20239363 build up rate format screeding

2
BUILT-UP RATE FOR SCREEDING TENDER FILE NO : PROJECT : LOCATION : SUPPLIER : SUB-CONTRACTOR : QUOTATION DATE : Material Cost Cement 10.35 per bags 50kg ( Including Rm 0.25 for unloadin Sand (ex-mining) 250.00 per loads ( 14 cu. yard ) or 23.48 per Cement & Sand ( 1:3 ) Mixed Material Cost Cement ( 1440kg/50 ) @ 1 m3 29 bags @ 10.35 300.15 White Lime ( 1 bag / 100 ft2 ) 0 bags @ 0.00 - Sand 3 m3 @ 23.48 70.45 Total cost For 4 m3 370.60 Net volume after shrinkage @ 33 1/3% 2.67 m3 Material cost per m3 138.90 Plant cost ( Concrete mixer @ 3.00/m3 ) 3.00 Total Cost : 141.90 Labour Cost Base screed 3.23 per m2 ( 0.30 per ft2 ) Labour Cost 2.20 per m2 ( 0.20 per ft2 ) Screeding Cost / 20mm thk Material cost 2.84 Wastage @ 5% 0.14 Total material cost / m2 2.98 Labour Cost 2.20 Plant Cost ( Inclusived ) - Tender Cost / m2 5.18

Upload: azaidi88

Post on 26-Oct-2015

10 views

Category:

Documents


1 download

DESCRIPTION

Build-Up-Rate-Format-Screeding

TRANSCRIPT

Page 1: 20239363 Build Up Rate Format Screeding

BUILT-UP RATE FOR SCREEDING

TENDER FILE NO :

PROJECT :

LOCATION :

SUPPLIER :

SUB-CONTRACTOR :

QUOTATION DATE :

Material Cost

Cement 10.35 per bags 50kg ( Including Rm 0.25 for unloading )Sand (ex-mining) 250.00 per loads ( 14 cu. yard ) or 23.48 per m3

Cement & Sand ( 1:3 ) Mixed Material Cost

Cement ( 1440kg/50 ) @ 1 m3 29 bags @ 10.35 300.15 White Lime ( 1 bag / 100 ft2 ) 0 bags @ 0.00 - Sand 3 m3 @ 23.48 70.45 Total cost For 4 m3 370.60

Net volume after shrinkage @ 33 1/3% 2.67 m3

Material cost per m3 138.90 Plant cost ( Concrete mixer @ 3.00/m3 ) 3.00 Total Cost : 141.90

Labour CostBase screed 3.23 per m2 ( 0.30 per ft2 )Labour Cost 2.20 per m2 ( 0.20 per ft2 )

Screeding Cost / m2

20mm thk Material cost 2.84 Wastage @ 5% 0.14 Total material cost / m2 2.98 Labour Cost 2.20 Plant Cost ( Inclusived ) - Tender Cost / m2 5.18

Page 2: 20239363 Build Up Rate Format Screeding

per m3

Cost / m2 25mm thk

3.55 0.18 3.72 2.20 - 5.92