Site Data & Test Report-Node B New Site
Circle AIRTEL KENYAStrategic Partner NOKIADate of Installation DD-MM-YYDate of Integration DD-MM-YYDate of Commissioning DD-MM-YY
Site Name KIHARA_RED_HILL_ROADAirtel 2G Site ID KBU065Airtel 3G Site IDTower company Site ID N/ASACFA ID N/ASite Lat/LongUMTS Band for Node B 900/2100
Type (GBT/RTT/RTP/IBS) GBTType of Node B (HSPA / MIMO ) N/A
Name of Infra Provider (Tower Company) N/AAnchor Operator N/ASharing Opco 1 N/ASharing Opco 2 N/A
Sharing Opco 3 N/A
Sharing Opco 4 N/A
N/A
Sites Layout Attached Acceptance KPI AttachedStandared Node AT Documents attached Site Photographs for RF & EMF AttachedEMF Compliance Format Attached
Site Address N/A
City Nairobi
Site Owner Details N/AName N/AAddress N/AMobile Numbers : N/ALandline Number (R) : N/ALandline Number (O) : N/A
Signoff :
Project Manager ( Airtel ) Project Manager (SP)
Mob Number Mob Number
Sign Sign
Name Name
Date : Date :
Infra Shared(Tower / DG / Shelter / AC / AC Mains / DC Btys etc)
document.xlsx
S.NoNode B
Activity Planned Actual Remarks 1 Site ID: KBU065 SITE ID KBU065 SITE ID KBU065
2 Site Name: KIHARA_RED_HILL_ROAD SITE NAME KIHARA_RED_HILL_ROAD SITE NAME KIHARA_RED_HILL_ROAD
3 BTS B Product Type (Configuration) - Indoor/Outdoor/Split Type OUTDOOR
4BTS B Hardware Details FLEXI MRBase Unit (Model No) N/ATower Unit (Model No) N/A
5 Site Address: N/A
6 Region and Circle: AIRTEL KENYA
7Latitude : -1.21944 -1.21944 NOT SHIFTEDLongitude : 36.77855 36.77855 NOT SHIFTED
8 Feeder Cable Type
Sector 1 Fiber
Sector 2 Fiber
Sector 3 Fiber
9 Feeder Cable Length
Sector 1
Sector 2
Sector 3
10 Power Output
Sector 1
Sector 2
Sector 3
11 BTS Material Check List Attached PAT ATTACHED
12 PAT ATTACHED
15 Test Handset Details Model Serial Number Phone Number SIM Number
FILL FILL FILL
16 Service Test
Voice call PASS
GPRS service test PASS
EDGE service test PASS
SMS Service test PASS
17
Antenna System DetailsItem List Sector 1 Sector 2 Sector 3 Sector 4
Planned Actual Planned Actual Planned Actual PlannedGSM Antenna Type Andrew Andrew Andrew Andrew Andrew Andrew
Antenna Type ( Part Code ) DBXLH-6565B-VTM DBXLH-6565B-VTM DBXLH-6565B-VTM DBXLH-6565B-VTM DBXLH-6565B-VTM DBXLH-6565B-VTM Antenna Quantity 1 1 1 1 1 1Antenna Height (AGL) 57.5 57.5 57.5 57.5 57.5 57.5Azimuth 0 0 120 120 240 240Electrical Downtilt 0 0 0 0 0 0Mechanical Downtilt 2 2 2 2 2 2
TMA
BCCH SCAN BCCH BCCH BCCH
TX Power ( On Top of BTS Cabinet )
18
Sector/ Cell Feeder Type Feeder Length (m) Measured VSWR Test Pass / FailSector 1 N/A N/A N/A
Sector 2 N/A N/A N/A
Sector 3 N/A N/A N/ASector 4 N/A N/A N/A
19
Mention Yes / NoFor Node B Cabinet PAT ATTACHED PAT ATTACHED PAT ATTACHED
