3 spaces nov 09
TRANSCRIPT
Engineering IT Infrastructure
www.Capitoline.eu
Introduction toData Centre Design
Barry Elliott BSc RCDD MBA CEng
Spaces and PlacesSpaces and Places
November 09
Engineering IT Infrastructure
www.Capitoline.eu
Spaces and Places
• Suitability of location
• Defining and sizing the ‘Spaces’
• Basic facilities requirements
Engineering IT Infrastructure
www.Capitoline.eu
Physical location and architectural issues
Does the data centre structure already exist, or are building works required?Are there any known seismic problems in the area?Any known ground subsidence problems in this area, e.g. old mining works?Any known security/ criminal problems likely with this area?Is connection to mains electrical, gas, water, sewage and telecoms services available?Is there a very close proximity to main roads, railway lines, airports, oil or chemical storage or works or military or nuclear installations?
Engineering IT Infrastructure
www.Capitoline.eu
Physical location and architectural issues
•Is there easy access to the site by road with parking/loading facilities available?•Are there lifts/goods lifts available if the data center is not on the ground floor? Are lifts big enough for the likely sizes of loads, e.g. UPS units etc.•Are there any excessive external sources of noise or vibration that will impact upon the data center site?•Will the proposed data center be a cause of noise or disturbance to adjoining offices?•Are there any potential EMC problems, e.g. mobile phone masts, lift motors on the other side of a wall, proximity to radar transmitters etc?•Is there access to a suitable external site for the air conditioner heat exchangers?•Is the building or room susceptible to lightning strikes?
Engineering IT Infrastructure
www.Capitoline.eu
TIA 942 location recommendations
are: •The building should not be in the flight path of any nearby airports.•The building should be no closer than 0.8 km (½ mile) from a railroad or major interstate highway to minimize risk of chemical spills.•The building should not be within 0.4 km (¼ mile) of an airport, research lab, chemical plant, landfill, river, coastline, or dam.•The building should not be within 0.8 km (½ mile) of a military base.•The building should not be within 1.6 km (1 mile) of nuclear, munitions, or defence plant.•The building should not be located adjacent to a foreign embassy.•The building should not be located in high crime areas.•EMC risks must be minimised by locating away from radar transmitters and mobile ‘phone masts
Engineering IT Infrastructure
www.Capitoline.eu
BICSI draft standard on data centre design
• 503 pages
• To be published in 2009
• Complementary to ANSI TIA 942
Engineering IT Infrastructure
www.Capitoline.eu
Very useful American information
Engineering IT Infrastructure
www.Capitoline.eu
0.8
TIA 942 BICSI BICSI
Railways 0.8 km 1.6 km
Highways 0.8 km 1.6 km
Military bases 1.6 km 13 km
Airport 0.4 km >8 km <48 km
Major met area <16 km
Height above flood level >3m
Waterway or coastline 0.4 km 1.6 km
100 year flood plain 91 m
Fire/police hospital < 8km
Canals/dams/reservoirs 0.4 km 3.2 km
High voltage power lines, petrol stations
1.6 km
Radar, TV 5 km
Fossil fuel power plant 8 km
Nuclear power plant 1.6 km 80 km
Engineering IT Infrastructure
www.Capitoline.eu
Offices next to Buncefield oil depot, Dec 2005
Building on the flight path of Tehran airport
Engineering IT Infrastructure
www.Capitoline.eu
Engineering IT Infrastructure
www.Capitoline.eu
Vodafone data center in Istanbul flooded –Sept 2009
Engineering IT Infrastructure
www.Capitoline.eu
Engineering IT Infrastructure
www.Capitoline.eu
The ‘Spaces’• Work Area
• Telecommunications Rooms– Or Telecommunications enclosures for small
projects
• Equipment Rooms• Entrance Rooms and Entrance Facilities• Computer Rooms• Data Centres
Engineering IT Infrastructure
www.Capitoline.eu
Horizontal cabling
Telecom Outlet, TO
Work Area
Patch Cable
Equipment or Telecommunications Room
Campus cabling
External telecoms cabling
Entrance facility Computer Room
Main Distribution Area
Backbone/Riser cabling
Telecommunications rooms
Engineering IT Infrastructure
www.Capitoline.eu
Telecommunications Room (TR) and Telecommunications Enclosure (TE)
• A TR is an enclosed architectural space for housing telecommunications equipment, cable terminations, and cross-connect cabling.
