4-lane_meham.doc
TRANSCRIPT
Detailed estimate for Constn. Of 4-lane from Km. 102.800 to 108.600 in Meham town1. Earth work in embankment with tibba sand with an avg. lead of 10 Km.
Km. 102.800 to 104.00 = 2x1.20 x 1000x3.10x1.00(Avg)= 7440.00 Cum
Km. 106.00 to 108.600 = 2x2.600x1000x3.10x1.00(Avg.)= 16120.00 Cum
23560.00 Cum D/d earth excavated from road side =23560-3420 = 20140.00 Cum
2. Earth work in excavation in trenches for widening of road as per MORT&H specification
Km. 102.800 to 104.00 = 2x 1200 x1.00 x0.45=1080.00 Cum
Km. 106.00 to 108.600 = 2x2600x1.00x0.45= 2340.00 Cum
3420.00 Cum3. Constn. of embankment from the excavated soil from
The trenches
(Qty. same as item No. 2)3420.00 Cum
4. Preparation of sub grade i/c rolling the same
Km. 102.800 to 104.00 = 2x1200 x3.107440.00 Sqm
Km. 106.00 to 108.600 = 2x2600x 3.1016120.00 Sqm
23560.00 Sqm
5. Pdg. & Laying 250mm thick GSB as per MORT&H specification
Km. 102.800 to 104.00 = 2x1200 x3.10x0..251860.00 Cum
Km. 106.00 to 108.600 = 2x2600x3.10x0.254030.00 Cum
5890.00 Cum
Below interlocking block
Km. 103.800 to 106.800 = 2x3000x2.5x0.10 1500.00 Cum
7390.00 Cum6. Pdg. & Laying 200mm thick WMM as per MORT&H specification
Km. 102.800 to 104.00 = 2x1200 x3.10x0.201488.00 Cum
Km. 106.00 to 108.600 = 2x2600x3.10x0.203224.00 Cum
4712.00 Cum
7. Pdg. & Laying primer coat over WMM surface as per clause
No. 502 of MORT&H specification
Km. 102.800 to 104.00 = 2x1200 x3.107440.00 Sqm
Km. 106.00 to 108.600 = 2x2600x3.1016120.00 Sqm
23560.00 Sqm
8. Providing and laying tack coat over existing black top surface
As per clause No. 503 of MORT&H specification.
Km. 102.800 to 108.600 = 2x5800x 7.50=87000.00 Sqm
87000 x3=261000.00 Sqm9. Providing and laying 75mm thick BM as per clause No. 504
Of MORT&H specification.
Km. 102.800 to 108.600 = 2x 5800x 7.50x0.075=6525.00 Cum
10. Providing and laying 50mm thick BM as per MORT&H
Specification.
Km. 102.800 to 108.600 = 2x5800x 7.50x0.05=4350.00 Cum11. Providing and laying 25 mm thick SDBC as per clause No. 510
Of MORT&H specification.
Km. 102.800 to 108.600 = 2x5800x 7.50x0.025=2175.00 Cum12. Providing and marking central line and boarder line with Ist
Quality thermoplastic paint as per MORT&H specification
Central line
Km. 102.800 to 108.600 = 2x 5.80 = 11.60 Km
11.60 @ 40 Sqm per Km 464.00 Sqm
12.Constn. Of 2x2 m RCC slab type culvert
At RD 103.800, 104.900, 105.200,106.2004 Nos13. Constn. Of central verge in the middle of road
Km. 102.800 to 104.00 = 1200.00 M
Km. 106.00 to 108.600 = 2600.00 M 3800.00 M
D/D Gap (-) 300 M
3500.00 M
14. Constn. Of RCC side drain
Km. 103.800 to 104.00 = 200 x2= 400 M
Km. 106.00 to 106.800 = 2x800 = 1600 M Total 2000.00 M
D/d Length of street (-) 300.00 M
1700.00 M 15.Constn. Of side drain in street portion
2x30x5 = 300 M
16. Pdg.& Laying 80mm thick interlocking paver blocks of all
Shapes and colours in design mix cement of Grade M-35
Over a bed of 30mm thick fine sand complete in all respect
on both side of road between main carriageway and side drian
Km. 103.800 to 106.80 = 2x3000x2.50 = 15000.00 Sqm17. Provision for shifting of Electric poles
18. Provision for deforsation
STATE
HARYANA
STATION
ROHTAK
DIVISION
PROVL. DIVISION NO.III (NH) ROHTAK
NAME OF WORK
DETAILED ESTIMATE FOR COSTN. OF
4-LANE ON NH-10 FROM KM. 102.800 TO 104.00 AND 106.00 TO 108.600 IN MEHAM TOWNMAJOR HEAD
5054- R&B (STATE)MINOR HEAD
ESTIMATED AMOUNT
Rs. 1507.29 LACS
Detailed Estimate framed by Sh. Hanumant Singh Sangwan HSE-I, Executive Engineer, Provl. Division No.3, Rohtak for the expenses of Constn. Of 4-lane on NH-10 from Km. 102.800 to 108.600 in Village Meham town.HISTORY AND REPORT :-
