and 500 m3/s to Lower Marikina River
2) Improvement Plan In Upper Marikina River, flow sections designed in the detailed design in 2002 can be remained.
Required discharge of Manggahan Floodway is 2,400 m3/s, same as design discharge. To recover the designed flow capacity, dredging works and relocation of illegal residents are required.
Increase of capacity of retarding basin up to 35 MCM is required by excavation of natural retarding basin where current capacity is 5 MCM.
Source: JICA Study Team Figure 4.34 Alternative-b: Phase IV without Dyke Heightening + Construction of Retarding
Basin (1/30 Years)
3) Scale of Retarding Basin
a) Retarding Basin Development In case the retarding basin development scenario is taken for 1/100 years flood management measures, the necessary capacities of retarding basin to reduce discharge at Sto.Nito to 3,100m3/s and 2,900m3/s are 20MCM and 25MCM, respectively. (refer to Table 4.20 and Figure 4.35)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-38
Table 4.20 Control Volume of Retarding Basin for 1/30 Flood
Return Period Number of FCB(Locations)
Area (ha)
Volume (1,000m3)
Average Excavation Depth(m)
Natural drainage
Before Control (m3/s)
After Control (m3/s)
Effect (m3/s)
30 8 371 20,007 4.0 Yes 3,970 3,100 870
30 8 371 25,296 7.5 No 3,970 2,890 1,080
Source: JICA Study Team
Source: JICA Study Team Figure 4.35 Hydrograph at Sto.Nino before and after Control by Retarding Basin
b) Enhancement of Natural Retarding Basin Necessary volume of retarding basin is estimated at 5 MCM to control discharge at Sto.Nino to 2,900 m3/s from 3,100 m3/s by cutting 200 m3/s of 1/30 years flood. Total retaining volume will be 35 MCM with current natural retarding function of 30 MCM.
Area and location of natural retarding basin is assumed as inundation area by 1/30 years flood by simulation as shown in Figure 4.36. The area is about 1,000ha and its capacity is about 30 MCM.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-39
Source: JICA Study Team
Figure 4.36 Location of Natural Retarding Basin (Estimated Inundation Area of 1/30 years Flood)
Inundation Area :949ha Inundation Volume :30.3MCM
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-40
(5) Evaluation of Alternatives
The 2 alternatives shown in Table 4.21 are compared as summarized in Table 4.22. Their discharge allocations and flow profiles are shown in Figure 4.38 to 4.40. Both alternatives is feasible, however, if land acquisition for retarding basin is difficult, Alternative-a is recommended since it can be implemented in the Phase IV Project.
Table 4.21 Summary of Alternatives for 1/30 Years Flood Management
Alternative Pasig NHCS Lower Marikina MCGS Mangahan Floodway Upper Marikina Upper-Upper
Marikina
a Existing Condition Close
River Improvement (PhaseⅢ)
With Excavation &
Widening Q=2,600m3/s
River Improvement (DD 2002) With CV*
Existing Condition +Natural Retarding Basin
b Existing Condition Close
River Improvement (PhaseⅢ)
With Excavation(removal of sedimentation)
Q=2,400m3/s
River Improvement (DD 2002) With CV*
Existing Condition +Natural Retarding Basin+Additional Capacity 5MCM
CV:Circulo Verde Development Plan
Upper Marikina River Improvement(DD 2002) ; Q2,900m3/s Source: JICA Study Team
3,100
3,100
1,300 600 500 500
0 2,600
700
Laguna Lake
Mang
ahan
Flo
odwa
y
Napin
dan
Chan
nel
Marikina River (Lower)Pasig River
Nangka River
Marik
ina Ri
verSto.Nino
Pasig River
San Ju
an Ri
ver
MCGS
NHCS
Rosario Weir
MontalbanAlternative-02Return Period: 30-yearNatural Retarding Basin: withNHCS: CloseMCGS: With
PP
Natural Retarding Basin
2,900
2,900
1,300 600 500 500
0 2,400
700
Laguna Lake
Mang
ahan
Flo
odwa
y
Napin
dan
Chan
nel
Marikina River (Lower)Pasig River
Nangka River
Marik
ina Ri
ver
Sto.Nino
Pasig River
San Ju
an Ri
ver
MCGS
NHCS
Rosario Weir
MontalbanAlternative-03Return Period: 30-yearNatural Retarding Basin +Flood Control Basin:NHCS: Close
PP
Natural Retarding Basin+Additonal CapacityV=5MCM
Source: JICA Study Team
Figure 4.37 Alternatives of Design Flood Discharge Allocation for 1/30 Years Flood
Alternative-a
Alternative-b
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-41
Table 4.22 Comparison of Alternatives for 1/30 Years Flood Management Alternative-a:
Channel Improvement of Marikina River + MCGS + Improvement of Manggahan
Floodway
Alternative-b: Channel Improvement of Marikina River +
MCGS + Retarding Basin
Structures Channel Improvement of Marikina River (PhaseⅡ&Ⅲ&Ⅳ)
MCGS
Channel Improvement of Marikina River (PhaseⅡ&Ⅲ&Ⅳ)
MCGS Discharge Allocation
3,100 m3/s at Rosario Weir is diverted to Main River with 500 m3/s and to Manggahan Floodway with 2,600 m3/s.
3,100 m3/s discharge is reduced to 2,900 m3/s at Sto.Nino by retarding basin. 2,900 m3/s at Rosario Weir is diverted to Main River with 500 m3/s and to Manggahan Floodway with 2,400 m3/s.
Water Level
Less than HWL in Pasig River. Less than HWL in Lower Marikina River. Excess HWL with 0.1 m to 0.5 m in Upper Marikina River.
Less than HWL in Pasig River. Less than HWL in Lower Marikina River. Excess HWL with 0.1 m to 0.5 m in Upper Marikina River due to Urban Development Project.
Measures for Excess Flood
Excess flood can be diverted to Laguna Lake by MCGS.
Excess flood can be diverted to Laguna Lake by MCGS.
Necessity of Additional Works
There is no re-improvement in PhaseII and III sections. Heightening of Phase IV section is required. Improvement of Manggahan Floodway is required.
There is no re-improvement in Phase II, III and IV sections. Construction of retarding basin upstream of Sto.Nino is required after Phase IV.
Evaluation Social impact is less since there is no change of HWL in Phase II and III sections. Heightening of Phase IV section is available. Discharge of excess flood to the center of Metro Manila can be controlled.
Good
Social impact is less since there is no change of HWL in Phase II, III and IV sections. Construction of retarding basin should be after Phase IV Project. Land acquisition for retarding basin is required. Discharge of excess flood to the center of Metro Manila can be controlled.
Fair Source: JICA Study Team
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
42
So
urce
: JIC
A St
udy
Team
Fi
gure
4.3
8 F
low
Pro
file
of A
ltern
ativ
e-a
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
43
So
urce
: JIC
A St
udy
Team
Fi
gure
4.3
9 Fl
ow P
rofil
e of
Alte
rnat
ive-
b
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-44
(6) Scale of Manggahan Floodway Improvement
1) Current Conditions Manggahan Flood way was completed in 1988 with the design discharge of 2,400m3/s. However, flow area has been reduced mainly due to houses in river course and sedimentation. If design discharge of 2,400m3/s flows into the channel, water level rise about 1.2m higher than design HWL, which is higher than current dyke level in the section from 1.5 to 3.0 km from Rosario Weir.
Figure 4.40 Current Conditions of Manggahan Floodway
Figure 4.41 Longitudinal Flow Profile (Current and after Excavation, Q=2,400m3/s)
2) Restoration to 2,400m3/s
This alternative is to restore capacity of Manggahan Floodway to the original design capacity of 2,400m3/s by resettlement of houses in river course and dredging works to the design riverbed level. Water level of the floodway with Q=2,400m3/s is confirmed by non-uniform flow calculation. Typical section and longitudinal flow profile are shown in Figure 4.44 and 4.45, respectively.
Lower End Start W.L.: Laguna Lake W.L. 13.9m River Section: Current condition (with Houses, n=0.300)
After dredging condition (n=0.030) Calculation Case: Design discharge 2400m3/s
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-45
Figure 4.42 Typical Section after Dredging Works
Figure 4.43 Longitudinal Flow Profile (After Excavation, Q=2,400m3/s)
3) Improvement to 2,600m3/s Water level increases about 30cm at Rosario Weir if discharge of 2,600m3/s flows into Manggahan Floodway. To reduce the water level to same as 2,400m3/s discharge, widening of river course is required as show in Figure 4.46. Longitudinal flow profile is shown in Figure 4.47.
Current Condition
After Dredging
Lower End Start W.L.: Laguna Lake W.L. 13.9m River Section: After dredging condition (n=0.030) Calculation Case: Design discharge 2400m3/s
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-46
Figure 4.44 Typical Section after Widening
Figure 4.45 Longitudinal Flow Profile
(After Excavation Q=2,400m3/s, With Widening Q=2,600m3/s)
0.5m 1:2.0
150m 1:2.0 1:2.0
Current Condition
After Dredging After Improvement
After Improvement
Current Condition
After Dredging
Lower End Start W.L.: Laguna Lake W.L. 13.9m River Section: After dredging condition (n=0.030)
After improvement condition (n=0.030) Calculation Case: After dredging Q=2400m3/s
After improvement Q=2600m3/s
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-47
(7) Lower Reach of MCGS
1) 1/30 Years Flood Allocation
River channel improvement in San Juan River is planned of which design discharge at confluence is 780m3/s with 1/100 years flood while 1/30 years flood discharge is 670m3/s. Since the applied hyetograph is different, peak discharge after the confluence is becomes 1,300m3/s which is 100 m3/s larger than the design discharge in the detailed design in 2002 as shown in Figure 4.48 and 4.49.
Figure 4.46 1/30 Years Flood Allocation in Pasig River
Figure 4.47 Hydrograph of 1/30 Years Flood at Confluence of San Juan River
2) 1/30 Years Flood Measure To flow the increased design discharge of 1,300m3/s, dredging of lower Pasig Reach from 0.0k to 2.0k to the design riverbed level in 1990 Master Plan. Longitudinal Flow Profile is shown in Figure 4.50.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
48
Sour
ce: J
ICA
Stud
y Te
am
Figu
re 4
.48
Long
itudi
nal F
low
Pro
file
of P
asig
-Low
er M
arik
ina
(Q=1
,300
m3 /s
)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-49
4.4.3 Flood Control Measures for 1/100 Years Flood
(1) Possible Measures for 1/100 Years Flood
As measures to be implemented after the Phase IV completed, flood control effects of possible 1/100 flood control facilities at upstream of Sto.Nino. Possible flood control facility is as follows.
Dam
Retarding Basin
Dam + Retarding Basin
Source: JICA Study Team Figure 4.49 Possible Flood Control Facilities Upstream of Sto.Nino for 1/100 Years Flood
(2) Flood Control Effect of Dam
For examination of effect of dam, 4 cases of reservoir capacities with 55 MCM, 65 MCM, 80 MCM and 90 MCM are examined. H-V curve is estimated based on the reservoir volumes by elevation which estimated by the WB Study since it was not examined in the JICA M/P Study. H-V curve is estimated by 1 m interval of elevation by spline interpolation. H-V relation and curve are shown in Table 4.23 and Figure 4.42, respectively.
Table 4.23 H-V Relation of Proposed Dam
Elevation(m) Volume(MCM) 55 0 60 2.325 80 32.325
100 89.025 120 181.53 140 320.63
Source: Master Plan for Flood Management in Metro Manila and Surrounding Areas, the World Bank
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-50
Source: JICA Study Team
Figure 4.50 H-V Curve of Proposed Dam
1) Conditions for Estimation of Flood Control Effect of Dam Flood control effect of dam is estimated based on the following conditions.
In the WB Study, sedimentation volume varies depending on dam height because it is estimated as 10% of total reservoir capacity. However, since sedimentation does not related to dam height, fixed dead volume is applied same as the JICA M/P Study.
Considering the safety factor, flood control capacity is set as 1.2 times of calculated flood control capacity
Peak outflow discharge is set considering flow capacity of downstream.
Basic specifications of dams are summarized in Table 4.24.
Table 4.24 Specifications of Dams Examined
Case H (m) E L top (m)
LWL (m)
SWL (m)
V total (1,000m3)
V effective (1,000m3)
V dead (1,000m3) Orifice
55MCM 68 98 67 93 63,551 54,398 9,153 5.7×5.7×3unit
65MCM 71 101 67 96 73,684 64,531 9,153 4.3×4.3×3unit
80MCM 75 105 67 100 86,342 77,189 9,153 3.1×3.1×3unit
90MCM 77 107 67 102 96,316 87,163 9,153 3.1×3.1×3unit Source: JICA Study Team
2) Estimation Results Flood control effect of dam is estimated as summarized in Table 4.25 and Figure 4.43 to 4.45. It is noted that hydrographs at Montalban and Sto.Nino does not consider inundation upstream.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-51
Table 4.25 Specifications of Dams Examined
Case Dam
Montalban (m3/s) Sto.Nino (m3/s) Peak Inflow (m3/s) Peak Outflow (m3/s)
55MCM
3,230
1,820 2,840 3,790 65MCM 1,450 2,500 3,470 80MCM 1,050 2,140 3,100 90MCM 710 1,900 2,900
Source: JICA Study Team
Source: JICA Study Team
Figure 4.51 Hydrographs at Dam Location
Source: JICA Study Team
Figure 4.52 Hydrographs at Montalban
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-52
Source: JICA Study Team
Figure 4.53 Hydrographs at Sto.Nino
(3) Flood Control Effect of Retarding Basin
1) Conditons for Estimation of Flood Control Effect of Retarding Basin Specifications of retarding basins are determined with the following conditions.
