We assist buildings and communities in achieving energy efficiency, saving money, and becoming more sustainable.
We are an applied research program at University of Illinois, working in collaboration with 360 Energy Group.
Our goal: Reduce the energy footprint of Illinois.
2
Who we are
![Page 3: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/3.jpg)
SEDAC is the Illinois Energy Conservation Code Training Provider
This training program is sponsored by Illinois EPAOffice of Energy
![Page 4: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/4.jpg)
Energy Code Assistance
• Technical support • 800.214.7954• [email protected]
• Online resources at sedac.org/energy-code
• Workshops• Webinars• Online on-demand training
modules
4
![Page 5: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/5.jpg)
www.sedac.org/energy-code
5
![Page 6: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/6.jpg)
www.sedac.org/energy-code
6
![Page 7: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/7.jpg)
www.sedac.org/energy-code
7
![Page 8: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/8.jpg)
www.sedac.org/energy-code
8
![Page 9: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/9.jpg)
Illinois Building Codes & Regulations
![Page 10: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/10.jpg)
10
![Page 11: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/11.jpg)
11
County / Municipal Code Reporting• 20 ILCS 3918/55
A municipality with a population of less than 1 million or a county adopting a new building code or amending an existing building code must provide an identification of the code by title & edition, or the amendment to the Commission.
![Page 12: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/12.jpg)
12
IL Bldg Code Requirements for Areas where no Bldg Code is adopted & registered
• Public Act 096-0704
All commercial construction after 7/1/2011, must comply with the 2006 or later editions of the IBC, IEBC, IPMC, and the 2008 or later edition of NEC.
New commercial bldgs. must pass inspection by an inspector qualified per CDB’s standard
![Page 13: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/13.jpg)
13
Which Version?• 70% (391 out of 566) of IL municipalities use IBC*.
9%
15%
21%
13%
25%
15%
2%
0
20
40
60
80
100
2000 2003 2006 2009 2012 2015 2018
No.
of M
unic
ipal
ity(T
otal
391
)
IBC Version
Which version of IBC is used?
* Based on the data from CDB.
![Page 14: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/14.jpg)
I-Codes by ICC
![Page 15: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/15.jpg)
What are the different I-Codes?
15
![Page 16: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/16.jpg)
Illinois Energy Conservation Code
![Page 17: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/17.jpg)
17
Illinois Energy Conservation Code
Anticipated to Change to IECC
![Page 18: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/18.jpg)
• The Illinois Energy Efficient Building Act requires the Illinois Energy Code Advisory Council, through the Capital Development Board (CDB), to review and adopt the most current version of the IECC within one year after its publication date (September 2017).
• The Code then becomes effective within 6 months after it is adopted by CDB, unless voted down by JCAR (March 1, 2019).
• The Council reviewed proposals for the IL Amendments based on 2018 IECC. They have been through the Joint Committee on Administrative Rules (JCAR) and the comment period just finished.
18
Illinois Energy Conservation CodeUpdated Illinois Energy Conservation Code based on 2018 IECC, with IL Amendments is anticipated to be effective March 1, 2019
![Page 19: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/19.jpg)
19
Chicago Energy Conservation Code
![Page 20: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/20.jpg)
20
Chicago Energy Conservation Code
Must be completed by an Illinois-licensed architect or
engineer
New Compliance Statement Effective June 20, 2018
![Page 21: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/21.jpg)
21
Chicago Energy Conservation Code (Commercial Compliance Method)
![Page 22: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/22.jpg)
22
Chicago Energy Conservation Code (Residential Compliance Method)
![Page 23: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/23.jpg)
2018 International Energy Conservation Code (IECC)
![Page 24: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/24.jpg)
24
2018 IECC Commercial Compliance Option
![Page 25: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/25.jpg)
25
2018 IECC Residential Compliance Option
![Page 26: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/26.jpg)
Residential:• A detached one-family or two family dwelling • Any building 3 stories or less above grade that contains
multiple dwelling units, where occupants reside on a primarily permanent basis (4 stories or less in Chicago)
• Examples:
26
Commercial or Residential?
