4.1 table 2-57 - productivity inc

61
1 Specification ............................................................................... 2-1 1.1 Machine Part and Name ........................................................... 2-1 1.2 Machine Specification ...............................................................2-2 1.2.1 Standard and Option Accessories ....................................2-6 1.3 Spindle Speed-Power Diagram ................................................ 2-11 1.4 Principal Dimensional Drawings .............................................. 2-13 1.4.1 External Dimensions ...................................................... 2-13 1.4.2 Axis Stroke and Reference Point ................................... 2-15 1.4.3 Relationship Between Workpiece and ATC..................... 2-17 2 Transports and Installation ........................................................ 2-21 2.1 Preparation Items before Installing .......................................... 2-21 2.1.1 Foundation work............................................................ 2-23 2.1.2 Foundation area ............................................................ 2-25 2.2 Process of Machine Installation .............................................. 2-34 2.3 Transport ............................................................................... 2-35 2.3.1 Instruction..................................................................... 2-35 2.3.2 Transportation method using crane ............................... 2-36 2.3.3 Transportation method using forklift .............................. 2-39 2.4 Machinery Package and Disassemblies .................................. 2-41 2.5 CHIP CONVEYOR.................................................................... 2-43 3 Leveling and Electric device..................................................... 2-46 3.1 Leveling ................................................................................. 2-46 3.2 Electric device....................................................................... 2-48 3.2.1 Grounding ..................................................................... 2-48 3.2.2 Check for power supply ............................................... 2-52 3.2.3 Check before operation ................................................ 2-52 3.2.4 Connecting Main Power ................................................ 2-53

Upload: others

Post on 29-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

1 Specification ............................................................................... 2-1

1.1 Machine Part and Name ........................................................... 2-1

1.2 Machine Specification ............................................................... 2-2

1.2.1 Standard and Option Accessories ....................................2-6

1.3 Spindle Speed-Power Diagram ................................................ 2-11

1.4 Principal Dimensional Drawings .............................................. 2-13

1.4.1 External Dimensions ...................................................... 2-13

1.4.2 Axis Stroke and Reference Point ................................... 2-15

1.4.3 Relationship Between Workpiece and ATC ..................... 2-17

2 Transports and Installation ........................................................ 2-21

2.1 Preparation Items before Installing .......................................... 2-21

2.1.1 Foundation work ............................................................ 2-23

2.1.2 Foundation area ............................................................ 2-25

2.2 Process of Machine Installation .............................................. 2-34

2.3 Transport ............................................................................... 2-35

2.3.1 Instruction ..................................................................... 2-35

2.3.2 Transportation method using crane ............................... 2-36

2.3.3 Transportation method using forklift .............................. 2-39

2.4 Machinery Package and Disassemblies .................................. 2-41

2.5 CHIP CONVEYOR .................................................................... 2-43

3 Leveling and Electric device ..................................................... 2-46

3.1 Leveling ................................................................................. 2-46

3.2 Electric device ....................................................................... 2-48

3.2.1 Grounding ..................................................................... 2-48

3.2.2 Check for power supply ............................................... 2-52

3.2.3 Check before operation ................................................ 2-52

3.2.4 Connecting Main Power ................................................ 2-53

4.1 Table ..................................................................................... 2-57

4.2 Tool Shank (BT50) ................................................................. 2-59

2-1

1 Specification

1.1 Machine Part and Name

Fig. 2-1. Machine Part and name

2-2

1.2 Machine Specification

1. KH50G

Table 2-1 Machine Specification

Item Unit KH50G (option)

Table

Table Size mm 500 × 500

Maximum Load Capacity kgf 2 - 800

Maximum Working Size mm ø900 × H780

Min. Indexing Angle. deg 1˚ [0.001˚]

Spindle

Spindle Taper - NT #50

SP. Speed (rpm) r/min 20 ~ 4500 [8000]

Spindle Motor Output (Max./Cont.) kW(HP) 18.5/15 [22/18.5]

Spindle Torque (Max./Cont.) N·m 901/730 [1071/901]

Spindle Driving Method - 2 Step Gear

Feed

Travel (X/Y/Z axis) mm 760/705/650

Distance from Column to SP. center mm 0 ~ 705

Distance from Table Surface to Sp mm 135 ~ 785

Rapid Feed Rate (X/Y/Z) m/min 20/20/20

Cutting Feed Rate (X/Y/Z) m/min 5

Slide Type - Box Guide

ATC

Number of Tools EA 40 [60, 90, 120]

