3.time management
DESCRIPTION
Project Time management Project Scheduling CPM PERT Critical Chain Project crashing Critical PathTRANSCRIPT
Project Scheduling
Identifying precedence relationships
Sequencing activities
Determining activity times & costs
Estimating material & worker requirements
Determining critical activities
2
© 1995 Corel Corp.
CPM and PERT
3
• Network techniques
• Developed in 1950’s
– CPM by DuPont for chemical plants (1957)
– PERT by Booz, Allen & Hamilton with the U.S. Navy,
for Polaris missile (1958)
• Consider precedence relationships and
interdependencies
• Each uses a different estimate of activity times
CPM/PERT
4
• The Critical Path Method (CPM) is a
project modeling technique developed
in the late 1950s by Morgan R. Walker
of DuPont and James E. Kelley, Jr. of
Remington Rand.
• PERT (Program Evaluation and
Review Technique) which was
developed at about the same time by
Booz Allen Hamilton and the US Navy.
Questions Which May Be Addressed from scheduling
5
• Is the project on schedule, ahead of schedule, or behind schedule?
• Is the project over or under cost budget?
• Are there enough resources available to finish the project on time?
• If the project must be finished in less than the scheduled amount of
time, what is the way to accomplish this at least cost?
The Six Steps for scheduling
6
• Define the project and prepare the work breakdown structure,
• Develop relationships among the activities. (Decide which activities must
precede and which must follow others.)
• Draw the network connecting all of the activities
• Assign time and/or cost estimates to each activity
• Compute the longest time path through the network. This is called the critical
path
• Use the network to help plan, schedule, monitor, and control the project
A Comparison of AON and AOA Network Conventions
7
8
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff.
B Select site and do site survey.
C Select equipment.
D Prepare final construction plans and layout.
E Bring utilities to the site.
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the hospital.
I Develop an information system.
J Install the equipment.
K Train nurses and support staff.
St. Adolf’s Hospital
9
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop an information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
St. Adolf’s Hospital
10
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
St. Adolf’s Hospital
11
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
St. Adolf’s Hospital
12
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
Example 4.1
St. Adolf’s Hospital
13
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
St. Adolf’s Hospital
14
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
St. Adolf’s Hospital
15
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
E
St. Adolf’s Hospital
16
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
E
F
St. Adolf’s Hospital
17
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
E
F
G
St. Adolf’s Hospital
18
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
E
F
G
H
St. Adolf’s Hospital
19
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
E
F
G
H
I
St. Adolf’s Hospital
20
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
E
F
G
H
I
J
St. Adolf’s Hospital
21
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Start
A
B
C
D
E
F
G
H
I
J
K
St. Adolf’s Hospital
22
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AON Network
Finish Start
A
B
C
D
E
F
G
H
I
J
K
Figure 4.2
St. Adolf’s Hospital
23
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network
St. Adolf’s Hospital
24
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network
A
Start
1
2
St. Adolf’s Hospital
25
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network
A
B
Start
1
2
4
St. Adolf’s Hospital
26
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network
A
B
C
D
Start
1
2
3
5
4
St. Adolf’s Hospital
27
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network F
A
B
C
D
H
E
G
I
Start
1
8 2
3 7
6 5
4
St. Adolf’s Hospital
28
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network F
A
B
C
D
H
E
G J
I
Start
1
8 2
3 7
6 5
4
St. Adolf’s Hospital
29
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network F
A
B
C
D
H
E
G J
I Dummy
Start
1
8 2
3 7
6 5
4
St. Adolf’s Hospital
30
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
AOA Network F
A
B
C
D
H
E
G
K
J
I
Finish
9
Dummy
Start
1
8 2
3 7
6 5
4
Figure 4.3
St. Adolf’s Hospital
31
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
St. Adolf’s Hospital
32
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
Figure 4.4
St. Adolf’s Hospital
33
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
St. Adolf’s Hospital
34
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
St. Adolf’s Hospital
35
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
St. Adolf’s Hospital
36
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
St. Adolf’s Hospital
37
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
St. Adolf’s Hospital
38
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
Path Expected Time (wks)
A-F-K 28
A-I-K 33
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
St. Adolf’s Hospital
39
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
Path Expected Time (wks)
A-F-K 28
A-I-K 33
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
St. Adolf’s Hospital
40
Immediate
Activity Description Predecessor(s)
A Select administrative and medical staff. —
B Select site and do site survey. —
C Select equipment. A
D Prepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security. A
G Purchase and take delivery of equipment. C
H Construct the hospital. D
I Develop and information system. A
J Install the equipment. E,G,H
K Train nurses and support staff. F,I,J
Completion Time
Finish Start
K
6
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
Path Expected Time (wks)
A-F-K 28
A-I-K 33
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
St. Adolf’s Hospital
41
St. Adolf’s Hospital
Critical Path Analysis
42
• Provides activity information ◦ Earliest (ES) & latest (LS) start
◦ Earliest (EF) & latest (LF) finish
◦ Slack (S): Allowable delay
• Identifies critical path ◦ Longest path in network
◦ Shortest time project can be completed
◦ Any delay on critical path activities delays project
◦ Critical path activities have 0 slack
Earliest Start and Finish Steps
43
• Begin at starting event and work forward
• ES = 0 for starting activities
– ES is earliest start
• EF = ES + Activity time
– EF is earliest finish
• ES = Maximum EF of all predecessors for non-
starting activities
Latest Start and Finish Steps
44
• Begin at ending event and work backward
• LF = Maximum EF for ending activities
– LF is latest finish; EF is earliest finish
• LS = LF - Activity time
– LS is latest start
• LF = Minimum LS of all successors for non-
ending activities
Latest Start and Finish Steps
45
Latest Finish
ES
LS
EF
LF
Earliest
Finish
Latest
Start
Earliest Start
Activity
Nam
e
Activity
Duration
46
St. Adolf’s Hospital
47
Earliest Start
and
Earliest Finish Times
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
I
15
F
10
Finish Start
St. Adolf’s Hospital
48
Earliest Start
and
Earliest Finish Times
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0
I
15
F
10
Earliest start time
Finish Start
St. Adolf’s Hospital
49
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
Earliest Start
and
Earliest Finish Times
Earliest start time Earliest finish time
Finish Start
St. Adolf’s Hospital
50
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
0 9
Earliest Start
and
Earliest Finish Times
Finish Start
St. Adolf’s Hospital
51
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
9 33
0 9 9 19
Earliest Start
and
Earliest Finish Times
Finish Start
St. Adolf’s Hospital
52
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22
9 33
0 9 9 19
12 22
Earliest Start
and
Earliest Finish Times
Finish Start
St. Adolf’s Hospital
53
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22
19 59
9 33
0 9 9 19
12 22
Earliest Start
and
Earliest Finish Times
Finish Start
St. Adolf’s Hospital
54
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22
22 57
19 59
9 33
0 9 9 19
12 22
Earliest Start
and
Earliest Finish Times
Finish Start
St. Adolf’s Hospital
55
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22
22 57
59 63 19 59
9 33
0 9 9 19
12 22
Earliest Start
and
Earliest Finish Times
Finish Start
St. Adolf’s Hospital
56
Earliest Start
and
Earliest Finish Times
Finish
Earliest start time Earliest finish time
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
Critical
path
Start
St. Adolf’s Hospital
57
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
Latest Start
and
Latest Finish Times
Finish Start
St. Adolf’s Hospital
58
Latest Start
and
Latest Finish Times
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
63 69 Latest
finish
time
Finish Start
St. Adolf’s Hospital
59
Latest Start
and
Latest Finish Times
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
63 69
Latest
start
time
Latest
finish
time
Finish Start
St. Adolf’s Hospital
60
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
53 63 63 69
59 63
Latest Start
and
Latest Finish Times
Finish Start
St. Adolf’s Hospital
61
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
53 63 63 69
24 59
19 59
35 59
59 63
Latest Start
and
Latest Finish Times
Finish Start
St. Adolf’s Hospital
62
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
53 63 63 69
14 24 24 59
9 19 19 59
35 59
59 63
Latest Start
and
Latest Finish Times
Finish Start
St. Adolf’s Hospital
63
Latest Start
and
Latest Finish Times
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Earliest start time Earliest finish time
Latest start time Latest finish time
Critical
path
Finish Start
St. Adolf’s Hospital
64
Gantt Charts
St. Adolf’s Hospital
65
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Activity Slack
Analysis
Finish Start
St. Adolf’s Hospital
66
St. Adolf’s Hospital
Activity Slack
Analysis
Start
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Activity Slack
Finish
67
Activity Slack
Analysis
Start
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Activity Slack
Slack = LS – ES
or
Slack = LF – EF
Finish
68
Activity Slack
Analysis
Start
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Activity Slack
SlackK = 63 – 63
or
SlackK = 69 – 69
Finish
69
Activity Slack
Analysis
Start
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Activity Slack
SlackK = 0
or
SlackK = 0
Finish
70
Activity Slack
Analysis
Start
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Finish
71
Activity Slack
Analysis
Start
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Node Duration ES LS Slack
Finish
72
Activity Slack
Analysis
Start
A
12
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 69
22 57
59 63 19 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 69
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Node Duration ES LS Slack
A 12 0 2 2
B 9 0 0 0
C 10 12 14 2
D 10 9 9 0
E 24 9 35 26
F 10 12 53 41
G 35 22 24 2
H 40 19 19 0
I 15 12 48 36
J 4 59 59 0
K 6 63 63 0
Finish
73
C
10
G
35
E
24
I
15
F
10
12 27
12 22
22 57
9 33
12 22
48 63
53 63
14 24 24 59
35 59
B
9
0 9
0 9
D
10
9 19
9 19
H
40
19 59
19 59
J
4
59 63
59 63
K
6
63 69
63 69
Critical Path
Node Duration ES LS Slack
A 12 0 2 2
B 9 0 0 0
C 10 12 14 2
D 10 9 9 0
E 24 9 35 26
F 10 12 53 41
G 35 22 24 2
H 40 19 19 0
I 15 12 48 36
J 4 59 59 0
K 6 63 63 0
Finish
74
C
10
G
35
E
24
I
15
F
10
12 27
12 22
22 57
9 33
12 22
48 63
53 63
14 24 24 59
35 59
B
9
0 9
0 9
D
10
9 19
9 19
H
40
19 59
19 59
J
4
59 63
59 63
K
6
63 69
63 69
Critical Path
A
12
0 12
2 14
Finish Start
Probabilistic Time Estimates
75 (a) Mean
m a b Time
Pro
ba
bil
ity
Probabilistic Time Estimates
76 (b) Mean
a b m
3s 3s
Area under curve
between a and b is
99.74%
Time
Pro
ba
bil
ity
77
A F
I
C G Finish
D
E
H B J
K
Start
Probabilistic Time
Estimates
St. Adolf’s Hospital
78
Activity B
Most
Optimistic Likely Pessimistic
(a) (m) (b)
7 8 15
Probabilistic Time
Estimates A F
I
C G Finish
D
E
H B J
K
Start
St. Adolf’s Hospital
79
Activity B
Most
Optimistic Likely Pessimistic
(a) (m) (b)
7 8 15
Probabilistic Time
Estimates
te = = 9 weeks 7 + 4(8) + 15
6
s2 = = 1.78 ( ) 15 - 7
6
2
A F
I
C G Finish
D
E
H B J
K
Start
St. Adolf’s Hospital
Expected Time
Time Variance
Project Times
80
• Expected project time (T)
– Sum of critical path activity
times, t
• Project variance (V)
– Sum of critical path activity
variances, v
Used to obtain probability
of project completion!
81
Optimistic Likely Pessimistic Expected Variance
Activity (a) (m) (b) Time (te ) (s2 )
Time Estimates (wk) Activity Statistics
St. Adolf’s Hospital
82
Optimistic Likely Pessimistic Expected Variance
Activity (a) (m) (b) Time (te ) (s2 )
Time Estimates (wk) Activity Statistics
A 11 12 13 12 0.11
B 7 8 15 9 1.78
C 5 10 15 10 2.78
D 8 9 16 10 1.78
E 14 25 30 24 7.11
F 6 9 18 10 4.00
G 25 36 41 35 7.11
H 35 40 45 40 2.78
I 10 13 28 15 9.00
J 1 2 15 4 5.44
K 5 6 7 6 0.11
St. Adolf’s Hospital
83
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
St. Adolf’s Hospital
84
s2 = (variances of activities) z = T –TE
s2
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
St. Adolf’s Hospital
85
s2 = (variances of activities) z = T – TE
s2
s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
St. Adolf’s Hospital
86
s2 = (variances of activities) z = T – TE
s2
s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89
z = 72 – 69
11.89
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
St. Adolf’s Hospital
87
s2 = (variances of activities) z = T – TE
s2
s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89
z = = 0.87 72 – 69
11.89
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
St. Adolf’s Hospital
88
s2 = (variances of activities) z = T – TE
s2
s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89
z = = 0.87 72 – 69
11.89
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
Pz = .8078 .81
St. Adolf’s Hospital
89
s2 = (variances of activities) z = T - TE
s2
s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89
z = = 0.87 72 - 69
11.89
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
Project duration (weeks)
69 72
Probability of
meeting the
schedule is
0.8078
Length of
critical path
Normal distribution:
Mean = 69 weeks;
s = 3.45 weeks
Probability of
exceeding 72
weeks is 0.1922
St. Adolf’s Hospital
90
s2 = (variances of activities) z = T – TE
s2
s2 = 0.11 + 2.78 + 7.11 + 5.44 + 0.11 = 15.55
z = = 1.27 72 – 67
15.55
Probabilities
Path = A - C - G - J - K
T = 72 days TE = 67 days
From Appendix 2
Pz = .8980 .90
St. Adolf’s Hospital
Γιατί να τελειώσω νωρίτερα???
91
Πιθανότητα να συμβεί
Χαμηλή
Υψηλή
Πιθανή Διάρκεια
(m)
Σύντομη (α)
Μεγάλη (b)
(TE)
Έχω καιρό ακόμη ...
Parkinson Law
Works Expand to fill the allotted time
Παράδειγμα πιθανότητας ολοκλήρωσης
έργου
92
Ποια είναι η αναμενόμενη πιθανότητα ολοκλήρωσης έργου
διάρκειας 40 εβδομάδων με τυπική απόκλιση 5 εβδομάδες.
Ποια είναι η πιθανότητα να τελειώσει το έργο σε 50 εβδομάδες
ή λιγότερο.
PERT Probability Example
You’re a project planner for General
Dynamics. A submarine project has
an expected completion time of 40
weeks, with a standard deviation of
5 weeks. What is the probability of
finishing the sub in 50 weeks or
less?
93
© 1995
Corel Corp.
Converting to Standardized Variable
94
T = 40
s = 5
50 X
Normal
Distribution
Z X T
= -
= -
= s
50 40
5 2 0 .
m z = 0
s Z = 1
Z 2.0
Standardized Normal
Distribution
Obtaining the Probability
95
m z = 0
s Z = 1
Z 2.0
Z .00 .01
0.0 .50000 .50399
: : : :
2.0 .97725 .97784 .97831
2.1 .98214 .98257 .98300
Standardized Normal Probability Table
(Portion)
Probabilities in body
.02
.50798
.97725
Factors to Consider when Crashing
96
• The amount by which an activity is crashed is, in
fact, permissible.
• Taken together, the shortened activity durations will
enable one to finish the project by the due date.
• The total cost of crashing is as small as possible.
Advantages of PERT/CPM
97
• Especially useful when scheduling and controlling large projects.
• Straightforward concept and not mathematically complex.
• Graphical networks aid perception of relationships among project activities.
• Critical path & slack time analyses help pinpoint activities that need to be
closely watched.
• Project documentation and graphics point out who is responsible for various
activities.
• Applicable to a wide variety of projects.
• Useful in monitoring schedules and costs.
Limitations of PERT/CPM
98
• Assumes clearly defined, independent, & stable
activities
• Specified precedence relationships
• Activity times (PERT) follow
beta distribution
• Subjective time estimates
• Over-emphasis on critical path
Gantt diagrams
Henry Gantt
Gantt Diagrams
• Standard way to present a schedule
Διάγραμμα Gantt
Milestones • Quite important for project management
• Signal the end of a verifiable task.
• Linked with deliverables
• Should be SMART :
– Specific
– Measurable
– Assignable
– Realistic
– Time-framed
Monitoring progress with Gantt charts
Gantt Charts
• Advantages
– Easy to understand
– Easy to show progress and status
– Easy to maintain
– Most popular view to communicate project status to client
and/or senior management
• Disadvantages
– Can be superficial
– Not always easy to see precedence, relationships
104
Thank you!