PAT ATTACHED PAT ATTACHED PAT ATTACHED
For UMTS Antenns PAT ATTACHED PAT ATTACHED PAT ATTACHEDFor TMA's PAT ATTACHED PAT ATTACHED PAT ATTACHEDFor Indoor Unit PAT ATTACHED PAT ATTACHED PAT ATTACHEDFor Outdoor Unit PAT ATTACHED PAT ATTACHED PAT ATTACHED
20 Earthing check for 2G equipment N/A
21 EMF Testing
Method Adopted
N/A
Compliance (Yes/No) N/A22 Wiring Diagram Enclosed Yes/No
23 GSM Alarm Verification
Critical Alarms Yes/No Yes/No Yes/NoTo be filled PAT ATTACHED PAT ATTACHED PAT ATTACHEDTo be filled PAT ATTACHED PAT ATTACHED PAT ATTACHEDTo be filled PAT ATTACHED PAT ATTACHED PAT ATTACHEDTo be filled PAT ATTACHED PAT ATTACHED PAT ATTACHEDTo be filled PAT ATTACHED PAT ATTACHED PAT ATTACHEDTo be filled PAT ATTACHED PAT ATTACHED PAT ATTACHEDTo be filled PAT ATTACHED PAT ATTACHED PAT ATTACHEDTMA Alarm
24 Attach Prediction Plots (Annexure 1) Yes/No N/A
25 Attach Drive Test Plots and Stats - Yes/No YES
26 Attach Walk Test Report for IBS Yes/No N/A ONLY FOR IBS
27 Yes/No N/A
28 Cell Design Data Yes/No YES
29 Drive Test Report (SCFT Checklist Completed) Yes/No YES
30 Parameter discrepancy Audit Report Yes/No AVAILABLE IF REQUIRED
31 Drive Test Log Files Yes/No AVAILABLE IF REQUIRED
32 Passive/Active AT Report Yes/No YES
33 2G>3G Neighbor Definition Audit Report Yes/No N/A
34 Core Side Snapshot for LAC/RAC Definition Yes/No NO
35 Complete BTS Configuration Snapshot Yes/No
36 Yes/No N/A
37 GSM ND report verified for KPIs checks Yes/No YES
Signoff :
Project Manager ( Airtel ) Project Manager (SP)
Date :Mobile Number: Mobile Number:
Telecom Material Check List verified against planned Material (Please attach the List )
GSM Cable Return loss, Cable Loss & VSWR Measurements :
Labelling done for All GSM and TX equipments Installed
For all Cables & Accessories
To be checked on IGB and OGB
To be checked on IGB and OGB
Coverage Certified to be in line with Prediction( Cluster Level)
COCO/IP Information(Ethernet Backhaul) with TXM BW Details
79
Site ID: 1465 Site Name: KIHARA_RED_HILL_ROAD Cell ID: 11465, 21465, 31465
New Site: Site Connected to RNC: yes
Others: Last Drive Performed:
No. Activity/Process MS1 MS2 MS3 Dongle cell 1 cell 2 cell 3 result Remarks
plan Check plan Check plan Check
Idle
1 MNC Y 3 03 03 03 03 03
2 MCC Y 639 639 639 639 639 639
3 LAC Y 70 70 70 70 70 704 RAC Y 245 245 245 245 245 245
5 SDCCH Y6 CCCH Y7 BCCH Y 108 108 121 121 118 118
8 TCH Y9 EDGE Enabeld Y Y Y Y Y Y Y Y Y Y
10 GPRS Y Y Y Y Y Y Y Y Y Y
Voice 11 Voice Call Setup Success rate (MO & MT) Y Y Y y 100 100 100
Nearest point testing
12 Nearest Dst for testing Y Y Y Y 78 63 107
13 RX level at above point Y Y Y Y -68 -64 -70
14 Rx Qual at above point Y Y Y Y -2 -3 -3
Data15 GPRS throughput Y Y Y Y 44 35 47
16 EDGE throguput Y Y Y Y 78.3 Kbps 76.1 Kbps 78.7 Kbps
Handover 17 Handover Function Y Y Y Y Y Y Y
18 Intra site handover Y Y Y Y Y Y Y
19 Inter celll handover Y Y Y Y Y Y Y
20 Latency Y Y Y Y 502 ms 491 ms 556 ms
21 Packet drop Y Y Y Y N N N
Remarks (Comments):
SP Signature Bharti Signature: Date:
drive
map
Rx-level Coverage Map per Sitedr
ive m
ap
C/I PLOT
Idle-ServRxLevIdle (dBm)
Below -105 (0) 0.0%
>= -105 to < -95 (0) 0.0%
>= -95 to < -85 (10) 1.3%
>= -85 to < -75 (66) 8.4%
>= -75 to < -65 (140) 17.9%
Above -65 (567) 72.4%
Idle-ServC2I (N/A)
Below 5.000000 (4) 0.5%
>= 5.000000 to < 8.000000 (15) 2.0%
>= 8.000000 to < 12.000000 (32) 4.2%
>= 12.000000 to < 18.000000 (110) 14.5%
Above 18.000000 (600) 78.8%
drive
map
QUAL PLOT
drive
map
Longcall-ServRxQualSub (RxQual)
Below 4 (521) 87.1%
>= 4 to < 6 (65) 10.9%
>= 6 to < 7 (12) 2.0%
drive
map
BCCH coverage map per sitedr
ive m
ap
Data RLC through put plot
Idle-ServBCCH (ARFCN)
108 (356) 44.7%
118 (68) 8.5%
121 (281) 35.3%
112 (29) 3.6%
124 (62) 7.8%
drive
map
EVENT HANDOVER
Data-RLC_Throughput_DL (kbps)
Below 16.00 (207) 32.2% >= 16.00 to < 32.00 (50) 7.8% >= 32.00 to < 64.00 (72) 11.2% >= 64.00 to < 100.00 (66) 10.3% >= 100.00 to < 150.00 (155) 24.1% Above 150.00 (92) 14.3%
EVENT CELL RESLECTION
Longcall-EventHandoverOK (EVENT)
U 1 (7) 1.1%
2G TO 3G n 3G TO 2G CELL RELECTION
Dual Mode-Uu_CellReselection (EVENT)
U 1 (11) 2.1%
Remarks (Comments): RSCP Coverage check till first handover or coverage dies out (whichever happens earlier)
NSN Signature: Bharti Signature: Date:
Dual Mode-Uu_IRAT_Reselection3G2G (EVENT)
3G-2G Reselection (1) 0.2%
Dual Mode-Uu_IRAT_Reselection2G3G (EVENT)
3G-2G Reselection (2) 0.4%
PRE POSTKPI Type Site Cell 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 29-Nov 30-Nov 1-Dec 2-Dec
TRAFFIC +/- 10% XX xxx
RxQual (0-4)
RxQual DL (0-4) Monitoring
RxQual UL (0-4) Monitoring
SD Blocking
TCH Blocking
TCH Drop
SD Drop
HOSR
Handover Incoming Monitoring
Handover Outgoing Monitoring
TASR
Hard Blocking
Soft Blocking
RASR Monitoring
Data Volume +/- 20%
TBF Drop
Edge Throughput
NSN Signature: Bharti Signature: Date:
POST3-Dec
Event
Blocked Call 0 0.00%
Call Attempt 62 100%
Call Setup 62 100.00%
Dropped Call 0 0.00%
Call Success 62 100%
Voice Call Drop Rate 0 0.00%
Call setup Success Rate 100.00% 100%
1.2 Long Call
Information Element Range % of Meas. Total Samples
Rx Qual sub 0-4 87.1% 521 598
Rx Qual sub 4-6 10.9% 65 598
Rx Qual sub >6 2.0% 12 598
C-I 0-5 0.50% 4 1651C-I 5-8 2.00% 15 1651C-I 8-12 4.20% 32 1651C-I 1218 14.50% 110 1651C-I >18 78.80% 600 1651Handover 7 n/a 7 n/a
Handover Failure 0 n/a 0 n/a
Handover Success 7 n/a 7 n/a
Handover Success Rate 100.00% n/a 100% n/a
2G to 3G Reselection yes n/a n/a n/a
RX Level (Dbm) Sample
0 to -65 567 72.4%
-65 to -75 140 17.9%
-75 to -85 66 8.4%
-85 to -95 10 1.3%
-95 to -105 0 0.0%
<-105 0 0.0%
Rx qual(db) Sample
0-4 521 87.1%
4-6 65 10.9%
6-7 12 2.0%
1.1 Short Call
#[No. of samples]
% Measurement
No. of Samples/Coun
t
1.3 Event Statistic
Percentage (%)
Percentage (%)
EDGE Throughput Sample
<16 252 40.8%
16-32 138 22.3%
32-64 75 12.1%
64-100 47 7.6%
100-150 32 5.2%
>150 74 12.0%
NSN Signature: Bharti Signature: Date:
Percentage (%)
Handover DT Summary
Cell-Log File Count Cell1-4 Cell2-6 Cell3-2
Draw handovers tested:
Sector 1 to 2 Y Y Y
Sector 2 to 3 Y Y Y
Sector 3 to 1 Y Y Y
Sector 1 to 3
Sector 3 to 2 Y Y Y
Sector 2 to 1 Y Y Y
Handover to 1st order Neighbor Y Y Y
HANDOVER to Tier – 1(2G-2G)Neighbor Cells, Voice
Serving Cell ID NCC BCC Remarks
11465 21431 112 2 3 Y ATTEMPT
21431 11465 108 2 0 Y ATTEMPT
11465 21465 118 2 6 Y ATTEMPT
21465 34916 109 0 5 Y ATTEMPT
34916 21465 118 2 6 Y
NSN Signature: Bharti Signature: Date:
Neighbor Cell ID
Neighbor Cell BCCH
Incoming HO 1-Tier
Outgoing HO 1-Tier
The purpose of this test is to verify that each sector is radiating and is able to complete a call
request from a test UE.
Sector ID BCCH
11465 108 22 0 2.7 Pass
21465 121 20 0 2.5 Pass
31465 118 20 0 2.8 Pass
The purpose of this test is to verify that each sector is able to complete
a video call request from a test UE.
Sector ID BCCH Success
11465 108 10 10 100% Pass
21465 121 10 10 100% Pass
31465 118 10 10 100% Pass
The purpose of this test is to verify that a cell is able to complete a PS (Data)
download using R99. This test is carried out on each sector of the site.
Sector ID BCCH File size Latency
11465 108 1 MB 78.3 Kbp/s 10 100% 502 ms
21465 121 1 MB 76.1 Kbp/s 10 100% 491 ms
31465 118 1 MB 78.7 Kbp/s 10 100% 556 ms
NSN Signature: Bharti Signature: Date:
1 Call Setup Testing for Each Sector1) Voice call for each sector
No of calls
Drop Call Rate
Call Setup time
Pass / Fail
2) GPRS for each sector
No of calls
Success rate
Pass / Fail
3) EDGE download for each sector
Mean Throughput
No of Calls
Success rate
The purpose of this test is to verify that each sector is radiating and is able to complete a call
Date:
Panaromic Photos
0° 30°
60° 90°
120° 150°
Panaromic Photos
180° 210°
240° 270°
300° 330°
Sector Photos
Sector1 Sector 2-
Sector 3 Tower Photo
B1 photo B2 photo B3 photo B4 photo
NSN Signature: Bharti Signature:
Bharti Signature: Date: