2019 FIVE-YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
Recommended by the Transportation Advisory Committee
February 26, 2019
Approved by the Board of Supervisors May 29, 2019
2018-2019 THROUGH 2022-2023
McCartney Road Project Before and After at Weaver Crossing
2019 FIVE-YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2018-2019 THROUGH 2022-2023
The Pinal County Board of Supervisors (Board) proudly presents the 2019 Five-Year Transportation Improvement and Maintenance Program (TIMP) for Budget Years 2018-2019 through 2022-2023. The TIMP is Pinal County’s near-term transportation plan that identifies potential funding and establishes a tentative schedule for planning, construction, and maintenance projects. It is fiscally constrained and updated annually with new projects added to the fifth year.
The Transportation Advisory Committee (TAC) is the Board appointed, ten member panel representing each of Pinal County’s five supervisor districts. The TAC is charged with prioritizing transportation projects for the TIMP and recommending the draft TIMP to the Board. On February 26, 2019, the TAC met in an open public meeting and recommended approval of the 2019 TIMP for Budget Years 2018-2019 through 2022-2023.
In recognition of their significant contributions, we would like to thank the TAC officers and members for their service to Pinal County.
First Row (L-R): Ron Vogler, District 4; Chair Maxine Brown, District 5; David Garcia, District 1 Second Row (L-R): Vice-Chair Kevin Louis, District 3; Ted Hawkins, District 4; Rusty Riggs, District 3
Not Pictured: William Beebe, District 5; Jim Fabris, District 2; and Anna Flores, District 1
2019 FIVE-YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2018-2019 THROUGH 2022-2023
The TAC conducts three public meetings during the months of September, November, and February in Florence and considers public comments in developing recommendations to the Board. We encourage you to attend the meetings and offer comments on the TIMP and future transportation projects.
Meetings are held on Tuesdays at the Pinal County Administrative Complex and begin at 2:30 p.m. as follows:
Agendas and minutes are posted in compliance with Arizona’s Open Meeting Law and can be found on Pinal County’s website: http://www.pinalcountyaz.gov/PublicWorks/TransportationPlanning/Pages/TACSchedule.aspx.
Funding for the TIMP is provided by revenues from the Pinal County Transportation Excise Tax, the half-cent sales tax, approved by voters in 2005. The sole purpose of the tax is to fund construction, maintenance, and roadside development projects throughout the county. Shopping and buying your gasoline locally ensure that quality transportation projects are planned and implemented countywide. With your support, we can continue building and improving the county’s transportation system.
Pinal County Board of Supervisors
September 24, 2019 November 26, 2019 February 25, 2020
Pete Rios, District 1; Chairman Mike Goodman, District 2; Vice-Chairman Stephen Miller, District 3; Anthony Smith, District 4; Todd House, District 5
2019 FIVE-YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2018-2019 THROUGH 2022-2023
GLOSSARY
Activity – Project work such as: pre-construction/construction/new construction/reconstruction, drainage, dust palliative, pavement preservation or safety.
Construction – The building of roadway and/or related infrastructure improvements.
Drainage – The management of storm water to protect private and/or public infrastructure.
Dust Palliative – A surface treatment applied to unimproved roadways to control dust.
New Construction – The establishment of a roadway and/or related infrastructure improvements.
Pavement Preservation – A topical treatment that extends the service life of existing pavement surfaces.
Pre-Construction – The project work conducted prior to construction of roadway and/or related infrastructure improvements such as: planning, environmental, design, and right-of-way acquisition.
Reconstruction – The rebuilding of roadway and/or related infrastructure improvements. Elements of new construction may be incorporated into the project.
Safety – The project work that eliminates or reduces the severity of roadway hazards. Examples include intersection realignment, guardrails, improved signage and/or pavement markings, traffic signals or related studies.
Status – The current state of the project such as: cancelled, closed, completed, pending, programmed, and underway
Cancelled – The project was terminated due to financial or other constraints such as unresolved right-of-way issues or changing priority.
Closed – The project was combined with another project (including allocated funding) to streamline activities or allocated funding for project was not used.
2019 FIVE-YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2018-2019 THROUGH 2022-2023
GLOSSARY (continued)
Completed – The project was successfully finished/constructed and closed out.
Pending – The project is about to start or awaiting the completion of another activity.
Programmed – The project was approved/authorized and scheduled for a future budget year.
Underway – The project is in progress.
Unfunded – Funding has not been identified/allocated.