• A TE is a case or housing for telecommunications equipment, cable terminations, and cross connect cabling.
Engineering IT Infrastructure
www.Capitoline.eu
Equipment Rooms
• An ER is an environmentally controlled centralized space for telecommunications equipment that usually houses a main or intermediate cross-connect.
• ERs differ from TRs in that ERs are generally considered to serve a building, a campus, a tenant, or a SP, whereas TRs serve a floor area of a building.
Engineering IT Infrastructure
www.Capitoline.eu
Entrance Facility
An EF is expected to provide the following:
• Point of demarcation between the SPs and customer premises cabling (if required).
• Primary (electrical) protection devices governed by the applicable electrical codes.
• Space to house the transition between cabling used in the OSP to cabling approved for intrabuilding use. This usually involves transition to fire-rated cable
Engineering IT Infrastructure
www.Capitoline.eu
Engineering IT Infrastructure
Sizing the Spaces
Engineering IT Infrastructure
www.Capitoline.eu
Telecommunications Room (TR) Guidelines
Floor Space Served
There must be at least one TR or ER per floor.
Multiple rooms are required if the cable length between the HC (FD) and the telecommunications outlet location, including slack, exceeds 90 m (295 ft) or if the usable floorspace to be served exceeds:
Engineering IT Infrastructure
www.Capitoline.eu
TR sizing –at least 9 sq m
Engineering IT Infrastructure
www.Capitoline.eu
Size of ER• Allow 9 sq m per work area
• Multiply No of work areas by 0.07 sq m
• Minimum size 3 x 5 m
• e.g. 5000 sq m of office space
• 5000/9 = 555
• 555 x 0.07 = 39 sq m
Engineering IT Infrastructure
www.Capitoline.eu
Size of Entrance FacilityBased on frames, ANSI/TIA/EIA-569-A
569A also states a min of 9 sq m for multi-tenanted buildings
space served Floor space dimensions Ent Room area
10 000 3660 x 1 930 7 sq m
20 000 3660 x 2 750 10 sq m
40 000 3660 x 3 970 14.5 sq m
50 000 3660 x 4 775 17.5 sq m
60 000 3660 x 5 600 20.5 sq m
80 000 3660 x 6 810 25 sq m
100 000 3660 x 8 440 31 sq m
Engineering IT Infrastructure
www.Capitoline.eu
TETR
Telecomm-unications Enclosure
Telecomm-unications Room
Equipment Room
Data centre
Computer RoomSupport areas
Tier 1 20% of CR
Tier 2 30%
Tier 3 80%
Tier 4 100%+
TREF
Entrance Facility EF (2 EF for Tiers 3&4)
ER
Serving a useable floor area of…….
<335 m2 <929 m2 <1860 m2
<7.2 m2 7.2 –15 m2 15-99 m2 100 m2 + (per CR)
CR
Summary of Spaces
Engineering IT Infrastructure
www.Capitoline.eu
Sizing the Computer Room
Engineering IT Infrastructure
www.Capitoline.eu
With typical 8-tile pitch 1 rack takes a footprint of 0.6 m x 2.4 m = 1.44 m(min pitch 7 tiles, max 9 tiles)
With realistic overheads, 1 ‘working’ rack per 3.16 sq m
What size computer room? By the rack…
Engineering IT Infrastructure
www.Capitoline.eu
What size of computer room? By the server……..
• ‘Average’ rack mounted server, 370 W
• 29 models, 50 to 900 W, 1 to 4 U• Average fitting into a 4 kW rack, 11 units• For every eight server racks, one comms and
one storage rack
11 servers per rack=0.34 sq m per server
Engineering IT Infrastructure
www.Capitoline.eu
300
250
200
150
100
50
00 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750
Sq m of floor space
servers
11 servers per rack, 4 kW per rack, 0.34 sq m per server. 8-tile pitch
Engineering IT Infrastructure
www.Capitoline.eu
IT Yield: How much floor space does useful ICT work?
• Theoretical maximum, ASHRAE 7-tile pitch model, 48%
• Realistic average, 20%
• Equivalent to one rack per 3.3 sq m
Engineering IT Infrastructure
www.Capitoline.eu
Floor space utilisation
floor space No of racks racks/sq m efficiency76 31 2.5 26.1%41 15 2.7 23.4%47 15 3.1 20.4%26 8 3.3 19.7%47 14 3.4 19.1%160 45 3.6 18.0%44 9 4.9 13.1%47 9 5.2 12.3%77 14 5.5 11.6%78 14 5.6 11.5%95 15 6.3 10.1%210 27 7.8 8.2%77 5 15.4 4.2% average 5.3 15.2% median 4.9 13.1%
floor space No of racks racks/sq m efficiency
369 144 2.6 25.0%400 140 2.9 22.4%195 68 2.9 22.3%170 57 3.0 21.5%55 18 3.1 20.9%43 14 3.1 20.8%235 74 3.2 20.2%199 60 3.3 19.3%210 60 3.5 18.3%189 44 4.3 14.9%100 20 5.0 12.8% average 3.3 19.9% median 3.1 20.8%
Existing sites New build projects
average rack footprint=0.64 sq m (weighted average of 600 and 800 racks)
Source: Capitoline survey
Engineering IT Infrastructure
www.Capitoline.eu
Ideal Computer Room size• If max ‘throw distance’ of aircon unit is 12 m
then max width is 24 m
24 m max
6 m min24 m max
CRAC unit
Rows of racks Ideal size is
between 144 and 600 m2
Engineering IT Infrastructure
www.Capitoline.eu
Ideal Computer Room size
• Rooms larger than 600 square metres tend to be difficult to manage
• They require large amounts of air conditioning
• CRAC units probably need to be in the middle of the floor, which makes calculations difficult
• Gas fire suppression quantities will be huge. A 900 sq m room will be >3600 m3
Engineering IT Infrastructure
www.Capitoline.eu
Sizing the Data Centre building and site
Engineering IT Infrastructure
www.Capitoline.eu
The relationship of the Spaces within a Data centre (TIA 942)
Separate UPS/battery room recommended if capacity exceeds
100 kVA
Engineering IT Infrastructure
www.Capitoline.eu
Space Function‘Computer room’, ‘server room’, ‘machine room’ etc
To house the computer racks and communications equipment. A generic space with sufficient air conditioning, power supplies and communications cabling to allow a non-application specific IT environment with best use of space
Control room An area, adjoining the computer room, where all control and monitoring functions relevant to the site are concentrated
General office area An office area where the IT staff can work
Telecommunications Entrance Facility
A room or area where all external communications cabling enters the building. It serves as a point of demarcation between different owners of cabling, provides a point for over-voltage protection and allows a transition from external (flammable) cables to internal cables. (Required BS 6701) Two required for T3/T4
Fire gas suppression store
If inert gas is used as the main fire suppression system then it requires a large volume for storage. Alternatively the gas bottles may be placed against a wall adjacent to the Computer Room or if a fluorocarbon gas is used (placed within the Computer Room) this area may be dispensed with
Electrical switch room A room where the external power cables enter the building and forms a point of demarcation between different cable owners plus all main switching and metering
UPS and battery room
For loads in excess of 100 kVA (TIA 942) it is recommended to have a separate UPS and battery room to save space and heat load in the main Computer Room
Generator room To house the standby diesel generators. This may be in or adjacent to the main building
Engineering IT Infrastructure
www.Capitoline.eu
Oil store To house the diesel fuel to run the standby generators for between 8 and 96 hours. This may be in or adjacent to the main building. The electrical switch room, UPS and generator must all be close to each other to minimise electrical losses in long power cables
Storage and build area
An area to store and unpack equipment and to build items like racks without making dust and causing disruption in the main Computer Room
Delivery and loading area
An area adjacent to the main doors to allow heavy equipment to be shipped into the building
Main entrance A secure entrance with anti-piggybacking- airlock controlsPlanning and meeting room
A room to hold meeting and provide additional office space
Internal staff facilities Male/female/disabled toilets. Shower room. Basic dining area and kitchen facilities
