2018 general rate case rebuttal testimony results of ... · selection process/criteria ... • key...
TRANSCRIPT
Application No.: A.16-09-001 Exhibit No.: SCE-25, Vol. 03 Witnesses: B. Chiu
J. Duran C. Fanous A. Stewart R. Worden
(U 338-E)
2018 General Rate Case Rebuttal Testimony
Results of Operations Volume 3 – Rebuttal to Various Ratemaking Proposals
Before the
Public Utilities Commission of the State of California
Rosemead, California
June 16, 2017
A 2
2nd ERRATA
Appendix E
SPIDACalc Selection Process
Southern California Edison2018 GRC A.16-09-001
DATA REQUEST SET TURN-SCE-022
To: TURNPrepared by: Chris Tang
Title: Project AnalystDated: 12/21/2016
Received Date: 12/21/2016
Question 17.a:
17. In SCE-02, Vol. 9, at pages 15-16, SCE describes how pole replacement projects at various “gates” of the pole replacement process were treated in the queue for reassessment with the updated SPIDACalc version.
a. For each “gate” as described in Table II-6 of the testimony, please provide the number of poles that were at that “gate” as of September 1, 2015.
Response to Question 17.a:
Below is a table that provides the number of poles that were at each gate as of September 1, 2015.
E-1
Southern California Edison2018 GRC A.16-09-001
DATA REQUEST SET TURN-SCE-022
To: TURNPrepared by: Chris Tang
Title: Project AnalystDated: 12/21/2016
Received Date: 12/21/2016
Question 17.b:
17. In SCE-02, Vol. 9, at pages 15-16, SCE describes how pole replacement projects at various “gates” of the pole replacement process were treated in the queue for reassessment with the updated SPIDACalc version.
b. For each “gate” as described in Table II-6 of the testimony, of the number of poles at the gate as of September 1, 2015, please provide the number of poles that were reassessed with the updated SPIDACalc version after September 1, 2015.
Response to Question 17.b:
Below is a table that provides the number of poles, by gate, that were re-assessed with the updated SPIDACalc version after September 1, 2015. Please note that the number of reassessed poles in Gate 1 is less than the number of poles in Gate 1 shown in the response to TURN-SCE-022 Q17a. This is because poles were removed from scope and no longer needed to be replaced. As a result, they did not require reassessment.
E-2
Southern California Edison2018 GRC A.16-09-001
DATA REQUEST SET TURN-SCE-022
To: TURNPrepared by: Debra Brooks
Title: Project ManagerDated: 12/21/2016
Received Date: 12/21/2016
Question 10.e:
10. In SCE-02, Vol. 9, at page 12, SCE states that through an RFP process it determined that SPIDACalc provided the best balance among accuracy, simplicity and conservatism.
e. Please identify by name and title the highest-ranking member of SCE’s management and executive teams that authorized the selection of the SPIDACalc software package. Please also provide all documentation provided to that person for his or her review prior to such authorization.
Response to Question 10.e:
SCE objects to the question to the extent that is is overbroad, as it requests "all documents provided to that person for his or her review prior to such authorization." Attached are the documents presented to management at the final stage of the evaluation process. The following is the list of names and title at the time of the decision of the highest-ranking member of SCE's management and executive teams that authorized the selection of the SPIDA Calc software package: Gregg Kludjian, Director Resource Planning and Performance Management (RPPM); Nestor Martinez, Director Central Design & Field Accounting (CD&FA); Tim Boucher, Acting Director Business Process and Technology Integration (BP&TI); Paul Joseph, Principal Manager BP&TI, Robert Francis LeMoine, Principal Manager T&D Maintenance and Inspection; James Harvey, Manager Transmission Design.
CONFIDENTIAL ATTACHMENTS
Attachments Marked Confidential in Accordance with D.16-08-024 – Basis for Confidentiality In Accompanying Confidentiality Declaration
Confidentiality_Declaration_TURN-SCE-022_10e.pdfConfidentiality_Declaration_TURN-SCE-022_10e.pdf
CRP Report_Out_Final_Confidential.pptxCRP Report_Out_Final_Confidential.pptx GapAnalysis_CRP_100212.xlsxGapAnalysis_CRP_100212.xlsx
Confidentialmaterial has beenredacted
E-3
Meeting Minutes_ PoLAR - CRP Report out Deck.emlMeeting Minutes_ PoLAR - CRP Report out Deck.eml
E-4.1
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Oct
. 4, 2
012
Pol
e Lo
adin
g A
pplic
atio
n R
epla
cem
ent
(PoL
AR
)
CR
P R
epor
t O
ut
Tim
eshe
et E
ntry
-Ti
tle
Con
fiden
tial
mat
eria
lin
the
orig
inal
resp
onse
has
been
reda
cted
E-4.1
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
RFP
Eva
luat
ion
Pro
cess
–St
ages
RFP
PR
OC
ESS
WRI
TTEN
RES
PON
SEPR
OO
F O
F CO
NCE
PTCO
NFE
REN
CE R
OO
M
PILO
T
Num
ber
of V
endo
rs4
31
Inpu
t D
ocum
ents
•D
etai
led
Busi
ness
Re
quire
men
ts•
Ente
rpris
e Fo
cus
•Cr
itica
l req
uire
men
ts u
sed
for
min
imum
thr
esho
ld
•D
etai
led
Scen
ario
s fo
r ea
ch
Div
isio
n (D
ist.
, Tra
ns, E
CS,
Engi
neer
ing)
•Ex
pect
ed O
utco
mes
•D
etai
led
Busi
ness
Re
quire
men
ts
•D
etai
led
scrip
ts
•D
etai
led
busi
ness
req
uire
men
ts•
Det
aile
d Ex
pect
ed O
utco
mes
(�
400)
•SC
E da
ta
Sele
ctio
n Pr
oces
s/Cr
iteria
•Ve
ndor
s el
imin
ated
if “
Criti
cal”
re
quire
men
ts n
ot m
et•
Scor
ing
vend
or w
ritte
n re
spon
ses
•Sc
orin
g ve
ndor
s ba
sed
on
vend
or p
erfo
rman
ce in
de
mos
to
Eval
uatio
n Te
am
•Co
nfig
ure
Vend
or p
rodu
ct o
n SC
E ha
rdw
are
•Te
st s
crip
ts t
o ve
rify
expe
cted
ou
tcom
es a
re m
et•
Conf
irm p
rodu
ct s
uita
bilit
y to
SCE
an
d ID
gap
s be
twee
n pr
oduc
t an
d SC
E ne
eds
•Re
com
men
d ga
p cl
osur
e st
rate
gy•
Reco
mm
end
vend
or p
rodu
ct
Resu
lt
•To
p tw
o ve
ndor
s th
e m
eet
criti
cal r
equi
rem
ents
mov
e on
to
Pro
of o
f Con
cept
•To
p ve
ndor
mov
es o
n to
Co
nfer
ence
Roo
m P
ilot
•Te
am m
akes
fin
al
reco
mm
enda
tions
to
exec
utiv
es
Bus
R
eqs
(80%
)
Tech
Req
(15%
)
Inte
grat
ion
(5%
)
Bus R
eqs (
60%
)
Tech
Req
(20%
)
Proj
Appr
oach
(10%
)
Cost
(10%
)
Com
mer
cial
(15%
)
Pro
ject
A
ppro
ach
(5%
)
Bus
Req
s (5
0%)
Tech
Req
(2
0%)
Cos
t of
Ow
ners
hip
(30%
)
Com
mer
cial
(35%
)(1
5%)
E-4.2
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P S
tatu
s an
d D
eliv
erab
les
•Po
LAR
CRP
Stat
us–
CRP
with
Spi
daSo
ftw
are
conc
lude
d on
Sep
t. 2
6–
Core
Tea
m t
o ex
ecut
ed 1
7 U
se C
ase
scen
ario
s w
ith S
CE d
ata,
incl
udin
g co
mpl
ex
and
infr
eque
nt p
ole
load
cas
es
–Ad
ditio
nal B
usin
ess
Reso
urce
s ex
ecut
ed a
sub
set
of 1
0 U
se C
ase
scen
ario
s,
sim
ulat
ing
com
mon
SCE
pol
e lo
adin
g ca
ses
–En
gine
erin
g SM
Es r
evie
wed
all
outp
uts
and
calc
ulat
ions
–IT
Tea
m c
ondu
cted
tec
hnic
al t
estin
g•
Key
Del
iver
able
s of
CRP
–Co
nfirm
atio
n of
the
pro
duct
fun
ctio
nalit
y an
d its
app
licat
ion
for
SCE’
s ne
eds
–Pl
an t
o ad
dres
s an
y ga
ps b
etw
een
the
desi
red
stat
e an
d th
e ve
ndor
pro
duct
fu
nctio
nalit
y–
Iden
tifie
d op
port
uniti
es t
hat
exis
t w
ithin
the
pro
duct
for
impr
ovin
g op
erat
ions
–Ch
ange
Im
pact
Ass
essm
ent
and
Trai
ning
rec
omm
enda
tions
•Re
com
men
datio
n–
Soft
war
e Ac
cept
ance
(G
aps
and
reso
lutio
ns)
–U
ser
Asse
ssm
ent
3
E-4.3
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Soft
war
e A
ccep
tabi
lity
Eval
uat
ion
•17
scr
ipts
exe
cute
d •
Expe
cted
Out
com
es w
ere
clas
sifie
d as
“Pa
ss”
or “
Fail”
–Al
l ste
ps p
asse
d w
ith t
he e
xcep
tion
of a
kno
wn
syst
em li
mita
tion
whi
ch
was
par
t of
one
of
the
scen
ario
s
•38
Gap
s w
ere
iden
tifie
d, a
ssig
ned
a se
verit
y, a
nd a
ssig
ned
one
of
the
follo
win
g m
itiga
tions
:–
The
gap
can
be o
verc
ome
by a
rec
onfig
urat
ion
of t
he t
ool
–Th
e ga
p ca
n be
ove
rcom
e by
an
acce
ptab
le p
roce
ss/s
yste
m w
ork
arou
nd–
The
gap
can
be o
verc
ome
by d
evel
opin
g th
e fu
nctio
nalit
y in
ano
ther
ex
istin
g SC
E sy
stem
oth
er t
han
the
vend
or p
rodu
ct–
The
gap
can
be o
verc
ome
by c
usto
miz
ing
the
vend
or p
rodu
ct–
The
gap
has
been
clo
sed
due
to u
ser
erro
r/m
is-u
nder
stan
ding
4
E-4.4
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Bus
ines
sU
se C
ase
Scen
ario
s
5
PoL
AR
CR
P U
SE C
ASE
MA
TRIX
UC
Ind
exB
us
Use
Cas
e Ti
tle
PL
1T&
DPe
rfor
min
g a
Pole
Loa
d di
scon
nect
fro
m t
he n
etw
ork,
the
n si
gnin
g on
to t
he
netw
ork,
man
ipul
atin
g, s
avin
g to
the
net
wor
k, a
nd p
rintin
g re
port
s.
PL
2D
&EC
S
Perf
orm
ing
a Po
le L
oad
Conn
ecte
d to
the
net
wor
k, p
erfo
rmin
g a
curr
ent
and
prop
osed
pol
e lo
ad c
ompa
rison
, w
ith S
CE,
(alte
rnat
ive
flow
: EC
S),
& 3
rd
Part
y fa
cilit
ies.
PL
3T&
DPe
rfor
min
g a
Pole
Loa
d w
ith S
CE F
acili
ties
incl
udin
g da
mag
e en
terie
s an
d ve
rifyi
ng p
ole
mea
sure
men
t in
form
atio
n an
d AN
SI m
inim
ums.
PL
4Tr
ans
Perf
orm
ing
a Po
le L
oad
with
mul
tiple
Guy
s an
d Q
ueen
spos
ts a
nd s
aves
/prin
ts
repo
rts
(alt.
flo
w:
split
guy
/leve
l) (t
ake
into
acc
ount
var
iabl
e gu
ying
sc
enar
ios)
PL
5D
ist
Perf
orm
ing
a Po
le L
oad
with
SCE
, (a
ltern
ativ
e flo
w:
ECS)
, an
d 3r
d pa
rty
atta
chm
ents
incl
udin
g gu
ying
tha
t ba
cks
up b
oth
SCE
and
3rd
part
y at
tach
men
ts.
PL
6T&
DPe
rfor
min
g a
Pole
load
of
a co
mpo
site
/fib
ergl
ass/
light
dut
y st
eel p
ole
with
at
tach
men
ts a
nd g
uyin
g .
Tran
smis
sion
Alte
rnat
e flo
w s
peci
fic t
o LD
SP.
PL
7T&
DPe
rfor
min
g a
Pole
load
of
a po
le w
ith a
tap
line
bac
ked
up b
y a
guy
stub
. Al
tern
ate
flow
for
Tra
nsm
issi
on t
o be
incl
uded
.
PL
8D
ist
EX 1
9738
45E
Que
ry a
nd P
ole
Load
of
an e
xist
ing
pole
tha
t is
a B
i-Se
ctor
/Dea
dend
Com
bo.