Delhi-Hissar-Sulemanki road (Designated as Maharaja Agersein Marg (NH-10) is an important National Highway which connected Delhi with Indo Pak border at Sulemanki the West. This National Highway passes through state of Haryana and Punjab. The development in this reason has been tremendous as this road serves the transportation need to defenses services deployed guarding the western boarder . Hence this highway has strategic importance the growth of traffic in the transport sector has almost direct bearing with the intensity of economic activity in this area.
The state of Haryana has made a remarkable progress in Industrial as well as agriculture sector which has great importance in the development of Haryana state. This has a direct bearing on this route. Hence constent effort have been made during past to improve the riding surface of the road The traffic on this route comprises of vehicles such a trucks, buses, Tailors, Jeep three wheeler cycles, Rickshaws and Animal drawan vehicle carts etc. The development in this region has been tremendous as the road also serves the transportation need to Defence services deployed for guarding the western border of the country.
Hence this highway has strategic importance for growth of traffic in transportation sector almost direct bearing with the intensity of economic activity in the area.
National Highway-10 from Km. 29.700 to 112.210 has been entrusted to NHAI vide Gazzete notification dated 27.9.07. NHAI is going to construct 4-laning of NH-10 from Km. 86.700 to 170.00 ( i.e. Bahu Akbarpur to Hisar) on BOT basis. There is a provision of bye pass in Meham town from Km. 102.800 to 108.600= 5.80 KM. After construction of this bye pass, the internal road passing through Meham town will be transferred to state PWD. People of this town have demanded improvement of this internal stretch. The condition of this stretches is not so good as no major expenditure is being incurred by NHAI / MORT&H on this stretch. To avoid encroachment on public land and to keep this stretch in good condition, improvement is urgently required. In Meham town.
The site has been inspected by the undersigned alongwith the Superintending Engineer, Rohtak circle, Rohtak on dated 19.6.2013 and raising has been proposed from Km. 106.600 to 108.600 as the existing road level is at the field level . The top of sub grade has been kept at 1.1 M above from the original ground level as per IRC 36 clause No. 6.7 with 500mm sub grade and detailed estimate has been prepared accordingly and is submited herewith for approval. The road from Km. 102.800 to 104 has already been raised after 1995 floods.
Accordingly an estimate for an amount of Rs.----------------- lacs has been prepared and submitted for arranging the administrative approval and allotment of funds from the competent authority. Now the estimate is submited for Technical sanction from the competent authority. The Expdr. Shall be charges against Major Head 5054-Road and bridges Central. DESIGN AND SCOPE :-
The following specification has been made in the estimate:-
1. Earth work in excavation in trenches
2. Constn. Of embankment with material excavated in trenches.3. Pdg. & Laying 250 mm thick GSB as per MORT&H Specification4. Pdg. & Laying 200 mm thick WMM as per MORT&H specification5. Pdg. & Laying primer coat over WMM surface using cationic emulsion with 60 kg per 100 Sqm as per MORT&H specification.6. Pdg. & Laying Tack coat over WMM surface using cationic emulsion with20 kg per 100 Sqm as per MORT&H specification The length of the ramps is as per site conditions7. Pdg. & Laying 75mm thick BM as per MORT&H specification8. Pdg. & Laying 50mm thick BM as per MORT&H specification9. Pdg. & Laying 25 mm thick SDBC as per MORT&H specification10. Constn. Of 4 No 2x2 m slab type culvert 11. Constn. Of 1 .20 m wide central verge 12. Marking centre line and border line with thermoplastic paint13. Shifting of electric poles14. Provision for deforstationSPECIFICATION :-
Latest MORT& specification shall strictly be followed during the execution of work.