• Rectory• Fraternity or sorority house• Dormitory• Rooming house
• Townhouse• Row house• Apartment house• Convent• Monastery
![Page 27: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/27.jpg)
• 5 story mixed use building with 2 stories of retail stores and 3 stories of apartments in Chicago
• 3 story mixed use building with 1 story of retail stores and 2 stories of apartments in Bloomington
• 5 story single family home
• 3 story hotel
27
Commercial or Residential?
![Page 28: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/28.jpg)
28
History of Model Codes ImprovementResidential
Commercial
![Page 29: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/29.jpg)
30
History of Model Codes ImprovementResidential
Commercial
2012 2015 IECC0.98 % Savings
2015 2018 IECC0 % Savings
![Page 30: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/30.jpg)
https://codes.iccsafe.org/public/document/iecc2018
31
Access to 2018 IECC
![Page 31: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/31.jpg)
• Energy efficiency improvement (initial estimate of 13-15% improvement)
• New Chapter (Ch.5) for existing buildings – 2015
• Mechanical Section (C 403): Reorganized, so all provisions for a type of equipment or system are in one place – 2018
32
2018 IECC Commercial Changes: Highlights
![Page 32: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/32.jpg)
• Additional efficiency package options (total of 8): Enhanced lighting control (C406.4) – 2015
Dedicated outdoor air system (C406.6) - 2015
High efficiency service water heating (C406.7) – 2015
Enhanced envelope performance (C406.8) – 2018
Reduced air infiltration (C406.9) – 2018
• Appendix CA Solar-Ready Zone – 2018
33
2018 IECC Commercial Changes: Highlights
![Page 33: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/33.jpg)
ASHRAE 90.1-2016 • New climate zone map (6 counties in Illinois – Calhoun,
Clark, Coles, Cumberland, Greene, Jersey: from 5A to 4A)
• New performance-based compliance path (Appendix G)
34
2018 IECC Commercial Changes: Highlights
![Page 34: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/34.jpg)
• C103.2 Information on construction documents - 20151. Insulation materials & their R-values2. Fenestration U-factors and SHGC3. Area-weighted U-factor and SHGC calculation4. Mechanical system design criteria5. Mechanical & SWH systems, equipment type, sizes, efficiencies6. Economizer description7. Equipment and system control8. Fan motor hp and controls9. Duct sealing, duct & pipe insulation & location10. Lighting fixture schedule & control narrative11. Location of daylight zones on floor plans12. Air sealing details
• C103.2.1 Building thermal envelope depictions – 2015The building thermal envelope shall be represented on the CD
35
2018 IECC Commercial Changes: Admin
![Page 35: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/35.jpg)
• C103.6 Building documentation and closeout submittal requirements: Record documents, compliance documents shall be provided to the owner within 90 days of certificate of occupancy. Also training for maintenance shall be provided.
• C105.1 Inspection: from “Construction work shall remain accessible and exposed” to “visible and accessible”
• C105.2.2 Thermal envelope inspection: from “Framing and rough-in inspection” to “Thermal envelope inspection”
36
2018 IECC Commercial Changes: Admin
![Page 36: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/36.jpg)
C202 Definition • Air barrier: added “continuous manner”• Alteration: removal of “requires a permit” language• Approved: from “Approval by the code official as a result
of investigation and tests conducted by him or her, or by nationally recognized organizations” to “Acceptable to the code official”
37
2018 IECC Commercial Changes: Admin
![Page 37: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/37.jpg)
• C201.3 Terms defined in other codesTerms that are not defined in this code but are defined in the IBC, IFC, IFGC, IMC, IPC or IRC shall have the meanings ascribe to them in those codes.