Candidate areas are selected based on the inundation area of 2009 Flood and un-urbanized area as of 2011. Bed elevation of retarding basin is determined as the level which allows natural drain to river. HWL of retarding basin is determined as same as HWL of Marikina River at drainage outlet position. HWL of Mrikina River is same as the design high water level.
Length of overflow dyke is determined to maximize capacity of retarding basin.
Specifications and locations of candidate retarding basins are shown in Table 4.26 and Figure 4.47.
Table 4.26 Specifications of Candidate Retarding Basin
NO. Area (ha)
HWL (EL.m)
Bed Elevation (EL.m)
Depth (m)
Capacity* (1,000m3)
1 85 26.254 22.254 4.0 4,870 2 114 26.142 22.142 4.0 6,195 3 82 24.877 20.877 4.0 4,267 4 8 24.749 20.749 4.0 397 5 36 23.880 19.880 4.0 1,901 6 21 21.761 17.761 4.0 1,137 7 16 21.229 17.229 4.0 835 8 8 21.637 17.637 4.0 405
Total 371 20,007 Remarks: Capacity is 1.2 times of calculated capacity considering safety factor. Source: JICA Study Team
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-53
Source: JICA Study Team
Figure 4.54 Locations of Candidate Retarding Basin
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-54
2) Estimation Results
The results of estimation of the maximum flood control effect of retarding basins against 1/100 years flood is shown in Table 4.26 and Figure 4.46. Effect is only 740 m3/s as evaluated as discharge at Sto.Nino.
Table 4.27 Flood Control Effect of Retarding Basin
Return Period Dam Size Number of
FCB(Locations) Area (ha)
Volume (1,000m3)
Average Excavation Depth(m)
Natural drainage
Before Control (m3/s)
After Control (m3/s)
Effect (m3/s)
100 Without Dam (FCB Only) 8 371 20,004 4 Yes 4,973 4,232 741
Source: JICA Study Team
Source: JICA Study Team
Figure 4.55 Hydrograph of Retarding Basin Effect at Sto.Nino (1/100 Flood) (4) Flood Control Effect of Dam + Retarding Basin
1) Conditons for Estimation of Flood Control Effect of Retarding Basin
The following cases are examined as the combination of dam and retarding basin.
Table 4.28 Estimation Cases of Dam + Retarding Basin
Case Composition Case 1 Dam (55MCM) + Retarding Basin (Max, Natural Drain) Case 2 Dam (65MCM) + Retarding Basin (Max, Natural Drain)
Source: JICA Study Team
2) Estimation Results The results of estimation of the maximum flood control effect of retarding basins against 1/100 years flood is shown in Table 4.29 and Figure 4.48.
Table 4.29 Flood Control Effect of Dam + Retarding Basin
Case Dam Size Number of FCB(Locations)
Area (ha)
Volume (1,000m3)
Average Excavation Depth(m)
Natural drainage
Before Control (m3/s)
After Control (m3/s)
Effect (m3/s)
Case1 55MCM 8 371 20,004 4 Yes 3,790 3,090 700
Case2 65MCM 8 371 20,004 4 Yes 3,470 2,850 620
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-55
Source: JICA Study Team
Source: JICA Study Team
Figure 4.56 Hydrographs of Dam + Retarding Basin Effect at Sto.Nino
(5) Lower Reach of MCGS
1) 1/100 Years Flood Allocation
1/100 years flood allocation in lower reach of MCGS is as shown in Figure 4.59 and 1/100 years flood discharge at river mouth becomes 1,400m3/s assuming channel improvement of San Juan River with design discharge of 780m3/s is completed. It is 200m3/s higher than the design discharge in the detailed design in 2002.
Case 1
Case 2
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-56
Figure 4.57 1/100 Years Flood Allocation in Pasig River and Hydrograph at Confluence of San
Juan River
2) 1/100 Years Flood Measure
To flow the increased design discharge of 1,400m3/s, dredging of lower Pasig Reach from 0.0k to 5.6k to the design riverbed level in 1990 Master Plan. Longitudinal Flow Profile is shown in Figure 4.50.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
57
So
urce
: JIC
A St
udy
Team
Fi
gure
4.5
8 Lo
ngitu
dina
l Flo
w P
rofil
e of
Pas
ig-L
ower
Mar
ikin
a (Q
=1,4
00m
3 /s)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-58
4.4.4 Flood Management Plan for 1/100 Years Flood Flood management plan for 1/100 years is examined considering development scenario of flood management measures. (1) Urgent Flood Management Measures
As the urgent flood management measures until the completion of Phase IV Project, the following 3 alternatives are considerable.
Alt-O: 1/30 years flood (as of 2002) measures by Phase IV component (Q=2,900m3/s at Sto.Nino)
Alt-A: 1/30 years flood measures by Phase IV components with improvement of Manggahan Floodway (Q=3,100m3/s at Sto.Nino)
Alt-B: 1/30 years flood measures by Phase IV components with improvement of retarding basin in upper-upper Marikina (Q=2,900m3/s at Sto.Nino)
Out of 3 alternatives, 2 alternatives to improve up to 1/30 years flood measures are recommended because additional measures can be included in Phase IV Project.
Table 4.30 Alternatives for Urgent Flood Management Measures
Source: JICA Study Team
(2) Development Scenario to 1/100 Years Flood Management
Alternatives of the phased development scenario to 1/100 years flood management are shown in Figure 4.50. After the Phase IV Project completed, safety degree can be improved by construction of dam or dam + retarding basin.
As for retarding basin development, the following 3 patterns shown in Figure 4.49 are possible. It shall be determined in detailed design stage.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-59
Source: JICA Study Team
Figure 4.59 Pattern of Retarding Basin Development
■Natural Retarding Basin
■Enhancement of Retarding Function (as of mid-stage of development)
■Retarding Basin Development
“Natural Retarding Basin” is to maintain current natural retarding function of basin. Some urbanized area will be included in the retarding basin.
“Retarding Basin Development” is to develop about 400 ha out of 1,000 ha natural retarding basin.
“Enhancement of Retarding Function” is to excavate whole or parts of 400 ha to improve retarding functions.
Current natural retarding basin is 1,000 ha with capacity of 30 MCM. Out of it, urbanized area is 60% with capacity of 18 MCM, and candidate retarding basin has area of 400 ha with capacity of 12 MCM.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
60
So
urce
: JIC
A St
udy
Team
Figu
re 4
.60
Alte
rnat
ives
of P
hase
d D
evel
opm
ent S
cena
rio
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-61
Source: JICA Study Team
Source: JICA Study Team
Figure 4.61 Images of Development Scenario(A-1 to A-3)
A-1: Dam + Natural Retarding Basin
Step1: 1/30 years
Step2: 1/100 years (Dam Completed)
A-2-1: Dam
Step1: 1/30 years
Step2: 1/100 years (Dam Completed)
A-3: Dam + Retarding Basin
Step1: 1/30 years
Step2: 1/30+α (Enhance of Retarding Function)
Step3: 1/100 years (Dam + Retarding Basin)
A-2-2: Dam + Temporary Retarding Basin
Step1: 1/30 years
Step2: 1/30+α(Enhance of Retarding Function)
Step3: 1/100 years (Dam Completed)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-62
Source: JICA Study Team
Figure 4.62 Images of Development Scenario(B-1 to B-4)
O-1: Dam + Natural Retarding Basin
Step1: 1/30 yeras (as of 2002)
Step2: 1/100 years (Dam Completed)
O-2: Dam
Step1: 1/30 years (as of 2002)
Step2: 1/100 years (Dam Completed)
B-1: Dam + Enhancement of Retarding Function
Step1: 1/30 (Enhance of Retarding Function)
Step2: 1/100 years (Dam Completed)
B-2-1: Dam
Step1: 1/30 (Enhance of Retarding Function)
Step2: 1/100 years (Dam Completed)
B-3: Dam + Retarding Basin Development
Step1: 1/30 (Enhance of Retarding Function)
Step2: 1/30 + α (Enhance of Retarding
Function)
Step3: 1/100 (Dam + Retarding Basin)
B-2-2: Dam Step1: 1/30 (Enhance of Retarding Function)
Step2: 1/30+α(Enhance of Retarding Function)
Step3: 1/100 years (Dam Completed)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-63
(3) Alternatives of 1/100 Years Flood Management Plan with Phase IV + Manggahan Floodway as 1/30 Years Measure
There are 4 alternatives can be applied if Phase IV + Manggahan Floodway is applied as 1/30 years flood management measures.
Alt A-1: Dam + Natural Retarding Basin
Alt A-2-1: Dam Only
Alt A-3: Dam + Retarding Basin Construction
Alt A-2-2: Dam + Temporary Retarding Basin (after dam completed, retarding basin will be demolished and land use changed.)
(4) Alternatives of 1/100 Years Flood Management Plan with Phase IV + Retarding Basin as 1/30 Years Measure
There are 6 alternatives can be applied if Phase IV + Retarding Basin is applied as 1/30 years flood management measures.
Alt O-1: Dam + Natural Retarding Basin
Alt O-2: Dam Only
Alt B-1: Dam + Natural Retarding Basin + Excavation of Retarding Basin
Alt B-2-1: Dam + Temporary Retarding Basin (after dam completed, retarding basin will be demolished and land use changed.)
Alt B-3: Dam + Retarding Basin Construction
Alt B-2-2: Dam + Temporary Retarding Basin (after dam completed, retarding basin will be demolished and land use changed.)
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
64
Tabl
e 4.
31
Alte
rnat
ives
for
Urg
ent F
lood
Man
agem
ent M
easu
res (
Sto.
Nin
o: 3
,100
m3 /s)
Fl
ood
Man
agem
ent
Mea
sure
s fo
r 1/1
00 Y
ears
Floo
dAl
tern
ativ
e-A-
1Al
tern
ativ
e-A-
2-1
Alte
rnat
ive-
A-3
Alte
rnat
ive-
A-2-
2
Disc
harg
e Al
loca
tion
Uppe
r Upp
er M
arik
ina
Rive
rD
am +
Nat
ural
Ret
ardi
ng B
asin
Dam
: 55
MCM
, Nat
ural
Ret
ardi
ng B
asin
: 30
MCM
Cha
nnel
Impr
ovem
ent
+ D
amDa
m: 8
0MCM
Cha
nnel
Impr
ovem
ent
+ D
am +
Ret
ardi
ngB
asin
Dam
: 55M
CM
Reta
rdin
g Ba
sin:
20M
CM
Cha
nnel
Impr
ovem
ent
+ D
am (
+E
nhan
cem
ent
of R
etar
ding
Fun
ctio
n)Da
m: 8
0MCM
Uppe
r Mar
ikin
a Ri
ver
Phas
e IV
Com
pone
nts
+ He
igth
ning
to3,
100m
3/s
Phas
e IV
Com
pone
nts
+ He
igth
ning
to3,
100m
3/s
Phas
e IV
Com
pone
nts
+ He
igth
ning
to3,
100m
3/s
Phas
e IV
Com
pone
nts
+ He
igth
ning
to3,
100m
3/s
Man
gaha
nDr
edgi
ng to
2,6
00m
3/s
Dred
ging
to 2
,600
m3/
sDr
edgi
ng to
2,6
00m
3/s
Dred
ging
to 2
,600
m3/
s
Lowe
r Mar
ikin
a Ri
ver
Curre
nt P
hase
III C
ompo
nent
sCu
rrent
Pha
se II
I Com
pone
nts
Curre
nt P
hase
III C
ompo
nent
sCu
rrent
Pha
se II
I Com
pone
nts
Pasi
g Ri
ver
Phas
e II
+ Dr
edgi
ng to
1,4
00m
3/s
Phas
e II
+ Dr
edgi
ng to
1,4
00m
3/s
Phas
e II
+ Dr
edgi
ng to
1,4
00m
3/s
Phas
e II
+ Dr
edgi
ng to
1,4
00m
3/s
61,8
13.7
65,6
10.6
66,2
76.1
69,4
92.5
(1.0
00)
(1.0
61)
(1.0
72)
(1.1
24)
Adva
ntag
esSc
ale
of D
am c
an b
e m
inim
ize
by u
tiliz
atio
n of
natu
ral r
etar
ding
bas
in.
Land
use
of re
tard
ing
basi
n is
ava
ilabl
e.
Safe
ty d
egre
e ca
n be
impr
oved
ste
pwis
e. S
cale
of d
am c
an b
e m
inim
ized
by
enha
ncem
ent o
fre
tard
ing
func
tion.
Mul
tiple
use
of r
etar
ding
bas
in is
ava
ilabl
e.
Land
use
of re
tard
ing
basi
n af
ter e
nhan
cem
ent o
ffu
nctio
n is
ava
ilabl
e.
Disa
dvan
tage
sLa
ndus
e of
reta
rdin
g ba
sin
shal
l be
regu
late
d.Ap
plic
able
onl
y wh
en g
eolo
gica
lly a
vaila
ble.
Land
acq
uisi
tion
of re
tard
ing
basi
n is
requ
ired.
Dam
is a
pplic
able
onl
y wh
en g
eolo
gica
llyav
aila
ble.
Sin
ce d
am d
evel
opm
ent i
s pl
anne
daf
ter e
nhan
cem
ent o
f ret
ardi
ng fu
nctio
n, in
vest
for t
empo
rary
mea
sure
is re
quire
d.
Proj
ect C
ost(m
illion
pes
o)
1,050
3,230
2,140
800
3,100
3,100
500
500
2,600
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nan
gka
Rive
r
Dam
Marikina River
Sto.
Nin
o
MCG
S
NH
CS
Rosa
rio
Wei
r
Mon
talb
an
V=8
0MCM
1,050
3,230
2,140
800
3,100
3,100
500
500
2,600
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nan
gka
Rive
r
Dam
Marikina River
Sto.
