Project Time Management Dr. Panos FITSILIS ([email protected])

Upload: panos-fitsilis

Post on 24-Dec-2014

30 views

Category:

Business


0 download

DESCRIPTION

Project Time management Project Scheduling CPM PERT Critical Chain Project crashing Critical Path

TRANSCRIPT

Page 1: 3.time management

Project Time Management

Dr. Panos FITSILIS

([email protected])

Page 2: 3.time management

Project Scheduling

Identifying precedence relationships

Sequencing activities

Determining activity times & costs

Estimating material & worker requirements

Determining critical activities

2

© 1995 Corel Corp.

Page 3: 3.time management

CPM and PERT

3

• Network techniques

• Developed in 1950’s

– CPM by DuPont for chemical plants (1957)

– PERT by Booz, Allen & Hamilton with the U.S. Navy,

for Polaris missile (1958)

• Consider precedence relationships and

interdependencies

• Each uses a different estimate of activity times

Page 4: 3.time management

CPM/PERT

4

• The Critical Path Method (CPM) is a

project modeling technique developed

in the late 1950s by Morgan R. Walker

of DuPont and James E. Kelley, Jr. of

Remington Rand.

• PERT (Program Evaluation and

Review Technique) which was

developed at about the same time by

Booz Allen Hamilton and the US Navy.

Page 5: 3.time management

Questions Which May Be Addressed from scheduling

5

• Is the project on schedule, ahead of schedule, or behind schedule?

• Is the project over or under cost budget?

• Are there enough resources available to finish the project on time?

• If the project must be finished in less than the scheduled amount of

time, what is the way to accomplish this at least cost?

Page 6: 3.time management

The Six Steps for scheduling

6

• Define the project and prepare the work breakdown structure,

• Develop relationships among the activities. (Decide which activities must

precede and which must follow others.)

• Draw the network connecting all of the activities

• Assign time and/or cost estimates to each activity

• Compute the longest time path through the network. This is called the critical

path

• Use the network to help plan, schedule, monitor, and control the project

Page 7: 3.time management

A Comparison of AON and AOA Network Conventions

7

Page 8: 3.time management

8

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff.

B Select site and do site survey.

C Select equipment.

D Prepare final construction plans and layout.

E Bring utilities to the site.

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security.

G Purchase and take delivery of equipment.

H Construct the hospital.

I Develop an information system.

J Install the equipment.

K Train nurses and support staff.

St. Adolf’s Hospital

Page 9: 3.time management

9

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop an information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