CARRYING OUT OF WORK :-
The work will be carried out after calling the competitive tender/quotation as per usual practice of the Deptt.RATES :-
Rates provides in the estimate are based on HSE + Ceiling premium thereon for analysis of rates. For NS item necessary analysis of rates have been prepared and appended in the estimate. Rates for material are based on the rates approved by the Zonal CommitteeCOST :-
Total cost of the work comes out to Rs. ------------- lacs including 1.5% Contingency charges.
Time :-
It will take nearly about 6 months to complete the work from the actual date of its commencement.
Executive Engineer,
Provl. Division No.3
Rohtak
Analysis of rate for Providing and marking center line with Hot applied thermoplastic Compound with reflectorising glass beads on bitumen surface as per clause No. 803 of MORTH specification
(Ch. 8 P-225)
(Taking out put 600 Sqm )
Unit : Sqm
1. LABOUR
MateDay 0.03@ 184/-Rs. 6.00
MazdoorDay 0.75@ 184/-Rs. 138.00
2. MACHINERY
Road marking machineHr 10 @ 60/-Rs. 600.00
Tractor TrollyHr 0.50@ 234/-Rs. 117.00
3. MATERIAL
Hot applied Thermoplastic Ltr 1500 @ 150/-Rs. 225000.00
Compound
Reflectorising glass bidsKg. 150.00@ 50/-Rs. 7500.00
Rs. 233291.00
Add 10% Over Head charges
Rs. 23329.00
Rs. 256620.00
Add 10% Contr. Profit
Rs. 25662.00
G. Total
Rs. 282282.00
Rate per Sqm = 282282/600= 470.47 say Rs. 470/- per Sqm
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
PWD B&R Br. Rohtak
PWD B&R Br. Rohtak
ANALYSIS OF RATE FOR CONSTN. OF RCC SIDE DRAIN1. Earth work in excavation in foundation, trenches
Etc. in all kind of soil, not exceeding 2 mtrs
Depth including dressing of bottom and sides
Of trenches (HSR 6.6)
1x1.70x 10 = 1.78 Cum
@ Rs. 58.17 (i/c premium)
Rs. 103.83
2. Cement conc. 1:4:8 with stone aggregate
20mm nominal size in F& P (HSR 10.38)
1x1.70 x0.10= 0.17 Cum
@ Rs. 2310/-(i/c Premium)
Rs. 392.70
3. RCC 1: 11/2 :3 in foundation and plinth (HSR 10.82+Note)
Raft 1x 1.50 x0.15= 0.225Cum
Walls 2 x0.80 x0.15 = 0.24 Cum
0.465 Cum
For Slab 1x1.5 x0.15= 0.225 Cum
0.690 Cum
@ Rs. 5966.40 (I/C Prem)
Rs. 4116.82
4 FE 500 EQR TMT Steel for RCC works
Where not include dint he complete rate of RCC (HSR 18.22)
Take @ 55 Kg per RMT of drain i/c cover
0.55 Qtl. @ Rs. 5502.30 per Qtl
Rs. 3026.56
5 150mm dia PVC pipe for drainage spouts
0.15 M @ 336.65 per 3 RMT
Rs. 16.83Total
Rs. 7656.74
Say Rs.7657.00/- per Mtr.
Executive Engineer,
Provl. Division No.3
Rohtak
Analysis of rate for construction of side drain (in street portion)
(Taking out put 10 M)
1. Earth work in excavation in foundation
Trenches etc. in all kind of soil (HSR 6.6)
10 x1.05x2.3
=24.15 Cum
@ Rs. 58.17 (i/c premium)
Rs. 1404.81
2. Plain cement concrete 1:2;4 with stone agg.
20mm Nominal size in foundation and plinth (HSR 10.41)
1x10x2.30x0.15 = 3.45Cum
@ Rs. 3385.80 (i.c premium)
Rs. 11681.00
3. Ist class brick work laid in cement sand mortor 1:3
In foundation and plinth (HSR 11.5)
2x10 x0.45+0.30 x 0.90
= 6.75 Cum
2
@ Rs. 3229.80 ( i/c premium)
Rs. 21801.00
5. Cement plaster 12mm thick in cement mortor 1:3
2x10 x 0.9= 18.00 Sqm
@ Rs. 90/- per Sqm (I.c premium)
Rs. 1620.006. RCC slab of 1:1 :3 (HSR 10.82 + Note)
10x1.80x0.20= 3.6 Cum
@ Rs. 5966.40 (I/c Prem)
Rs. 21479.00
7. Cost of steel (HSR 18.22)
3.60 Cum @ 90 Kg per cum = 3.24 Qtl
@ Rs. 5502.30 per Qtl
Rs. 17827.00
Total
Rs. 75812.81
Rate per RMT = 75812.81/10 = 7581.28
Say Rs. 7581.00
Analysis of rate for Providing and laying Granular sub base (Based on HSR)
(Taking out put 300 Cum)
Unit : Cum
1. Supply of H\GSB,
1.28 Cum @ 605.20 cum
Rs. 774.662. Laying and consolidation of stone metal
3. as per Granular sub base (HSR 24.5)
1.28 Cum @ 25.15 per cum
Rs. 32.19
Add 370% premium on Rs. 32.19Rs. 119.11
TotalRs. 925.96
Day Rs. 926/- per cum
Executive Engineer,
Provl. Division No.3
Rohtak
Analysis of rate for Providing and laying Wet Mix macadam (Based on HSR)(Taking out put 225 Cum)
Unit : Cum
1. Supply of 45 to 22.4mm stone agg,
89.10 Cum @ 764.70
Rs. 68135.002. Supply of 22.4 to 2.36mm guage
118.80 Cum @ 764.70 per cumRs.90846.003. Supply of stone dust 2.36mm and below
89.10 cum @ 841.70 per cumRs. 74995.004. Laying and consolidation of stone metal
Wet Mix madam (HSR 24.8)
297 Cum @ 36.20 per cum
Rs. 10751.00
Add 370 % premium on Rs. 11345/-Rs. 41976.00
TotalRs. 286703.00
Rate per cum =286703/ 225 = Rs. 1274.23 Say 1274.25
Executive Engineer,
Provl. Division No.3
Rohtak
Analysis of rate for Providing and laying bituminous primer coat over WMM surface with cationic emulsion bitumen using 60 Kg per 100 Sqm (Based on HSR)
(Taking out put 100 Sqm)
Unit : Sqm
1. Collection of bitumen Emulsion
0.06 MT @ 49360/-Rs.2961.602. Labour for laying primer coat over WMM surface
(HSR 24.29)
100 Sqm @ 45.18 per % SqmRs. 45.18
Add 370% premium on Rs. 45.18Rs. 167.16
Rs. 3173.94
Rate per Sqm = 3173.94 /100 = 31.74 Say Rs. 31.75
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.5
Rohtak
Jhajjar
Analysis of rate for Constn. of embankment from the material obtained from excavation
Unit : Cum
1.Supply of tibba sand with an avg. lead of 1 Km
Rs. 12.00
Add 300% premium
Rs. 66.00 2Add unloading plus premium
Rs. 9.62
3. Add extra for laying as per to the specification
(HSR 6.2 G 1)
Rs. 0.68
Add 425% premium
Rs. 2.89
4.Add extra for watering (HSR 6.2 G ii)
Rs. 0.75
Add 425% premium
Rs. 3.18
5.
Add extra for rolling to the specification (HSR 6.2 G v)Rs. 2.25
Add 135% premium
Rs. 3.04
Total
Rs. 100.41
Say Rs. 100.00 per cum
Analysis of rate for Constn. of embankment from the material obtained from excavation
Unit : Cum
1.Supply of tibba sand with an avg. lead of 9 Km
Rs. 27.00
Add 450% premium
Rs. 121.50 Add unloading plus premium
Rs. 9.62
3. Add extra for laying as per to the specification
(HSR 6.2 G 1)
Rs. 0.68
Add 425% premium
Rs. 2.89
4.Add extra for watering (HSR 6.2 G ii)
Rs. 0.75
Add 425% premium
Rs. 3.18
5.
Add extra for rolling to the specification (HSR 6.2 G v)Rs. 2.25
Add 135% premium
Rs. 3.045. Add compensation of earth ( HSR 6.4)
0.35 + 500 % premium
Rs. 17.85
Total
Rs. 188.76
Say Rs. 189.00 per cum
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
Rohtak
Rohtak
Detailed estimate for Constn. Of 4-lane from Km. 102.800 to 108.600 in Meham town
1. Dismentaling /scaryfication of road including soling and wearing coat, screening And screening and stacking of old serviceable material. (HSR 24.37)
Km. 106.600 to 108.600 = 2x1000x10 =20000.00 Sqm2. Earth work in embankment with tibba sand with an avg. lead of 10 Km.
Km. 102.800 to 104.00 = 2x1.20 x 1000x3.10 ( D.A.)
Km. 106.00 to 106.600 = 2x0.600x1000x3.10 (D.A.)= 25128.00 Cum
Km. 106.600 to 108.600 = 2x1000x (18.20+25)/2 x1.70 = 73440.00 Cum Total 98568.00 Cum
D/D Crust thickness = 2x1000x18.20 x0.60 ( - ) 21840.00 Cum
D/d Qty. of sub grade = 2x 2x1000 x7.50x 0.50 (-) 15000.00 Cum
36840.00
Net Qty. 98568- 36840 = 61728.00
3. Constn. of sub grade with soil CBR not less than 9%
Km. 106.600 to 108.600 = 2x2x1000 x 7.5 x0.50= 15000.00 Cum4. Pdg. & Laying 250mm thick GSB as per MORT&H specification
Km. 102.800 to 104.00 = 2x1200 x3.10x0..251860.00 Cum
Km. 106.00 to 106.600 = 2x 600x3.10x0.25930.00 CumKm. 106.600 to 108.600 = 2x2x1000 x7.50 x0.257500.00 Cum
10290.00 Cum
Below interlocking block
Km. 103.800 to 106.800 = 2x3000x2.5x0.10 1500.00 Cum
11790.00 Cum
5. Pdg. & Laying 200mm thick WMM as per MORT&H specification
Km. 102.800 to 104.00 = 2x1200 x3.10x0.201488.00 Cum
Km. 106.00 to 106.600 = 2x600x3.10x0.20744.00 Cum
Km. 106.600 to 108.600 = 2x2x1000 x7.5 x0.206000.00 Cum
8232.00 Cum
6. Pdg. & Laying primer coat over WMM surface as per clause
No. 502 of MORT&H specification
Km. 102.800 to 104.00 = 2x1200 x3.107440.00 Sqm
Km. 106.00 to 106.600 = 2x600x3.103720.00 Sqm Km. 106.600 to 108.600 = 2x2x2000 x7.5 30000.00 Sqm
41160.00 Sqm
7. Providing and laying tack coat over existing black top surface
As per clause No. 503 of MORT&H specification.
Km. 102.800 to 108.600 = 2x5800x 7.50=87000.00 Sqm
87000 x3=261000.00 Sqm8. Providing and laying 75mm thick BM as per clause No. 504
Of MORT&H specification.
Km. 102.800 to 108.600 = 2x 5800x 7.50x0.075=6525.00 Cum
9. Providing and laying 50mm thick BM as per MORT&H
Specification.
Km. 102.800 to 108.600 = 2x5800x 7.50x0.05=4350.00 Cum
10. Providing and laying 25 mm thick SDBC as per clause No. 510
Of MORT&H specification.
