Technical Report
November 2005
National Instrument 43-101Standards of Disclosure for Mineral Projects
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
2/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S i
SUMMARY
LIST OF FIGURES..................................................................................................................................... vii
LIST OF TABLES........................................................................................................................................ ix1.0 INTRODUCTION...............................................................................................................................1 2.0 DENIAL .............................................................................................................................................13.0 SITUATION GO-POLITIQUE..........................................................................................................1
3.1 Corporate Profile.........................................................................................................................23.2 Project Description and Location................................................................................................43.3 Project History ............................................................................................................................53.4 Mining Claims and Authorizations ..............................................................................................6
3.4.1. Legal Structure of Mining Claims ...........................................................................................63.4.2. Authorization to Initiate Mine Operations ...............................................................................73.4.3. Authorization to Operate (ICPE).............................................................................................83.4.4. Property and Surface Rights ..................................................................................................93.4.5. Additional Exploration Rights .................................................................................................9
4.0 GEOLOGY ......................................................................................................................................124.1.1 Mineralization .......................................................................................................................19
5.0 DEPOSIT GEOLOGY......................................................................................................................215.1 Unified Model............................................................................................................................215.2 Scout Zone................................................................................................................................215.3 CC-08 Zone ..............................................................................................................................215.4 CC-88 Zone ..............................................................................................................................22
6.0 EXPLORATION PROGRAM AND DATA COLLECTION................................................................266.1 Exploration Strategy .................................................................................................................26
6.1.1 Mapping................................................................................................................................26 6.1.2 Trenching..............................................................................................................................26 6.1.3 Ground Geophysics..............................................................................................................266.1.4 BRGM Soil Geochemistry Programs....................................................................................276.1.5 Drilling Programs..................................................................................................................276.1.6 Targeted Soil Geochemistry.................................................................................................28
6.2 Data Collection .........................................................................................................................286.2.1. Soil Sampling........................................................................................................................286.2.2. BRGM Deep Augering..........................................................................................................296.2.3. Trenching..............................................................................................................................29 6.2.4. Percussion Drilling................................................................................................................296.2.5. Diamond Drilling ...................................................................................................................30
6.3 Data Storage and Manipulation ................................................................................................317.0 ASSAY RECONCILIATION.............................................................................................................32
7.1 Assaying Procedures................................................................................................................327.1.1. Assay Laboratories...............................................................................................................357.1.2. Duplicates and Standards ....................................................................................................367.1.3. Check Assay Program (QA/QC)...........................................................................................387.1.4. Pulp Duplicates.....................................................................................................................417.1.5. Coarse Reject Duplicates.....................................................................................................41
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
3/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S ii
7.1.6. Field Duplicates....................................................................................................................43 7.1.7. Twinned Drill Holes ..............................................................................................................45
7.2 External Laboratories (Assay Precision Control)......................................................................46
8.0 ADDITIONAL POTENTIAL..............................................................................................................49
8.1 Future Resources in the Camp Caiman Area...........................................................................498.1.1 Nearby Extensions ...............................................................................................................49 8.1.2 Depth Extensions .................................................................................................................49 8.1.3 Regional Extensions.............................................................................................................50 8.1.4 SMBG and CBJ-France Permits ..........................................................................................50
9.0 ORE CHARACTERIZATION...........................................................................................................529.1 Gold Size and Distribution ........................................................................................................53 9.2 Metallurgical Testwork..............................................................................................................54
9.2.1 Overview of Tests and Summary of Results ........................................................................549.2.2 Ore Characterization and Grindability ..................................................................................569.2.3 Gravity Concentration Testwork...........................................................................................609.2.4 Cyanide Leach Testwork......................................................................................................61
9.2.5 Thickening and Sedimentation Testwork .............................................................................66 9.2.6 Miscellaneous Slurry Characteristics ...................................................................................679.2.7 Flotation Testwork ................................................................................................................68 9.2.8 Bio-oxidation/Pressure Oxidation Testwork .........................................................................709.2.9 Cyanide Detoxification Testwork..........................................................................................719.2.10 Arsenic..................................................................................................................................74
10.0 MINERAL RESOURCES ESTIMATION .........................................................................................7510.1 Geological Interpretation...........................................................................................................7510.2 3D Modeling..............................................................................................................................7510.3 Compositing..............................................................................................................................76 10.4 Variography ..............................................................................................................................78 10.5 Mineral Resources....................................................................................................................79
10.5.1 Description Resource Estimation Parameters .....................................................................7910.5.1.1 Geometry of the Block Model ......................................................................................7910.5.1.2 Resource Estimation Parameters................................................................................80 10.5.1.3 Estimate Parameters ...................................................................................................80
10.5.2 Specific Gravity.....................................................................................................................8210.5.3 Mineral Resource .................................................................................................................82
11.0 MINING ...........................................................................................................................................8711.1 General .....................................................................................................................................87 11.2 Geotechnical.............................................................................................................................87 11.3 Bulk Density of Mined Materials ...............................................................................................91 11.4 Conception of pits and equipment ............................................................................................91
11.4.1 Loading and Hauling Operations..........................................................................................91 11.4.2 Mining Roads and ramp design............................................................................................9211.4.3 Waste Dumps.......................................................................................................................9211.4.4 Maintenance equipment .......................................................................................................93
11.5 Infrastructure and Support Facilities.........................................................................................93 11.5.1. Heavy Equipment Shop........................................................................................................9311.5.2. Warehouse ...........................................................................................................................93 11.5.3. Fuel Storage.........................................................................................................................9411.5.4. Wash Bay .............................................................................................................................94
