2019 industry reference document (32) of (32) project

14
2020 NEI Report of Project Management Lessons Learned and Best Practices Construction of New Nuclear Power (NNP) Plants 32 Public Domain Reference Documents High Bridge Associates, Inc. www.hba‐inc.com 2019 Industry Reference Document (32) of (32) Project Management Lessons Learned & Keys to Success 13 pages Kenneth Aupperle, Senior Vice President High Bridge Associates, Inc.

Upload: others

Post on 22-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

2020 NEI Report of Project Management Lessons Learned and Best Practices Construction of New Nuclear Power (NNP) Plants 

32 Public Domain Reference Documents  

High Bridge Associates, Inc.    www.hba‐inc.com  

              

2019 Industry Reference Document (32) of (32) 

Project Management Lessons Learned & Keys to Success 13 pages 

   

Kenneth Aupperle, Senior Vice President High Bridge Associates, Inc. 

 

1

1

“Connecting Vision and Plans with Performance and Execution”

Kuwait City, Kuwait: April 2011International Atomic Energy Agency Workshop

Nuclear Power Project Management

Washington, DC: November 2009American Nuclear Society, Winter MeetingNuclear Project Management Insights and Challenges

Cairo, Egypt: November 2012International Atomic Energy Agency WorkshopProject Management for Nuclear Construction

Stockholm, Sweden: November 2014Nordic  Nuclear SymposiumIntegration and Project Management Lessons learned

Washington, DC: November 2007American Nuclear Society, Winter Meeting

Industry Lessons Learned & Key Success Factors

Cadarache, France: July 2013ITER International Fusion Project

Nuclear Industry Project Management Lessons Learned

Confidential Client: October 2016Planning and Integration Workshop

Nuclear Industry Project Management Lessons Learned

NC State University: November 2017Graduate Construction Management ProgramProject Management Lessons Learned Workshop

Nuclear Energy Institute (NEI): December 2019NEI Industry Report

Project Management Lessons Learned & Best Practices

High Bridge Update for Industry: December 2019Various Industry StakeholdersProject Management Lessons Learned & Insights

2

11. Utility owner‐led & aggressive risk identification, integration, & opportunity management

12. Pre‐assembly/modularization techniques coupled with over the top construction

13. Simplified and timely project performance reporting

14. Rigorous configuration management & change control

15. Management of internal & external stakeholders

 5.  Best athelete for the job approach (individual/corporate) & clear definition of project roles

 6.  Collaborative "win‐win" contracting strategy instead of confrontational "win‐lose" approach

 7.  Teamwork, open communications, no surprises, & "sink or swim together" culture

 8.  Completed detailed design incorporating vendor submittal details before construction start

 9.  Ingrained nuclear construction, quality, & safety culture & training

10. Understanding first of a kind (FOAK) & design maturity status realities

 1.  Utility owner‐led integrated project team organization approach

 2.  Passionate leadership & extreme ownership from the top

 3.  Intense up‐front planning & integrated project schedule controlled by owner

 4.  Realistic & integrated performance baselines for scope, cost, schedule, & risk

1

2

2

High Bridge is a planning & project management company that:◦ Serves utility owners, EPC firms, & original equipment manufacturers

◦ Has extensive experience supporting NNP & other large FOAK projects

◦ Has studied project management lessons learned & best practices for over 25 years

High Bridge Senior Vice President Ken Aupperle:◦ Leads our planning & lessons learned consulting practice since 1994

◦ Has compiled >150 industry publications regarding lessons & keys to success

◦ Has presented lessons learned papers at >20 domestic & international forums

High Bridge assembled a team in 2019 to update its lessons learned & best practices based on 32 publications spanning > 40 years & case studies for 10 successful projects:◦ It prepared a lessons learned & best practices report for the NEI in 4Q19

◦ It updated its data base & prepared this overview of project management lessons learned & insights for NNP & Mega‐Project Construction

3

4

Those who cannot remember the past are 

condemned to repeat it….George Santayana 

It’s a form of insanity to repeat the same steps over & over and to expect a different result….

