20239363 build up rate format screeding
DESCRIPTION
Build-Up-Rate-Format-ScreedingTRANSCRIPT
BUILT-UP RATE FOR SCREEDING
TENDER FILE NO :
PROJECT :
LOCATION :
SUPPLIER :
SUB-CONTRACTOR :
QUOTATION DATE :
Material Cost
Cement 10.35 per bags 50kg ( Including Rm 0.25 for unloading )Sand (ex-mining) 250.00 per loads ( 14 cu. yard ) or 23.48 per m3
Cement & Sand ( 1:3 ) Mixed Material Cost
Cement ( 1440kg/50 ) @ 1 m3 29 bags @ 10.35 300.15 White Lime ( 1 bag / 100 ft2 ) 0 bags @ 0.00 - Sand 3 m3 @ 23.48 70.45 Total cost For 4 m3 370.60
Net volume after shrinkage @ 33 1/3% 2.67 m3
Material cost per m3 138.90 Plant cost ( Concrete mixer @ 3.00/m3 ) 3.00 Total Cost : 141.90
Labour CostBase screed 3.23 per m2 ( 0.30 per ft2 )Labour Cost 2.20 per m2 ( 0.20 per ft2 )
Screeding Cost / m2
20mm thk Material cost 2.84 Wastage @ 5% 0.14 Total material cost / m2 2.98 Labour Cost 2.20 Plant Cost ( Inclusived ) - Tender Cost / m2 5.18
per m3
Cost / m2 25mm thk
3.55 0.18 3.72 2.20 - 5.92