PL
9T&
DPe
rfor
min
g a
Pole
load
usi
ng a
n XM
L (o
r ot
her
file
type
) to
mim
ic in
tegr
atio
n w
ith o
ther
sys
tem
s.
PL
10T&
DPe
rfor
min
g a
Pole
load
and
sha
ring
it w
ith a
noth
er u
ser
usin
g ap
plic
atio
n co
ntro
l pro
cess
es.
PL
11Tr
ans
Perf
orm
ing
a Po
le lo
ad o
n a
line
of p
oles
. U
se o
f te
mpl
ates
or
copy
/pas
te
func
.
PL
12T&
DPe
rfor
min
g a
pole
load
tak
ing
into
acc
ount
ele
vatio
n ch
ange
s of
roc
k an
chor
s.P
L 13
T&D
Perf
orm
ing
a po
le lo
ad o
n a
corn
er p
ole
with
a 3
wire
circ
uit.
PL
14T&
DPe
rfor
min
g a
Pole
load
on
a de
aden
d po
le w
ith a
pus
h br
ace.
PL
15D
ist
EX 1
1249
346E
Que
ry a
nd P
ole
Load
of
an e
xist
ing
pole
tha
t is
dea
dend
gu
yed.
PL
16EC
SIn
stal
latio
n of
ECS
fac
ilitie
s on
an
exis
ting
pole
PL
17EC
SPo
le lo
ad o
f an
exi
stin
g EC
S po
le
E-4.5
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Tech
nica
l Eva
luat
ion 6
IDC
ateg
ory
Nam
eC
rite
ria
1In
tegr
atio
nLi
cens
e Ac
tivat
ion
The
test
for
this
scen
ario
will
beco
nsid
ered
succ
essf
ulw
hen
the
licen
selis
ton
the
licen
sese
rver
refle
cts
the
conf
igur
atio
nof
the
licen
seke
ysas
desi
red.
2In
tegr
atio
nLi
cens
e Se
rver
In
tegr
atio
nTh
ete
stfo
rth
issc
enar
iow
illbe
cons
ider
edsu
cces
sful
whe
nth
ecl
ient
mac
hine
sha
vere
ceiv
edth
eco
rrec
tlic
ense
keys
.3
Secu
rity
Use
rAu
then
ticat
ion
The
test
for
this
scen
ario
will
beco
nsid
ered
succ
essf
ulw
hen:
1)Th
eto
olau
then
ticat
esa
user
that
has
prov
ided
valid
iden
tific
atio
n;
2)Th
eto
oldo
esno
tau
then
ticat
ea
user
that
has
prov
ided
inva
lidid
entif
icat
ion.
4Se
curit
yU
ser
Auth
oriz
atio
nTh
ete
stfo
rth
issc
enar
iow
illbe
cons
ider
edsu
cces
sful
whe
n:
1)Th
eto
olgr
ants
the
prop
erpe
rmis
sion
sto
anau
then
ticat
edus
erba
sed
onth
eus
ergr
oup(
s)th
eau
then
ticat
edus
eris
assi
gned
to;
2)Th
eto
olgr
ants
aus
erpe
rmis
sion
sas
pres
crib
edby
the
vend
orw
hen
the
user
has
2ro
les
that
have
conf
lictin
grig
hts.
5Co
nfig
urab
ility
Clie
nt D
ata
Conf
igur
atio
nTh
ete
stfo
rth
issc
enar
iow
illbe
cons
ider
edsu
cces
sful
whe
nth
eto
olau
tom
atic
ally
sync
hron
izes
the
clie
ntda
tafil
eson
the
clie
ntm
achi
nes
with
the
activ
ecl
ient
data
files
trac
ked
byth
elic
ense
serv
er.
E-4.6
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Gap
Sev
erit
y
•Th
roug
hout
scr
ipt
exec
utio
n, id
entif
ied
issu
es
wer
e as
sign
ed a
sev
erity
bas
ed o
n th
e fo
llow
ing
clas
sific
atio
n:
7
Issu
e Se
veri
ty
Seve
rity
Des
crip
tion
1 - A
pplic
atio
n te
rmin
ates
abn
orm
ally
This
is w
hen
the
appl
icat
ion
cras
hes
or s
huts
do
wn
or ju
st h
angs
with
no
resp
onse
.
2 - F
ails
to m
eet c
ritic
al B
usin
ess
Req
uire
men
t
Tthe
app
licat
ion
does
not
mee
t a c
ritic
al
busi
ness
requ
irem
ent a
nd th
ere
is n
o w
orka
roun
d an
d w
e ca
nnot
del
iver
the
syst
em w
ithou
t thi
s re
quire
men
t.
3 - F
ails
to m
eet n
on-c
ritic
al B
usin
ess
Req
uire
men
t (w
orka
roun
d ex
ists
)
Whe
n th
e ap
plic
atio
n do
es n
ot m
eet a
bu
sine
ss re
quire
men
t and
ther
e is
a
wor
karo
und
or w
e co
uld
deliv
er th
e sy
stem
w
ithou
t thi
s re
quire
men
t.
4 - C
osm
etic
def
ect
Thes
e ar
e pr
oble
ms
with
how
the
data
is
bein
g di
spla
yed
or th
e la
yout
of t
he w
indo
w
or re
port
that
is c
osm
etic
in n
atur
e.
E-4.7
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P G
ap A
naly
sis
•38
Gap
s w
ere
iden
tifie
d by
the
tes
ters
–Se
v1:
0
–Se
v2:
15
–Se
v3:
6
–Se
v4:
5
–Cl
osed
: 1
2
•Ad
ditio
nal o
ppor
tuni
ties
foun
d in
the
fol
low
ing
area
s:–
Web
bas
ed c
olla
bora
tion
with
join
t ut
ilitie
s an
d on
-line
form
aut
omat
ion
–Ph
otom
etric
Ana
lytic
s–
Spid
aSi
lk p
rodu
ct t
o re
plac
e Sa
g 10
•Bu
sine
ss R
equi
rem
ent
docu
men
t ha
s be
en u
pdat
ed b
ased
on
gap
anal
ysis
res
ults
•Al
l kno
wn
gaps
in t
he S
pida
Apps
will
be
inco
rpor
ated
into
Spi
daCO
TS–
Curr
ently
, the
onl
y id
entif
ied
cust
omiz
atio
n fo
r Po
LAR
will
be
in t
he a
rea
of in
tegr
atio
n w
ith o
ther
SCE
app
licat
ions
and
inco
rpor
atio
n in
to S
CE
envi
ronm
ent.
8
E-4.8
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Use
r Ev
alu
atio
n
•Ea
ch s
crip
t w
as a
lso
asse
ssed
in t
he f
ollo
win
g ar
eas
and
rate
d as
“Ex
celle
nt,”
“G
ood,
” “F
air,
” or
“Po
or”:
–Ea
se o
f N
avig
atio
n–
Spee
d of
App
licat
ion
–Ab
ility
to
ente
r ne
eded
info
rmat
ion
–La
yout
of
Repo
rt–
Sequ
ence
of
even
ts
•W
ith f
ew e
xcep
tions
, all
item
s co
nsis
tent
ly s
core
d go
od
or e
xcel
lent
:–
Exce
ptio
ns d
ue p
artic
ular
dev
ice
conf
igur
atio
ns in
the
tra
inin
g ro
om.
9
E-4.9
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P G
aps
(Ope
n Se
v. 2
/3)
10
Cate
gory
Desc
riptio
nSe
vD
ispo
sitio
nFi
le�R
eten
tion
Rete
ntio
n�of
�eve
ry�la
yer�i
n�th
e�pr
ojec
t�file
.2
New
�BR�
Mea
sure
men
ts
Nee
d�ab
ility
�to�d
eter
min
e�po
le�d
iam
eter
�with
out�a
ddin
g�th
roug
h�bo
lt�as
�dam
age.
�Th
is�co
uld�
be�in
�the�
form
�of�a
�tool
�tip�
as�th
e�us
er�h
over
s�ove
r�a�p
oint
�the�
pole
�OR�
to�h
ave�
this�
info
rmat
ion�
disp
laye
d�so
mew
here
�in�th
e�U
I�bas
ed�o
n�a�
"use
r�id
entif
ied�
clic
k"2
New
�BR�
Mat
eria
lAn
chor
s�and
�guy
s�to�
be�b
undl
ed�a
nd�p
lace
d�to
geth
er�b
ased
�on�
CU�k
it.3
New
�BR�
Usa
bilit
y/M
at.
Mak
e�W
ire/G
uy�S
elec
tion�
Avai
labl
e/N
ot�A
vaila
ble�
on�a
�per
�ow
ner�b
asis�
in�th
e�M
ater
ial�s
ectio
n.3
New
�BR�
Mod
elin
gO
ffset
�for�e
quip
men
t�nee
ds�to
�be�
man
ually
�adj
uste
d�(+
�or��
).�Fr
ame�
of�R
e fer
ence
�sh
ould
n't�s
hift
�whe
n�cr
oss�a
rm�is
�mov
ed.
2N
ew�B
R�M
ater
ial
Equi
pmen
t�nee
ds�to
�be�
to�a
ttac
hed�
to�e
quip
men
t�not
�just
�to�th
e�po
le2
New
�BR�
Usa
bilit
yAb
ility
�to�a
dd�a
�dou
ble�
cros
s�arm
�end
�bra
cket
�with
�att
ache
d�in
sula
tor
2N
ew�B
R�
Usa
bilit
yAb
ility
�to�m
odify
�tens
ions
�on�
the�
fron
t�end
�as�o
ppos
ed�to
�the�
equi
pmen
t�pr
oper
ties�
by�e
n ter
ing�
spec
ific�
tens
ion�
valu
e.2
New
�BR�
Mea
sure
men
tsAb
ility
�to�a
dd�d
ecim
al�m
easu
rem
ents
�to�a
ll�fie
lds
2N
ew�B
R�
Mea
sure
men
tsSP
IDA�
need
s�to
�allo
w�th
e�us
er�to
�inpu
t�and
/or�i
dent
ify�d
etai
led�
Pole
/Pus
h�Br
ace�
info
rmat
ion�
such
�as�P
ole�
Clas
s/He
ight
/Set
ting�
Dept
h.�
2N
ew�B
R�
E-4.10
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R11
Cate
gory
Desc
riptio
nSe
vDi
spos
ition
Mea
sure
men
tsSP
IDA�
to�a
pply
�all�
mea
sure
men
ts�fo
r�the
�pus
h/po
le�b
race
�as�p
art�o
f�pus
h/po
le�b
race
�ana
lysis
2N
ew�B
R�
Usa
bilit
y
For�t
rans
miss
ion�
rela
ted�
scen
ario
s�in�
whi
ch�c
ondu
ctor
�is�st
rung
�ont
o�of
fset
�insu
lato
rs�(e
asts
ide�
of�p
ole�
1�w
ests
ide�
of�p
ole�
2),�a
�seco
ndar
y�po
le�is
�requ
ired�
for�t
he�p
ole�
back
�and
�pol
e�ah
ead�
to�
prop
erly
�acc
ount
�for�a
ngle
s/te
nsio
ns.�W
ould
�like
�Spi
da�to
�allo
w�fo
r�mod
elin
g�an
d�an
alys
is�of
�th
ese�
scen
ario
s2
New
�BR�
Usa
bilit
y
Whe
n�tr
ansf
errin
g�lo
ad�fo
r�a�sp
an�g
uy�fr
om�a
noth
er�p
ole,
�the�
span
�guy
�ang
le�sh
ows�
a�di
ffere
nt�
dire
ctio
n,�th
ough
�the�
seco
ndar
y�po
le�is
�bei
ng�m
oved
�to�a
�diff
eren
t�pla
nar�a
ngle
.�SPI
DA�n
eeds
�to
�show
�the�
dire
ctio
n�of
�the�
span
�guy
.��SP
IDA�
shou
ld�sh
ow�th
e�po
int�l
oad�
dire
ctio
n�in
�the�
top/
side�
view
.2
New
�BR�
Usa
bilit
yTe
nsio
ns�fo
r�spa
n�gu
y�be
twee
n�st
ub�a
nd�m
aste
r�pol
e�do
�not
�mat
ch�te
nsio
ns�o
f�spa
n�gu
y�be
twee
n�tw
o�lin
e�po
les
2Po
ssib
le�
defe
ctU
sabi
lity
Nee
d�to
�show
�offs
et�o
f�eac
h�w
ire�o
n�th
e�w
ire�ta
b�in
�the�
tab l
e�vi
ew3
New
�BR�
Usa
bilit
yW
hen�
usin
g�fr
om�p
revi
ous�o
r�to�
next
,�SPI
DA�re
sets
�arm
�ang
les.
�Nee
d�to
�reta
in�a
ngle
�pr
oper
ties.
3N
ew�B
R�
Usa
bilit
y
Whe
n�lo
adin
g�sp
an�g
uys�u
sing�
"fro
m�p
roje
ct"�s
peci
fied�
as�a
n�"o
ther
"�spa
n�gu
ys�a
s�bei
ng�
brou
ght�i
n�as
�an�
inco
rrec
t�att
achm
ent�a
nd�p
reve
nts�t
he�p
ole�
from
�bei
ng�a
naly
zed.
