4.1 table 2-57 - productivity inc
TRANSCRIPT
1 Specification ............................................................................... 2-1
1.1 Machine Part and Name ........................................................... 2-1
1.2 Machine Specification ............................................................... 2-2
1.2.1 Standard and Option Accessories ....................................2-6
1.3 Spindle Speed-Power Diagram ................................................ 2-11
1.4 Principal Dimensional Drawings .............................................. 2-13
1.4.1 External Dimensions ...................................................... 2-13
1.4.2 Axis Stroke and Reference Point ................................... 2-15
1.4.3 Relationship Between Workpiece and ATC ..................... 2-17
2 Transports and Installation ........................................................ 2-21
2.1 Preparation Items before Installing .......................................... 2-21
2.1.1 Foundation work ............................................................ 2-23
2.1.2 Foundation area ............................................................ 2-25
2.2 Process of Machine Installation .............................................. 2-34
2.3 Transport ............................................................................... 2-35
2.3.1 Instruction ..................................................................... 2-35
2.3.2 Transportation method using crane ............................... 2-36
2.3.3 Transportation method using forklift .............................. 2-39
2.4 Machinery Package and Disassemblies .................................. 2-41
2.5 CHIP CONVEYOR .................................................................... 2-43
3 Leveling and Electric device ..................................................... 2-46
3.1 Leveling ................................................................................. 2-46
3.2 Electric device ....................................................................... 2-48
3.2.1 Grounding ..................................................................... 2-48
3.2.2 Check for power supply ............................................... 2-52
3.2.3 Check before operation ................................................ 2-52
3.2.4 Connecting Main Power ................................................ 2-53
4.1 Table ..................................................................................... 2-57
4.2 Tool Shank (BT50) ................................................................. 2-59
2-2
1.2 Machine Specification
1. KH50G
Table 2-1 Machine Specification
Item Unit KH50G (option)
Table
Table Size mm 500 × 500
Maximum Load Capacity kgf 2 - 800
Maximum Working Size mm ø900 × H780
Min. Indexing Angle. deg 1˚ [0.001˚]
Spindle
Spindle Taper - NT #50
SP. Speed (rpm) r/min 20 ~ 4500 [8000]
Spindle Motor Output (Max./Cont.) kW(HP) 18.5/15 [22/18.5]
Spindle Torque (Max./Cont.) N·m 901/730 [1071/901]
Spindle Driving Method - 2 Step Gear
Feed
Travel (X/Y/Z axis) mm 760/705/650
Distance from Column to SP. center mm 0 ~ 705
Distance from Table Surface to Sp mm 135 ~ 785
Rapid Feed Rate (X/Y/Z) m/min 20/20/20
Cutting Feed Rate (X/Y/Z) m/min 5
Slide Type - Box Guide
ATC
Number of Tools EA 40 [60, 90, 120]
Tool Shank - BT50
Max. Tool Dia. (W.T/W.O) mm ø110 / ø245
Max. Tool Length mm 400
Max. Tool Weight kg 20 [35]
Tool Selection Method - Fixed Address
Tool Change Time T-T sec 5.5
C-C sec 9
APC
No. of Pallet EA 2
APC Change Time sec 16
Table Type - SHUTTLE
2-3
Table 2-1 Machine Specification (continue)
Item Unit KH50G (option)
Tank
Capacity
Coolant Tank ℓ 400
Lubricating Tank ℓ 3.4
Power
Supply
Spindle Cooling Unit ℓ 60
Air Consumption (0.5MPa) ℓ/min 300
Electric Power Supply KVA 40
Thickness of Power Cable Sq Over 25
Voltage V/Hz 220 / 60(200 / 50)
Machine
Floor Space (L×W) mm 2890 × 4340
Height mm 3076
Weight kg 12000
Specifications are subject to change for improvement without notice.