Tool Shank - BT50

Max. Tool Dia. (W.T/W.O) mm ø110 / ø245

Max. Tool Length mm 400

Max. Tool Weight kg 20 [35]

Tool Selection Method - Fixed Address

Tool Change Time T-T sec 5.5

C-C sec 9

APC

No. of Pallet EA 2

APC Change Time sec 16

Table Type - SHUTTLE

2-3

Table 2-1 Machine Specification (continue)

Item Unit KH50G (option)

Tank

Capacity

Coolant Tank ℓ 400

Lubricating Tank ℓ 3.4

Power

Supply

Spindle Cooling Unit ℓ 60

Air Consumption (0.5MPa) ℓ/min 300

Electric Power Supply KVA 40

Thickness of Power Cable Sq Over 25

Voltage V/Hz 220 / 60(200 / 50)

Machine

Floor Space (L×W) mm 2890 × 4340

Height mm 3076

Weight kg 12000

Specifications are subject to change for improvement without notice.

2-4

2. KH63G

Table 2-1 Machine Specification

Item Unit KH63G (option)

Table

Table Size mm 630 × 630

Maximum Load Capacity kgf 2 - 1000

Maximum Working Size mm ø1120 × H875

Min. Indexing Angle. deg 1˚ [0.001˚]

Spindle

Spindle Taper - NT #50

SP. Speed (rpm) r/min 20 ~ 4500 [8000]

Spindle Motor Output (Max./Cont.) kW(HP) 22/18.5 [26/22]

Spindle Torque (Max./Cont.) N·m 1071/901 [1267/1071]

Spindle Driving Method - 2 Step Gear

Feed

Travel (X/Y/Z axis) mm 950/825/760

Distance from Column to SP. center mm 0 ~ 825

Distance from Table Surface to Sp mm 175 ~ 935

Rapid Feed Rate (X/Y/Z) m/min 20/20/20

Cutting Feed Rate (X/Y/Z) m/min 5

Slide Type - Box Guide

ATC

Number of Tools EA 40 [60, 90, 120]

Tool Shank - BT50

Max. Tool Dia. (W.T/W.O) mm ø110 / ø245

Max. Tool Length mm 600

Max. Tool Weight kg 20 [35]

Tool Selection Method - Fixed Address

Tool Change Time T-T sec 5.5

C-C sec 9

APC

No. of Pallet EA 2

APC Change Time sec 16

Table Type - SHUTTLE

2-5

Table 2-1 Machine Specification (continue)

Item Unit KH63G (option)

Tank

Capacity

Coolant Tank ℓ(gel) 400

Lubricating Tank ℓ(gel) 3.4

Power

Supply

Spindle Cooling Unit ℓ(gel) 60

Air Consumption (0.5MPa) ℓ/min 300

Electric Power Supply KVA 40

Thickness of Power Cable Sq Over 25

Voltage V/Hz 220 / 60(200 / 50)

Machine

Floor Space (L×W) mm(in) 3225 × 4820

Height mm(in) 3106

Weight kg(lb) 14000

Specifications are subject to change for improvement without notice.

2-6

1.2.1 Standard and Option Accessories

: Standard : Option : Prior Consultation X : Non Application - : Impossible

Table 2-2 Standard and Option Accessories

ITEM Remark KH50G KH63G

Spindle

4500rpm(18.5/15kW) GEAR(2STEP) -

4500rpm(22/18.5kW) GEAR(2STEP)

4500rpm(26/22kW) GEAR(2STEP) -

8000rpm(18.5/15kW) GEAR(2STEP) -

8000rpm(22/18.5kW) GEAR(2STEP)

8000rpm(26/22kW) GEAR(2STEP) -

Spindle Cooling System

ATC

ATC Extension

40

60

90

120

Tool Shank Type BT50

Heavy Weight Tool 20 kg

35 kg

U-Center D'andrea

STUD BOLT

COLLET Change

45 。

60 。

90 。

Servo Motor Magazine

Table & Column

APC SHUTTLE

TAP TYPE Pallet

T-SLOT Pallet

B-Axis Table 1。

0.001。

2-7

Table 2-2 Standard and Option Accessories (continue)

ITEM Remark KH50G KH63G

Coolant System

Std. Coolant (Nozzle)