�SCE
�doe
sn't�
wan
t�cro
ss�a
rm�to
�bise
ct�li
ne�a
ngle
.2
New
�BR�
Usa
bilit
yW
hen�
chan
ging
�som
ethi
ng�o
n�th
e�lin
e�po
le�a
nd�a
naly
zing,
�the�
stub
�pol
e�at
tach
men
t�qua
litie
s�do
�not
�cha
nge�
alon
g�w
ith�it
.�3
New
�BR�
Usa
bilit
yIf�
a�po
int�l
oad�
is�be
ing�
brou
ght�i
n�fr
om�a
n�at
tach
men
t�hig
her�t
han�
the�
load
�rece
ivin
g�po
le,�
does
�not
�mod
el�p
rope
rly,�m
ust�u
se�ta
ble�
view
�to�a
djus
t�hei
ghts
.3
Poss
ible
�de
fect
SPID
AMin
�Joi
nt�
Pole
�Disc
ussio
nSP
IDAM
in�to
�inte
grat
e�sp
ecifi
c�ID
R�re
late
d�fo
rms�a
s�par
t�of�t
he�ID
R�pr
oces
s�an
d�ro
ute/
popu
late
�them
�bas
ed�o
n�w
ork�
flow
s/co
ntro
ls�id
entif
ied�
by�S
CE.
2N
ew�B
R�
SPID
AMin
�Joi
nt�
Pole
�Disc
ussio
n
Inte
grat
e�E1
P2�w
orkf
low
�spec
ific�
to�3
rdpa
rty�
inad
equa
cy�v
iola
tions
.�Cur
rent
ly�a
n�el
ectr
onic
�at
tach
men
t�in�
the�
notif
icat
ion�
that
�nee
ds�to
�be�
sepa
rate
d�to
�pro
vide
�onl
y�sp
ecifi
c�in
form
atio
n�to
�the�
mem
ber�u
tility
�thi
s�att
achm
ent�(
WLE
A�ou
tput
)�mus
t�be�
sepa
rate
d.2
New
�BR�
E-4.11
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Feed
back
fro
m B
usin
ess
Expe
rts
Base
d on
obs
erva
tions
at
CRP
and
thei
r in
tera
ctio
ns w
ith t
he C
OTS
App
licat
ion:
•D
ata
entr
y up
fron
t m
ay t
ake
a bi
t m
ore
time,
but
new
fun
ctio
ns s
uch
as
“Cop
y/Pa
ste”
and
tem
plat
e ba
sed
pole
mod
els
will
like
ly s
ave
time
over
all.
•D
efin
itely
wor
th t
he in
vest
men
t.
A lo
t of
asp
ects
will
mak
e ou
r jo
bs e
asie
r:–
Copy
fea
ture
s re
duce
s ne
ed t
o cr
eate
a n
ew p
ole
mod
el e
ach
time
–Vi
sual
izat
ion
aids
in a
bilit
y to
con
stru
ct m
odel
•Sp
ida
Calc
is d
efin
itely
an
impr
ovem
ent
over
the
cur
rent
too
l. I
t w
ill b
e m
ore
accu
rate
and
yie
ld b
ette
r re
sults
.•
Dur
ing
CRP,
Spi
daCa
lcw
as v
ery
stab
le.
Muc
h m
ore
so t
han
othe
r pr
oduc
ts
have
bee
n at
thi
s st
age
in t
he p
roce
ss h
isto
rical
ly.
12
E-4.12
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Ove
rall
Sum
mar
y
•CR
P w
as s
ucce
ssfu
lly e
xecu
ted
ahea
d of
sch
edul
e•
Furt
her
eval
uatio
n of
Spi
daCa
lcis
con
tinui
ng b
y se
vera
l of
the
tes
ters
–Sp
ida
Calc
has
been
load
ed o
n th
eir
devi
ces
–Co
nduc
ting
eval
uatio
n of
abi
lity
to im
plem
ent
Spid
aCa
lcCO
TS A
s-Is
–
Pote
ntia
lly c
ould
rep
lace
Loa
d Es
timat
or a
s ea
rly a
s Q
1, 2
013
•Te
chni
cal F
easi
bilit
y an
d Fi
nanc
ial P
rude
ncy
unde
r co
nsid
erat
ion
–Bu
sine
ss T
este
rs a
nd E
ngin
eerin
g ar
e st
rong
ly in
su
ppor
t of
thi
s ap
proa
ch
13
E-4.13
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Team
Rec
omm
enda
tion
•Th
e Po
LAR
team
and
bus
ines
s ex
pert
s re
com
men
d w
e en
gage
Spi
daSo
ftw
are
as t
he s
elec
ted
vend
or f
or S
CE’s
ne
w p
ole
load
ing
appl
icat
ion.
•Th
e te
am’s
con
fiden
ce is
bas
ed o
n:–
Succ
essf
ul c
ompl
etio
n of
all
CRP
scrip
ts
–O
vera
ll U
ser
Eval
uatio
n sc
ored
exc
elle
nt o
r go
od in
all
area
s–
Vend
or’s
dem
onst
rate
d ab
ility
to
met
our
usa
bilit
y,
inte
grat
ion,
and
eng
inee
ring
requ
irem
ents
14
E-4.14
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Nex
t St
eps
•O
btai
n sp
onso
r su
ppor
t of
rec
omm
enda
tion
to
enga
ge in
con
trac
t ne
gotia
tions
with
Spi
daSo
ftw
are,
Inc
.•
Cont
inue
pre
para
tion
for
Dec
embe
r CR
T
16
E-4.15
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P D
eliv
erab
les
•Fi
nal r
ecom
men
datio
n of
the
ven
dor
and
the
suita
bilit
y of
the
ven
dor
prod
uct
for
SCE
(Th
is d
eck
-com
plet
e)•
Sim
ulat
ion
of S
CE b
usin
ess
flow
s in
the
ven
dor
prod
uct
(Scr
ipts
and
sc
enar
ios
–du
e m
id N
ovem
ber)
–Va
lidat
ion
of t
he S
CE b
usin
ess
flow
s•
Iden
tific
atio
n of
dat
a an
d ex
tern
al p
roce
ss r
equi
rem
ents
(Ad
ditio
nal B
R’s
iden
tifie
d af
ter
the
CRP
-com
plet
e)•
List
of
outs
tand
ing
proc
ess,
fun
ctio
nalit
y, a
nd d
ata
issu
es a
nd p
oten
tial g
ap
reso
lutio
n re
com
men
datio
ns (
Gap
Ana
lysi
s D
ocum
ents
-co
mpl
ete)
•Id
entif
icat
ion
of S
CE o
rgan
izat
ions
, the
ir ro
les
and
resp
onsi
bilit
ies
(Upd
ated
O
rg im
pact
cha
rts,
R&
R, S
take
hold
er m
atrix
–du
e en
d of
Oct
.)•
Supp
ortin
g no
tes,
less
ons
lear
ned
and
com
men
ts f
rom
the
ses
sion
s (C
RP
note
s fr
om a
naly
sts
-co
mpl
ete)
•En
gine
erin
g re
view
of
calc
met
hodo
logy
acr
oss
indu
stry
app
licat
ions
(O
-Ca
lc, P
LS, E
DM
). (
Due
mid
Nov
embe
r) 17
E-4.16
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Bac
k-U
p
18
E-4.17
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Pro
ject
Cos
t &
Sch
edul
e•
Estim
ated
Pro
ject
Cos
t:–
2012
: $
2M–
2013
: $
7M–
2014
: $
5M•
Sche
dule
cur
rent
ly b
eing
ref
ined
in c
onju
nctio
n w
ith v
endo
r–
Plan
to
issu
e PO
s fo
r Li
cens
e/M
aint
enan
ce &
P/A
Pha
se in
Dec
embe
r –
Pres
ent
to C
RT in
Dec
embe
r–
Phas
ed im
plem
enta
tions
ten
tativ
ely
plan
ned
for
Q1,
201
3; Q
4, 2
013
and
Q2,
201
4
19
May
–Ju
ne 2
012
•May
9:
RF
P Re
leas
ed•J
une
13:
Re
spon
ses
Rece
ived
July
201
2•R
FP W
ritte
n Re
spon
se
Eval
uatio
n•J
uly
11:
D
owns
elec
tto
3 v
endo
rs
conf
irmed
Au
g -
Oct
. 20
12•A
ug 1
-15:
Pr
oof
of
Conc
ept
•Sep
t/O
ct:
Conf
eren
ce
Room
Pilo
t
Nov
embe
r20
12•F
inal
ize
CRT
Pack
age
Dec
. 201
2•P
rese
nt
PoLA
R to
CR
T•I
ssue
Ve
ndor
PO
(s)
for
P/A
Phas
e &
Lic
ense
s
Jan
uar
y20
13•I
ssue
ve
ndor
PO
fo
r fu
ll pr
ojec
t
Q1
2013
-Q
1 20
14•D
esig
n,
Cons
truc
t, T
est
•Dep
loym
ents
•P1:
Q
1, 2
013
•P2:
Q
4, 2
013
•P3:
Q
2, 2
014
E-4.18
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P P
ilot
–Te
am S
ched
ule
20
Resource�Nam
eM
onda
yTu
esda
yW
edne
sday
Thur
sday
Frid
ayG
roup
Vend
or
Cor
e Te
amx
xx
xx
Deb
ra B
rook
s
Cor
e Te
amx
xx
xx
Pet
er G
ergi
s
Eval
Tea
mx
xx
Dan
iel H
oche
var
Eval
Tea
mx
xx
Al M
acia
s
Eval
Tea
mx
xx
Rya
n Fl
ores
Eval
Tea
mx
xx
Eric
Man
uel
Eval
Tea
mx
xx
Dan
iel U
iriu
Eval
Tea
m- M
&I R
evie
wx
Art
Per
alta
/Bria
n Fl
ynn
Tran
smis
sion
& D
istri
butio
nEng
inee
ring
Out
put R
ev.
xC
hris
/Nor
man
/Jim
/Sar
a
E-4.19
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P E
xecu
tion
Sch
edul
e
21
Group
Mon
day
Tues
day
Wed
nesd
ayTh
ursd
ayFr
iday
Nam
e
Cor
e Te
amx
xx
xx
Deb
ra B
rook
s
Cor
e Te
amx
xx
xx
Pet
er G
ergi
s
Loca
l D P
lann
ing
xx
xx
Al M
acia
s
M&I
xx
xx
Art
Per
alta
M&I
xx
xx
Bria
n Fl
ynn
Tech
Pla
nnin
gx
xx
Dan
Hoc
heva
r
Tran
smis
sion
Des
ign
xx
xx
xD
anie
l Uriu
Tran
smis
sion
Des
ign
xx
xx
xEr
ic M
anue
l
Dis
tribu
tion
Engi
neer
ing
(out
put r
ev.)
xx
Jim
Day
Dis
tribu
tion
Engi
neer
ing
(out
put r
ev.)
xx
Sara
Ville
gas
Tech
/ND
Px
xx
xx
Jam
e Sc
hofie
ld
ECS
xx
xJo
se G
onza
lez
Des
ign
Supp
ort
xx
xR
icha
rd M
oral
es
Loca
l D P
lann
ing
xx
xx
Rya
n Fl
ores
Trai
ning
xx
xx
xSt
eve
Kerm
an
Trai
ning
xx
Tom
Sm
ith
Tran
smis
sion
Eng
inee
ring
(out
put r
ev.)
Rev
Pas
s 1
Rev
Pas
s 2
Chr
isto
pher
Nor
man
Tran
smis
sion
Eng
inee
ring
(out
put r
ev.)
