341st cons

17
T A K I N C A R E O F B U S I N E S S 3 4 1 s t C O N T R A C T I N G 1 341st CONS Home of the Two-Time AFSPC Top Dollar Champions! “Takin Care of Business”

Upload: eliora

Post on 25-Feb-2016

50 views

Category:

Documents


0 download

DESCRIPTION

341st CONS. “Takin Care of Business”. Home of the Two-Time AFSPC Top Dollar Champions!. Claims. Claims defined FAR Clauses Basis for Claims Changes Constructive Changes Delays Breach of Implied Duties Mistake Allowable Compensation . Claims. Claim defined - FAR 33.201 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: 341st CONS

TA K IN ’ C A R E O F B U SI N ESS

341st C O N T R A C T IN G

1

341st CONS

Home of theTwo-Time AFSPC

Top Dollar Champions!

“Takin Care of Business”

Page 2: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

2

Claims

• Claims defined• FAR Clauses• Basis for Claims

– Changes– Constructive Changes– Delays– Breach of Implied Duties– Mistake

• Allowable Compensation

Page 3: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

3

Claims

• Claim defined - FAR 33.201– “a written demand, as a matter of right”– seeking payment of a “sum certain” or adjustment

or interpretation of contract terms– “arising under or relating to a contract”– certification required if over $100K

• Customer/requiring activity must be advised and involved

• CO required to respond w/i 60 days

Page 4: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

4

Claims

• Contract Clauses– FAR 52.233-1 Disputes (Contract Disputes Act of

1978)– FAR 52.243-1 Changes - Fixed-Price– FAR 52.243-4 Changes (used in construction

contracts)– FAR 52.242-17 Government Delay of Work– FAR 52.242-14 Suspension of Work– FAR 52.236-2 Differing Site Conditions

Page 5: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

5

Claims

• The Changes Clause - FAR 52.243-1– The CO may, at any time, by written order, without

notice to sureties make changes within the general scope of the contract in any one or more of the following:• Drawings and specs• Method of shipment or packing• Place of delivery

Page 6: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

6

Claims

• Changes - fixed-price– Contractor must assert its right to an adjustment

within 30 days from receipt of a written order.

• What if -– No written notice from contractor is received within

30 days?– No written order is given?– Change is outside the general scope of contract?

Page 7: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

7

Claims

• Constructive Change Doctrine– Any oral direction, instruction, interpretation or

determination which can be reasonably construed as a change to the contract.

• What if - – The oral directive comes from someone other than

a CO?

Page 8: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

8

Claims

• Changes Clause-Construction FAR 52.243-4– The CO may, at any time, without notice to

sureties, by written order designated or indicated to be a change order, make changes within the general scope of the contract, including:• Drawings and specs• Method or manner of performance• In GFP, GFM or site• Acceleration in performance of the work

Page 9: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

9

Claims

• Changes Clause - Construction– Provides for adjustment based on oral “direction,

instruction, interpretation or determination.”

• Contractor must provide written notice that it considers the action to be a change

• No adjustment shall be allowed for costs incurred more than 20 days before Contractor’s written notice to CO, except for an adjustment based on defective specs.

Page 10: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

10

Claims

• Impact Under Changes Clause– “If any change increases or decreases a

contractor’s cost of, or time required for, performance . . . the Contracting Officer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.”

• Profit included

Page 11: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

11

Claims

• Equitable adjustment– What is it?– Claim?

• Failure to agree to an adjustment shall be a dispute• Contractor required to continue performance

– Certification required?– DFARS 243.2

Page 12: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

12

Claims

• Impact under delay of work clauses

– An adjustment to the cost of performance (excluding profit) and delivery or performance dates

Page 13: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

13

Claims

• Differing Site Conditions - FAR 52.236-2– Allows for additional compensation when

subsurface or unknown latent physical conditions are experienced that differ materially from those indicated in the contract.

– Contractor must notify the Contracting Officer before conditions are disturbed.

Page 14: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

14

Claims

• Claims for Breach of Contract– Breach of implied duties

• Cooperation• Good faith and fair dealing• Implied warranty of adequacy of specifications

– Cardinal Changes

• Claims for Mistake– Unilateral vs. Bilateral

Page 15: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

15

Claims

• Modifications in Settlement of Claims

– Must include release language

– Must have legal review and approval regardless of dollar value

Page 16: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

16

Claims

• What if -

– Contractor submits a legally deficient claim?– Contractor submits an unsupported claim?– Contractor understates cost impact and we know

it?

Page 17: 341st CONS

TA K IN ’ C A R E O F B U SI N E SS

341st C O N T R A C T IN G

17

Claims

• Conclusion– Evaluate:

• Has a claim been submitted?– Are all legal requirements present?

• Has adequate supporting data been submitted?• Has customer/requiring activity evaluated the claim?• Has a valid basis for a claim been alleged?• Has SJA reviewed claim?• Does modification include release & satisfaction?