Electrical substation Due to the power load it is likely that separate electrical substation would be needed by the utility company. This should be away from the main building to reduce EMC issues
Air conditioning condensers
If split DX units are to be used then a condenser unit is needed for each Computer Room DX unit. These must be in a secure area either adjacent to the main building or even on top of it, but preferably not over the computer room itself
Main gate and hard standing
A secure main gate leading onto hard standing area of sufficient space and strength for HGVs to unload heavy equipment and manoeuvre
External staff facilities
Parking space for cars, bicycle storage and smoking shelter
Engineering IT Infrastructure
www.Capitoline.eu
Ratio of support areas to Computer Room – Uptime Institute
• Tier 1 20%
• Tier 2 30%+
• Tier 3 80-90%
• Tier 4 100%+
Engineering IT Infrastructure
www.Capitoline.eu
CR 240 m2
Total 620 m2
Support to CR, 160%
Engineering IT Infrastructure
www.Capitoline.eu
CR 240 m2
Building 620 m2 (2.6 x CR), 160% support areaTotal site footprint 1674 m2 (2.7 x building)
Engineering IT Infrastructure
www.Capitoline.eu
CR 340 m2
Building 744 m2 (2.2 x CR), 120% support areaTotal site footprint 1674 m2 (2.25 x building)
Engineering IT Infrastructure
www.Capitoline.eu
CR 480 m2 (2 x 240)Building 990 m2 (2 x CR), 106% support areaTotal site footprint 1998 m2 (2 x building)
Engineering IT Infrastructure
www.Capitoline.eu
Facilities requirements• Room dimensions and height• Floor strength• Connection of services• External services• Access, loading, DDA etc• Décor• Lighting• Fire Regulations
Engineering IT Infrastructure
www.Capitoline.eu
Facilities requirements, in separate chapters
• Raised floor design
• Power supplies, UPS and earthing
• HVAC
• Cable containment and management
• Fire detection and suppression
• Generic cabling and interconnection
Engineering IT Infrastructure
www.Capitoline.eu
Data centres are places of work and are subject to the same rules as any other place of work
• EU Construction Products Directive 89/106/EEC• EU Electromagnetic Compatibility Directive 89/336/EEC• EU Low Voltage Directive 2006/95/EC• EU Measures to improve safety & health of workers at work 89/391/EEC• EU Health & safety requirements of the workplace directive 89/654/EEC• Minimum requirements for the provision of H&S signs at work 92/58/EEC• Noise at work directive 2003/10/EC• Energy services directive 2006/32/EC• EU Energy performance of buildings directive 2002/91/EC
Engineering IT Infrastructure
www.Capitoline.eu
Minimum ceiling height: The minimum height in the computer room shall be 2.6 m (8.5 ft) from the finished floor to any obstruction such as sprinklers, lighting fixtures, or cameras.. A minimum of 460 mm (18 in) clearance shall be maintained from water sprinkler heads.
Absolute min slab to slab height is 2.9 m, i.e. 400 mm under floor, 2.1 m racks, 400 mm air return path
Room height (TIA 942)
Engineering IT Infrastructure
www.Capitoline.eu
Floor strength (TIA 942)
Minimum floor loading capacity The minimum distributed floor loading capacity shall be 7.2 kPA. The recommended distributed floor loading capacity is 12 kPA. The floor shall also have a minimum of 1.2 kPA hanging capacity for supporting loads that are suspended from the bottom of the floor (for example, cable ladders suspended from the ceiling of the floor below). The recommended hanging capacity of the floor is 2.4 kPA.
Engineering IT Infrastructure
www.Capitoline.eu
Lighting shall be a minimum of 500 lux in the horizontal plane and 200 lux in the vertical plane, measured 1 m above the finished floor in the middle of 4 all aisles between cabinets.
Lighting (TIA 942)
Engineering IT Infrastructure
www.Capitoline.eu
Access
Doors shall be a minimum of 1 m wide and 2.13 m high, without doorsills, hinged to open outward (code permitting) or slide side-to-side, or be removable. Doors shall be fitted with locks and have either no center posts or removable center posts to facilitate access for large equipment. Exit requirements for the computer room shall meet the requirements of any other local requirements.