Budget Year 2018-2019Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Arizona City Safety Study Multiple Intersections Pre-Construction $100,000 14ProgrammedJohn Kraft a
Baseline Avenue Mohican Rd-East 980 feet Construction $55,417 15PendingLindsey Randall b
Cactus Wren Street Mountain View Rd-Val Vista Rd New Construction $61,700 25UnderwayLindsey Randall a
Florence-Kelvin Highway Donnelly Wash-East 2 miles Construction $0 21ClosedJohn Kraft b
Gantzel Road Chandler Heights Rd Construction $325,000 32, 5CompletedLindsey Randall a
Germann Road Meridian Rd-Ironwood Dr New Construction $1,728,756 32PendingCeleste Garza b
Germann Road Meridian Rd-Ironwood Dr Pre-Construction $244,124 42UnderwayCeleste Garza a
Hohokam Road Paisano Dr-Quartzite Dr Construction $286,300 41UnderwayLindsey Randall b
Lost Dutchman Road Sun Rd-Prospectors Rd Construction $156,000 55PendingLindsey Randall a
McCartney Road Interstate 10-Evans Rd Reconstruction $3,500,000 51, 3CompletedLindsey Randall b
Safety Program Countywide Safety $500,000 67ProgrammedJohn Kraft a
Sunland Gin Road Battaglia Dr Intersection Safety $350,000 64CompletedJohn Kraft b
$7,307,297SUBTOTAL IMPROVEMENT
MAINTENANCEProject Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Arica Road Isom Rd-Trekell Rd Dust Palliative $120,000 74CompletedJohn Kraft a
Battaglia Drive Chuichu Rd-Del Rio Rd Pavement Preservation $200,000 73, 4UnderwayJohn Kraft b
Carefree Place State Route 347-Pepper Pl Dust Palliative $500,000 84PendingJohn Kraft a
Cattle Tank Road Davis Ranch Rd-Park Link Dr Dust Palliative $1,300,000 81, 4CompletedJohn Kraft b
Chuichu Road Battaglia Dr-Interstate 8 Pavement Preservation $2,000,000 93CompletedJohn Kraft a
Dust Abatement Program Countywide Dust Palliative $1,000,000 97ProgrammedJoe Ortiz b
Dust Abatement Program Apache Junction area Dust Palliative $500,000 105ProgrammedLindsey Randall a
Fulcar Road Hidden Valley Rd-Table Top Rd Dust Palliative $240,000 104CompletedJohn Kraft b
Mount Lemmon Road Campo Benito Rd-.5 miles south of AZ Zipline Dust Palliative $250,000 111CompletedJohn Kraft a
Peters Road Santa Cruz Wash-Corrales Rd Dust Palliative $252,083 113PendingJohn Kraft b
Sage Street Barnes Rd-Miller Rd Dust Palliative $120,000 124CompletedJohn Kraft a
Sotol Road Warren Rd-Hidden Valley Rd Dust Palliative $150,000 124CompletedJohn Kraft b
Stagecoach Pass Avenue Schnepf Rd-Ghost Rider St Pre-Construction $0 135ClosedLindsey Randall a
$6,632,083SUBTOTAL MAINTENANCE
$13,939,380GRAND TOTAL 2018-2019
District 7 = Multiple districts or countywide
Budget Year 2019-2020Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Florence-Kelvin Highway Donnelly Wash-Apache Kid. Rd Construction $1,050,000 131ProgrammedJohn Kraft b
Gantzel Road Queen Creek (Wash) Pre-Construction $50,000 142, 5ProgrammedLindsey Randall a
Hash Knife Draw Road Schnepf Rd-Sierra Vista Dr Construction $110,000 145PendingLindsey Randall b
Jackpot Street Skyline Dr-Rolling Ridge Rd Construction $82,500 155PendingLindsey Randall a
Magma Road Hunt Hwy-Gary Rd (Edwards Rd) Pre-Construction $500,000 152UnderwayLindsey Randall b
Roberts Road Felix Rd-Joel Rd Construction $38,542 165ProgrammedLindsey Randall a
Rolling Ridge Road Schnepf Rd-Sierra Vista Dr Construction $110,000 165ProgrammedLindsey Randall b
Safety Program Countywide Safety $500,000 177ProgrammedJohn Kraft a
Sage Brush Avenue Schnepf Rd-Sierra Vista Dr Construction $110,000 175ProgrammedLindsey Randall b
Stagecoach Pass Avenue Ghost Rider St-Sierra Vista Dr Construction $0 185ClosedLindsey Randall a
Tombstone Street Skyline Dr-Rolling Ridge Rd Construction $82,500 185PendingLindsey Randall b
Val Vista Road Warren Rd-Hidden Valley Rd Construction $520,000 194CompletedJohn Kraft a
$3,153,542SUBTOTAL IMPROVEMENT
MAINTENANCEProject Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Ashmoore Street Passmore Rd-Baldwin Av Dust Palliative $59,000 193, 4ProgrammedJohn Kraft b
Boyd Road Roosevelt St-End of road (Scenic St) Dust Palliative $11,000 205CompletedLindsey Randall a
Dolores Place-Shirley Road Olberg Rd-Avram Rd Dust Palliative $78,100 202UnderwayLindsey Randall b
Donnaloy Road Wilma Rd-Brenner Pass Rd Dust Palliative $84,700 212UnderwayLindsey Randall a
Dust Abatement Program Countywide Dust Palliative $2,000,000 217ProgrammedJoe Ortiz b
Marlow Road Jacob Waltz St-End of road Dust Palliative $15,958 225PendingLindsey Randall a
Olberg Road Arizona Farms Rd-Brenner Pass Rd Dust Palliative $102,083 222UnderwayLindsey Randall b
Pavement Preservation Program Countywide Pavement Preservation $700,000 237ProgrammedJoe Ortiz a
Plaza Drive Moon Vista St-Goldpoppy St Dust Palliative $6,667 235ProgrammedLindsey Randall b
Reed Road Bartlett Rd-At wash before Cactus Forest Rd Dust Palliative $91,667 241ProgrammedLindsey Randall a
Stagecoach Pass Avenue Schnepf Rd-Sierra Vista Dr Dust Palliative $328,333 245ProgrammedLindsey Randall b
Whirly Bird Road Amarillo Valley Rd-Ralston Rd Dust Palliative $300,000 254ProgrammedJohn Kraft a
$3,777,508SUBTOTAL MAINTENANCE
$6,931,050GRAND TOTAL 2019-2020
District 7 = Multiple districts or countywide
Budget Year 2020-2021Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Bunkhouse Road Veteran's Memorial Blvd-San Manuel Lodge Reconstruction $50,000 251ProgrammedJohn Kraft b
Cordones Road Catalina Hills Rd-Biosphere Rd Pre-Construction $0 264CancelledJohn Kraft a
Hunt Highway (Old) Pioneer Path-Wildhorse Dr Construction $125,000 262ProgrammedLindsey Randall b
Judd Road-Tourmaline Drive Gantzel Rd-Copper Basin Development Construction $1,250,000 272ProgrammedCeleste Garza a
Kenworthy Road Germann Rd-Pima Rd Reconstruction $550,000 272ProgrammedLindsey Randall b
Magma Road Hunt Hwy-Gary Rd (Edwards Rd) Construction $3,500,000 282PendingLindsey Randall a
Mountain View Road Broadway Av Intersection Construction $250,000 285ProgrammedLindsey Randall b
Ocotillo Road Meridian Rd-Ironwood Dr Construction $0 292CancelledLindsey Randall a
Red Rock Access Road Red Rock to Pinal Airpark Rd Pre-Construction $250,000 294ProgrammedJohn Kraft b
Safety Program Countywide Safety $500,000 307ProgrammedJohn Kraft a
$6,475,000SUBTOTAL IMPROVEMENT
MAINTENANCEProject Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Bowlin Road Hidden Valley Rd-Stonebluff Rd Dust Palliative $100,000 304ProgrammedLindsey Randall b
Logan Boulevard Diffin Rd-Reed Rd Dust Palliative $125,000 311ProgrammedLindsey Randall a
Louis Johnson Drive Amarillo Valley Rd-State Route 347 Dust Palliative $250,000 314ProgrammedLindsey Randall b
Midway Road Beggs Rd-Marsh Rd Dust Palliative $230,000 323, 4ProgrammedLindsey Randall a
Rhea Road Brennar Pass Rd-Donnaloy Rd Dust Palliative $30,000 322ProgrammedLindsey Randall b
River Road Redington Rd-Copper Creek Rd Dust Palliative $200,000 331ProgrammedJohn Kraft a
Rockcliffe Boulevard Oracle Ranch Rd (West)-Alice St Dust Palliative $30,000 331ProgrammedJohn Kraft b
Stonebluff Road Farrell Rd-Bowlin Rd Dust Palliative $100,000 344ProgrammedLindsey Randall a
Tweedy Road Storey Rd-Randolph Rd Dust Palliative $250,000 343ProgrammedLindsey Randall b
$1,315,000SUBTOTAL MAINTENANCE
$7,790,000GRAND TOTAL 2020-2021
District 7 = Multiple districts or countywide
Budget Year 2021-2022Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Florence-Kelvin Highway Apache Kid Rd-Zellweger Rd Construction $250,000 351ProgrammedJohn Kraft a
Heather Drive Kashmir Rd-Lamb Rd Construction $125,000 354ProgrammedJohn Kraft b
Judd Road-Tourmaline Drive Gantzel Rd-Copper Basin Development Construction $1,250,000 362ProgrammedCeleste Garza a
Kenworthy Road Combs Rd-Chandler Heights Rd Construction $1,500,000 362, 5ProgrammedLindsey Randall b
Peart Road Interstate 8-Early Rd Reconstruction $2,520,000 373ProgrammedJohn Kraft a
Pinal Airpark Road Interstate 10-Trico Rd Construction $650,000 374ProgrammedJohn Kraft b
Safety Program Countywide Safety $500,000 387ProgrammedJohn Kraft a
Trekell Road S. Hanna Rd-Interstate 8 Reconstruction $540,000 383ProgrammedJohn Kraft b
$7,335,000SUBTOTAL IMPROVEMENT
MAINTENANCEProject Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Camino Viejo Road Camino Viejo W-Enrada del Oro Dr Dust Palliative $940,000 395ProgrammedLindsey Randall a
Encanto Lane Cactus Forest Rd-840' North Dust Palliative $100,000 391ProgrammedLindsey Randall b
Orville Drive Diffin Rd-Quail Run Rd Dust Palliative $130,000 401ProgrammedLindsey Randall a
River Road Redington Rd-Copper Creek Rd Dust Palliative $200,000 401ProgrammedJohn Kraft b
Thunderbird Road Teel Rd-Mayer Rd Reconstruction $450,000 414ProgrammedJohn Kraft a
$1,820,000SUBTOTAL MAINTENANCE
$9,155,000GRAND TOTAL 2021-2022
District 7 = Multiple districts or countywide
Budget Year 2022-2023Transportation Improvement and Maintenance ProgramImprovement
Project Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Judd Road - Tourmaline Drive Gantzel Rd - Copper Basin Development Construction $1,250,000 412New ProjectCeleste Garza b
Quail Run Road Dirt Rd - Orville Rd Culvert/ARDP $75,000 421New ProjectLindsey Randall a
Ralston Road at Vekol Wash Crossing Contruction $1,500,000 424New ProjectJohn Kraft b
Safety Program Countywide Safety $500,000 437ProgrammedJohn Kraft a
Skyline Drive Charbray Dr - Gantzel Rd New Construction $2,000,000 432New ProjectLindsey Randall b
$5,325,000SUBTOTAL Improvement
MaintenanceProject Location Activity PageDistrictStatus
PROJECT TYPE
Total CostProject Manager
Fresno Road Warren Rd - Ralston Rd Dust Palliative $150,000 444New ProjectJohn Kraft a
MaryLynne Lane Missile Base Rd - North .75 mi Dust Palliative $150,000 444New ProjectJohn Kraft b
Mount Lemmon Road Rio Del Oro Rd - .14 East of Camp Ground Dust Palliative $750,000 451New ProjectJohn Kraft a
Ottawa Road Ottawa Rd - Bobcat Rd - Watson Wy Dust Palliative $150,000 453New ProjectJohn Kraft b
Park Link Drive 1 mile East of Pecan Dust Palliative $1,000,000 461New ProjectJohn Kraft a
River Road Redington Rd - Copper Creek Rd Dust Palliative $200,000 461New ProjectJohn Kraft b
Royce Road Ivar Rd - Hooper Trl Dust Control $50,000 472New ProjectLindsey Randall a
Selma Hwy Pinal County Portions (1.0 mi) Pavement Preservation $425,000 471,3New ProjectJohn Kraft b
$2,875,000SUBTOTAL Maintenance
$8,200,000GRAND TOTAL 2022-2023
District 7 = Multiple districts or countywide
Length in Miles
Arizona City Safety Study Multiple Intersections
Pre-Construction
$100,000
$0
$100,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 4Project Manager John Kraft E-mail [email protected]
Comments Location: Battaglia Drive from Sunland Gin Road to Overfield Road, Battaglia Drive from Chuichu Road to Del Rio Road, Lamb Road from Battaglia Drive to Milligan Road, Milligan Road from Sunland Gin Road Overfield Road, Overfield Road from Battaglia Drive to Milligan Road, and Sunland Gin Road from Battaglia Drive to Milligan RoadActivity: Reviewing drainage concerns throughout Arizona City Streets and Mountain View Estates. Working with Flood Control on possible retention basin near Henness, South of Battaglia.
