3.16 duration estimating worksheet
TRANSCRIPT
![Page 1: 3.16 Duration Estimating Worksheet](https://reader036.vdocuments.us/reader036/viewer/2022082421/55cf9aab550346d033a2d38e/html5/thumbnails/1.jpg)
DURATION ESTIMATING WORKSHEET
Project Title: Date Prepared:
Parametric Estimates
WBS ID Effort Hours % Available
Analogous Estimates
WBS ID Multiplier
Three Point Estimates
WBS ID
Resource Quantity
Performance Factor
Duration Estimate
Previous Activity
Previous Duration
Current Activity
Duration Estimate
Optimistic Duration
Most Likely Duration
Pessimistic Duration
Weighting Equation
Expected Duration Estimate
![Page 2: 3.16 Duration Estimating Worksheet](https://reader036.vdocuments.us/reader036/viewer/2022082421/55cf9aab550346d033a2d38e/html5/thumbnails/2.jpg)
![Page 3: 3.16 Duration Estimating Worksheet](https://reader036.vdocuments.us/reader036/viewer/2022082421/55cf9aab550346d033a2d38e/html5/thumbnails/3.jpg)
Parametric Estimates
WBS ID Effort Hours % available1.1 150 2 75%
Analogous Estimates
WBS ID Prior activity Duration
1.1 Build deck 160 sq. ft. 10 days
Three Point Estimates
WBS ID1.1 20 25 36
Resource Quantity
Prior Variable
Optimistic estimate
Most likely estimate
Pessimistic estimate
![Page 4: 3.16 Duration Estimating Worksheet](https://reader036.vdocuments.us/reader036/viewer/2022082421/55cf9aab550346d033a2d38e/html5/thumbnails/4.jpg)
Parametric Estimates
80% 125
Analogous Estimates
Multiplier
200 sq. ft. 1.25 12.5
Three Point Estimates
(o+4m+p)/6 26
Performance factor
Duration Estimate
Current variable
Duration Estimate
Weighting factor
Expected Duration Estimate