38
2018 IECC Commercial: Definition
![Page 38: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/38.jpg)
• Above-grade wall: A wall associated with the building thermal envelope that is more than 15% above grade… - 2015
• Below-grade wall: A wall associated with the basement or first story of the building that is part of the building thermal envelope that is not less than 85% below grade… - 2015
• Air curtain: A device that generates & discharges a laminar air system intended to prevent the unconditioned exterior air - 2015
39
2018 IECC Commercial Changes: Definition
![Page 39: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/39.jpg)
• More detailed requirements for controls: Change from “be capable of” to “be configured”)
40
2018 IECC Commercial Changes: Definition
![Page 40: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/40.jpg)
• C303.1.1 Building thermal envelope insulation. For roof insulation installed above the deck, R-value shall be labeled as required by the material standards specified in the Table 1508.2 of IBC
• C303.2 Installation. Materials, systems and equipment shall be installed in accordance with the manufacturer’s instruction and IBC.
41
2018 IECC Commercial General Requirements
![Page 41: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/41.jpg)
R202 Definition• Air barrier: added “continuous manner”• Alteration: removal of “requires a permit” language• Approved: from “Approval by the code official as a result
of investigation and tests conducted by him or her, or by nationally recognized organizations” to “Acceptable to the code official”
• Air-impermeable insulation: An insulation that functions as an air barrier material
42
2018 IECC Residential Changes: Admin
![Page 42: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/42.jpg)
Commercial
![Page 43: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/43.jpg)
Low-energy Building
Space conditioning peak load of <1.0 watt per square foot (<3.41 Btuh per square foot)
Exempt from the building thermal envelope requirements
44
Envelope [C402.1.1]
![Page 44: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/44.jpg)
Equipment Building
Exempt from the building thermal envelope requirements
5 criterion
Typically at the base of a radio or cellular tower for equipment
47
Envelope [C402.1.2]
![Page 45: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/45.jpg)
Envelope R-Values
Improvement in R-values for continuous insulation for insulation entirely above roof deck from R-25 continuous to R-30 continuous
48
Envelope [C402.1.3]
![Page 46: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/46.jpg)
Heated Slab Insulation
R-5 continuous insulation required under heated slabs for both commercial and residential
49
Envelope [C402.1.3]
Image courtesy of DOE
![Page 47: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/47.jpg)
Daylight Zones
New section on Daylight zones, includes both top lit and side lit daylight zones
50
Envelope [C402.4.4]
Image courtesy of International Code Council
![Page 48: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/48.jpg)
Daylight Zones
51
Envelope [C402.4.4]
![Page 49: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/49.jpg)
Air sealing
Requires sealing to allow for expansion, contraction, vibration, etc.
52
Envelope [C402.5.1.1(3)]
Photo Courtesy of Matt Risinger
![Page 50: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/50.jpg)
Equipment Efficiency
Increases minimum AFUE for furnaces from 78% to 80%
53
HVAC [C403.3.2(4)]
![Page 51: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/51.jpg)
BoilersGas fired boilers <300 kbtu cannot have a constant burning pilot light
Hot water boilers <300 kbtu must have temperature reset unless providing tankless domestic hot water production
54
HVAC [C403.3.2(5)]
![Page 52: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/52.jpg)
Heat Rejection
New section for hydronic heat pump systems using cooling towers for heat rejection
Specifically talks about automatic control of the bypass valve or turning off the circulation pump
55
HVAC [C403.4.3.3.2]
![Page 53: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/53.jpg)
Thermostat Deadband Exception
New exception for occupancies or applications requiring precision indoor temperature control as approved by the code official
56
HVAC [C403.4.1.2]
![Page 54: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/54.jpg)
Expanded VFDs
•Pumps and fans with 2hp and larger now required•Increased allowance for DDC controlled systems
57
HVAC [C403.4.4]
![Page 55: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/55.jpg)
Improved HVAC Turndown
Reduced minimum airflow from 30% to 20% of maximum
58
HVAC [C403.6.1]
Heating Cooling
Cooling & Reheat
Heating Cooling
Cooling & Reheat
2012 IECC
2018 IECC
![Page 56: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/56.jpg)
Parallel-flow VAV
New section for parallel-flow fan powered VAV air terminal control
Requires fan be off unless trying to provide heating, then fan comes on to provide heat before activating heating coil
59
HVAC [C403.6.7]
![Page 57: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/57.jpg)
Ventilation Controls
Ventilation system controls now mandatory•Demand Control Ventilation•Enclosed Parking Garage Ventilation Controls•Ventilation Air Heating Control•Energy Recovery Ventilation Systems•Kitchen Exhaust Systems•Automatic Control of HVAC Systems Serving Guestrooms
•Shutoff Dampers
60
HVAC [C403.7]
![Page 58: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/58.jpg)
Ventilation Heating Controls
New section for Ventilation air heating control
Ventilation air can not exceed 60F when majority of zones require cooling
61
HVAC [C403.7.3]
![Page 59: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/59.jpg)
Energy Recovery Requirements
Split the airflow requirements based on operating hours per year into (less than 8,000 and 8,000 or more)
62
HVAC [C403.7.4]
![Page 60: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/60.jpg)
Ventilation Energy Recovery
Provides for de minimis ventilation without requiring energy recovery
63
HVAC [C403.7.4(1)]
PERCENT (%) OF OUTDOOR AIR AT FULL DESIGN AIRFLOW RATE
10-19% 20-29% 30-39% 40-49% 50-59% 60-69% 70-79% 80%+
DESIGN SUPPLY FAN AIRFLOW RATE (cfm)
200+ 130+ 100+ 80+ 70+ 60+ 50+ 40+
Table C403.7.4(2) (excerpt)ENERGY RECOVERY REQUIREMENT [Zone 4A, 5A, 6A, 6B, 7, 8]
(Ventilation systems operating not less than 8,000 hours per year)
![Page 61: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/61.jpg)
Guestroom Automatic Controls
Automatic HVAC control now required for buildings with over 50 guestrooms
64
HVAC [C403.7.6]
Image courtesy of Wattstopper
![Page 62: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/62.jpg)
Pressure Drop Adjustment
Adds systems required to maintain a pressure differential between rooms for allowance for pressure drop adjustment
Clarifies adjustment for energy recovery devices for each air stream
65
HVAC [C403.8.1(2)]
![Page 63: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/63.jpg)
Motor Nameplates
New Exception:Fans smaller than 1 hp are not required to be listed on the drawings
66
HVAC [C403.8.2]
![Page 64: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/64.jpg)
Heat Rejection Fan Control
Changes the control scheme for fan speed control on heat rejection equipment (5hp or more total fan power)
Fan speed to vary based on leaving fluid temperature or condensing temperature and pressure of the heat rejection device (must use VFDs)
67
HVAC [C403.9.1]
![Page 65: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/65.jpg)
Refrigeration Equipment
Most sections for equipment efficiency now mandatory•Walk-in coolers/freezers, Warehouse coolers/freezers
•Walk-in coolers/freezers•Refrigerated display cases
68
HVAC [C403.10]
![Page 66: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/66.jpg)
Refrigeration Performance
Several new requirements for walk-in and reach-in coolersIncludes things such as:
automatic door closersinsulationnight coversoccupancy sensorselectronically commutated motorsefficient lighting
69
HVAC [C403.10]
![Page 67: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/67.jpg)
Walk-in Door Performance
