Ministry of Transportation and Infrastructure (MOTI)
Peace District
By Hali DavenportActing District Manager
November 8, 2018
2018 Project Delivery Update
D-1
November 8, 2018
![Page 2: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/2.jpg)
2018-11-02
2
RESURFACING COMPLETED
• North Peace Asphalt Surfacing
• Jackfish Lake Road Sealcoat• West Fraser Road Paving• H97 Dawson Creek to
Kiskatinaw Bridge Mill & Fill • H29 Bullmoose to Sukunka
HIPR
ADDITIONAL RESURFACING
• Farrell Creek Road
• Patch paving on Braden, Sweetwater, BessboroughRoads
D-1
November 8, 2018
![Page 3: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/3.jpg)
2018-11-02
3
BRIDGE WORK COMPLETED
• Large Culvert Replacement• Roseland Culvert
Replacement• Scour Remediation –
McLean & St John 3• Brassey Creek Bridge –
Substructure Rehabilitation
BRIDGE PROJECTS IN PROGRESS
`
• La Guarde Culvert Replacement – 2019 early tender
• Scour Remediation Design & Survey – Benson & Gunter Remediation in 2019
• Taylor Bridge Business Case
D-1
November 8, 2018
![Page 4: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/4.jpg)
2018-11-02
4
ENGINEERING/ CONSTRUCTION
• H97/Swanson Lumber Road Signalization (design only)• Baldonnel Area Drainage Review and Road Improvements• Farrell Creek Geotechnical Assessment• South Taylor Hill Phase 2 • Peace District Pullouts
COMMUNITY SAFETYENHANCEMENTS
COMPLETED
• Murray River Boat Launch Access Improvements• 911 Signage• North Taylor Hill Reflectivity • H97 Museum Cross Walk
D-1
November 8, 2018
![Page 5: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/5.jpg)
2018-11-02
5
COMMUNITY SAFETY ENHANCEMENTS
• Dawson Creek Pedestrian Count Down Timers - in progress
• Chetwynd Pedestrian Count Down Timers – in progress
• Dawson Creek Bus Shelters H97/11th and H97/13th – on hold
• Canyon Creek Crosswalk -Ongoing discussions
SIDE ROAD IMPROVEMENTS
• Gravelling• Dust Control• Side Road Rehabilitation –
culvert installations, ditching, base repairs
• Slides & Washouts – 2017 freshet
• Triad Road Improvements
D-1
November 8, 2018
![Page 6: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/6.jpg)
2018-11-02
6
SLIDES AND WASHOUTS
• 2018 freshet works and July significant rain event
• 85 sites identified throughout the Peace
• 30 delivered under Provincial funding
• Remainder delivered under MC’s quantified plan or District program
OLD FORT SLIDE
D-1
November 8, 2018
![Page 7: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/7.jpg)
2018-11-02
7
OLD FORT SLIDE
South Peace 2016 Flood Recovery Program
2018 Flood Construction Projects
D-1
November 8, 2018
![Page 8: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/8.jpg)
2018-11-02
8
Chetwynd Area
Zonnebeke
Tippy Corner Bridge• Replacement of the existing
2.7m culvert with a 17.5m bridge and new highway approaches
• Construction start: Spring 2018
• Mainline bridge and road works completed in October 2018
• Completion: September 2019
D-1
November 8, 2018
![Page 9: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/9.jpg)
2018-11-02
9
Crassier Creek Bridge
• Replacement of the existing 18.2m bridge with a 36m bridge as well as 1.1km of new highway, to improve the highway geometry and improve access to the Willow Creek Mine road
• Construction completed October 2018
Willow Flats Bridge• Replacement of the
existing culvert with a 13.5m bridge and new highway approaches
• Construction substantially completed October 2018
• Minor works in 2019.
D-1
November 8, 2018
![Page 10: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/10.jpg)
2018-11-02
10
Bowlder Creek Bridge • Located 25km west of
Chetwynd
• Replacement of the existing culvert with a 30.5m bridge and new highway approaches
• Construction: Summer 2018 – Fall 2019
Commotion Creek Bridge
• Replacement of the existing culvert with a 38m bridge and new highway approaches
• Construction substantially complete November 2018
• Minor works 2019
D-1
November 8, 2018
![Page 11: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/11.jpg)
2018-11-02
11
Stone Creek Bridge
• Replacement of existing culvert with a 19m bridge and new highway approaches
• Mainline bridge and road works completed in October 2018
• Completion August 2019
Zonnebeke Multiplate
• H29S: Replacement of the existing culvert with a 5 meter multiplate
• Construction 2017-Summer 2019
• Project delayed
D-1
November 8, 2018
![Page 12: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/12.jpg)
2018-11-02
12
Dawson Creek Area
Rolla Road Bridge
• Replacement of existing culverts with a 50m bridge and new highway approaches
• Construction: 2018-2020
D-1
November 8, 2018
![Page 13: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/13.jpg)
2018-11-02
13
8th Street Bridge
• Replacement of existing culverts with a 5 lane, 48m bridge
• Construction: Fall 2018 to 2020
Walper Bridge
• Located 44 km south of Dawson Creek
• Replacement of existing culverts with a 25m bridge
• Completion Nov 2018
D-1
November 8, 2018
![Page 14: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/14.jpg)
2018-11-02
14
2019 Flood Construction Projects
• Fur Thief Bridge, located 41 km west of Chetwynd
• Parnell Road Bridge, located 15 km north of Dawson creek on Parnell Road (213 Rd)
• Gladys Bridge, located 17 km south of Dawson Creek
• Gibbons Multi-plate, located 29 km west of Dawson Creek
For Reference
• DriveBC
• The Program Website • https://www2.gov.bc.ca/gov/content/transportation/transportation-
infrastructure/projects/highway-97-north-bridges
• TranBC Flickr site
D-1
November 8, 2018
![Page 15: 2018 Project Delivery Updateprrd.bc.ca/board/agendas/2018/2018-33-983818624/pages/documen… · Microsoft PowerPoint - Program Presentation1.pptx [Read-Only] Author: AD0018 Created](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ffb830373edb61d1567dd40/html5/thumbnails/15.jpg)
2018-11-02
15
Conclusion
D-1
November 8, 2018