Km. 102.800 to 108.600 = 2x5800x 7.50x0.025=2175.00 Cum
11. Providing and marking central line and boarder line with Ist
Quality thermoplastic paint as per MORT&H specification
Central line
Km. 102.800 to 108.600 = 2x 5.80 = 11.60 Km
11.60 @ 40 Sqm per Km 464.00 Sqm
12.Constn. Of 2x2 m RCC slab type culvert
At RD 103.800, 104.900, 105.200,106.200 ,4 Nos
13. Constn. of 1.00 m dia Hume pipe culvert 106.950 107.8752 Nos
14. Constn. Of central verge in the middle of road
Km. 102.800 to 104.00 = 1200.00 M
Km. 106.00 to 108.600 = 2600.00 M 3800.00 M
D/D Gap (-) 300 M
3500.00 M
15. Constn. Of RCC side drain
Km. 103.800 to 104.00 = 200 x2= 400 M
Km. 107.00 to 107.800 = 2x800 = 1600 M Total 2000.00 M
D/d Length of street (-) 300.00 M
1700.00 M
16. Constn. Of side drain in street portion
2x30x5 = 300 M
17.. Pdg.& Laying 80mm thick interlocking paver blocks of all
Shapes and colours in design mix cement of Grade M-35
Over a bed of 30mm thick fine sand complete in all respect
on both side of road between main carriageway and side drian
Km. 103.800 to 106.00 = 2x2200x2.50 = 11000.00 Sqm
Km. 107.00 to 107.800 = 2x800 x2.504000.00 Sqm
15000.00 Sqm18. Provision for shifting of Electric poles
19. Provision for deforsation
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
Rohtak
Rohtak
CREDIT OF OLD BITUMENOUS MATEIAL1. Black top surface
KM. 106.600 TO 108.600 = 2000 X 10 X 0.10 = 2000.00 CUMTake 80 % = 2000 x 80 % =1600.00 Cum
Used in Recycling 30% qty of old material to be used in recycelling
0.30 x1.33 = 0.40 Cum Loose Qty.
1600 /0.40 = 4000.00 Cum is to be recycelling with old material
2. Qty. of stone metal
KM. 106.600 TO 108.600 = 2000 X 10 X 0.40 = 8000.00 CUMTake 80% credit = 8000 x 80% =6400.00 Cum
@ Rs. 600/- per cum
Rs. 3840000/-
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
Rohtak
Rohtak
Analysis of rate for Providing and laying 1.00 m dia Hume pipe culvert
1. Earth work in excavation in foundation trenches etc. in all kind
Of soil not exceeding 2 M depth
Under pipe 1x 25.00 x 4.55 x 1.68
= 191.10 Cum
Toe wall 1x2x3.66 x2.00x4.55
= 66.61 Cum
257.71 Cum
@ Rs. 58.17 per Cum
Rs. 14991.00
2. Cement concrete 1:3:6 with stone aggregate 20mm nominal size
In foundation and plinth
Toe wall 1x2x3.66x1.90 x0.75
= 10.43 Cum
Under Pipe 25.00 x 1.68 x0.45
= 18.90 Cum
29.33 Cum @ Rs. 2217.05 Per cumRs. 65026.003. Ist class brick work laid in cement sand mortar 1:3 in
In foundation and plinth.
Toe wall Ist Step 2x 3x1.12x1.22 = 8.20 Cum
2nd step 2x3x0.75x0.61
= 2.75 Cum
3rd step 2x3x0.52 x1.22
= 3.80 Cum
4th step 2x3x0.33x1.35
= 2.67 Cum
17.42 Cum
D/d 2x 22x (1.50)2 x(1.12 +0.33)(-)
= 1.30 Cum
7x42
16.12 Cum
Parapet 2x3x0.33x0.60
1.19 Cum
17.31 Cum
@ Rs. 3229.80 per cum
Rs. 55908.00
4. Providing and laying 1200mm dia Hume pipe NP-3
25 Mtrs @ 3600 per RMTRs. 90000.00
5. Cement pointing 1;2 in deep variety
Toe wall
Outer side 1x2x3 x1.80
= 10.80
Top 1x2x3.00 x0.33
= 1.98
Front rear side 2x2x(1.12+0.33)x1.80
= 5.22
2 18.18 Sqm
D/d pipe portion 22/7 x1.5 +1.5 (-) 3.532 14.65 Sqm
Parapet
2x2x 3 x0.60 7.20 Sqm
Top 2x3x0.33 1.98 Sqm
Front rear side 2x2x0.33x.0.60 0.79 Sqm
24.62 Sqm
@ Rs. 90/- per Sqm
Rs. 2216.00G. Total
Rs. 228141.00Analysis of rate for Constn. of embankment from Flyash from Panipat Thermal plant with an avg. lead of 90 Km
Unit : Cum
1.Supply of Fly ash with an avg. lead of 90 Km i/ cpremium
Rs. 386.10 Add unloading plus premium
Rs. 9.62
3. Add extra for laying as per to the specification
(HSR 6.2 G 1)
Rs. 0.68
Add 425% premium
Rs. 2.89
4.Add extra for watering (HSR 6.2 G ii)
Rs. 0.75
Add 425% premium
Rs. 3.18
5.
Add extra for rolling to the specification (HSR 6.2 G iv a)
Rs. 13.30
Add 110% premium
Rs. 14.63 Add 25% shrikange
Rs. 107.75
Rs. 538.75
Say Rs. 535.00 per cum
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
Rohtak
Rohtak
Analysis of rate for constn. of retaining wall ( 3.675 M height)(Taking output 10 M) Unit : RMT
1.`Earth work in excavation in foundation and plinth (HSR 6.6)
10x3.4 x1= 34.00 Cum
@ Rs. 58.17 per cum
Rs. 1979.00
3. Cement conc. 1:2;4 (HSR 10.41)
10 x3.1 x0.1 = 3.1 Cum
@ Rs. 3385.80
Rs. 10496.00
4. RCC 1:1 1/2:3 for wall and other items (HSR 10.86 +10.95)
10 x3.1 x0.3 = 9.3 cum
10 3.375 x0.4 = 13.5 Cum22.8 Cum @ Rs. 6538/- per cum Rs. 149066.005. Steel for RCC work (HSR 18.22)
15.10 Qtl (D.A.) @ Rs. 5502.30 per Qtl
Rs. 83085.00
Rs. 244626.00
Rate per RMT = 244626/10 = Rs. 24462.6 say Rs. 24462/-
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
Rohtak
Rohtak
Analysis of rate for constn. of Retaining wall ( 2.675 M height)(Taking output 10 M) Unit : RMT
1.`Earth work in excavation in foundation and plinth (HSR 6.6)
10x 3.4 x1= 34.00 Cum
@ Rs. 58.17 per cum
Rs. 1979.00
3. Cement conc. 1:2;4 (HSR 10.41)
10 x3.1 x0.1 = 3.1 Cum
@ Rs. 3385.80
Rs. 10496.00
4. RCC 1:2:3 for wall and other items (HSR 10.86 +10.95)
10 x3.1 x0.3 = 9.3 cum
10x 2.375 x0.4 = 9.5 Cum18.8Cum @ Rs. 6538/- per cum Rs. 122914.00
5. Steel for RCC work (HSR 18.22)
12.41 Qtl (D.A.) @ Rs. 5502.30 per Qtl Rs. 68283.00
Rs. 203672.00
Rate per RMT = 203672/10 = 20367.00DETAIL OF STEEL FOR RETAINING WALL (HEIGHT 3.675 M) (Taking out Put 10 Mtrs) Steel for Raft
12 mm dia Main 150 mm c/c 2x67 x3.5 = 469 Mtr @ 0.89 Kg per RMT = 4.17 Qtl
10 mm dia distribution 150 mm c/c 10 M x21 Nos = 210 Mtr @ 0.62 Kg per RMT = 1.30 Qtl
12 mm dia distribution 150 mm c/c 10 x21 = 210 Mtrs @ 0.89 Kg per RMT = 1.86 Qtl.
Steel for wall12 mm dia Main 150 mm c/c 7.95x67 = 532.65 Mtr @ 0.89 Kg per RMT = 4.74 Qtl
10 mm dia distribution 150 mm c/c 10 M x49 Nos = 490 Mtr @ 0.62 Kg per RMT = 3.038 Qtl
Total 15.10 Qtl.
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
Rohtak
Rohtak
Detail of Qty. of R.E. wall and Re-construction of Central verge1.