11.6 Mining Reserves .......................................................................................................................9411.7 Production Schedule.................................................................................................................9611.8 Capital Costs ..........................................................................................................................100
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
4/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S iii
11.9 Manpower ...............................................................................................................................10211.10 Operating Costs......................................................................................................................106
12.0 PROCESSING ..............................................................................................................................11012.1 Design Criteria ........................................................................................................................110
12.2 Process Flowsheet .................................................................................................................112 12.3 Plant Design and Location......................................................................................................114 12.4 Primary Crushing ....................................................................................................................11512.5 Saprolite Feed System ...........................................................................................................11712.6 Grinding ..................................................................................................................................11712.7 Gravity Circuit .........................................................................................................................11812.8 Thickener ................................................................................................................................11812.9 Leach/CIP Circuit....................................................................................................................11912.10 Carbon Stripping/Carbon Reactivation/Gold Refining ............................................................12012.11 Reagent Storage Building.......................................................................................................122 12.12 Reagent Preparation...............................................................................................................12212.13 Support Infrastructure.............................................................................................................12512.14 Offices and Process Automation System ...............................................................................126
12.15 Mill Workshop .........................................................................................................................127 12.16 Manpower Requirement .........................................................................................................12712.17 Operating Cost........................................................................................................................130
13.0 INFRASTRUCTURE AND SUPPORT FACILITIES......................................................................13513.1 Site Access .............................................................................................................................135
13.1.1. North Access ......................................................................................................................13613.1.2. South Access......................................................................................................................13613.1.3. Site Roads ..........................................................................................................................137
13.2 Service Buildings ....................................................................................................................137 13.2.1. Administrative Building .......................................................................................................13913.2.2. Heliport ...............................................................................................................................13913.2.3. Heavy Equipment Shop and Warehouse...........................................................................139
13.2.4. Fuel Storage.......................................................................................................................14013.3 Municipal Works .....................................................................................................................141 13.3.1. Drinking Water....................................................................................................................14113.3.2. Fire Protection ....................................................................................................................141 13.3.3. Waste Water Treatment Plant ............................................................................................14113.3.4. Camp..................................................................................................................................142
13.4 Cayenne Office .......................................................................................................................142 13.5 Permanent Housing ................................................................................................................142 13.6 Capital Costs ..........................................................................................................................142
14.0 ADMINISTRATION ET SERVICES...............................................................................................14414.1 Organizational Structure.........................................................................................................144
14.1.1 Operating Workforce ..........................................................................................................144 14.2 General Services ....................................................................................................................146
14.2.1 General Management.........................................................................................................14714.2.2 Corporate Expenses...........................................................................................................14714.2.3 Accounting..........................................................................................................................147 14.2.4 Telecommunications ..........................................................................................................147 14.2.5 Environmental Management ..............................................................................................14714.2.6 Human Resources..............................................................................................................14814.2.7 Purchasing and Procurement.............................................................................................14814.2.8 Health and Safety...............................................................................................................149 14.2.9 Public Security....................................................................................................................14914.2.10 Housing and Cars...............................................................................................................149
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
5/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S iv
14.3 Transportation of Manpower and Materials............................................................................150 14.3.1 Road Transportation...........................................................................................................15014.3.2 Shipping..............................................................................................................................151 14.3.3 Air Transportation...............................................................................................................152 14.3.4 Human Resource Requirements........................................................................................152
14.4 Operating Costs......................................................................................................................154
15.0 ENVIRONMENTAL LEGISLATION AND WORK REGULATION .................................................15615.1 Authorizations .........................................................................................................................156
15.1.1 Authorization for the Initiation of Mine Operations .............................................................156 15.1.2 Authorization to Operate a Mineral Processing Plant ........................................................15915.1.3 Construction and Deforestation Authorization....................................................................16115.1.4 Road Building Authorization...............................................................................................162
15.2 Environmental Impact Study...................................................................................................16215.2.1 Classified Installations........................................................................................................163 15.2.2 Initiation of Mine Operations...............................................................................................164
15.3 Danger Study..........................................................................................................................16515.3.1 Classified Installations........................................................................................................165
15.3.2 Initiation of Mine Operations...............................................................................................166 15.4 Tailings and Water Management............................................................................................16615.5 Geotechnical Investigations....................................................................................................169
15.5.1 Drilling and Sampling .........................................................................................................169 15.5.2 Tailings Site Characterization.............................................................................................17015.5.3 Hydraulic Conductivity Test................................................................................................17215.5.4 In-laboratory Testing Program............................................................................................173
15.6 Geological Model ....................................................................................................................174 15.6.1 Geological Characteristics of the Tailings Site...................................................................174 15.6.2 Local Stratigraphy ..............................................................................................................17415.6.3 Structure.............................................................................................................................176 15.6.4 Laterization.........................................................................................................................176 15.6.5 Tailings Impoundment Evaluation ......................................................................................176
15.7
Natural Hazard Assessment...................................................................................................17715.7.1 Flooding..............................................................................................................................177