Nin
o
MCG
S
NH
CS
Rosa
rio
Wei
r
Mon
talb
an
V=8
0MCM
1,820
3,230
2,840
800
3,100
3,100
500
500
02,600
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nan
gka
Rive
r
Dam
Marikina River
Sto.
Nin
o
MCG
S
NH
CS
Rosa
rio
Wei
r
Mon
talb
an
V=5
5MCM
Nat
ural
Re
tard
ing
Basi
nA=
1000
ha
1,820
3,230
2,840
800
3,100
3,100
500
500
02,600
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nan
gka
Rive
r
Dam
Marikina River
Sto.
Nin
o
MCG
S
NH
CS
Rosa
rio
Wei
r
Mon
talb
an
V=55
MCM
Floo
d Co
ntro
l Ba
sin
A=40
0ha
So
urce
: JIC
A St
udy
Team
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
65
Tabl
e 4.
32
Alte
rnat
ives
for
Urg
ent F
lood
Man
agem
ent M
easu
res (
Sto.
Nin
o: 2
,900
m3 /s)
Fl
ood
Man
agem
ent
Mea
sure
s fo
r 1/1
00 Y
ears
Floo
dAl
tern
ative
-O-1
Alte
rnat
ive-O
-2Al
tern
ative
-B-1
Alte
rnat
ive-B
-2-1
Alte
rnat
ive-B
-3Al
tern
ative
-B-2
-2
Disc
harg
e Al
locat
ion
Uppe
r Upp
er M
ariki
na R
iver
Dam
+ N
atur
al R
etar
ding
Bas
inDa
m: 6
5 M
CM, N
atur
al Re
tard
ing B
asin:
30
MCM
Chan
nel I
mpr
ovem
ent +
Dam
Dam
: 90M
CM
Dam
+ R
etar
ding
Bas
inDa
m: 5
5MCM
Na
tura
l Ret
ardin
g Ba
sin:
30M
CM+
Reta
rding
Bas
in: 5
MCM
Chan
nel I
mpr
ovem
ent +
Dam
(Enh
ance
men
t of R
etar
ding
Bas
in)
Dam
: 90M
CM
Cha
nnel
Impr
ovem
ent
+ D
am +
Ret
ardi
ngBa
sin
Dam
: 65M
CM
Reta
rdin
g Ba
sin 4
00ha
, 20M
CM
Chan
nel I
mpr
ovem
ent +
Dam
(Enh
ance
men
t of R
etar
ding
Bas
in)
Dam
: 90M
CM
Uppe
r Mar
ikina
Rive
rPh
ase
IV C
ompo
nent
sPh
ase
IV C
ompo
nent
sPh
ase
IV C
ompo
nent
sPh
ase
IV C
ompo
nent
sPh
ase
IV C
ompo
nent
sPh
ase
IV C
ompo
nent
s
Man
gaha
nCu
rrent
Plan
to 2
,400
m3/
sCu
rrent
Plan
to 2
,400
m3/
sCu
rrent
Plan
to 2
,400
m3/
sCu
rrent
Plan
to 2
,400
m3/
sCu
rrent
Plan
to 2
,400
m3/
sCu
rrent
Plan
to 2
,400
m3/
s
Lowe
r Mar
ikina
Rive
rCu
rrent
Pha
se III
Com
pone
nts
Curre
nt P
hase
III C
ompo
nent
sCu
rrent
Pha
se III
Com
pone
nts
Curre
nt P
hase
III C
ompo
nent
sCu
rrent
Pha
se III
Com
pone
nts
Curre
nt P
hase
III C
ompo
nent
s
Pasig
Rive
rPh
ase
II + D
redg
ing to
1,4
00m
3/s
Phas
e II +
Dre
dging
to 1
,400
m3/
sPh
ase
II + D
redg
ing to
1,4
00m
3/s
Phas
e II +
Dre
dging
to 1
,400
m3/
sPh
ase
II + D
redg
ing to
1,4
00m
3/s
Phas
e II +
Dre
dging
to 1
,400
m3/
s
61,6
25.3
65,2
57.5
63,5
18.5
67,6
83.3
66,0
87.7
69,1
39.4
(1.0
00)
(1.0
59)
(1.0
31)
(1.0
98)
(1.0
72)
(1.1
22)
Adva
ntag
esSc
ale o
f Dam
can
be
mini
mize
by
utiliz
ation
of
natu
ral r
etar
ding
basin
.La
ndus
e of
reta
rding
bas
in is
avail
able.
Safe
ty d
egre
e ca
n be
impr
oved
ste
pwise
. Sca
leof
dam
can
be
mini
mize
d by
enh
ance
men
t of
reta
rding
func
tion.
Land
use
of re
tard
ing b
asin
afte
r enh
ance
men
t of
func
tion
is av
ailab
le.
Safe
ty d
egre
e ca
n be
impr
oved
ste
pwise
. Sca
leof
dam
can
be
mini
mize
d by
enh
ance
men
t of
reta
rding
func
tion.
Land
use
of re
tard
ing b
asin
afte
r enh
ance
men
t of
func
tion
is av
ailab
le.
Disa
dvan
tage
sLa
ndus
e of
reta
rding
bas
in sh
all b
e re
gulat
ed.
Appli
cable
only
whe
n ge
ologic
ally
avail
able.
Land
use
of re
tard
ing b
asin
shall
be
regu
lated
.
Dam
is a
pplic
able
only
when
geo
logica
llyav
ailab
le. S
ince
dam
dev
elopm
ent i
s pla
nned
afte
r enh
ance
men
t of r
etar
ding
func
tion,
inve
stfo
r tem
pora
ry m
easu
re is
requ
ired.
Land
acq
uisitio
n of
reta
rding
bas
in is
requ
ired.
Dam
is a
pplic
able
only
when
geo
logica
llyav
ailab
le. S
ince
dam
dev
elopm
ent i
s pla
nned
afte
r enh
ance
men
t of r
etar
ding
func
tion,
inve
stfo
r tem
pora
ry m
easu
re is
requ
ired.
Proje
ct C
ost(m
illion
pes
o)
710
3,230
1,900
800
2,900
2,900
500
500
02,400
Laguna Lake
Mangahan Floodway
Mar
ikin
a Riv
er
(Low
er)
Nang
ka R
iver
Dam
Marikina River
Sto.
Nino
MCG
S
NHCS
Rosa
rioW
eir
Mon
talb
an
V=90
MCM
710
3,230
1,900
800
2,900
2,900
500
500
02,400
Laguna Lake
Mangahan Floodway
Mar
ikin
a Riv
er
(Low
er)
Nang
ka R
iver
Dam
Marikina River
Sto.
Nino
MCG
S
NHCS
Rosa
rioW
eir
Mon
talb
an
V=90
MCM
710
3,230
1,900
800
2,900
2,900
500
500
02,400
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nang
ka R
iver
Dam
Marikina River
Sto.
Nin
o
MCG
S
NHC
S
Rosa
rioW
eir
Mon
talb
an
V=90
MCM
1,820
3,230
2,840
800
2,900
2,900
500
500
02,400
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nan
gka R
iver
Dam
Marikina River
Sto.
Nino
MCG
S
NHC
S
Rosa
rioW
eir
Mon
talb
an
V=55
MCM
Natu
ral
Reta
rdin
g Ba
sin+A
ddito
nal
Capa
city
V=5M
CM
1,450
3,230
2,500
800
2,900
2,900
500
500
02,400
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nang
ka R
iver
Dam
Marikina River
Sto.
Nino
MCG
S
NHC
S
Rosa
rioW
eir
Mon
talb
an
V=65
MCM
Natu
ral
Reta
rdin
g Bas
inA=
1000
ha
1,450
3,230
2,500
800
2,900
2,900
500
500
02,400
Laguna Lake
Mangahan Floodway
Mar
ikin
a Ri
ver
(Low
er)
Nang
ka R
iver
Dam
Marikina River
Sto.
Nino
MCG
S
Floo
d Co
ntro
l Bas
in
A=40
0ha
NHC
S
Rosa
rio
Wei
r
Mon
talb
an
V=65
MCM
So
urce
: JIC
A St
udy
Team
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
66
(5)
Com
pari
son
with
Pro
pose
d M
easu
res b
y W
B S
tudy
Fe
asib
ility
, mea
sure
s ag
ains
t exc
ess
disc
harg
e, e
cono
mic
effi
cien
cy a
nd s
ocia
l im
pact
are
com
pare
d am
ong
Alt
A-2
-1, A
lt B
-3 a
nd th
e pr
opos
ed m
easu
res
by W
B
Stud
y as
show
n in
Tab
le 4
.33.
Tabl
e 4.
33
Com
pari
son
with
Pro
pose
d M
easu
res b
y W
B S
tudy
Alt
A-2
: Dam
Onl
y A
lt B
-3: D
am +
Ret
ardi
ng B
asin
Con
stru
ctio
n W
B S
tudy
D
isch
arge
A
lloca
tion
1,050
3,230
2,140
800
3,100
3,100
1,400
600
500
500
02,600
780
Laguna Lake
Mangahan Floodway
Napindan Channel
Mar
ikin
a Ri
ver
(Low
er)
Pasi
g Ri
ver
Nan
gka
Rive
r
Dam
Marikina River
Sto.
Nin
o
Pasi
g Ri
ver
San Juan River
MCG
S
NH
CS
Rosa
rio
Wei
r
Mon
talb
an
Alte
rnat
ive-
ARe
turn
Perio
d: 1
00-y
ear
Dam
: Lar
geFl
ood
Cont
rol B
asin
: with
out
NH
CS: C
lose
MCG
S: W
ith
PP
V=80
MCM
1,450
3,230
2,500
800
2,900
2,900
1,400
600
500
500
02,400
780
Laguna Lake
Mangahan Floodway
Napindan Channel
Mar
ikin
a Riv
er
(Low
er)
Pasi
g Riv
er
Nang
ka R
iver
Dam
Marikina River
Sto.
Nino
Pasi
g Riv
er
San Juan River
Manila Bay
MCG
S
Floo
d Co
ntro
l Bas
in
A=40
0ha
NHCS
Rosa
rioW
eir
Mon
talb
an
Alte
rnat
ive-
BRe
turn
Perio
d: 1
00-y
ear
Dam
: Med
ium
Floo
d Co
ntro
lBas
inN
HCS
: Clo
seM
CGS:
With
PP
V=65
MCM
Scal
e of
Fa
cilit
y D
am: V
=55M
CM
R
etar
ding
Bas
in: W
ithou
t C
hann
el Im
prov
emen
t:
Pasi
g : 1
,400
m3 /s
N
apin
dan
Can
nel:
With
out
Low
er M
arik
ina:
500
m3 /s
Man
gaha
n Fl
oodw
ay:2
,600
m3 /s
U
pper
Mar
ikin
a : 3
,100
m3 /s
U
pper
-Upp
er M
arik
ina:
3,1
00m
3 /s
Dam
: V=6
5MC
M
Ret
ardi
ng B
asin
: 371
ha(8
site
s)
Cha
nnel
Impr
ovem
ent:
Pa
sig
:1,4
00m
3 /s
Nap
inda
n C
anne
l: w
ithou
t Lo
wer
Mar
ikin
a: 5
00m
3 /s
Man
gaha
n Fl
oodw
ay:2
,400
m3 /s
U
pper
Mar
ikin
a: 2
,900
m3 /s
U
pper
-Upp
er M
arik
ina:
2,9
00m
3 /s
Dam
: H=7
2m
Nat
ural
Ret
ardi
ng B
asin
: 980
ha
Cha
nnel
Impr
ovem
ent:
Pasi
g : 1
,800
m3 /s
N
apin
dan
Can
nel:
800m
3 /s
Low
er M
arik
ina
: 1,2
00m
3 /s
Man
gaha
n Fl
oodw
ay:2
,000
m3 /s
U
pper
Mar
ikin
a : 3
,000
m3 /s
U
pper
-Upp
er M
arik
ina:
2,9
00m
3 /s
Feas
ibili
ty
Hei
ghte
ning
a p
art o
f Pha
se IV
Sec
tion
is re
quire
d.
A
dditi
onal
wor
k fo
r Pha
se II
I and
IV is
not
requ
ired.
In
flow
thro
ugh
Nap
inda
n is
unc
erta
in.
Dre
dgin
g, a
dditi
onal
wor
ks i
n Ph
ase
III
and
IV S
ectio
ns
and
heig
hten
ing
of N
apin
dan
Chan
nel i
s req
uire
d.
Mea
sure
s fo
r Ex
cess
Flo
od
Con
trolle
d by
MC
GS
C
ontro
lled
by M
CG
S
Floo
d ris
k in
crea
se.
Proj
ect C
ost
63,0
75 M
Pes
os (1
00%
) 65
,808
M P
esos
(104
%)
82,7
63 M
Pes
os (1
31%
) So
cial
Impa
ct
Hei
ghte
ning
a p
art o
f Pha
se IV
Sec
tion
is re
quire
d.
Land
acq
uisi
tion
for r
etar
ding
bas
in is
requ
ired.
La
nd a
cqui
sitio
n fo
r N
apin
dan
heig
hten
ing
and
reta
rdin
g ba
sin
is re
quire
d.
Sour
ce: J
ICA
Stud
y Te
am
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-67
4.4.5 Project Cost Estimate for Alternatives
Project cost is estimated based on the previous studies, “The Preparatory Study for Pasig-Mairkina River Channel Improvement (Phase III)” conducted by JICA (hereinafter referred to as the “JICA FS”) and “Master Plan for Flood Management in Metro Manila and Surrounding Areas” conducted by WB (hereinafter referred to as the “WB Study”) as shown below.
