22 march 2007 slide 1 sub-deduct networks john mcnamara
TRANSCRIPT
22 March 2007 Slide 1
Sub-deduct Networks
John McNamara
Insert strapline22 March 2007 Slide 2
Overview
Characteristics of a Sub-deduct Network Ofgem Concerns - Safety, Charging Regulatory Framework & Internal Legal Advice Independent Legal Counsel Way Forward
Insert strapline22 March 2007 Slide 3
Characteristics of a Sub-deduct Network
History and profile of networks Exemption Regime UNC – Part of system / Exempted Person Competitive Supply Market Ownership and maintenance responsibility ?
Insert strapline22 March 2007 Slide 4
Ofgem Concerns
Safety - Sub-deduct pipe work inferior to DN and IGT pipe work?
Charging – Shippers unable to avoid charges at primary meter.
Insert strapline22 March 2007 Slide 5
Reg Framework & Internal Legal Advice
Gas Act 1986 – Sections 6A and 10(3) The pipeline Safety Regulations 1996 – 3(4) Gas Transporters Licence – SLC 4B, SSC A50 &
A22a UNC – section G 20 Conclusion “none of BG successor entities holds
responsibility for the pipe-lines beyond the emergency control valve”
Insert strapline22 March 2007 Slide 6
Independent Legal Counsel
Blackstone Chambers – Dec 06 “Relevant legislation did not appear inconsistent with
Ofgem conclusion”. “However no sufficient clear stipulation in the
legislation to render the position free from real doubt”
Counsel advice – retrieve sample original agreements to form a more confident view
Insert strapline22 March 2007 Slide 7
Way Forward
Quantify the risk – cross industry dialogue Determine number of sub-deduct networks that
form part of system under UNC Source original documentation Adoption by DNs Change to legislation
Insert strapline22 March 2007 Slide 8
Promoting choice and value for all gas and electricity customers