Spindle Thru Coolant

5 bar - -

20 bar

30 bar

70 bar, 15L

70 bar, 30L

Jet Coolant

Gun Coolant

Side Oil Hole Coolant

Air Gun

Spindle Air Blow

Tool Measuring Air Blow (Only for TLM)

Air Blow for Automation

Thru MQL Device (Without MQL)

Coolant Chiller

Power Coolant System (For Automation)

Chip Disposal

Coolant Tank 400 ℓ

Cabin Screw Chip Conveyor

Chip Conveyor

(Hinge/Scraper)

Left (Front)

Left(Rear)

Special Chip Conveyor (Drum Filter)

Chip Box

Std.(180L)

Swing(200L)

Large Size(330L)

Customized

Safety Device

APC Splash Guard

Total Splash Guard

2-8

Table 2-2 Standard and Option Accessories (continue)

ITEM Remark KH50G KH63G

Software

Machine Guidance

HWTM

DNC Software

Dialogue Program

Tool ID Manager

Spindle Heat Distortion

Compensation

Spindle Warm up Function

Electric Device

Call Light 1 Color:

Call Light 3 Color:

Call Light & Buzzer 3 Color: B

Work Light

Electric Cabinet Light

Door Inter-Lock

Remote MPG

3-axis MPG

Spindle Load Meter LED TYPE

Spindle RPM Meter LED TYPE

Work Counter Digital

Total Counter Digital

Tool Counter Digital

Multi Tool Counter 6 EA

9 EA

Electric Circuit Breaker

AVR(Auto Voltage Regulator)

Transformer & Cable 35 kVA

Flash Memory Card

Auto Power Off

Back up Module for Black out

2-9

Table 2-2 Standard and Option Accessories (continue)

ITEM Remark KH50G KH63G

Measuring Device

Air Zero TACO

SMC

Work Measuring Device

TLM

Marposs/Renishaw/Bloom

Touch

Laser

Tool Broken Detective Device

Linear Scale X/Y/Z-axis

Rotary Scale B-axis

Pallet Close Confirmation Device

Coolant Level Sensor Only for Chip Conveyor

Environment

Air Conditioner

Dehumidifier

Oil Mist Collector

Oil Skimmer Only for Chip Conveyor

MQL

Fixture & Automation

Sub Operation Panel

Control of Additional Axis 1 axis/Pallet

External M code 4ea

Automation Interface

I/O Extension (In & Out) 16Contact

32Contact

PPL(6PPL)

2-10

Table 2-2 Standard and Option Accessories (continue)

ITEM Remark KH50G KH63G

Hyd. Device

Std. Hyd. Unit 45 bar/60 ℓ

Center Type Hyd. Supply Unit

(Upper) 2x4(8 Port)

Manual Coupler 2x3(4 Port)

Auto Coupler

Hyd. Unit for Fixture

45 bar

70 bar

100 bar

Customized

ETC

Tool Box

Customized Color Need for Munsel NO.

CAD&CAM Software

AIR Lift Slide Method Z-axis

The specifications as above will only serve as a reference

2-11

1.3 Spindle Speed-Power Diagram

1. KH50G (4500 rpm)

Fig. 2-2 Spindle Speed-Power Diagram

2. KH50G (8000 rpm)

Fig. 2-2 Spindle Speed-Power Diagram

2-12

3. KH63G (4500 rpm)

Fig. 2-2 Spindle Speed-Power Diagram

4. KH63G (8000 rpm)

Fig. 2-2 Spindle Speed-Power Diagram

2-13

1.4 Principal Dimensional Drawings

1.4.1 External Dimensions

Fig. 2-3 Principal Dimensional Drawings (KH50G)

2-14

Fig. 2-3 Principal Dimensional Drawings (KH63G)

2-15

1.4.2 Axis Stroke and Reference Point

Fig. 2-4 Axis Stroke and Reference Point (KH50G)

2-16

Fig. 2-4 Axis Stroke and Reference Point (KH63G)

2-17

1.4.3 Relationship Between Workpiece and ATC

Fig. 2-5 Relationship Between Workpiece and ATC (KH50G)

2-18

Fig. 2-5 Relationship Between Workpiece and ATC (KH50G)

Du

rin

g A

TC

op

era

tion

, th

ere

is

no

in

terf

ere

nce

be

twe

en

the

ma

chin

e an

d t

oo

l. H

ow

eve

r, a

pa

rtic

ula

r w

ork

pie

ce m

ay

inte

rfe

re w

ith th

e m

ach

ine ;

it d

ep

end

s up

on

th

e too

l sh

ape

.