Rev
Pas
s 1
Rev
Pas
s 2
Nor
man
Juf
er
E-4.20
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P T
eam
Rol
es
22
Nam
eD
epar
tmen
tTi
tleR
ole
Al M
acia
sD
C&
MP
lann
er 2
Cor
e -T
este
rA
rt P
eral
taR
PP
MTS
PC
ore
-Tes
ter
Bria
n Fl
ynn
RP
PM
TSP
Cor
e -T
este
rD
an H
oche
var
CD
&FA
Pla
nner
3 T
ech
Des
ign
Cor
e -T
este
rD
anie
l Uriu
Tran
smis
sion
Est
imat
orC
ore
-Tes
ter
Eric
Man
uel
Tran
smis
sion
Est
imat
orC
ore
-Tes
ter
Jim
Day
E&
TSD
istrb
utio
n E
ngin
eer
Cor
e -T
este
rR
yan
Flor
esC
D&
FAP
lann
er 2
-N
DP
Cor
e -T
este
rS
ara
Ville
gas
E&
TSD
istrb
utio
n E
ngin
eer
Cor
e -T
este
rC
hris
Nor
man
E&
TSTr
ans
Eng
inee
rTe
ster
Jam
es S
chof
ield
CD
&FA
Pla
nner
2 -
Tech
Des
ign
Test
erJo
se G
onza
lez
JrE
&TS
EC
STe
ster
Nor
man
Juf
erE
&TS
Tran
s E
ngin
eer
Test
erR
icha
rd M
oral
esC
D&
FAD
esig
n S
uppo
rtTe
ster
Ste
ve K
erm
anTD
BU
Tra
inin
gTr
aine
r -D
Pla
nnin
gTe
ster
Tom
Sm
ithTD
BU
Tra
inin
gTr
aine
r -D
Pla
nnin
gTe
ster
Arn
old
"Ski
p" V
ega
IT&
BI
IT P
M L
ead
Pro
ject
Sup
port
Deb
ra B
rook
sB
P&
TIP
roje
ct M
anag
erP
roje
ct S
uppo
rtP
eter
Ger
gis
BP
&TI
TSP
BU
Sup
port
Chr
istin
e W
ang
IT&
BI
IT S
yste
m A
naly
stIT
Hen
ry D
otso
nIT
&B
IIT
ITK
arl B
urge
ssIT
&B
IIT
Eng
inee
rIT
Mik
e V
aziri
OS
Pro
cure
men
t Age
ntIT
Pai
ge H
ong
IT&
BI
IT E
ngin
eer
ITP
rem
kum
ar N
aren
dran
IT&
BI
IT S
ecur
ity S
peci
alis
tIT
E-4.21
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
CR
P S
ucce
ss C
rite
ria
•Th
e ev
alua
tion
of t
he C
RP w
ill r
esul
t in
one
sco
re.
To b
e ch
arac
teriz
ed a
s a
succ
ess
the
busi
ness
eva
luat
ion
resu
lts m
ust
mee
t th
e fo
llow
ing
min
imum
th
resh
old:
–10
0% o
f Se
verit
y 1
and
Seve
rity
2 is
sues
are
clo
sed
by o
ne o
f th
e fo
llow
ing
miti
gatin
g ac
tions
:•
A re
conf
igur
atio
n of
the
too
l res
ultin
g in
the
issu
e be
ing
reso
lved
•Ap
prov
ed m
odifi
catio
n of
the
pro
cess
or
acce
pted
sys
tem
wor
k ar
ound
res
ultin
g in
the
issu
e be
ing
reso
lved
•Cu
stom
izat
ion
of a
noth
er e
xist
ing
SCE
syst
em o
ther
tha
n th
e ve
ndor
pro
duct
the
del
iver
s th
e re
quire
d ca
pabi
litie
s an
d re
solv
es t
he is
sue
appr
oved
by
the
IT a
nd t
he b
usin
ess
spon
sors
•Cu
stom
izat
ion
of t
he v
endo
r pr
oduc
t ap
prov
ed b
y th
e ve
ndor
and
bus
ines
s sp
onso
rs
–Th
e m
itiga
tion
plan
for
Sev
erity
3 a
nd S
ever
ity 4
issu
es w
ill b
e le
ft t
o th
e di
scre
tion
of t
he p
roje
ct t
eam
. –
Seve
rity3
and
Sev
erity
4 is
sues
may
als
o be
clo
sed
with
no
furt
her
actio
n (i.
e. a
ccep
ted
as is
).
–Ap
prov
al t
o ac
cept
the
fun
ctio
nal g
ap a
nd a
ll m
itiga
tion
actio
ns b
y th
e bu
sine
ss s
pons
or•
Any
iden
tifie
d IT
issu
es m
ust
also
be
miti
gate
d an
d ap
prov
ed b
y IT
m
anag
emen
t.
23
E-4.23
Southern California Edison2018 GRC A.16-09-001
DATA REQUEST SET SED-SCE-Verbal-005
To: SEDPrepared by: Martin Collette
Title: Project ManagerDated: 12/19/2016
Received Date: 12/19/2016
Question 01:
Originator: Wendy Al-Mukdad
1. How was SpidaCalc benchmarked and the underlying calculation identified as being ‘best practice’?
Response to Question 01:
During the Proof of Concept (POC) evaluation effort, Engineering evaluated Power Line Systems (PLS), Osmose and SPIDA software packages. SCE had prior pole loading experience with an Access Database calculation program, but it was limited in its calculation ability for complex pole loading. SCE did not have experience with the specific program inputs and loading methodologies of the proposed software packages. For this reason, the software vendors were asked to present their program analysis for nine pole loading scenarios, and to present detailed hand calculations for comparison to the program results.
The pole loading scenarios selected were a mix of pole types that were representative of pole configurations on the SCE system, as well as a pole loading scenario to analyze the effect of decay. Each software package was scored based on the methodologies of the program, rather than on specific numerical results. The program results from each vendor were not compared to other vendors, as the initial program assumptions were not specified nor uniform (for example, specific pole modulus or load distribution on pole due to guys was not specified). The results of the evaluation indicated that all three programs were technically acceptable for SCE use. The PLS software was the most technically superior software, as it offered the most complete modelling capability and could utilize a non-linear methodology that was the most accurate, although not feasible to recreate with a hand calculation. Osmose and SPIDA had very similar, but acceptable, scores with minor deductions because both were not able to perform H-frame structure analysis and both had to perform secondary calculations with assumed factors to analyze pole buckling. The Osmose program had a slightly lower score than SPIDA because the SPIDA program was thought to have a better fiberglass pole analysis methodology.�
E-5
�PoLAR POC Engineering Scores
Scenario Type PLS OSMOSE SPIDAUnguyed Grade B 2 2 2Unguyed Grade A 2 2 2
Guyed Angle 2 2 2Deadend Grade A 2 2 2Deadend Grade B 2 2 2Guyed Fiberglass 2 1 2
H-Frame 2 1 13-Pole Structure 2 2 2Decayed Pole 2 2 2
Buckling 2 1 1TOTAL 20 17 18
The attachment 'PoLAR_POC_BU_Orientation' summarizes the results after an RFP had been issued, and describes the planned Proof of Concept Evaluation of the three vendors selected. Descriptions of all 22 use cases considered in the RFP process are contained in the spreadsheets in the zip file "02_POC_UC_1_to_22.zip." The attachments, 'Osmose Proposal,' 'PLSi_poc_reports' and 'SPIDA HandCalc 1-9 and Methodology' provide detailed descriptions and results for the nine scenarios selected for more detailed engineering evaluation from each of the three vendors involved in the Proof of Concept Evaluation.
It should be noted that this technical evaluation was one component of the overall evaluation of the alternative software packages.
02_POC_UC_1_to_22.zip02_POC_UC_1_to_22.zip
Attachment SED-Verbal-005 Q1 Osmose Proposal Aug 2012 (002).pdfAttachment SED-Verbal-005 Q1 Osmose Proposal Aug 2012 (002).pdf
Attachment SED-Verbal-005 Q1 PLSi_poc_reports.zipAttachment SED-Verbal-005 Q1 PLSi_poc_reports.zip
Attachment SED-Verbal-005 Q1 SPIDA HandCalcs1-9 and Methodolgy.pdfAttachment SED-Verbal-005 Q1 SPIDA HandCalcs1-9 and Methodolgy.pdf
Attachment SED-Verbal-005 Q1 PoLAR_POC_BU_Orientation_7 25 12 v2.pptxAttachment SED-Verbal-005 Q1 PoLAR_POC_BU_Orientation_7 25 12 v2.pptx
E-6
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
July
-Aug
ust
2012
Pol
e Lo
adin
g A
pplic
atio
n R
epla
cem
ent
(PoL
AR
)
PO
C E
valu
atio
n M
etho
dolo
gy
Tim
eshe
et E
ntry
-Ti
tle
E-7
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Age
nda
•W
elco
me
and
Intr
oduc
tions
•Ex
pect
ed O
utco
mes
of
Toda
y’s
Mee
ting
•Po
LAR
Back
grou
nd•
RFP
Stag
e 1
-Re
cap
of V
endo
r’s w
ritte
n re
spon
ses
•RF
P St
age
2 -
Proo
f of
Con
cept
(PO
C)–
POC
Eval
uatio
n Te
am–
Scen
ario
s an
d Ex
pect
ed O
utco
mes
•PO
C Ev
alua
tion
Tim
etab
le
•N
ext
Step
s•
Q&
A
2
E-8
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Expe
cted
Out
com
e of
Tod
ay
•En
sure
a c
omm
on u
nder
stan
ding
of
the
PoLA
RPO
C Ve
ndor
ev
alua
tion
met
hodo
logy
•Re
view
com
pone
nts
of t
he “
Proo
f of
Con
cept
” st
age:
–PO
C us
e of
“w
ork
requ
est”
sce
nario
s –
POC
scor
ing
proc
ess:
•Bu
sine
ss R
equi
rem
ents
•Te
chni
cal R
equi
rem
ents
•Co
mm
erci
al E
valu
atio
n
–PO
C Ev
alua
tion
Tim
elin
e
•Cl
arify
you
r ro
le, r
espo
nsib
ilitie
s an
d w
hat
is e
xpec
ted
of Y
OU
as
a m
embe
r of
thi
s Te
am
•U
nder
stan
d th
e Ru
les
of E
ngag
emen
t –
“Con
fiden
tialit
y ”
3
E-9
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
PoL
AR
Ove
rvie
wM
issi
on•
Del
iver
a c
ompr
ehen
sive
sol
utio
n to
ena
ble
TDBU
per
sonn
el t
o pe
rfor
m p
ole
load
ing
anal
ysis
whi
ch m
eets
saf
ety
and
regu
lato
ry r
equi
rem
ents
and
per
form
s ef
fect
ivel
y w
ithin
a d
ynam
ic t
echn
ical
land
scap
e–
Com
preh
ensi
ve:
Ena
bles
Dis
trib
utio
n, T
rans
mis
sion
, ECS
and
3rd
par
ty s
cena
rios
–Co
mpl
ianc
e: D
ata
rete
ntio
n, m
easu
rem
ent
poin
ts, l
inea
r/no
n-lin
ear,
FE
anal
ysis
–In
tegr
atio
n: O
ptim
izes
AU
D a
nd G
IS;
scal
able
; ab
ility
to
run
non-
inte
grat
ed a
nd
disc
onne
cted
from
the
net
wor
k
Obj
ecti
ves
•D
eliv
er a
n ap
plic
atio
n to
per
form
con
sist
ent
and
relia
ble
calc
ulat
ions
whi
ch c
an b
e su
cces
sful
ly e
xecu
ted
by S
CE d
esig
n an
d pl
anni
ng p
erso
nnel
•D
eliv
er a
use
r fr
iend
ly t
ool t
hat
supp
orts
wor
k flo
w o
ptim
izat
ion
•Ef
fect
ivel
y le
vera
ge t
he in
tegr
ated
tec
hnic
al a
rchi
tect
ure,
incl
udin
g re
trie
val o
f as
set
data
fro
m S
AP, p
opul
atio
n of
mea
sure
men
t po
ints
for
com
plia
nce
repo
rtin
g, a
nd
inte
grat
ion
with
the
AU
D d
esig
n pr
oces
s
4
May
–Ju
ne 2
012
•May
9:
RF
P Re
leas
ed•J
une
13:
Re
spon
ses
Rece
ived
July
201
2•R
FP W
ritte
n Re
spon
se
Eval
uatio
n•J
uly
11:
D
owns
elec
tto
3 v
endo
rs
conf
irmed
Au
g -
Oct
. 20
12•A
ug 1
-15:
Pr
oof
of
Conc
ept
•Sep
t/O
ct:
Conf
eren
ce
Room
Pilo
t
Nov
embe
r20
12•F
inal
ize
CRT
Pack
age
Dec
embe
r20
12•P
rese
nt
PoLA
R to
CR
T
Jan
uar
y20
13•I
ssue
ve
ndor
PO
Q1
2013
-Q
1 20
14•D
esig
n,
Cons
truc
t, T
est
•Dep
loym
ent
Q1,
20
14
E-10
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Rec
ap o
f W
ritt
en E
valu
atio
n R
esul
ts
5
E-11
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
RFP
Eva
luat
ion
Pro
cess
–St
ages
RFP
PR
OC
ESS
WRI
TTEN
RES
PON
SEPR
OO
F O
F CO
NCE
PTCO
NFE
REN
CE R
OO
M
PILO
T
Num
ber
of V
endo
rs4
31
Inpu
t D
ocum
ents
•D
etai
led
Busi
ness
Re
quire
men
ts•
Ente
rpris
e Fo
cus
•Cr
itica
l req
uire
men
ts u
sed
for
min
imum
thr
esho
ld
•D
etai
led
Scen
ario
s fo
r ea
ch
Div
isio
n (D
ist.
