2019 q3 darlington refurbishment report - home | opg · balance of plant work is a “very diverse...

4
Q3 2018 A REPORT ON CANADA’S LARGEST CLEAN ENERGY PROJECT DARLINGTON REFURBISHMENT Workers inspecting fuel channels at Pickering Nuclear, prior to transferring the components to Darlington Nuclear for installation.

Upload: others

Post on 05-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2019 Q3 Darlington Refurbishment Report - Home | OPG · Balance of plant work is a “very diverse portfolio,” said Project Director Pejman Asgaripour. It includes steam generator

Q3 2018

A REPORT ON CANADA’S LARGEST CLEAN ENERGY PROJECT

DARLINGTON REFURBISHMENT

WWW.OPG.COM @opgpics@opg Ontario Power Generation

A WOMAN IN TRADES

Statistics show that as few as five per cent of Ontario tradespeople are female. That

number was even smaller when Christy DeCarlo began her pipefitter apprenticeship:

she was the only woman in a group of 75.

“It was challenging at times back then, but I developed broader shoulders and

thicker skin,” says DeCarlo, now a Quality Control Inspector and Level Two Welding

Inspector on Darlington Refurbishment. “There were times early on when I really

thought I’d pack it in, but I decided I wasn’t going to let someone else’s behaviour

change the course of my life.”

A pipefitter by trade since 2010, DeCarlo’s previous career path as hospital unit clerk

helped shape a safety mindset that she demonstrates both on and off the job. She

recently noticed a potential risk of falling by workers, outside her apartment building.

“There was a group working on an elevated work platform — they weren’t tied off

and were climbing on the rails,” she recalls.

So, DeCarlo went to her apartment’s management office, and vocalized the risk

management was taking on by allowing contractors to work in an unsafe manner.

“Management stopped the job,” DeCarlo says, noting her rationale for speaking up was simple: “I couldn’t live with

myself if something happened.”

DeCarlo moved out of hospital work, completing an apprenticeship in western Canada, through the Southern Alberta

Institute of Technology. Before joining Darlington Refurbishment in February 2017, DeCarlo had been working as a

commissioning pipefitter at a potash mine in Saskatchewan.

“If you are curious and have some mechanical aptitude, enquire with your local trade unions — don’t let your gender hold

you back,” she says. “Go for it!”

Ontario Power Generation (OPG) produces almost half the electricity that Ontario homes, schools, hospitals and businesses rely on each day. After decades of reliable power generation, OPG’s Darlington Nuclear Generating Station is receiving a mid-life refurbishment that will benefit Ontarians for another 30 years.

To learn more about Darlington Refurbishment, the largest clean energy project in Canada, visit our website at www.opg.com and subscribe to the Darlington Refurbishment Newsletter.

Have questions? Contact us at [email protected].

To help build Ontario’s

skilled trades capacity,

OPG recently held our

second annual Darlington

Refurbishment Student Day

when students from local

high schools were invited

for a chance to learn about

the various skilled trades

opportunities available in

the nuclear industry.

OPG President and CEO Jeff Lyash and Ontario

Minister of Energy Greg Rickford on the viewing

platform in front of the full-scale reactor replica

at the Mock-up and Training Facility at Darlington

Energy Complex, Oct. 2018.

Workers inspecting fuel channels at Pickering Nuclear, prior to

transferring the components to Darlington Nuclear for installation.

Page 2: 2019 Q3 Darlington Refurbishment Report - Home | OPG · Balance of plant work is a “very diverse portfolio,” said Project Director Pejman Asgaripour. It includes steam generator

Q3 2018

A REPORT ON CANADA’S LARGEST CLEAN ENERGY PROJECT

DARLINGTON REFURBISHMENT

WWW.OPG.COM @opgpics@opg Ontario Power Generation

A WOMAN IN TRADES

Statistics show that as few as five per cent of Ontario tradespeople are female. That

number was even smaller when Christy DeCarlo began her pipefitter apprenticeship:

she was the only woman in a group of 75.

