3nd Quarter Contractor Business Meeting
September 14, 2012
Mike KehoePlant Engineering
Facilities Session
2
Agenda
– Huntington-Ingalls Incorporated video– Unplanned Event – Argon Pipe Leak – Kehoe– Crane Accident at Pier 6 – Kehoe– Safety – Rod Taylor
• Contractor propane bottles• Grating hazard (bicycle hazard)• Safety harness• September is Fire Prevention Month
3
Unplanned Event – Argon Pipe Leak
• June 12, 2012 - Southeast corner of Building 213.
• Concrete forms were being installed.
• Form pin was driven into a 1 ½” copper argon gas pipe.
• Ground not marked after backfill.
• Follow procedures. Must renew excavation boundaries and marks.
4
Crane Operations
• Problem areas – Crane Related Deficiency Reports (CRDR), lift plans
• Accident Rates – 1 accident at Pier 6 since last meeting. Going well. Keep up the good work.
• When the cable touched the electrical boom, it was determined that the cable was a part of the crane; therefore, it was interpreted as if the crane hit the electrical boom.
• When we write on a lift plan that casual or incidental contact will take place, the crane quality control team must give written approval of the lift plan. Part of crane accident reporting procedure.
5
Definition of a Reportable Crane Accident
• An accident occurs when any one or more of the elements in the envelope of operation fails to perform correctly during the L&H operation, including operation during maintenance or testing resulting in the following:
• (a) Personnel injury or death.
• (b) Material or equipment damage
• (c) Dropped load
• (d) Derailment
• (e) Two-blocking
• (f) Overload
• (g) Collision, including unplanned contact between the load, crane and/or other objects.
6
O27 - Safety
Contractor propane cylinders
• All contractor propane cylinders shall be identified with a label or tag containing a minimum of company name and emergency telephone number.
7
O27 - Safety
Grating hazard (bicycle hazard)
• Grating openings run parallel to the primary direction of travel. Bicycle tires can get stuck causing the bike to come to a sudden stop.
• Please reports any such hazards to your contract coordinator.
8
O27 - Safety
Safety harnesses and fall protection
9
O27 - Safety
September is Fire Prevention Month
• 35 foot rule
• Reporting fires
• Fire aboard USS Miami
10
QUESTIONS????
• If you have questions regarding this presentation, please contact your Contract Coordinator or: