    Wireless hardware installation key point

    Orange Project_JordanV1.4

    This document including most frequently mistakes has made during site installation

    and swap.

    If you have any questions and suggestion regarding installation and swap,

    please feedback

    [email protected]

    [email protected]

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    2/431

    1Contents

    1. Cabinet1.1 Cabinet location

    1.2 Equipment layout in BTS and TP cabinet of scenario 1

    2. Main equipment2.1 RRU Installation principle

    2.2 MRFU Install Position Principle

    2.3 The mounting ears and cable claw of DCDU -12B

    2.4 Sensor installation in TP48200A power cabinet

    2.5 AC input power cable installation

    2.6 Battery installation in TP48200A power cabinet

    2.7 TP48200A Power System Commissioning

    3. Antenna&feeder system3.1 Distinguish the right port of New antenna

    3.2 Use double screws to fix Wireless ANT on mast/pole

    3.4 Color ring principle for jumper

    3.5 How to measure the azimuth of ANT

    3.6 How to adjust the down-tilt of ANT

    4. DC power distribution

    4.1 The TP48200A MCB distribution for DCDU4.2 The DCDU distribution for RRU

    5. Cable installation5.1 Cable route at outdoor cabinets

    5.2 Monitor cable from TP to BBU

    5.3 Transmission cable from MW IDU to BTS

    5.4 Install AISG cable from ANT to RRU

    5.5 Hoist RRU fiber

    6. Grounding6.1 cabinet & RRU grounding

    6.2 RRU Power cable grounding

    6.3 7/8feeder grounding

    7. Waterproof7.1 The connector of jumper waterproofed

    7.2 7/8feeder grounding waterproofed

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    3/432

    cabinet

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    4/43

    800mm

    3

    1.1 The base &cabinet installation on concrete

    BTS3900A & TP48200A cabinet on concrete must be 40-150mmaway from each other, make sure the door of cabinet can beopened normally.

    The cable between two cabinetsneed to use PVC Pipe, to protectcable from damage !!!

    50mm

    2 cabinet at same level

    BTS39 A TP482 A

    BTS39 A TP482 A

    BTS at Left TP at Right

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    5/434

    1.2 Equipment layout of scenario 1 (1/3)

    General view

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    6/43

    1.2 Equipment layout of scenario 1 (2/3)

    5

    The equipment layout in BTS3900A cabinet

    DCDU-12A for

    BBU and Fan

    BBU3910

    DCDU-12B for3G and 4G RRU

    1DCDU-12B maximumsupport 6 RRU, In casemore than 6RRUs, mustadd another DCDU-12Bhere.

    DCDU-12A for

    MRFU power

    MR

    FUd

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    7/43

    1.2 Equipment layout of scenario 1 (3/3)

    6

    The equipment layout in TP48200A cabinet

    DDF for E1s

    DCDU-12B for RTN power

    RTN location

    AC/DC Breaker

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    8/437

    Main equipment

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    9/438

    2.1 RRU Install Position Principle

    If have space on mast/ tower, each sector install 2 RRUs, one is 3G RRU,

    another is 4G RRU

    If no enough space on mast/ tower, 3 RRUs can be combined, they are same

    frequency . the other 3RRUs also be combined.

    One RRU is 1800M_4Ganother is 2100M_3G

    Same frequency 18 M_4G

    4G

    4G

    4G

    Same frequency 21 M_3G

    3G 3G 3G

    Using joint bar connect

    each RRU

    Using joint bar connect each RRU

    4G

    3G

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    10/439

    2.2 MRFU Install Position Principle

    MRFU module for 2G, install at the low rack of BTS3900A cabinet

    If the sector of 2G is 1

    3, MRFU install as below:

    If the sector of 2G is 46, MRFU install as below:

    1

    2

    3

    1 2 3 4 5

    6

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    11/4310

    2.3 The mounting ears and cable claw of DCDU -12B

    Before install the DCDU-12B in BTS&TP cabinet, must adjust the mounting ear to moveforward, and install cable claw at DCDU-12B right side

    The material of DCDU-12B :

    Cable claw for DCDU-12BMounting ear

    Mounting ear

    Cable claw for DCDU-12B

    Move forward Move forward

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    12/43

    2.4 Lamp & Sensor installation inTP48200A cabinet

    11

    Sensor Installation Layout

    Water Sensor

    Lamp

    Smoke Sensor

    Temperature

    and Humidity

    Sensor

    Sensor Cable Port

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    13/43

    2.4 Lamp installation(1/4)

    12

    Installing a lamp

    Procedure:

    Install a lamp on the fastener on the right of the cabinet.

    Connect the negative (-) lamp power cable for the lamp to the 10A (C10)load circuit breaker.

    Connect the positive (+) lamp power cable to the RTN+ busbar.

    Lamp Power Cable (-)

    Lamp Power Cable (+)

    Lamp

    RTN+busbar

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    14/43

    2.4 Smoke Sensor installation(2/4)

    13

    Procedure:

    Remove screws that secure the smoke sensor to the right of the cabinet top.

    Dismantle smoke sensor base from the sensor, secure the smoke sensor base to

    the top of the cabinet by using the removed screws.

    Secure the smoke sensor to the base.

    Connect one end of the signal cable to the smoke sensor and the other end tothe SMOKE port on the UIM panel.

    Installing a Smoke Sensor

    Smoke SensorInstallation Location

    1

    Smoke Sensor Base

    2

    3

    SmokeSensor

    Smoke Sensor Port

    Smoke Sensor Port

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    15/43

    2.4 Water Sensor installation (3/4)

    14

    Installing a Water Sensor

    Procedure:

    Put the water sensor in the cable strip in the right part of the cabinet bottom(ensure that the sensor is 5 mm to 10 mm away from the cabinet bottom), and

    secure the sensor with a cable tie.

    Connect the water sensor signal cable to the WATER port on the UIM panel.

    Water Sensor Port

    Water Sensor Port

    Water Sensor

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    16/43

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    17/43

    2.5 AC input power cable installation

    16

    Procedure:

    Lay out an AC input power cable, and route it into the cabinet through thecable hole in the left part of the cabinet bottom.

    Find a spare(or new purchase and install) 3*25A(there-phase 25A) AC circuitbreaker in AC box.

    Secure the AC input power cable to the corresponding AC input circuit breakers

    and terminal.

    Installing AC Input Power Cables

    Note:

    If the AC box cant reuse or re-install 3*25A breaker, only allow to

    use single-phase breaker(at least 1*10A) for temporary pre-

    commissioning of BTS/MW, But should turn off the existing power

    system before swapping, and relocate Huawei power system AC

    INPUT to three-phase circuit breaker(3*25A).

    3*25ACircuit Breaker

    in AC box

    AC INPUT

    Circuit Breaker

    in Power System

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    18/43

    2.6 Battery installation

    17

    Procedure:

    Installing Batteries

    Remove the insulation cover from thebatteries.

    Install copper bars between batteries.

    Reinstall the insulation covers onto thetwo batteries in the middle.

    Take negative battery cables from the left side of the battery compartment, and

    connect the cables to negative battery terminals.

    After you install all negative battery cables, take positive battery cables from the

    right side of the battery compartment, and connect the cables to positive batteryterminals.

    Reinstall the insulation covers onto the batteries on the left and right sides.

    Install batteries into thebattery compartment in the

    sequence.

    Insulation Cover

    Copper Bar

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    19/43

    2.7 Power System Commissioning(1/2)

    18

    Procedure:

    Measure the input voltage on the AC input circuit breaker. The value shouldrange from 85 V AC to 300 V AC.

    Switch on the AC input circuit breaker and measure the output voltage of theAC input circuit breaker. The value should range from 85 V AC to 300 V AC.

    Check that the indicators on the rectifiers are steady on.

    Measure the voltage between the -48 V busbar and the RTN+ busbar. The valueshould range from -42 V DC to -58 V DC.

    1. Connecting the AC Power Supply

    Procedure:

    2. Setting the Display Language

    3. Setting the Date and Time

    Main Menu Second Level Menu Third Level Menu Default Value Setting

    SettingWizard

    Date and Time

    Date and Time -Set to the local date

    and time.

    Time ZoneUTC +08:00

    BeijingSet to the local time

    zone.

    NTP Enable No

    Yes/No

    NOTE

    Set the parameter toYesif you need tosynchronize the SMUtime and the sitenetwork server time.

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    20/43

    2.7 Power System Commissioning (2/2)

    19

    4. Setting Battery Parameters

    5. Setting Sensor Parameters

    Main

    Menu

    Second

    Level Menu

    Third

    Level Menu

    Fourth

    Level Menu

    Default

    Value

    Setting Value

    Parameters Settings

    Battery

    BasicParameters

    Battery 1Connected

    Yes If 2battery strings are

    connected, set Battery 1Connectedto BatteryConnectedto Yes.

    Battery 2Connected

    Yes

    Rated Capacity 150 Ah

    Rated capacity of thebatteries in a battery string.

    NOTE

    The batteries controlled byone circuit breaker or fuseare called a battery string.

    OtherParameters InstallationTime - Set to the current date

    Main Menu

    Second

    Level Menu

    Third

    Level Menu

    Fourth

    Level Menu

    Default Value Setting

    ParametersSettings Power System Sensor Config.Para.

    Water Sensor None

    Set to Yes.

    Smoke Sensor None

    Ambient Temp.Sensor

    None

    Ambient Humi.Sensor

    None

    Procedure:

    Switch off AC input circuit breakers.

    Switch on the battery circuit breaker, then switch on AC input circuit breakers.

    Switch all the circuit breakers to the appropriate status based on site requirements.

    Observe the power system for 15 minutes. If no alarm (excluding door alarms) is

    generated on the LCD during this period, the voltage and current for batteries andloads are normal.

    6. Connecting the Battery Supply

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    21/4320

    Antenna&feeder system

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    22/43

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    23/4322

    3.2 Use double screws to fix Wireless ANT

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    24/4323

    3.3 Color ring principle

    Sector A

    Blue

    900M_GSM 2100M_3G 1800M_4G

    TX RX TX RX TX RX

    1 2 3 4 5 6

    Sector B

    Red

    900M_GSM 2100M_3G 1800M_4G

    TX RX TX RX TX RX

    1 2 3 4 5 6

    Sector C

    Yellow

    900M_GSM 2100M_3G 1800M_4G

    TX RX TX RX TX RX

    1 2 3 4 5 6

    Sector D

    White

    900M_GSM 2100M_3G 1800M_4G

    TX RX TX RX TX RX

    1 2 3 4 5 6

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    25/4324

    3.4 How to measure the azimuth of ANT

    Step1: Make the mid-line of compass is same with thedirection of Antenna

    Azimut h= the red value found on the compass via theobserving hole

    Record the value.

    Be sure that the position of compass was put it correctly

    Dont test on the tower

    Keep more than 2 meters from the tower

    Keep the compass in horizontal

    Make the compass in same direction with target

    antenna

    Record and call OMC to confirm the azimuth value of all the sectors

    Read the Red number from the observewindow (the first number)

    Make the compass same direction withantenna

    horizontal

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    26/4325

    3.5 How to adjust the down-tilt of ANT

    This small triangle using todefine mechanical down tilt

    The HW Tri-band antenna length is 2.6 meters, should set mechanical tiltaccording to the marker of L=2.6

    Record and call OMC to confirm the M-tilt value of all the sectors

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    27/4326

    DC power distribution

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    28/4327

    4.1 The TP48200A MCB distribution for DCDU

    BATLVDLVD

    Note:

    IF RRU more than 6pcs, must add one new DCDU-12B_2. It is the red color in the BTScabinet as picture.

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    29/4328

    4.2 The RRU Power distribution at DCDU-12B

    1DCDU-12B maximum suppor6RRU,iF RRU more than 6pcs,must add one new DCDU-12B.It is the red one DCDU-12B_2

    in the picture.

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    30/4329

    Cable installation

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    31/4330

    5.1 Cable route at cabinet

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    32/43

    5.2 Install Monitor cable from TP to BBU

    31

    The blue cable is monitor cable from TP to BBU

    Note:

    For temporary scenario, BBUinstall at TP cabinet, the monitorcable from TP to BBU, BBU side

    is port

    Monitor0

    at UPEUboard.

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    33/43

    5.3 Transmission cable from MW IDU to BTS

    32

    OTE:use the RTN950, the transmission

    able should connect to the GEectrical port 3 of EG4 board.

    Connect to RTN905 GE port3

    Connect to RTN950 EG4--GE port3

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    34/4333

    5.4 Install AISG cable from ANT to RRU

    AISG cable will be installed from 3G RRU 3839 to antenna

    AISG cable input

    inside the RRU

    AISG cable input on

    the antenna

    3G RRU

    AISG cable is waterproof, no need waterproof for connector.

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    35/4334

    5.5 Hoist RRU fiber

    Do not remove the stretch

    sling and protection pipe

    when lifting RRU fiber !!

    Making asimple wirespool tools

    Using wirespool tools

    3 fiberstwisttogether

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    36/4335

    Grounding

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    37/4336

    6.1 Cabinet & RRU grounding

    BTS3900A cabinet grounding TP48200A cabinet grounding

    RRU grounding

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    38/4337

    6.2 RRU power cable grounding (1/2)

    The shielding layer of RRU power cable need to grounding usingclip in RRU

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    39/4338

    6.2 RRU power cable grounding(2/2)

    When RRU power cable through into BTS cabinet, must use 6 in 1 grounding clamp for shieldlayer grounding of RRU power cable !

    6 in 1 grounding clamp, 1clamp can fix 6pcs RRU powercable. remove the black cover of power cable, and fix in

    clamp

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    40/4339

    6.3 7/8feeder grounding

    7/8feeder need to grounding at the bottom of tower/mast.

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    41/4340

    Waterproof

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    42/4341

    7.1 The connector of jumper waterproof

  • 7/21/2019 3.5 Orange Handbook - Wireless Hardware Installation Key Points V1.4_201...

    43/43

    7.2 7/8feeder waterproof

    The shielding layer of 7/8feeder need to grounding at the bottomof tower /mast !!!