15.7.2 Seismic Activity and Ground Motion ..................................................................................17815.7.3 Lightning .............................................................................................................................179 15.7.4 Cyclones.............................................................................................................................179 15.7.5 Forest Fires ........................................................................................................................179 15.7.6 Dam Failure ........................................................................................................................179
15.8 Thickened Tailings Production................................................................................................18015.8.1 Location ..............................................................................................................................180 15.8.2 Design Criteria....................................................................................................................18115.8.3 Process Flowsheet .............................................................................................................181
15.9 Thickened Tailings Pumping...................................................................................................18215.9.1 Pumping System ................................................................................................................182 15.9.2 Piping..................................................................................................................................182
15.10 Management of Thickened Tailings........................................................................................18215.10.1 Design Criteria....................................................................................................................18415.10.2 Closure and Restoration Plan ............................................................................................18615.10.3 Tailings Management .........................................................................................................187 15.10.4 Deposition Area Development............................................................................................18815.10.5 Fill Plan Discussion .........................................................................................................190 15.10.6 Typical Stages in Cell Life ..................................................................................................192
15.11 Dam Design ............................................................................................................................19315.11.1 General...............................................................................................................................193 15.11.2 Design Criteria....................................................................................................................193
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
6/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S v
15.11.3 Details and Comments .......................................................................................................19615.11.4 Geometry and Materials .....................................................................................................19615.11.5 Settlement ..........................................................................................................................197 15.11.6 Stability ...............................................................................................................................19715.11.7 Fill Volumes........................................................................................................................199
15.11.8 Instrumentation...................................................................................................................200 15.12 Tailings Characteristics...........................................................................................................20015.13 Closure of the Thickened Tailings Deposition Area ...............................................................200
15.13.1 General...............................................................................................................................200 15.13.2 Cell Closure........................................................................................................................200 15.13.3 Spillways.............................................................................................................................201
15.14 Mine Tailings Purification Plant ..............................................................................................203 15.14.1 Cyanide Detoxification........................................................................................................20315.14.2 . Arsenic Precipitation.........................................................................................................204 15.14.3 Detoxification Plant Control ................................................................................................204
15.15 Tailings Pumping ....................................................................................................................20515.15.1 Pumping System ................................................................................................................205 15.15.2 Piping..................................................................................................................................205
15.16 Water Balance ........................................................................................................................206 15.16.1 Process and Service Water................................................................................................20815.16.2 Reclaim Water....................................................................................................................20915.16.3 Drinking Water....................................................................................................................20915.16.4 Pit Dewatering Water .........................................................................................................20915.16.5 Runoff .................................................................................................................................210 15.16.6 Final Effluent.......................................................................................................................21015.16.7 Operating Costs..................................................................................................................211
16.0 CONSTRUCTION SCHEDULE AND MANAGEMENT.................................................................21216.1 Management Methodology .....................................................................................................21216.2 Engineering.............................................................................................................................212
16.2.1 Road Engineering...............................................................................................................21216.2.2
Infrastructure Engineering ..................................................................................................212
16.2.3 Geotechnical Engineering ..................................................................................................21316.2.4 Electrical and Automation Engineering ..............................................................................213
16.3 Procurement ...........................................................................................................................213 16.3.1 Longueuil Administrative Office..........................................................................................214 16.3.2 Houston Purchasing Department .......................................................................................21416.3.3 Cayenne Office and Site ....................................................................................................214
16.4 Construction Management......................................................................................................21416.4.1 Administrative Office Team................................................................................................214
16.5 Field Team..............................................................................................................................21616.5.1 Technology Transfer ..........................................................................................................216
16.6 Project Schedule.....................................................................................................................21616.6.1 Year 2005...........................................................................................................................21816.6.2 Year 2006...........................................................................................................................218
16.6.3 Year 2007...........................................................................................................................21816.7 Construction Manpower..........................................................................................................21816.8 Indirect Costs..........................................................................................................................22116.9 Contingency............................................................................................................................223
17.0 OPERATING COST ESTIMATE...................................................................................................22417.1 Operating Costs......................................................................................................................22417.2 Capital Expenditures...............................................................................................................22617.3 Preproduction Expenditures ...................................................................................................226 17.4 Production Expenditures.........................................................................................................229
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
7/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S vi
17.5 Closure and Rehabilitation Plan .............................................................................................23117.5.1 Introduction.........................................................................................................................231 17.5.2 Rehabilitation Goals ...........................................................................................................23117.5.3 Closure and Rehabilitation Criteria.....................................................................................23217.5.4 Closure of the Various Project Elements ...........................................................................233
17.5.5 Revegetation Trials ............................................................................................................24017.5.6 Post-Closure Plan ..............................................................................................................24117.5.7 Timetable and Costs ..........................................................................................................242
18.0 FInancial Analysis .........................................................................................................................247 18.1 Methodology and Parameters ................................................................................................247
18.1.1 Gold Price...........................................................................................................................24718.1.2 Cost of Electricity................................................................................................................24818.1.3 Fuel Price ...........................................................................................................................248 18.1.4 /US$ Exchange Rate........................................................................................................250
18.2 Taxation ..................................................................................................................................25018.2.1 Direct Taxation ...................................................................................................................251 18.2.2 Income Taxes and Indirect Taxes ......................................................................................251
18.3 Government Aid......................................................................................................................25418.4 Economic Analysis..................................................................................................................25518.4.1 Cash Flow Analysis ............................................................................................................255Capital Costs.....................................................................................................................................255Working Capital.................................................................................................................................256Residual Value..................................................................................................................................256Closure and Rehabilitation................................................................................................................25618.4.2 Internal Rate of Return .......................................................................................................259 18.4.3 Payback Period ..................................................................................................................259
18.5 Sensitivities.............................................................................................................................259
19.0 MARKETS AND CONTRATS .......................................................................................................264
20.0 CONCLUSION AND RECOMMENDATION..................................................................................26520.1 Conclusion ..............................................................................................................................26520.2 Recommendation....................................................................................................................266
21.0 BIBLIOGRAPHY............................................................................................................................267
22.0 APPROVAL AND SIGNATURES..................................................................................................268
23.0 CERTIFICATES OF QUALIFICATIONS .......................................................................................269
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
8/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S vii
LIST OF FIGURES
Figure 3.1 Location of French Guiana in South America.............................................................................1
Figure 3.2 Cambior Society..........................................................................................................................3
Figure 3.3 Permit Location and Geological Context ..................................................................................10
Figure 4.1 Camp Caiman Project Plan View and Geology ........................................................................14
Figure 4.2 Camp Caiman Project 3D Geology........................................................................................... 15
Figure 4.3 Camp Caiman Project 3D Mineralized Zones ..........................................................................16
Figure 4.4 Camp Caiman Project Mineralized Zone..................................................................................17
Figure 5.1 Camp Caiman Project Section 300NW, SCOUT Zone.............................................................23
Figure 5.2 Camp Caiman Project Section 450SE, CC-08 Zone................................................................24
Figure 5.3 Camp Caiman Project Section 925SE, CC-88 Zone................................................................25
Figure 7.1 Assay Procedure Flowsheet .....................................................................................................34
Figure 7.2 Camp Caiman Project QA/QC Program ...................................................................................40
Figure 8.1 Camp Caiman Project Location Plan........................................................................................51
Figure 12.1 Schematic Flowsheet.............................................................................................................113
Figure 12.2 Plan 604-D-101.....................................................................................................................116
Figure 13.1 Camp Caiman Access Road..................................................................................................135
Figure 13.2 General Service Building Layout ..........................................................................................138
Figure 14.1 Organigram............................................................................................................................145
Figure 15.1 Authorization procedure for mine development.....................................................................158
Figure 15.2 Authorization procedure for operation of an ICPE.................................................................160
Figure 15.3 Plan 805-G-0147-OC.............................................................................................................168
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
9/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S viii
Figure 15.4 Saprock Size Distribution Curbs Summary ..........................................................................171
Figure 15.5 Geological Tailing Site ..........................................................................................................175
Figure 15.6 Tailings Deposition Method ...................................................................................................184
Figure 15.7 Deposition Model ..................................................................................................................191
Figure 15.8 Deposition Area and Flow of Surface Water after Restoration.............................................202
Figure 15.9 Camp Caiman Water Balance ..............................................................................................207
Figure 16.1 Administrative Office Team...................................................................................................215
Figure 16.2 Field Team............................................................................................................................217
Figure 16.3 Manpower and cumulative manhours for Camp Caiman construction project.....................220
Figure 17.1 Life of Tailings Pond Cells Year -2 ....................................................................................235
Figure 17.2 Life of Tailings Pond Cells Year -1 ....................................................................................236
Figure 17.3 Life of Tailings Pond Cells Year 1 .....................................................................................237
Figure 17.4 Life of Tailings Pond Cells Year 3 .....................................................................................238
Figure 18.1 Gold Price in US$ and .......................................................................................................248
Figure 18.2 Diesel Fuel and Crude Oil Prices..........................................................................................250
Figure 18.3 Sensitivity: Rate of Return ....................................................................................................261
Figure 18.4 Sensitivity: Present Value Discounted at 8%........................................................................262
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
10/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S ix
LIST OF TABLES
Table 4.1 Camp Caiman Project Weathering Profile .................................................................................18
Table 6.1 Summary of Camp Caiman Drilling Programs...........................................................................27
Table 6.2 Holes Drilled in the Mineralized Zone ........................................................................................31
Table 7.1 Control Standard Statistics (g/t) .................................................................................................37
Table 7.2 Check Assay Results .................................................................................................................38
Table 7.3 Summary of Reassays Performed by CGL in 1997-1998 .........................................................42
Table 7.4 Summary of Reassays Performed by SGS in 1998-2000 .........................................................42
Table 7.5 Summary of Reassays Performed by Filab in 2002-2005 .........................................................43
Table 7.6 Summary of Field (Percussion Drilling) Duplicate Assays by CGL and Filab............................44
Table 7.7 Summary of Field Duplicates (Diamond Drilling) Assayed by CGL in 1998..............................45
Table 7.8 Checks Between CGL and SGS in 1998 ...................................................................................46
Table 7.9 Checks Between SGS and CGL in 1998-2000.......................................................................... 47
Table 7.10 Checks Between Filab and ALS-Chemex, 2002-2005 ............................................................48
Table 9.1 Recovery Versus Grind Size Composite Sample 1 ................................................................53
Table 9.2 Bond indice (LR 9712089) .........................................................................................................56
Table 9.3 Comparative Results Coarse Material Content ......................................................................56
Table 9.4 Work Index Comparison Mill Rod ...........................................................................................57
Table 9.5 Comparison of Ball Mill Work Indices ........................................................................................58
Table 9.6 Comparative Assessment Saprolite Lumping Effect ..............................................................59
Table 9.7 Work Indice Determined ............................................................................................................59
Table 9.8 Gravity Concentration (Knelson et Mozley) ...............................................................................60
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
11/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S x
Table 9.9 Overall Recovery GRG ..............................................................................................................61
Table 9.10 Zone 88 Saprolite Gravity/Cyanidation Gravity Tailings (1999).........................................62
Table 9.11 Zone Scout Saprolite Gravity/Cyanidation Gravity Tailings (1999) ................................62
Table 9.12 Cyanidation Saprolite composite (2004)...............................................................................63
Table 9.13 Gravity Separation/cyanidation testwork Sulfides (1998) .....................................................64
Table 9.14 Recovery vs grind size Sulfides (1998) ................................................................................65
Table 9.15 Recovery vs grind size Transition P2391B (1997) ............................................................65
Table 9.16 Sedimentation static testwork (1999)....................................................................................66
Table 9.17 Sedimentation High rate thickening testwork........................................................................67
Table 9.18 Flotation Collector and Depressant Assessment.....................................................................69
Table 9.19 Calcite Depressant Assessment.............................................................................................. 70
Table 9.20 Oxidation and Cyanidation Ore and Flotation Concentrates ................................................71
Table 9.21 Cyanide Detoxification Direct Cyanidation............................................................................73
Table 9.22 Cyanide Detoxification Oxidation Tailings + Flotation Tailings.............................................74
Table 9.23 Cyanide Detoxification Results ................................................................................................74
Table 10.1 5 meter Composite gold value stastistic ..................................................................................77
Table 10.2 Modeled Correlograms for Camp Caiman Scout and CC-08 + CC-88 Zones.........................78
Table 10.3 Camp Caiman Interpolation spherical ID3, April 2005.............................................................81
Table 10.4 Summary of Densities by Lithology.......................................................................................... 82
Table 10.5 In-Situ Camp Caiman Resources Classified by Material Type................................................84
Table 10.6 Camp Caiman In-situ Resources Classified by Zone ..............................................................85
Table 10.7 Camp Caiman in situ measured and indicated resources per area.........................................86
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
12/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S xi
Table 11.1 Lerchs-Grossman Optimization Parameters............................................................................90
Table 11.2 Material Properties by Rock Type............................................................................................91
Table 11.3 Camp Caiman Reserves by Pit and Rock Type ......................................................................95
Table 11.4 Tonnage Mined from Pits .........................................................................................................97
Table 11.5 Tonnage Mined from CC-88 Pit ...............................................................................................97
Table 11.6 Tonnage Mined from the Scout Pit ..........................................................................................98
Table 11.7 Mine to Mill ...............................................................................................................................98
Table 11.8 Stockpile Status .......................................................................................................................99
Table 11.9 Mine Capital Expenditures ($ US)..........................................................................................101
Table 11.10 Manpower Requirements by Departments ..........................................................................103
Table 11.11 Operation Manpower Requirements ....................................................................................104
Table 11.12 Maintenance Manpower Requirements ...............................................................................105
Table 11.13 Mine Operating Budget by Activity .......................................................................................107
Table 11.14 Mine Operating Budget per tonne........................................................................................108
Table 11.15 Unit Costs by Rock Type .....................................................................................................109
Table 12.1 Mill Availability........................................................................................................................110
Table 12.2 Production..............................................................................................................................111
Table 12.3 Manpower Planning - Mill.......................................................................................................129
Table 12.4 Mill Production Summary.......................................................................................................131
Table 12.5 Mill Operating Cost Summary................................................................................................132
Table 12.6 Mill Consumables per Feed Type ..........................................................................................133
Table 12.7 Costs per Type of Ore Life of Mine .....................................................................................134
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
13/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S xii
Table 13.1 Infrastructure and Auxiliary Facilities Capital Cost Estimate ..............................................143
Table 14.1 CBJ-CAIMAN Manpower Summary.....................................................................................146
Table 14.2 CBJ-CAIMAN - Manpower .....................................................................................................153
Table 14.3 General Services and Administration Operating Budget by Activity......................................155
Table 15.1 Thickened Tailings Design Criteria ........................................................................................181
Table 15.2 Design Criteria Tailing Production ......................................................................................185
Table 15.3 Main Development Phases ....................................................................................................189
Table 15.4 Principal Characteristics of teh Dams and Berms .................................................................195
Table 15.5 Estimated fill quantities (m3) ..................................................................................................199
Table 15.6 Summary of Cyaide Detoxification (SO2/AIR) Testwork ........................................................204
Table 15.7 Estimate of volumes of water from runoff and seepage ........................................................208
Table 15.8 Estimate of Runoff and Seepage Water Volumes from the Waste Dumps ...........................210
Table 16.1 Summary of indirect costs......................................................................................................221
Table 17.1 Operating costs......................................................................................................................225
Table 17.2 Operating costs by currency ..................................................................................................226
Table 17.3 Pre-production Expenditure ...................................................................................................227
Table 17.4 Pre-production Expenditure ...................................................................................................230
Table 17.5 Restauration surfaces ............................................................................................................244
Table 17.6 Dismantling ............................................................................................................................245
Table 17.7 Rehabilitation Costs (US$).....................................................................................................246
Table 18.1 On Site Composition of Gazole Price ....................................................................................249
Table 18.2 CBJ-CAIMAN Production Calendar .......................................................................................257
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
14/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S xiii
Table 18.3 Monetary Flux ........................................................................................................................258
Table 18.4 Actual Value (k US$)..............................................................................................................259
Table 18.5 Parameter Variance ...............................................................................................................260
Table 18.6 Risk Summary........................................................................................................................263
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
15/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 1
1.0 INTRODUCTION
The feasibility study for the Camp Caiman project in French Guiana was carried out by the CBJ-CAIMANproject team together with Cambiors Projects and Construction group, supported by independent
consultants retained for specific technical and financial issues.
The various groups that assisted Cambior on this project, along with their fields of activity and specialties,
are shown in the following table:
Mineral resource estimate: Cambior business development and exploration
Geology department, OMAI Gold Mines Ltd.
Mining reserves: Project technical team
Qualified person, Cambior Inc. Technical Services
Mine plan: Project technical team
Capital and operating costs: Cambior Inc. Projects and Construction Group
Project technical team
Pit slope stability: Golder Associates Inc., Denver, Colorado USA.
Hydrogeology, soil bearing capacity, Golder Associates Inc., Montral, Qubec, Canada
Waste dump stability, ground water analysis:
Metallurgical testwork: AMTEC, Australia
Bateman Minerals, Australia
Dawson Metallurgical Laboratories Limited, AustraliaGoldfield, South Africa
INCO Technical Services, Ontario, Canada
Jack Irvine, Ontario, Canada
Lakefield Research Limited, Ontario, Canada
Pacock Industrial, Australia
Metallurgical process: Met-Chem Inc. Montral, Qubec, Canada
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
16/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 2
Tailings paste process: Golder Paste Technology, Sudbury, Ontario
Tailings cells and settling ponds: Golder Associates Inc., Montral, Qubec, Canada
Review of design and tailings storage methods: C.O. Brawner Engineering, Vancouver, Canada
Permit applications for ICPE and Initiation Apave, France
of mine operations: ALTOA, Cayenne, French Guiana
ANTEA Antille-Guyane, Cayenne, French Guiana
B. Bordenave Consultance, Trgunc, France
BRGM, Cayenne, French Guiana
Cabinet ECOBIOS, Cayenne, French Guiana
Defos du Rau, Cayenne, French Guianameraude, Cayenne, French Guiana
FUGRO Gotechnique, Cayenne, French Guiana
G.A. Borstad Associates Ltd, Sidney, BC, Canada
GAIA Hydrobiologie, St-Sulpice sur Lze, France
GEOHYD, Cayenne, French Guiana
Goplus Environnement, Gardouch, France
GEOREM, Chizeuil, France
Golder et Associs, Montral, Qubec
Golder Associates, London, Ontario, Canada
Hydreco, Kourou, French Guiana
INERIS, Verneuil-en-Halatte, France
Institut Pasteur, Cayenne, French Guiana
IRD, Cayenne, French Guiana
Laboratoires Filab, Cayenne, French Guiana
Laboratoires Filab, Chenve, France
Laboratories Wolff Environment, Evry, France
LGIT, Grenoble, France
NRAP, French Guiana
ONF, Cayenne, French Guiana
Royal Haskoning, Villeneuve dAsq, France
Saunier et Associs, Lille, France
SGS, Accra, Ghana
URSTM, Rouyn-Noranda, Qubec, Canada
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
17/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 3
Access road: ALTOA, Cayenne, French Guiana
French Guiana taxation: Bobrie Conseil, Cayenne, France
Ernst and Young, Toulouse, FranceOGEFA, Cayenne, France
PWC, Montral, Canada and Paris, France
Power generation: Kaehnee, Vancouver, Canada
Human resources: Bobrie Conseil, Cayenne, France
This feasibility study sets out in detail the mining and mineral processing operation, support activities and
capital and operating costs required to develop the Camp Caiman project. It describes the miningreserves and mineral resources, the mining plan, the metallurgical process and the tailings storage
methods, as well as water treatment, the mine infrastructure and finally, the environmental considerations
that apply to the operation in relation with the requirements in French Guiana.
This document also presents the schedules and the capital and operating costs, within a 10% margin of
error. All costs shown are in US dollars; the following exchange rates were used in the third quarter of
2005:
1 US dollar = 0.833 Euros
1 US dollar = 1.25 Canadian dollars
All data discussed in this document supports the technical success of the Camp Caiman project.
This Technical Report 43-101 recapitulates the information and the results of the feasibility study of CBJ-
Caiman. The feasibility study of the project and the documents are available for a review at the Cambiors
offices in Longueuil. This report also contains the information which had not been verified and reviewed
during the feasibility study of CBJ-CAIMAN, but which was finished and subjected to the Government ofFrench Guyana. The information has been reviewed and verified since and is included in this report.
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
18/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 1
2.0 DENIAL
This report is based on the information contained in the feasibility study of CJB-CAIMAN INC.S as well ason councillors' reports supporting the feasibility study. The authors compiled the information contained in
this report from these sources. A review and verification beyond the feasibility study was not executed.
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
19/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 1
3.0 SITUATION GO-POLITIQUE
Camp Caiman is a gold project indirectly owned by Cambior Inc. (Cambior). Prior to August 2002, theproject was owned by Asarco Inc. (Asarco) through its French Guiana subsidiary, Asarco Guyane
Franaise SARL (AGF). The project lies 45 kilometres (km) southwest of Cayenne, the main city in
French Guiana, and is accessible by road. French Guiana has been a French overseas dpartement
(dpartement doutre-mer, or DOM) since 1946, and as such is subject to French and European law. It is
located in northeastern South America, and shares a border with Suriname to the west and Brazil to the
east and south (Figure 3.1). French Guiana occupies an area of about 84,000 square kilometres (km2),
95% of which is covered by humid tropical forest. The country has a censured population of about
157,000 inhabitants, most living along the coast. The capital Cayenne itself has a population of about
51,000, with a total of about 84,000 people living in the greater Cayenne area, which includes the
adjacent communities of Rmire-Montjoly and Matoury.
0 200
km
CAMPCAMAN
OMAIROSEBEL
Georgetown
Paramaribo
Cayenne
Amriquedu Sud
GUYANA
SURINAMEGUYANE
FRANAISE
Ocan Atlantique
Location of French Guiana in South America
Figure 3.1
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
20/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 2
French Guianas GNP is about US $1 billion, and inflation runs at around 2.5%. All transactions are
conducted in Euros. The town of Kourou, northwest of Cayenne, is the launch site for Ariane rockets and
the site of Europes Spaceport. The space industry is the French Guianas leading economic activity,
followed by gold mining.
The mining industry consists primarily of small and medium-sized placer operations, with a large number
of illegal sites. Declared production is in the order of 3.5 tonnes (112,500 ounces) per year, with true
production estimated at over 10 tonnes (321,500 ounces).
Shrimping, lumber and tourism also contribute to the Guianese economy, which is nonetheless heavily
supported by both Paris and Brussels under a six-year national and European subsidy agreement
(contrat de plan tat-Rgion).
Air France has daily flights between Paris and Cayenne, and there are regular flights to Miami, the
Antilles and Brazil.
3.1 Corporate Profile
The Camp Caiman project is owned by CBJ-CAIMAN, a simplified form of incorporation (socit par
actions simplifie, or SAS) with a share capital of 6,010,500, registered in December 2004 as the
transformation of AGF, a limited liability company (Socit Responsabilit Limite, or SARL). The headoffice of CBJ-Caiman is located at PK 6,5 Route de Montjoly, Chemin Poupon, 97354 Rmire-Montjoly in
French Guiana.
The sole shareholder of CBJ-CAIMAN S.A.S. (CBJ-CAIMAN) is CBJ-FRANCE, an SAS with a share
capital of 270,000, registered in December 2004 as the transformation of SARL CBJ-France. The head
office of SARL CBJ-France is at PK 6,5 Route de Montjoly, Chemin Poupon, 97354
Rmire-Montjoly in French Guiana.
CBJ-FRANCE S.A.S. (CBJ-France) is 92.6% owned by Ariane Holdings (Barbados) Inc., a company
incorporated in Barbados and wholly-owned by CBJ Caiman Inc. (a Canadian company), and 7.4%
owned by CBJ Caiman Inc., which is in turn wholly-owned by Cambior (Figure 3.2).
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
21/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 3
Cambior inc.(Canada)
CBJ Caiman inc.(Canada)
Ariane Holdings (Barbados) Inc.
(Barbade)
CBJ-France S.A.S.(Guyane franaise)
CBJ-Caiman S.A.S.(Guyane franaise)
100 %
92,6 %7,4 %
100 %
100 %
Figure 3.2
Procedures are presently underway to eliminate Ariane Holdings Barbados and CBJ Caiman Inc. bytransferring the Barbados Company to Canada and merging the two companies with their parent,
Cambior Inc. This will simplify the French subsidiarys corporate structure and accounting procedures, as
well as the fiscal fees and perhaps the defiscalization process with French fiscal authorities. These
changes should be completed by the end of the fiscal 2005.
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
22/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 4
For all intents and purposes, CBJ-CAIMAN and CBJ-FRANCE are wholly-owned subsidiaries of Cambior.
Cambior is an international mining company created in 1986 through the privatization of mining assets in
Quebec. It is based in Qubec and has six producing mines: five gold mines (three in Quebec, one in
French Guiana and one in Suriname) that produced 694,000 ounces (nearly 22 tonnes) of gold in 2004and a large niobium mine in Quebec (Niobec), as well as a 70% interest, through a subsidiary, in Omai
Bauxite Limited, a bauxite mine located in Linden, French Guiana. Cambior also has numerous
exploration projects in Canada, the United States, Peru and the Guiana Shield. At this time, Cambior
employs almost 2,700 people, more than 60% in the Guiana Shield. All Cambior mines are certified
under the ISO 14001 environmental standard. Cambior shares trade on the Toronto Stock Exchange
(TSX) and the American Stock Exchange (AMEX) under the symbol CBJ. Its warrants (CBJ.WT.C and
CBJ.WT.D) are listed on the TSX.
3.2 Project Description and Location
The Camp Caiman gold project consists of three contiguous exclusive exploration permits (permis
exclusifs de recherches, or PER) covering a total area of 71 km2, including the 30 km2Camp Caiman
mining concession.
The Camp Caiman gold project is in the Roura commune, 45 km south-southeast of Cayenne as the crow
flies, in the DOM of French Guiana (). The project is accessed by about 65 km of paved road from
Cayenne: first the RN-2 from Cayenne to Regina, then the CD6 from the town of Roura to the village ofKaw, and finally in a 4x4 vehicle over a five kilometre logging road. The project lies at the base of the
southwest slope of Kaw Mountain, a 310 metre (m) high, 40 km long hill. An unpaved access road about
16.6 km long from the RN-2 (Piste Sud) should be functional by the end of 2006.