New section for performance standards for walk-in coolers effective Jan 1, 2020Sets maximum energy consumption
70
HVAC [C403.10]
![Page 68: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/68.jpg)
HVAC Construction
Consolidated section, now mandatory•Duct and plenum insulation and sealing•Duct construction•Piping insulation
71
HVAC [C403.11]
![Page 69: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/69.jpg)
C404 Service Water Heating
![Page 70: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/70.jpg)
High Input Service Water Heating
1 million btu/h or more of service water heating equipment requires efficiency of 90% or more
Exceptions for site recovered energy or small units
73
SWH [C404.2.1]
![Page 71: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/71.jpg)
Maximum Pipe Length
Volume from heated water supply to fixture is no more than 2 oz for lavatories and ½ gallon for other fixture types
74
SWH [C404.5]
![Page 72: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/72.jpg)
Water Storage Tank Heat Traps
Heat Traps now required for hot water storage tanks, not just water heaters
75
SWH [C404.3]
![Page 73: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/73.jpg)
Pool Cover Exception
Increases threshold of site recovered or renewable energy to qualify for exception to a pool cover from 70% to 75%
76
SWH [C404.9.3]
Image courtesy of Royal Swimming Pools
![Page 74: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/74.jpg)
Residential Lighting Restriction
•Residential lighting provisions allowed ONLY for multifamily buildings
•All others use commercial lighting provisions
77
Lighting [C405.1]
![Page 75: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/75.jpg)
Luminaire Level Lighting Controls
•Allows for luminaire lighting controls to take the place of centralized controls
•Must include occupancy sensor, ambient light sensor, and wireless zoning with reprogramming capability
78
Lighting [C405.2]
Image courtesy of Cree
![Page 76: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/76.jpg)
Occupancy/Vacancy Sensor
1. Classrooms/lecture/training rooms2. Conference/meeting/multipurpose rooms3. Copy/print rooms4. Lounges/breakrooms5. Enclosed offices6. Open plan offices*7. Restrooms8. Storage rooms9. Locker rooms10.Warehouse storage areas*11.Other spaces 300 square feet of less enclosed by
floor-to-ceiling height partitions
79
Lighting [C405.2.1]
![Page 77: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/77.jpg)
Occupancy Sensor Time
Reduces the occupancy sensor time delay from 30 minutes to 20 minutes
80
Lighting [C405.2.1.1]
![Page 78: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/78.jpg)
Daylight Responsive Exception
Does not require daylight-responsive if less than 150 watts in the side lit or toplit zone
81
Lighting [C405.2.3]
![Page 79: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/79.jpg)
Daylight Responsive Exception
•Does not require daylight-responsive controls If 40% lower than wattage allowance of the daylit area
• If 50% of the building is in the daylit area, then no controls if at least 20% lower than the total allowance (50% of 40%)
82
Lighting [C405.2.3]
![Page 80: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/80.jpg)
Roof Monitors
•Provides calculation methodology for roof monitors
83
Lighting [C405.2.3.3]
![Page 81: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/81.jpg)
Daylit Zones
84
Lighting [C405.2.3.3]
![Page 82: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/82.jpg)
Lighting Controls
•No longer allows captive key systems for sleeping units
86
Lighting [C405.2.4]
![Page 83: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/83.jpg)
Increased Exterior Lighting Controls
•Daylight shutoff•Time switch control functionality•Decorative lighting shut off during non-business hours
•Lighting setback – 30% watts minimum•Exception for dwelling controlled exterior lighting
87
Lighting [C405.2.6]
![Page 84: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/84.jpg)
Track Lighting Demand Reduction
Reduces demand from 30W/ft to 8W/ft
88
Lighting [C405.3.1]
![Page 85: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/85.jpg)
Reduced Lighting Power Allowances
•Office 0.9 to 0.79 – 12% reduction•Library 1.3 to 0.78 – 40% reduction
89
Lighting [C405.3.2]
![Page 86: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/86.jpg)
Exterior Lighting Exceptions
Additional exceptions to exterior lighting calculations
•Approved lighting for safety considerations•Emergency lighting•Exit signs•Art•National flag•Water features and swimming pools•Lighting controlled from within dwelling units in compliance with R404.1
90
Lighting [C405.4.1]
![Page 87: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/87.jpg)
Exterior Lighting Allowance
•Lower power allowances for exterior lighting•~30% Lower
91
Lighting [C405.4.2]
![Page 88: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/88.jpg)
Gas Lighting Pilot
•Continuous burning pilot light for gas lighting is prohibited
92
Lighting [C405.4.3]
Image courtesy of This Old House
![Page 89: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/89.jpg)
Increased Efficiencies
Dry-type transformers & Motors
93
Power [C405.6-7]
Images courtesy of Schneider Electric Image courtesy of Baldor
![Page 90: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/90.jpg)
Additional Efficiency
•New section of additional efficiency options [Required for prescriptive path]
1. More efficient HVAC (10%)2. Reduce lighting power density (by 10%)3. Enhanced lighting controls4. On-site renewables (0.5 W/SF or 3%)5. Dedicated OA6. High efficiency service water heating7. Enhanced envelope (15%)8. Reduced air infiltration
94
Efficiency [C406]
![Page 91: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/91.jpg)
Reduced Infiltration
•New section for enhanced envelope performance•Building tested air leakage of 0.25 cfm/ft2 at 75 Pascals
•Buildings over 250,000 ft2 may be tested in sections of not less than 25% of floor area
95
Efficiency [C406.9]
![Page 92: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/92.jpg)
Electric Vehicles
•Electric vehicles excluded from energy calculation
96
Performance [C407.1]
Image courtesy of Chevrolet
![Page 93: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/93.jpg)
Renewable Energy Credit Limits
•Limits on-site renewable credits in energy model to 5%
•Allows Code Official to request documentation on renewables used for credit
97
Performance [C407.3]
Image courtesy of solartrader.ca
![Page 94: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/94.jpg)
Operations and Maintenance
Building O&M must be provided to building owner
98
Maintenance & Commissioning [C408.1.1]
Image courtesy of Berkeley
![Page 95: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/95.jpg)
Commissioning Report
Adds functional performance test procedures to the commissioning report, required to be provided to the Code Official
99
Maintenance & Commissioning [C408.2.4]
![Page 96: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/96.jpg)
CHAPTER 5Existing Buildings
![Page 97: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/97.jpg)
Change in Space Conditioning
Allows for performance alternatives for compliance•Can not exceed 110% of either allowed UA or allowed annual energy cost depending on path chosen
101
Alterations[C503.2]
![Page 98: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/98.jpg)
Excess Fenestration
•Provides exception for buildings with fenestration areas above code
102
Alterations[C503.3]
Image courtesy of Providence Daily
![Page 99: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/99.jpg)
Residential
![Page 100: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/100.jpg)
Information on Construction Documents
1. Insulation materials and their R-values2. Fenestration U-factors and SHGC3. Area-weighted U-factor and SHGC calculations4. Mechanical system design criteria5. Mechanical and service water-heating systems and equipment types, sizes, and efficiencies6. Equipment and system controls7. Duct sealing, duct and pipe insulation and location8. Air sealing details
R103.2.1 Building thermal envelope depiction: The building’s thermal envelope shall be represented on the construction documents.