, Tra
ns, E
CS,
Engi
neer
ing)
•Ex
pect
ed O
utco
mes
•D
etai
led
Busi
ness
Re
quire
men
ts
•D
etai
led
scrip
ts
•D
etai
led
busi
ness
req
uire
men
ts•
Det
aile
d Ex
pect
ed O
utco
mes
(�
400)
•SC
E da
ta
Sele
ctio
n Pr
oces
s/Cr
iteria
•Ve
ndor
s el
imin
ated
if “
Criti
cal”
re
quire
men
ts n
ot m
et•
Scor
ing
vend
or w
ritte
n re
spon
ses
•Sc
orin
g ve
ndor
s ba
sed
on
vend
or p
erfo
rman
ce in
de
mos
to
Eval
uatio
n Te
am
•Co
nfig
ure
Vend
or p
rodu
ct o
n SC
E ha
rdw
are
•Te
st s
crip
ts t
o ve
rify
expe
cted
ou
tcom
es a
re m
et•
Conf
irm p
rodu
ct s
uita
bilit
y to
SCE
an
d ID
gap
s be
twee
n pr
oduc
t an
d SC
E ne
eds
•Re
com
men
d ga
p cl
osur
e st
rate
gy•
Reco
mm
end
vend
or p
rodu
ct
Resu
lt
•To
p tw
o ve
ndor
s th
e m
eet
criti
cal r
equi
rem
ents
mov
e on
to
Pro
of o
f Con
cept
•To
p ve
ndor
mov
es o
n to
Co
nfer
ence
Roo
m P
ilot
•Te
am m
akes
fin
al
reco
mm
enda
tions
to
exec
utiv
es
Bus
R
eqs
(70%
)
Tec
h R
eq(1
5%)Inte
grat
ion
(15%
)
Bus R
eqs (
60%
)
Tech
Req
(20%
)
Proj
Appr
oach
(10%
)
Cost
(10%
)
Com
mer
cial
(15%
)
Pro
ject
A
ppro
ach
(5%
)
Bus
Req
s (5
0%)
Tech
Req
(2
0%)
Cos
t of
Ow
ners
hip
(30%
)
Com
mer
cial
(35%
)(1
5%)
E-12
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
RFP
Eva
luat
ion
Res
ult
s
7
RFP
Eva
luat
ion
Sum
mar
y
Sect
ion
Wei
ghtin
g
Vend
or P
ropo
sal
Spid
aA
DSK
&O
SMO
SEED
M&
PLS
Trim
ble
Bus
ines
s R
equi
rem
ents
60%
54.3
045
.20
47.4
627
.40
Tech
nica
l Req
uire
men
ts20
%15
.40
11.8
09.
8011
.30
Pro
ject
App
roac
h5%
4.69
3.62
1.13
2.64
Com
mer
cial
Ass
essm
ent
15%
12.5
011
.10
6.45
6.20
Tota
l10
0%86
.971
.764
.847
.5
RFP
Eva
luat
ion
Sum
mar
y
Sect
ion
Wei
ghtin
gVe
ndor
Pro
posa
lSp
ida
AD
SK&
OSM
OSE
EDM
&PL
STr
imbl
eB
usin
ess
Req
uire
men
ts60
%54
.30
45.2
047
.46
27.4
0Te
chni
cal R
equi
rem
ents
20%
15.4
011
.80
9.80
11.3
0To
tal
100%
69.7
57.0
57.3
38.7
Whe
n co
mpa
ring
just
B
R a
nd T
echn
ical
, A
DS
K &
PLS
sco
re
with
in .3
poi
nts
E-13
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Team
Rec
omm
enda
tion
•D
ue t
o th
e cl
osen
ess
of B
R/Te
chni
cal s
core
s of
AD
SK/O
smos
ean
d ED
M/P
LS, i
t is
rec
omm
ende
d th
at
thre
e ve
ndor
s ar
e in
vite
d fo
r PO
C:–
Spid
a–
ADSK
/OSM
OSE
–ED
M/P
LS•
Spon
sor
appr
oval
of
reco
mm
enda
tion
rece
ived
on
7/12
8
E-14
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Pro
of o
f C
once
pt E
valu
atio
n
9
E-15
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Pro
of o
f C
once
pt•
As a
res
ult
of t
he w
ritte
n ev
alua
tion
is c
ompl
eted
, thr
ee v
endo
rs h
ave
been
in
vite
d to
par
ticip
ate
in t
he “
Proo
f of
Con
cept
” (P
OC)
–Th
e pr
ojec
t te
am h
as c
ompl
eted
a s
et o
f sc
enar
ios
for
the
POC,
and
iden
tify
the
“exp
ecte
d ou
tcom
es”
for
each
sce
nario
–Th
e to
p th
ree
vend
ors
from
the
writ
ten
eval
uatio
n ha
ve b
een
invi
ted
to p
artic
ipat
e in
the
“Pr
oof
Of
Conc
ept”
(PO
C)
•D
urin
g th
e PO
C, t
he t
hree
ven
dors
will
use
the
ir so
ftw
are
to d
emon
stra
te o
ur
scen
ario
s–
The
POC
Eval
uatio
n Te
am w
ill b
e co
mpr
ised
of
Proj
ect
Team
mem
bers
, IT,
SCM
, an
d re
pres
enta
tive
SMEs
fro
m P
WRD
and
E&
TS
–Th
e PO
C Ev
alua
tion
Team
will
ens
ure
the
“crit
ical
exp
ecte
d ou
tcom
es”
are
succ
essf
ully
met
, as
wel
l as
Com
mer
cial
and
Tec
hnic
al c
riter
ia
The
top
vend
or f
rom
thi
s ph
ase
will
be
invi
ted
for
a “C
onfe
renc
e Ro
om P
ilot”
10
Bus
Req
s (5
0%)
Tech
Req
(2
0%)
Cos
t of
Ow
ners
hip
(30%
)
Com
mer
cial
(35%
)
(15%
)
E-16
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
PO
C B
usin
ess
Par
tici
pant
s
11
Nam
eD
epar
tmen
tTi
tleD
ebra
Bro
oks
BP
&TI
Pro
ject
Man
ager
Pet
er G
ergi
sB
P&
TITS
PR
yan
Flor
esC
D&
FAP
lann
er 2
-N
DP
Dan
Hoc
heva
rC
D&
FAP
lann
er 3
–Te
ch P
lann
ing
Al M
acia
sD
C&M
Plan
ner 2
Jim
Day
E&
TSD
istrb
utio
n E
ngin
eer
Sar
a Vi
llega
sE
&TS
Dis
trbut
ion
Eng
inee
rA
rt P
eral
taR
PP
MTS
PB
rian
Flyn
nR
PP
MTS
PD
anie
l Uriu
Tran
smis
sion
Est
imat
orC
hris
Nor
man
E&
TSTr
ans
Eng
inee
rN
orm
an J
ufer
E&
TSTr
ans
Eng
inee
rE
ric M
anue
lTr
ansm
issi
onE
stim
ator
Ric
hard
Mor
ales
CD
&FA
Des
ign
Sup
port
Jose
Gon
zale
z Jr
E&
TSE
CS
-D
efer
red
to D
/T S
ME
sE
ric 7
Lop
ezE
&TS
EC
S -
Def
erre
d to
D/T
SM
Es
E-17
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Bus
ines
s R
equi
rem
ent
Eval
uati
on•
22 s
cena
rios
have
bee
n pr
ovid
ed t
o th
e ve
ndor
s tw
o w
eeks
prio
r to
ap
pear
ance
•Ea
ch s
cena
rio h
as b
een
assi
gned
to
one
of t
he f
ollo
win
g ca
tego
ries
and
wei
ghte
d as
fol
low
s:–
Calc
ulat
ions
-40
%
(20%
of
Tota
l PO
C)–
Gen
eral
Cap
abili
ty-
30%
(1
5% o
f To
tal P
OC)
–U
sabi
lity
-15
%
(7.5
% o
f To
tal P
OC)
–W
orkf
low
-10
%
(5%
of
Tota
l PO
C)–
Each
sce
nario
s w
ill a
lso
rece
ive
an “
Ove
rall
Usa
bilit
y” A
sses
smen
t, a
ccou
ntin
g fo
r th
e re
mai
ning
5%
(2.
5% o
f To
tal P
OC)
•Ea
ch s
tep
in t
he s
cena
rio w
ill b
e as
sign
ed a
sco
re:
–3
= C
OTS
ful
ly d
emon
stra
tes
and
mee
ts r
equi
rem
ent
–2
= D
emon
stra
tion
incl
udes
cus
tom
ized
sol
utio
n an
d m
eets
the
req
uire
men
t–
1 =
Cus
tom
izat
ion
nece
ssar
y, is
not
dem
onst
ratio
n, b
ut f
ully
exp
lain
ed (
and/
or
non-
func
tiona
l dem
onst
ratio
n) a
nd m
eets
req
uire
men
t–
0 =
Ven
dor
does
not
mee
t re
quire
men
t
•Ea
ch s
tep
is s
core
d on
whe
ther
it m
eets
the
exa
ct s
tep
or n
ot.
Usa
bilit
y As
sess
men
t w
ill d
eter
min
e ho
w w
ell t
he p
roce
ss m
eets
the
inte
nt.
•Cu
stom
izat
ion
= C
ode
deve
lopm
ent
(doe
s no
t in
clud
e co
nfig
urat
ion)
12
E-18
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Engi
neer
ing
Cal
cula
tion
Sco
ring
•9
scen
ario
s re
quire
tha
t th
e ve
ndor
pro
vide
bot
h ha
nd c
alcu
latio
ns a
nd
resu
lts f
rom
the
ir to
ol in
ord
er t
o ve
rify
cons
iste
ncy
and
relia
bilit
y de
rivat
ion
•D
ue t
o th
e so
phis
ticat
ion
of t
echn
olog
y be
ing
eval
uate
d, it
is n
ot e
xpec
ted
that
the
ven
dors
cal
cula
tions
mat
ch S
CE’s
cal
cula
tions
exa
ctly
•Th
e ra
w s
core
for
Cal
cula
tions
will
be
base
d on
the
fol
low
ing:
–M
eets
(2)
= H
and
calc
ulat
ions
mat
ches
the
app
licat
ion
resu
lts.
If
resu
lts d
on’t
mat
ch S
CE’s
, ven
dor
also
pro
vide
s ex
pres
sed
will
ingn
ess
to
unde
rsta
nd d
elta
wor
k w
ith S
CE o
n ag
reea
ble
solu
tion.
–Pa
rtia
lly M
eets
(1)
= H
and
calc
ulat
ion
has
been
pro
vide
d, b
ut
met
hodo
logy
is n
ot y
et b
uilt
in t
he a
pplic
atio
n. I
f re
sults
don
’t m
atch
SC
E’s,
ven
dor
also
pro
vide
s ex
pres
sed
will
ingn
ess
to u
nder
stan
d de
lta
wor
k w
ith S
CE o
n ag
reea
ble
solu
tion.
–D
oes
not
Mee
t (0
) =
Unw
illin
gnes
s to
dis
clos
e m
etho
dolo
gy a
nd/o
r re
sults
don
’t m
atch
SCE
’s r
esul
tsan
d ve
ndor
doe
s no
t ex
pres
s w
illin
gnes
s to
und
erst
and
delta
and
wor
k w
ith S
CE o
n ag
reea
ble
solu
tion.
13
E-19
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Add
itio
nal S
cori
ng C
onsi
dera
tion
s•
A m
inim
um b
asel
ine
for
Engi
neer
ing
has
been
est
ablis
hed
by s
elec
ting
Scen
ario
s 2,
4, 9
for
Pas
s/Fa
il Ev
alua
tion:
–Pa
ss w
ill b
e gi
ven
if th
e so
lutio
n m
eets
our
req
uire
men
ts (
eith
er C
OTS
or
cust
omiz
ed)
–Ve
ndor
s th
at p
asse
s th
e in
itial
eva
luat
ion
will
pro
ceed
to
POC
scor
ing
–SC
E de
sire
s th
at a
ll th
ree
scen
ario
s ar
e pa
ssed
; ho
wev
er, i
f no
sin
gle
vend
or
pass
es a
ll th
ree,
the
n SC
E m
ay e
lect
to
allo
w a
ven
dor
to c
ontin
ue t
hrou
gh t
he
proc
ess
if th
ey p
rovi
de a
ccep
tabl
e ex
plan
atio
n of
var
iatio
n
•Th
roug
h pr
esen
tatio
n, A
d-ho
c re
ques
ts m
ay b
e m
ade
to d
emon
stra
te a
bilit
y to
mee
t re
quire
men
ts p
er t
heir
writ
ten
resp
onse
s:–
If a
ven
dor
stat
ed a
bilit
y to
mee
t re
quire
men
ts, b
ut a
re u
nabl
e to
dem
onst
rate
or
pro
vide
rea
sona
ble
expl
anat
ion,
the
tea
m m
ay e
lect
to
not
reco
mm
end
for
CRP
–Ve
ndor
s w
ill a
lso
be a
sked
to
show
inpu
ts in
the
app
licat
ion
for
Engi
neer
ing
Scen
ario
s
•Th
e hi
ghes
t ov
eral
l sco
re w
ill b
e in
vite
d in
for
a C
onfe
renc
e Ro
om P
ilot
–In
the
eve
nt o
f a
tie/c
lose
sco
re, t
he v
endo
r w
ith t
he h
ighe
r “U
sabi
lity”
sco
re w
ill
be in
vite
d fo
r CR
P, o
r (p
endi
ng r
esou
rces
& s
ched
ule)
bot
h ve
ndor
s m
ay b
e in
vite
d fo
r CR
P
14
E-20
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Scen
ario
Sco
ring
Pro
cess
•Af
ter
vend
or d
emon
stra
tion,
sco
ring
team
will
mee
t to
de
term
ine
cons
ensu
s sc
ores
for
eac
h sc
enar
io s
tep
•Ea
ch s
crip
t w
ill b
e di
scus
sed
for
a to
tal o
f 7
min
utes
–5
min
utes
for
dis
cuss
ion
–2
min
utes
to
assi
gn c
onse
nsus
sco
ring
–In
cas
e of
no
cons
ensu
s, t
ake
low
est
asse
ssm
ent
(unl
ess
mos
t qu
alifi
ed S
ME
stro
ngly
dis
agre
es)
•N
o di
scus
sion
out
side
the
rev
iew
ses
sion
(“C
OD
E O
F SI
LEN
CE”)
unt
il al
l sco
ring
is c
ompl
eted
•Th
is in
clud
es h
allw
ay c
onve
rsat
ions
dur
ing
brea
ks•
Trea
t ea
ch o
ther
will
pro
fess
iona
l cou
rtes
y an
d re
spec
t
15
E-21
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Dem
onst
rate
our
SC
E C
ore
Val
ues
16
Inte
grit
y•
Be o
pen
and
hone
st•
Del
iver
on
com
mitm
ents
and
pro
mis
es•
Actio
ns a
nd w
ords
are
con
sist
ent
Exce
llenc
e•
Acce
pt a
ccou
ntab
ility
for
actio
ns
•Ac
ts w
ith a
sen
se o
f pu
rpos
e•
Build
on
the
stre
ngth
s of
div
ersi
ty•
Sets
hig
h ex
pect
atio
ns a
nd d
eliv
er
resu
lts
Res
pect
•As
sum
es b
est
inte
ntio
ns•
Fost
ers
a po
sitiv
e, o
pen
envi
ronm
ent
•Re
cogn
izes
the
con
trib
utio
ns o
f ot
hers
Con
tinu
ous
Impr
ovem
ent
•Co
nsis
tent
ly r
aise
the
per
form
ance
bar
•En
sure
s ot
hers
hav
e th
e co
ntex
t an
d in
form
atio
n to
suc
ceed
•W
elco
mes
cha
nge
and
new
idea
s
Team
wor
k•
Stre
ngth
en p
erfo
rman
ce t
hrou
gh
mut
ual s
uppo
rt•
Enco
urag
e cr
oss-
orga
niza
tiona
l co
llabo
ratio
n •
Invo
lves
oth
ers
and
seek
s th
eir
inpu
t•
Mak
es d
ecis
ions
for
the
grea
ter
good
, no
t se
lf-in
tere
st
E-22
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
PO
C T
echn
ical
Par
tici
pant
s•
A te
chni
cal q
uest
ionn
aire
has
bee
n pr
epar
ed, w
hich
cov
ers
a w
ide
varie
ty o
f ev
alua
tion
area
s•
The
tech
nica
l eva
luat
ion
team
will
con
duct
its
eva
luat
ion
thro
ugh
obse
rvat
ions
dur
ing
the
dem
onst
ratio
n an
d a
sepa
rate
Q&
A se
ssio
n•
Scor
es w
ill b
e w
eigh
ted
base
d on
the
ou
tline
d pa
ram
eter
s in
the
cha
rt
17
Eval
uatio
n�Ar
eaW
eigh
tAp
plic
atio
n�Ar
chite
ctur
e5.
00%
Avai
labi
lity
7.50
%Ca
paci
ty5.
00%
Conf
igur
abili
ty10
.00%
Data
�Arc
hite
ctur
e10
.00%
Depl
oym
ent�A
rchi
tect
ure
5.00
%Ex
tens
ibili
ty2.
50%
Inte
grat
ion�
Arch
itect
ure
12.5
0%M
aint
aina
bilit
y5.
00%
Net
wor
k�Ar
chite
ctur
e5.
00%
Ope
rabi
lity
5.00
%Pe
rform
ance
5.00
%Re
cove
rabi
lity
7.50
%Se
curit
y�Ar
chite
ctur
e5.
00%
Test
abili
ty2.
50%
Use
r�Int
erfa
ce7.
50%
Tota
ls10
0.00
%
Tech
nica
lEva
lTea
mD
epar
tmen
tTi
tleA
rnol
d "S
kip"
Veg
aIT
&B
IIT
PM
Lea
dK
arl B
urge
ssIT
&B
IIT
Eng
inee
rH
enry
Dot
son
IT&
BI
IT A
rchi
tect
Pre
mku
mar
Nar
endr
anIT
&B
IIT
Sec
urity
Spe
cial
ist
TBD
IT&
BI
IT M
aint
enan
ce T
eam
E-23
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Com
mer
cial
Eva
luat
ion
18
Com
mer
cial
Eval
Team
Dep
artm
ent
Title
Mik
e Va
ziri
OS
Pro
cure
men
t Age
nt
Pau
l Jos
eph
BP
&TI
Pro
gram
Man
ager
Bre
nda
Ste
ckle
rIT
&B
ITD
M M
anag
er
Cate
gory
Crite
rion
$TC
OPr
ice
- Ba
se30
% o
f Sco
ring
Pric
e -
Prof
essi
onal
Ser
vice
sCO
TsD
eliv
ery/
Sche
dule
Lice
nses
Ref
resh
Mai
nten
ance
- V
endo
r Co
stM
aint
enan
ce -
Int
erna
l SCE
Cos
tW
arra
ntie
sIn
tegr
atio
n Co
st -
Cos
t to
Bui
ld I
nteg
rati
onTO
TAL
- TC
O$
Ts&C
s3%
of T
otal
Sco
ring
DBE
2% o
f Tot
al S
corin
g
Tota
l�35
% o
f Tot
al C
omm
erci
al S
corin
g
The
com
mer
cial
eva
luat
ion
will
be
asse
ssed
and
wei
ghte
d as
follo
ws:
E-24
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
PO
C L
ocat
ion
Kello
gg W
est
Conf
eren
ce C
ente
r &
Hot
el
Cal P
oly
Pom
ona
Foun
datio
n In
c.
3801
W. T
empl
e Av
e. B
ldg.
76
Pom
ona,
Ca
9176
8Ro
om:
Hill
side
Eas
t 1&
2
•Ea
sies
t ac
cess
is f
rom
Tem
ple
Aven
ue a
nd 5
7 fr
eew
ay s
ide
•M
apQ
uest
and
oth
er m
appi
ng a
pplic
atio
ns d
on't
tend
to
find
loca
tion
corr
ectly
.•
Park
ing
is a
t th
e fa
r en
d of
the
driv
eway
•
Conf
eren
ce c
ente
r is
a s
hort
wal
k ba
ck d
own
the
hill
on t
he n
orth
sid
e of
th
e dr
ivew
ay•
Park
ing
pass
es/t
ags
will
be
avai
labl
e in
the
mai
n lo
bby.
Pl
ease
pla
ce y
our
park
ing
perm
it on
you
r re
arvi
ew m
irror 19
E-25
SOU
THER
N C
ALIF
ORN
IA E
DIS
ON
®SM
BP&
TI:
PoLA
R
Sche
dule
•Ve
ndor
1:
Aug
ust
1 &
2•
Vend
or 2
: A
ugus
t 7
& 8
•Ve
ndor
3:
Aug
ust
13 &
14
•Co
nfer
ence
Roo
m P
ilot
–pl
anne
d fo
r Se
pt/O
ct.
20
E-26
PoLAR Proof of Concept Hand Calculations and Comparison in
SPIDA R©Calc
August 12, 2012
Contents
1 Introduction 31.1 Analysis Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2 GO95 Overview 32.1 Loading Rules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.1.1 Zone Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32.2 Safety Factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3 Finite Element Analysis Formulation 43.1 Stiffness Matrix Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.1.1 Frame Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53.1.2 Bar Element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.2 Matrix Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63.3 Guying Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63.4 Structural Damage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4 Structure Loading 74.1 Transverse Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74.2 Longitudinal Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.2.1 Tension Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74.3 Vertical Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84.4 Total Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
1
E-27
CONTENTS
5 Proof of Concept Examples 95.1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95.2 Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
6 Proof of Concept 1 96.1 Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96.2 Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
6.2.1 Transverse Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.2.2 Vertical Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116.2.3 Longitudinal Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116.2.4 Stress Calculation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126.2.5 Results Comparison . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
7 Proof of Concept 2 127.1 Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127.2 Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137.3 Pole Stress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
8 Proof of Concept 3 148.1 Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148.2 Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
9 Proof of Concept 4 179.1 Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179.2 Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
10 Proof of Concept 5 2010.1 Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2010.2 Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
11 Proof of Concept 6 2311.1 Additional Capabilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
12 Proof of Concept 7 2312.1 Additional Capabilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2312.2 Analysis Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
13 Proof of Concept 8 2413.1 Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2413.2 Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
14 Proof of Concept 9 2714.1 Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2714.2 Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Appendix A: Sample Bar Problem 28
Page 2 of 29 Copyright c© SPIDAWEB, LLC *Confidential* Internal Use Only
E-28
6 PROOF OF CONCEPT 1
Fbar = σbar ∗A (12)
5 Proof of Concept Examples
5.1 Overview
The overall strategy of the following examples will be to demonstrate the accuracy of the SPIDACalc analysisengine. To achieve this we have attempted to provide hand calculations for structures we feel it is appropriate todo so. Some of these examples do not lend themselves particularly well to hand calculation comparisons primarilybecause of the assumptions that would have to be made to make them solvable. This particularly shows up instructures with more than guy wire. Pole structures, with guy wires present, force the assumption of some loaddistribution between the guy wires. These poles would be examples of over-determined systems. You can notknow how much force goes into each guy wire without taking the boundary conditions and material propertiesinto account, which is exactly what the finite model does. For simple examples with low number of guy wires,some assumptions can be made with reasonable accuracy to approximate the correct answer. However, evenwith simple examples we will see that those assumptions don’t always catch the worst case location of stress inthe pole, or properly account for the interplay of all the material properties, forces applied and geometry of thestructure.
5.2 Assumptions
Unless otherwise specified in any specific ”Proof of Concept” item documentation we have made the followingassumptions:
• The construction grade is A.
• The load case is GO95 Light.
• Final tension will be used.
6 Proof of Concept 1
6.1 Setup
Table 1: Pole and Conductor Information for Proof of Concept 1
Component Property Value
Load Information Construction Grade BGO 95 Load Zone Light
Distance to Next and Previous Pole 150 ftWind Pressure 8 lb/ft2
Pole Safety Factor 3
Continued. . .
Copyright c© SPIDAWEB, LLC *Confidential* Internal Use Only Page 9 of 29
E-29
6 PROOF OF CONCEPT 1
Component Property ValuePole Height 45 ft
Species Douglas FirClass 4
Pole Top Circumference 21 inAbove Ground Line 38.5 ft
Ground Line Circumference 34.82 inMaximum Fiber Stress 8000 lb/in2
Modulus of Elasticity 2500000Wires 1-4 Phases 3
Type 1/0 ACSRAttachment Height 38 ft
Diameter 0.03316 ftTension 1445 lb
6.2 Analysis
The first step in the loading percentage calculation is to determine all of the loading components. Because thisexample does not have a guy wire, the transverse forces can be used to find the sum of the moments at the polebase, which can be used along with the vertical forces to determine the maximum stress.
6.2.1 Transverse Loading
The transverse loading on the pole is the wind loading on the wires plus the wind loading on the pole. Theequation for the transverse force on a given wire is given in Equation 13.
Fwire = D ∗ pw ∗ l ∗ np (13)
Where D is the diameter of the wire with ice (ft), pw is the pressure of the wind (lb/ft2), l is the averagelength of the wire spans (ft), and np is the number of phases. In this calculation, the length of the wire isactually half of the span to the next pole, but since this example has an equal span of 100 feet next and previous,the final wire length is 100 feet. Where a line angle is present, the force acted upon by the tension in the wiresis calculated by the simple vector component in Equation 14.
FWireTension = T ∗ sin(θ) (14)
Where T is the wire tension, and θ is the line angle.To calculate the moment from any force take the force and multiply it by the distance from the point of
interest. In this case, the distance is the height from the ground to the attachment point of the wire. The windforce acting on the pole itself is also calculated.
To calculate the moment for the pole, the force on the pole is first calculated. This force is shown in Equation15
Fpole = A ∗ pw (15)
Page 10 of 29 Copyright c© SPIDAWEB, LLC *Confidential* Internal Use Only
E-30
6 PROOF OF CONCEPT 1
Where A is the side area of the pole. The forces are calculated for the pole and for the wires in Table 1 andare shown in Table 16.
Fpw = 28.49ft.2 ∗ 8lb./ft.2 = 227.952lb.
Fww = 150ft. ∗ 4 ∗ 2.65lb./ft. = 159.2lb. (16)
Where Fpw is force of wind on pole and Fww is the force of wind on wire. Using these calculated transverseforces, the moments from the wires and pole are calculated by multiplying by the distance away from the baseof the pole. The resultant moments are displayed in Table 17. The moment arm of the pole is the height of thecentroid of the trapezoid formed by the side of the pole.