Status Programmed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
1a
Length in Miles
Baseline Avenue Mohican Rd-East 980 feet
Construction
$55,417
$0
$55,417
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction expected after July 2018. Construction delayed to Spring 2019 due to lack of right-of-way donations, straightening up intersection and concreting dip. Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Pending
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.19
1b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Cactus Wren Street Mountain View Rd-Val Vista Rd
New Construction
$61,700
$0
$61,700
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction expected after July 2018. From Pending to Underway. Chip seal Spring 2019.
Status Underway
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.22
2a
Length in Miles
Florence-Kelvin Highway Donnelly Wash-East 2 miles
Construction
$0
$0
$0
Activity
County Cost
Non County Cost
IMPROVEMENT
District 1Project Manager John Kraft E-mail [email protected]
Comments Status: From Programmed to Pending. Design expected July 2018 and construction expected Summer 2019. From pending to closed. Project will be combined with Florence-Kelvin Highway, from Gardenshire Rd. to Apache Kid Rd, BY2019-2020.Cost: From $800,000 to $0
Status Closed
Maintenance Area Riverside
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
2
2b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Gantzel Road Chandler Heights Rd
Construction
$325,000
$0
$325,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2, 5Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Traffic SignalStatus: From Programmed to Completed. Traffic signal activitated July 2017.
Status Completed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
3a
Length in Miles
Germann Road Meridian Rd-Ironwood Dr
New Construction
$98,696
$1,630,060
$1,728,756
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Celeste Garza E-mail [email protected]
Comments Activity: Construction of two-lane roadBudget Year: Carryover from 2014-2015 to 2018-2019County Cost: $98,696 reflects Pinal County's cost share matchStatus: From Programmed to Pending. Design underway and construction expected Winter 2018. Project was awarded Surface Transportation Program (federal) funds through Maricopa Association of Governments. Design nearly complete, will advertise construction March 2019, project start Fall 2019.
Status Pending
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 6621139
1
3b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Germann Road Meridian Rd-Ironwood Dr
Pre-Construction
$13,866
$230,258
$244,124
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Celeste Garza E-mail [email protected]
Comments Activity: Right-of-way acquisition, environmental, design for construction of two-lane road, and plan review by the Arizona Department of TransportationCounty Cost: $13,866 reflects Pinal County's cost share matchBudget Year: 2017-2018 to 2018-2019Status: Design underway and is approximately 60% complete (Stage 3) with review/management by Arizona Department of Transportation. Project was awarded Surface Transportation Program (federal) funds through Maricopa Association of Governments. Construction scheduled Winter 2018.
Status Underway
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 6621139
1
4a
Length in Miles
Hohokam Road Paisano Dr-Quartzite Dr
Construction
$286,300
$0
$286,300
Activity
County Cost
Non County Cost
IMPROVEMENT
District 1Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction expected Summer 2018. From Pending to Underway. Chip seal Spring 2019Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Underway
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.33
4b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Lost Dutchman Road Sun Rd-Prospectors Rd
Construction
$156,000
$0
$156,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction scheduled Summer 2018. Need right-of-way donation, if obtained construction scheduled Summer 2019. Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Pending
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.6
5a
Length in Miles
McCartney Road Interstate 10-Evans Rd
Reconstruction
$3,500,000
$0
$3,500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 1, 3Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Installation of culverts at dip crossings. Status: Construction completed November 2018.
Status Completed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
3.1
5b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Safety Program Countywide
Safety
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 7Project Manager John Kraft E-mail [email protected]
Comments Activity: Direct funding to the Roadway Safety ProgramCounty Cost: Reduce from $1,000,000 to $500,000 and carryover $500,000 to Budget Year 2020-2021 to rebalance Safety Program funding.
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
6a
Length in Miles
Sunland Gin Road Battaglia Dr Intersection
Safety
$350,000
$0
$350,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Westbound Turn laneStatus: From Programmed to Underway. Design underway and construction scheduled Summer 2018. From underway to Completed November 2018.
Status Completed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 19118
0
6b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Arica Road Isom Rd-Trekell Rd
Dust Palliative
$120,000
$0
$120,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager John Kraft E-mail [email protected]
Comments Status: From Programmed to Completed.
Status Completed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
1
7a
Length in Miles
Battaglia Drive Chuichu Rd-Del Rio Rd
Pavement Preservation
$200,000
$0
$200,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 3, 4Project Manager John Kraft E-mail [email protected]
Comments Status: From Pending to Underway. Profile mill and AC overlay from Chuichu Rd to Peart Rd is complete. Peart Rd to Toltec Hwy micro surfacing Spring 2019.
Status Underway
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
4.5
7b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Carefree Place State Route 347-Pepper Pl
Dust Palliative
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Dust palliative includes 4.1 miles of the following roadways: Carefree Place, Reitz Ranch Road, Padilla Road, Clayton Road, and Lopez Road.Budget Year: Advance from 2019-2020 to 2018-2019 to combine with projects programmed under the State Implemention Plan for completion after July 2018.Status: From Programmed to Pending. ARDP Spring/Summer 2019.
Status Pending
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 27124
4.1
8a
Length in Miles
Cattle Tank Road Davis Ranch Rd-Park Link Dr
Dust Palliative
$1,300,000
$0
$1,300,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1, 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Asphalt rock dust palliativeCounty Cost: From $750,000 to $1,300,000 due to Bureau of Land Management requirementsBudget Year: From 2016-2017 to 2017-2018 to 2018-2019Status: From Pending to Underway. Phased construction (Phase 2-Clearing and Grubbing) underway with chip seal expected Fall 2018. From Underway to Completed, awaiting repair of pavement in13 area due to rain/flooding issues. Notice of Termination after 70% of native seed is re-established.
Status Completed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
5.5
8b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Chuichu Road Battaglia Dr-Interstate 8
Pavement Preservation
$2,000,000
$0
$2,000,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 3Project Manager John Kraft E-mail [email protected]
Comments Status: From Programmed to Pending. Planning to contract Pavement Preservation after July 2018. From Programmed to Complete.
Status Completed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
4.3
9a
Length in Miles
Dust Abatement Program Countywide
Dust Palliative
$1,000,000
$0
$1,000,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 7Project Manager Joe Ortiz E-mail [email protected]
Comments Activity: Area Engineers' discretionary project(s) to address fugitive dust (Particulate Matter 2.5 and 10) in Pinal County's Non-Attainment areas
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
9b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Dust Abatement Program Apache Junction area
Dust Palliative
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Area Engineer's discretionary project(s) to address fugitive dust (Particulate Matter 10) in Pinal County's Non-Attainment area (T1N, R8E)Status: 3.22 miles of Asphalt rock dust palliatives in the southeast Apache Junction area scheduled Summer 2018. Looking to chip an additional 1 mile Spring 2019.
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
10a
Length in Miles
Fulcar Road Hidden Valley Rd-Table Top Rd
Dust Palliative
$240,000
$0
$240,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager John Kraft E-mail [email protected]
Comments Status: From Programmed to Completed. Completed in 2016 as part of the State Implementation Plan.
Status Completed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
2
10b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Mount Lemmon Road Campo Benito Rd-.5 miles south of AZ Zipline
Dust Palliative
$250,000
$0
$250,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager John Kraft E-mail [email protected]
Comments Activity: Continuation of asphalt rock dust palliative and cutoff walls at wash crossingBudget Year: From 2020-2021 to 2018-2019Status: From Programmed to Pending. Asphalt rock dust palliative is expected Summer 2018. From Pending to Complete on 8/20/2018.
Status Completed
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 141
2
11a
Length in Miles
Peters Road Santa Cruz Wash-Corrales Rd
Dust Palliative
$252,083
$0
$252,083
Activity
County Cost
Non County Cost
MAINTENANCE
District 3Project Manager John Kraft E-mail [email protected]
Comments Budget Year: From 2017-2018 to 2018-2019Status: From Programmed to Pending. Construction scheduled after July 2018. ARDP Summer 2019Project Manager: From Lindsey Randall to John KraftE-mail: From [email protected] to [email protected]
Status Pending
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
1.6
11b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Sage Street Barnes Rd-Miller Rd
Dust Palliative
$120,000
$0
$120,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager John Kraft E-mail [email protected]
Comments Status: From Programmed to Completed. Construction completed August 2017.
Status Completed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
12a
Length in Miles
Sotol Road Warren Rd-Hidden Valley Rd
Dust Palliative
$150,000
$0
$150,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager John Kraft E-mail [email protected]
Comments Status: From Programmed to Completed. Completed April 2017.
Status Completed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
1
12b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Stagecoach Pass Avenue Schnepf Rd-Ghost Rider St
Pre-Construction
$0
$0
$0
Activity
County Cost
Non County Cost
MAINTENANCE
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Underway to Closed. Funding and project is combined with Stagecoach Pass Avenue project programmed in Budget Year 2019-2020.County Cost: From $50,000 to $0.Activity: In-house design and right-of-way design. Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Closed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.8
13a
Length in Miles
Florence-Kelvin Highway Donnelly Wash-Apache Kid. Rd
Construction
$1,050,000
$0
$1,050,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 1Project Manager John Kraft E-mail [email protected]
Comments Activity: L-2 Standard - 6 inch Aggregate Base over Double Chip SealStatus: Combined with Florence-Kelvin Highway project from Donnelly Wash, East 2 miles. New limits are from Donnelly Wash-Apache Kid Rd.Cost: Increased from $250,000 to $1,050,000
Status Programmed
Maintenance Area Riverside
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 3030
5
13b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Budget Year 2018-2019
Length in Miles
Gantzel Road Queen Creek (Wash)
Pre-Construction
$50,000
$0
$50,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2, 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: Design to start July 2019
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 4010
0.07
14a
Length in Miles
Hash Knife Draw Road Schnepf Rd-Sierra Vista Dr
Construction
$110,000
$0
$110,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction expected Summer 2018 as part of the State Implementation Plan. Need 2 out of 33 grants of easements from property owners. Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Pending
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 8125
1
14b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Jackpot Street Skyline Dr-Rolling Ridge Rd
Construction
$82,500
$0
$82,500
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: From Programmed to Pending. All grants of easement received from proerty owners.
Status Pending
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 10116
0.75
15a
Length in Miles
Magma Road Hunt Hwy-Gary Rd (Edwards Rd)
Pre-Construction
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Right-of-way acquisition from Arizona State Land DepartmentStatus: Right-of-way application has been submitted to Arizona State Land Department
Status Underway
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
15b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Roberts Road Felix Rd-Joel Rd
Construction
$38,542
$0
$38,542
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: Construction Fall 2019
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 15035
0.35
16a
Length in Miles
Rolling Ridge Road Schnepf Rd-Sierra Vista Dr
Construction
$110,000
$0
$110,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: Have 2 of 36 grants of easements form property owners
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 16114
1
16b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Safety Program Countywide
Safety
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 7Project Manager John Kraft E-mail [email protected]
Comments Activity: Direct funding to the Roadway Safety ProgramCounty Cost: Reduce from $1,000,000 to $500,000 and carryover $500,000 to Budget Year 2021-2022 to rebalance Safety Program funding.
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
17a
Length in Miles
Sage Brush Avenue Schnepf Rd-Sierra Vista Dr
Construction
$110,000
$0
$110,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: Have 2 of 40 grants of easements from property owners
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 17126
1
17b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Stagecoach Pass Avenue Ghost Rider St-Sierra Vista Dr
Construction
$0
$0
$0
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Closed. Funding and project is combined with Stagecoach Pass Avenue project programmed in Budget Year 2019-2020.County Cost: $28,333.00 to $0.Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Closed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 18127
1
18a
Length in Miles
Tombstone Street Skyline Dr-Rolling Ridge Rd
Construction
$82,500
$0
$82,500
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: From Programmed to PendingActivity: Received all grants of easements from property owners
Status Pending
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 20115
0.75
18b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Val Vista Road Warren Rd-Hidden Valley Rd
Construction
$520,000
$0
$520,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 4Project Manager John Kraft E-mail [email protected]
Comments Status: From Programmed to Completed. Completed August 2017 as part of the State Implementation Plan.
