3.16 duration estimating worksheet

6
DURATION ESTIMATING WORKSHEET Project Title: Date Prepared: Parametric Estimates WBS ID % Available Analogous Estimates WBS ID Multiplier Three Point Estimates WBS ID Effort Hours Resource Quantity Performance Factor Previous Activity Previous Duration Current Activity Optimistic Duration Most Likely Duration Pessimistic Duration Weighting Equation

Upload: rochdibahiri4184

Post on 28-Nov-2015

16 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: 3.16 Duration Estimating Worksheet

DURATION ESTIMATING WORKSHEET

Project Title: Date Prepared:

Parametric Estimates

WBS ID Effort Hours % Available

Analogous Estimates

WBS ID Multiplier

Three Point Estimates

WBS ID

Resource Quantity

Performance Factor

Duration Estimate

Previous Activity

Previous Duration

Current Activity

Duration Estimate

Optimistic Duration

Most Likely Duration

Pessimistic Duration

Weighting Equation

Expected Duration Estimate

Page 2: 3.16 Duration Estimating Worksheet
Page 3: 3.16 Duration Estimating Worksheet

Parametric Estimates

WBS ID Effort Hours % available1.1 150 2 75%

Analogous Estimates

WBS ID Prior activity Duration

1.1 Build deck 160 sq. ft. 10 days

Three Point Estimates

WBS ID1.1 20 25 36

Resource Quantity

Prior Variable

Optimistic estimate

Most likely estimate

Pessimistic estimate

Page 4: 3.16 Duration Estimating Worksheet

Parametric Estimates

80% 125

Analogous Estimates

Multiplier

200 sq. ft. 1.25 12.5

Three Point Estimates

(o+4m+p)/6 26

Performance factor

Duration Estimate

Current variable

Duration Estimate

Weighting factor

Expected Duration Estimate