DDA. Ramps to be not less than 1:12 (see Raised Floor section). All pathways to be >900 wide
Engineering IT Infrastructure
www.Capitoline.eu
Decor (TIA 942)
Décor. Floors, walls, and ceiling shall be sealed, painted, or constructed of a material to minimize dust. Finishes should be light in color to enhance room lighting. Floors shall have anti-static properties as per IEC 61000-4-2.
Engineering IT Infrastructure
www.Capitoline.eu
Connection of services
• Electricity supply– Who from, capacity, where does it enter the
building, more than one?
• Telecommunications– Who from, capacity/type, where does it enter the
building, more than one?
• Gas, water, drainage, sewage• No other service should cross the Computer
Room space
Engineering IT Infrastructure
www.Capitoline.eu
External services
• Suitable location for standby generators– Noise, weight, security, fuel storage,
proximity
• Suitable location for external air conditioning components– DX Condenser units, central chiller system
etc, weight, security, power supplies, proximity
Engineering IT Infrastructure
Fire Regulations
Fire Plan and Risk assessmentEmergency lighting and signageDoors and Emergency exits
Engineering IT Infrastructure
www.Capitoline.eu
Fire safety planThe fire safety plan is a multilayered approach that requires a coordinated plan for
•Designing for low flammability and fire risk•Operating with low risk•Emergency exits•Emergency lighting•Emergency exit signage•Fire detection, appropriate to the area covered•Fire alarm•Multi-level automatic fire suppression•Manual fire alarm and portable fire extinguishers•Staff training and fire drills in place•Maintenance plan for all equipment involved
Engineering IT Infrastructure
www.Capitoline.eu
What Is Emergency Lighting?
• The lighting required for use when the supply to normal lighting fails, enabling safe exit from a building
Engineering IT Infrastructure
www.Capitoline.eu
Directives
• The Construction Products Directive (89/106)
• The Workplace Directive (89/654)
• The Signs Directive (90/664)
• The Regulatory Reform (Fire Safety) Order
Engineering IT Infrastructure
www.Capitoline.eu
EXIT SIGNS• There are, and have been 3 types of exit signs, with an appropriate
level of legislation enforcing each type :.
This sign is now obsolete & was replaced with a
pictogram sign from 24th December 1998
The Interim Format Sign, This sign is
deemed to comply with Signs Directive
and can be used within premises that
already use this format.
The European Signs Directive Format as
designated by the Health & Safety (Signs &
Signals) Regulations. This is now the preferred
format and must be applied to all new
applications.
Engineering IT Infrastructure
www.Capitoline.eu
Stage 1• Points of emphasis – Mandatory locations to cover
specific hazards and highlight safety equipment and signs :
a) NEAR STAIRS – each tread
should receive lightb) NEAR CHANGES OF LEVEL
A 7 point plan can now be considered for the detailed design….
Engineering IT Infrastructure
www.Capitoline.eu
Stage 1
c) NEAR CHANGES IN
DIRECTION & INTERSECTIONS
ALONG CORRIDORS
d) TO ILLUMINATE EXIT DOORS & SAFETY SIGNS
Engineering IT Infrastructure
www.Capitoline.eu
Stage 1
e) NEAR FIRE FIGHTING & FIRST AID EQUIPMENT
f) TO ILLUMINATE FIRE CALL POINTS
Engineering IT Infrastructure
www.Capitoline.eu
Stage 1
g) OUTSIDE AND NEAR TO EACH FINAL EXIT
h) TO ILLUMINATE EXIT DOORS
Engineering IT Infrastructure
www.Capitoline.eu
Fire exits
• ‘Normal’ risk, furthest distance to the fire exit must be less than 18 m if the room has only one exit
• For rooms with more than one exit the max distance must be > 45 m
• Essentially this means any room more than 80 sq m needs more than one exit
Engineering IT Infrastructure
www.Capitoline.eu
PAS 79:2005 Fire risk assessment. Guidance and a recommended
methodology • 750 mm pathways for escape
• 900 mm if wheelchairs access required