2-4
2. KH63G
Table 2-1 Machine Specification
Item Unit KH63G (option)
Table
Table Size mm 630 × 630
Maximum Load Capacity kgf 2 - 1000
Maximum Working Size mm ø1120 × H875
Min. Indexing Angle. deg 1˚ [0.001˚]
Spindle
Spindle Taper - NT #50
SP. Speed (rpm) r/min 20 ~ 4500 [8000]
Spindle Motor Output (Max./Cont.) kW(HP) 22/18.5 [26/22]
Spindle Torque (Max./Cont.) N·m 1071/901 [1267/1071]
Spindle Driving Method - 2 Step Gear
Feed
Travel (X/Y/Z axis) mm 950/825/760
Distance from Column to SP. center mm 0 ~ 825
Distance from Table Surface to Sp mm 175 ~ 935
Rapid Feed Rate (X/Y/Z) m/min 20/20/20
Cutting Feed Rate (X/Y/Z) m/min 5
Slide Type - Box Guide
ATC
Number of Tools EA 40 [60, 90, 120]
Tool Shank - BT50
Max. Tool Dia. (W.T/W.O) mm ø110 / ø245
Max. Tool Length mm 600
Max. Tool Weight kg 20 [35]
Tool Selection Method - Fixed Address
Tool Change Time T-T sec 5.5
C-C sec 9
APC
No. of Pallet EA 2
APC Change Time sec 16
Table Type - SHUTTLE
2-5
Table 2-1 Machine Specification (continue)
Item Unit KH63G (option)
Tank
Capacity
Coolant Tank ℓ(gel) 400
Lubricating Tank ℓ(gel) 3.4
Power
Supply
Spindle Cooling Unit ℓ(gel) 60
Air Consumption (0.5MPa) ℓ/min 300
Electric Power Supply KVA 40
Thickness of Power Cable Sq Over 25
Voltage V/Hz 220 / 60(200 / 50)
Machine
Floor Space (L×W) mm(in) 3225 × 4820
Height mm(in) 3106
Weight kg(lb) 14000
Specifications are subject to change for improvement without notice.
2-6
1.2.1 Standard and Option Accessories
: Standard : Option : Prior Consultation X : Non Application - : Impossible
Table 2-2 Standard and Option Accessories
ITEM Remark KH50G KH63G
Spindle
4500rpm(18.5/15kW) GEAR(2STEP) -
4500rpm(22/18.5kW) GEAR(2STEP)
4500rpm(26/22kW) GEAR(2STEP) -
8000rpm(18.5/15kW) GEAR(2STEP) -
8000rpm(22/18.5kW) GEAR(2STEP)
8000rpm(26/22kW) GEAR(2STEP) -
Spindle Cooling System
ATC
ATC Extension
40
60
90
120
Tool Shank Type BT50
Heavy Weight Tool 20 kg
35 kg
U-Center D'andrea
STUD BOLT
COLLET Change
45 。
60 。
90 。
Servo Motor Magazine
Table & Column
APC SHUTTLE
TAP TYPE Pallet
T-SLOT Pallet
B-Axis Table 1。
0.001。
2-7
Table 2-2 Standard and Option Accessories (continue)
ITEM Remark KH50G KH63G
Coolant System
Std. Coolant (Nozzle)
Spindle Thru Coolant
5 bar - -
20 bar
30 bar
70 bar, 15L
70 bar, 30L
Jet Coolant
Gun Coolant
Side Oil Hole Coolant
Air Gun
Spindle Air Blow
Tool Measuring Air Blow (Only for TLM)
Air Blow for Automation
Thru MQL Device (Without MQL)
Coolant Chiller
Power Coolant System (For Automation)
Chip Disposal
Coolant Tank 400 ℓ
Cabin Screw Chip Conveyor
Chip Conveyor
(Hinge/Scraper)
Left (Front)
Left(Rear)
Special Chip Conveyor (Drum Filter)
Chip Box
Std.(180L)
Swing(200L)
Large Size(330L)
Customized
Safety Device
APC Splash Guard
Total Splash Guard
2-8