The local environment is humid tropical forest with average temperatures of about 29C during the day
and 23C at night. Kaw Mountain is the first obstacle met by clouds coming in from the Atlantic Ocean.
This is therefore one of the rainiest areas of French Guiana, with rainfall averaging
4,118 millimetres (mm) (average 1998 to 2003) and reaching a maximum of 5,678 mm in 2000. Rainfall
is mainly concentrated in the rainy season, from December to June. The Camp Caiman area, like the restof French Guiana, is not in a seismic zone and is not affected by hurricanes.
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
23/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 5
3.3 Project History
The Camp Caiman project is a direct result of the French Guianas mining inventory, created by the
Bureau de recherches gologiques et minires (BRGM) between 1975 and 1995 for the Ministry ofIndustry.
The Camp Caiman area was put up for public auction by the French state through the Regional Bureau of
Industry, Research and the Environment (Direction Rgionale de lIndustrie, de la Recherche et de
lEnvironnement,or DRIRE) in 1994. In competition with numerous other companies, AGF, at the time a
subsidiary of the American company Asarco, submitted the winning bid. Two contiguous exploration
permits, Camp Caiman Est and Ouest, were initially granted in July 1995 for a two-year period, renewable
twice. Three other permits, Camp Caiman Trsor, Trsor Est and Trsor Ouest, were granted in January
1998. The remaining permit, Camp Caiman Patawa, was granted on March 10, 1999. These permitswere subsequently reduced and merged to form three contiguous PER with a total surface area of
71 km2, described in the next chapter.
Work by BRGM at Camp Caiman consisted of soil geochemistry programs that identified a large, seven
kilometre gold anomaly.
From 1996 to 1999, intensive drilling (diamond and reverse circulation totalling over 55,600 m in
544 holes) by AGF resulted in the identification of two significant primary gold deposits. An initial
feasibility study was done, including an environmental impact study, and an application for a 30 km 2
mining concession within the exploration permits was filed in April 1999.
The acquisition of Asarco by Mexican mining company Grupo Mexico, S.A. de C.V. in 1999 brought about
a change in the new structures corporate objectives for French Guiana and its commitment to the Camp
Caiman project. The mining concession application was allowed to go dormant. A small drilling program
was carried out in 2,000 (4,180 m in 47 holes) and the Camp Caiman project was put up for sale.
In August 2002, a junior mining company, Ariane Gold Corp. (Ariane Gold), created in March 2002, finally
purchased the shares of AGF through its French Guianese subsidiary, CBJ-France SARL, and its
Barbadian subsidiary, Ariane Holdings (Barbados) Inc., for a total of US $16,444,600 payable in five
installments.
Intense drilling (diamond and reverse circulation) resumed in September 2002, with the goal of outlining
the measured and indicated resource.
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
24/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 6
An initial assessment performed in June 2003 resulted in an estimate of 37.4 tonnes of gold contained.
The 1999 environmental impact statement was updated, and a second application for a 30 km2mining
concession, along the same lines as the 1999 application, was filed on July 23, 2003 with the Directorate
for Energy and Raw Material Resources (Direction des Ressources nergtiques et Minrales, orDIREM), an arm of the Ministry of Industrys General Directorate for Energy and Raw Materials (Direction
gnrale de lnergie et des matires premires, or DGERM) in Paris.
On November 29, 2003, Ariane Gold merged with the Canadian mining group of Cambior and AGF to
become an indirectly-held, wholly-owned subsidiary of Cambior. From that point on, Cambior assumed
the financial obligations of Ariane Gold and its subsidiaries for payment of the balance of the acquisition
price to Asarco. As of August 17, 2004, two equal amounts of US $4,136,800 remain payable to Asarco,
one on August 16, 2006 and the other 120 days after the commencement of commercial production from
the Camp Caiman project.
Diamond and reverse circulation drilling programs continued until the end of March 2004 to test the
proximal extensions of the two known deposits and their satellite zones.
At June 30, 2005, a total of 140 km of drilling had been done at Camp Caiman in 1,941 holes, including
nearly 82 km of diamond drilling in 713 holes. Of this, nearly 80 km in 1,336 holes were drilled between
September 2002 and June 2005 by Ariane Gold and then CBJ-CAIMAN.
3.4 Mining Claims and Authorizations
3.4.1. Legal Structure of Mining Claims
The Camp Caiman project is covered by three contiguous PER covering a total area of 71 km2: Trsor to
the west, Camp Caiman in the centre and Camp Caiman Patawa to the east.
On July 23, 2003, AGF filed an application with the DIREM for a 50-year, 31 km2
mining concession. Theconcession covers almost all of the Camp Caiman PER and straddles the southeastern portion of the
Trsor PER.
Following a public inquiry held from November 20 to December 19, 2003 in the Roura commune, and the
administrative review that took place in parallel with it, the applicant reduced the life of the concession to
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
25/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 7
25 years. The application cleared the Departmental Mines Commission in Cayenne on
February 26, 2004, with a favourable opinion issued for a 15-year period.
The application was then sent to the General Mines Council (Conseil Gnral des Mines, or CGM) inParis on July 12, 2004, which issued a favourable opinion for a 15-year period and smaller surface area
(without specifying the extent of the reduction).
DIREM sent the application to the State Council on August 17, 2004 with a favourable opinion for the
application as filed by AGF (30 square kilometres for 25 years), disregarding the CGMs opinion. The
State Council is the final stage of the review prior to signature of a decree by the prime minister granting
the mining concession.
It should be noted that opinions issued by the Departmental Mines Commission, the CGM and the StateCouncil are consultative only. The mining concession was delivered by Prime Ministers decree to CBJ-
CAIMAN on November 26, 2004 in accordance to the parameters suggested by the DIREM, which
correspond fully to those sought by CBJ-CAIMAN.
The three PER that form the Camp Caiman project expired on July 31, 2004, and applications to extend
the Trsor and Camp Caiman Patawa PER for five years to July 31, 2009 were submitted to DIREM on
March 29, 2004.
Obtaining the mining concession is necessary but not sufficient to mine the deposits. Once the
concession has been granted, the Mining Code requires that an application for an authorization to initiate
mine operations must also be filed.
3.4.2. Authorization to Initiate Mine Operations
The conditions for granting authorization for the initiation of mine operations are outlined in decree
No. 2001-205 of March 6, 2001 applying and adapting to French DOM decree No. 95-696 of May 9, 1995
on the initiation of mine operations and mining policy.
The perimeter of the facilities in question includes the open pits, waste dumps, mine roads and surface
facilities required for mine operation. All these facilities must be located within the perimeter of the mining
concession.
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
26/291
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
27/291
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
28/291
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
29/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 11
There are placer gold operations all along the projects. The northwest part of the permits, in the crossing
and Sainte-Marie area, was the site of a significant gold operation, both placer and primary, with a total
declared production of about 3.3 tonnes (106,000 ounces) of gold: 2 tonnes (65,000) ounces of placer
gold along the crossing, Anthony and Willy creeks in the second half of the 19 thcentury and early 20thcentury, and about 1.3 tonnes (41,000 ounces) of primary gold at the crossing and Sainte-Marie sites
between 1985 and 1996.
Exploration work (soil geochemistry, deep manual and mechanized auguring, trenching and diamond
drilling) by BRGM, SMBG and CBJ-FRANCE generated results that warranted continued work.
The existence of the south access road offers very good synergy with Camp Caiman, as future gold
mining would be facilitated by the presence of the Camp Caiman infrastructure.
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
30/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 12
4.0 GEOLOGY
The volcanic-sedimentary geology of the Camp Caiman area consists of three main stratigraphic entities(Figure 4.2). Mafic volcanic rocks of the Paramaca Formation at the base are covered by a normally
graded bedding of stratified grey pelites, greywackes and siltites of the Armina Formation. Small
porphyry and intermediate sills are also present in the Armina Formation, cutting obliquely across the
sedimentary beds. The top of the Armina Formation shows inverse grading, changing gradually from
clayey facies to the locally kaolinitic terrigene sandstone facies and quartz-pebble conglomerates
associated with the Orapu Formation.
Two phases of folding produced the map pattern shown in Figure 4.1, Figure 4.2 and Figure 4.3. The first
phase produced tight folds as well as deeply penetrating regional schistosity (S1) accompanied by
metamorphism to lower green schist facies. The second phase produced open folds and regional
northwest southeast crenulations (S2).
These two deformation phases have affected the gold mineralization, giving it a generally sinuous trace in
three dimensions.
Numerous east-west, near-orthogonal, post-mineralization dolerite veins cut the mineralized body. These
vertical veins are several kilometres long and can have a true width of over 40 metres (m).
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
31/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 13
The geology is masked by the equatorial forest cover. On hill tops and flanks, it is also hidden by three
levels of very hard laterite pan, each ranging in thickness from 0 to 5 m. In low lying areas, alluvial
deposits 0 to 5 m thick also play a role. It should be noted that the gold anomaly lies at a break in the
topographic slope. This anomaly is potentially larger that the BRGM work indicates, as it is probablymasked by the laterite pan to the north and alluvials to the south.
During a period of over 100 million years, intense tropical weathering altered all the rocks to laterites and
saprolites to a depth of more than 120 m below surface (Figure 4.4). A few resistant outcrops of Orapu
quartz-pebble conglomerates can be seen locally within the property boundaries.
Tropical alteration of the Guiana Shield considerably transformed and dismantled the paleo-relief, forming
strong saprolitic horizons often covered by discontinuous laterite layers and more erosion-resistant
duricrust. The vegetation cover has protected the soil from erosion. The chemical effects of tropicalweathering include the destruction of the crystal structure of the fresh rock primary minerals by intense
leaching of the silicates (SiO2) and alumina (Al2O3).
This results in the formation of secondary minerals (Ti and Al clays and oxides), mobilization and partial
precipitation of Fe and Mn, and concentration of the more resistant minerals such as zircon, magnetite
and quartz. This chemical phenomenon also tends to concentrate the gold near its source (supergene
gold).
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
32/291
TECHNICAL REPORT
CAMBIOR INC. / CBJ-CAIMAN S.A.S
Camp Caiman ProjectPlan View and Geology
Scout Zone CC-88 Zone
CC-08 Zone
Dolerite
Conglomerate
Porphyry
Flysch
Graphitic Flysch
Coarse-grain Flysch
Greywacke
Volcanics
Pits
Anomalies
Roura-Cayenne
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
33/291
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
34/291
TECHNICAL REPORT
CAMBIOR INC. / CBJ-CAIMAN S.A.S
Scout Zone
CC-08 Zone
Camp Caiman Project3D Mineralized Zones
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
35/291
TECHNICAL REPORT
CAMBIOR INC. / CBJ-CAIMAN S.A.S
Saprolite
TransitionRock
Laterite
Landslide and residues
Mineralized Zone
Alluvials
Camp Caiman ProjectMineralized Zone
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
36/291
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
37/291
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
38/291
-
7/27/2019 43-101 Technical Report Camp Caiman Project, Cambior Nov 2004
39/291
TECHNICAL REPORT National Instrument 43 - 101
CAMBIOR INC. / CBJ-CAIMAN S.A.S 21
5.0 DEPOSIT GEOLOGY
5.1 Unified Model
The deposit was originally divided into three mineralized zones called, from west to east, the Scout,
CC-08 and CC-88 (Figure 4.1) zones. Recent geological interpretations indicate that these three zones
are three subdomains of a single metallotect, with many geological characteristics common to the overall
deposit. For the purposes of regional modeling and resource estimation, it is more practical to describe
each of these zones individually.
5.2 Scout Zone
Occupying the west half of the deposit, the Scout zone consists of a main lens pinching in the northern
and southern extension. The lens is the continuity of the mineralization of the CC-08 and CC-88 zones.
This lens is essentially shaped like a flat-lying Z, encased exclusively in graphitic flyschs of the Armina
Formation, near felsic and intermediate porphyry veins (Figure 5.1). The anticlinal part of the Z
represents the largest volume of the mineralized lens, which has a maximum width of about 50 m. The
primary sulfides present are arsenopyrite and pyrite, forming most 5% of the whole.
The mineralized zone was tested almost exclusively in saprolite on a 25 m x 25 m grid, over a distance of
1,100 m and to a maximum depth of 140 m below surface. Very locally, a 12.5 m x