  • 8/11/2019 4 M&E of Programs and Projects 2

    1/43

    Monitoring & Evaluation

    of

    Programs and Projects

    Nov 5, 2013

  • 8/11/2019 4 M&E of Programs and Projects 2

    2/43

    Setting up an M&E System

  • 8/11/2019 4 M&E of Programs and Projects 2

    3/43

    1. Agree on your M&E

    Framework

    What is M&Edefines the significantterms

    What is M&E for - determines theoperational objectives

    What principles govern M&E

    What will M&E focus onidentifies theareas of concern needed for decisionmaking

    What information are neededidentifies the appropriate period forgathering

    The

    foundationused for

    designing

    the M&Emechanism

  • 8/11/2019 4 M&E of Programs and Projects 2

    4/43

    M & E

    is the continuing and systematic process of

    INFORMATION

    relevant to planning, implementation, andevaluation of programs and projects

    in support of decision making of management and

    key stakeholders to improve delivery of outputs

    and outcomes.

    Collectingdata

    Analyzingdata

    Reporting

  • 8/11/2019 4 M&E of Programs and Projects 2

    5/43

    Purpose of M&E

    The M & E seeks to establish a systematicand continuous process for gathering,

    processing, interpreting, analyzing and storing

    data for management decision towards

    continuous improvement of the

    delivery of education services

    organizational performance

  • 8/11/2019 4 M&E of Programs and Projects 2

    6/43

    M&E Objectives:

    Provide education management with information on the

    implementation status of the Projectfor purposes of making

    decisions in order to improve its efficiencyand effectiveness

    Make information available to school and division

    management to be able to adjustthe approaches and

    strategies being utilized in implementing the project

    Establish information on the achievement ofproject objectivesand its contribution to attainment of school performance

    indicators

    monitoring

    adjustment

    evaluation

  • 8/11/2019 4 M&E of Programs and Projects 2

    7/43

    Operational Objectives

    Provide the division management information on the

    delivery of education services as basis for Technical

    Assistance.

    Provide the division management information on the

    implementation of programs and projects

    Provide the division management information on the

    optimal use of Education Resources for districts and

    schools.

    Provide the division management information on

    division organizational health/ performance to

    improve organizational effectiveness and organizational

    resource support.

  • 8/11/2019 4 M&E of Programs and Projects 2

    8/43

    Governing principles

    Quality of informationappropriate, sufficient and Accurate Efficiency- Results are achieved with minimum input resources but

    not compromising quality and timeliness of information

    Transparency of Information to Key Stakeholders - timely

    disclosure of information and methodology to stakeholders Synergy- encourages participative and collaborative decision-

    making processes among the different

    M&E for Learning and Accountability - providesopportunities for continuous improvement of

    practices/performance

    Focus - calls for careful planning and purposive prioritization ofactivities

  • 8/11/2019 4 M&E of Programs and Projects 2

    9/43

    M&E FOCAL AREAS IN THE REGION

    M&E Content

    Areas

    Support forthe Delivery

    of BasicEducation

    Programs and Projects

    Educational Resource

    DivisionOrganizational

    Health &Performance

    Organizational Effectiveness

    Organizational Resource

    Support

  • 8/11/2019 4 M&E of Programs and Projects 2

    10/43

    M&E FOCAL AREAS IN THE DIVISION

    M&E ContentAreas

    Delivery ofEducational

    Services

    Technical

    Assistance

    SBM Implementationand Assessment

    Curriculum

    Implementation

    Teaching Learning

    And Assessment

    EducationalPrograms and

    Projects

    Educational

    Resources

    DivisionOrganizational

    Health &Performance

    OrganizationalEffectiveness

    Organizational

    Resource Support

  • 8/11/2019 4 M&E of Programs and Projects 2

    11/43

    Project Life Span

    M 1 M 2 M 3 M 4 M 5 M 6 M 7 M 8 M 9 M

    10

    M

    11

    M

    12

    Start End-of

    Project

    WHAT DOES THIS SUGGEST?