Reconstruction of Central verge
Km. 104.00 to 104.300 = 300 Mtr
2. Constn. of Retaining wall
Km. 106.480 to 106.580.00 = 100 Mtrs
Executive Engineer,
Sub Divisional Engineer,
Provl. Division No.3
Provl. Sub Division No.6
Rohtak
Rohtak
Analysis of rate for constn. of Retaining wall ( 3.50 M height)(Taking output 10 M) Unit : RMT
1.`Earth work in excavation in foundation and plinth (HSR 6.6)
10 2 x4.1 = 82.00 Cum @ 58.17 per cum
Rs. 4770.00
2. Cement conc. 1:2;4 ( HSR 10.41)
10 x 4.10 x0.50 = 20.5 Cum
For topping 10 x 0.70 x0.15 = 1.05 Cum
21.55 @ Rs. 3385.80 per cum Rs. 72964.00.3. Ist class brick work in 1:3 ( HSr 11.5
Ist step 10 x 3.10 x0.50 =15.50 Cum
2nd step 10 x2.7 x0.50 = 13.50 Cum
3rd step 10x2.3x0.50
= 11.50 Cum4th step 10 x1.90 x0.50
= 9.50 Cum
5th step 10 x1.70 x0.50
= 8.50 Cum
6th step 10 x1.50 x0.50
= 7.50 Cum
7th step 10 x1.30 x0.50
= 6.50 Cum
8th step 10 x1.10 x0.50
= 5.50 Cum
9th step 10 x0.9 x0.5
= 4.50 Cum
10th step 10 x0.7 x0.5
= 3.50 Cum
Total
86.00 Cum @ Rs. 3229.80Rs. 277763.00
Rs. 355497.00
Rate per RMT = 355497 /10 = Rs. 35549.700 Say Rs. 35550/-
QTY. OF RETAINING WALL ( LENGTH 100 M)1 . Earth work in excavation ( HSR 6.6) = 820 Cum
2. Cement conc. 1;2;4 (HSR 10.41 ) = 215.50 Com
3.. Ist class brick work in 1:3 (HSR 11.5 ) = 860.00 Cum To
The Nodal Officer ( Forest Conservation)
O/o Principal Chief Conservator of forest
Haryana, Panchkula
No. Dated :-
Subject :-Diversion of 4.56 ha of forest land for 4-laniong of Nh-10 Rohtak-Hisar road
Km. 102.800 to 104.00 and 106.00 to 108.600 in Meham town under forest division
and district Rohtak , Haryana.
Ref. :-
The project site has been inspected by the under signed on ------------ alongwith Mr. H.S. Sangwan Executive Engineer, Provl. Division No.3 (NH) Rohtak and officials of forest Department and the following observations were made :-
During the inspection it was found that the diversion of 4.56 ha of Forest land is required which is unavoidable and the barest minimum for the project. There is no alternative suitable non Forest land is available for the project . The RD/ Km wise details of required of forest land is given below :-
RD/ KmLength in MtrWidth in areaArea in Sqm
102.800 to 104.001200The existing metalled road is 10.00 Meter wide with 1.00 meter berm/ shoulder on each side with a total formation width of 12.00 Meter. Widening of existing carriageway from 10.00 M to 16.20 M with side drain on both side has been proposed and thus road formation will be increased from 12 mtr. to 24 Mtr and forest land in 12 mtr on both side s will be affected.14400.00
106.00 to 108.6002600The existing metalled road is 10.00 Meter wide with 1.00 meter berm/ shoulder on each side with a total formation width of 12.00 Meter. Widening of existing carriageway from 10.00 M to 16.20 M with side drain on both side has been proposed and thus road formation will be increased from 12 mtr. to 24 Mtr and forest land in 12 mtr on both side s will be affected.31200.00
2.There are------------- trees and -------------- saplings proposed to be felled for the project. The tree species involved are of eucalyptus , kikar, shisham and Misc. species. The marking of the trees proposed for felling has been done as per the projects site plan and -------- trees ---------- saplings are necessarily required to be felled. The trees standing outside proposed formation width has been left out and non marked for felling. The project site is passing through/ surrounded by agricultural fields and there is no rare/ endangered/ unique species of flora and fauna in the area.3.Total ROW of this road is 30.00 m except abadi areas. The present width of the road is 12 mtr. which is to be widened to 24.00 Mtr. If concentric widening is done, a strip of 3.00 mts is left on both side to accommodate utilities running along the road and afforestation in a available balance strip on both sides of road can be carried out . In case ecentric widening is carried out ( Widening in one side only) it is not possible. Thus possibility of expansion of road on one side is not feasible.4.The user agency has not violated the provision of forest conservation Act 1980 and no work has been started with out proper sanction of the competent authority.
So, it is recommended that the proposal may be approved/ sanctioned in the larget public interest.
Date :-
Place
Conservator of forest
Central circle, Rohtak
Endst No. Dated :-
Copy of divisional Forest Officer, Rohtak ./ Executive Engineer, Provl. Division No.3 (NH) PWD B&R Br. Rohtak for their information and for further necessary action.
Date :-
Place
Conservator of forest
Central circle, Rohtak