Status Completed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 22036
1
19a
Length in Miles
Ashmoore Street Passmore Rd-Baldwin Av
Dust Palliative
$59,000
$0
$59,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 3, 4Project Manager John Kraft E-mail [email protected]
Comments
Status Programmed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 23022
0.5
19b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Boyd Road Roosevelt St-End of road (Scenic St)
Dust Palliative
$11,000
$0
$11,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: From Programmed to CompletedActivity: Completed Summer 2018 with Dust Abatement project
Status Completed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 25015
0.1
20a
Length in Miles
Dolores Place-Shirley Road Olberg Rd-Avram Rd
Dust Palliative
$78,100
$0
$78,100
Activity
County Cost
Non County Cost
MAINTENANCE
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction expected Summer 2018 as part of the State Implementation Plan. From Pending to Underway. First coat completed, scheduling second coat. Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Underway
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 28121
0.71
20b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Donnaloy Road Wilma Rd-Brenner Pass Rd
Dust Palliative
$84,700
$0
$84,700
Activity
County Cost
Non County Cost
MAINTENANCE
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction expected Summer 2018 as part of the State Implementation Plan. From Pending to Underway. First coat completed, second coat being scheduled. Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Underway
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 29120
0.77
21a
Length in Miles
Dust Abatement Program Countywide
Dust Palliative
$2,000,000
$0
$2,000,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 7Project Manager Joe Ortiz E-mail [email protected]
Comments Activity: Area Engineers' discretionary project(s) to address fugitive dust (Particulate Matter 2.5 and 10) in Pinal County's Non-Attainment areas
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
21b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Marlow Road Jacob Waltz St-End of road
Dust Palliative
$15,958
$0
$15,958
Activity
County Cost
Non County Cost
MAINTENANCE
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]: From Programmed to PendingActivity: Summer 2020
Status Pending
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 30012
0.15
22a
Length in Miles
Olberg Road Arizona Farms Rd-Brenner Pass Rd
Dust Palliative
$102,083
$0
$102,083
Activity
County Cost
Non County Cost
MAINTENANCE
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Status: From Programmed to Pending. Construction expected Summer 2018 as part of the State Implementation Plan. From Pending to Underway. First coat completed, second coat being scheduled. Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Underway
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 31119
0.93
22b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Pavement Preservation Program Countywide
Pavement Preservation
$700,000
$0
$700,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 7Project Manager Joe Ortiz E-mail [email protected]
Comments Activity: Direct funding to the Pavement Preservation Program
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
23a
Length in Miles
Plaza Drive Moon Vista St-Goldpoppy St
Dust Palliative
$6,667
$0
$6,667
Activity
County Cost
Non County Cost
MAINTENANCE
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 32016
0.06
23b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Reed Road Bartlett Rd-At wash before Cactus Forest Rd
Dust Palliative
$91,667
$0
$91,667
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager Lindsey Randall E-mail [email protected]
Comments Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 35029
0.74
24a
Length in Miles
Stagecoach Pass Avenue Schnepf Rd-Sierra Vista Dr
Dust Palliative
$328,333
$0
$328,333
Activity
County Cost
Non County Cost
MAINTENANCE
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Location: From Schnepf Rd-Ghost Rider St to Schnepf Rd-Sierra Vista DrStatus: Combined Stagecoach Pass Avenue projects from Budget Year 2018-2019 and 2019-2020 into one Stagecoach Pass Avenue project from Schnepf Rd-Sierra Vista Dr. Development North of area will improve roadway and county will chip seal roadway once improvements are made.County Cost: from $250,000 to $328,333.Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
1.8
24b
Budget Year 2019-2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Whirly Bird Road Amarillo Valley Rd-Ralston Rd
Dust Palliative
$300,000
$0
$300,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Dust palliative includes Whirly Bird Road from Amarillo Valley Rd to Ralston Rd and Garnet Road from Whirly Bird Rd to Century Rd
Status Programmed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 36008
3
25a
Length in Miles
Bunkhouse Road Veteran's Memorial Blvd-San Manuel Lodge
Reconstruction
$50,000
$0
$50,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 1Project Manager John Kraft E-mail [email protected]
Comments Activity: Resize culvert to driveway and reconstruct roadway for proper drainage
Status Programmed
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 134
0.2
25b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Budget Year 2019-2020
Length in Miles
Cordones Road Catalina Hills Rd-Biosphere Rd
Pre-Construction
$0
$0
$0
Activity
County Cost
Non County Cost
IMPROVEMENT
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Design Concept Report for new roadwayCounty Cost: From $250,000 to $0.00Status: From Programmed to Cancelled. Project is now funded by the Pinal Regional Transportation Authority.
Status Cancelled
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 156
3.5
26a
Length in Miles
Hunt Highway (Old) Pioneer Path-Wildhorse Dr
Construction
$125,000
$0
$125,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Concrete ford crossingProject Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 181
0
26b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Judd Road-Tourmaline Drive Gantzel Rd-Copper Basin Development
Construction
$1,250,000
$0
$1,250,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Celeste Garza E-mail [email protected]
Comments Activity: Construction of new road on Judd Road alignmentCounty Cost: $1,250,000 will be programmed annually for 4 years (Year 1).
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 176
1.5
27a
Length in Miles
Kenworthy Road Germann Rd-Pima Rd
Reconstruction
$550,000
$0
$550,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: RehabilitationProject Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 178
1
27b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Magma Road Hunt Hwy-Gary Rd (Edwards Rd)
Construction
$3,500,000
$0
$3,500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Continuation of improvements on alignmentStatus: Project is a high priority for Transportation Advisory Committee and Staff. Staff is exploring other funding opportunities to advance the project schedule. From Programmed to Pending.Budget Year: 2020-2021County Cost: From $1,250,000.00 to $3,500,000.00
Status Pending
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 1420144
1.5
28a
Length in Miles
Mountain View Road Broadway Av Intersection
Construction
$250,000
$0
$250,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Intersection reconstruction and culvert installationProject Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 179
0
28b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Ocotillo Road Meridian Rd-Ironwood Dr
Construction
$0
$0
$0
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Roadway wideningStatus: This portion of Ocotillo Rd has been annexed by Queen Creek, project has been closed and will be constructed by Queen Creek.
Status Cancelled
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 177
1
29a
Length in Miles
Red Rock Access Road Red Rock to Pinal Airpark Rd
Pre-Construction
$250,000
$0
$250,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Environmental Clearnace/Right-of-Way Acquisition. Replacement project for Cordones Road. Red Rock Access Road was previously programmed on the Transportation Improvement and Maintenance Program but was cancelled in 2015. Pre-Construction funding is necessary to evaluate a secondary access to Pinal Airpark.
Status Programmed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
3
29b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Safety Program Countywide
Safety
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 7Project Manager John Kraft E-mail [email protected]
Comments Activity: Direct funding to the Roadway Safety ProgramCounty Cost: Add $500,000 to Budget Year 2020-2021 to rebalance Safety Program funding.
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
30a
Length in Miles
Bowlin Road Hidden Valley Rd-Stonebluff Rd
Dust Palliative
$100,000
$0
$100,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager Lindsey Randall E-mail [email protected]
Comments
Status Programmed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.6
30b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Logan Boulevard Diffin Rd-Reed Rd
Dust Palliative
$125,000
$0
$125,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Dust palliative is contingent on receiving right-of-way donationsProject Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 147
1
31a
Length in Miles
Louis Johnson Drive Amarillo Valley Rd-State Route 347
Dust Palliative
$250,000
$0
$250,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager Lindsey Randall E-mail [email protected]
Comments
Status Programmed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 137
2
31b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Midway Road Beggs Rd-Marsh Rd
Dust Palliative
$230,000
$0
$230,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 3, 4Project Manager Lindsey Randall E-mail [email protected]
Comments
Status Programmed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 130
2
32a
Length in Miles
Rhea Road Brennar Pass Rd-Donnaloy Rd
Dust Palliative
$30,000
$0
$30,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments Status: Dust palliative may be completed in conjunction with the Donnaloy Road project that is programmed in Budget Year 2019-2020.Project Manager: From Celeste Garza to Lindsey RandallE-mail: From [email protected] to [email protected]
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.3
32b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
River Road Redington Rd-Copper Creek Rd
Dust Palliative
$200,000
$0
$200,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager John Kraft E-mail [email protected]
Comments Status: Dust palliative is contigent on receiving right-of-way donations.Length: Dust palliative will extend to existing 5 miles of paved roadway.County Cost: $200,000 will be programmed annually for 4 years (Year 1).
Status Programmed
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 191
8
33a
Length in Miles
Rockcliffe Boulevard Oracle Ranch Rd (West)-Alice St
Dust Palliative
$30,000
$0
$30,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager John Kraft E-mail [email protected]
Comments Comments: Dust palliative is contigent on receiving right-of-way donations
Status Programmed
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 132
0.25
33b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Stonebluff Road Farrell Rd-Bowlin Rd
Dust Palliative
$100,000
$0
$100,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager Lindsey Randall E-mail [email protected]
Comments
Status Programmed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 149
1
34a
Length in Miles
Tweedy Road Storey Rd-Randolph Rd
Dust Palliative
$250,000
$0
$250,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 3Project Manager Lindsey Randall E-mail [email protected]
Comments Comments: Carmichael Road to Randolph Road is located within the City of Coolidge
Status Programmed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 1400188
2
34b
Budget Year 2020-2021 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Florence-Kelvin Highway Apache Kid Rd-Zellweger Rd
Construction
$250,000
$0
$250,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 1Project Manager John Kraft E-mail [email protected]
Comments Activity: L-2 Standard - 6 inch Aggregate Base over Double Chip SealProject Manager: From Angeline To to John Kraft
Status Programmed
Maintenance Area Riverside
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 253
0.75
35a
Length in Miles
Heather Drive Kashmir Rd-Lamb Rd
Construction
$125,000
$0
$125,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Roadway construction with Aggregate Base and Asphalt ConcreteLength: 900'
Status Programmed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 249
900
35b
Budget Year 2021-2022 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Judd Road-Tourmaline Drive Gantzel Rd-Copper Basin Development
Construction
$1,250,000
$0
$1,250,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2Project Manager Celeste Garza E-mail [email protected]
Comments Activity: Construction on new road on Judd alignmentCounty Cost: $1,250,000 will be programmed annually for 4 years (Year 2)
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 176
1.5
36a
Length in Miles
Kenworthy Road Combs Rd-Chandler Heights Rd
Construction
$1,500,000
$0
$1,500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 2, 5Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Construction of an L-2 Standard roadway. This project in contingent on funding availability (project is partially funded at this time).
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 207
1.15
36b
Budget Year 2021-2022 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Peart Road Interstate 8-Early Rd
Reconstruction
$2,520,000
$0
$2,520,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 3Project Manager John Kraft E-mail [email protected]
Comments Activity: Remove existing pavement and replace with L-2 Modified Standard.
Status Programmed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 269
2
37a
Length in Miles
Pinal Airpark Road Interstate 10-Trico Rd
Construction
$650,000
$0
$650,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Driveways, possible left turn acceleration/merge lane, and possible roadway mill and replace.
Status Programmed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 251252
2
37b
Budget Year 2021-2022 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Safety Program Countywide
Safety
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 7Project Manager John Kraft E-mail [email protected]
Comments Activity: Direct funding to the Roadway Safety ProgramCounty Cost: Add $500,000 to Budget Year 2021-2022 to rebalance Safety Program funding.
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
38a
Length in Miles
Trekell Road S. Hanna Rd-Interstate 8
Reconstruction
$540,000
$0
$540,000
Activity
County Cost
Non County Cost
IMPROVEMENT
District 3Project Manager John Kraft E-mail [email protected]
Comments Activity: Remove existing pavement and replace with L-2 Modified Standard.
