3 spaces nov 09

62
Engineering IT Infrastructure www.Capitoline.eu Introduction to Data Centre Design Barry Elliott BSc RCDD MBA CEng Spaces and Spaces and Places Places November 09

Upload: somy-else

Post on 29-Nov-2014

46 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Introduction toData Centre Design

Barry Elliott BSc RCDD MBA CEng

Spaces and PlacesSpaces and Places

November 09

Page 2: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Spaces and Places

• Suitability of location

• Defining and sizing the ‘Spaces’

• Basic facilities requirements

Page 3: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Physical location and architectural issues

Does the data centre structure already exist, or are building works required?Are there any known seismic problems in the area?Any known ground subsidence problems in this area, e.g. old mining works?Any known security/ criminal problems likely with this area?Is connection to mains electrical, gas, water, sewage and telecoms services available?Is there a very close proximity to main roads, railway lines, airports, oil or chemical storage or works or military or nuclear installations?

Page 4: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Physical location and architectural issues

•Is there easy access to the site by road with parking/loading facilities available?•Are there lifts/goods lifts available if the data center is not on the ground floor? Are lifts big enough for the likely sizes of loads, e.g. UPS units etc.•Are there any excessive external sources of noise or vibration that will impact upon the data center site?•Will the proposed data center be a cause of noise or disturbance to adjoining offices?•Are there any potential EMC problems, e.g. mobile phone masts, lift motors on the other side of a wall, proximity to radar transmitters etc?•Is there access to a suitable external site for the air conditioner heat exchangers?•Is the building or room susceptible to lightning strikes?

Page 5: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

TIA 942 location recommendations

are: •The building should not be in the flight path of any nearby airports.•The building should be no closer than 0.8 km (½ mile) from a railroad or major interstate highway to minimize risk of chemical spills.•The building should not be within 0.4 km (¼ mile) of an airport, research lab, chemical plant, landfill, river, coastline, or dam.•The building should not be within 0.8 km (½ mile) of a military base.•The building should not be within 1.6 km (1 mile) of nuclear, munitions, or defence plant.•The building should not be located adjacent to a foreign embassy.•The building should not be located in high crime areas.•EMC risks must be minimised by locating away from radar transmitters and mobile ‘phone masts

Page 6: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

BICSI draft standard on data centre design

• 503 pages

• To be published in 2009

• Complementary to ANSI TIA 942

Page 7: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Very useful American information

Page 8: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

0.8

TIA 942 BICSI BICSI

Railways 0.8 km 1.6 km

Highways 0.8 km 1.6 km

Military bases 1.6 km 13 km

Airport 0.4 km >8 km <48 km

Major met area <16 km

Height above flood level >3m

Waterway or coastline 0.4 km 1.6 km

100 year flood plain 91 m

Fire/police hospital < 8km

Canals/dams/reservoirs 0.4 km 3.2 km

High voltage power lines, petrol stations

1.6 km

Radar, TV 5 km

Fossil fuel power plant 8 km

Nuclear power plant 1.6 km 80 km

Page 9: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Offices next to Buncefield oil depot, Dec 2005

Building on the flight path of Tehran airport

Page 10: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Page 11: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Vodafone data center in Istanbul flooded –Sept 2009

Page 12: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Page 13: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

The ‘Spaces’• Work Area

• Telecommunications Rooms– Or Telecommunications enclosures for small

projects

• Equipment Rooms• Entrance Rooms and Entrance Facilities• Computer Rooms• Data Centres

Page 14: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Horizontal cabling

Telecom Outlet, TO

Work Area

Patch Cable

Equipment or Telecommunications Room

Campus cabling

External telecoms cabling

Entrance facility Computer Room

Main Distribution Area

Backbone/Riser cabling

Telecommunications rooms

Page 15: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Telecommunications Room (TR) and Telecommunications Enclosure (TE)

• A TR is an enclosed architectural space for housing telecommunications equipment, cable terminations, and cross-connect cabling.

• A TE is a case or housing for telecommunications equipment, cable terminations, and cross connect cabling.

Page 16: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Equipment Rooms

• An ER is an environmentally controlled centralized space for telecommunications equipment that usually houses a main or intermediate cross-connect.

• ERs differ from TRs in that ERs are generally considered to serve a building, a campus, a tenant, or a SP, whereas TRs serve a floor area of a building.

Page 17: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Entrance Facility

An EF is expected to provide the following:

• Point of demarcation between the SPs and customer premises cabling (if required).

• Primary (electrical) protection devices governed by the applicable electrical codes.

• Space to house the transition between cabling used in the OSP to cabling approved for intrabuilding use. This usually involves transition to fire-rated cable

Page 18: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Page 19: 3 Spaces Nov 09

Engineering IT Infrastructure

Sizing the Spaces

Page 20: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Telecommunications Room (TR) Guidelines

Floor Space Served

There must be at least one TR or ER per floor.

Multiple rooms are required if the cable length between the HC (FD) and the telecommunications outlet location, including slack, exceeds 90 m (295 ft) or if the usable floorspace to be served exceeds:

Page 21: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

TR sizing –at least 9 sq m

Page 22: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Size of ER• Allow 9 sq m per work area

• Multiply No of work areas by 0.07 sq m

• Minimum size 3 x 5 m

• e.g. 5000 sq m of office space

• 5000/9 = 555

• 555 x 0.07 = 39 sq m

Page 23: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Size of Entrance FacilityBased on frames, ANSI/TIA/EIA-569-A

569A also states a min of 9 sq m for multi-tenanted buildings

space served Floor space dimensions Ent Room area

10 000 3660 x 1 930 7 sq m

20 000 3660 x 2 750 10 sq m

40 000 3660 x 3 970 14.5 sq m

50 000 3660 x 4 775 17.5 sq m

60 000 3660 x 5 600 20.5 sq m

80 000 3660 x 6 810 25 sq m

100 000 3660 x 8 440 31 sq m

Page 24: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

TETR

Telecomm-unications Enclosure

Telecomm-unications Room

Equipment Room

Data centre

Computer RoomSupport areas

Tier 1 20% of CR

Tier 2 30%

Tier 3 80%

Tier 4 100%+

TREF

Entrance Facility EF (2 EF for Tiers 3&4)

ER

Serving a useable floor area of…….

<335 m2 <929 m2 <1860 m2

<7.2 m2 7.2 –15 m2 15-99 m2 100 m2 + (per CR)

CR

Summary of Spaces

Page 25: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Sizing the Computer Room

Page 26: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

With typical 8-tile pitch 1 rack takes a footprint of 0.6 m x 2.4 m = 1.44 m(min pitch 7 tiles, max 9 tiles)

With realistic overheads, 1 ‘working’ rack per 3.16 sq m

What size computer room? By the rack…

Page 27: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

What size of computer room? By the server……..

• ‘Average’ rack mounted server, 370 W

• 29 models, 50 to 900 W, 1 to 4 U• Average fitting into a 4 kW rack, 11 units• For every eight server racks, one comms and

one storage rack

11 servers per rack=0.34 sq m per server

Page 28: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

300

250

200

150

100

50

00 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750

Sq m of floor space

servers

11 servers per rack, 4 kW per rack, 0.34 sq m per server. 8-tile pitch

Page 29: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

IT Yield: How much floor space does useful ICT work?

• Theoretical maximum, ASHRAE 7-tile pitch model, 48%

• Realistic average, 20%

• Equivalent to one rack per 3.3 sq m

Page 30: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Floor space utilisation

   

floor space No of racks racks/sq m efficiency76 31 2.5 26.1%41 15 2.7 23.4%47 15 3.1 20.4%26 8 3.3 19.7%47 14 3.4 19.1%160 45 3.6 18.0%44 9 4.9 13.1%47 9 5.2 12.3%77 14 5.5 11.6%78 14 5.6 11.5%95 15 6.3 10.1%210 27 7.8 8.2%77 5 15.4 4.2%     average 5.3 15.2%  median 4.9 13.1%

     floor space No of racks racks/sq m efficiency

369 144 2.6 25.0%400 140 2.9 22.4%195 68 2.9 22.3%170 57 3.0 21.5%55 18 3.1 20.9%43 14 3.1 20.8%235 74 3.2 20.2%199 60 3.3 19.3%210 60 3.5 18.3%189 44 4.3 14.9%100 20 5.0 12.8%           average 3.3 19.9%  median 3.1 20.8%

Existing sites New build projects

average rack footprint=0.64 sq m (weighted average of 600 and 800 racks)

Source: Capitoline survey

Page 31: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Ideal Computer Room size• If max ‘throw distance’ of aircon unit is 12 m

then max width is 24 m

24 m max

6 m min24 m max

CRAC unit

Rows of racks Ideal size is

between 144 and 600 m2

Page 32: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Ideal Computer Room size

• Rooms larger than 600 square metres tend to be difficult to manage

• They require large amounts of air conditioning

• CRAC units probably need to be in the middle of the floor, which makes calculations difficult

• Gas fire suppression quantities will be huge. A 900 sq m room will be >3600 m3

Page 33: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Sizing the Data Centre building and site

Page 34: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

The relationship of the Spaces within a Data centre (TIA 942)

Separate UPS/battery room recommended if capacity exceeds

100 kVA

Page 35: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Space Function‘Computer room’, ‘server room’, ‘machine room’ etc

To house the computer racks and communications equipment. A generic space with sufficient air conditioning, power supplies and communications cabling to allow a non-application specific IT environment with best use of space

Control room An area, adjoining the computer room, where all control and monitoring functions relevant to the site are concentrated

General office area An office area where the IT staff can work

Telecommunications Entrance Facility

A room or area where all external communications cabling enters the building. It serves as a point of demarcation between different owners of cabling, provides a point for over-voltage protection and allows a transition from external (flammable) cables to internal cables. (Required BS 6701) Two required for T3/T4

Fire gas suppression store

If inert gas is used as the main fire suppression system then it requires a large volume for storage. Alternatively the gas bottles may be placed against a wall adjacent to the Computer Room or if a fluorocarbon gas is used (placed within the Computer Room) this area may be dispensed with

Electrical switch room A room where the external power cables enter the building and forms a point of demarcation between different cable owners plus all main switching and metering

UPS and battery room

For loads in excess of 100 kVA (TIA 942) it is recommended to have a separate UPS and battery room to save space and heat load in the main Computer Room

Generator room To house the standby diesel generators. This may be in or adjacent to the main building

Page 36: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Oil store To house the diesel fuel to run the standby generators for between 8 and 96 hours. This may be in or adjacent to the main building. The electrical switch room, UPS and generator must all be close to each other to minimise electrical losses in long power cables

Storage and build area

An area to store and unpack equipment and to build items like racks without making dust and causing disruption in the main Computer Room

Delivery and loading area

An area adjacent to the main doors to allow heavy equipment to be shipped into the building

Main entrance A secure entrance with anti-piggybacking- airlock controlsPlanning and meeting room

A room to hold meeting and provide additional office space

Internal staff facilities Male/female/disabled toilets. Shower room. Basic dining area and kitchen facilities

Electrical substation Due to the power load it is likely that separate electrical substation would be needed by the utility company. This should be away from the main building to reduce EMC issues

Air conditioning condensers

If split DX units are to be used then a condenser unit is needed for each Computer Room DX unit. These must be in a secure area either adjacent to the main building or even on top of it, but preferably not over the computer room itself

Main gate and hard standing

A secure main gate leading onto hard standing area of sufficient space and strength for HGVs to unload heavy equipment and manoeuvre

External staff facilities

Parking space for cars, bicycle storage and smoking shelter

Page 37: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Ratio of support areas to Computer Room – Uptime Institute

• Tier 1 20%

• Tier 2 30%+

• Tier 3 80-90%

• Tier 4 100%+

Page 38: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

CR 240 m2

Total 620 m2

Support to CR, 160%

Page 39: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

CR 240 m2

Building 620 m2 (2.6 x CR), 160% support areaTotal site footprint 1674 m2 (2.7 x building)

Page 40: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

CR 340 m2

Building 744 m2 (2.2 x CR), 120% support areaTotal site footprint 1674 m2 (2.25 x building)

Page 41: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

CR 480 m2 (2 x 240)Building 990 m2 (2 x CR), 106% support areaTotal site footprint 1998 m2 (2 x building)

Page 42: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Facilities requirements• Room dimensions and height• Floor strength• Connection of services• External services• Access, loading, DDA etc• Décor• Lighting• Fire Regulations

Page 43: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Facilities requirements, in separate chapters

• Raised floor design

• Power supplies, UPS and earthing

• HVAC

• Cable containment and management

• Fire detection and suppression

• Generic cabling and interconnection

Page 44: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Data centres are places of work and are subject to the same rules as any other place of work

• EU Construction Products Directive 89/106/EEC• EU Electromagnetic Compatibility Directive 89/336/EEC• EU Low Voltage Directive 2006/95/EC• EU Measures to improve safety & health of workers at work 89/391/EEC• EU Health & safety requirements of the workplace directive 89/654/EEC• Minimum requirements for the provision of H&S signs at work 92/58/EEC• Noise at work directive 2003/10/EC• Energy services directive 2006/32/EC• EU Energy performance of buildings directive 2002/91/EC

Page 45: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Minimum ceiling height: The minimum height in the computer room shall be 2.6 m (8.5 ft) from the finished floor to any obstruction such as sprinklers, lighting fixtures, or cameras.. A minimum of 460 mm (18 in) clearance shall be maintained from water sprinkler heads.

Absolute min slab to slab height is 2.9 m, i.e. 400 mm under floor, 2.1 m racks, 400 mm air return path

Room height (TIA 942)

Page 46: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Floor strength (TIA 942)

Minimum floor loading capacity The minimum distributed floor loading capacity shall be 7.2 kPA. The recommended distributed floor loading capacity is 12 kPA. The floor shall also have a minimum of 1.2 kPA hanging capacity for supporting loads that are suspended from the bottom of the floor (for example, cable ladders suspended from the ceiling of the floor below). The recommended hanging capacity of the floor is 2.4 kPA.

Page 47: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Lighting shall be a minimum of 500 lux in the horizontal plane and 200 lux in the vertical plane, measured 1 m above the finished floor in the middle of 4 all aisles between cabinets.

Lighting (TIA 942)

Page 48: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Access

Doors shall be a minimum of 1 m wide and 2.13 m high, without doorsills, hinged to open outward (code permitting) or slide side-to-side, or be removable. Doors shall be fitted with locks and have either no center posts or removable center posts to facilitate access for large equipment. Exit requirements for the computer room shall meet the requirements of any other local requirements.

DDA. Ramps to be not less than 1:12 (see Raised Floor section). All pathways to be >900 wide

Page 49: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Decor (TIA 942)

Décor. Floors, walls, and ceiling shall be sealed, painted, or constructed of a material to minimize dust. Finishes should be light in color to enhance room lighting. Floors shall have anti-static properties as per IEC 61000-4-2.

Page 50: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Connection of services

• Electricity supply– Who from, capacity, where does it enter the

building, more than one?

• Telecommunications– Who from, capacity/type, where does it enter the

building, more than one?

• Gas, water, drainage, sewage• No other service should cross the Computer

Room space

Page 51: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

External services

• Suitable location for standby generators– Noise, weight, security, fuel storage,

proximity

• Suitable location for external air conditioning components– DX Condenser units, central chiller system

etc, weight, security, power supplies, proximity

Page 52: 3 Spaces Nov 09

Engineering IT Infrastructure

Fire Regulations

Fire Plan and Risk assessmentEmergency lighting and signageDoors and Emergency exits

Page 53: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Fire safety planThe fire safety plan is a multilayered approach that requires a coordinated plan for 

•Designing for low flammability and fire risk•Operating with low risk•Emergency exits•Emergency lighting•Emergency exit signage•Fire detection, appropriate to the area covered•Fire alarm•Multi-level automatic fire suppression•Manual fire alarm and portable fire extinguishers•Staff training and fire drills in place•Maintenance plan for all equipment involved

Page 54: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

What Is Emergency Lighting?

• The lighting required for use when the supply to normal lighting fails, enabling safe exit from a building

Page 55: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Directives

• The Construction Products Directive (89/106)

• The Workplace Directive (89/654)

• The Signs Directive (90/664)

• The Regulatory Reform (Fire Safety) Order

Page 56: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

EXIT SIGNS• There are, and have been 3 types of exit signs, with an appropriate

level of legislation enforcing each type :.

This sign is now obsolete & was replaced with a

pictogram sign from 24th December 1998

The Interim Format Sign, This sign is

deemed to comply with Signs Directive

and can be used within premises that

already use this format.

The European Signs Directive Format as

designated by the Health & Safety (Signs &

Signals) Regulations. This is now the preferred

format and must be applied to all new

applications.

Page 57: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Stage 1• Points of emphasis – Mandatory locations to cover

specific hazards and highlight safety equipment and signs :

a) NEAR STAIRS – each tread

should receive lightb) NEAR CHANGES OF LEVEL

A 7 point plan can now be considered for the detailed design….

Page 58: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Stage 1

c) NEAR CHANGES IN

DIRECTION & INTERSECTIONS

ALONG CORRIDORS

d) TO ILLUMINATE EXIT DOORS & SAFETY SIGNS

Page 59: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Stage 1

e) NEAR FIRE FIGHTING & FIRST AID EQUIPMENT

f) TO ILLUMINATE FIRE CALL POINTS

Page 60: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Stage 1

g) OUTSIDE AND NEAR TO EACH FINAL EXIT

h) TO ILLUMINATE EXIT DOORS

Page 61: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

Fire exits

• ‘Normal’ risk, furthest distance to the fire exit must be less than 18 m if the room has only one exit

• For rooms with more than one exit the max distance must be > 45 m

• Essentially this means any room more than 80 sq m needs more than one exit

Page 62: 3 Spaces Nov 09

Engineering IT Infrastructure

www.Capitoline.eu

PAS 79:2005 Fire risk assessment. Guidance and a recommended

methodology • 750 mm pathways for escape

• 900 mm if wheelchairs access required