Table 2-2 Standard and Option Accessories (continue)
ITEM Remark KH50G KH63G
Software
Machine Guidance
HWTM
DNC Software
Dialogue Program
Tool ID Manager
Spindle Heat Distortion
Compensation
Spindle Warm up Function
Electric Device
Call Light 1 Color:
Call Light 3 Color:
Call Light & Buzzer 3 Color: B
Work Light
Electric Cabinet Light
Door Inter-Lock
Remote MPG
3-axis MPG
Spindle Load Meter LED TYPE
Spindle RPM Meter LED TYPE
Work Counter Digital
Total Counter Digital
Tool Counter Digital
Multi Tool Counter 6 EA
9 EA
Electric Circuit Breaker
AVR(Auto Voltage Regulator)
Transformer & Cable 35 kVA
Flash Memory Card
Auto Power Off
Back up Module for Black out
2-9
Table 2-2 Standard and Option Accessories (continue)
ITEM Remark KH50G KH63G
Measuring Device
Air Zero TACO
SMC
Work Measuring Device
TLM
Marposs/Renishaw/Bloom
Touch
Laser
Tool Broken Detective Device
Linear Scale X/Y/Z-axis
Rotary Scale B-axis
Pallet Close Confirmation Device
Coolant Level Sensor Only for Chip Conveyor
Environment
Air Conditioner
Dehumidifier
Oil Mist Collector
Oil Skimmer Only for Chip Conveyor
MQL
Fixture & Automation
Sub Operation Panel
Control of Additional Axis 1 axis/Pallet
External M code 4ea
Automation Interface
I/O Extension (In & Out) 16Contact
32Contact
PPL(6PPL)
2-10
Table 2-2 Standard and Option Accessories (continue)
ITEM Remark KH50G KH63G
Hyd. Device
Std. Hyd. Unit 45 bar/60 ℓ
Center Type Hyd. Supply Unit
(Upper) 2x4(8 Port)
Manual Coupler 2x3(4 Port)
Auto Coupler
Hyd. Unit for Fixture
45 bar
70 bar
100 bar
Customized
ETC
Tool Box
Customized Color Need for Munsel NO.
CAD&CAM Software
AIR Lift Slide Method Z-axis
The specifications as above will only serve as a reference
2-11
1.3 Spindle Speed-Power Diagram
1. KH50G (4500 rpm)
Fig. 2-2 Spindle Speed-Power Diagram
2. KH50G (8000 rpm)
Fig. 2-2 Spindle Speed-Power Diagram
2-12
3. KH63G (4500 rpm)
Fig. 2-2 Spindle Speed-Power Diagram
4. KH63G (8000 rpm)
Fig. 2-2 Spindle Speed-Power Diagram
2-13
1.4 Principal Dimensional Drawings
1.4.1 External Dimensions
Fig. 2-3 Principal Dimensional Drawings (KH50G)
2-17
1.4.3 Relationship Between Workpiece and ATC
Fig. 2-5 Relationship Between Workpiece and ATC (KH50G)
2-18
Fig. 2-5 Relationship Between Workpiece and ATC (KH50G)
Du
rin
g A
TC
op
era
tion
, th
ere
is
no
in
terf
ere
nce
be
twe
en
the
ma
chin
e an
d t
oo
l. H
ow
eve
r, a
pa
rtic
ula
r w
ork
pie
ce m
ay
inte
rfe
re w
ith th
e m
ach
ine ;
it d
ep
end
s up
on
th
e too
l sh
ape
.
Th
e a
bo
ve d
iag
ram
sho
ws
that
the
la
rge
st w
ork
pie
ce i
s p
lace
d o
n t
he p
alle
t a
t X
-axis
+ d
ire
ctio
n s
tro
ke a
nd t
he t
oo
l is
rep
lace
d w
ith t
he
la
rge
st t
oo
l. T
hen
, th
e a
rea s
had
ed
with s
lan
ted l
ine
s in
terf
ere
with
th
e w
ork
pie
ce.
Whe
n r
ep
laci
ng
too
ls,
be
su
re tha
t n
o t
oo
l inte
rfe
res
with
th
e w
ork
pie
ce.
2-21
2 Transports and Installation
2.1 Preparation Items before Installing
• Before installing the machine, read and understand the safety notice
thoroughly in this manual.
• While installing, there should be no oil or water on the floor to prevent
the workers from slipping.
• Before working, check again it is installed at a proper place.
1. Installation Conditions
(1) The following places are favorable to install the machine.
a. The place without condensing and dewiness due to the temperature change
b. The place with an even and resistant surface
c. The place with stable utility supply and maintenance
d. The place where the machine can be easily relocated
e. The place without the danger of fire or explosion
(2) The following shall be avoided.
a. The place with direct ray of light, near heating elements, with too much temperature
change.
b. The place with excessive dust and moist
c. The place near vibrating machines
d. The place with weak ground
e. The place with uneven or slide ground
• When there has to be a vibrating machine nearby, some kind of a
vibration absorber shall be placed around the machine.
• If special options are attached on the machine, the space for
maintenance shall be insured.
2-22
2. Installation Environment
Table 2-4. Installation Environment
Classification Contents
Temperature 0 ~45 Celsius shall be maintained
Humidity 10 %~75% RH
Space Additional space at least of 600mm around the machine for maintenance
and repair
Light lighting facility of at least 300 Lux
Purity Better than Class 100
Noise Lower than 70 dB(A)
Temperature of Storage -20 ~ +65
Install the air supply with the air dryer because a machine may be
damaged when the air contains much humidity or the air is not.
3. Notes in using (NC)
This equipment is a CNC that the inside of control panel consists of various electronic
control units. In order to use it effectively, should use the basic knowledge for PC. In
addition, there is a safety unit so as to protect against the external shock or burn out, but
note that the failure can be caused by an excessive shock.
2-23
2.1.1 Foundation work
1. without using Foundation Bolt
(1) Put the leveling seat at the place shown in foundation diagram.
(2) After inserting the leveling bolt in the machine, put it above the leveling seat with about
10 mm distance from the upper side of leveling seat.
(3) Adjust the leveling bolt, set the level of machine correctly and then tighten the leveling
nut.
2. Using Foundation Bolt (optional)
(1) Place the machine at the place to be installed and perform the 1st leveling work. If the
leveling seat is out of its position or it is impossible to adjust it with the leveling bolt due
to poor foundation, use a wedge to do a leveling work.
(2) After completion on the first leveling work, insert the foundation bolt from the bottom of
machine and install it to the machine using nuts.
(3) Fill the mortar up to the bottom and the side of leveling seat and stir it with a bar.
(4) Adjust the leveling bolt, complete leveling work in all sides, and then engage the
foundation bolt tightly.
2-25
2.1.2 Foundation area
Table 2-4 Foundation area
No. Model Name ATC OPTION Remark
1
KH50G
40 Tools
2 60 Tools
3 90 Tools
4 120 Tools
5
KH63G
40 Tools
6 60 Tools
7 90 Tools
8 120 Tools
2-34
2.2 Process of Machine Installation
The following process shall be observed.
1. Move the machine to the location to be installed.
2. Remove all the wrapping material covering the machine.
3. Assemble additional parts to the main body.
4. Connect the power cable.
5. Turn on the main power switch on the right side of Control box.
6. Turn right the Emergency Stop switch to release. It is on the control panel on the machine
front.
7. Turn the Operate/Stop switch to toward operate. It is on the control panel.
8. The preparation process of the machine operation has been finished.
2-35
2.3 Transport
2.3.1 Instruction
1. The Machine is consisted of 3 kinds of main elements, such as machine body, control
panel, hydraulic unit and each of wiring and hydraulic piping is connected. Also, all units
are attached to machine body and machine is not disassembled and can move to
desired distance.
2. There are 2 types, such as crane and forklift for moving method.
3. If installation is performed according with this operation manual, can obtain machine
precision of desired product.
• When transporting the machine, be careful not to crane with other
objects.
• Never stand or walk under highly-lifted machine.
• When machine is transported, pay attention that your body part does
not inserted.
• Prior to transporting the machine, check each part of the machine is
properly fixed to each other.
• When lifting the machine, slowly do a job, ensuring a full balance.
• Be careful not to give a shock to the body of machine, the Electric
Control Panel, and other electric devices.
• Transport the coolant tank after removing it from the body of machine.
• Before machine is transported, check that already installed machine
dose not interfered. If sufficient space is not distributed, contact to
responsible person of factory and rearrange the machine or remove
safety. If you do not remove it, provide the attention to worker and
obtain the safety.
2-36
2.3.2 Transportation method using crane
1. Horizontal level should be maintained during transportation, if some case.
2. The machine shall not move by fixing securely it to transportation device.
3. As Top hook of machine is damaged by contact of wire rope, it should be transported by
providing the cloths (protective cloths).
4. If you lift the machine, slowly lift as possible as and verify that the wire rope and the
machine is a level again by temporarily stopping at a falling moment
5. As shown in the figure, after lifting the machine by engaging the wire rope to hook on top
of machine, it should be moved to designated area.
6. Verify following items, when you work.
(1) Adjust the center by moving the saddle table so that center of machine load can be
position to lifting fixture, and lower the main spindle head to the lowest bottom in order
to lower the gravity of center as possible as.
(2) Using load of crane and Wire capacity is follows as.
a. KH50G (Crane: 18 t)
Machine ATC Weight(t) Wire A Wire B Wire C
40 PCS ATC ATTACHED 13.5 Ø22×4.00 m Ø22×4.00 m Ø22×8.25 m
60 PCS ATC ATTACHED 14.1 Ø22×4.00 m Ø22×4.00 m Ø22×8.25 m
90 PCS ATC ATTACHED 15.0 Ø22×3.96 m Ø22×4.00 m Ø22×8.50 m
120 PCS ATC UNATTACHED 11.9 Ø22×4.10 m Ø22×4.00 m Ø22×8.00 m
b. KH63G (Crane: 25.95 t)
Machine ATC Weight(t) Wire A Wire B Wire C
40 PCS ATC ATTACHED 14.5 Ø24×4.50 m Ø24×4.50 m Ø24×10.00 m
60 PCS ATC ATTACHED 15.1 Ø24×4.50 m Ø24×4.50 m Ø24×10.20 m
90 PCS ATC ATTACHED 16.0 Ø24×3.96 m Ø24×4.00 m Ø24×9.40 m
120 PCS ATC UNATTACHED 12.9 Ø22×4.50 m Ø22×4.50 m Ø24×10.00 m
2-38
• With the machine lifted slightly, check all sides for balance and the
rope is reached to the cover or other parts.
• When more than 2 persons have to lift the machine, they should work
together, communicating each other.
• Do not use rusty or shorted wire ropes.
• When lifting the machine, slowly do a job. If the wire rope is tightened,
temporarily stop and check an eye bolt is clamped and then lift up to
the desired height.
• When pulling down, also do it slowly. Just before reached the floor,
stop it and check the position and then pull down completely.
• Only the experienced-personnel should perform a crane work.
2741-69-301-00
HOOK (R)
2741-69-302-00
HOOK (L)
2-39
2.3.3 Transportation method using forklift
• Only who has the forklift driver's license can convey the machine by
forklift.
• To avoid damage around the protruded part of machine, the task
should be performed by two persons, of which one is a supervisor.
• Put down the machine slowly not to give a shock on the floor.
• Hold wood between the forklift and the machine for lifting.
Fig. 2-9. Transportation method using forklift
2-40
Fig. 2-10. Fork position
Only who has the forklift driver's license can convey the machine by
forklift.
To avoid damage around the protruded part of machine, the task
should be performed by two persons, of which one is a supervisor.
Put down the machine slowly not to give a shock on the floor.
Hold wood between the forklift and the machine for lifting.
Fork Position
2-41
2.4 Machinery Package and Disassemblies
This paragraph describes how to packing and unpacking the machine before and after
shipment as well as the precautions and other necessary information for users.
As any damage or error to the machine may occur without correct packing and unpacking of
the machine are made, the users must fully understand how to packing and unpacking the
machine described below.
This paragraph describes how to packing and unpacking the machine before and after
shipment as well as the precautions and other necessary information for users.
As any damage or error to the machine may occur without correct packing and unpacking of
the machine are made, the users must fully understand how to packing and unpacking the
machine described below.
1. MACHINERY PACKAGING
(1) Machinery must be cleaned before packaging and the process must be conducted
inside the clean room.
(2) Use tape or rope to fix machinery to prevent machinery from rotation or spin.
(3) Appropriate amount of damp-proof material must be included with machinery during
packaging process to prevent damp build-up.
(4) Machinery should be packed at least 2 times, using an Air Wrap to prevent exterior
entry of air & resin and shock.
(5) The person in charge of machinery packaging must select appropriate packaging type
for machinery packaging.
(6) When machinery requires wooden packaging, consult packaging specialists for
packaging process.
(7) After packaging, appropriate number should be recorded on the box exterior for
distinction.
(8) Warning and precaution stickers must be attached to the packaging box exterior and
followed during delivery process.
(9) Machinery must be packed once by plastic then again by packaging wrap.
2-42
2. DISASSEMBLE PACKAGING
(1) This machinery is Air Wrapped from factory as one piece when it is sent out.
(2) Wooden safety frame must be removed.
(3) When packaged machinery is delivered, un-pack immediately to check and assure
system damage didn’t occur during delivery process.
(4) Machinery damage inspection list is as follows;
a. Check damage including imprints on machinery exterior
b. Check safety cover for damage
(5) Take particular care during un-packaging process as damage could occur on
machinery if packaged machinery is dropped.
(6) If there is no machinery damage, check to assure all items listed in packing list is
included and provided
2-43
2.5 CHIP CONVEYOR
1 Installation
(1) chip conveyor is, in principle, designed to be used indoors. please consult with manu-
facture for supplement if chip conveyor shall be used outdoors.
(2) install geared motor horizontally.
(3) fix firmly to avoid vibration during operation.
(4) load/unload the chip conveyor with cranes using a rope.(do not use forklifts and other
transportation equipment except cranes.)
(5) when loading/unloading the chip conveyor, fix the rope to the lifting lug firmly.
(6) when transporting the chip conveyor, fix it firmly to avoid swing during transportation.
(7) install the conveyor inside a machine or fix it on the factory floor, and fix the level bolt
on the floor.
2. Operation Precautions
(1) chip conveyor is delivered after a thorough test run. however, please check the take-
up adjustment bolt during installation if the bolts are loosened during transportation.
check also the chain belt looseness.
(2) check and remove foreign materials from the conveyor belts.
(3) check the direction of rotation of the belt when start run switch is on.
(4) operate conveyor while machine tools discharge chips.
(5) always check it noese and heat in geared motor, rotation and electric current
(6) pay attention during oiling so that the friction plate of a torque limit may not be stained
with oil.
(7) always check it the chain tension of main and driving is normal.
(8) when operating the chip conveyor after long-time suspension, make sure a lot of chips
may not flow in and then operate it.
(9) do not remove the dog of a torque limit.
(Limit switch Attaching type: As Option is applied, standard is not applied.)
2-45
Table 2-5 Lists of parts
No. NAME No. NAME
1 BODY 21 TAKE UP FRAME
2 GEARED MOTOR 22 BEARING
3 KEY 23 ADJUSTING BOLT
4 COVER 24 COVER
5 SPROCKET WHEEL 25 BOLT
6 SET SCREW 26 BOLT
7 ROLLER CHAIN (DRIVING) 27 SPRING WASHER
8 BOLT 28 NUT
9 WASHER 29 HINGE PLATE
10 TORQUE LIMIT UNIT 30 PIN
10A HOUSING 31 SIDE PLATE
10B LINING(FRICTION PLATE) 32 SIDE PLATE-ROLLER CHAIN
10C SPROCKET WHEEL 33 ROLLER-ROLLER CHAIN (MAIN)
10D BEARING 34 WASHER
10E COLLAR 35 SPLIT PIN
10F CONE SPRING 36 WHEEL SHAFT
10G NUT 37 DU BUSH
10H SET SCREW 38 WHEEL
11 BOLT 39 WASHER
12 REAR COVER 40 BOLT
13 DRIVE SHAFT A-1 SCRAPER
14 KEY A-2 ROLLER CHAIN (MAIN)
15 KEY A-3 WASHER
16 KEY A-4 BOLT
17 SPROCKET WHEEL
18 SET SCREW
19 SPROCKET WHEEL
20 SET SCREW
2-46
3 Leveling and Electric device
3.1 Leveling
Leveling is the No.1 factor determining the accuracy of machine.
To level the machine is the most basic operation to have influence on the owrkpiece and the
life span of machine.
First, place machine on the levelling sheet, and then align the levelling bolt on machine and
lower it in position.
The level gauge suited for this use is that has the sensitivity scale of 0.02 mm per in.(The
length of level gauge is 200 mm). Do not use the level gauge used in construction field.
Handle level gauge so that each end maintains same direction.
The surface where level gauge is placed should be clean and free from any dust.
Adjust the on the center of table as follows so that the horizontal reading does not differ from
the longitudinal reading by more than 0.04 mm/m.
When fis the levelling bolt, be careful not to be loosen it.
Foundation bolts may be used for fixing if mechanical vibration rises now and then due to
ununiform work or intermittent cutting.
Check the level every day for 2~3 days from the installation. Then check it every month for six
months from installation, and every three months thereafter.
2-48
3.2 Electric device
3.2.1 Grounding
Only authorized engineer can do earth working. Failure to comply may
result in personal severe injury, death, or accident.
1. All electric devices should be grounded to prevent personal injury and misoperation of the
machine according to the specification, after installed.
2. Select the grounding point as close to the machine as possible and perform wiring
independently.
3. Do the third-class grounding only by the authorized engineer.
- Grounding resistance : under 100 Ω
- Thickness of wire
- Measuring device : 500 V Megger
Table 2-7. Thickness of wire
Wire area S mm2 for power supply Min. area Sp mm2 of ground wire
S ≤16
16 < S ≤ 35
S > 35
S
16
S/2
2-49
(1) Grounding Method
The machine should be grounded by one of the following methods.
a. Individual grounding
Fig 2-10 Individual grounding
2-50
b. Common grounding
The grounding line of each machine should be grounded at its ground terminal
directly. (Only one line to one terminal)
Fig. 2-11 Common grounding
Grounding resistance =
100
Ω Number of
machine
2-52
3.2.2 Check for power supply
The equipment is delivered under our strict Q.C, but in case of state before delivery is not
maintain to 100% by vibration during transportation for long time and temperature change,
occurs. Equipment installer verify following check before power supply and then supply the
power.
1. Checks before power supply
(1) Verification for assembled state of each of parts in control panel (part loosing).
(2) Verification for assembled state of assembled connector in control panel and unite.
(3) Check and supplement whether assembled wire is loosen of Terminal Block
(4) Check setting current value of Breaker for protecting Motor (Check that it is met to
Marking section)
(5) Check that connector assembled to control panel, is screwed.
(6) Check other general motor connection wire and signal and power connector of Servo /
Spindle Motor is assembled.
(7) Check joint section of hose connection (hydraulic/cutting oil/pneumatic) for machine
section.
(8) Check (RED Colored Bracket) separation of each of fixture (X, Y, Z axis, for lathe, X, Z
axis)
3.2.3 Check before operation
1. Before operation, read install and operation manual supplied from our company and
operate according with indicated method.
2. To operate safely, machine purchaser direct that only employees trained in basic handling
course, are operated machine.
3. After supplying main power, check that main parts of machine are leaked, while the
machine keeps normally operated (Machine Ready) status and use after lubrication Unit
is normally lubricated.
2-53
3.2.4 Connecting Main Power
Fig. 2-17. Connecting Main Power
1. Power Switch
Install other machines with the independent power switches at the place where easy to
open and close. See the following table for the capacity of fuse.
Table 2-8. Fuse Capacity and Available Wire
Model Power capacity
(kVA)
Available Wire [²] Fuse [A]
L01, L02, L03 Grounding Line
KH50G 40 38 19 125
KH63G 40 38 19 125
2-54
2. Changing Electric Units According to Voltage and Frequency
According to the voltage and frequency of the power of factory, it needs to change the
setting of electric applications. Prior to changing, check its voltage and frequency.
Power Voltage: 200/220 V±10 %
Power Frequency: 50/60 Hz±1 Hz
• If the voltage fluctuated seriously, it may cause disoperation of the
machine and failure of the electric and electronic parts. Therefore, set
the fluctuating rate not to exceed ±10 %.
(1) Tab Changing for Controlling Transformer
Open the door of the Electric Control Panel, remove the plastic cover of Transformer
and then change the wiring as shown in the following table.
Table 2-9. Voltage
Voltage R2 T2
191~210 V 200 V 0 V
211~240 V 220 V 0 V
(2) External Transformer
Table 2-10. External Transformer (in case of 380V and 400V and 415V, 440V)
Model Voltage - Primary Transformer Capacity
KH50G/63G 380V, 400V, 415V, 440V 20 kVA
2-55
Fig. 2-14 External Transformer
Electric equipment generating high frequency noise(Welding machine,
high frequency dryer, anti-electric processor) shall use a separated
distributing board or install another distributing board to be apart more
than 20 m.
When the voltage exceeds the allowance or fluctuate too much, a
constant voltage equipment is required. If equipment like welding
machine is to be contacted to the power line, excessive noise may be
generated and cause machine malfunction. Separated those equipment
from machine power line.
2-56
3. Connection of power line
Before installation and work, read following precaution and perform the work.
Connect power line after equipment is completely installed. After verify that main power switch
of equipment (QF1: adjacent in door section or side section of control panel or transformer),
connect the machine to main power switch firstly.
At this time, terminal for grounding exists around main power switch. After connecting firstly
using specified ground wire to prevent equipment and person from electrical shock and
contact according with L01, L02, L03 sequence.
For opposite power line, after check that 3 phases voltage and setting voltage is matched in
user’s facility power inlet (distribution power panel), if it is not fault, connect PE, L01, L02, L03
sequences with breaker for distribution power panel is switched Off.
In additional, Check that each of phase is correctly connected with Phase Detector to match
phase sequence of 3 phases.
• Power inlet sequence for machine
Enter according with facility distribution power panel breaker ON → Main switch ON →
Operation panel power switch ON sequences.
If 3 phases, 4 lines power connection, power connection is different according with supply
voltage of equipment, In this case, contact to our electrical technician and then install it.
• Supply the power and then operate the machine after following is checked.
After power supply, with operation panel power switch ON, if indication of machine lubricating
Gauge is not reached to normal pressure (motor is rotating), phase of supply power is
changed and check that phase of applicable power and main power line is changed after
power shut off.
• This machine is applied TN power line system,
• TT Power line system must be applied ELB
• If you want ELB(Earth Leackage Braker) you can purchase
• Please check the earh line(PE) every 6 month
• If you move the machine, You must check the earth line(PE)