Status Programmed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 271
0.4
38b
Budget Year 2021-2022 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Camino Viejo Road Camino Viejo W-Enrada del Oro Dr
Dust Palliative
$940,000
$0
$940,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 5Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: State Land right-of-way is needed to complete the dust palliative
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 212
2.4
39a
Length in Miles
Encanto Lane Cactus Forest Rd-840' North
Dust Palliative
$100,000
$0
$100,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Dust Palliative will include Indigo Road, the unpaved segment of Leisure Lane, and Page Road for a total of 1 mile.
Status Programmed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 193
1
39b
Budget Year 2021-2022 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Orville Drive Diffin Rd-Quail Run Rd
Dust Palliative
$130,000
$0
$130,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager Lindsey Randall E-mail [email protected]
Comments
Status Programmed
Maintenance Area San Tan
Transporation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 217
1.13
40a
Length in Miles
River Road Redington Rd-Copper Creek Rd
Dust Palliative
$200,000
$0
$200,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 1Project Manager John Kraft E-mail [email protected]
Comments Status: Dust palliative is contigent on receiving right-of-way donations.Length: Dust palliative will extend to existing 5 miles of paved roadway.County Cost: $200,000 will be programmed annually for 4 years (Year 2).
Status Programmed
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 191
8
40b
Budget Year 2021-2022 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Budget Year 2021-2022
Length in Miles
Thunderbird Road Teel Rd-Mayer Rd
Reconstruction
$450,000
$0
$450,000
Activity
County Cost
Non County Cost
MAINTENANCE
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Roadway Widening
Status Programmed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 216
1.5
41a
Length in Miles
Judd Road - Tourmaline Drive Gantzel Rd - Copper Basin Development
Construction
$1,250,000
$0
$1,250,000
Activity
County Cost
Non County Cost
Improvement
District 2Project Manager Celeste Garza E-mail [email protected]
Comments Activity: Construction on new road on Judd alignmentCounty Cost: $1,250,000 will be programmed annually for 4 years (Year 3)
Status New Project
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
41b
Budget Year 2022-2023 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Quail Run Road Dirt Rd - Orville Rd
Culvert/ARDP
$75,000
$0
$75,000
Activity
County Cost
Non County Cost
Improvement
District 1Project Manager Lindsey Randall E-mail [email protected]
Comments Activity: Construct with Orville Road project in Budget Year 2021-2022
Status New Project
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 283
42a
Length in Miles
Ralston Road at Vekol Wash Crossing
Contruction
$1,500,000
$0
$1,500,000
Activity
County Cost
Non County Cost
Improvement
District 4Project Manager John Kraft E-mail [email protected]
Comments
Status New Project
Maintenance Area Hidden Valley
Funding SourcePROJECT TYPE
Total Cost
Project Number 382
42b
Budget Year 2022-2023 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Safety Program Countywide
Safety
$500,000
$0
$500,000
Activity
County Cost
Non County Cost
Improvement
District 7Project Manager John Kraft E-mail [email protected]
Comments Activity: Direct fuunding to the Roadway Safety ProgramCounty Cost: Add $500,000 to Budget Year 2022-2023 to rebalance Safety Program funding
Status Programmed
Maintenance Area Multiple
Transprtation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
43a
Length in Miles
Skyline Drive Charbray Dr - Gantzel Rd
New Construction
$2,000,000
$0
$2,000,000
Activity
County Cost
Non County Cost
Improvement
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments
Status New Project
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 325
43b
Budget Year 2022-2023 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Fresno Road Warren Rd - Ralston Rd
Dust Palliative
$150,000
$0
$150,000
Activity
County Cost
Non County Cost
Maintenance
District 4Project Manager John Kraft E-mail [email protected]
Comments
Status New Project
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 337
44a
Length in Miles
MaryLynne Lane Missile Base Rd - North .75 mi
Dust Palliative
$150,000
$0
$150,000
Activity
County Cost
Non County Cost
Maintenance
District 4Project Manager John Kraft E-mail [email protected]
Comments Activity: Dust Palliative to County right-of-way, approximately .75 miles.
Status New Project
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 295
44b
Budget Year 2022-2023 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Mount Lemmon Road Rio Del Oro Rd - .14 East of Camp Ground
Dust Palliative
$750,000
$0
$750,000
Activity
County Cost
Non County Cost
Maintenance
District 1Project Manager John Kraft E-mail [email protected]
Comments
Status New Project
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 393
45a
Length in Miles
Ottawa Road Ottawa Rd - Bobcat Rd - Watson Wy
Dust Palliative
$150,000
$0
$150,000
Activity
County Cost
Non County Cost
Maintenance
District 3Project Manager John Kraft E-mail [email protected]
Comments
Status New Project
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 286
45b
Budget Year 2022-2023 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Park Link Drive 1 mile East of Pecan
Dust Palliative
$1,000,000
$0
$1,000,000
Activity
County Cost
Non County Cost
Maintenance
District 1Project Manager John Kraft E-mail [email protected]
Comments
Status New Project
Maintenance Area Arizona City
Funding SourcePROJECT TYPE
Total Cost
Project Number 319
46a
Length in Miles
River Road Redington Rd - Copper Creek Rd
Dust Palliative
$200,000
$0
$200,000
Activity
County Cost
Non County Cost
Maintenance
District 1Project Manager John Kraft E-mail [email protected]
Comments Status: Dust palliative is contingent on receiving right-of-way donations.Length: Dust palliative will extend to existing 5 miles of paved roadway.County Cost: $200,00 will be programmed annually for 4 years (Year 3).
Status New Project
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
46b
Budget Year 2022-2023 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520-866-6411 (telephone)520-866-6511 (fax)
Length in Miles
Royce Road Ivar Rd - Hooper Trl
Dust Control
$50,000
$0
$50,000
Activity
County Cost
Non County Cost
Maintenance
District 2Project Manager Lindsey Randall E-mail [email protected]
Comments
Status New Project
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 285
47a
Length in Miles
Selma Hwy Pinal County Portions (1.0 mi)
Pavement Preservation
$425,000
$0
$425,000
Activity
County Cost
Non County Cost
Maintenance
District 1,3Project Manager John Kraft E-mail [email protected]
Comments Length: Overlay 1.0 mile of County maintained portion
Status New Project
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 415
47b
Budget Year 2022-2023 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132