Th

e a

bo

ve d

iag

ram

sho

ws

that

the

la

rge

st w

ork

pie

ce i

s p

lace

d o

n t

he p

alle

t a

t X

-axis

+ d

ire

ctio

n s

tro

ke a

nd t

he t

oo

l is

rep

lace

d w

ith t

he

la

rge

st t

oo

l. T

hen

, th

e a

rea s

had

ed

with s

lan

ted l

ine

s in

terf

ere

with

th

e w

ork

pie

ce.

Whe

n r

ep

laci

ng

too

ls,

be

su

re tha

t n

o t

oo

l inte

rfe

res

with

th

e w

ork

pie

ce.

2-19

Fig. 2-5 Relationship Between Workpiece and ATC (KH63G)

2-20

Fig. 2-5 Relationship Between Workpiece and ATC (KH63G)

2-21

2 Transports and Installation

2.1 Preparation Items before Installing

• Before installing the machine, read and understand the safety notice

thoroughly in this manual.

• While installing, there should be no oil or water on the floor to prevent

the workers from slipping.

• Before working, check again it is installed at a proper place.

1. Installation Conditions

(1) The following places are favorable to install the machine.

a. The place without condensing and dewiness due to the temperature change

b. The place with an even and resistant surface

c. The place with stable utility supply and maintenance

d. The place where the machine can be easily relocated

e. The place without the danger of fire or explosion

(2) The following shall be avoided.

a. The place with direct ray of light, near heating elements, with too much temperature

change.

b. The place with excessive dust and moist

c. The place near vibrating machines

d. The place with weak ground

e. The place with uneven or slide ground

• When there has to be a vibrating machine nearby, some kind of a

vibration absorber shall be placed around the machine.

• If special options are attached on the machine, the space for

maintenance shall be insured.

2-22

2. Installation Environment

Table 2-4. Installation Environment

Classification Contents

Temperature 0 ~45 Celsius shall be maintained

Humidity 10 %~75% RH

Space Additional space at least of 600mm around the machine for maintenance

and repair

Light lighting facility of at least 300 Lux

Purity Better than Class 100

Noise Lower than 70 dB(A)

Temperature of Storage -20 ~ +65

Install the air supply with the air dryer because a machine may be

damaged when the air contains much humidity or the air is not.

3. Notes in using (NC)

This equipment is a CNC that the inside of control panel consists of various electronic

control units. In order to use it effectively, should use the basic knowledge for PC. In

addition, there is a safety unit so as to protect against the external shock or burn out, but

note that the failure can be caused by an excessive shock.

2-23

2.1.1 Foundation work

1. without using Foundation Bolt

(1) Put the leveling seat at the place shown in foundation diagram.

(2) After inserting the leveling bolt in the machine, put it above the leveling seat with about

10 mm distance from the upper side of leveling seat.

(3) Adjust the leveling bolt, set the level of machine correctly and then tighten the leveling

nut.

2. Using Foundation Bolt (optional)

(1) Place the machine at the place to be installed and perform the 1st leveling work. If the

leveling seat is out of its position or it is impossible to adjust it with the leveling bolt due

to poor foundation, use a wedge to do a leveling work.

(2) After completion on the first leveling work, insert the foundation bolt from the bottom of

machine and install it to the machine using nuts.

(3) Fill the mortar up to the bottom and the side of leveling seat and stir it with a bar.

(4) Adjust the leveling bolt, complete leveling work in all sides, and then engage the

foundation bolt tightly.

2-24

Fig. 2-4 Foundation work

2-25

2.1.2 Foundation area

Table 2-4 Foundation area

No. Model Name ATC OPTION Remark

1

KH50G

40 Tools

2 60 Tools

3 90 Tools

4 120 Tools

5

KH63G

40 Tools

6 60 Tools

7 90 Tools

8 120 Tools

2-26

1. KH50G (ATC 40 Tools)

Fig. 2-5. Foundation area

2-27

2. KH50G (ATC 60 Tools)

Fig. 2-5. Foundation area

2-28

3. KH50G (ATC 90 Tools)

Fig. 2-5. Foundation area

2-29

4. KH50G (ATC 120 Tools)

Fig. 2-5. Foundation area

2-30

5. KH63G (ATC 40 Tools)

Fig. 2-5. Foundation area

2-31

6. KH63G (ATC 60 Tools)

Fig. 2-5. Foundation area

2-32

7. KH63G (ATC 90 Tools)

Fig. 2-5. Foundation area

2-33

8. KH63G (ATC 120 Tools)

Fig. 2-5. Foundation area

2-34

2.2 Process of Machine Installation

The following process shall be observed.