Table 4.34 Source of Cost Estimation Section/Facility Scale Source & Base Year of Estimation Reference in Original Report
Pasig River
1,300m3/s WB Study in 2011 P5-105 1,400m3/s WB Study in 2011 P5-105
Pasig River Phase2 Phase2 JICA FS in 2010 P6-5 Lower Marikina River Phase3 JICA FS in 2010 P6-5 MCGS MCGS JICA FS in 2010 P6-5
Manggahan Floodway
2,400m3/s WB Study in 2011 P5-105 2,600m3/s WB Study in 2011 P5-105
Upper Marikina River
Phase4 JICA FS in 2010 P6-5 3,100m3/s WB Study in 2011 P6-5
Upper Upper Marikina River
NRB WB Study in 2011 P5-105 RB 20MCM RB 8MCM RB 5MCM CI 2,900m3/s WB Study in 2011 P5-105 CI 3,100m3/s WB Study in 2011 P5-105
Dam
90MCM WB Study in 2011 P5-105 80MCM WB Study in 2011 P5-105 65MCM WB Study in 2011 P5-105 55MCM WB Study in 2011 P5-105
RB: Retarding Basin, CI: Channel Improvement, NRB: Natural Retarding Basin
The following assumptions are applied to estimate the project costs. <WB Study> The following ratios are applied to estimate Engineering Service Cost, Administration Cost and Physical Contingency, referring to the WB Study Report. Since Price Contingency was not estimated in the WB Study, it is estimated as 10% of all other costs considering recent price escalation in Metro Manila.
Engineering Service Cost: 16% of Direct Construction Cost Administration Cost: 35% of Direct Construction Cost and Compensation Cost Physical Contingency: 5% of Direct Construction Cost
<JICA FS> All necessary cost items except price contingency was estimated in the JICA FS, however, compensation, engineering service, administration and physical contingency was not estimated by section/facility. Thus, these costs are estimated by ratio of direct construction cost as shown below. Price Contingency is estimated as 10% of all other costs considering recent price escalation in Metro Manila.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-68
Table 4.35 Project Cost Allocation by Component
Financial Project Cost of Phase III
unit: Million Pesos
年
Direct Construction Consulting Services Compensation Adm.
Phase II Phase III Physical Conting
Non structural Measures
Construction Supervision
Physical Contingency
Base Cost Physical Conting
Base Cost
a b c d e f g h i
2013 0 0 0 97.7 80.6 8.9 17.4 0.9 6.5
2014 630.6 451.4 54.1 65.2 53.7 6 37.8
2015 945.3 675.4 81 65.2 53.7 6 54.6
2016 945.3 675.4 81 65.2 53.7 6 54.6
2017 313.6 220.6 26.7 32.6 26.9 3 18.7
Total 2834.8 2022.8 242.8 325.9 268.6 29.9 17.4 0.9 172.2
0.58358 0.41642
Phas Ⅱ 2834.8 141.7 190.2 156.7 17.4 10.2 0.5 100.5
Phas Ⅲ 2022.8 101.1 135.7 111.9 12.5 7.2 0.4 71.7
Direct construction
cost
Compensation cost
Engineering service cost
Administration cost
Physical contingency
cost
a ,b g d+e i c+e+f
Phas Ⅱ 2834.8 10.2 346.9 100.5 159.6
Phas Ⅲ 2022.8 7.2 247.6 71.7 114
Financial Project Cost of Phase IV
unit: Million Pesos
年
Direct Construction Consulting Services Compensation Adm.
MCGS Phase IV Physical Conting
Non structural Measures
Construction Supervision
Physical Contingency
Base Cost Physical Conting
Base Cost
a b c d e f g h i 2017 40.8 2 4 0.2 1.5
2018 496.2 481.6 48.9 97.7 131.2 11.5 14.1 0.7 28.6
2019 744.8 720.2 73.3 65.2 87.5 7.6 50.8
2020 744.8 720.2 73.3 65.2 87.5 7.6 50.8
2021 744.8 720.2 73.3 65.2 87.5 7.6 50.8
2022 243 235.2 23.9 32.6 43.7 3.8 17.5
Total 2973.6 2877.4 292.7 325.9 478.2 40.1 18.1 0.9 200
0.508221 0.491779
MCGS 2973.6 148.8 165.6 243.0 20.4 3.0 0.1 101.6
Phase IV 2877.4 143.9 160.3 235.2 19.7 15.1 0.8 98.4
Direct constructio
n cost
Compensation cost
Engineering service
cost
Administration cost
Physical contingenc
y cost
a ,b g d+e i c+e+f
MCGS 2973.6 3 408.6 101.6 169.3
Phase IV 2877.4 15.1 395.5 98.4 164.4
Remarks for cost estimate of each section/facility is as follows. (1) Pasig River
Based on the direct construction cost of riverbed excavation to increase flow capacity up to 1,700m3/s which estimated by the WB Study, direct construction cost for channel improvement work is estimated with following manner. It is noted that compensation is not included.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-69
c) Direct Construction Cost Direct Construction Cost: 4,825mil.peso(1,700m3/s) Increase of Flow Capacity: 1,700-1,200=500m3/s Unit Cost for Flow Capacity Increase: 9.65 mil.peso/1m3/s Flow Capacity Improvement up to 1,300m3/s: (1,300-1,200)×9.65=965 mil.peso Flow Capacity Improvement up to 1,400m3/s: (1,400-1,200)×9.65=1,930 mil.peso
d) Compensation Cost
Since the work component is riverbed excavation, compensation is not estimated.
(2) Pasig River Phase2
Price contingency is added to the cost which estimated in the JICA FS.
(3) Lower Marikina Phase3 Price contingency is added to the cost which estimated in the JICA FS. (4) MGCS Price contingency is added to the cost which estimated in the JICA FS.
(5) Upper Marikina
1) Phase4
Price contingency is added to the cost which estimated in the JICA FS.
2) 3,100m3/s Direct construction cost and compensation cost are estimated by target flow capacity ratio based on Phase 4 cost of which target capacity is 2,900m3/s. (6) Manggahan Floodway
1) 2,400m3/s
The following cost estimate is applied based on the WB Study.
Direct Construction Cost: 3,252mil.peso Compensation Cost: 89mil.peso
2) 2,600m3/s
Direct construction cost and compensation cost are estimated by target flow capacity ratio based on the WB Study.
a) Direct Construction Cost
2,400m3/s: 3,252 mil.peso 2,600m3/s: (2,600/2,400)×3,252=3,523.0 mil.peso
b) Compensation Cost 2,400m3/s: 89mil.peso 2,600m3/s: (2,600/2,400)×89=96.4 mil.peso
(7) Upper-upper Marikina River
1) Natural Retarding Basin (NRB)
Only compensation cost is estimated based on the WB Study. The unit compensation cost by the WB
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-70
Study is expensive, 32 mil. Peso/ha since it includes compensation for houses/building. Thus, 5 mil. peso/ha is applied for compensation of bare land based on the hearing results to DPWH.
2) Retarding Basin (RB) Major works for retarding basin construction with capacity of 8 MCM and 5 MCM is excavation. The direct construction cost is estimated applying unit cost of 300 peso/m3 for excavation, hauling and other works. For the improvement works to 20 MCM capacity, unit price of 200 peso/m3 for embankment is applied.
Table 4.36 Cost Estimate of Retarding Basin Case Cost Item Work Item Unit Q'ty
Unit Cost(peso)
Cost(mil.peso)
RemarksPriceYear
Excavation m3 - 300 - Including Hauling & Finishing 2011
Embankment m3 - 200 - 2011
Total - Urban Area ha 600 32,000,000 19,200 Land + House 2011
Bare Land ha 400 5,000,000 2,000 Land only 2012
Total 21,200 Excavation m3 - 300 - Including Hauling & Finishing 2011
Embankment m3 1,960,000 200 392 2011
Total 392 Urban Area ha - 32,000,000 - Land + House 2011
Bare Land ha 400 5,000,000 2,000 Land only 2012
Total 2,000 Excavation m3 8,000,000 300 2,400 Including Hauling & Finishing 2011
Embankment m3 - 200 - 2011
Total 2,400 Urban Area ha - 32,000,000 - Land + House 2011
Bare Land ha 400 5,000,000 2,000 Land only 2012
Total 2,000 Excavation m3 5,000,000 300 1,500 Including Hauling & Finishing 2011
Embankment m3 - 200 - 2011
Total 1,500 Urban Area ha - 32,000,000 - Land + House 2011
Bare Land ha 250 5,000,000 1,250 Land only 2012
Total 1,250
Compensation
Direct ConstructionCost
Compensation
NRB
20 MCM
8 MCM
5MCM
Direct ConstructionCost
Compensation
Direct ConstructionCost
Compensation
Direct ConstructionCost
3) Channel Improvement Works (CI) The direct construction cost for channel improvement to the capacity of 2,900 m3/s is estimated based on the WB Study of which major works is embankment. The direct construction cost for channel improvement to the capacity of 3,100 m3/s is estimated applying capacity ratio. The compensation cost is estimated based on Phase 4 unit cost by the JICA FS applying channel length. a) Direct Construction Cost
2,900m3/s: 1,341 mil.peso (WB Study) 3,100m3/s: (3,100/2,900)×1,341=1,433.5 mil.peso
b) Compensation Cost Phase IV Section (Upper Marikina, 6.8km Length) 2,900m3/s: 15.1 mil.peso 3,100m3/s: 16.1 mil.peso
Upper Upper Marikina Section (14.2km Length) 2,900m3/s: (14.2/6.8) x 15.1 = 31.5 mil.peso 3,100m3/s: (14.2/6.8) x 16.1 = 33.6 mil.peso
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-71
(8) Dam
The unit construction cost per 1m dam height is estimated based on the direct construction cost estimated by the WB Study. The necessary dam height for storage capacity is estimated based on H-V curve formulated by the Study, and the direct construction cost is estimated as follows.
Table 4.37 Cost Estimate of Dam
Case Dam Height (m) Direct Construction Cost
(mil.peso) 55 MCM 68 8,160 60 MCM 69 8,280 65 MCM 71 8,520 80 MCM 75 9,000 90 MCM 78 9,360
(9) Cost for Each Section and Estimation of Current Price Since base years of cost estimation is different between the JICA FS (2010) and the WB Study (2011), the current price as of year 2012 is estimated applying the price escalations based on CPI of Metro Manila as shown in Table 10. The prices before and after conversion is shown in Table 12 and Table 13, respectively. Applied price escalations are as follows.
2010 2012: 1.070 2011 2012: 1.029
Table 4.38 CPI of Metro Manila Year 2010 2011 2012 CPI 116.3 120.9 124.4
(10) Project Costs of Proposed Alternatives
The summary of project cost estimate of proposed alternatives is shown in Table 4.39 while the breakdown of each alternative is shown in Table 4.42.
Table 4.39 Summary of Project Cost of Proposed Alternatives (2012 Price)
Scale Alternatives Components Project Cost
(million peso) 1/30 O PhaseIV Component+NRB:30MCM 20,131.9
A PhaseIV Component+NRB:30MCM + Manggahan Floodway Improvement 22,170.8
B PhaseIV Component +RB:35MCM 25,034.1 1/100 A-1 Dam:55MCM+NRB:30MCM 59,866.0
A-2-1 Dam:80MCM 63,074.9 A-3 Dam:55MCM+RB:20MCM 66,110.7
A-2-2 Dam:80MCM* 66,742.1 O-1 Dam:65MCM+NRB:30MCM 59,694.5 O-2 Dam:90MCM 62,772.4 B-1 Dam:55MCM+RB:35MCM 61,479.3
B-2-1 Dam:90MCM* 65,064.5 B-3 Dam:65MCM+RB:20MCM 65,808.3
B-2-2 Dam:90MCM* 66,439.6 Note) NRB: Natural Retarding Basin, RB: Retarding Basin, *After Dam, RB will be demolished.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
72
Tabl
e 4.
40
Proj
ect C
ost b
efor
e C
onve
rsio
n un
it: m
illio
n pe
so
Sect
ion
Con
tent
s
Dire
ct
cons
truct
ion
cost
Com
pens
atio
n co
st
Engi
neer
ing
serv
ice
cost
Ad
min
istra
tion
cost
Phys
ical
co
ntin
genc
y co
st
Pric
e co
ntin
genc
y co
st
Tota
l R
emar
ks
a b
c=a*
16%
d=
(a+b
)*3.
5%
e=a*
5%
f=Σ(
a~e)
*10%
g=
Σ(a~
f)
Pasi
g R
iver
1,
300m
3 /s
965.
0
0.0
15
4.4
33
.8
48.3
12
0.2
1,
321.
7
2011
1,40
0m3 /s
1,
930.
0
0.0
30
8.8
67
.6
96.5
24
0.3
2,
643.
2
2011
Pasi
g R
iver
Pha
se2
Phas
e2
2,83
4.8
10
.2
346.
9
100.
5
159.
6
345.
2
3,79
7.2
20
10
Low
er M
arik
ina
Riv
er
Phas
e3
2,02
2.8
7.
2
247.
6
71.7
11
4.0
24
6.3
2,
709.
6
2010
MC
GS
MC
GS
2,97
3.6
3.
0
408.
6
101.
6
169.
3
365.
6
4,02
1.7
20
11
Man
ggah
an F
lood
way
2,
400m
3 /s
3,25
2.0
89
.0
520.
3
116.
9
162.
6
414.
1
4,55
4.9
20
11
2,60
0m3 /s
3,
523.
0
96.4
56
3.7
12
6.7
17
6.2
44
8.6
4,
934.
6
2011
Upp
er M
arik
ina
Riv
er
Phas
e4
2,87
7.4
15
.1
395.
5
98.4
16
4.4
35
5.1
3,
905.
9
2010
3,10
0m3 /s
3,
075.
8
16.1
42
2.8
10
5.2
17
5.7
37
9.6
4,
175.
2
2010
Upp
er U
pper
Mar
ikin
a R
iver
NR
B 0.
0
21,2
00.0
0.
0
742.
0
0.0
2,
194.
2
24,1
36.2
20
11
RB
20M
CM
2,
792.
0
2,00
0.0
44
6.7
16
7.7
13
9.6
55
4.6
6,
100.
6
2011
RB
8MC
M
2,40
0.0
2,
000.
0
384.
0
154.
0
120.
0
505.
8
5,56
3.8
20
11
RB
5MC
M
1,50
0.0
1,
250.
0
240.
0
96.3
75
.0
316.
1
3,47
7.4
20
11
CI 2
,900
m3 /s
1,
341.
0
31.5
21
4.6
48
.0
67.1
17
0.2
1,
872.
4
2011
CI 3
,100
m3 /s
1,
433.
5
33.6
22
9.4
51
.3
71.7
18
2.0
2,
001.
5
2011
Dam
90M
CM
9,
360.
0
0.0
1,
497.
6
327.
6
468.
0
1,16
5.3
12
,818
.5
2011
80M
CM
9,
000.
0
0.0
1,
440.
0
315.
0
450.
0
1,12
0.5
12
,325
.5
2011
65M
CM
8,
520.
0
0.0
1,
363.
2
298.
2
426.
0
1,06
0.7
11
,668
.1
2011
55M
CM
8,
160.
0
0.0
1,
305.
6
285.
6
408.
0
1,01
5.9
11
,175
.1
2011
N
ote)
NR
B: N
atur
al R
etar
ding
Bas
in, R
B: R
etar
ding
Bas
in, C
I: C
hann
el Im
prov
emen
t So
urce
of i
tem
a, b
, c, d
and
e: J
ICA
SF R
epor
t, C
ost f
or C
I 3,1
00 m
3 /s is
est
imat
ed b
ased
on
cost
for C
I 2,9
00m
3 /s.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
73
Tabl
e 4.
41
Proj
ect C
ost a
fter
Con
vers
ion
(201
2 Pr
ice)
un
it: m
illio
n pe
so
Sect
ion
Con
tent
s D
irect
co
nstru
ctio
n co
st
Com
pens
atio
n co
st
Engi
neer
ing
serv
ice
cost
Ad
min
istra
tion
cost
Phys
ical
co
ntin
genc
y co
st
Pric
e co
ntin
genc
y co
st
Tota
l R
emar
ks
Pasi
g R
iver
1,
300m
3 /s
993.
0
0.0
15
8.9
34
.8
49.7
12
3.7
1,
360.
1
1,40
0m3 /s
1,
986.
0
0.0
31
7.8
69
.6
99.3
24
7.3
2,
720.
0
Pasi
g R
iver
Pha
se2
Phas
e2
3,03
3.2
10
.9
371.
2
107.
5
170.
8
369.
4
4,06
3.0
Lo
wer
Mar
ikin
a R
iver
Ph
ase3
2,
164.
4
7.7
26
4.9
76
.7
122.
0
263.
5
2,89
9.2
M
CG
S M
CG
S 3,
181.
8
3.2
43
7.2
10
8.7
18
1.2
39
1.2
4,
303.
3
Man
gaha
n Fl
oodw
ay
2,40
0m3 /s
3,
346.
3
91.6
53
5.4
12
0.3
16
7.3
42
6.1
4,
687.
0
2,60
0m3 /s
3,
625.
2
99.2
58
0.0
13
0.4
18
1.3
46
1.6
5,
077.
7
Upp
er M
arik
ina
Riv
er
Phas
e4
3,07
8.8
16
.2
423.
2
105.
3
175.
9
380.
0
4,17
9.4
3,10
0m3 /s
3,
291.
1
17.2
45
2.4
11
2.6
18
8.0
40
6.2
4,
467.
5
Upp
er U
pper
Mar
ikin
a R
iver
NR
B 0.
0
21,8
14.8
0.
0
763.
5
0.0
2,
257.
8
24,8
36.1
RB
20M
CM
2,
873.
0
2,00
0.0
45
9.7
17
2.6
14
3.6
57
0.7
6,
219.
6
RB
8MC
M
2,46
9.6
2,
000.
0
395.
1
158.
5
123.
5
520.
5
5,66
7.2
R
B 5M
CM
1,
543.
5
1,25
0.0
24
7.0
99
.1
77.2
32
5.3
3,
542.
1
CI 2
,900
m3 /s
1,
379.
9
32.4
22
0.8
49
.4
69.0
17
5.1
1,
926.
6
CI 3
,100
m3 /s
1,
475.
1
34.6
23
6.1
52
.8
73.8
18
7.3
2,
059.
7
Dam
90M
CM
9,
631.
4
0.0
1,
541.
0
337.
1
481.
6
1,19
9.1
13
,190
.2
80M
CM
9,
261.
0
0.0
1,
481.
8
324.
1
463.
1
1,15
3.0
12
,683
.0
65M
CM
8,
767.
1
0.0
1,
402.
7
306.
8
438.
4
1,09
1.5
12
,006
.5
55M
CM
8,
396.
6
0.0
1,
343.
5
293.
9
419.
8
1,04
5.4
11
,499
.2
N
ote)
NR
B: N
atur
al R
etar
ding
Bas
in, R
B: R
etar
ding
Bas
in, C
I: C
hann
el Im
prov
emen
t
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-74
(11) Project Cost of WB Proposal
The project cost of proposed measures by the WB (Alternative-02) is estimated adding engineering service cost, administration cost, physical contingency and Price contingency cost to the direct construction cost and compensation cost estimated by the WB Study. For comparison purpose, the cost for San Juan River improvement is excluded since it was not estimated in the JICA FS. On the other hand, the project costs for Phase II and Phase III project based on the JICA FS are added. The breakdown of project cost in 2011 price and 2012 price are shown in Table 4.43.
Table 4.42(1) Project Cost of WB Proposed Measures (2011 Price)
unit: million peso
Section Contents Direct
construction cost
Compensation cost
Engineering service cost
Administration cost
Physical contingency
cost
Price contingency
cost Total
Pasig River Dredging 4,825.0 - 772.0 168.9 241.3 600.7 6,607.9
Phase 2※ 2,948.2 10.6 360.8 104.5 166.0 359.0 3,949.1 Napindan Chanel Heightening of Parapet 98.0 - 15.7 3.4 4.9 12.2 134.2
Lower Marikina River
Dredging and Heightening 186.0 - 29.8 6.5 9.3 23.2 254.8
Phase 3※ 2,103.7 7.5 257.5 74.6 118.6 256.2 2,818.1
MCGS - - - - - - - -
Mangahan Floodway
Dredging 3,252.0 89.0 520.3 116.9 162.6 414.1 4,554.9
Upper Marikina River
Dyke and Excavation 5,601.0 4,309.0 896.2 346.9 280.1 1,143.3 12,576.5
Upper Upper Marikina River
Dyke and Excavation 1,341.0 31,521.0 214.6 1,150.2 67.1 3,429.4 37,723.3
Dam H=72m 8,626.0 - 1,380.2 301.9 431.3 1,073.9 11,813.3
Total 28,980.9 35,937.1 4,447.1 2,273.8 1,481.2 7,312.0 80,432.1 ※JICA FS Cost converted to 2011 Price
Table 4.43(2) Project Cost of WB Proposed Measures (2012 Price)
2012 価格
unit:million peso
Section Contents Direct
construction cost
Compensation cost
Engineering service
cost
Administration cost
Physical contingen
cy cost
Price contingen
cy cost Total
Pasig River Dredging 4,964.9 - 794.4 173.8 248.2 618.1 6,799.4
Phase 2※ 3,033.2 10.9 371.2 107.5 170.8 369.4 4,063.0
Napindan Chanel Heightening of Parapet 100.8 - 16.1 3.5 5.0 12.5 137.9
Lower Marikina River
Dredging and Heightening 191.4 - 30.6 6.7 9.6 23.8 262.1 Phase 3※ 2,164.4 7.7 264.9 76.7 122.0 263.5 2,899.2
MCGS - - - - - - - -
Mangahan Floodway
Dredging 3,346.3 91.6 535.4 120.3 167.3 426.1 4,687.0
Upper Marikina River
Dyke and Excavation 5,763.4 4,434.0 922.1 356.9 288.2 1,176.5 12,941.1
Upper Upper Marikina River
Dyke and Excavation 1,379.9 32,435.1 220.8 1,183.5 69.0 3,528.8 38,817.1
Dam H=72m 8,876.2 - 1,420.2 310.7 443.8 1,105.1 12,156.0
Total 29,820.5 36,979.3 4,575.7 2,339.6 1,523.9 7,523.8 82,762.8 Price in 2012, ※JICA FS
(12) Comparison of Project Costs Comparison of proposed project costs between the JICA Study and the WB Study is summarized in Table 4.44.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-75
Table 4.43 Comparison of Project Cost between JICA Study and WB Study
Section Contents JICA Study
A-2-1: CI + Dam
JICA Study B-3:
CI + Dam + RB WB Study
Pasig River Dredging 1,400m3/s 2,720.0 2,720.0 -
1,800m3/s - - 6,799.4
Pasig River Phase2 Phase2 4,063.0 4,063.0 4,063.0
Napindan Chanel Heightening of Parapet - - 137.9
Lower Marikina River Phase3 2,899.2 2,899.2 2,899.2
Dredging and Heightening - - 262.1
MCGS MCGS 4,303.3 4,303.3 -
Mangahan Floodway 2,400m3/s - 4,687.0 4,687.0
2,600m3/s 5,077.7 - -
Upper Marikina River
Phase4 - 4,179.4 -
3,100m3/s 対応 4,467.5 - -
Dyke and Excavation - - 12,941.1
Upper Upper Marikina River
NRB with Future Dyke Heightening (3,100m3/s in Channel) 24,801.5 -
NRB with Future RB Development (2,900m3/s in Channel + 20MCM in RB) - 22,803.7
RB 20MCM - 6,219.6 -
CI 2,900m3/s - 1,926.6 -
CI 3,100m3/s 2,059.7 - -
Dyke and Excavation - - 38,817.1
Dam
Dam 80MCM H=75m 12,683.0 - -
Dam 65MCM H=71m - 12,006.5 -
Dam H=72m - - 12,156.0
Total 63,074.9 65,808.3 82,762.8
4.5 Investigation of Appropriateness of Measures to Floods
The appropriateness of measures to floods is investigated by Economic Evaluation taking into consideration this project forms a part of the public investment in order to reduce floods damage in the Metro Manila.
4.5.1 Economic Cost The market prices of Pasig River Dredging, Pasig River Phase 2, Lower Marikina River, MCGS, Manggahan Floodway, Upper Marikina River, Dam are converted to the economic prices by multiplying the conversion factor shown below. Table 4.45 shows the economic cost for the Target Case. The economic cost descriptions for all cases are shown in Appendix.
The conversion factors of the past investigation (Preparatory Study for Pasig-Marikina River Channel Improvement Project (Phase III), hereinafter, referred to as “Preparatory Study”) are used in this study.
Table 4.44 Conversion Factors
Item Conversion Factors
1 Direct Construction Cost 0.79
2 Compensation 0.57
3 Engineering Service 1.19
4 Government Administration 0.97
5 Physical Contingency 0.93
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-76
Table 4.45 Economic Cost of the Target Case (million pesos)
Alternatives Direct
construction cost
Compensation cost
Engineering service cost
Administration cost
Physical contingency
cost Total
O 11,695.6 73.9 2,418.0 502.9 760.0 15,450.3
A 12,868.1 78.8 2,694.9 553.6 830.5 17,025.8
B 13,699.4 807.1 2,901.0 632.8 878.0 18,918.3
A-1 20,285.9 12,513.2 4,482.7 1,613.0 1,267.0 40,161.8
A-2-1 22,134.1 12,513.2 4,928.3 1,693.5 1,375.9 42,645.0
A-3 23,720.9 12,513.2 5,310.7 1,831.7 1,469.2 44,845.7
A-2-2 24,085.0 12,513.2 5,398.4 1,847.3 1,490.8 45,334.7
O-1 20,190.5 12,508.3 4,465.4 1,608.6 1,260.1 40,032.9
O-2 21,963.4 12,508.3 4,892.7 1,686.0 1,364.4 42,414.8
B-1 21,117.2 12,508.3 4,688.8 1,692.3 1,314.6 41,321.1
B-2―1 23,182.8 12,508.3 5,186.6 1,782.1 1,436.2 44,096.0
B-3 23,550.3 12,508.3 5,275.2 1,824.0 1,457.8 44,615.5
B-2-2 23,914.4 12,508.3 5,362.9 1,839.7 1,479.3 45,104.5
4.5.2 Economic Benefit The benefit in a Flood Prevention Project is the expected amounts of average annual damage reduction prevented by the project based on the difference of damage reduction amount between With Project Case and Without Project Case.
To put it concretely, details are given below.
(1) Arrangement of the assets in the probable flood area
(2) Calculation of the flood damage amounts by each occurrence probability through the flood simulation in Without Project Case
(3) Calculation of the expected amounts of average annual damage reduction based on the flood damage amounts both in With Project Case and Without Project Case
Table 4.47 shows the detail of Flood Damage.
Table 4.46 Detail of Flood Damage Division Detail
Direct Damage
Damage to Residential Buildings Damage to Household Effects Damage to Depreciable Assets of Business Establishments Damage to Inventories of Business Establishments Damage to Agricultural Crops Damage to Infrastructure
Indirect Damage
Loss of Interruption of Business Activities Emergency Cleaning Cost for Household Emergency Measure for Business Establishments
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-77
(1) Assets in the probable flood area
Table 4.47 Assets in the probable flood area Item Quantity Assets(Pesos)
Number of Residential Buildings 2,703,072 511,421,308,169
Residential Area (m2) 132,450,550 -
Number of Household 2,703,072 -
Number of a Household 11,623,212 -
Household Effects - 257,873,112,047
Number of Business Establishments (Manufacturing)
12,480 -
Depreciable Assets - 74,218,756,576
Stock Inventories - 62,659,009,122
Number of Business Establishments (Retailing)
311,581 -
Depreciable Assets - 90,371,391,749
Stock Inventories - 765,461,898,115
Cultivated Land Area (m2) 6,911,629 -
Crops - 27,646,515 Note; Each unit value is estimated below by multiplying CPI based on the past investigation (Detailed
Engineering Design of Pasig-Marikina River Channel Improvement Project, (hereinafter, referred to as ”Detailed Investigation”).
・Residential Building :189,200 Pesos/Building ・Household Effects:95,400 Pesos/Household ・Depreciable Assets of Business Establishments (Manufacturing):5,947,100 Pesos ・Stock Inventories of Business Establishments (Manufacturing):7,241,400 Pesos ・Depreciable Assets of Business Establishments (Retailing):201,100 Pesos ・Stock Inventories of Business Establishments (Retailing):2,456,700 Pesos ・Crops:40,000 Pesos/ha
(2) Flood Damage
1) Direct Damage
a) Damage to Residential Buildings The damage to residential buildings in the probable flood area is estimated as follows.
Damage to Residential Building = Assets Amount of Residential Buildings in a unit area x Damage Rate of Residential Buildings in inundation depth
Damage Rate of Residential Buildings in inundation depth is shown below.
Table 4.48 Damage Rate of Residential Buildings in inundation depth Inundation Depth Less than 0.5m 0.5 m~0.99 m 1.0 m~1.99 m 2.0 m~2.99 m 3.0 m and over
Damage Rate 0.092 0.119 0.266 0.580 0.834 Source: The Manual of Economical Investigation of Flood Disaster (the Ministry of Land, Infrastructure and
Transportation, Japan 2005 April)
b) Damage to Household Effects
The damage to household effects in the probable flood area is estimated as follows. Damage to Household Effects = Amounts of Household Effects in a unit area x Damage Rate of
Household Assets in inundation depth
Damage Rate of Household Effects in inundation depth is shown below.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-78
Table 4.49 Damage Rate of Household Assets in inundation depth Inundation Depth Less than 0.5m 0.5 m ~0.99 m 1.0 m ~1.99 m 2.0 m ~2.99 m 3.0 m and over
Damage Rate 0.145 0.326 0.508 0.928 0.991 Source: The Manual of Economical Investigation of Flood Disaster (the Ministry of Land, Infrastructure and
Transportation, Japan 2005 April) c) Damage to Business Establishments
The damage to business establishments in the probable flood area is estimated as follows. Damage to Depreciable Assets = Amounts of Depreciable Assets in a unit area x Damage Rate
of Depreciable Assets in inundation depth Damage to Stock Inventories = Amounts of Stock Inventories in a unit area x Damage Rate of
Stock Inventories in inundation depth
Damage Rate of Business Establishments in inundation depth is shown below.
Table 4.50 Damage Rate of Depreciable Assets and Stock Inventories in inundation depth Inundation Depth Less than 0.5 m 0.5 m~0.99 m 1.0 m~1.99 m 2.0 m~2.99 m 3.0 m and over
Damage Rate (Depreciable Assets)
0.232 0.453 0.789 0.966 0.995
Damage Rate (Stock Inventories)
0.128 0.267 0.586 0.897 0.982
Source: The Manual of Economical Investigation of Flood Disaster (the Ministry of Land, Infrastructure and Transportation, Japan 2005 April)
d) Damage to Agricultural Crops
The damage to agricultural crops is estimated as follows. Damage to Agricultural Crops = Amount of Agricultural Crops in a unit area x Damage Rate of
Agricultural Crops in inundation depth
Damage Rate of Agricultural Crops in inundation depth is shown below
Table 4.51 Damage Rate of Agricultural Crops in inundation depth Inundation Depth Less than 0.5 m 0.5 m~0.99 m 1.0 m~1.99 m 2.0 m~2.99 m 3.0 m and over
Damage Rate (7 days and over)
0.67 0.74 0.91 0.91 0.91
Source: The Manual of Economical Investigation of Flood Disaster (the Ministry of Land, Infrastructure and Transportation, Japan 2005 April), Average Value of Cultivated Field
e) Damage to Infrastructure
Damage to Infrastructure is 35% of Total Assets Amount in the same way as “Preparatory investigation”.
2) Indirect Damage Indirect Damage is 10% of Total Direct Damage in the same way as “Preparatory Investigation”. (3) Damage Amount
Table 4.53 shows the damage amount, 112,312 million Pesos for 30- probability year flow amount and 182,916 million Pesos for 100-probability year flow amount.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-79
Table 4.52 Damage Amount by Probability year ITEM
2-probability year 5-probability year 10-probability year 20-probability year 30-probability year 50-probability year 100-probability year
Number of Residential Buildings 2,231,905,354 6,553,171,480 8,701,915,032 10,718,881,437 12,338,687,289 15,008,257,030 19,793,054,564
Household Effects 2,231,905,354 6,553,171,480 8,701,915,032 10,718,881,437 12,338,687,289 15,008,257,030 19,793,054,564
Number of Business
Establishments (Manufacturing)
Depreciable Assets 836,532,676 2,573,997,642 3,371,030,413 4,063,096,629 4,619,283,775 5,690,163,598 7,578,291,351
Stock Inventories 1,018,591,871 3,134,190,871 4,104,686,256 4,947,370,639 5,624,603,845 6,928,545,119 9,227,596,473
Number of Business
Establishments (Retailing)
Depreciable Assets 557,744,554 1,716,171,057 2,247,579,691 2,709,003,583 3,079,832,315 3,507,274,298 5,052,702,482
Stock Inventories 6,813,580,532 20,965,278,148 27,457,130,920 33,094,028,355 37,624,187,210 46,346,531,390 61,725,381,341
Crops 2,008,619 3,832,554 4,709,093 5,181,819 5,397,013 5,570,595 5,810,989
Sub Total 13,692,268,958 41,499,813,231 54,588,966,438 66,256,443,899 75,630,678,734 92,494,599,059 123,175,891,764
Infrastructure 4,792,294,135 14,524,934,631 19,106,138,253 23,189,755,365 26,470,737,557 32,373,109,671 43,111,562,117
Indirect Damage 1,848,456,309 5,602,474,786 7,369,510,469 8,944,619,926 10,210,141,629 12,486,770,873 16,628,745,388
Total 20,333,019,403 61,627,222,649 81,064,615,160 98,390,819,190 112,311,557,920 137,354,479,602 182,916,199,270
Damage Amount (Pesos)
(4) (4) Expected Amount of Average Annual Damage Reduction Consequently the expected amount of average annual damage reduction can be estimated about 25,671 thousand Pesos for 30-probability year flow amount and 28,937 thousand Pesos for 100-probability year flow amount as shown below, which is calculated by multiplying the amount of average annual damage corresponding to probable flood with occurrence probability and by accumulating the annual damage of each probable flood.
Table 4.53 Expected Amount of Average Annual Damage Reduction (30-probability year flow amount) 1,000 Pesos
①
Without Project
②
With Project
③
Damage
Reduction (①
-②)
12,294,036
19,428,628
23,915,014
25,670,867
0.100
0.050
0.017
98,390,819
112,311,558
Sectional
probability
12,294,036
7,134,592
4,486,386
1,755,853
98,390,819
112,311,558
40,980,121
71,345,919
89,727,717
0.3000
0
0
0
0 105,351,189
20,333,019
61,627,223
81,064,615
20,333,019
61,627,223
81,064,615
2,860
3,030
1/2
1/5
1/10
1/20
1/30
Size of Flow
(m3/s)
Average Annual
Exceedance
Probability
1,620
2,290
2,670
Damage Amount
Sectional
Average
Damage
Amount of
Average
Annual Damage
Expected
Amount of
Average Annual
Damage
Reduction
Table 4.54 Expected Amount of Average Annual Damage Reduction (100-probability year flow amount) 1000 Pesos
①
Without Project
②
With Project
③
Damage
Reduction (①
-②)
12,294,036
19,428,628
23,915,014
25,670,867
27,335,307
28,936,661
12,294,036
7,134,592
4,486,386
1,755,853
1,664,440
1,601,353
124,833,019
160,135,339
0.300
0.100
0.050
0.017
0.013
0.010
40,980,121
71,345,919
89,727,717
105,351,189
0
20,333,019
61,627,223
81,064,615
98,390,819
112,311,558
137,354,480
182,916,199
0
0
0
0
0
0
20,333,019
61,627,223
81,064,615
98,390,819
112,311,558
137,354,480
182,916,199
1/2
1/5
1/10
1/20
1/30
1/50
1/100
Expected
Amount of
Average AnnualDamage
Reduction
Size of Flow
(m3/s)
Average Annual
ExceedanceProbability
Damage Amount
Sectional
AverageDamage
Sectional
probability
Amount of
AverageAnnual Damage
The map of areas likely to be inundated by probability year are shown in Figures below.
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-80
Figure 4.63 Map of areas likely to be inundated by probability year(1/2、1/5)
Figure 4.64 Map of areas likely to be inundated by probability year(1/10、1/20)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-81
Figure 4.65 Map of areas likely to be inundated by probability year(1/30、1/50)
Figure 4.66 Map of areas likely to be inundated by probability year(1/100)
The Republic of the Philippines Data Collection Survey on Flood Management in Metro Manila
Final Report 4-82
4.5.3 Economic Evaluation
The economic evaluation for 13 cases (3-case under 30-year return period and 10-case of 100-year return period) shown in Table 4.56 is carried out by utilizing both the abovementioned economic cost and benefit. 13 cases are confirmed to be expected on a economic benefits as a result of high cost-effectiveness as organized into the Table4.57. Economic Internal Rate of Return (EIRR)
Although there is a discrepancy between cases that 3-case under 30-year return period shows over 25% of EIRR and 10-case of 100-year return period shows 17% of EIRR range, all cases have a high cost-effectiveness because of the value far above 15% of EIRR.
Net Present Value (NPV) All cases have a high cost effect judging from that the benefit exceeds the economic cost greatly, yet there is a discrepancy between 3-case under 30-year return period with over 40,000 Million Pesos of NPV and 10-case of 100-year return period with the range between 8,000 Million Pesos and 11,000 Million Pesos of NPV in a manner similar to EIRR.
Benefit Cost Ratio (B/C Ratio) A similar relation holds for B/C Ratio. Although there is a discrepancy 3-case under 30-year return period showing over 3 of the B/C Ratio and 10-case of 100-year return period showing the B/C Ration raging between 1.3 and 1.5, all cases have a high cost-effectiveness because of the value far above 1 of B/C Ratio.
The case showing highest value for EIRR and B/C among 13 cases is the case ① (Phase IV Component Buildup Plan). As concerns NPV, the case ② (Alternative Plan A)) comes first. From this, meanwhile 3-case under 30-year return period indicates high evaluation, there is no big difference between 10-case of 100-year return period. The cash flows for all cases are shown in Appendix.
Table 4.55 Investigation Cases
Return Period Case Alternative
Economic Internal Rate of Return (EIRR)
Net Present Value (NPV)
Benefit Cost Ratio (B/C Ratio)
1/30 ① Alternative Plan O* 63.50% 91,769 Million Pesos 8.1 ② Alternative Plan A 62.60% 98,136 Million Pesos 7.9 ③ Alternative Plan B 28.00% 40,868 Million Pesos 3.7
1/100 ④ Alternative Plan (A-1) 17.60% 10,973 Million Pesos 1.4 ⑤ Alternative Plan (A-2-1) 17.30% 9,854 Million Pesos 1.4 ⑥ Alternative Plan (A-3) 17.00% 8,689 Million Pesos 1.3 ⑦ Alternative Plan (A-2-2) 17.00% 8,542 Million Pesos 1.3 ⑧ Alternative Plan (O-1) 17.70% 11,259 Million Pesos 1.5 ⑨ Alternative Plan (O-2) 17.40% 10,189 Million Pesos 1.4 ⑩ Alternative Plan (B-1) 17.50% 10,591 Million Pesos 1.4 ⑪ Alternative Plan (B-2-1) 17.20% 9,369 Million Pesos 1.4 ⑫ Alternative Plan (B-3) 17.10% 9,024 Million Pesos 1.3 ⑬ Alternative Plan (B-2-2) 17.10% 8,877 Million Pesos 1.3
* : Design Flood Discharge of 2,900m3/s is reevaluated as 1/20 years flood as previously mentioned.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
83
4.6
Com
pari
son
of S
tudy
Con
tent
s and
Res
ults
with
Pre
viou
s Stu
dies
Th
e co
nten
ts a
nd re
sults
are
com
pare
d w
ith th
e pr
evio
us st
udie
s as s
umm
ariz
ed in
Tab
le 4
.60.
Tabl
e 4.