St. Adolf’s Hospital

Page 10: 3.time management

10

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

St. Adolf’s Hospital

Page 11: 3.time management

11

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

St. Adolf’s Hospital

Page 12: 3.time management

12

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

Example 4.1

St. Adolf’s Hospital

Page 13: 3.time management

13

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

St. Adolf’s Hospital

Page 14: 3.time management

14

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

St. Adolf’s Hospital

Page 15: 3.time management

15

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

E

St. Adolf’s Hospital

Page 16: 3.time management

16

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

E

F

St. Adolf’s Hospital

Page 17: 3.time management

17

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

E

F

G

St. Adolf’s Hospital

Page 18: 3.time management

18

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

E

F

G

H

St. Adolf’s Hospital

Page 19: 3.time management

19

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

E

F

G

H

I

St. Adolf’s Hospital

Page 20: 3.time management

20

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

E

F

G

H

I

J

St. Adolf’s Hospital

Page 21: 3.time management

21

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Start

A

B

C

D

E

F

G

H

I

J

K

St. Adolf’s Hospital

Page 22: 3.time management

22

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AON Network

Finish Start

A

B

C

D

E

F

G

H

I

J

K

Figure 4.2

St. Adolf’s Hospital

Page 23: 3.time management

23

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network

St. Adolf’s Hospital

Page 24: 3.time management

24

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network

A

Start

1

2

St. Adolf’s Hospital

Page 25: 3.time management

25

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network

A

B

Start

1

2

4

St. Adolf’s Hospital

Page 26: 3.time management

26

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network

A

B

C

D

Start

1

2

3

5

4

St. Adolf’s Hospital

Page 27: 3.time management

27

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network F

A

B

C

D

H

E

G

I

Start

1

8 2

3 7

6 5

4

St. Adolf’s Hospital

Page 28: 3.time management

28

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network F

A

B

C

D

H

E

G J

I

Start

1

8 2

3 7

6 5

4

St. Adolf’s Hospital

Page 29: 3.time management

29

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network F

A

B

C

D

H

E

G J

I Dummy

Start

1

8 2

3 7

6 5

4

St. Adolf’s Hospital

Page 30: 3.time management

30

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

AOA Network F

A

B

C

D

H

E

G

K

J

I

Finish

9

Dummy

Start

1

8 2

3 7

6 5

4

Figure 4.3

St. Adolf’s Hospital

Page 31: 3.time management

31

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

St. Adolf’s Hospital

Page 32: 3.time management

32

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

Figure 4.4

St. Adolf’s Hospital

Page 33: 3.time management

33

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

St. Adolf’s Hospital

Page 34: 3.time management

34

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

St. Adolf’s Hospital

Page 35: 3.time management

35

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

St. Adolf’s Hospital

Page 36: 3.time management

36

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

St. Adolf’s Hospital

Page 37: 3.time management

37

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

St. Adolf’s Hospital

Page 38: 3.time management

38

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

Path Expected Time (wks)

A-F-K 28

A-I-K 33

A-C-G-J-K 67

B-D-H-J-K 69

B-E-J-K 43

St. Adolf’s Hospital

Page 39: 3.time management

39

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

Path Expected Time (wks)

A-F-K 28

A-I-K 33

A-C-G-J-K 67

B-D-H-J-K 69

B-E-J-K 43

St. Adolf’s Hospital

Page 40: 3.time management

40

Immediate

Activity Description Predecessor(s)

A Select administrative and medical staff. —

B Select site and do site survey. —

C Select equipment. A

D Prepare final construction plans and layout. B

E Bring utilities to the site. B

F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A

G Purchase and take delivery of equipment. C

H Construct the hospital. D

I Develop and information system. A

J Install the equipment. E,G,H

K Train nurses and support staff. F,I,J

Completion Time

Finish Start

K

6

I

15

F

10

C

10

D

10

E

24

G

35

H

40

J

4

A

12

B

9

Path Expected Time (wks)