Mp = 227.952lb. ∗ 17.663ft. = 4026.285ft. · lb.Mw = 159.2lb. ∗ 38ft. = 6049.6ft. · lb. (17)
We then do an comparison between this value and that value calculated by SPIDACalc in Table 2.
Table 2: Groundline moment comparisons between SPIDACalc and hand calculations.
SPIDACalc 10076ft. · lb.Hand Calculations 10075.88ft. · lb.
6.2.2 Vertical Loading
The second type of loading to be calculated is the vertical loading component of the structure and its members.The vertical force generated by the wires is given in Equation 18.
Fv = (Vi ∗ ρ+ l ∗ ρlin) ∗ np (18)
For zones where ice is present, Vi is the volume of ice, ρ is the density of ice, and ρlin is the linear density ofthe wire This force is summed for each wire and then added to the weight force of the pole, which is the densityof the pole multiplied by its volume. These values are computed and shown in Table 19.
Fpv = 41.55ft.3 ∗ 31lb/ft.3 = 1288.24lb.
Fwv = 0.1451lb./ft. ∗ 150ft. ∗ 4 = 87.1lb. (19)
6.2.3 Longitudinal Loading
In this example the net longitudinal loading is equal to zero. The longitudinal loading is equal to zero becausethe next and previous spans are equal to each other and in line. However, the longitudinal force is calculatedbased on the tension of the wire and the formula is shown in Equation 20. It should also be noted that becauseof the change in temperature, ice weighting and wind loading on the wire, the tension could change from the
Copyright c© SPIDAWEB, LLC *Confidential* Internal Use Only Page 11 of 29
E-31
7 PROOF OF CONCEPT 2
initial stringing tension given in Table 1. These tensions are calculated with an iterative process with well knownequations [3]. These calculations are not used here for simplicity, but are considered more accurate.
Fl = T ∗ cos(θ) (20)
Where T is the load case tension in the wire, and θ is the line angle if it exisits.
6.2.4 Stress Calculation
The stress is calculated in this example from a combination of vertical force and ground line moment. Theequation for stress in an un-guyed pole is found in Equation 21.
σ =Fv
A+
Mc
I(21)
Using Equation 21, we calculate the stress in this example in Equation 22.
σpole =1375lb
96.38in2+
48315.421in ∗ lb · 3.34in739.29in4
(22)
6.2.5 Results Comparison
Comparing the above calculated results to the calculated SPIDACalc results is done in Table 3, the safety factorscompare very closely.
Table 3: Groundline stress comparisons between SPIDACalc and hand calculations.
SPIDACalc Safety Factor 8.79Calculated Safety Factor 8.69
7 Proof of Concept 2
The second example shares much with the first, except the addition several conductors on unequal spans.
7.1 Setup
Table 4: Pole and Conductor Information for Proof of Concept 1
Component Property Value
Load Information Construction Grade AGO 95 Load Zone Light
Distance to Next Pole 250 ftDistance to Previous Pole 150 ft
Wind Pressure 12 lb/ft2
Continued. . .
Page 12 of 29 Copyright c© SPIDAWEB, LLC *Confidential* Internal Use Only
E-32
Power Line Systems, Inc. Page 1/2
PLS-CADD Version 12.23x64 11:07:37 AM Monday, July 30, 2012Power Line Systems, Inc.Project Name: 'c:\sce\poc\poc_uc_1.LOA'
Criteria Notes: GO95 Light 8 lb Wind
Structure # '________.___'Station (ft) 0.00, Line angle (deg) 0, Orientation angle (deg) 0Cost 0.00
Project Name : Project Notes: Project File : c:\sce\poc\distribution\structures\poc_uc_1.polDate run : 11:07:31 AM Monday, July 30, 2012by : PLS-POLE Version 12.23Licensed to : Power Line Systems, Inc.
Successfully performed linear analysis
The model has 0 warnings.
Loads from direct link to PLS-CADD
*** Analysis Results:
Minimum element Safety Factor is 8.60 for Wood Pole "P" in load case "8lb -Wind,I NA-"Minimum insulator Safety Factor is 251.21 for Post "LI" in load case "8lb +Wind,I NA+"
Summary of Foundation Loads For All Load Cases:
Load Case Joint Long. Tran. Vert. Shear Tran. Long. Vert. Bending Found. Label Force Force Force Force Moment Moment Moment Moment Usage (kips) (kips) (kips) (kips) (ft-k) (ft-k) (ft-k) (ft-k) %-------------------------------------------------------------------------------------- 8lb +Wind,I NA+ P:g -0.00 -0.39 -1.17 0.39 10.21 -0.05 0.00 10.21 0.00 8lb -Wind,I NA- P:g -0.00 0.39 -1.17 0.39 -10.21 -0.05 0.00 10.21 0.00
Summary of Tip Deflections For All Load Cases:
Note: postive tip load results in positive deflection
Load Case Joint Long. Tran. Vert. Resultant Long. Tran. Twist Label Defl. Defl. Defl. Defl. Rot. Rot. (in) (in) (in) (in) (deg) (deg) (deg)-------------------------------------------------------------------- 8lb +Wind,I NA+ P:t 0.03 8.77 -0.00 8.77 0.01 -1.89 -0.00 8lb -Wind,I NA- P:t 0.03 -8.77 -0.00 8.77 0.01 1.89 -0.00
*** Overall summary for all load cases - Usage = Maximum Stress / Allowable Stress*** Overall summary for all load cases - Safety Factor = Allowable Stress / Maximum Stress
Summary of Wood Pole Usages:
Wood Pole Maximum Load Case Segment Weight Label Usage % Number (lbs)------------------------------------------------- P 11.62 8lb -Wind,I NA- 25 1293.0
Summary of X-Arm Usages:
X-Arm Maximum Load Case Segment Weight Label Usage % Number (lbs)---------------------------------------------- XARM 3.53 8lb -Wind,I NA- 4 70.5
*** Maximum Stress Summary for Each Load Case
Summary of Maximum Usages by Load Case:
Load Case Maximum Element Element
E-33
Power Line Systems, Inc. Page 2/2
Usage % Label Type------------------------------------------ 8lb +Wind,I NA+ 11.62 P Wood Pole 8lb -Wind,I NA- 11.62 P Wood Pole
Summary of Wood Pole Usages by Load Case:
Load Case Maximum Wood Pole Segment Usage % Label Number------------------------------------------ 8lb +Wind,I NA+ 11.62 P 25 8lb -Wind,I NA- 11.62 P 25
Summary of X-Arm Usages by Load Case:
Load Case Maximum X-Arm Segment Usage % Label Number--------------------------------------- 8lb +Wind,I NA+ 3.53 XARM 5 8lb -Wind,I NA- 3.53 XARM 4
Summary of Insulator Usages:
Insulator Insulator Maximum Load Case Weight Label Type Usage % (lbs)--------------------------------------------------- LI Post 0.40 8lb +Wind,I NA+ 0.0 CI Post 0.40 8lb +Wind,I NA+ 0.0 RI Post 0.40 8lb +Wind,I NA+ 0.0 N Post 0.40 8lb +Wind,I NA+ 0.0
*** Weight of structure (lbs): Weight of X-Arms: 70.5 Weight of Wood Poles: 1293.0 Total: 1363.5
*** End of Report
E-34
E-35
E-36
E-37
E-38
E-39
E-40
E-41
E-42
Appendix F
Engineering Analysis
Southern California Edison2018 GRC A.16-09-001
DATA REQUEST SET TURN-SCE-022
To: TURNPrepared by: Martin Collette
Title: Principal AdvisorDated: 12/21/2016
Received Date: 12/21/2016
Question 06:
6. In SCE-02, Vol. 9, at page 9, SCE states that it began using SPIDACalc as an enterprise-wide tool in April of 2013, and that in December of 2014 SCE engineering identified some potential improvement areas in SPIDACalc’s safety factor calculation methodology. Please provide a copy of all documents, notes and memoranda, including electronic correspondence, from April of 2013 through December of 2014 that reflect SCE engineering identifying or communicating issues or concerns with SPIDACalc, or otherwise identifying potential improvement areas in SPIDACalc.
Response to Question 06:
SCE objects to the question to the extent that is is overbroad, as it requests "all documents, notes and memoranda" covering SCE's evaluation of the SPIDA Calc tool and software. The systematic evaluation of SPIDA Calc by SCE's Engineering group was carried out between July and December of 2014. SCE's Pole Loading Program employees responsible for conducting this engineering evaluation made reasonable searches of their documents in response to this document request.
As discussed in the testimony (see page 13), SCE planners at times noted that SPIDA Calc called for larger pole sizes than might have been expected to meet minimum safety requirements. However, SCE had also recently implemented higher wind loading specifications and expanded the boundaries of the high-wind areas throughout the service territory, which would have resulted in larger pole sizes. As a result, the concerns initially raised by the planners were not inconsistent with outcomes expected.
Given that the Pole Loading Program was new and extensive, a group consisting of field personnel and program management was set up to discuss the ongoing status of the program. Initial feedback from field personnel indicated SPIDACalc was producing results that, even accounting for the change in wind standards and high-wind areas, still seemed to run counter to historical experience. These were communicated to the Pole Loading Program management. Based on this feedback, it was a decided that an independent engineering analysis of SPIDACalc results would be prudent.
F-1
The independent evaluation was initiated upon the request from Mr. Ken Trainor, Director of the Pole Assessment and Remediation, on June 30, 2014. SCE Engineering prepared a proposal outlining the plan for this independent evaluation with key steps and a tentative schedule along with required resources to perform the independent evaluation. The initial draft plan was issued on July 18, 2014, and it included the following key steps in the initial plan:
1. Identify pole construction types for evaluation§ Select three samples for each of the following type:
i. Tangent pole with equal tensionii. Angle pole (bisector guyed pole)iii. Guyed pole/deadend pole (in-line guyed pole)iv. In-line span guyed polev. H-frame
2. Complete first pass of calculation§ Perform pole loading calculation of 15 samples on SPIDA and PLS Software
using SCE’s standard values/assumptions3. Complete second pass of calculation
§ Conduct field survey and perform pole loading calculation of 15 sample on SPIDA and PLS Software using field surveyed data
4. Complete evaluation and make recommendation.
Please refer to the attachment 'SPIDA Evaluation Proposed Plan 20140718'.
Engineering began the independent (separate and stand-alone effort independent of the Pole Loading Program evaluation of SPIDACalc) in late July 2014, after reaching agreement on the proposed evaluation plan. Along the way the team encountered a number of challenges such as overcoming the learning curve of independent engineers previously not involved in the pole loading program, matching the detailed modeling of the selected pole samples from SPIDA to PLS-CADD and PLS Pole, conversion of field sag measurements to usable tension inputs for modeling the pole samples with field surveyed tensions, the increase in scope on the actual number of poles assessed due to adding poles with queen posts and the need to include adjacent poles to correctly model field conditions, and the increase in scope of involving an outside entity as an additional validation measure in November of 2014. These challenges and scope changes shifted the completion date of this independent evaluation to December of 2014.
The Engineering team presented their findings to the PLP team on December 11, 2014. During the time from late July to early December, two major progress updates were given in September and November of 2014 to the working team of the Pole Loading Program. Please refer to the attachments 'SPIDA Evaluation Progress Updates - 20140908', 'SPIDA Evaluation Progress Updates - 20141120' and 'SPIDA Evaluation Progress Updates - 20141211'. SCE's preliminary research shows that Mr. Ken Trainor was briefed on these findings after the September and November updates to the working team. SCE is in the process of verifying this. Mr. Trainor was aware of the final results of the analysis in December, 2014. SPIDA management was also present at the December meeting and detailed discussion on the necessary changes to SPIDACalc were communicated by SCE to SPIDA.
F-2
Please note that SCE has not conducated a search of all documents, notes, memoranda, and electronic correspondence between April, 2013 and December, 2014 regarding SCE engineering identifying issues, identifying potential improvements, or communicating with SPIDACalc, but is providing the key documents that have resulted in updating SPIDACalc and implementation of the revised pole loading assessment.
SPIDA Evaluation Progress Updates - 20140908.pptxSPIDA Evaluation Progress Updates - 20140908.pptx
SPIDA Evaluation Progress Updates - 20141120_Thuan.pptxSPIDA Evaluation Progress Updates - 20141120_Thuan.pptx
SPIDA Evaluation Progress Updates - 20141211_kv.pptxSPIDA Evaluation Progress Updates - 20141211_kv.pptx
SPIDA Evaluation Progress Updates_Meeting_Notes_20140909.docxSPIDA Evaluation Progress Updates_Meeting_Notes_20140909.docx
SPIDA Evaluation Proposed_Plan_20140718.pptxSPIDA Evaluation Proposed_Plan_20140718.pptx
F-3
T&
D E
ngin
eeri
ng
12/1
1/20
14
Engi
neer
ing
Eval
uatio
n fo
r SP
IDA
F-4.1
Proj
ect P
lan
2 �
Obj
ectiv
es:
1.Pe
rfor
m e
ngin
eeri
ng e
valu
atio
n of
SPI
DA
by
com
pari
ng w
ith
PLS-
CA
DD
/PLS
-PO
LE
2.Id
entif
y an
y ga
ps w
ithin
SPI
DA
3.