60
Com
pari
son
of J
ICA
Prep
arat
ory
Stud
y, W
B S
tudy
and
Dat
a C
olle
ctio
n Su
rvey
(Thi
s Stu
dy)
Item
JIC
A Pr
epar
atory
Stu
dy
WB
Stud
y D
ata C
olle
ction
Sur
vey
(TH
IS S
TUD
Y)
Des
ign
Hye
togr
aph
Obj
ectiv
e Im
porta
nt it
em fo
r esti
mat
ion
of p
eak
disc
harg
e and
scale
of s
tora
ge fa
cility
(cap
acity
)
App
lied
Hye
togr
aph
Mid
dle-
peak
Fict
iona
l Hye
togr
aph
Hye
togr
aph
base
d on
pro
babl
e ra
infa
ll in
tensit
ies b
y ra
infa
ll du
ratio
ns o
f Por
t Are
a
Type
1: T
ypho
on O
ndoy
Typ
e O
bser
ved
Hye
togr
aph
Type
2: M
iddl
e-pe
ak F
ictio
nal H
yeto
grap
h H
yeto
grap
h ba
sed
on p
roba
ble
rain
fall
inten
sitie
s by
ra
infa
ll du
ratio
ns o
f Por
t Are
a
Obs
erve
d 7
Hye
togr
aphs
+
Mid
dle-
peak
Fi
ction
al
Hye
togr
aph
Evalu
ation
JIC
A Pr
epar
atory
Stu
dy ap
plied
sam
e meth
od as
JICA
Mas
ter P
lan in
1990
. WB
Stud
y an
alyze
d Ty
phoo
n O
ndoy
Typ
e and
Mid
dle-
peak
Fict
iona
l Typ
e and
appl
ied T
ypho
on O
ndoy
Ty
pe.
It
is ne
cess
ary
to an
alyze
var
ious
hye
togr
aphs
sinc
e it i
s unc
ertai
n th
at w
hich
hye
togr
aph
with
enlar
gem
ent t
o pr
obab
le ra
infa
ll ca
uses
the l
arge
st pe
ak d
ischa
rge.
In th
is St
udy,
anot
her 6
hye
togr
aphs
bes
ide
Typh
oon
Ond
oy T
ype
and
Mid
dle-
peak
Fict
iona
l Typ
e is
anal
yzed
and
con
clude
d th
at pe
ak d
ischa
rge
and
nece
ssar
y ca
pacit
y of
stor
age
facil
ity b
ecom
es m
axim
um w
hen
Typh
oon
Ono
dy T
ype i
s app
lied.
Estim
ation
of
Basin
Ave
rage
Ra
infa
ll
Obj
ectiv
e Im
porta
nt It
em to
estim
ate p
roba
ble r
ainfa
ll, p
eak
disc
harg
e and
scale
of s
tora
ge fa
cility
(cap
acity
) con
sequ
ently
Estim
ation
M
ethod
of
Ba
sin
Aver
age
Rain
fall
Rain
fall
at Po
rt A
rea x
Rain
fall A
djus
tmen
t Coe
fficie
nt
Esti
mate
d as
uni
form
rain
fall
in w
hole
area
Ty
pe 1
: Typ
hoon
Ond
oy T
ype
Thi
esse
n M
ethod
and A
djus
tmen
t by
IDW
Meth
od
Esti
mate
d ea
ch 3
4 Th
iesse
n Po
lygo
n Ty
pe 2
: Mid
dle-
peak
Fict
iona
l Hye
togr
aph
IDW
Meth
od
Esti
mate
d fo
r 3 S
ub-b
asin
s
Adj
usted
by
Thies
sen
Meth
od a
nd I
DW
Meth
od b
ased
on
obse
rved
rain
fall
Evalu
ation
JIC
A Pr
epar
atory
Stu
dy ap
plied
sam
e meth
od as
JICA
Mas
ter P
lan in
1990
. 199
0 M
aster
Plan
did
not
cons
ider
spati
al va
riatio
n du
e to
lack
of d
ata. I
n W
B St
udy,
meth
ods t
o an
alyze
sp
atial
and
time v
ariat
ion
wer
e app
lied
base
d on
rece
nt d
ata.
Sp
atial
varia
tion
shall
be
cons
ider
ed to
esti
mat
e ba
sin a
vera
ge ra
infa
ll ac
cura
tely.
Thus
, in
this
Stud
y, m
ethod
s to
anal
yze
spati
al an
d tim
e va
riatio
n ar
e ap
plied
bas
ed o
n da
ta af
ter
1994
.
Des
ign
Rain
fall
Dur
ation
O
bjec
tive
Item
whi
ch af
fect
peak
disc
harg
e and
scale
of s
tora
ge fa
cility
(cap
acity
), de
pend
ing
on b
asin
char
acte
ristic
s suc
h as
bas
in ar
ea, s
lope
, lan
duse
and
so o
n.
A
pplie
d D
esig
n Ra
infa
ll D
urati
on
2 da
ys r
ainfa
ll is
appl
ied t
o co
ver
obse
rved
rain
fall
dura
tion
of p
ast f
lood
s.
2 da
ys r
ainfa
ll is
appl
ied t
o co
ver
obse
rved
rain
fall
dura
tion
of p
ast f
lood
s.
Rel
atio
n be
twee
n ra
infa
ll an
d w
ater
lev
el i
s an
alyz
ed.
Due
to it
s hig
h co
rrel
atio
n, 1
day
rain
fall
is a
pplie
d.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
84
Item
JIC
A Pr
epar
atory
Stu
dy
WB
Stud
y D
ata C
olle
ction
Sur
vey
(TH
IS S
TUD
Y)
Evalu
ation
Bo
th JI
CA S
tudy
and
WB
Stud
y ap
plied
2 d
ays r
ainfa
ll to
cove
r the
obs
erve
d ra
infa
ll du
ratio
ns. H
owev
er, p
recip
itatio
n un
til fl
ood
conc
entra
tion
time i
s the
mos
t im
porta
nt in
runo
ff an
alysis
. Th
us, c
orre
latio
ns o
f 1 d
ay ra
infa
ll an
d 2
days
rain
fall
with
wat
er le
vel a
re ex
amin
ed an
d it
is fo
und
that
corre
latio
n of
1 d
ay ra
infa
ll is
muc
h hi
gher
than
2 d
ays r
ainfa
ll. S
ince
it d
oes
not e
ffect
to ru
noff
analy
sis th
at 1
day
rain
fall
does
not
cove
r obs
erve
d ra
infa
ll, it
is ap
prop
riate
to ap
ply
1 da
y ra
infa
ll.
Ba
sin A
vera
ge
Prob
able
Rain
fall
Obj
ectiv
e Im
porta
nt to
estim
ate r
unof
f disc
harg
e for
each
pro
babl
e yea
r.
App
lied
Basin
Av
erag
e Pr
obab
le Ra
infa
ll
Who
le Ba
sin (2
day
s)
・30
yea
rs
392.
3mm
・
100
year
s
445
.8m
m
Type
1: T
ypho
on O
ndoy
Typ
e O
bser
ved
2 da
ys ra
infa
ll x
Enlar
gem
ent R
atio
Esti
mate
d ea
ch 3
4 Th
iesse
n Po
lygo
n 3
Sub
-bas
in A
vera
ge R
ainfa
ll (T
rial b
y WB
Stud
y)
Ret
urn
Perio
dSB
-01
SB-0
2SB
-31
3036
836
939
010
043
944
446
8
Prob
able
2 d
ays
Rai
nfal
l
Ty
pe 2
: Mid
dle-
peak
Fict
iona
l Hye
togr
aph
Esti
mate
d fo
r 3 S
ub-b
asin
s R
etur
nPe
riod
SB-0
1SB
-02
SB-3
130
368
366
382
100
438
441
458
Prob
able
2 d
ays
Rai
nfal
l
Who
le B
asin
(1 d
ay)
・30
yea
rs
232.
4mm
・
100
year
s
285
.5m
m
Evalu
ation
2
days
bas
in av
erag
e pro
babl
e rain
fall
was
estim
ated
bot
h by
JICA
and
WB
Stud
ies. I
n th
is St
udy,
1 da
y ba
sin p
roba
ble r
ainfa
ll is
estim
ated
.
In th
is St
udy,
typh
oon
type
rain
fall
and
mon
soon
type
rain
fall
are
anal
yzed
sep
arate
ly, b
ecau
se th
ese
typh
oon
and
mon
soon
are
diff
eren
t phe
nom
ena
and
it is
unce
rtain
whi
ch
phen
omen
a ca
uses
larg
er fl
oods
. As a
resu
lt of
ana
lysis
, typ
hoon
type
rain
fall
caus
es la
rger
pro
babl
e ra
infa
ll. It
is sa
id th
at ac
cura
cy o
f pro
babl
e an
alysis
is im
prov
ed b
y an
alyzi
ng
rain
fall
with
caus
es.
Floo
d D
ischa
rge
at St
.Nin
o
Obj
ectiv
e D
ischa
rge a
t Sto
.Nin
o is
impo
rtant
to ca
libra
te m
odel
cons
tants
whi
ch is
the k
ey o
f acc
urac
y of
runo
ff m
odel.
Si
nce i
t is d
ifficu
lt of
cont
inuo
us o
bser
vatio
n of
disc
harg
e dire
ctory
, H-Q
equa
tion
to co
nver
t fro
m w
ater l
evel
to d
ischa
rge i
s app
lied.
A
pplie
d Es
timati
on
of F
lood
D
ischa
rge
Ann
ual
high
est
wat
er l
evel
in 1
958-
77,
1986
, an
d 19
94-2
009
wer
e con
verte
d to
disc
harg
e.
H-Q
Equ
ation
:
・Q
= 3
2.03
×( H
-10.
80)2
H
< 1
7.0
・Q
= 1
7.49
× (H
-8.6
1)2
H >
17.
0 H
-Q e
quati
on w
as m
ade
base
d on
obs
erve
d di
scha
rge
and
wat
er le
vel d
ata in
195
8-77
and
1986
. M
ax. d
ischa
rge o
f Typ
hoon
Ond
oy (2
009)
・
3,21
1m3 /se
c
Ann
ual
high
est
wate
r le
vel
in
1958
-77,
19
86,
and
1994
-200
9 w
ere c
onve
rted
to d
ischa
rge.
H-Q
Equ
ation
:
・Q
= 3
1.44
×( H
-10.
96)2
H
> 1
3.0
H
-Q e
quati
on w
as m
ade b
ased
on
obse
rved
disc
harg
e an
d w
ater
lev
el da
ta in
195
8-77
and
198
6, a
nd e
stim
ated
di
scha
rge
by u
nifo
rm f
low
and
obs
erve
d w
ater
lev
el in
19
94-2
009.
M
ax. d
ischa
rge o
f Typ
hoon
Ond
oy (2
009)
・
3,95
0m3 /se
c
Ann
ual h
ighe
st w
ater l
evel
in 1
958-
77, 1
986,
and
1994
-200
9 w
ere c
onve
rted
to d
ischa
rge.
H-Q
Equ
ation
: ・
Q =
32.
03 ×
( H-1
0.80
)2
H <
14.
0 ・
Q =
25.
65 ×
(H-1
0.46
)2
H >
14.
0 H
-Q e
quati
on w
as m
ade
base
d on
obs
erve
d di
scha
rge
and
wat
er l
evel
data
in
1958
-77
and
1986
, an
d es
timat
ed
disc
harg
e by
non
-uni
form
flow
and
obs
erve
d w
ater
leve
l in
1994
-200
9.
Max
. disc
harg
e of T
ypho
on O
ndoy
(200
9)
・3,
480m
3 /sec
Evalu
ation
H
-Q eq
uatio
n by
JICA
Stu
dy w
as b
ased
on
obse
rved
data
, how
ever
, obs
erve
d da
ta du
ring
flood
was
spar
se an
d ac
cura
cy in
hig
h w
ater
leve
l is u
ncer
tain.
H
-Q eq
uatio
n by
WB
Stud
y w
as b
ased
on
obse
rved
and
estim
ated
data
, how
ever
, acc
urac
y of
esti
mat
ed d
ischa
rge i
s low
sinc
e ene
rgy
grad
ient a
nd ro
ughn
ess c
oeffi
cient
appl
ied fo
r
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
85
Item
JIC
A Pr
epar
atory
Stu
dy
WB
Stud
y D
ata C
olle
ction
Sur
vey
(TH
IS S
TUD
Y)
estim
ation
is n
ot p
rope
r.
In th
is St
udy,
non-
unifo
rm fl
ow ca
lcul
ation
is ap
plied
to es
timate
H-Q
equa
tion
in h
igh
wate
r lev
el so
that
accu
racy
in h
igh
wate
r lev
el is
impr
oved
. A
pply
ing
the H
-Q eq
uatio
n es
timat
ed in
this
Stud
y, pe
ak d
ischa
rge a
t Sto
.Nin
o of
Ond
oy T
ypho
on is
estim
ated
as 3
,500
m3/
s. Si
nce a
ccur
acy
of H
-Q eq
uatio
n is
impr
oved
, acc
urac
y of
estim
ated
disc
harg
e is a
lso im
prov
ed.
Runo
ff A
naly
sis
Obj
ectiv
e It
is th
e ana
lysis
to co
nver
t rain
fall
to d
ischa
rge,
and
accu
racy
of a
naly
sis ef
fect
peak
disc
harg
e and
scal
e of s
tora
ge fa
cility
. Ru
noff
Ana
lysis
M
ethod
Rain
fall-
Runo
ff M
odel
Stor
age F
uncti
on M
ethod
: Mou
ntain
ous A
rea
Q
uasil
inier
Sto
rage
Typ
e: U
rban
ized A
rea
Calib
ratio
n an
d Ve
rifica
tion
of M
odel
Para
met
ers
2
flood
s in
2004
was
repr
oduc
ed.
M
odel
para
met
ers
wer
e ca
libra
ted t
o co
nfor
m
calcu
lated
hyd
rogr
aph
to o
bser
ved
disc
harg
e.
Pa
ram
eter
s fo
r St
orag
e Fu
nctio
n M
ethod
(de
lay
facto
rs)
wer
e de
term
ined
ba
sed
on
prev
ious
m
odel.