104
Admin [R103.2]
![Page 101: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/101.jpg)
Inspections
1. Footing & Foundation2. Framing & rough-in3. Plumbing4. Mechanical5. Final
105
Admin [R105]
![Page 102: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/102.jpg)
Footing & Foundation Inspection
Inspections associated with footings and foundations shall verify compliance with the code as to R-value, location, thickness, depth of burial and protection of insulation as required by the code and approved plans and specifications
106
Admin [R105.2.1]
![Page 103: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/103.jpg)
Framing & Rough-in Inspection
Inspections at framing and rough-in shall be made before application of interior finish and shall verify compliance with the code as to: types of insulation and corresponding R-values and properties such as U-factor and SHGC and proper installation; and air leakage controls as required by the code; and approved plans and specifications
107
Admin [R105.2.2]
![Page 104: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/104.jpg)
Pluming Inspection
Inspections at plumbing rough-in shall verify compliance as required by the code and approved plans and specifications as to types of insulation and corresponding R-values and protection, and required controls
108
Admin [R105.2.3]
![Page 105: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/105.jpg)
Mechanical rough-in Inspection
Inspections at mechanical rough-in shall verify compliance as required by the code and approved plans and specifications as to installed HVAC equipment type and size, required controls, system insulation and corresponding R-value, system air leakage control, programmable thermostats, dampers, whole-house ventilation, and minimum fan efficiency
109
Admin [R105.2.4]
![Page 106: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/106.jpg)
Final Inspection
The building shall have a final inspection and shall not be occupied until approved. The final inspection shall include verification of the installation of all required building systems, equipment and controls and their proper operation and the required number of high-efficacy lamps and fixtures
110
Admin [R105.2.5]
![Page 107: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/107.jpg)
Residential Certificate
Permanent certificate shall be completed by the builder or other approved party and posted …•Predominant R-values of insulation•U-factors of fenestration•SHGC of fenestration•Results for components covering largest areas where multiples occur
•Results from duct/envelope leakage tests•Types & efficiencies of heating, cooling, and service water heating equipment
111
General [R401.3]
![Page 108: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/108.jpg)
Residential Certificate
112
General [R401.3]
![Page 109: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/109.jpg)
Log Homes
Log homes designed in accordance with ICC 400 exempted from the thermal envelope requirements
113
Envelope [R402.1]
Image courtesy of Log Home Living
![Page 110: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/110.jpg)
Window U-Factors
Modest improvement in window U-factors
114
Envelope [R402.1.2]
Climate Zone
2012 U-Factor
2018 U-Factor
4 U-0.35 U-0.325 U-0.32 U-0.30
![Page 111: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/111.jpg)
Reduced Insulation
Provides allowance for reduced insulation in ceilings without attic spaces, but insulation must extend over the top plate
115
Envelope [R402.2.2]
Image courtesy of Pacific Northwest National Labs
![Page 112: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/112.jpg)
Access Doors Exception
New exception to allow vertical doors to meet the fenestration requirements in Table R402.1.2
116
Envelope [R402.2.4]
![Page 113: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/113.jpg)
Partial Structural Sheathing
New provision to allow reduced insulation where structural sheathing is used to provide consistent total sheathing thickness
117
Envelope [R402.2.7]
Image courtesy of International Code Council
![Page 114: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/114.jpg)
Floor Insulation Exception
New exception to allow Alternative insulation methods using continuous insulation or insulating the top side of the sheathing
118
Envelope [R402.2.8]
Image courtesy of International Code Council
![Page 115: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/115.jpg)
Sunroom Insulation
Sunrooms enclosing conditioned space shall meet the insulation requirements of this codeException: Sunrooms with thermal isolation and enclosing conditioned space
Min. ceiling insulation R-19 for zone 4 and R-24 for zone 5Min. exterior wall insulation R-13
119
Envelope [R402.2.13]
![Page 116: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/116.jpg)
Sunroom Fenestration
Sunrooms enclosing conditioned space shall meet the fenestration requirements of this codeException: Sunrooms with thermal isolation and enclosing conditioned space
Max U-factor of 0.45 for windowsMax U-factor of 0.70 for skylights
120
Envelope [R402.3.5]
![Page 117: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/117.jpg)
Air Barrier & Insulation
Table R402.4.1.1 can be very usefulCovers many errors in installation
125
Envelope [R402.4.1.1]
![Page 118: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/118.jpg)
Ductwork Testing
Provides exception for testing ERV and HRV ductwork from testing
126
SYSTEMS[R403.3.3]
Image courtesy of Panasonic
![Page 119: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/119.jpg)
Ducts Buried in Ceiling Insulation
Provides allowance for duct insulation in buried duct work (for simulated energy performance analysis)
127
SYSTEMS [R403.3.6]
![Page 120: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/120.jpg)
Hot Water Mainenance Systems
Provides provisions for heat maintenance systems including circulating or heat trace
128
SYSTEMS[R403.5.1]
![Page 121: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/121.jpg)
Drain Water Heat Recovery
Drain water heat recover units shall comply with CSA B55.2.
