TABLE OF CONTENTS CHAPTER TITLE PAGE TABLE OF CONTENTS i LIST OF TABLES iii LIST OF FIGURES iv LIST OF ABBREVIATIONS v LIST OF APPENDICES vi 1 INTRODUCTION 1 1.1 Project Proposal 1 1.2 PMA Question 2 2 METHODOLOGY 3 3 PROJECT PROPOSAL 4 3.1 EXECUTIVE SUMMARY 4 3.2 PROJECT BACKGROUND 5 3.2.1 Project Overview 5 3.2.2 Project Initiative 6 3.3 PROJECT TEAM AND ORGANISATION 6 3.3.1 Feasibility and Benchmark 6 3.3.2 Evaluation Criteria 9 3.3.3 Past Experience 12 3.3.4 Organisation and Human Resource 12 3.4 PROPOSED PROJECT APPROACH 16 3.4.1 Technical Approach 16 3.4.2 Project Diagram 21 3.4.3 Deliverable Specification 21 3.4.4 Project Schedule 22 3.4.5 Implementation Plan 22

Upload: salehuddin-abdul-kadir

Post on 21-Jul-2015

317 views

Category:

Education


2 download

TRANSCRIPT

Page 1: 3   pma salehuddin - resource and project management

TABLE OF CONTENTS

CHAPTER TITLE PAGE

TABLE OF CONTENTS i

LIST OF TABLES iii

LIST OF FIGURES iv

LIST OF ABBREVIATIONS v

LIST OF APPENDICES vi

1 INTRODUCTION 1

1.1 Project Proposal 1

1.2 PMA Question 2

2 METHODOLOGY 3

3 PROJECT PROPOSAL 4

3.1 EXECUTIVE SUMMARY 4

3.2 PROJECT BACKGROUND 5

3.2.1 Project Overview 5

3.2.2 Project Initiative 6

3.3 PROJECT TEAM AND ORGANISATION 6

3.3.1 Feasibility and Benchmark 6

3.3.2 Evaluation Criteria 9

3.3.3 Past Experience 12

3.3.4 Organisation and Human Resource 12

3.4 PROPOSED PROJECT APPROACH 16

3.4.1 Technical Approach 16

3.4.2 Project Diagram 21

3.4.3 Deliverable Specification 21

3.4.4 Project Schedule 22

3.4.5 Implementation Plan 22

Page 2: 3   pma salehuddin - resource and project management

ii

3.4.6 Statement of Work 25

3.4.7 Administration Plan 29

3.4.8 Logistic Support 30

3.4.9 Quality Plan 31

3.4.10 HSE Plan 41

3.4.11 Risk and Mitigation Plan 44

3.5 COST AND PAYMENT APPROACH 50

3.5.1 Cost Estimate 50

3.5.2 Type of Contact 50

3.5.3 Payment Terms 52

3.6 CONTACT 53

REFERENCES 54

Appendices A - F 56-61

Page 3: 3   pma salehuddin - resource and project management

iii

LIST OF TABLES

TABLE NO. TITLE PAGE

3.3.2 Evaluation Criteria 10-11

3.48a Logistic Plan Guideline 30

3.48b Sample of Logistic Support 31

3.4.11 Risk Register 47-49

Page 4: 3   pma salehuddin - resource and project management

iv

LIST OF FIGURES

FIGURE NO. TITLE PAGE

3.3.4a Project Organisation Chart ............................................................ 12

3.3.4b Human Resource Histogram .......................................................... 15

3.4.4 Project Scheduling ......................................................................... 22

3.4.5a Project Flowchart ........................................................................... 23

3.4.5b Work Breakdown Structure ........................................................... 24

3.48 Logistic Supply Chain ................................................................... 30

Appendix A Location of Project Site ................................................................. 56

Appendix B Site Plan ......................................................................................... 57

Appendix C Floor Plan ....................................................................................... 58

Appendix D Elevation Plan ................................................................................ 59

Appendix E Site Accessibility Plan ................................................................... 60

Appendix F Utilities Plan .................................................................................. 61

Page 5: 3   pma salehuddin - resource and project management

v

LIST OF ABBREVIATIONS

BC - Building Code

BP - Building Plan

EMOSHM - Executive Masters in Occupational Safety and Health Management

GMP - Guaranteed Maximum Price

HIRARC - Hazard identification, Risk Assessment and Risk Control

HSE - Health, Safety and Environment

IIF - Incident Injury Free

IPD - Integrated Project Delivery

PCG - Project Control Group

PMA - Post Module Assignment

QA - Quality Assurance

QC - Quality Control

RFI - Request for Information

RFP - Request for Proposal

RMK - Rancangan Malaysia Kesepuluh

SDIS - Safety Data Information Sheet

SF - Square Feet

MR - Minimum Requirement

Page 6: 3   pma salehuddin - resource and project management

vi

LIST OF APPENDICES

APPENDIX NO. TITLE PAGE

A Location of Project Site 56

B Site Plan 57

C Floor Plan 58

D Elevation Plan 59

E Site Accessibility Plan 60

F Utilities Plan 61

Page 7: 3   pma salehuddin - resource and project management

INTRODUCTION

1.1 Project Proposal

Project proposals are made with one goal in mind: to convince that you are

the right person for the job. It is essentially a project bid that requires a detailed

analysis of the project that can take weeks or months to complete. Gido and

Clements (2003) states that a project proposal is a selling document and not a

technical report. In the proposal the contractor must convince the Client that the

contractor:

(1) Understands what the customer is looking for.

(2) Can carry out the proposed project.

(3) Will provide the greatest value to the customer.

(4) Will capitalize on its successful experience with previous related

projects.

(5) Will do the work professionally.

(6) Will achieve intended results.

(7) Will complete the project within budget and on schedule.

(8) Will satisfy the customer.

Project proposals should be written in a simple concise manner and must

specifically address the customer’s requirements as laid out in the RFP. It should

also be realistic, in terms of the proposed scope, cost and schedule, in the eyes of the

Client. According to Wysocki, Beck and Crane (2000), project proposals can have

any number of attachments accordingly to the project from feasibility studies to best-

of-breed analysis and should contain the following:

(1) Description of work activities.

(2) Resources required to complete each activity.

Page 8: 3   pma salehuddin - resource and project management

2

(3) The scheduled start and end date.

(4) Estimated cost and completion date of the project.

`Cleland and King (1988) states that a project proposal consists of three

separate proposals that is the; commercial proposal, project execution proposal and

technical proposal. Each of the mentioned proposals can stand on its own as a

separate document or combined into one project proposal. In many cases, these three

types of proposal documents are usually inclusive in one project proposal.

Finally, it is critical that the terms and condition portion of the proposal be

reviewed and approved before submission of the proposal to the customer.

Kerzner (2001) further mentions that the legal representative is responsible for the

preparation for the type of contract and terms portion of the proposal. Generally,

contracts with the legal department are handled through or in coordination with the

proposal group.

2.1 PMA Question

The PMA provided by Dr Mohd Yusof Md Daud (2013) queries the

following: Develop a project proposal base on the following area (select one topic

only). You are encouraged to write the project proposal in which you are familiar

with or you have some extend of experiences in the particular project as your case

study. If you are selecting real case project (finished or ongoing) you can use the

same title as in your real project.

Page 9: 3   pma salehuddin - resource and project management

3

The topic selected for this PMA is:

ANY CONSTRUCTION PROJECT / SUB PROJECT

Guidelines: Contents may include in the proposal:

i. Project overview

ii. Project initiative

iii. Feasibility study and benchmark

iv. Possible project risk at the initial and ongoing project and

mitigation plan

v. Organisation and human resource planning

vi. Project planning (use tool such as Gantt Chart, WBS)

vii. Include all the flow chart / appropriate diagram

viii. Add other key element (optional) to enrich your proposal

METHODOLOGY

Methodology is the manner, method, procedure, way or approach that will be

used to attain, achieve, and accomplish the PMA question. The method used is

application of knowledge gained from the classes attended so far during EMOSHM,

refer to project management books and using real project proposals collected as

examples. I have only managed to acquire small portions of several project proposals

throughout the search of a full project proposal document due to the confidentiality

of its content towards the contractors and Clients. When comparing the several

project proposals, it is discovered that project proposals may take different formats

and usually depends on the requirement of the Client or RFP. Therefore, a large part

of the PMA proposal will be fabricated in assumption using the project management

books as guidelines in order to produce a complete project proposal.

Page 10: 3   pma salehuddin - resource and project management

4

PROJECT PROPOSAL

3.1 EXECUTIVE SUMMARY

XYZ Berhad is pleased to submit a proposal to provide a project proposal of an

Education College for a private company. This project is located on land area of 37,

787 SF with the necessary car-parking facilities and infrastructure. The entire

development will be constructed in different phases. The following are the planned

phases by the Client:

(1) Phase 1 – To construct college block as per diagram in appendix.

(2) Phase 2 – To construct car-parking facilities as per diagram in

appendix.

(3) Phase 3 – To construct all roadways, landscape areas and other

associated facilities to support the functioning of Phase 1 and 2.

Our proposal is based on the type, duration, and the number of people deployed to

provide the service plus the head office technical service group support required to

effectively deliver the service. As requested by the Client, the project proposal will

address the following:

(1) Project Overview

(2) Project Initiative

(3) Feasibility and Benchmark

(4) Evaluation Criteria

(5) Past Experience

(6) Organisation and Human Resource

(7) Technical Approach

(8) Project Diagram

(9) Deliverable Specification

(10) Project Schedule

Page 11: 3   pma salehuddin - resource and project management

5

(11) Implementation Plan

(12) Statement of Work

(13) Administration Plan

(14) Logistic Support

(15) Quality Plan

(16) HSE Plan

(17) Risk and Mitigation Plan

(18) Cost Estimate

(19) Type of Contact

(20) Payment Terms

3.2 PROJECT BACKGROUND

3.2.1 Project Overview

XYZ Berhad has established a track record in Malaysia for creating quality

developments. It is understood that ABC is desirous to procure the services of an

international organisation possessing the suitable expertise to assist them in the

development of Education College Project. Before listing the project overview, it is

important for us to show the designs and authority submissions understanding as

follows:

(1) We understand that the submission has been made and the necessary

approval obtained.

(2) We understand, the (BP) submission is yet to be made to the

authorities and is expected to be submitted for approval by the Client around

mid December 2013.

(3) We understand that the soil investigation works is currently ongoing

and hence the piling and the structural design is yet to be finalised.

(4) We understand the Architectural design is yet to be fully developed

and finalised by the Client.

Page 12: 3   pma salehuddin - resource and project management

6

3.2.2 Project Initiative

The Education College Project is visional in supporting the Tenth Malaysia Plan

(RMK) from the aspect of education. In addition, it will also boost the economy with

its education business. It will also contribute in innovating science and technology

by the research conducted in the college. The land area used for the project site

which is barren and unsuitable for agricultural purpose will also be utilized for a

good cause. Finally, the Education College will also provide job opportunities for

Malaysia.

3.3 PROJECT TEAM AND ORGANIZATION

3.3.1 Feasibility and Benchmark

We believe that Client will benefit from the experience and capability that XYZ

Berhad can bring to this project. We are also confident that we have the capability to

provide world class professional services to Client in the realization of this project.

We look forward to develop a mutually beneficial relationship with Client on this

project and in future world class professional services to the Client in the realization

of this project. From the abovementioned, XYZ Berhad is exceptional in the

following:

(1) Legal Feasibility.

(2) Operational Feasibility.

(3) Economic Feasibility.

(4) Technical Feasibility.

(5) Schedule Feasibility.

(6) Market and Real Estate Feasibility.

(7) Resource Feasibility.

(8) Cultural Feasibility.

(9) Financial Feasibility.

Page 13: 3   pma salehuddin - resource and project management

7

Our global experience and local understanding in managing commercial, retail, hotel

and residential projects will be an invaluable aid in achieving the international

standard of quality within a challenging timetable. This is proven by the following:

Technical and Industry Sector Knowledge. We understand our Clients’ business and

the financial drivers of their industry. By combining this sector knowledge with our

solid technical and commercial grounding, we are able to consistently produce a

better financial outcome for our Clients.

Innovative Effective Solutions. Innovation is a business process at XYZ Berhad. We

are constantly innovating what and how we deliver. Our innovations whether at

design, procurement or construction stages always ensure that we exceed Client’s

expectations whilst minimizing the total project cost.

Flexibility to service the needs of our Clients. Whilst we have strong operating

processes and protocols, our Clients can choose from a wide array of service

offerings that can be tailored to their particular circumstances. Our flexible approach

ensures that we deliver what and where the Client wants us to deliver.

Global Experience with Local Expertise. XYZ Berhad has a track record of

delivering projects throughout the world which has been operating for more than 20

years and has delivered more than 100 projects in the region. Our global track record

combined with our profound understanding of Asian culture, local code

requirements, suppliers & subcontractors, ensures that world’s best practices can be

delivered locally.

Surety of Delivery. XYZ Berhad has the necessary financial strength and resources

to manage the outcome of a project, notwithstanding the specific project constraints

like geography, bureaucracy, availability of materials and equipment etc. We pride

ourselves with a corporate history of having delivered projects within the time

committed by us and to Client’s satisfaction. Our surety of delivery sets us apart

from the strongest of our competitors.

Page 14: 3   pma salehuddin - resource and project management

8

Lowest End Cost. XYZ Berhad has the ability to bundle all the project services

required on a project into an integrated offering for the Client, which maximises

value for money for the Client. Our experience, and that of our repeat Clients,

repeatedly confirms our long held belief that the sum of the unbundled project

services is always more than that of an integrated bundle.

The Best People in the Industry. XYZ Berhad believes that its true assets are its

people. We boast of having the best people in the industry who have technical,

commercial, managerial and industry sector specialisation. To be at the forefront of

our industry and several steps ahead of the competition, XYZ Berhad continually

invests in training of its people. The quality of our people is one of the important

factors behind XYZ Berhad’s ability to consistently generate Maximum Value for

our Clients.

Relationship Driven. At XYZ Berhad, a Satisfied Client is our ultimate goal. We see

ourselves as an extension of the Client addressing issues in the best interests of the

Client, and not as a supplier to our Clients. We put our Clients’ interests ahead of

profits, and that is why more than half of our business comes from repeat Clients. We

highly value the trust and confidence that our Clients place in us.

Environmental, Health and Safety in Delivery / Site Safety. XYZ Berhad are

committed to operate (IIF). In this regard, we proactivelywork with all stakeholders

to make this vision a reality. Therefore, XYZ Berhad’s way is putting Safety First

and never compromising on it. XYZ Berhad have a set of minimum safety

requirements called (MRs) that is implemented in every project site. These are: Fall

Prevention, Logistics, Ground & Civil Works, Lifting & Slinging, Electrical Safety,

Health, Protective Equipment & Welfare, Fire & Emergency, Environment.

The following are our previous projects and track record as the benchmark:

(1) Petronas Twin Towers in KLCC, KL.

(2) KL Sentral, KL.

(3) Crowne Plaza Mutiara, KL.

Page 15: 3   pma salehuddin - resource and project management

9

(4) Won the first ever Platinum Award under Singapore BCA’s Green

Mark scheme.

(5) The first project to be awarded a 5-Star rating under the Green Star

scheme in Australia.

(6) Targeted to be the first 6-Star Green Star rated Building in Australia.

(7) The development is targeted to achieve a Platinum Award under the

Green Mark Scheme.

3.3.2 Evaluation Criteria

The project must address and may be awarded point sup to the amount listed of each

of the following criteria by the Client. The evaluation criteria given by the Client is

on the next page.

Page 16: 3   pma salehuddin - resource and project management

10

Table 3.3.2 : Evaluation Criteria

Page 17: 3   pma salehuddin - resource and project management

11

Table 3.3.2 : Continued

Page 18: 3   pma salehuddin - resource and project management

12

3.3.3 Past Experience

Capability and Experience. XYZ Berhad has a combined staff strength of more than

17,000 highly qualified professionals worldwide. We employ a combination of

expatriates and local staff. Many of the expatriate Project Managers have been

working and living in Asia, bringing international project management knowledge

from the West and marrying that to an understanding of the culture of the East gained

through their years spent in the region. Many of our Asian Project Managers were

educated abroad and have extensive working experience in international

environments and firms. Most importantly, they speak the local language.

Experience and Knowledge in the Development of Similar Commercial Projects.

XYZ Berhad has extensive global and Malaysia experience in managing similar

development projects. Our extensive Project and Construction Management

experience, will be a strong support to the Client.

3.3.4 Organisation and Human Resource

Figure 3.3.4a : Project Organization Chart

Page 19: 3   pma salehuddin - resource and project management

13

The following is a brief description of the roles and responsibilities of the key

positions within our proposed Project Team. XYZ Berhad Project Team will be the

single point of contact for Client in this project (Within the XYZ Berhad Team, the

Project Manager would be the primary contact). The team will deal with the design,

procurement and commercial issues and shall consist of specialist professionals

dedicated to the project including:

The Project Manager is responsible for the day to day operational direction of his

element(s) during all phases of the works where he is supported by the Assistant

Project Managers. The Project Manager reviews and monitors design and

construction activities to ensure delivery in accordance with Client’s requirements.

The Project Manager has rights to stop any works that is carried out unsafely or that

is non-compliant to MR for safety.

Other Project Team Members. assist the Project Manager in all aspects of the project

including management of the Consultants and the Contractor. They oversee the day to

day operations including overall progress, quality, contractor’s HSE compliances, and

coordination with the other Project Team members.

Safety Officer. in conjunction with the Project Manager will impart the HSE global

minimum requirements and will provide the point of contact for monitoring

compliance with authority’s occupational safety and health regulations during

construction activities. The Safety Officer will have to be empowered by the Client

to stop any non-safety compliant works or unsafe conditions/situation that they deem

is necessary during the day to day operations. He will then report these non

compliances to the Project Manager.

Project Control Group (PCG). The PCG meetings are proposed to be held routinely

and form the most important management review function for the Project. They are a

forum for regular, open and formal interaction between senior management of the

Client and XYV Berhad in order to maintain a consistent overview and reasoned

involvement in major decisions. The role of the PCG is to:

Page 20: 3   pma salehuddin - resource and project management

14

(1) Review and accept presented reports and submissions;

(2) Give direction or make decisions;

(3) Resolve different viewpoints (if any);

(4) As required, refer items back to the team for additional work or re-

presentation;

(5) Highlight unresolved issues; and

(6) Review project and contractual status.

As such, the PCG meetings are not intended as problem-solving sessions, this being

within the domain of the regular weekly meetings. The PCG meetings are

formalized with pre-distributed agendas and reports covering all key aspects of the

project. Agendas include reference to the resolutions to be sought from the meetings.

Formal minutes with agreed action items are prepared by XYZ Berhad following

each meeting and distributed to all parties. Previous meeting minutes must be

adopted before proceeding with the next meeting. The PCG papers and minutes

provide a convenient and centralized method of recording the latest project status and

contractual position. As the project proceeds, the extent of reporting against each

item will vary. It is recommended, however, that the agenda items remain as an

additional project discipline. Issues dealt with at the PCG’s would include:

(1) Procedural.

(2) Schedule.

(3) Authorities.

(4) Quality Control.

(5) Construction Report.

(6) Contractual Report.

(7) Project Completion Report.

Page 21: 3   pma salehuddin - resource and project management

15

Whereas the main jizz of our human resource planning are as follows:

Staff Acquisition. The project staff will consist entirely of internal resources. There

will be no outsourcing/contracting of staff within the scope of this project. The

Project Manager will negotiate with functional and department managers in order to

identify and assign resources in accordance with the project organizational structure.

All resources must be approved by the appropriate functional/department manager

before the resource may begin any project work. The Project Team will not be co-

located for this project and all resources will remain in their current workspace.

Resource Calendars. The Project will last for 72 months. All resources are required

before the project can begin. The resource histogram below illustrates:

Figure 3.3.4b : Human Resource Histogram

Training. There is currently no training scheduled with regards to the Project since

the organization has adequate staff with required skill sets. However, if training

requirements are identified, funding will be provided from the project reserve.

Page 22: 3   pma salehuddin - resource and project management

16

Performance Reviews. The Project Manager will review each team member’s

assigned work activities at the onset of the project and communicate all expectations

of work to be performed. The Project Manager will then evaluate each team member

throughout the project to evaluate their performance and how effectively they are

completing their assigned work. Prior to releasing project resources, the Project

Manager will meet with the appropriate functional manager and provide feedback on

employee project performance. The functional managers will then perform a formal

performance review on each team member.

Recognition and Rewards. Although the scope of this project does not allow for

ample time to provide cross-training or potential for monetary rewards there is

several planned recognition and reward items for Project Team members.

3.4 PROPOSED PROJECT APPROACH

3.4.1 Technical Approach

During the construction phase of the project, we will provide all management and

related services as necessary to adequately supervise, monitor and coordinate the

work. Our Team will manage all conditions of the site work rules and will establish

and monitor safety, security, cleaning and other conditions. The following items are

also critical to a successful construction project and will be provided by XYZ

Berhad.

Our team will implement the following key activities that were developed during the

pre-construction phase:

(1) Verification of project schedule.

(2) Expedition of long lead items.

(3) Expedition of purchasing and buyouts.

(4) Verification of accelerated release of critical material.

Page 23: 3   pma salehuddin - resource and project management

17

(5) Confirmation of each action reviewed in preconstruction.

(6) Verification of the record keeping and audit trails.

Our Team will establish lines of authority in order to execute the project in a

coordinated and efficient basis and will prepare a chart graphically indicating those

lines of authority.

Our Team will establish, implement and maintain procedures to assure coordination

among the Architect,consultants, subcontractors, and all local municipal authorities,

governmental agencies, utility companies, etc., who may be involved in the project.

Our Team will prepare and develop an on-site record keeping system, which will be

sufficient in detail to satisfy an audit by the owner. Such records shall include, but

will not be limited to, daily logs, progress schedules, manpower breakdowns (daily

by trade), financial reports, quantities, material lists, shop drawing logs, etc. In the

event that an interpretation of the meaning and intent of the contract documents

becomes necessary during construction, our Team will ascertain the Architect’s

interpretation and transmit such information to appropriately.

Our Team will hold weekly job meetings with the owner’s representatives,

Architects and other necessary parties to discuss procedures, progress, problems,

scheduling, and open items.

Our Team will constantly review the adequacy supervision, personnel, equipment

and the availability of necessary materials and supplies. When inadequate, our team

will direct the necessary action to be taken by the subcontract involved.

Our Team will assist the Client in obtaining the general building permits and

Certificates of Occupancy as required, and will coordinate the obtaining of all legally

required permits, licenses and certificates. We will assemble these documents from

the contractors and deliver them at the completion of the work.

Page 24: 3   pma salehuddin - resource and project management

18

Our Team will coordinate all work until final completion and acceptance of the

project by the Client, including a comprehensive final inspection to ensure that the

materials furnished and work performance are in accordance with the contract

documents.

Coordinate Testing and Inspection. XYZ Berhad will develop and enforce a quality

control system in order to ensure that the highest required standards of construction

are met. Our Team will develop a checking and testing procedure to ensure that all

systems are adequately tested and balanced prior to their acceptance.

Our Team will coordinate all testing provided by others, as required by the technical

sections of the specifications, and as required by the building code.

Our Team will keep an accurate record of all tests, inspections conducted and test

reports.

Our Team will coordinate the services of professional Engineers, and the Architect,

as required by the building codes, for work, if any, that would be performed for the

owner directly.

Coordinate Shop Drawings Submissions. XYZ Berhad will receive and review for

compliance with the contract documents, all shop drawings, materials and other

items submitted by the subcontractors. Requests for approval, delivery schedules,

material lists, shop drawings, samples, plus more, will be commented upon and

submitted to the Architect for concurring approval. Approvals of technical adequacy

of shop drawings and samples will remain the duty of the Architect. We will oversee

the submission of all shop drawings, composite shop and coordination drawings,

brochures and material samples

Labor and Community Relations. XYZ Berhad will make recommendations, as

necessary, for the development and administration of an effective labor and

community relations program for the project and for avoidance of labor disputes

during construction.

Page 25: 3   pma salehuddin - resource and project management

19

Changes in the Work. XYZ Berhad will establish and implement procedures for

controlling and processing change orders that will satisfy the owner’s requirements.

Our Team will maintain adequate cost accounting records with respect to portions of

work, if any, performed on a time-and-material, unit cost or similar basis which

require the keeping of records and computations.