Inte
grate
d A
naly
sis M
odel
of B
asin
, Ri
ver
and
Floo
d Pl
ains
Ba
sin:
Rain
fall-
Runo
ff M
odel
(S
CS
Uni
t H
ydro
grap
h M
ethod
)
Rive
r: O
ne-d
imen
siona
l Uns
teady
Flo
w M
odel
Fl
ood
Plain
: Tw
o-di
men
siona
l Uns
tead
y Fl
ow M
odel
Calib
ratio
n an
d Ve
rifica
tion
of M
odel
Para
met
ers
Fl
ood
by O
ndoy
Typ
hoon
was
repr
oduc
ed.
M
odel
para
met
ers
wer
e ca
libra
ted
to
conf
orm
ca
lculat
ed h
ydro
grap
h to
obs
erve
d pe
ak d
ischa
rge
and
wat
er le
vel.
Mod
el w
as v
erifi
ed b
y re
prod
ucin
g 20
04 fl
ood
and
1998
floo
d.
Inte
grate
d A
naly
sis m
odel
of b
asin
, riv
er c
ourse
and
flo
od
plain
.
Basin
: Rain
fall-
Runo
ff M
odel
(WEB
-DH
M M
odel)
Rive
r Co
urse
: O
ne-d
imen
siona
l N
on-u
nifo
rm
Flow
M
odel
Fl
ood
Plain
: Tw
o-di
men
siona
l Uns
tead
y Fl
ow A
naly
sis
Mod
el
Ca
libra
tion
and
Verif
icatio
n of
Mod
el Pa
ram
eter
s
Floo
d by
Ond
oy T
ypho
on w
as re
prod
uced
.
Mod
el pa
ram
eter
s w
ere
calib
rated
to
co
nfor
m
calcu
lated
hyd
rogr
aph
to o
bser
ved
hydr
ogra
ph a
s w
ell
as p
eak
disc
harg
e and
wat
er le
vel.
Mod
el w
as v
erifi
ed b
y re
prod
ucin
g 20
04 f
lood
and
20
12 fl
ood.
Evalu
ation
JIC
A St
udy
appl
ied lu
mpe
d sy
stem
mod
el so
that
spati
al va
riatio
n of
rain
fall
coul
d no
t rep
rodu
ced
well
.
WB
Stud
y als
o ap
plied
lum
ped
syste
m m
odel.
To
repr
oduc
e spa
tial v
ariat
ion,
rive
r bas
in w
as se
gmen
talize
d in
to sm
all s
ub-b
asin
s, ho
wev
er, i
t cou
ld n
ot re
prod
uce w
ell.
Th
is St
udy
appl
ies d
istrib
uted
syste
m m
odel
whi
ch c
an re
prod
uce
spati
al va
riatio
n of
rain
fall.
Thi
s mod
el ca
n als
o an
alyz
e lo
ng te
rm ru
noff
so th
at it
can
repr
oduc
e so
il an
d riv
er
cour
se co
nditi
ons b
efor
e flo
od.
In W
B St
udy,
peak
disc
harg
e an
d w
ater l
evel
wer
e co
nfor
med
in th
e ca
libra
tion
of m
odel.
On
the
othe
r han
d, c
alibr
ation
of m
odel
in th
is St
udy
is co
nduc
ted to
con
form
calc
ulate
d hy
drog
raph
to o
bser
ved
hydr
ogra
ph as
well
as p
eak
disc
harg
e and
wate
r lev
el.
Cons
ider
ing
mod
el ch
arac
terist
ics an
d ca
libra
tion
meth
od, f
lood
analy
sis m
odel
in th
is St
udy
is ap
prop
riate
com
parin
g pr
evio
us st
udies
.
Wate
r Lev
el in
La
guna
Lak
e O
bjec
tive
Wate
r lev
el in
Lag
una L
ake e
ffect
disc
harg
e of M
angg
ahan
Flo
odw
ay an
d w
ater l
evel
of M
arik
ina R
iver
ups
tream
of M
angg
ahan
Flo
odw
ay.
A
pplie
d W
ater
Leve
l in
La
guna
La
ke
Aver
age W
ater L
evel
durin
g Fl
ood:
12.
2m
Obs
erve
d W
ater
Lev
el du
ring
Ond
oy T
ypho
on:
12.7
8-13
.85m
Past
Hig
hest
Wate
r Lev
el af
ter M
angg
ahan
Flo
odw
ay
Cons
tructe
d: 1
3.90
m
Evalu
ation
JIC
A St
udy
appl
ied av
erag
e wat
er le
vel d
urin
g flo
od w
hich
is le
ss th
an o
bser
ved
wat
er le
vel d
urin
g O
ndoy
Typ
hoon
.
WB
Stud
y ap
plied
obs
erve
d w
ater l
evel
durin
g Ty
phoo
n O
ndoy
, how
ever
, wat
er le
vel i
n La
guna
Lak
e at
the
mom
ent o
f pea
k w
ater
leve
l of M
arik
ina
Rive
r is l
ess t
han
peak
wat
er
level.
In
this
Stud
y, pa
st m
axim
um w
ater
leve
l is a
pplie
d sin
ce th
ere
is a
case
that
peak
wate
r lev
el in
Lag
una
Lake
occ
ur p
rior t
o pe
ak w
ater
leve
l in
the
river
, and
wate
r lev
el in
Lag
una
Lake
doe
s not
dec
line i
n sh
ort t
ime o
nce r
ise.
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
86
Item
JIC
A Pr
epar
atory
Stu
dy
WB
Stud
y D
ata C
olle
ction
Sur
vey
(TH
IS S
TUD
Y)
Wate
r lev
el in
Lag
una
Lake
effe
ct di
scha
rge
of M
angg
ahan
Flo
odw
ay a
nd it
is n
eces
sary
that
plan
ned
dive
rsion
disc
harg
e is
main
tain
ed a
fter p
eak
wat
er le
vel i
n La
guna
Lak
e. D
iver
sion
volu
me
to M
angg
ahan
Flo
odw
ay is
qui
te im
porta
nt to
floo
d co
ntro
l plan
of P
asig
-Mar
ikin
a Riv
er. C
onsid
erin
g sa
fety
of f
lood
con
trol p
lan, t
he a
pplie
d w
ater
leve
l in
this
Stud
y is
appr
opria
te.
In
unda
tion
Ana
lysis
O
bjec
tive
It is
impo
rtant
for e
valu
ation
of p
lanne
d flo
od co
ntro
l fac
ilitie
s.
App
lied
Inun
datio
n A
naly
sis
Inun
datio
n Ana
lysis
Mod
el
Ri
ver:
One
-dim
ensio
nal U
nstea
dy F
low
Mod
el
Floo
d Pl
ain:
Two-
dim
ensio
nal
Uns
tead
y Fl
ow
Mod
el
Fl
ood
by T
ypho
on O
ndoy
was
repr
oduc
ed.
Si
mul
ation
res
ults
wer
e w
ell c
onfo
rmed
with
in
tervi
ew su
rvey
resu
lts.
Inte
grate
d A
naly
sis M
odel
of B
asin
, Ri
ver
and
Floo
d Pl
ains
Fl
ood
by T
ypho
on O
ndoy
was
repr
oduc
ed.
Si
mul
ation
re
sults
w
ere
wel
l co
nfor
med
w
ith
inun
datio
n m
ap b
ased
on
flood
dam
age s
urve
y.
Inte
grate
d A
naly
sis m
odel
of b
asin
, riv
er c
ourse
and
flo
od
plain
.
Floo
d by
Typ
hoon
Ond
oy w
as re
prod
uced
.
Sim
ulati
on re
sults
wer
e well
conf
orm
ed w
ith in
unda
tion
map
bas
ed o
n flo
od d
amag
e sur
vey.
Evalu
ation
N
ot so
muc
h di
ffere
nce a
mon
g th
e stu
dies
.
Basic
Des
ign
Disc
harg
e W
ithou
t In
unda
tion
Pr
obab
le D
ischa
rge a
t Sto
.Nin
o ・
30 y
ears
2,
740
m3 /se
c ・
100
year
s
3,
210
m3 /se
c
(Not
anal
yzed
) Pr
obab
le D
ischa
rge a
t Sto
.Nin
o ・
30 y
ears
3,
990
m3 /se
c ・
100
year
s
4,
980
m3 /se
c
With
In
unda
tion
(Not
anal
yzed
) Pr
obab
le D
ischa
rge a
t Sto
.Nin
o ・
30 y
ears
3,
600
m3 /se
c ・
100
year
s
4,
100
m3 /se
c La
rge
scale
inun
datio
n at
left
side
betw
een
conf
luen
ce o
f N
angk
a Riv
er an
d Ro
sario
Weir
by
dyke
bre
ak
・30
yea
rs
3,03
0 m
3 /sec
・10
0 ye
ars
3,58
0 m
3 /sec
Floo
d D
ischa
rge
Allo
catio
nDes
ign
30 y
ears
Pr
evio
us d
ischa
rge a
lloca
tion
is ap
plied
.
Coun
term
easu
res a
gain
st 30
yea
r pro
babl
e flo
od:
・Ri
ver I
mpr
ovem
ent
・M
CGS
(Not
impl
emen
ted in
Pha
se II
I) 30
yea
rs pr
obab
le di
scha
rge (
with
MCG
S)
Secti
on
Q(m
3/s)
Waw
a 1,
590
(Non
e)
The f
ollo
win
g co
unter
mea
sure
are r
ecom
men
ded.
Co
unter
mea
sure
s aga
inst
30 y
ear p
roba
ble f
lood
: A
ltern
ative
-A;
・Ri
ver I
mpr
ovem
ent
・M
CGS
・Im
prov
emen
t of
Man
ggah
an F
lood
way
A
ltern
ative
-B;
・Ri
ver I
mpr
ovem
ent
・M
CGS
・Co
nstru
ction
of R
etard
ing
Basin
30
yea
rs pr
obab
le di
scha
rge (
with
MCG
S)
uni
t: Q
(m3 /s)
Secti
on
Alt-
A
Alt-
B W
awa
2,72
0 2,
720
The
Rep
ublic
of
the
Phili
ppin
es
Dat
a C
olle
ctio
n Su
rvey
on
Floo
d M
anag
emen
t in
Met
ro M
anila
Fina
l R
epor
t 4-
87
Item
JIC
A Pr
epar
atory
Stu
dy
WB
Stud
y D
ata C
olle
ction
Sur
vey
(TH
IS S
TUD
Y)
Rodo
riges
Brid
ge
2,11
0 Be
fore
Nan
gka R
iver
2,
420
St. N
ino
2,90
0 M
anga
han
Floo
dway
2,
400
Low
er M
arik
ina R
iver
50
0 N
apin
dan
Chan
nel
0 Pa
sig R
iver
60
5 Sa
nJua
n Ri
ver
700
Pasig
Riv
er –
Man
ila B
ay
1,20
0
Mon
talba
n Br
idge
3,
560
3,56
0 (R
etard
ing
Basin
)
St
. Nin
o 3,
100
2,90
0 M
anga
han
Floo
dway
2,
600
2,40
0 Lo
wer
Mar
ikin
a Riv
er
500
500
Nap
inda
n Ch
anne
l 0
0 Pa
sig R
iver
60
0 60
0 Sa
nJua
n Ri
ver
700
700
Pasig
Riv
er –
Man
ila B
ay
1,30
0 1,
300
100
year
s (N
one)
Alte
rnati
ve
2 in
cludi
ng
the
follo
win
g m
easu
res
is re
com
men
ded.
Co
unter
mea
sure
s aga
inst
100
year
pro
babl
e flo
od:
・Ri
ver I
mpr
ovem
ent
・M
arik
ina D
am
・Re
tardi
ng B
asin
・
Non
-stru
ctura
l Mea
sure
s 10
0 ye
ars p
roba
ble d
ischa
rge (
with
out M
CGS)
Se
ction
Q
(m3/
s) W
awa
3,60
0 M
arik
ina D
am
900
Mon
talba
n Br
idge
2,
400
(Reta
rdin
g Ba
sin)
St
. Nin
o 2,
900
Man
gaha
n Fl
oodw
ay
2,00
0 Lo
wer
Mar
ikin
a Riv
er
1,00
0 N
apin
dan
Chan
nel
600
Pasig
Riv
er
850
SanJ
uan
Rive
r 1,
000
Pasig
Riv
er –
Man
ila B
ay
1,80
0
Alte
rnati
ve A
-2-1
and
B-3
are s
how
n in
belo
w.
Coun
term
easu
res a
gain
st 10
0 ye
ar p
roba
ble f
lood
: A
lerna
tive-
A-2
-1;
・Ri
ver I
mpr
ovem
ent
・M
CGS
・Im
prov
emen
t of
Man
ggah
an F
lood
way
・
Mar
ikin
a Dam
A
lerna
tive-
B-3;
・
Rive
r Im
prov
emen
t ・
MCG
S ・
Mar
ikin
a Dam
・
Retar
ding
Bas
in
100
year
s pro
babl
e disc
harg
e (w
ith M
CGS)
u
nit:(
m3 /s)
Secti
on
A-2
-1
B-3
Waw
a 3,
230
3,23
0 M
arik
ina D
am
1.26
0 1.
260
Mon
talba
n Br
idge
2,
140
2,50
0 (R
etard
ing
Basin
)
St
. Nin
o 3,
100
2,90
0 M
anga
han
Floo
dway
2,
400
2,40
0 Lo
wer
Mar
ikin
a Riv
er
500
500
Nap
inda
n Ch
anne
l 0
0 Pa
sig R
iver
60
0 60
0 Sa
nJua
n Ri
ver
780
780
Pasig
Riv
er –
Man
ila B
ay
1,40
0 1,
400