129
SYSTEMS [R403.5.4]
![Page 122: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/122.jpg)
HRV / ERV Fan Efficiency
•Minimum fan efficiency of 1.2 cfm/w is added for Heat Recovery Ventilator and Energy Recovery Ventilator for whole house mechanical ventilation system.
130
SYSTEMS [R403.6.1]
Image courtesy of Calcs Plus
![Page 123: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/123.jpg)
Ducts in Conditioned Space
Provides criteria to determine if ducts are inside conditioned space or not.
•Completely inside air barrier OR•Buried in the ceiling insulation AND
•Air handler within air & thermal barrier•Duct leakage <1.5 cfm per 100 sf•Full depth insulation above duct
131
SYSTEMS [R403.3.7]
![Page 124: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/124.jpg)
Equipment Sizing
Heating and cooling equipment shall be sized in accordance with ACCA Manual S based on building loads calculated in accordance with ACCA Manual J or other approved heating and cooling calculation methodologies.
132
SYSTEMS [R403.7]
![Page 125: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/125.jpg)
Pool Cover Exception
Increases minimum renewable or site-recovered energy for pools from 70% to 75% to not need a pool cover
133
SYSTEMS[R403.10.3]
Image courtesy of Royal Swimming Pools
![Page 126: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/126.jpg)
High Efficiency Lighting
• Increases high efficiency lighting to 90% from 75%•Eliminates the low-voltage exception
134
Lighting [R404.1]
![Page 127: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/127.jpg)
Ventilation
Ventilation system must be included in energy model
135
Performance[R405.1]
Image courtesy of Panasonic
![Page 128: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/128.jpg)
Multifamily Unit Modeling
Batch sampling is allowed for stacked multifamily units
136
Performance[R405.4.2]
![Page 129: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/129.jpg)
Reference Model
Includes mechanical ventilation in the reference design
137
Performance [R405.5.2(1)]
Image courtesy of Calcs Plus
![Page 130: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/130.jpg)
Energy Rating Reference
•Changes reference design from IECC 2006 to RESNET/ICC 301
•Clarifies electric vehicle charging is excluded from rating
138
ERI [R406.3]
Image courtesy of Chevrolet
![Page 131: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/131.jpg)
Energy Rating Index
• Increase of Max. ERI score
139
ERI [R406.4]
Climate Zone
2018 ERI Score
4 625 61
Image courtesy of Energy IQ
![Page 132: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/132.jpg)
Energy Rating Software
•Removes calculation software listing
140
ERI [R406.7]
![Page 133: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/133.jpg)
CHAPTER 5Existing Buildings
![Page 134: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/134.jpg)
Fenestration Compliance
•Allows for weighted area average for multiple fenestrations for compliance
142
Alterations [R503.1.1.1]
Image courtesy of Providence Daily
![Page 135: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/135.jpg)
Residential air leakage decreasing to 4 ACH
For low-rise multifamily buildings, dwelling units shall be tested and verified as having a leakage rate of not exceeding 0.25 cfm/ft2 of enclosure area (all six sides of the dwelling unit) … Testing shall be conducted with an unguarded blower door at a pressure of 50 Pa. Where required by the code official, testing shall be conducted by an approved third party…
144
IL Code Amendment Proposals
![Page 136: 2018 IECC Updates from 2012 & Building Codes](https://reader030.vdocuments.us/reader030/viewer/2022020917/61c1a3526dda792e2319fc33/html5/thumbnails/136.jpg)
… For buildings with more than 7 units, a sampling protocol is allowed by an approved third party. The sampling protocol requires the first 7 units to be tested without any failures. Upon successful testing of those initial 7 units, remaining units can be sampled at a rate of 1 in 7. If any sample unit fails compliance with the maximum allowable air leakage rate, two additional units in the same sample set must be tested. If additional failures occur, all units in the sample set must be tested. In addition, all units in the next sample set bust be tested for compliance before sample of further units can be continued.
145
IL Code Amendment Proposals cont.