  • 8/11/2019 4 M&E of Programs and Projects 2

    12/43

    Hierarchy of M E Task Levels

    M&E TaskLevels

    Progress M&E

    Inputs Outputs

    Result M&E

    IntermediateResults

    Outcomes

  • 8/11/2019 4 M&E of Programs and Projects 2

    13/43

    Adequacy of

    Resources Needed

    to implement the

    program

    e.g. Parents,financial, time,

    No. of

    pupils

    who

    benefit

    theprogram

    Percentage of

    Increase in

    Nutritional

    Status ofPupils

    Percentage of

    :

    Increase

    /decrease of:

    Drop-outFailure

    NAT

  • 8/11/2019 4 M&E of Programs and Projects 2

    14/43

    INTEGRATION OF M&E

    CONTENT AREAS ANDTASK LEVELS

  • 8/11/2019 4 M&E of Programs and Projects 2

    15/43

    Scope of M & E for a

    Project/Program

    EFFICIENCY EFFICIENCY/EFFECTIVENESS EFFECTIVENESSRELEVANCE

    SUSTAINABILITY

    FORMATIVE SUMMATIVE

  • 8/11/2019 4 M&E of Programs and Projects 2

    16/43

    Why monitor project/program implementation?

    implementation?Why monitor?

    (M&E Objective)

    What to monitor?

    (Content / Focal area)1. Provide management with

    information on the status of

    implementation to improve its

    efficiency

    Efficiency of implementation

    Are outputs accomplished as

    planned during the quarter

    Are funds utilized as budgeted ?

    2. Obtain information forimplementers to make adjustment

    Efficiency/ Effectiveness What are the implementation

    issues?

    Is the project improving SBM level

    of practice?

    3. Establish information on the

    achievement of project objectives

    and sustainability of outcomes

    Effectiveness/ Relevance/

    Sustainability

    Are the project objectives

    attained?

    Does the project improve school

    performance indicators?

    What sustainability measures wereapplied?

  • 8/11/2019 4 M&E of Programs and Projects 2

    17/43

    M&E Task Levels & Focus

    Focus

    FORMATIVE SUMMATIVE

    ResultsProgress

    Efficiency

    Status of implementation

    (quantity and time)

    - Rate of Fund Utilization

    - Issues & concerns

    Effectiveness

    Attainment of Project objectives

    End-of-year accomplishments

    Improved SBM level of practice

    Relevance Alignment of results to SIP Objectives;EFA / BESRA Performance indicators

    Sustainability

    Sustainability measures applied in the implementation of SBM-Grant

    project

    Lessons learned to sustain SBM-G Implementation

  • 8/11/2019 4 M&E of Programs and Projects 2

    18/43

    Translating them to M&E questions (SBM-Grant)

    Focus Progress Results

    Efficiency

    Are the project activities

    implemented as planned?

    Are the funds spent as

    proposed?What are the implementation

    issues?

    Effectiveness

    Are the proposal objectives

    attained?

    Did the project help advance SBM ?

    RelevanceDid the project contribute to SIP

    objectives? EFA/BESRA goals

    SustainabilityWhat strategies were employed to sustain the project?

    What good practices from the project can be mainstreamed?

  • 8/11/2019 4 M&E of Programs and Projects 2

    19/43

    M&E System: What it requires

    PROCESSES

    STRUCTURE-

    TOOLS

    Technologies/methodologies ( datacollection, processing & analysis,

    reporting, etc)

    People who will execute theprocesses

    Instruments/ Templates that will assist

    the concerned personnel perform theprocesses

  • 8/11/2019 4 M&E of Programs and Projects 2

    20/43

    Setting Up an M & E System

    Step 1Organize

    Division M&ETeam and clarify

    terms of

    reference

    Step 2DM&E to identify

    the scope of theM&E (Content Areasand Tools) as givenin the framework.

    Step 3Specify theinformation

    requirementsand set-up the

    monitoring plan

  • 8/11/2019 4 M&E of Programs and Projects 2

    21/43

    TA Plan TA Plan

    SUGGESTEDM&E STRUCTUREANDCOMMUNICATION

    FLOWFORSBM GRANTIMPLEMENTATION

    Reporting & Feedbacking

    School

    QMT

    School

    QMT

    School

    QMT

    School

    QMT

    RO

    Results & Recommendations

    Division

    QMT

    ( EPS + M&E Team)

    TA Team( EPS s)

    District QMT District QMT

  • 8/11/2019 4 M&E of Programs and Projects 2

    22/43

    M&E Tools

  • 8/11/2019 4 M&E of Programs and Projects 2

    23/43

    School M&E Tools

    Template 1: Physical and Financial Output Tracking Form

    (Quarterly)

    Template 2: Log sheet for Issues; (Quarterly)

    Template 3: Project M&E Results Frame And Status (Annual /

    End of Project)

  • 8/11/2019 4 M&E of Programs and Projects 2

    24/43

    TEMPLATE DATA ELEMENTS IN THE

    TEMPLATE

    USE OF THE TEMPLATE

    Template 1: Overall Project

    Objectives/ Outputs

    Planned quantity &

    MOV of outputs for

    the period (e.g.

    quarter)

    Accomplishment

    (quantity) for the

    reporting period

    This template is meant to assist the

    project M&E team with tracking the

    progress of achievements (physical

    outputs).

    It can be used as checklist of

    deliverables, processing of collected

    information regarding progress and

    recording of results.

    Physical

    Output

    Tracking

    Form

    (Quarterly)

  • 8/11/2019 4 M&E of Programs and Projects 2

    25/43

    PROJECT/OUTPUT

    PHYSICALOUTPUT FINANCIALTARGET

    TARGET ACTUAL % BUDGETEXPENDITU

    RE%

    NOTE: Write only those outputs with

    physical and financial targets.

    LEGEND: % - Percentage of Accomplishment = (Target

    divided by Actual) x 100

    School: District:

    Month/Year: School Year:

  • 8/11/2019 4 M&E of Programs and Projects 2

    26/43

    TEMPLATE DATA ELEMENTS IN THE

    TEMPLATE

    USE OF THE TEMPLATE

    Template 2: Challenges/ Issues

    encountered

    Actions Taken To

    Resolve The Issue

    And

    The AccountableUnit/Person That

    Resolved The Issue

    Lessons Learned

    (From Facilitating &Hindering Factors)

    Sustainability

    Measures Taken

    The objective of this template is to

    record periodically the following:

    Issues encountered and plan of

    action to resolve the issue;

    Lessons learned during the

    implementation period; and

    Measures taken to ensuresustainability of the initiatives

    Log sheet

    for

    Issues;

    Lessons

    Learned;Sustaina-

    bility Log

    (Quarterly)

    LOG SHEET FOR ISSUES

  • 8/11/2019 4 M&E of Programs and Projects 2

    27/43

    CHALLENGES/ ISSUES ENCOUNTERED By CategoriesActions taken to

    RESOLVE the Issue:Unit/Person

    STRATEGIESORTECHNIQUESUSEDTO

    IMPLEMENTPROGRAMORPROJECT

    ( TECHNICAL)

    WORKINGRELATIONSHIPSBETWEENAND

    AMONGTHEIMPLEMENTATIONTEAMS

    (INSTITUTIONAL)

    GENERATIONANDUTILIZATIONOFFUNDS/

    RESOURCES(FINANCIAL)

    STAKEHOLDERS PARTICIPATION

    ( SOCIAL)

    Other factors outside of school

    Environment

    ( Political / Environmental)

    LOGSHEETFORISSUES

  • 8/11/2019 4 M&E of Programs and Projects 2

    28/43

    TEMPLATE DATA ELEMENTS IN THE

    TEMPLATE

    USE OF THE TEMPLATE

    Template 3: Overall Project

    Objectives: Goal,Purpose, Objectives Per

    Component; And

    Outputs Per

    Component

    Indicator/s (of SuccessPer Objective)

    Accomplishments per

    indicator

    Facilitating Factors

    Hindering Factors

    This template is used to articulate

    the desired results of the projectand summative status of the project

    implementation. It also documents

    the factors that helped reach results

    and/ or made the achievement of

    results difficult.

    Project M&E

    Results Frame

    and Status

    (Annual / End

    of Project)

  • 8/11/2019 4 M&E of Programs and Projects 2

    29/43

    1

    FACILITATINGFACTORS

    2

    HINDERINGFACTORS

    3

    LESSONSLEARNED

    INSTRUCTIONS:

    Write in Column 1those experiences/factors which have influenced the

    successful implementation of the project.

    In Column 2, indicate those which have caused delay or unsuccessful delivery of

    the planned target.

    In Column 3, write the Lessons Learned derived from both facilitating and

    hindering factors. Lessons learned from facilitating factors are stated as values/

    good practices/ principles. Lessons learned from hindering factors are stated as

    what could have beenA

    Lessons Learned

  • 8/11/2019 4 M&E of Programs and Projects 2

    30/43

    TEMPLATE DATA ELEMENTS IN THE

    TEMPLATE

    USE OF THE TEMPLATE

    School Tools

    4: This template is intended to guide the schoolswrite their terminal report upon completion ofthe project.

    The report provides useful information :

    for evaluating the project, for

    communicating the successes of the school,

    for sharing their good practices and lessons

    learned

    and as a data-driven source of feedback for

    planning the technical assistance of divisions

    to schools.

    Project

    Completion

    Report

    (Annual / End

    of Project)

  • 8/11/2019 4 M&E of Programs and Projects 2

    31/43

    Sections in the PCR What to Write

    Project Title Title of the SBM-Grant Fund project as stated in the approved project

    proposal

    Project Location Name of School and address

    Project Summary This is mainly drawn from the approved project proposal and may include:

    -Background or context of the Project (includes relevance of the Project to

    problems identified in the SIP)

    - Project Objectives

    - Project description (i.e., technical, organizational, leadership, logistics,

    human resource, etc)

    - Strategies and methods utilized

    -

    Project beneficiaries- Project cost and financing arrangement

    - Intended significance of the results of the Project to the School

    Actual Results or

    Outcomes of the

    Project

    Describe the changes by comparing the conditions of project beneficiaries

    before, during and after the project implementation. Changes may be in

    quantitative or qualitative terms or a combination of both (i.e, improvement

    in learning achievement rate, reduction in dropout rate, change from

    negative to positive behavior, change from restraining to facilitating learning

    environment, etc.)

    Compare the intended significance of the Project with the actual results and

    explain the variance, if any

    Cite critical incidents, if available

    Problems

    Encountered andSolutions

    Describe the problems encountered and their context in the different stages

    of project implementation, the solutions applied and the results of theapplication of each solution

  • 8/11/2019 4 M&E of Programs and Projects 2

    32/43

    Division Tools

    Template 5: Division Consolidation of School Project

    Accomplishments and Issues

    Template 6: Division Log on Issues and Lessons Learned

    Template 7: Division Report on SBM Implementation

  • 8/11/2019 4 M&E of Programs and Projects 2

    33/43

    Division Tools

    Template 5:

    Division

    Consolidation of

    School Project

    Accomplishments

    and Issues

    School

    Type Of Municipality

    No. Of Physical

    Outputs

    % Of Accomplished

    Outputs As Of

    Reporting

    Major Issues Resolved Action Taken

    Issues/Challenges

    Needing DO Assistance

    This template shows the aggregation of

    the project accomplishments of and the

    implementation issues encountered by the

    schools coming from their M&E reports.

    Information generated from this

    consolidation provides Division

    management the status of projectimplementation of concerned schools and

    how the schools could be assisted in

    strengthening SBM implementation.

  • 8/11/2019 4 M&E of Programs and Projects 2

    34/43

    SCHOOLTYPE

    OF

    MUN.

    PROJECT TITLE

    No of

    Physical

    Output

    s

    % of

    Accomplishe

    d Outputs as

    of Reporting

    Period

    Major Issues

    Resolved

    Action taken Issues/Challenges Needing

    DO Assistance

    Total=

    Min.

    %=

    Max

    %=

    Template 5: Division Consolidation of School Project Accomplishments and

    Issues

  • 8/11/2019 4 M&E of Programs and Projects 2

    35/43

    Division Tools

    Template 6:

    Division Log on

    Issues andLessons Learned

    Major issues /concerns

    encountered by the

    Division in managingSBM implementation

    The technical assistance

    needs of the division

    from the Region tostrengthen its capability

    to further help schools

    implement SBM

    Factors that have helpedfacilitate SBM

    implementation in the

    Division.

    This is a reflection sheet for the

    issues and challenges

    encountered by the division asthey manage the implementation

    of SBM in schools and the

    technical assistance they need

    from the region. This can be part

    of the Division Report to besubmitted to the Region.

  • 8/11/2019 4 M&E of Programs and Projects 2

    36/43

    Template 6: Division Log on

    Issues and Lessons Learned

    http://localhost/var/www/apps/conversion/tmp/scratch_5/SBM%20M&E/SBM%20M&E%20Operational%20Plan%20and%20Tools.docxhttp://localhost/var/www/apps/conversion/tmp/scratch_5/SBM%20M&E/SBM%20M&E%20Operational%20Plan%20and%20Tools.docx
  • 8/11/2019 4 M&E of Programs and Projects 2

    37/43

    Division Tools

    Template 7:

    Division Report on

    SBMImplementation

    This report template guides the

    Divisions in preparing their

    quarterly/annual report to the Regionon matters related to SBM

    implementation.

    Contents of the report focus on the

    major findings obtained from M&Ereports of schools and their analyses

    in order to arrive at recommendations

    for advancing SBM implementation in

    the division.

  • 8/11/2019 4 M&E of Programs and Projects 2

    38/43

    Consolidation Tools for the

    Region

  • 8/11/2019 4 M&E of Programs and Projects 2

    39/43

    Template 7: Division Report

    on SBM Implementation

    http://localhost/var/www/apps/conversion/tmp/scratch_5/SBM%20M&E/SBM%20M&E%20Operational%20Plan%20and%20Tools.docxhttp://localhost/var/www/apps/conversion/tmp/scratch_5/SBM%20M&E/SBM%20M&E%20Operational%20Plan%20and%20Tools.docx
  • 8/11/2019 4 M&E of Programs and Projects 2

    40/43

    Template 8:

    Consolidation

    of DivisionIssues and

    Challenges

    Division

    Type Of Division

    Issues And

    Concerns (bytype):

    a. Technical

    b. Institutional

    c. Financiald. Political

    e. Environment

    al

    f. Social

    This template shows the

    aggregation of the

    implementation issues

    encountered by the divisions asreflected in their M&E reports

    and on how they could be

    assisted in strengthening SBM

    implementation by the Regionand Central Office .

  • 8/11/2019 4 M&E of Programs and Projects 2

    41/43

    Template 9:

    Regional

    Report on SBM

    Implementation

    This report template guides the

    Regions in preparing their

    quarterly/annual report to the

    Central Office on mattersrelated to SBM

    implementation. Contents of

    the report focus on the major

    findings obtained from M&Ereports of divisions and their

    analyses to provide input to TA

    planning of the Region to the

    Divisions and

    recommendations to Central

    Office for improving policy

    guidelines /issuances on SBM.

  • 8/11/2019 4 M&E of Programs and Projects 2

    42/43

    Lessons

    M&E must have a purpose! (Objective)

    NOT a hit and miss activity

    M&E must have focal areas depending on purpose!

    Focus defined by stage of implementation

    e.g. Efficiency vs Effectiveness

    M&E is not data gathering alone!

    Analysis of data needed to arrive at information!

    Information to be communicated to relevant units

    M&E supports decision making for QA, TA , planadjustment, policy development

  • 8/11/2019 4 M&E of Programs and Projects 2

    43/43

    Maraming Salamat Po!