1. Move the machine to the location to be installed.

2. Remove all the wrapping material covering the machine.

3. Assemble additional parts to the main body.

4. Connect the power cable.

5. Turn on the main power switch on the right side of Control box.

6. Turn right the Emergency Stop switch to release. It is on the control panel on the machine

front.

7. Turn the Operate/Stop switch to toward operate. It is on the control panel.

8. The preparation process of the machine operation has been finished.

2-35

2.3 Transport

2.3.1 Instruction

1. The Machine is consisted of 3 kinds of main elements, such as machine body, control

panel, hydraulic unit and each of wiring and hydraulic piping is connected. Also, all units

are attached to machine body and machine is not disassembled and can move to

desired distance.

2. There are 2 types, such as crane and forklift for moving method.

3. If installation is performed according with this operation manual, can obtain machine

precision of desired product.

• When transporting the machine, be careful not to crane with other

objects.

• Never stand or walk under highly-lifted machine.

• When machine is transported, pay attention that your body part does

not inserted.

• Prior to transporting the machine, check each part of the machine is

properly fixed to each other.

• When lifting the machine, slowly do a job, ensuring a full balance.

• Be careful not to give a shock to the body of machine, the Electric

Control Panel, and other electric devices.

• Transport the coolant tank after removing it from the body of machine.

• Before machine is transported, check that already installed machine

dose not interfered. If sufficient space is not distributed, contact to

responsible person of factory and rearrange the machine or remove

safety. If you do not remove it, provide the attention to worker and

obtain the safety.

2-36

2.3.2 Transportation method using crane

1. Horizontal level should be maintained during transportation, if some case.

2. The machine shall not move by fixing securely it to transportation device.

3. As Top hook of machine is damaged by contact of wire rope, it should be transported by

providing the cloths (protective cloths).

4. If you lift the machine, slowly lift as possible as and verify that the wire rope and the

machine is a level again by temporarily stopping at a falling moment

5. As shown in the figure, after lifting the machine by engaging the wire rope to hook on top

of machine, it should be moved to designated area.

6. Verify following items, when you work.

(1) Adjust the center by moving the saddle table so that center of machine load can be

position to lifting fixture, and lower the main spindle head to the lowest bottom in order

to lower the gravity of center as possible as.

(2) Using load of crane and Wire capacity is follows as.

a. KH50G (Crane: 18 t)

Machine ATC Weight(t) Wire A Wire B Wire C

40 PCS ATC ATTACHED 13.5 Ø22×4.00 m Ø22×4.00 m Ø22×8.25 m

60 PCS ATC ATTACHED 14.1 Ø22×4.00 m Ø22×4.00 m Ø22×8.25 m

90 PCS ATC ATTACHED 15.0 Ø22×3.96 m Ø22×4.00 m Ø22×8.50 m

120 PCS ATC UNATTACHED 11.9 Ø22×4.10 m Ø22×4.00 m Ø22×8.00 m

b. KH63G (Crane: 25.95 t)

Machine ATC Weight(t) Wire A Wire B Wire C

40 PCS ATC ATTACHED 14.5 Ø24×4.50 m Ø24×4.50 m Ø24×10.00 m

60 PCS ATC ATTACHED 15.1 Ø24×4.50 m Ø24×4.50 m Ø24×10.20 m

90 PCS ATC ATTACHED 16.0 Ø24×3.96 m Ø24×4.00 m Ø24×9.40 m

120 PCS ATC UNATTACHED 12.9 Ø22×4.50 m Ø22×4.50 m Ø24×10.00 m

2-37

2-38

• With the machine lifted slightly, check all sides for balance and the

rope is reached to the cover or other parts.

• When more than 2 persons have to lift the machine, they should work

together, communicating each other.

• Do not use rusty or shorted wire ropes.

• When lifting the machine, slowly do a job. If the wire rope is tightened,

temporarily stop and check an eye bolt is clamped and then lift up to

the desired height.

• When pulling down, also do it slowly. Just before reached the floor,

stop it and check the position and then pull down completely.

• Only the experienced-personnel should perform a crane work.

2741-69-301-00

HOOK (R)

2741-69-302-00

HOOK (L)

2-39

2.3.3 Transportation method using forklift

• Only who has the forklift driver's license can convey the machine by

forklift.

• To avoid damage around the protruded part of machine, the task

should be performed by two persons, of which one is a supervisor.

• Put down the machine slowly not to give a shock on the floor.

• Hold wood between the forklift and the machine for lifting.

Fig. 2-9. Transportation method using forklift

2-40

Fig. 2-10. Fork position

Only who has the forklift driver's license can convey the machine by

forklift.

To avoid damage around the protruded part of machine, the task

should be performed by two persons, of which one is a supervisor.

Put down the machine slowly not to give a shock on the floor.

Hold wood between the forklift and the machine for lifting.

Fork Position

2-41

2.4 Machinery Package and Disassemblies

This paragraph describes how to packing and unpacking the machine before and after

shipment as well as the precautions and other necessary information for users.

As any damage or error to the machine may occur without correct packing and unpacking of

the machine are made, the users must fully understand how to packing and unpacking the

machine described below.

This paragraph describes how to packing and unpacking the machine before and after

shipment as well as the precautions and other necessary information for users.

As any damage or error to the machine may occur without correct packing and unpacking of

the machine are made, the users must fully understand how to packing and unpacking the

machine described below.

1. MACHINERY PACKAGING

(1) Machinery must be cleaned before packaging and the process must be conducted

inside the clean room.

(2) Use tape or rope to fix machinery to prevent machinery from rotation or spin.

(3) Appropriate amount of damp-proof material must be included with machinery during

packaging process to prevent damp build-up.

(4) Machinery should be packed at least 2 times, using an Air Wrap to prevent exterior

entry of air & resin and shock.

(5) The person in charge of machinery packaging must select appropriate packaging type

for machinery packaging.

(6) When machinery requires wooden packaging, consult packaging specialists for

packaging process.

(7) After packaging, appropriate number should be recorded on the box exterior for

distinction.

(8) Warning and precaution stickers must be attached to the packaging box exterior and

followed during delivery process.

(9) Machinery must be packed once by plastic then again by packaging wrap.

2-42

2. DISASSEMBLE PACKAGING

(1) This machinery is Air Wrapped from factory as one piece when it is sent out.

(2) Wooden safety frame must be removed.

(3) When packaged machinery is delivered, un-pack immediately to check and assure

system damage didn’t occur during delivery process.

(4) Machinery damage inspection list is as follows;

a. Check damage including imprints on machinery exterior

b. Check safety cover for damage

(5) Take particular care during un-packaging process as damage could occur on

machinery if packaged machinery is dropped.

(6) If there is no machinery damage, check to assure all items listed in packing list is

included and provided

2-43

2.5 CHIP CONVEYOR

1 Installation

(1) chip conveyor is, in principle, designed to be used indoors. please consult with manu-

facture for supplement if chip conveyor shall be used outdoors.

(2) install geared motor horizontally.

(3) fix firmly to avoid vibration during operation.

(4) load/unload the chip conveyor with cranes using a rope.(do not use forklifts and other

transportation equipment except cranes.)

(5) when loading/unloading the chip conveyor, fix the rope to the lifting lug firmly.

(6) when transporting the chip conveyor, fix it firmly to avoid swing during transportation.

(7) install the conveyor inside a machine or fix it on the factory floor, and fix the level bolt

on the floor.

2. Operation Precautions

(1) chip conveyor is delivered after a thorough test run. however, please check the take-

up adjustment bolt during installation if the bolts are loosened during transportation.

check also the chain belt looseness.

(2) check and remove foreign materials from the conveyor belts.

(3) check the direction of rotation of the belt when start run switch is on.

(4) operate conveyor while machine tools discharge chips.

(5) always check it noese and heat in geared motor, rotation and electric current

(6) pay attention during oiling so that the friction plate of a torque limit may not be stained

with oil.

(7) always check it the chain tension of main and driving is normal.

(8) when operating the chip conveyor after long-time suspension, make sure a lot of chips

may not flow in and then operate it.

(9) do not remove the dog of a torque limit.

(Limit switch Attaching type: As Option is applied, standard is not applied.)

2-44

Fig. 2-8 Chip conveyors

2-45

Table 2-5 Lists of parts

No. NAME No. NAME

1 BODY 21 TAKE UP FRAME

2 GEARED MOTOR 22 BEARING

3 KEY 23 ADJUSTING BOLT

4 COVER 24 COVER

5 SPROCKET WHEEL 25 BOLT

6 SET SCREW 26 BOLT

7 ROLLER CHAIN (DRIVING) 27 SPRING WASHER

8 BOLT 28 NUT

9 WASHER 29 HINGE PLATE

10 TORQUE LIMIT UNIT 30 PIN

10A HOUSING 31 SIDE PLATE

10B LINING(FRICTION PLATE) 32 SIDE PLATE-ROLLER CHAIN

10C SPROCKET WHEEL 33 ROLLER-ROLLER CHAIN (MAIN)

10D BEARING 34 WASHER

10E COLLAR 35 SPLIT PIN

10F CONE SPRING 36 WHEEL SHAFT

10G NUT 37 DU BUSH

10H SET SCREW 38 WHEEL

11 BOLT 39 WASHER

12 REAR COVER 40 BOLT

13 DRIVE SHAFT A-1 SCRAPER

14 KEY A-2 ROLLER CHAIN (MAIN)

15 KEY A-3 WASHER

16 KEY A-4 BOLT

17 SPROCKET WHEEL

18 SET SCREW

19 SPROCKET WHEEL

20 SET SCREW

2-46

3 Leveling and Electric device

3.1 Leveling

Leveling is the No.1 factor determining the accuracy of machine.

To level the machine is the most basic operation to have influence on the owrkpiece and the

life span of machine.

First, place machine on the levelling sheet, and then align the levelling bolt on machine and

lower it in position.

The level gauge suited for this use is that has the sensitivity scale of 0.02 mm per in.(The

length of level gauge is 200 mm). Do not use the level gauge used in construction field.

Handle level gauge so that each end maintains same direction.

The surface where level gauge is placed should be clean and free from any dust.

Adjust the on the center of table as follows so that the horizontal reading does not differ from

the longitudinal reading by more than 0.04 mm/m.

When fis the levelling bolt, be careful not to be loosen it.

Foundation bolts may be used for fixing if mechanical vibration rises now and then due to

ununiform work or intermittent cutting.

Check the level every day for 2~3 days from the installation. Then check it every month for six

months from installation, and every three months thereafter.

2-47

Fig. 2-13 Leveling

Level

2-48

3.2 Electric device

3.2.1 Grounding

Only authorized engineer can do earth working. Failure to comply may

result in personal severe injury, death, or accident.

1. All electric devices should be grounded to prevent personal injury and misoperation of the

machine according to the specification, after installed.

2. Select the grounding point as close to the machine as possible and perform wiring

independently.

3. Do the third-class grounding only by the authorized engineer.

- Grounding resistance : under 100 Ω

- Thickness of wire

- Measuring device : 500 V Megger

Table 2-7. Thickness of wire

Wire area S mm2 for power supply Min. area Sp mm2 of ground wire

S ≤16

16 < S ≤ 35

S > 35

S

16

S/2

2-49

(1) Grounding Method

The machine should be grounded by one of the following methods.

a. Individual grounding

Fig 2-10 Individual grounding

2-50

b. Common grounding

The grounding line of each machine should be grounded at its ground terminal

directly. (Only one line to one terminal)

Fig. 2-11 Common grounding

Grounding resistance =

100

Ω Number of

machine

2-51

c. Never ground in the following methods

.

Fig. 2-12 Never ground in the following methods

2-52

3.2.2 Check for power supply

The equipment is delivered under our strict Q.C, but in case of state before delivery is not

maintain to 100% by vibration during transportation for long time and temperature change,

occurs. Equipment installer verify following check before power supply and then supply the

power.

1. Checks before power supply

(1) Verification for assembled state of each of parts in control panel (part loosing).

(2) Verification for assembled state of assembled connector in control panel and unite.

(3) Check and supplement whether assembled wire is loosen of Terminal Block

(4) Check setting current value of Breaker for protecting Motor (Check that it is met to

Marking section)

(5) Check that connector assembled to control panel, is screwed.

(6) Check other general motor connection wire and signal and power connector of Servo /

Spindle Motor is assembled.

(7) Check joint section of hose connection (hydraulic/cutting oil/pneumatic) for machine

section.

(8) Check (RED Colored Bracket) separation of each of fixture (X, Y, Z axis, for lathe, X, Z

axis)

3.2.3 Check before operation

1. Before operation, read install and operation manual supplied from our company and

operate according with indicated method.

2. To operate safely, machine purchaser direct that only employees trained in basic handling

course, are operated machine.

3. After supplying main power, check that main parts of machine are leaked, while the

machine keeps normally operated (Machine Ready) status and use after lubrication Unit

is normally lubricated.

2-53

3.2.4 Connecting Main Power

Fig. 2-17. Connecting Main Power

1. Power Switch

Install other machines with the independent power switches at the place where easy to

open and close. See the following table for the capacity of fuse.

Table 2-8. Fuse Capacity and Available Wire

Model Power capacity

(kVA)

Available Wire [²] Fuse [A]

L01, L02, L03 Grounding Line

KH50G 40 38 19 125

KH63G 40 38 19 125

2-54

2. Changing Electric Units According to Voltage and Frequency

According to the voltage and frequency of the power of factory, it needs to change the

setting of electric applications. Prior to changing, check its voltage and frequency.

Power Voltage: 200/220 V±10 %

Power Frequency: 50/60 Hz±1 Hz

• If the voltage fluctuated seriously, it may cause disoperation of the

machine and failure of the electric and electronic parts. Therefore, set

the fluctuating rate not to exceed ±10 %.

(1) Tab Changing for Controlling Transformer

Open the door of the Electric Control Panel, remove the plastic cover of Transformer

and then change the wiring as shown in the following table.

Table 2-9. Voltage

Voltage R2 T2

191~210 V 200 V 0 V

211~240 V 220 V 0 V

(2) External Transformer

Table 2-10. External Transformer (in case of 380V and 400V and 415V, 440V)

Model Voltage - Primary Transformer Capacity

KH50G/63G 380V, 400V, 415V, 440V 20 kVA

2-55

Fig. 2-14 External Transformer

Electric equipment generating high frequency noise(Welding machine,

high frequency dryer, anti-electric processor) shall use a separated

distributing board or install another distributing board to be apart more

than 20 m.

When the voltage exceeds the allowance or fluctuate too much, a

constant voltage equipment is required. If equipment like welding

machine is to be contacted to the power line, excessive noise may be

generated and cause machine malfunction. Separated those equipment

from machine power line.

2-56

3. Connection of power line

Before installation and work, read following precaution and perform the work.

Connect power line after equipment is completely installed. After verify that main power switch

of equipment (QF1: adjacent in door section or side section of control panel or transformer),

connect the machine to main power switch firstly.

At this time, terminal for grounding exists around main power switch. After connecting firstly

using specified ground wire to prevent equipment and person from electrical shock and

contact according with L01, L02, L03 sequence.

For opposite power line, after check that 3 phases voltage and setting voltage is matched in

user’s facility power inlet (distribution power panel), if it is not fault, connect PE, L01, L02, L03

sequences with breaker for distribution power panel is switched Off.

In additional, Check that each of phase is correctly connected with Phase Detector to match

phase sequence of 3 phases.

• Power inlet sequence for machine

Enter according with facility distribution power panel breaker ON → Main switch ON →

Operation panel power switch ON sequences.

If 3 phases, 4 lines power connection, power connection is different according with supply

voltage of equipment, In this case, contact to our electrical technician and then install it.

• Supply the power and then operate the machine after following is checked.

After power supply, with operation panel power switch ON, if indication of machine lubricating

Gauge is not reached to normal pressure (motor is rotating), phase of supply power is

changed and check that phase of applicable power and main power line is changed after

power shut off.

• This machine is applied TN power line system,

• TT Power line system must be applied ELB

• If you want ELB(Earth Leackage Braker) you can purchase

• Please check the earh line(PE) every 6 month

• If you move the machine, You must check the earth line(PE)

2-57

4.1 Table

1. KH50G

Fig 2-15 Table (KH50G)

2-58

2. KH63G

Fig 2-15 Table (KH63G)

2-59

4.2 Tool Shank (BT50)

Fig 2-16 Tool Shank (BT50)