Albert Einstein

3

4

3

Project management has received much attention recently ◦ Why are  projects plagued with schedule delays, cost overruns, & quality issues

◦ How does this occur with abundant industry guidance & digital tools available

Key insights & conclusions◦ A nuclear project involves many technical, economic, & cultural challenges

◦ Project organization & first of a kind issues are more challenging than technology & science issues

◦ Project management involves art & leadership along with science & systems

Critical decision‐making information is often lost due to overwhelming data

◦ Risk & opportunity management instead of risk shedding

◦ Various parameters can create “blind spots” in the planning & knowledge management process that result in obstacles for applying lessons learned & best practices for the organization & execution of FOAK NNP construction projects

Owner‐led integrated project teams (IPT), best athlete for the job, open communications, teamwork, simplified management systems, ingrained nuclear culture, training, & passionate leadership are essential◦ The US nuclear industry has many past projects, accomplishments, & public domain information 

to learn from to plan a project foundation for success

5

6

# 223 48 175 46 129 33 98%  100% 22% 78% 21% 58% 15% 44%

US Commercial Nuclear Industry Accomplishments ‐ 1960's to 1990's

Past Lessons & Practices Must Be Applied for Future Success

Projects StartedOver 25Years

Projects CancelledPrior To

Construction

PlantsThat

StartedConstruction

PlantsCancelled During

Construction

Plants Completed & Operation 

Started

Plants Still 

Operating

Plants De‐Commissioned

or Shut Down

Num

ber o

f  Nuclear Pow

er Units      

200

150

100

50

1980's....Over 70 Nuclear Plants in Various Stages of Construction

Onging at the Same TimeThroughout the United States!

5

6

4

7

Since the 1970's,Our Industry Data & Experience Spans >150 Industry White Papers & >100 Nuclear Projects

Based on 32 industry documents/reports &10 successful project Case Studies

we have distilled 1,000's of issues & parameters 

into what we conclude are the “Top 15 Elements” for building a foundation for success based on

89 lessons learned & 59 best practiceswe identified.

8

Year

Report

Published

Report

Reference

Number

Industry

Publishing

Organization

Industry Report/Paper/Presentation Description Pages

1978 1 Owners, EPC Firms, & AFL‐CIO Nuclear Power Construction Stabilization Agreement (NPCSA) 11

1983 2 FP&L/PMI Conference St. Lucie #2 ‐ A Nuclear Plant Built on Schedule, W. Derrickson 54

1984 3 Ebasco/ASCE Conference St. Lucie 2 ‐ Doing It Right In Nuclear Construction, L. Tsakiris 18

1984 4 NRC NUREG 1055 Improving Design and Construction of Nuclear Power Plants 174

1987 5 IAEA ‐ Vienna Achievements in Construction and Best Practices 4961988 6 Rand Corporation Understanding the Outcomes of Mega Projects 104

1990 7 DOE Duke Improving Nuclear Construction Performance 308

1990 8 DOE Duke Enhancing Nuclear Construction through Design 378

1999 9 National Academy of Science Report to Congress, Improving Project Management in the DOE 149

2007 10 ANS ‐ High Bridge and  Burns & Roe Nuclear Industry Construction Lessons Learned 5

2007 11 Nuclear News Ft. Calhoun's Big Steam Generator Refurbishment Outage 5

2009 12 URENCO LES Lessons Learned ‐ Construction of the National Enrichment Facility in NM 16

2009 13 TetraTech, Inc. New Nuclear Plants  Need To Adopt the Outage Management Mentality 8

2010 14 Nuclear Energy Institute (NEI) Lessons Learned from Nuclear Construction 24

2010 15 UK Royal Academy of Engineering Nuclear Lessons Learned on Various Projects 80

2010 16 STUK Finland Regulator Experiences from construction of Olkiluoto 3 plant in Finland 36

1 to 16 Sub Total Total 1,866

Learning Legacies & Insights Spanning 40 Years & 32 Reference Documents

Basis for Evaluation of Key Issues for Success

Go to High Bridge Website at hba‐inc.com to download copies of these documents

7

8

5

9

Year

Report

Published

Report

Reference

Number

Industry

Publishing

Organization

Industry Report/Paper/Presentation Description Pages

2010 17 High Bridge Associates Compilation of Partnering and Integrated Project Team White Papers 136

2012 18 UK Royal Academy of Engineering Nuclear Construction Lessons Learned 23

2012 19 Price Waterhouse Cooper Third Global Survey of Project Management Trends and Practices 40

2013 20 Olympics Delivery Authority London 2012 Olympics, Project Controls Lessons Learned 27

2013 21 High Bridge Associates Alternating 4/10's ‐ Accelerated Schedules & Reduced Costs 14

2016 22 Electricity Journal SMR Deployment and Learning from the Past 8

2017 23 World Nuclear Association Lesson ‐ learning in Nuclear Construction Projects 24

2017 24 High Bridge Associates Construction Productivity Impacts due to Extended Weeks & Shift Work 85

2017 25 Jocko Willink & Leif Babin Extreme Ownership ‐ How US Navy Seals Lead and Win (Summary) 25

2018 26 Energy Technologies Institute ‐ UK Nuclear Cost Drivers Summary Report 55

2018 27 Nuclear Energy Institute (NEI) Assessment of Part 52 Licensing Impacts on Construction 9

2018 28 Massachusetts Institute of Technology The Future of Nuclear Energy in a Carbon Constrained World 275

2018 29 NIC/Texas A&M ‐ High Bridge Assoc. Integrated Project Teams and Leadership for Advanced Reactor Projects 11

2019 30 EPRI ‐ Dominion Economic Roadmap for Nuclear Power Plant Construction 242

2019 31 David B. Amerine Push It to Move It ‐ Lessons Learned in Nuclear Project Management 250

2019 32 High Bridge Associates Nuclear Project Management. Lessons Learned and Keys to Success 13

Documents 17 to 32 Sub Total 1,237

Documents 1 t0 16 Sub Total 1,866

Documents 1 to 32 Total 3,103

Learning Legacies & Insights Spanning 40 Years & 32 Reference Documents

Basis for Evaluation of Key Issues for Success

Go to High Bridge Website at hba‐inc.com to download copies of these documents

River Bend Nuclear Power Station Unit 1 St. Lucie Nuclear Power Station Unit 2  Palo Verde Nuclear Power Station Units 1, 2, and 3 Watts Bar Nuclear Power Station Unit 2 Rocky Flats Decontamination & Decommissioning Project Selected Steam Generator Replacement & Refurbishment Projects Spallation Neutron Source (SNS) Accelerator Project 2012 London Olympics Site and Facilities Infrastructure  WPPSS 2 Washington Public Power Supply System Nuclear Unit 2 Barakah Nuclear Power Station Units 1 to 4 (United Arab Emirates)

Go to High Bridge Website at hba‐inc.com to download copies of these documents

10

9

10

6

A. Project Organization, Owner Led Integrated Team, and Best Athlete Approach◦ Extreme Ownership and Leadership from the Top◦ Organizational Challenges are Tougher than Technical Issues◦ Collaborative Win/Win instead of Confrontational Win/Lose Contracting Strategies◦ Aggressive Risk and Opportunity Management instead of Risk Shedding Approach◦ Ingrained Large Nuclear Construction, Quality, and Safety Culture and Mentality

B. First of a Kind (FOAK) Project Parameters and Challenges◦ Recognizing what FOAK Is◦ Experience of Stakeholders◦ Design Maturity and Details Required for Construction◦ Realistic Cost and Schedule Baselines

C. Project Management Involves Art and Science◦ Integrated Project Schedule, Owner Control, and Simplified Reporting System◦ Rigorous Configuration Management and Design Change Control◦ Labor Efficiency, Extended Workweeks, Shiftwork, and Fatigue◦ Modularization Potential Benefits and Drawbacks◦ Managing Project Internal and External Stakeholders

11

12

Lessons 

Learned29

Lessons 

Learned25

Lessons 

Learned35

Lessons 

Learned89

Best 

Practices20

Best 

Practices18

Best 

Practices21

Best 

Practices59

Total 49 Total 43 Total 56 Total 148

A.

Project Organization, 

Owner Led Integrated 

Team, and Best 

Athlete Approach

B.

First of a Kind (FOAK) 

Project Parameters 

and Challenges

C.

Project Management 

Involves Art 

and Science

Total

Go to High Bridge Website at hba‐inc.com to download a compiled list of theseLessons Learned & Best Practices

11

12

7

13

11. Utility owner‐led & aggressive risk identification, integration, & opportunity management

12. Pre‐assembly/modularization techniques coupled with over the top construction

13. Simplified and timely project performance reporting

14. Rigorous configuration management & change control

15. Management of internal & external stakeholders

 5.  Best athelete for the job approach (individual/corporate) & clear definition of project roles

 6.  Collaborative "win‐win" contracting strategy instead of confrontational "win‐lose" approach

 7.  Teamwork, open communications, no surprises, & "sink or swim together" culture

 8.  Completed detailed design incorporating vendor submittal details before construction start

 9.  Ingrained nuclear construction, quality, & safety culture & training

10. Understanding first of a kind (FOAK) & design maturity status realities

 1.  Utility owner‐led integrated project team organization approach

 2.  Passionate leadership & extreme ownership from the top

 3.  Intense up‐front planning & integrated project schedule controlled by owner

 4.  Realistic & integrated performance baselines for scope, cost, schedule, & risk

We reviewed public domain information & past successful & troubled projects to:

o Determine what strategic project management practices made a difference for 

successful planning, organizing & execution of the projects.

We concluded that industry stakeholder recognition & understanding of lessons learned & best practices can be inhibited & adversely impacted due to various & not so obvious reasons

These included the following parameters that can create “Blind Spots” in the planning & knowledge management process:◦ Inadequate experience with nuclear industry large FOAK projects◦ Conservative owner corporate cultures vs. aggressive project mindsets◦ Human emotions, personalities, & leadership◦ Strategic long‐term vs. tactical short‐term considerations

14

Go to High Bridge Website at hba‐inc.com to download a narrative discussion of these planning Blind Spots

13

14

8

These blind spots & obstacles have resulted in utility owners & contractors adopting practices that:◦ Inhibited teamwork, dissuaded open communications, & clouded 

transparency, resulting in negative cost/schedule performance Dealing with these blind spots & cultures requires a good leader & 

not just a good manager:◦ Managing how things are done in the short term (doing things right) is 

generally easier than facilitating strategic corporate policies for what should be done (doing the right things) in the long term

◦ A grasp of the big picture is needed to see through blind spots & facilitate actions for what is needed for project success in a dynamic environment amid constantly changing priorities & often self‐serving stakeholder cultures

15

16

Managing Mega‐Construction ProjectsRecognize Art & Science ‐ Focus on the Basics

,TOOLSSoftware,

Technology

,PROCESSESMethodology,

& Organization,PEOPLERoles & Responsibilities,

..... FrameworkSystematic &

Structured

..... FoundationLeadership,

Planning, &Integration

..... FacilitatorsInformation &

Routines

Priorities & Key Elements

Science

Art

A great organization will overcome imperfect management processes & tools to succeed!!!

15

16

9

The “Triangle” of focus and priorities is “Upside Down”

Tools & technology have gotten too sophisticated, powerful, flexible, & complex◦ Nuclear outage mentality tends to drive to more detail

◦ Capability & flexibility of software gets abused

◦ Data overwhelms ability to focus on critical information

◦ Digital capabilities have created a sterile/impersonal process

◦ Increased data/automation has decreased stakeholder accountability

◦ Management system reporting/maintenance is enormous

17

Beware of Bits & Bytes….B³

1960 1970 1980 1990 2000 2010

18

CS² ‐ Cost Schedule

Control System

EVMS ‐ Earned Value

Management System

Kilobytes       Megabytes        Gigabytes       Terabytes     ???

More Details = More Maintenance & Less AccountabilityInformation Overload  =  Confusion & Excuses

Beware of Bits and Bytes = B3

PMS ‐ Performance 

Measurement System

17

18

10

W. Edward Demming:◦ Just because you can measure everything doesn’t mean you should

Albert Einstein:◦ Everything should be made as simple as possible

Benjamin Franklin:◦ Time Is Money

Leonardo Di Vinci:◦ Simplicity is the ultimate sophistication

Kelly Johnson: ◦ Lockheed Lead Design Engineer for U‐2, SR‐71 Blackbird, & other airplanes

◦ Design jet aircraft simply so they can be maintained by an average mechanic

Design with simplicity and avoid complexity:◦ Digital computer era allows complexity to flourish….B3

◦ Provide required details but be cautious & maintain balance with simplicity

19

20

Consider more target schedule incentive milestones that offer win‐win solutions & outcomes◦ Firm fixed price contracts often create conditions adverse to goals

◦ Establish collaborative “win‐win” contracting strategies vs. confrontational win‐lose strategies

◦ Rally limited resources around near term & meaningful goals

◦ Spend money on incentives that foster team spirit/cooperation

Project “teamwork” is inversely proportional to the thickness of contract terms & conditions◦ Communications, coordination, cooperation, & priorities

◦ Open exchange/no surprises vs. guarded/closed information

◦ Management & production focus vs. contracts & legal jousting

◦ Sink or swim together vs. blaming the other party

19

20

11

21

Design Maturity & Fixed Price ContractingUnderstand Construction Contractor Interfaces

22

4.8 billion £ ‐ 20 Year Project

Site 260 hectares

Main building 396m x 176 m x 40 m

Largest free‐standing structure in UK

1993 Formal planning application 

2001 Formal government approval

2002 Start civil construction

2008 Construction complete

Willie Walsh, British Airways President and CEO

Integrated Project Team Approach – Contractors focus on what they do well, work together to solve technical problems, & no surprises

Fair Profits ‐ Don’t spend money/time/resources on legal jousting

21

22

12

23

Detailed “done‐done” design before starting construction Understand regulatory/quality/safety needs to ingrain nuclear mentality Nuclear regulator will hold owner/licensee accountable….not contractors

◦ Most risks cannot be shed….they must be managed Develop hybrid contracting strategies that provide win‐win solutions Implement rigorous configuration management & design change control Planning, transparent information, teamwork, & no surprises 

◦ Keep It Simple & Less Is More….Beware of Bits & Bites◦ Project teamwork is inversely proportional to thickness of contracts

Organization/people challenges are tougher than technical/science issues◦ NRC NUREG 1055 (1986) & NAS DOE Report to Congress (1999)◦ Adopt owner‐led Integrated Project Team (IPT) organization approach

A Multi‐Year/$Billion Nuclear Project is like a military campaign◦ An experienced, motivating & passionate Project Leader  is critical◦ Extreme Ownership & Leadership from the top is essential!!!

24

23

24

13

25

48 Years of Experience in Commercial Nuclear/Fossil Power & Government DOE Sectors Spanning Science, Defense, & EM Programs (Inactive Q Clearance)◦ 1994 to present with High Bridge/Team Associates – Project Management Consulting firm ◦ 1971 to 1994 with Stone & Webster ‐ EPC firm ◦ Various assignments spanning strategic planning, project management, earned value,

construction, risk management, cost estimating, scheduling, & process improvement◦ Numerous leadership roles on major nuclear power & DOE defense/science/HLW  projects

Senior Vice President with High Bridge/Team Associates◦ Leading nuclear supplier of planning & project management consulting & staffing services◦ Supporting utility owners, DOE/O&M’s, engineer/constructors, & equipment manufacturers

High Bridge Practice Lead (1994 to Present)◦ Independent cost, schedule, & risk assessments for >100 projects valued at >$300 billion◦ Nuclear industry project management lessons learned & best practices, cost/schedule data base, &  analysis of industry risk issues

Project Manager & lead author for preparation of 2019 NEI Report◦ Supporting utility owners “New Nuclear” planning, organizing, & project deployment programs spanning 

various OEM/EPC New Nuclear consortiums◦ Consults with the International Atomic Energy Agency (IAEA) as a Subject Matter Expert (SME) for Planning & Project Management

Stone & Webster Engineering Corporation (1971‐1995) Commercial nuclear power, energy, infrastructure, and large DOE science projects Vice President, Regional Manager, Director of Construction, Project Manager, Estimating Manager, Scheduling Manager Project Controls Manager, Project Controls Engineer, Chief Scheduler, Planning & Scheduling Engineer

Education Graduate Level Executive Program in Business Administration ‐ Northeastern University, 1987 BS in Construction Management ‐ Syracuse University, Summa cum Laude, 1971 AS in Construction Management ‐ Hudson Valley Community College, Magna cum Laude, 1969

26

25

26