General Conditions Items. XYZ Berhad will provide general conditionsitems as

required by the project for clean-up, hoisting, temporary facilities, protective field

offices and field telephone for the use of owner representatives and their consultants.

Our Team will provide adequate personnel to supervise those items and will

constantly track and report on General Conditions expenses.

Proactive Scheduling. The schedule will be used as a tool to discuss deliveries and

installation sequences. Any problems or issues will be addressed accordingly and the

schedule will be adjusted to reflect the changes, if necessary. We will update the

current schedule and review it against the baseline schedule to identify potential

conflicts or impacts due to the latest adjustments. The schedule will then be

discussed with the owner and subcontractors reviewing possible solutions to

minimize the impacts and take proactive steps necessary to insure that the project

will be delivered on time and within budget.

Closing Out the Project. At the proper time, the Project Team will coordinate with

the Architect the preparation of a punch list indicating the items of work remaining

to be accomplished and will ensure that these items are completed in an expeditious

manner. Our Team will prepare certificates of substantial and final completion, as

required, and will assemble all guarantees, warranties, etc., as required by the

contract documents, and will forward them to the owner, certifying that they are

complete and cover all work as required. Our Team will coordinate and expedite the

preparation by the subcontractors of operating manuals and similar instructions. Our

Team will also obtain the Architect’s approval to ensure that they are sufficiently

comprehensive and will forward them to appropriate personnel. XYZ Berhad will

work closely with all project personnel relative to start-up following project

completion. This not only includes maintenance personnel, but also personnel who

Page 26: 3   pma salehuddin - resource and project management

20

need to have a working understanding of the building to do their job properly. This

provides the owner with the comfort of knowing our Team is still available, if

needed, to oversee repairs or replacements of specific construction-related items.

Whether a large project or a small one, the XYZ Berhad Team follows a meticulous

methodology that provides the Client with a step-by-step process outlining each of its

many tasks necessary to the successful completion of the project. The ultimate goal

is the commitment of our Team to do whatever is required to make the construction

of every project a consummate success.

Proactive Scheduling. The XYZ Berhad Team approach is to be proactive in

scheduling. Achieving predictable project outcomes is a process that depends on

current and accurate information, communication, and teamwork. We strive to great

lengths to produce an initial target schedule incorporating requirements from all

parties including: owners, designers, contractors, suppliers and end users. This

establishes the baseline schedule that serves as a measuring point for the entire

project. By focusing on the initial scheduling plan we have essentially minimized the

potential problems that will slow down the project. We use Primavera, the most

comprehensive scheduling program available, as our scheduling software. The

Project Team will review the 14-day look-ahead schedules weekly during the

subcontractor’s and owner’s coordination meetings. The schedule will be used as a

tool to discuss deliveries and installation sequences. Any problems or issues will be

addressed accordingly and the schedule will be adjusted to reflect the changes, if

necessary. The Project Team will update the current schedule and review it against

the baseline schedule to identify potential conflicts or impacts due to the latest

adjustments. The schedule will then be discussed with the Client and subcontractors

in order to review possible solutions to minimizing impacts and methods of taking

proactive steps necessary to insure that the project will be delivered on time and on

budget.

Page 27: 3   pma salehuddin - resource and project management

21

3.4.2 Project Diagrams

The initial proposed inception of the project are in the diagram/site plan as shown in the

appendix section of the project proposal. Please refer to the appendices section.

3.4.3 Deliverable Specifications

Page 28: 3   pma salehuddin - resource and project management

22

3.4.4 Project Scheduling

Figure 3.4.4 : Project Scheduling

3.4.5 Implementation Plan

Referring to the Gantt Chart in the Project Scheduling above, an estimated of 26

million construction hours will be required throughout the duration of the project.

The construction workforce is estimated to peak in late 2014 and early 2015. The

site construction labour force is based on a 14 days on 7 days off, two-shift, 10 h/d

rotation. Lessons learned from previous large project experiences will be applied to

develop and maintain control strategies for efficient project execution. A detailed

implementation plan will be produced once the contract with XYZ Berhad is agreed

upon which will include; development and execution, Engineering and procurement,

temporary facilities, project camp and transportation and construction according to

the phases of the project. The following figures are the implementation flow chart

and work breakdown structure:

Page 29: 3   pma salehuddin - resource and project management

23

Figure 3.4.5a : Project Flow Chart

Page 30: 3   pma salehuddin - resource and project management

24

Figure 3.4.5b : Work Breakdown Structure

Figure 3.4.5b : Continued

Page 31: 3   pma salehuddin - resource and project management

25

3.4.6 Statement of Work

A detailed statement of work according to the scheduled milestone and other

requirements consisting of period of performance, place of performance and work

requirements (kickoff, design, implementation and closure). The scope of work for

the project are:

Project Strategy: Prepare an overall master program setting out the summary of

major activities and overall project duration and major milestones.

Conceptual Cost Estimate: Based on conceptual design monitor and manage the

Quantity Surveyor to prepare an elemental Conceptual Cost Estimate.

Procurement Strategy: Develop a strategy of how the construction will be procured

(contract packaging), taking into consideration specific project conditions in terms of

time, design, local and international resources, long lead deliveries, local

requirements, site-wide purchasing opportunities and standard contract

documentation, with input from the Client’s Consultants.

Project Organisation Structure: Prepare project specific organization plans and

structures and define responsibilities and reporting relationships.

Project Procedures Manual: With the Consultants prepare the Project Procedures

Manual, to cover project details, directory, communications, reporting, financial

matters, meetings, drawings, circulation of correspondence, bid packages, tenders,

payments, defects liability and certification requirements.

Construction Strategy: Develop a preliminary overall construction strategy of the

Site including phasing and sequencing, logistic and safety plan.

Design Process Management: With the Design Team, establish detailed design

programs and identify deliverables including drawings, design calculations,

Page 32: 3   pma salehuddin - resource and project management

26

specifications and quality control procedures. Monitor design progress, identify

programme divergence and recommend remedial action. Solicit from the Client’s

Consultants and report on cost and time effects of design changes. Monitor that the

Lead Architect holds regular Design Team meetings to resolve outstanding matters.

Document Control Implementation: With the Design Team, implement document

issue, numbering, coding and distribution system.

Project Cost Plan: When the design develops to the degree where the quantities and

specifications are available, monitor and manage the Quantity Surveyor to develop

the elemental Conceptual Estimate into a detailed elemental Cost Estimate which,

when agreed with the Client, becomes the Project Cost Plan.

Cost Management: Assist the Client in establishing the Project Budget using the

Project Cost Plan. Monitor the Project Budget throughout the Project life. With the

Quantity Surveyor provide the Client with information on the financial status of the

Project, actual cost against Cost Plan, cash flow analyses and forecasts, impact of

change orders and forecast anticipated cost needed to complete the Project. Review

and advice on payments to Contractors and Consultants.

Liaise with Authorities: Assist the Client in liaison with government authorities,

statutory agencies and utility companies i.e. planning permits, building regulations,

transportation, water and power.

Procurement / Pre-contract & Bidding: Implement strategies, plans and guidelines for

the procurement of all Project services. Solicit interest and assist in the development

of bid lists, pre-qualification and tender schedules, and attend Bid Clarification

Meetings.

Contract Documentation: Determine scope of contracted elements, advice on the

preparation of contractual terms, and monitor and manage the preparation of

construction contracts or purchase orders.

Page 33: 3   pma salehuddin - resource and project management

27

Buildability Analysis: Undertake buildability analysis and review main contractors’

method statements with a view of optimising proposed methods of construction in

terms of cost, time and quality.

Pre-Construction Works: Advice and assist the Design Team and the Client in

obtaining all requisite approvals, for pre-construction activities.

Schedule Management: Establish schedule reporting formats, manage and report on

the progress against the established Master Programme. Develop detailed schedules

as necessary for easy monitoring purposes.

Contract(s) Tender & Award: Manage the tender process, evaluate and recommend

award of construction contracts and on behalf of the Client, issue formal notices to

proceed.

Detailed Design: Review and monitor the completion of designs and specifications

within the programme.

Construction: On behalf of the Client, periodically review progress and performance,

chair weekly site meetings and advice on any issues.

Monitoring of Construction Progress: Review, monitor and advice on the

construction progress against schedule.

Quality Assurance / Quality Control: Review and advice on the Quality Assurance /

Quality Control implemented by the Architect & consultants of the Client.

Site Safety: On behalf of the Client, periodically review and audit the Contractor’s

HSE plan for implementation and compliances.

Page 34: 3   pma salehuddin - resource and project management

28

Document Control Implementation (where applicable): With the Project Team,

review and if necessary, recommend document issue, numbering, coding and

distribution system.

Change Order Management: Review and advice on the Change Order reporting

system.

Performance Measurement: Report on progress as the project evolves, in terms of

work performed and progress achieved, tying together physical progress and

financial status. Review compliance and assess performance of all Project

participants.

Cost Management: Review the Client’s Project Budget. Monitor the cost of changes

prepared by the Quantity Surveyor against the budget. With the Quantity Surveyor,

Architect, provide the Client with information on the financial status of the project,

actual cost against cost plan, cash flow analyses and forecast, impact of change

orders and forecast anticipated cost needed to complete the Project.

Reporting: Assemble monthly reports which include progress photographs, status of

design, permits or licenses, performance, schedule report, cost / financial reports,

bonds, problem areas and recommendations for action.

Commissioning: Review and advice on the procedures for the commissioning of all

services that are established and implemented by others.

Additional Services: Additional services shall be all other services required by the

Client that are not outlined in basic services above and shall be subject to such

additional fees to be agreed with the Client. For the avoidance of doubt, should the

scope of the Project increase substantially beyond the basic services, or the basic

services are required to be performed beyond the scheduled period as specified in the

agreement, such services shall be deemed to be additional services subject always to

prior written approval of the Client, provided always that such approval shall not be

unreasonably withheld. Should the Client request any additional services required

Page 35: 3   pma salehuddin - resource and project management

29

completing the Project during the period of the agreement; the Project Manager shall

be compensated for based upon a monthly fee to be agreed with the Client. The

Project Manager shall notify in advance the Client in writing and to obtain the

Client’s prior written approval provided always that such approval shall not be

unreasonably withheld, before such additional services are to be performed by the

Project Manager.

3.4.7 Administration Plan

This detailed administration plan after the award of contract to XYZ Berhad is

intended to:

(1) Identify needs and resources for administering contracts.

(2) Identify team members for construction administration.

(3) Establish interrelationships of team members and relative authority

and responsibilities.

(4) Establish procedures and processes for the timely approval of change

orders, claims and field adjustments.

(5) Provide for decision making at the lowest level possible for change

orders, claims and field changes.

(6) Provide mechanisms for timely and routine meetings between the

Contractor and the construction administration team during construction;

Reports and Monitoring. In addition to any other reports and forms required for

construction management, the Project Team must submit the following reports on a

weekly basis:

(1) Daily Inspection Reports.

(2) Weekly Contract Time Summary.

(3) Weekly Quantity and Cost Estimate Summary

These reports shall be submitted to the Project Manager. The Project Manager then

submits a Monthly Project Status Report to the Client.

Page 36: 3   pma salehuddin - resource and project management

30

3.4.8 Logistic Support

Figure 3.4.8 : Logistic Supply Chain

Table 3.4.8a : Logistic Plan Guideline

Page 37: 3   pma salehuddin - resource and project management

31

Table 3.4.8b : Sample of Logistic Support

3.4.9 Quality Plan

DESIGN DEVELOPMENT QA/QC.

Design review will be an ongoing activity, XYZ BERHAD will perform major

reviews of the contract documents. Design changes will be tracked as identified in

the contract. XYZ BERHAD will review drawings at each of the above stages of

completion to ensure constructability and functionality. These reviews will also be

used to ensure that schedule and budget remain in compliance with the original RFP.

XYZ BERHAD will provide contract document timeline requirements to the

consultants to ensure that the overall project schedule is maintained.

ARCHITECTURAL QA/QC.

Unless otherwise excluded from the scope of work, the Architect will carry out a

general review of the construction work at intervals appropriate to the stage of

construction, which the Architect consider necessary to determine if the work is in

general conformity with the contract documents. The general review of construction

will be carried out and will include the following:

Page 38: 3   pma salehuddin - resource and project management

32

1. Commences during the design and documentation phases with review of the

required quality and performance of each Architectural component.

2. Project is continued with appropriate documentation to establish levels of quality

and performance.

The Architect will:

1. Review mock-ups and field samples of work, when requested by XYZ BERHAD,

for compliance with drawings and specifications, and if necessary to establish quality

control standards for the work.

2. Attend meetings with XYZ BERHAD, their Client and suppliers to assist in

resolution of construction, sequencing and quality control matters.

3. Review work during the course of construction, on a random sampling basis for

conformance with the requirements of the documents and good acceptable trade

practices.

4. Review finished areas of work for acceptance, recording deficiencies and

providing a written report to XYZ BERHAD on the day of the inspection.

5. Follow up with XYZ BERHAD to review work redone and deficiencies corrected.

6. Coordinate with the quality control/assurance work of others (structural,

mechanical, electrical, etc.) to ensure consistency of approach, level of quality

assurance and reporting documentation.

7. Keep current and updated Architectural drawings to assist XYZ BERHAD in

preparing as-builts at completion of project.

8. Certify payment for construction work, monthly progress draws and holdback

release.

9. Certify upon completion to the authorities having jurisdiction where the work has

been built in conformance with the approved drawings and specifications.

STRUCTURAL QA/QC.

Field Review of Concrete Construction:

1· The classes of concrete exposure and strengths of concrete required for different

elements of the structure.

Page 39: 3   pma salehuddin - resource and project management

33

2· Special requirements for some elements such as minimum cement content, special

aggregate grading, super-plasticizers in columns, walls or slabs on grade.

3. Concrete testing procedures on high strength concrete.

4· Verify that proposed mixes have been submitted and that they are acceptable

specified tolerances.

5· Requirements for review of formwork construction by Engineer responsible for

formwork design.

6· Curing procedures.

7· Hot & cold weather protection requirements.

8· Requirements for saw-cutting of slabs on grade.

9· Review and approve conduit and sleeving requirements

Excavation and Foundations QA/QC:

1· Excavation Shoring

2· Review with XYZ BERHAD requirements for monitoring location and movement

of shoring, for testing of tie-backs and installation of lagging.

3· Review site visit reports submitted by Engineer.

4· Review geotechnical reports submitted by the Engineer.

Foundations QA/QC:

1· Confirm with XYZ BERHAD that bearing conditions at footings and verified that

they are acceptable for the support of the loads at the design pressures.

2· Check the dimensions and reinforcement of column and wall footings / piles.

Formwork QA/QC:

1· Review with XYZ BERHAD the requirements for camber and elevation survey of

formwork for slab pours as outlined in the specification.

2· Review with XYZ BERHAD proposed stripping and re-shoring sequencing.

3· Review reports of site review of formwork and shoring.

4· Before concrete is placed, confirm that forms are clean of debris and other foreign

material by a random check of the form area.

Page 40: 3   pma salehuddin - resource and project management

34

Concrete Walls QA/QC:

1· Grade walls with minimum reinforcement

2· Review length of wall pours with XYZ BERHAD.

3· Check wall pour for dimension, cleanliness of forms, reinforcement size, and

cover of pours.

4· Review inspection reports of concrete supplied.

5· Check wall thickness, rebar size, spacing, cover, placement and length of wall

pours.

6· Review inspection reports of concrete supplied.

Columns QA/QC:

1· Check the dimensions, rebar size and placement of columns poured.

2· Review inspection reports of concrete supplied.

Slabs QA/QC:

1· Check slab thickness, rebar size, spacing, cover and chairing of the slab pour

areas.

2· Check beam dimensions, rebar size, quantity cover and chairing of beams.

3· Review inspection reports of concrete supplied.

Beams QA/QC:

1· Check beam dimensions, rebar size, quantity, cover and chairing of rebar.

2· Review inspection reports of concrete supplied.

Tolerance for Suspended Concrete Flat Slab QA/QC:

1· Review with XYZ BERHAD the specified floor finish tolerances and camber

requirements.

2· Review results of survey of finish of concrete surface taken before formwork is

removed.

3· Review results of survey of slabs taken after shoring is removed.

Page 41: 3   pma salehuddin - resource and project management

35

Slabs On Grade QA/QC:

1· Review requirements for sub-base.

2· Review the report of compaction testing carried out, and ensure the subgrade is

acceptable.

3· Review with XYZ BERHAD the specified floor finish tolerances.

4· Check slab thickness and location of bulkheads for construction joints.

5· Review the proposed curing methods and that compatibility with subsequent

finishes has been considered.

Precast Concrete QA/QC:

Review that the appropriate level of quality assurance is provided in the

interpretation of the design requirements, the preparation of shop drawings, the

manufacture of components and in the assembly of the components in the field.

Structural Steel QA/QC:

1· Review with the structural steel subcontractor their proposed procedures for

welding inspection.

2· Review painting requirements specified versus paint on steelwork delivered to

site.

3· Review reports submitted by structural steel subcontractor.

Load Bearing and Engineered Masonry QA/QC:

1· Review with XYZ BERHAD which masonry (if any) is Engineered.

2· Review with XYZ BERHAD the test required for Engineered masonry.

3· Review reports prepared if Engineered masonry is used.

4· Review typical bearing details and anchorage.

Masonry Based On Engineered Analysis QA/QC:

1· Review with XYZ BERHAD supply of masonry units to specified strength, mortar

and grout requirements.

2· Check reinforcement size, spacing and placement.

Page 42: 3   pma salehuddin - resource and project management

36

MECHANICAL QA/QC.

Engineer or delegate under his supervision, shall:

1. Make periodic visits to the site to determine that the work is in general conformity

with the mechanical plans and related specifications for the mechanical systems;

2. Record mechanical deficiencies found during site visits and provide written

reports of the deficiencies to the Architect and XYZ BERHAD– this report is to be

issued on the day of the inspection;

3. Review and take action if necessary, the reports of independent inspection, testing

called for in the mechanical plans and related specifications and which pertain

directly to the work being reviewed;

4. Attend mechanical / electrical site coordination / commissioning meetings and

others when requested to do so by XYZ BERHAD;

5. Interpret mechanical plans and related specifications when requested to do so;

6. Review shop drawings and samples submitted for compliance with the intent of

the mechanical plans and related specifications.

Underground Plumbing QA/QC:

1· Hot and cold weather protection requirements.

2· Bedding materials and installation.

3· Incoming service connections.

4· Sleeving.

5· Quality and standard of workmanship.

6· High pressure steam.

7· Welding.

8· X-ray.

Above Ground Plumbing QA/QC:

1· Installation of drainage products.

2· Pipe installation, materials, hangers and venting.

3· Sleeving.

4· Quality and standard of workmanship.

5. Unions or flanges: provide for ease of maintenance and disassembly.

6. Space for servicing, disassembly and removal of equipment and components.

Page 43: 3   pma salehuddin - resource and project management

37

7. Equipment drains: pipe to floor drains.

8. Install equipment, rectangular cleanouts and similar items parallel to or

perpendicular to building lines.

ELECTRICAL QA/QC.

The general review, which shall be carried out by a Professional Engineer of delegate

under his supervision shall:

1. Make periodic visits to the site to determine that the work is in general conformity

with the electrical plans and related specifications for the electrical systems;

2. Record electrical deficiencies found during site visits and provide written reports

of the deficiencies to the Architect and XYZ BERHAD’s General Superintendent;

3. Review the reports of independent inspection, where these pertain directly to the

work being reviewed;

4. Attend mechanical / electrical site coordination / commissioning meetings and

others when requested to do so by XYZ BERHAD ;

5. Interpret electrical plans and related specifications when requested to do so by

XYZ BERHAD;

6. Review shop drawings and samples for compliance with the intent of the electrical

plans and related specifications.

Field Review of Underground Conduit and Services QA/QC:

1· Incoming services.

2· Concrete duct-banks.

3· Concrete encasement of slab-on-grade raceways.

4· Raceway materials.

5· Quality and standard of workmanship.

Field Review of Conduit in Suspended Slabs QA/QC:

1· Conduit routing.

2· Conduit crossings.

3· Materials.

4· Quality and standard of workmanship.

Page 44: 3   pma salehuddin - resource and project management

38

Field Review of Cabling QA/QC:

1· Cable installation.

2· Cable termination.

Field Review of Lighting & Equipment QA/QC:

1· Fixture support and alignment.

2· Equipment mounting.

3· Equipment designations.

4· Equipment locations.

5· Resolving coordination conflicts arising on site.

6· Quality and standard of workmanship.

CONSTRUCTION INSPECTION & TESTING PLAN QA/QC

XYZ BERHAD’s inspection and testing plan for the Education College has been

developed by drawing on information available in the RFP, as well as the experience

of XYZ BERHAD Staff and input from the Client. Inspection of materials and work

in progress will be the responsibility of XYZ BERHAD to ensure that the work

conforms to the contract documents and is ready for testing or inspection by an

independent testing agency.

Field Inspection QA/QC:

1. Pre-Work Coordination Meetings: Prior to any trade contractor starting work, a

pre-work coordination meeting will be held. XYZ BERHAD’s Project Manager will

chair the meeting and prepare an agenda. At a minimum, the meeting agenda will

cover contract, submittal, quality control, training, safety and environmental

requirements of the contract documents, as well as work and coordination

procedures.

2. Follow-Up Inspection: XYZ BERHAD will monitor the work on a daily basis to

assure the continuing conformance of the work to the workmanship standards.

Architect will provide site review as required by BC. Follow-up inspections will be

Page 45: 3   pma salehuddin - resource and project management

39

monitored by XYZ BERHAD Quality Control to ensure all deficiencies are

corrected.

3. Completion Inspection. When an area of work is complete, XYZ BERHAD

Quality Control will conduct completion inspections. Deficiencies will be noted on a

deficiency list. The appropriate testing agency will perform testing for those sections

of work as noted.

Approved Material Inspections QA/QC:

All materials, equipment, etc. to be incorporated into the work will be subject to

periodic inspection by the Quality Control staff. XYZ BERHAD will utilize a five

point field inspection:

1· Proper identification

2· Damage

3· Evidence of prior acceptance

4· Completeness

5· Proper documentation

Material Test Procedures QA/QC:

1. Testing. Take random samples and test them for conformance with the contract

documents. These results will be distributed to all parties. The Quality Control will

review all test results and follow up as appropriate.

2. Samples. Approved samples of materials to be incorporated into the job will be

maintained in the site office for use in comparing to installed material. Site mock-

ups, as required, will be maintained during construction at a designated location on

site.

Re-Work Procedures QA/QC:

All deficiencies or deviations from specified requirements, with respect to quality,

workmanship, materials, equipment or supplies will be dealt with in the following

manner:

1. Deficiencies to be noted on Inspection Report.

Page 46: 3   pma salehuddin - resource and project management

40

2. Deficiencies will be immediately corrected and Quality Control to ensure

reinspection is performed and all deficiencies corrected.

3. Track deficiencies using the central inspection record log.

4. The XYZ BERHAD Project Manager and Quality Control will meet with all

parties involved in any deficiency to determine a solution to the problem. The

solution will then be recorded and implemented in accordance with contract

documents. Once the deficiency has been rectified, the Quality Control Inspector will

re-inspect the original deficiency in regard to the agreed solution. If warranted,

deficient work which cannot be satisfactorily corrected in place will be removed and

replaced at the written direction. All such re-work shall be performed using

procedures written and approved.

DOCUMENTATION FOR NON-CONFORMITIES

Each inspector for the Architect shall submit a list of deficiencies to XYZ BERHAD

following each inspection. XYZ BERHAD will log these items on a central

deficiency log, and distribute the inspection reports to the Client. A copy of the log

for each inspection will be printed off and placed in a binder in the job site plan

room. Once the deficient item has been corrected and reinspected, the inspector will

sign off against the item in the plan room binder copy.

DOCUMENTATION/RECORDS

Quality Control records will be maintained by XYZ BERHAD’s Quality Control.

The quality control files will be protected from deterioration or damage throughout

the period of the contract. Hard copies of all quality control records will be

maintained in file cabinets. An electronic database will be utilized to facilitate

retrieval of documents. The quality control records will be indexed and filed within

the XYZ BERHAD filing system.

Page 47: 3   pma salehuddin - resource and project management

41

CHANGES TO CONTRACT

Change Orders, Variations and RFI will be issued to the Architect and applicable

parties. All drawings will be kept up to date with changes or technical information

being recorded and logged as revisions are received. Trade contractors affected by

Change Orders or RFI will be notified as quickly as possible. All RFI will be posted

and distributed to all affected parties. A master log book for recording all Change

Orders will be maintained by XYZ BERHAD. Voided drawings or documents will

be marked as such.

AUDITING PROCEDURES

XYZ BERHAD’s Project Management Team and the XYZ BERHAD Peer Review

Team will perform periodic audits of the Quality Control Program, including Quality

Control and Quality Assurance Programs. These audits will verify to the authority

that the required quality is being maintained and that the records reflect the actual

quality of the work.

3.4.10 HSE Plan

MANAGEMENT STRUCTURE AND RESPONSIBILITIES

The responsibilities of the site management team such as the site manager, site

foreman and Safety Officer can be found within the company’s health and safety

policy within the health and safety folder in the site office.

HEALTH AND SAFETY TARGETS FOR THE PROJECT – SETTING

STANDARDS

1. This project will be completed with no major injury accidents.

2. All workers will attend appropriate safety induction and tool box talks that will be

recorded and monitored.

Page 48: 3   pma salehuddin - resource and project management

42

HEALTH AND SAFETY ARRANGEMENTS

1. Regular Liaison. This is achieved via progress meetings, which will include a

health and safety item on the agenda. The discussions and actions arising from each

meeting will be noted and distributed to all interested parties for further

dissemination within their respective organisations. The Safety Officer will carry out

toolbox talks on site. When appropriate the arrangements for communicating with

workers who do not speak Bahasa Malaysia or English as a second language will be

followed. These are detailed within the company’s health and safety policy in the

health and safety folder which is located in the site office.

2. Consultation With the Workforce. Employees and sub-contractors are encouraged

to raise health and safety issues and concerns with the site foreman on an ongoing

basis and during toolbox talks. SDIS will be made available to any employee or sub-

contractor who wishes to see them.

3. Handling Design Changes During Construction Phase. The site manager will

consult with the Client if any significant design changes arise during the course of

construction which give rise to additional significant risks. (eg. the hollow core floor

slabs will be a contractor design). These can be discussed during the progress

meetings.

3. Site Security/Access. The site security requirements identified in the site security

risk assessment will be fully implemented.

4. Site Induction. All those working on site will be briefed during the induction stage

on the main risks associated with the site and relevant information. The site foreman

will check for evidence of competence when personnel arrive on site which may

include training records. Visitors will be given a brief site induction – they will be

accompanied at all times. A young person’s risk assessment will be carried out at this

stage for all personnel who are under 18 years of age and this will be held in the

company’s health and safety folder located in the site office.

Page 49: 3   pma salehuddin - resource and project management

43

5. On Site Training. Where appropriate, on the job training will be given under the

supervision of a competent person. Details of training will be recorded and held in

the company’s health and safety folder within the site office.

6. Welfare Facilities and First Aid Arrangements. Welfare facilities such as site

office, canteen facilities and a toilet connected to a foul sewer will be on site within a

compound for the duration of the contract. The welfare facilities provided will

contain hot running water, heating and facilities for heating food. During the

induction, all employees and visitors will be adviced of the location of the welfare

facilities and canteen. There will be an appointed person/first aider on site, along

with a fully stocked first aid kit located in the site office. There will be a mobile

phone available on site to summons an ambulance if needed. Details of the local

hospital will be located within the site office. To prevent the infestation of rodents all

food will be consumed within the designated canteen area. Personnel are not

permitted to consume or be under the influence of alcohol or illegal substances on

site.

7. Reporting Of Accidents, Incidents and Near Misses. All accidents must be

reported and recorded (health and safety folder located in the site office). An

accident book can be used for this purpose. All accidents will be investigated to

prevent any re-occurrence. The site foreman will be responsible for completing a

HIRARC form where necessary and will advice the site manager of all accidents,

incidents and near misses. All HIRARC forms will be forwarded to Safety Officer by

the site manager.

8. Production and Approval of Method Statements. The residual risk register

provided by the designer, the SDIS and the risk assessments will all be used to

inform the method statements for the project. The site manager/site foreman will

review and explain all method statements to the appropriate personnel, who will be

carrying out or affected by the particular work activity. The site manager will arrange

for any additional risk assessments and method statements to be written if necessary.

Page 50: 3   pma salehuddin - resource and project management

44

9. Site Rules. All those working on this project will be briefed on the site rules

during the induction stage.

10. Fire and Evacuation Procedures. Fire and evacuation arrangements will be

displayed in the site office and canteen.

HIRARC

A detailed HIRARC will be prepared and regularly updated once the project is

commenced. These will be the responsibility of the Safety Officer for controlling

significant site risks. The risk assessments can be found within the company’s health

and safety folder located in the site office.

3.4.11 Risk and Mitigation Plan

RISK MANAGEMENT APPROACH

The approach we will take to manage risks for this project included a methodical

process by which the Project Team identified, scored, and ranked the various risks.

The most likely and highest impact risks were added to the project schedule to ensure

that the assigned Risk Managers take the necessary steps to implement the mitigation

response at the appropriate time during the schedule. Risk Managers will provide

status updates on their assigned risks in the bi-weekly Project Team meetings, but

only when the meetings include their risk’s planned timeframe. Upon the completion

of the project, during the closing process, the Project Manager will analyze each risk

as well as the risk management process. Based on this analysis, the Project Manager

will identify any improvements that can be made to the risk management process for

future projects. These improvements will be captured as part of the lessons learned

knowledge base.

Page 51: 3   pma salehuddin - resource and project management

45

RISK IDENTIFICATION

For this project, risk identification is be conducted in the initial project risk

assessment meeting. The method used by the Project Team to identify risks was the

Crawford Slip method:

1. Expert Interview. The interviews revealed several risks which were then mitigated

by making changes to the project plan. The remaining risks are included in the Risk

Register.

2. Risk Assessment Meeting. A risk assessment meeting was held with key team

members and stakeholders. The risks identified during this meeting were added to

the project plan and Risk Register.

3. Historical Review of Similar Projects. The Project Team reviewed the history of

similar projects in order to determine the most common risks and the strategies used

to mitigate those risks.

RISK QUALIFICATION AND PRIORITIZATION

In order to determine the severity of the risks identified by the team, a probability

and impact factor was assigned to each risk. This process allowed the Project

Manager to prioritize risks based upon the effect they may have on the project. The

Project Manager utilized a probability-impact matrix to facilitate the team in moving

each risk to the appropriate place on the chart. Once the risks were assigned a

probability and impact and placed in the appropriate position on the chart, the

recorder captured the finished product and the Project Manager moved the process

on to the next step: risk mitigation/avoidance planning.

Page 52: 3   pma salehuddin - resource and project management

46

RISK MONITORING

The most likely and greatest impact risks have been added to the project plan to

ensure that they are monitored during the time the project is exposed to each risk. At

the appropriate time in the project schedule a Risk Manager is assigned to each risk.

During the bi-weekly Project Team meeting the Risk Manager for each risk will

discuss the status of that risk; however, only risks which fall in the current time

period will be discussed. Risk monitoring will be a continuous process throughout

the life of this project. As risks approach on the project schedule the Project

Manager will ensure that the appropriate Risk Manager provides the necessary status

updates which include the risk status, identification of trigger conditions, and the

documentation of the results of the risk response.

RISK MITIGATION AND AVOIDANCE

The Project Manager will lead the Project Team in developing responses to each

identified risk. As more risks are identified, they will be qualified and the team will

develop avoidance and mitigation strategies. These risks will also be added to the

risk register and the project plan to ensure they are monitored at the appropriate

times and are responded to accordingly.

The risks for this project will be managed and controlled within the constraints of

time, scope, and cost. All identified risks will be evaluated in order to determine

how they affect this triple constraint. The Project Manager, with the assistance of the

Project Team, will determine the best way to respond to each risk to ensure

compliance with these constraints.

In extreme cases it may be necessary to allow flexibility to one of the project’s

constraints. Only one of the constraints for this project allows for flexibility as a last

resort. If necessary, funding may be added to the project to allow for more resources

in order to meet the time (schedule) and scope constraints. Time and scope are firm

constraints and allow for no flexibility. Again, the cost constraint is flexible only in

extreme cases where no other risk avoidance or mitigation strategy will work.

Page 53: 3   pma salehuddin - resource and project management

47

RISK REGISTER

The Risk Register for this project is a log of all identified risks, their probability and

impact to the project, the category they belong to, mitigation strategy, and when the

risk will occur. The register was created through the initial project risk management

meeting led by the Project Manager. During this meeting, the Project Team

identified and categorized each risk. Additionally, the team assigned each risk a

score based on the probability of it occurring and the impact it could potentially

have. The Risk Register also contains the mitigation strategy for each risk as well as

when the risk is likely to occur.

Based on the identified risks and timeframes in the risk register, each risk has been

added to the project plan. At the appropriate time in the plan—prior to when the risk

is most likely to occur—the Project Manager will assign a Risk Manager to ensure

adherence to the agreed upon mitigation strategy. The Risk Manager will provide

the status of their assigned risk at the bi-weekly Project Team meeting for their risk’s

planned timeframe.

Table 3.4.11 – Risk Register

Page 54: 3   pma salehuddin - resource and project management

48

Table 3.4.11 – Continued

Page 55: 3   pma salehuddin - resource and project management

49

Table 3.4.11 – Continued

Page 56: 3   pma salehuddin - resource and project management

50

3.5 COST AND PAYMENT APPROACH

3.5.1 Cost Estimate

3.5.2 Type of Contact

Every construction project has its own set of circumstances that can involve timing,

legal obligations, ownership configuration, limitations, financing objectives, owner

in-house resources, and more. XYZ Berhad construction company offers a variety

types to suit your needs. The following is a list of the basics of the various

contractual arrangements available in order to assist the Client’s decision-making

process:

Page 57: 3   pma salehuddin - resource and project management

51

1. GUARANTEED MAXIMUM PRICE

A GMP contract is a cost-type contract, in which the construction contractor is

compensated for actual costs incurred, plus a fixed fee subject to a ceiling price. The

contractor is responsible for cost overruns, unless the GMP has been increased via

formal change order as a result of additional scope from the Client. Savings resulting

from cost underruns are returned to the Client.

2. LUMP SUM

The contractor agrees to build a project with a specific scope for a fixed price. A

lump-sum contract is suitable if the scope and schedule of the project are sufficiently

defined to allow the contractor to fully estimate project costs.

3. UNIT PRICE

This kind of contract is based on estimated quantities of items included in the project

and their unit prices. The final price of the project is dependent needed to carry out

the work. In general, this contract is only suitable for projects in which the scope is

reasonably well established, and the different (but not their numbers) can be

accurately identified in the contract documents.

4. COST PLUS

Cost plus is a contract agreement wherein the purchaser agrees to pay the cost of the

work, including all trade contractor work, labor, materials, an amount for contractor

overhead and profit. These types of contracts are favored where the scope of work is

indeterminate or highly uncertain, labor, material, and equipment needed are also

uncertain.

5. COST-REIMBURSABLE ALTERNATIVE

With cost-reimbursable alternative contracts, contractors are paid for the work with a

mix of reimbursable and fixed or incentive costs. Cost-reimbursable contracts are

effective when the general scope of work and schedule are defined, but there is

uncertainty in quantities or execution. Under cost-alternative contracts, uncertainty in

project scope is borne by the Client. Cost-reimbursable alternative contracts offer

significant flexibility for responding that are uncertain. There are different variations

Page 58: 3   pma salehuddin - resource and project management

52

of basic cost-reimbursable alternative contracts, including cost-reimbursable plus

fixed fee, cost-performance-based incentives, direct cost-reimbursable plus fixed

construction management costs, and others.

6. INTEGRATED PROJECT DELIVERY/ALLIANCE

IPD contracts, or “Alliance” contracts, represent the latest trend towards a more

collaborative approach to delivering IPD contracts are unique in that they require the

involvement of owners, designers, builders, and key stakeholders on a project as early

as possible— at the conceptual stage. This contract type results in more transparency

among all the parties involved on a construction project. Additionally, both shared by

the parties who enter into the IPD contract, resulting in greater integration of

resources, processes, and expertise than would be possible traditional contract

arrangements.

3.5.3 Payment Terms

XYZ Berhad requires 50% of upfront costs be paid immediately upon award of the

contract. Remaining 50% may be paid upon project close out and beginning of

management and operations of the payroll solution. All monthly fees are due on the

first business day of each month. Any additional work required by the Client outside

of the scope of the contract will be billed separately and will be charged at 50%

immediately upon award of the contract and 50% upon acceptance of the

deliverable(s).

The minimum term for this contract is 12 months from the time of project closeout

and beginning of management and operations of the payroll solution. Any monthly

rate increases for the follow on term will be provided to Archway Consulting no later

than 30 calendar days from the end of the initial 12 month term.

If contract cancellation is required, 90 days of notice must be given by either party.

If the contract is cancelled prior to the completion of the initial term, payment must

be made for all services provided including full payment until the end of the contract

Page 59: 3   pma salehuddin - resource and project management

53

term or 90 days, whichever is longer. Late payment fees will be assessed after 30

days. Final terms and conditions will be provided in final contract.

3.6 CONTACT

XYZ Berhad is here to serve you. Please feel free to contact the Project Manager at

any time if you have any questions or require additional information.

XYZ Berhad

(Attn: Salehuddin Bin Abdul Kadir)

123 Jalan Harimau

Bandar Gagah,

40200 Kuala Lumpur

(019-3765957)

[email protected]

www.XYZ-Berhad.com

Page 60: 3   pma salehuddin - resource and project management

54

REFERENCES

Billows D. (2002). Essentials Of Project Management, Hampton Group: USA.

Charvat J. (2003). Project Management Methodologies: Selecting, Implementing,

Supporting Methodologies and Processes For Projects, John Wiley & Sons:

USA.

Cleland D.I. and King W. R. (1988). Project Management Handbook, 2nd

Edition,

Van Nostrand Reinhold: USA.

Clements J. P. and Gido J. (2009). Effective Project Management, South Western

Cengage Learning: USA.

Clements J.P. and Gido J. (2003). Successful Project Management, 2nd

Edition,

Thomson South Western: USA.

Mohd Yusof Md Daud (2013). Lecture notes. UTM KL: KLIA College.

Field M. and Keller L. (1998). Project Management. International thomson Business

Press: UK.

Harvad Business School (2004). Managing Projects Large and Small: The

Fundamental Skills For Delivering On Budget And On Time, Harvar

Business School Press: USA.

Haynes M.E. (1989). Project Management: From Idea To Implementation, Crisp

Publications: USA.

Kezner H. (2001). Project Management: A Systems Approach To Planning,

Scheduling and Controlling, 7th

Edition, John Wiley & Sons: USA.

Larson E. W. and Gray C. F. (2011). Project Management: The Managerial Process,

Mcgraw Hill: USA.

Page 61: 3   pma salehuddin - resource and project management

55

Lee H. W. and Kheng L. G. (2004). Project Management, Prentice Hall: Singapore.

Mantel S. J., Meredith J. R., Shafer S.M. and Sutton M. M. (2001). John Wiley &

Sons: USA.

Meredith J. R. and Mantel S. J. (2010).Project Management: A Managerial

Approach, John Wiley & Sons: USA.

Project Management Institute (2008). A Guide To The Project Management Body Of

Knowledge, PMI:USA.

Sunny and Baker K. (1998). The Complete Idiot’s Guide To Project Management,

Alpha Books: USA.

Tan A. A. L. (2006). Project Management As A Dynamic Career, Venton

Professional: Malaysia.

Watson C. S. (1997). Managing Projects For Personal Success, International

Thomson Business Press: USA.

Westland J. (2006). The Project Management Cycle, Kogan Page: UK.

Wysocki R. K., Beck R. and Crane D. B. (2000). Effective Project Management, 2nd

Edition, John Wiley & Sons: USA.

Page 62: 3   pma salehuddin - resource and project management

56

APPENDIX A: Location of Project Site

Page 63: 3   pma salehuddin - resource and project management

57

APPENDIX B: Site Plan

Page 64: 3   pma salehuddin - resource and project management

58

APPENDIX C: Floor Plan

Page 65: 3   pma salehuddin - resource and project management

59

APPENDIX D: Elevation Plan

Page 66: 3   pma salehuddin - resource and project management

60

APPENDIX E: Site Accessibility Plan

Page 67: 3   pma salehuddin - resource and project management

61

APPENDIX F: Utilities Plan