A-F-K 28

A-I-K 33

A-C-G-J-K 67

B-D-H-J-K 69

B-E-J-K 43

St. Adolf’s Hospital

Page 41: 3.time management

41

St. Adolf’s Hospital

Page 42: 3.time management

Critical Path Analysis

42

• Provides activity information ◦ Earliest (ES) & latest (LS) start

◦ Earliest (EF) & latest (LF) finish

◦ Slack (S): Allowable delay

• Identifies critical path ◦ Longest path in network

◦ Shortest time project can be completed

◦ Any delay on critical path activities delays project

◦ Critical path activities have 0 slack

Page 43: 3.time management

Earliest Start and Finish Steps

43

• Begin at starting event and work forward

• ES = 0 for starting activities

– ES is earliest start

• EF = ES + Activity time

– EF is earliest finish

• ES = Maximum EF of all predecessors for non-

starting activities

Page 44: 3.time management

Latest Start and Finish Steps

44

• Begin at ending event and work backward

• LF = Maximum EF for ending activities

– LF is latest finish; EF is earliest finish

• LS = LF - Activity time

– LS is latest start

• LF = Minimum LS of all successors for non-

ending activities

Page 45: 3.time management

Latest Start and Finish Steps

45

Latest Finish

ES

LS

EF

LF

Earliest

Finish

Latest

Start

Earliest Start

Activity

Nam

e

Activity

Duration

Page 46: 3.time management

46

St. Adolf’s Hospital

Page 47: 3.time management

47

Earliest Start

and

Earliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

I

15

F

10

Finish Start

St. Adolf’s Hospital

Page 48: 3.time management

48

Earliest Start

and

Earliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0

I

15

F

10

Earliest start time

Finish Start

St. Adolf’s Hospital

Page 49: 3.time management

49

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

Earliest Start

and

Earliest Finish Times

Earliest start time Earliest finish time

Finish Start

St. Adolf’s Hospital

Page 50: 3.time management

50

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

0 9

Earliest Start

and

Earliest Finish Times

Finish Start

St. Adolf’s Hospital

Page 51: 3.time management

51

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

9 33

0 9 9 19

Earliest Start

and

Earliest Finish Times

Finish Start

St. Adolf’s Hospital

Page 52: 3.time management

52

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

9 33

0 9 9 19

12 22

Earliest Start

and

Earliest Finish Times

Finish Start

St. Adolf’s Hospital

Page 53: 3.time management

53

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

19 59

9 33

0 9 9 19

12 22

Earliest Start

and

Earliest Finish Times

Finish Start

St. Adolf’s Hospital

Page 54: 3.time management

54

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

22 57

19 59

9 33

0 9 9 19

12 22

Earliest Start

and

Earliest Finish Times

Finish Start

St. Adolf’s Hospital

Page 55: 3.time management

55

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

22 57

59 63 19 59

9 33

0 9 9 19

12 22

Earliest Start

and

Earliest Finish Times

Finish Start

St. Adolf’s Hospital

Page 56: 3.time management

56

Earliest Start

and

Earliest Finish Times

Finish

Earliest start time Earliest finish time

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

Critical

path

Start

St. Adolf’s Hospital

Page 57: 3.time management

57

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

Latest Start

and

Latest Finish Times

Finish Start

St. Adolf’s Hospital

Page 58: 3.time management

58

Latest Start

and

Latest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

63 69 Latest

finish

time

Finish Start

St. Adolf’s Hospital

Page 59: 3.time management

59

Latest Start

and

Latest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

63 69

Latest

start

time

Latest

finish

time

Finish Start

St. Adolf’s Hospital

Page 60: 3.time management

60

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

53 63 63 69

59 63

Latest Start

and

Latest Finish Times

Finish Start

St. Adolf’s Hospital

Page 61: 3.time management

61

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

53 63 63 69

24 59

19 59

35 59

59 63

Latest Start

and

Latest Finish Times

Finish Start

St. Adolf’s Hospital

Page 62: 3.time management

62

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

53 63 63 69

14 24 24 59

9 19 19 59

35 59

59 63

Latest Start

and

Latest Finish Times

Finish Start

St. Adolf’s Hospital

Page 63: 3.time management

63

Latest Start

and

Latest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Earliest start time Earliest finish time

Latest start time Latest finish time

Critical

path

Finish Start

St. Adolf’s Hospital

Page 64: 3.time management

64

Gantt Charts

St. Adolf’s Hospital

Page 65: 3.time management

65

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Activity Slack

Analysis

Finish Start

St. Adolf’s Hospital

Page 66: 3.time management

66

St. Adolf’s Hospital

Activity Slack

Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Activity Slack

Finish

Page 67: 3.time management

67

Activity Slack

Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Activity Slack

Slack = LS – ES

or

Slack = LF – EF

Finish

Page 68: 3.time management

68

Activity Slack

Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Activity Slack

SlackK = 63 – 63

or

SlackK = 69 – 69

Finish

Page 69: 3.time management

69

Activity Slack

Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Activity Slack

SlackK = 0

or

SlackK = 0

Finish

Page 70: 3.time management

70

Activity Slack

Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Finish

Page 71: 3.time management

71

Activity Slack

Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Node Duration ES LS Slack

Finish

Page 72: 3.time management

72

Activity Slack

Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 63 19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Node Duration ES LS Slack