“It was challenging at times back then, but I developed broader shoulders and

thicker skin,” says DeCarlo, now a Quality Control Inspector and Level Two Welding

Inspector on Darlington Refurbishment. “There were times early on when I really

thought I’d pack it in, but I decided I wasn’t going to let someone else’s behaviour

change the course of my life.”

A pipefitter by trade since 2010, DeCarlo’s previous career path as hospital unit clerk

helped shape a safety mindset that she demonstrates both on and off the job. She

recently noticed a potential risk of falling by workers, outside her apartment building.

“There was a group working on an elevated work platform — they weren’t tied off

and were climbing on the rails,” she recalls.

So, DeCarlo went to her apartment’s management office, and vocalized the risk

management was taking on by allowing contractors to work in an unsafe manner.

“Management stopped the job,” DeCarlo says, noting her rationale for speaking up was simple: “I couldn’t live with

myself if something happened.”

DeCarlo moved out of hospital work, completing an apprenticeship in western Canada, through the Southern Alberta

Institute of Technology. Before joining Darlington Refurbishment in February 2017, DeCarlo had been working as a

commissioning pipefitter at a potash mine in Saskatchewan.

“If you are curious and have some mechanical aptitude, enquire with your local trade unions — don’t let your gender hold

you back,” she says. “Go for it!”

Ontario Power Generation (OPG) produces almost half the electricity that Ontario homes, schools, hospitals and businesses rely on each day. After decades of reliable power generation, OPG’s Darlington Nuclear Generating Station is receiving a mid-life refurbishment that will benefit Ontarians for another 30 years.

To learn more about Darlington Refurbishment, the largest clean energy project in Canada, visit our website at www.opg.com and subscribe to the Darlington Refurbishment Newsletter.

Have questions? Contact us at [email protected].

To help build Ontario’s

skilled trades capacity,

OPG recently held our

second annual Darlington

Refurbishment Student Day

when students from local

high schools were invited

for a chance to learn about

the various skilled trades

opportunities available in

the nuclear industry.

OPG President and CEO Jeff Lyash and Ontario

Minister of Energy Greg Rickford on the viewing

platform in front of the full-scale reactor replica

at the Mock-up and Training Facility at Darlington

Energy Complex, Oct. 2018.

Workers inspecting fuel channels at Pickering Nuclear, prior to

transferring the components to Darlington Nuclear for installation.

Page 3: 2019 Q3 Darlington Refurbishment Report - Home | OPG · Balance of plant work is a “very diverse portfolio,” said Project Director Pejman Asgaripour. It includes steam generator

180

160

140

120

100

80

60

40

20

0

DAYS

—-—-—-—-—-—-

-—-

-—-—-—-—-

—-—-

-—-—-

—-—-—-—-—-—-—-—-

-—-

-—-—-—-—-—-—-—-

-—-—-—-

-—-—-—-—-—-

Removeend fittings Remove

pressure tubes

Remove calandria tubes-

—-—- -

—-—-—-—-—-—-

—-—-

-—-

Segment 2B: Remove reactor components

Segment 2B Dec 17 Start

In addition to work underway on the Unit 2 reactor,

other work taking place during Refurbishment will help

ensure Darlington’s long-term safety, reliability and

asset preservation.

Balance of plant work is a “very diverse portfolio,” said

Project Director Pejman Asgaripour. It includes steam

generator maintenance and modification.

“The stream generator is the only life-limiting component

not being replaced during Refurbishment,” Asgaripour

said, noting the other two, pressure tubes and feeders, are

being replaced. “The work we are doing now will ensure

our steam generators are reliable and fit for service for

the second life of Darlington.”

While other nuclear refurbishments have included steam

generator replacement, it was deemed unnecessary

at Darlington, provided a series of maintenance and

modifications scope, which were carried out to enhance

inspection capability and proactively deal with any

plausible equipment risks.

This series of work included cleaning all 16,000 tubes of

the station’s four steam generators.

Project manager Jos Diening likens the need for cleaning

to that of a household kettle — after it’s been in use

for boiling water for a while, some build-up of minerals

develops inside.

“The same thing happens in the steam generators, with

magnetite,” Diening said. “It’s critical that we clean them

out to provide efficient heat transfer.”

Teamwork between project partners BWXT, CANDU

Energy and OPG, including outstanding communication,

led to the successful, on-time cleaning of all of the unit’s

steam generator tubes.

“The biggest factor in the success of this project is

summarized in two words: integration and collaboration,”

said Pedro Fleites, BWXT’s site manager.

Removed magnetite will now be shipped to Western

Waste Management Facility, where it will be safely stored.

“The steam generators will be much more efficient, so we

can generate more energy,” Diening said.

THE UNIT 2 DARLINGTON REFURBISHMENT SCHEDULE

Oct 15, 2016Breaker Open

Shut down reactor

Defuel reactor

Install barriers to isolate Unit 2 from station Containment

pressure test

Segment 1: Defuel reactor and isolate from the station

Open airlocks and install shielding

Remove interferences and install work platform

Sever pressure tubes and bellows

Segment 2A: Prepare for reactor component removal

Remove feeder tubes

Inspect and install calandria tubes

Inspect and install fuel channels (pressure tubes, bellows and end-fittings)

Install feeder tubes

Segment 3: Install reactor components

Progress as at Sept 30, 2018

Segment 3 May 3, 2018

Project Complete Feburary 27, 2020

Load fuel and remove equipment

Heat up and low power testing

High power tests and connection to the grid

Segment 4: Load fuel, test and restart reactor

Segment 4 Aug 7 2019 Start

180

160

140

120

100

80

60

40

20

0

DAYS

While work is underway on the Unit 2 reactor, the Darlington Refurbishment team has been focused on preparing for Unit

3 refurbishment, scheduled to start by February 2020.

Lessons learned from the detailed planning, preparation and execution on the first reactor are fully being incorporated

into our Unit 3 Refurbishment plans.

Those plans include the recent completion of a Full Scope Maintenance Simulator, which will validate work before it is

carried out on the actual reactor unit, and the construction of the project’s second Refurbishment Control Centre where

the team will remotely oversee the removal and installation of components inside Unit 3.

“We’ve been able to look farther ahead because of lessons learned on Unit 2 refurbishment,” said Paul Ross, Project

Director of Refurbishment Execution. “Orders have already been placed for materials and we’ve started staffing up in

key areas.”

The Unit 3 refurbishment team has also been putting innovative technology, such as virtual reality, to use.

“By using virtual reality, we can artificially map out an area inside the reactor and plan the space and location of

components, equipment and people before actually stepping into the space,” says Ross. “This helps us validate logistics

in advance, thereby, saving time and effort.”

Two years have now passed since Ontario Power Generation

and our project partners started Darlington Refurbishment — a

10-year project that began with successfully shutting down Unit

2, the first of our four nuclear reactors at Darlington Nuclear

Generating Station to undergo a mid-life refurbishment. Today,

with just over a year to go before we start work on Unit 3,

Darlington Refurbishment remains on time and on budget,

with more than 11 million hours worked safely since the start

of the project.

During the third quarter of 2018, the project team started

carrying out the complex task of rebuilding the reactor. In

June, we began installing 480 calandria tubes, the last of

which has now been inserted. At the same time, we made

significant progress overhauling the Unit 2 turbine generator,

and completed maintenance and modifications on our steam

generators and fuelling machines.

As well, we made significant headway on plans and

preparations for Unit 3 refurbishment, which is scheduled for

no later than February 2020. In addition to installing a Full

Scope Maintenance Simulator that will be used for training,

we constructed a second Refurbishment Control Centre to

facilitate the team’s remote oversight and performance of

work on the unit.

In this report, you’ll learn more about the status of Darlington

Refurbishment during OPG’s third quarter, and the innovation,

technology and highly skilled people who are driving it.

Dietmar Reiner,Senior Vice President, Nuclear Projects

MEETING OUR COMMITMENTS

PROJECT PILLAR PERFORMANCEOPG’s project pillars measure the organization’s

success in maintaining high standards in worker

safety, quality of work, and ability to adhere to

schedule and overall project cost. Here is an

overview of our project pillar performance during

the third quarter of the year (July 1 — September

30, 2018).

SCHEDULEUnit 2 remains on schedule.

COSTUnit 2 refurbishment costs are $27 million

below plan. The life-to-date cost for Unit 2

and the forecasted completion of the overall

project remains on budget.

SAFETYOne minor medically treated injury occurred in

the third quarter. There have been no lost time

injuries and more than 11 million hours worked

safely since the start of the project.

QUALITYNo Quality-related events resulting in loss of

generation or impacts to the schedule.

ENVIRONMENTEnvironmental performance has been good

with no reportable spills or infractions in Q3.

Emissions are well below all regulatory limits.

Magnetite is a rock mineral that builds up inside

the generators’ tubes after years of use, similar

to the way limescale lines the inside of a kettle

over time.

Through a process that involved shooting high

pressure water through the steam generator

tubes, the Darlington Refurbishment team

removed 250 grams of magnetite from each of

the 16,000 steam generator tubes, totaling more

than 5,000 kilograms of magnetite!

GEARING UP FOR UNIT 3 REFURBISHMENT

ENSURING THE LONG-TERM SAFETY AND RELIABILITY OF THE STATION

Full Scope Maintenance Simulator,

Darlington Maintenance and Computer

Development Facility, 2018.

Page 4: 2019 Q3 Darlington Refurbishment Report - Home | OPG · Balance of plant work is a “very diverse portfolio,” said Project Director Pejman Asgaripour. It includes steam generator

Q3 2018

A REPORT ON CANADA’S LARGEST CLEAN ENERGY PROJECT

DARLINGTON REFURBISHMENT

WWW.OPG.COM @opgpics@opg Ontario Power Generation

A WOMAN IN TRADES

Statistics show that as few as five per cent of Ontario tradespeople are female. That

number was even smaller when Christy DeCarlo began her pipefitter apprenticeship:

she was the only woman in a group of 75.

“It was challenging at times back then, but I developed broader shoulders and

thicker skin,” says DeCarlo, now a Quality Control Inspector and Level Two Welding

Inspector on Darlington Refurbishment. “There were times early on when I really

thought I’d pack it in, but I decided I wasn’t going to let someone else’s behaviour

change the course of my life.”

A pipefitter by trade since 2010, DeCarlo’s previous career path as hospital unit clerk

helped shape a safety mindset that she demonstrates both on and off the job. She

recently noticed a potential risk of falling by workers, outside her apartment building.

“There was a group working on an elevated work platform — they weren’t tied off

and were climbing on the rails,” she recalls.

So, DeCarlo went to her apartment’s management office, and vocalized the risk

management was taking on by allowing contractors to work in an unsafe manner.

“Management stopped the job,” DeCarlo says, noting her rationale for speaking up was simple: “I couldn’t live with

myself if something happened.”

DeCarlo moved out of hospital work, completing an apprenticeship in western Canada, through the Southern Alberta

Institute of Technology. Before joining Darlington Refurbishment in February 2017, DeCarlo had been working as a

commissioning pipefitter at a potash mine in Saskatchewan.

“If you are curious and have some mechanical aptitude, enquire with your local trade unions — don’t let your gender hold

you back,” she says. “Go for it!”

Ontario Power Generation (OPG) produces almost half the electricity that Ontario homes, schools, hospitals and businesses rely on each day. After decades of reliable power generation, OPG’s Darlington Nuclear Generating Station is receiving a mid-life refurbishment that will benefit Ontarians for another 30 years.

To learn more about Darlington Refurbishment, the largest clean energy project in Canada, visit our website at www.opg.com and subscribe to the Darlington Refurbishment Newsletter.

Have questions? Contact us at [email protected].

To help build Ontario’s

skilled trades capacity,

OPG recently held our

second annual Darlington

Refurbishment Student Day

when students from local

high schools were invited

for a chance to learn about

the various skilled trades

opportunities available in

the nuclear industry.

OPG President and CEO Jeff Lyash and Ontario

Minister of Energy Greg Rickford on the viewing

platform in front of the full-scale reactor replica

at the Mock-up and Training Facility at Darlington

Energy Complex, Oct. 2018.

Workers inspecting fuel channels at Pickering Nuclear, prior to

transferring the components to Darlington Nuclear for installation.