CONTRACTOR

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 1 of 4

A/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

1jPlant Operations FM Design Chart 6.2.11

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-12

D-11PM coordinates furniture plan & room numbering

D-1Pre-design meeting held to discuss

contract deliverables

D-4Design team

produces 90-95% SD’s and submits

for review

D-7Design team incor-porates comments into 100% SD & updates estimate

D-3Design team

develops schematic design

D-9PM authorizes design team to start DD docs

D-6PM confirms docs comply

with the intent of the program

D-5PM distributes SD docs for review and comment by the Project team

D-8PM and client approve schematic design documents

D-10Design develops

design

SELECTION OF DESIGN TEAM

(RFQ)

SELECTION OF DESIGN TEAM

(CSA)

D-2Project Charter

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 2 of 4

1jPlant Operations FM Design Chart 2.17.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-26

Y

N

From D-11

D-13PM receives and distributes DD docs for review

D-12Design team

produces 50% DD’s and submits

for review

D-20PM authorizes design team continue DD

docs

D-15PM confirms docs comply

with the intent & standards

D-14Project team reviews documents and comments

D-19PM, ED, user and client review design development documents, as required

D-22PM receives and distributes DD docs for review

D-21Design team

produces 90-95% DD’s and submits

for review

D-25Design team incor-porates comments into 90-95% DD’s & prepares estimate

D-24PM confirms docs comply

with the intent & standards

D-23Project team reviews documents and comments

Does CFPC

approve?

D-16Design team incorporates

comments into 50% DD’s

D-17PM sends to

CFPC for ExteriorArchitectural

Approval

D-18Design team

incorporates CFPC comments into

50% DD’s

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 3 of 4

1jPlant Operations FM Design Chart 2.17.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-39

D-30PM receives and distributes CD docs for review

D-29Design team

produces 50% CD’s and submits

for review

D-33Design team incorporates

comments into 50% CD’s

D-35PM authorizes design team continue CD’s

D-32PM confirms docs comply

with the intent & standards

D-31Project team reviews documents and comments

D-34PM, ED, user and client review construction documents, as required

D-37PM receives and distributes CD docs for review

D-36Design team

produces 90-95% CD’s and submits

for review

D-38Project team reviews documents and comments

D-27PM authorizes design team to

start CD’s

D-28Project team develops construction documents

From D-25

D-26PM, ED, user and client review design development documents, as required

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 4 of 4

1jPlant Operations FM Design Chart 2.17.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

&/or

D-41PM, ED, User and Client review approve construction documents

TO PROCUREMENT

OF OWNER PROVIDED SERVICES

TO FORMAL CONTRACTOR

CSP SELECTION(BID)

TO CONTRACTOR

RFP SELECTION

TO JOC PROCUREMENT

OF CONTRACTOR

TO INFORMAL CONTRACTOR

CSP SELECTION(3 Informal Bids)

From D-38

D-40Design team incor-porates comments

into 100% CD’s

D-39PM confirms docs comply

with the intent of the program

Page 2: 4-Step 4 FM Design (1 of 4) -rev 3 · contractor step 4: facilities management design process page 1 of 4 a/e and other consultants evp admin & finance/ plant operations plant operations

CONTRACTOR

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 1 of 4

A/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

1jPlant Operations FM Design Chart 6.2.11

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-13

D-12Facilities Information Services develops furniture plan & room numbering

D-1Pre-design meeting held to discuss

contract deliverables

D-5PM receives and distributes SD docs for review

D-4Design team

produces 90-95% SD’s and submits

for review

D-8Design team incor-porates comments into 100% SD &

prepares estimate

D-3Project team develops schematic design

D-10PM authorizes design team to start DD docs

D-7PM confirms docs comply

with the intent of the program

D-6Project team reviews documents and comments

D-9PM, ED, User and client approve schematic design documents

D-11Project team develops design development

documents

SELECTION OF DESIGN TEAM

(RFQ)

SELECTION OF DESIGN TEAM

(CSA)

D-2Project Charter

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 2 of 4

1jPlant Operations FM Design Chart 6.2.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-23

Y

N

From D-11

D-12Design team

produces 50% DD’s and submits

for review

D-18PM authorizes design team continue DD

docs

D-14PM confirms docs comply

with the intent & standards

D-17PM and client review design development documents, as required

D-19Design team

produces 90-95% DD’s and submits

for review

D-22Design team incor-porates comments into 90-95% DD’s & updates estimate

D-21PM confirms docs comply

with the intent & standards

Does CFPC

approve?

D-15Design team incorporates

comments into 50% DD’s

D-16PM sends to

CFPC for ExteriorArchitectural

Approval

D-16Design team

incorporates CFPC comments into

50% DD’s

D-13PM distributes SD docs for review and comment by the Project team

D-20PM distributes SD docs for review and comment by the Project team

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 3 of 4

1jPlant Operations FM Design Chart 2.17.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-39

D-30PM receives and distributes CD docs for review

D-29Design team

produces 50% CD’s and submits

for review

D-33Design team incorporates

comments into 50% CD’s

D-35PM authorizes design team continue CD’s

D-32PM confirms docs comply

with the intent & standards

D-31Project team reviews documents and comments

D-34PM, ED, user and client review construction documents, as required

D-37PM receives and distributes CD docs for review

D-36Design team

produces 90-95% CD’s and submits

for review

D-38Project team reviews documents and comments

D-27PM authorizes design team to

start CD’s

D-28Project team develops construction documents

From D-25

D-26PM, ED, user and client review design development documents, as required

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 4 of 4

1jPlant Operations FM Design Chart 2.17.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

&/or

D-41PM, ED, User and Client review approve construction documents

TO PROCUREMENT

OF OWNER PROVIDED SERVICES

TO FORMAL CONTRACTOR

CSP SELECTION(BID)

TO CONTRACTOR

RFP SELECTION

TO JOC PROCUREMENT

OF CONTRACTOR

TO INFORMAL CONTRACTOR

CSP SELECTION(3 Informal Bids)

From D-38

D-40Design team incor-porates comments

into 100% CD’s

D-39PM confirms docs comply

with the intent of the program

Page 3: 4-Step 4 FM Design (1 of 4) -rev 3 · contractor step 4: facilities management design process page 1 of 4 a/e and other consultants evp admin & finance/ plant operations plant operations

CONTRACTOR

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 1 of 4

A/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

1jPlant Operations FM Design Chart 6.2.11

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-13

D-12Facilities Information Services develops furniture plan & room numbering

D-1Pre-design meeting held to discuss

contract deliverables

D-5PM receives and distributes SD docs for review

D-4Design team

produces 90-95% SD’s and submits

for review

D-8Design team incor-porates comments into 100% SD &

prepares estimate

D-3Project team develops schematic design

D-10PM authorizes design team to start DD docs

D-7PM confirms docs comply

with the intent of the program

D-6Project team reviews documents and comments

D-9PM, ED, User and client approve schematic design documents

D-11Project team develops design development

documents

SELECTION OF DESIGN TEAM

(RFQ)

SELECTION OF DESIGN TEAM

(CSA)

D-2Project Charter

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 2 of 4

1jPlant Operations FM Design Chart 6.2.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-27

Y

N

From D-12

D-14PM receives and distributes DD docs for review

D-13Design team

produces 50% DD’s and submits

for review

D-21PM authorizes design team continue DD

docs

D-16PM confirms docs comply

with the intent & standards

D-15Project team reviews documents and comments

D-20PM, ED, user and client review design development documents, as required

D-23PM receives and distributes DD docs for review

D-22Design team

produces 90-95% DD’s and submits

for review

D-26Design team incor-porates comments into 90-95% DD’s & prepares estimate

D-25PM confirms docs comply

with the intent & standards

D-24Project team reviews documents and comments

Does CFPC

approve?

D-17Design team incorporates

comments into 50% DD’s

D-18PM sends to

CFPC for ExteriorArchitectural

Approval

D-19Design team

incorporates CFPC comments into

50% DD’s

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 3 of 4

1jPlant Operations FM Design Chart 6.2.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-34

D-26Design team

produces 50% CD’s and submits

for review

D-29Design team incorporates

comments into 50% CD’s

D-31PM authorizes design team continue CD’s

D-28PM confirms docs comply

with the intent & standards

D-30PM and client review construction documents, as required

D-32Design team

produces 90-95% CD’s and submits

for review

D-24PM authorizes design team to

start CD’s

D-25Design team

develops construction documents

From D-22

D-23PM and client review design development documents, as required

D-27PM distributes SD docs for review and comment by the Project team

D-33PM distributes SD docs for review and comment by the Project team

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 4 of 4

1jPlant Operations FM Design Chart 2.17.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

&/or

D-41PM, ED, User and Client review approve construction documents

TO PROCUREMENT

OF OWNER PROVIDED SERVICES

TO FORMAL CONTRACTOR

CSP SELECTION(BID)

TO CONTRACTOR

RFP SELECTION

TO JOC PROCUREMENT

OF CONTRACTOR

TO INFORMAL CONTRACTOR

CSP SELECTION(3 Informal Bids)

From D-38

D-40Design team incor-porates comments

into 100% CD’s

D-39PM confirms docs comply

with the intent of the program

Page 4: 4-Step 4 FM Design (1 of 4) -rev 3 · contractor step 4: facilities management design process page 1 of 4 a/e and other consultants evp admin & finance/ plant operations plant operations

CONTRACTOR

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 1 of 4

A/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

1jPlant Operations FM Design Chart 6.2.11

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-13

D-12Facilities Information Services develops furniture plan & room numbering

D-1Pre-design meeting held to discuss

contract deliverables

D-5PM receives and distributes SD docs for review

D-4Design team

produces 90-95% SD’s and submits

for review

D-8Design team incor-porates comments into 100% SD &

prepares estimate

D-3Project team develops schematic design

D-10PM authorizes design team to start DD docs

D-7PM confirms docs comply

with the intent of the program

D-6Project team reviews documents and comments

D-9PM, ED, User and client approve schematic design documents

D-11Project team develops design development

documents

SELECTION OF DESIGN TEAM

(RFQ)

SELECTION OF DESIGN TEAM

(CSA)

D-2Project Charter

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 2 of 4

1jPlant Operations FM Design Chart 6.2.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-27

Y

N

From D-12

D-14PM receives and distributes DD docs for review

D-13Design team

produces 50% DD’s and submits

for review

D-21PM authorizes design team continue DD

docs

D-16PM confirms docs comply

with the intent & standards

D-15Project team reviews documents and comments

D-20PM, ED, user and client review design development documents, as required

D-23PM receives and distributes DD docs for review

D-22Design team

produces 90-95% DD’s and submits

for review

D-26Design team incor-porates comments into 90-95% DD’s & prepares estimate

D-25PM confirms docs comply

with the intent & standards

D-24Project team reviews documents and comments

Does CFPC

approve?

D-17Design team incorporates

comments into 50% DD’s

D-18PM sends to

CFPC for ExteriorArchitectural

Approval

D-19Design team

incorporates CFPC comments into

50% DD’s

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 3 of 4

1jPlant Operations FM Design Chart 6.2.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

To D-40

D-31PM receives and distributes CD docs for review

D-30Design team

produces 50% CD’s and submits

for review

D-34Design team incorporates

comments into 50% CD’s

D-36PM authorizes design team continue CD’s

D-33PM confirms docs comply

with the intent & standards

D-32Project team reviews documents and comments

D-35PM, ED, user and client review construction documents, as required

D-38PM receives and distributes CD docs for review

D-37Design team

produces 90-95% CD’s and submits

for review

D-39Project team reviews documents and comments

D-28PM authorizes design team to

start CD’s

D-29Project team develops construction documents

From D-26

D-27PM, ED, user and client review design development documents, as required

STEP 4: FACILITIES MANAGEMENT DESIGN PROCESSPage 4 of 4

1jPlant Operations FM Design Chart 6.2.11

CONTRACTORA/E AND OTHER CONSULTANTS

EVP ADMIN & FINANCE/

PLANT OPERATIONS

UH DEPARTMENTS

SKILLED TRADES AND TECHNICAL

SHOPS

MINOR AND PLANNED PROJECTS

or or

or

Y

N

Y

N

FORMAL COMPETITIVE

SEALED PROPOSAL

(RFP)

FORMALCOMPETITIVE

BID (IFB)

Isproject under

$25k?

JOB ORDER CONTRACTOR PROCUREMENT

INFORMAL BID

Isproject under

$250k?

PROCUREMENT OF OWNER PROVIDED SERVICES

Y

N

Is procurement

of Owner-provided Services required?

D-36PM and Client review approve construction documents

From D-33

D-35Design team incor-porates comments

into 100% CD’s

D-34PM confirms docs comply

with the intent of the program