A 12 0 2 2

B 9 0 0 0

C 10 12 14 2

D 10 9 9 0

E 24 9 35 26

F 10 12 53 41

G 35 22 24 2

H 40 19 19 0

I 15 12 48 36

J 4 59 59 0

K 6 63 63 0

Finish

Page 73: 3.time management

73

C

10

G

35

E

24

I

15

F

10

12 27

12 22

22 57

9 33

12 22

48 63

53 63

14 24 24 59

35 59

B

9

0 9

0 9

D

10

9 19

9 19

H

40

19 59

19 59

J

4

59 63

59 63

K

6

63 69

63 69

Critical Path

Node Duration ES LS Slack

A 12 0 2 2

B 9 0 0 0

C 10 12 14 2

D 10 9 9 0

E 24 9 35 26

F 10 12 53 41

G 35 22 24 2

H 40 19 19 0

I 15 12 48 36

J 4 59 59 0

K 6 63 63 0

Finish

Page 74: 3.time management

74

C

10

G

35

E

24

I

15

F

10

12 27

12 22

22 57

9 33

12 22

48 63

53 63

14 24 24 59

35 59

B

9

0 9

0 9

D

10

9 19

9 19

H

40

19 59

19 59

J

4

59 63

59 63

K

6

63 69

63 69

Critical Path

A

12

0 12

2 14

Finish Start

Page 75: 3.time management

Probabilistic Time Estimates

75 (a) Mean

m a b Time

Pro

ba

bil

ity

Page 76: 3.time management

Probabilistic Time Estimates

76 (b) Mean

a b m

3s 3s

Area under curve

between a and b is

99.74%

Time

Pro

ba

bil

ity

Page 77: 3.time management

77

A F

I

C G Finish

D

E

H B J

K

Start

Probabilistic Time

Estimates

St. Adolf’s Hospital

Page 78: 3.time management

78

Activity B

Most

Optimistic Likely Pessimistic

(a) (m) (b)

7 8 15

Probabilistic Time

Estimates A F

I

C G Finish

D

E

H B J

K

Start

St. Adolf’s Hospital

Page 79: 3.time management

79

Activity B

Most

Optimistic Likely Pessimistic

(a) (m) (b)

7 8 15

Probabilistic Time

Estimates

te = = 9 weeks 7 + 4(8) + 15

6

s2 = = 1.78 ( ) 15 - 7

6

2

A F

I

C G Finish

D

E

H B J

K

Start

St. Adolf’s Hospital

Expected Time

Time Variance

Page 80: 3.time management

Project Times

80

• Expected project time (T)

– Sum of critical path activity

times, t

• Project variance (V)

– Sum of critical path activity

variances, v

Used to obtain probability

of project completion!

Page 81: 3.time management

81

Optimistic Likely Pessimistic Expected Variance

Activity (a) (m) (b) Time (te ) (s2 )

Time Estimates (wk) Activity Statistics

St. Adolf’s Hospital

Page 82: 3.time management

82

Optimistic Likely Pessimistic Expected Variance

Activity (a) (m) (b) Time (te ) (s2 )

Time Estimates (wk) Activity Statistics

A 11 12 13 12 0.11

B 7 8 15 9 1.78

C 5 10 15 10 2.78

D 8 9 16 10 1.78

E 14 25 30 24 7.11

F 6 9 18 10 4.00

G 25 36 41 35 7.11

H 35 40 45 40 2.78

I 10 13 28 15 9.00

J 1 2 15 4 5.44

K 5 6 7 6 0.11

St. Adolf’s Hospital

Page 83: 3.time management

83

Probabilities

Critical Path = B - D - H - J - K

T = 72 days TE = 69 days

St. Adolf’s Hospital

Page 84: 3.time management

84

s2 = (variances of activities) z = T –TE

s2

Probabilities

Critical Path = B - D - H - J - K

T = 72 days TE = 69 days

St. Adolf’s Hospital

Page 85: 3.time management

85

s2 = (variances of activities) z = T – TE

s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

Probabilities

Critical Path = B - D - H - J - K

T = 72 days TE = 69 days

St. Adolf’s Hospital

Page 86: 3.time management

86

s2 = (variances of activities) z = T – TE

s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

z = 72 – 69

11.89

Probabilities

Critical Path = B - D - H - J - K

T = 72 days TE = 69 days

St. Adolf’s Hospital

Page 87: 3.time management

87

s2 = (variances of activities) z = T – TE

s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

z = = 0.87 72 – 69

11.89

Probabilities

Critical Path = B - D - H - J - K

T = 72 days TE = 69 days

St. Adolf’s Hospital

Page 88: 3.time management

88

s2 = (variances of activities) z = T – TE

s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

z = = 0.87 72 – 69

11.89

Probabilities

Critical Path = B - D - H - J - K

T = 72 days TE = 69 days

Pz = .8078 .81

St. Adolf’s Hospital

Page 89: 3.time management

89

s2 = (variances of activities) z = T - TE

s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

z = = 0.87 72 - 69

11.89

Probabilities

Critical Path = B - D - H - J - K

T = 72 days TE = 69 days

Project duration (weeks)

69 72

Probability of

meeting the

schedule is

0.8078

Length of

critical path

Normal distribution:

Mean = 69 weeks;

s = 3.45 weeks

Probability of

exceeding 72

weeks is 0.1922

St. Adolf’s Hospital

Page 90: 3.time management

90

s2 = (variances of activities) z = T – TE

s2

s2 = 0.11 + 2.78 + 7.11 + 5.44 + 0.11 = 15.55

z = = 1.27 72 – 67

15.55

Probabilities

Path = A - C - G - J - K

T = 72 days TE = 67 days

From Appendix 2

Pz = .8980 .90

St. Adolf’s Hospital

Page 91: 3.time management

Γιατί να τελειώσω νωρίτερα???

91

Πιθανότητα να συμβεί

Χαμηλή

Υψηλή

Πιθανή Διάρκεια

(m)

Σύντομη (α)

Μεγάλη (b)

(TE)

Έχω καιρό ακόμη ...

Parkinson Law

Works Expand to fill the allotted time

Page 92: 3.time management

Παράδειγμα πιθανότητας ολοκλήρωσης

έργου

92

Ποια είναι η αναμενόμενη πιθανότητα ολοκλήρωσης έργου

διάρκειας 40 εβδομάδων με τυπική απόκλιση 5 εβδομάδες.

Ποια είναι η πιθανότητα να τελειώσει το έργο σε 50 εβδομάδες

ή λιγότερο.

Page 93: 3.time management

PERT Probability Example

You’re a project planner for General

Dynamics. A submarine project has

an expected completion time of 40

weeks, with a standard deviation of

5 weeks. What is the probability of

finishing the sub in 50 weeks or

less?

93

© 1995

Corel Corp.

Page 94: 3.time management

Converting to Standardized Variable

94

T = 40

s = 5

50 X

Normal

Distribution

Z X T

= -

= -

= s

50 40

5 2 0 .

m z = 0

s Z = 1

Z 2.0

Standardized Normal

Distribution

Page 95: 3.time management

Obtaining the Probability

95

m z = 0

s Z = 1

Z 2.0

Z .00 .01

0.0 .50000 .50399

: : : :

2.0 .97725 .97784 .97831

2.1 .98214 .98257 .98300

Standardized Normal Probability Table

(Portion)

Probabilities in body

.02

.50798

.97725

Page 96: 3.time management

Factors to Consider when Crashing

96

• The amount by which an activity is crashed is, in

fact, permissible.

• Taken together, the shortened activity durations will

enable one to finish the project by the due date.

• The total cost of crashing is as small as possible.

Page 97: 3.time management

Advantages of PERT/CPM

97

• Especially useful when scheduling and controlling large projects.

• Straightforward concept and not mathematically complex.

• Graphical networks aid perception of relationships among project activities.

• Critical path & slack time analyses help pinpoint activities that need to be

closely watched.

• Project documentation and graphics point out who is responsible for various

activities.

• Applicable to a wide variety of projects.

• Useful in monitoring schedules and costs.

Page 98: 3.time management

Limitations of PERT/CPM

98

• Assumes clearly defined, independent, & stable

activities

• Specified precedence relationships

• Activity times (PERT) follow

beta distribution

• Subjective time estimates

• Over-emphasis on critical path

Page 99: 3.time management

Gantt diagrams

Henry Gantt

Page 100: 3.time management

Gantt Diagrams

• Standard way to present a schedule

Page 101: 3.time management

Διάγραμμα Gantt

Page 102: 3.time management

Milestones • Quite important for project management

• Signal the end of a verifiable task.

• Linked with deliverables

• Should be SMART :

– Specific

– Measurable

– Assignable

– Realistic

– Time-framed

Page 103: 3.time management

Monitoring progress with Gantt charts

Page 104: 3.time management

Gantt Charts

• Advantages

– Easy to understand

– Easy to show progress and status

– Easy to maintain

– Most popular view to communicate project status to client

and/or senior management

• Disadvantages

– Can be superficial

– Not always easy to see precedence, relationships

104

Page 105: 3.time management

Thank you!