Rec
omm
end
proc
ess f
or b
ridg
ing
thos
e ga
ps
Iden
tify
pole
co
nstr
uctio
n ty
pes f
or
eval
uatio
n
Com
plet
e fir
st
pass
of
calc
ulat
ion
Com
plet
e se
cond
pas
s of
calc
ulat
ion
Com
plet
e ev
alua
tion
and
mak
e re
com
men
datio
n
07/2
5/14
09
/02/
14
10/3
1/14
12
/11/
14
F-4.2
Exec
utiv
e Su
mm
ary
3
Engi
neer
ing
Eval
uati
on
�O
ut o
f 19
pole
s eva
luat
ed, t
en (5
0%) e
ither
faile
d or
had
sign
ifica
ntly
wor
se re
sults
usin
g SP
IDA
.
�SP
IDA
and
PLS
-CA
DD
pro
duce
d co
mpa
rabl
e re
sults
on
tang
ent p
ole
with
equ
al
tens
ion.
�SP
IDA
has
sign
ifica
nt li
mita
tions
for
angl
e bi
sect
or, c
orne
r an
d de
aden
d po
les.
�SP
IDA
is in
adeq
uate
for
hand
ling
H-f
ram
e an
d ot
her
mul
ti-po
le st
ruct
ures
.
�ED
M In
tern
atio
nal v
erifi
ed a
nd a
gree
d w
ith S
CE
engi
neer
ing
eval
uatio
n re
sults
.
Rec
omm
end
atio
ns
�Sh
ort T
erm
: Use
PLS
-CA
DD
to p
ole
load
ang
le b
isect
or, c
orne
r, de
aden
d po
les a
nd H
-Fr
ames
.
�Lo
ng Te
rm:
Dev
elop
/Im
plem
ent k
ey im
prov
emen
ts/c
hang
es to
SPI
DA
as i
dent
ified
on
slide
#7.
Nex
t St
eps
Task
s R
esp
onsi
bili
ty
Dat
e
Iden
tify
Scop
e fo
r PL
S-C
AD
D w
ork.
Ph
il an
d T
huan
Q
1, 2
015
Rev
iew
SPI
DA
scop
e ch
ange
and
dev
elop
im
plem
enta
tion
plan
. D
ebra
, Nor
m, T
huan
and
SP
IDA
Q
1, 2
015
F-4.3
Fiel
d Su
rvey
Dat
a (S
ee S
lides
15
-17
for F
ield
Sur
vey
Exam
ple)
4
�SP
IDA
and
PLS
-CA
DD
: �
Mea
sure
wir
e te
nsio
ns u
sing T
ruPu
lse,
TruA
ngle
, or T
otal
Sta
tion
�Sa
g an
d w
eath
er w
ere
used
to d
eter
min
e ac
tual
max
imum
wir
e te
nsio
ns
�PL
S-C
AD
D o
nly:
�
Unl
evel
span
s and
une
qual
span
le
ngth
s con
sider
ed
�SP
IDA
onl
y:
�A
ll sp
ans m
odel
ed a
s lev
el sp
ans a
nd
shor
t spa
n/lo
ng sp
an in
tera
ctio
ns
igno
red
(can
’t be
cal
cula
ted
in
curr
ent v
ersio
n of
tool
)
SCE
Def
aults
(S
ee S
lides
13
-14
for S
CE
Def
ault
Exam
ple)
�SP
IDA
and
PLS
-CA
DD
: �
Def
ault
max
imum
wir
e te
nsio
ns
from
TO
H/D
OH
�St
anda
rd fi
eldi
ng p
ract
ices
�St
anda
rd fi
eldi
ng e
quip
men
t
�PL
S-C
AD
D o
nly:
�
Stan
dard
PLS
-CA
DD
des
ign
para
met
ers f
or w
ood
pole
s
�SP
IDA
onl
y:
�St
anda
rd S
PID
A c
lient
file
(des
ign
para
met
ers)
Sum
mar
y of
Inpu
t Dat
a to
SPI
DA
and
PLS-
CAD
D
F-4.4
5 Results Comparison For SCE Defaults
(See Slides 10-12 for Pole Construction Examples)
SCE
Defa
ult T
ensi
ons
SPID
APL
S-CA
DD
Pole
Heig
htCl
ass
Win
dGr
ade
New
/In
-Ser
vice
(I.
S.)
Pole
Guy
Clas
s+
Guys
Pole
Guy
Clas
s+
Guys
1437
855E
70H1
12A
New
3.56
N/A
3.84
N/A
1341
082E
752
12A
New
3.06
N/A
3.17
N/A
1172
243E
404
18A
I.S.
1.71
N/A
H11.
88N
/A1
2115
818E
752
12A
New
3.98
2.01
3.71
2.24
1598
122E
504
12A
I.S.
1.14
0.83
16
5.83
2.12
144
7699
6E75
H112
AN
ew3.
822.
086.
042.
083
2115
779E
752
12A
New
1.72
2.26
H25.
603.
043
1840
428E
75
212
AN
ew3.
172.
408.
592.
461,
5w
/guy
stub
182
4123
E40
412
AN
ew3.
303.
754.
575.
3512
4005
1E50
312
AN
ew1.
616.
95H1
2.20
25.1
91
1,5
1437
877E
701
12A
New
4.65
6.88
5.61
15.6
61
w/g
uy st
ub 4
3061
91E
305
12A
I.S.
5.95
3.57
11.2
79.
6914
3788
0E70
212
AI.S
.4.
2012
.98
5.65
14.3
9w
/guy
stub
143
7950
E40
512
AN
ew12
.67
6.54
12.5
56.
9816
8276
2E80
212
BN
ew3.
432.
108.
036.
05w
/guy
stub
168
2763
E40
412
BN
ew2.
252.
632
3.43
3.89
1
1882
080/
1882
081E
701
18A
New
1.35
30.0
12
3.95
12.9
52
1881
668E
/188
1669
E70
118
AN
ew1.
601.
632
3.61
2.68
2
1881
667E
/806
447E
701
18A
New
0.95
N/A
Guy
St
ub2
3.43
N/A
2
2115
818E
752
12A
New
3.98
2.01
3.71
2.24
1682
763E
404
12B
New
2.25
2.63
23.
433.
8918
2412
3E40
412
AN
ew3.
303.
754.
575.
355
Dead
end
Pole
(Que
en P
ost)
Tang
ent
Angl
e Bi
sect
or
Corn
er (I
n-lin
ed g
uyed
)
Dead
end
Pole
(Spa
n gu
yed)
H-fr
ame
SPID
A Is
sues
Pole
Con
stru
ctio
n Ty
peSa
fety
Fac
tor
Req'
d to
Pas
sSa
fety
Fac
tor
Req'
d to
Pas
s
F-4.5
6
Results Comparison For Advance Field Survey (See Slide 10-12 for Pole Construction Examples)
Fiel
d Su
rvey
Ten
sion
sSP
IDA
PLS-
CADD
Pole
Heig
htCl
ass
Win
dGr
ade
New
/ In-
Serv
ice
(I.S.
)Po
leGu
yCl
ass
+ Gu
ysPo
leGu
yCl
ass
+ Gu
ys
1437
855E
70H1
12A
New
3.56
N/A
3.81
N/A
1341
082E
752
12A
New
3.06
N/A
3.13
N/A
1172
243E
404
18A
I.S.
1.67
N/A
H11.
85N
/A1
2115
818E
752
12A
New
2.51
2.77
12.
612.
901
1598
122E
504
12A
I.S.
2.45
2.36
22.
332.
533
144
7699
6E75
H112
AN
ew3.
462.
553.
332.
30
2115
779E
752
12A
New
3.36
3.91
9.74
4.74
318
4042
8E
752
12A
New
6.20
3.72
16.5
34.
681,
5w
/guy
stub
182
4123
E40
412
AN
ew4.
014.
525.
927.
0412
4005
1E50
312
AN
ew1.
585.
75H1
2.16
25.9
61
1,5
1437
877E
701
12A
New
4.11
9.76
5.58
34.1
91
w/g
uy st
ub 4
3061
91E
305
12A
I.S.
7.47
4.67
12.6
414
.14
1437
880E
702
12A
I.S.
3.92
13.9
35.
1614
.32
w/g
uy st
ub 1
4379
50E
405
12A
New
12.7
96.
9712
.53
6.95
1682
762E
802
12B
New
3.01
6.51
3.16
6.66
w/g
uy st
ub 1
6827
63E
404
12B
New
2.29
2.72
23.
684.
551
1882
080/
1882
081E
701
18A
New
1.27
21.4
82
4.80
10.4
32
1881
668E
/188
1669
E70
118
AN
ew1.
641.
532
3.61
2.70
2
1881
667E
/806
447E
701
18A
New
0.95
N/A
Guy
Stub
23.
42N
/A2
2115
818E
752
12A
New
2.51
2.77
12.
612.
901
1682
763E
404
12B
New
2.29
2.72
23.
684.
5518
2412
3E40
412
AN
ew4.
014.
525.
927.
045
Dead
end
Pole
(Que
en P
ost)
Spid
aIs
sues
Re
q'd
to P
ass
Safe
ty F
acto
rRe
q'd
to P
ass
Pole
Con
stru
ctio
n Ty
peSa
fety
Fac
tor
Dead
end
Pole
(Spa
n gu
yed)
Corn
er P
ole
(In-li
ned
guye
d)
Angl
e Bi
sect
or
Tang
ent
H-fr
ame
F-4.6
Sum
mar
y of
Fin
ding
s an
d R
ecom
men
datio
ns
7
Iden
tifi
ed G
aps
R
ecom
men
ded
Sol
utio
n St
atus
1 W
ire T
ensio
ns d
o no
t cha
nge
with
pol
e tip
def
lect
ion.
SP
IDA
mod
el n
eeds
to in
corp
orat
e w
ires
into
the
finite
mod
el.
Plan
ned
to b
e in
corp
orat
ed a
s par
t of a
non
-lin
ear
anal
ysis
upda
tes.
2 SP
IDA
can
not e
valu
ate
H-f
ram
e or
any
fr
ame
stru
ctur
e as
they
are
trul
y de
pict
ed.
SPID
A t
o m
odel
mul
ti-po
le
stru
ctur
es a
s the
y tr
uly
appe
ar.
(Pla
nner
s to
use
the
curr
ent j
ob a
id
for
now.
)
On
SPID
A ro
adm
ap fo
r Po
LAR
rele
ase.
3 SC
E us
es a
hig
hly
inac
cura
te p
ole
buck
ling
form
ula
in S
PID
A w
hich
is n
ot
nece
ssar
y sin
ce th
e FE
ana
lysis
de
term
ines
pol
e st
abili
ty.
Pole
buc
klin
g in
SPI
DA
shou
ld b
e re
mov
ed to
pro
vide
mor
e ac
cura
te
pole
load
ing
resu
lts. F
inite
ele
men
t an
alys
is ca
ptur
es th
e co
mpl
ete
stab
ility
of t
he p
ole.
SCE
to u
pdat
e re
quir
emen
ts w
ithin
the
SPID
A c
lient
file
to re
mov
e po
le b
uckl
ing.
4 Ve
ry lo
ng sp
an g
uys n
eed
a la
rge
pre-
stre
ss to
kee
p th
e po
le p
lum
b. S
PID
A
does
not
allo
w p
re-t
ensio
n.
Plan
ners
to b
e al
low
ed to
use
a
tens
ion
adju
stm
ent f
acto
r or
SPI
DA
to
be
upda
ted
to sh
ow tr
ue p
re-
tens
ion
inst
ead
of h
avin
g th
e op
tions
fo
r fu
ll or
slac
k te
nsio
n on
ly.
On
the
road
map
for
incl
usio
n in
to
SPID
ACal
c. S
CE
will
be
heav
ily in
volv
ed in
as
sistin
g w
ith th
e de
sign
and
calc
ulat
ion
logi
c.
5 W
ire T
ensio
ns in
SPI
DA
rem
ain
cons
tant
re
gard
less
of w
ind
angl
e SP
IDA
mod
el n
eeds
to in
corp
orat
e w
ires
into
the
finite
mod
el.
Plan
ned
to b
e in
corp
orat
ed a
s par
t of a
non
-lin
ear
anal
ysis
upda
tes.
`
F-4.7
SPID
A Im
plem
enta
tion
Dat
es
8
Iden
tifi
ed S
olut
ion
R
ecom
men
ded
R
elea
se D
ate
1 2 3 4 5 F-4.8
R
efer
ence
Info
rmat
ion
9
F-4.9
Proj
ect P
lan
10
Iden
tify
pole
co
nstr
uctio
n ty
pes f
or
eval
uatio
n
Com
plet
e fir
st
pass
of
calc
ulat
ion
Com
plet
e se
cond
pas
s of
calc
ulat
ion
Com
plet
e ev
alua
tion
and
mak
e re
com
men
datio
n
Act
ivit
y:
Sele
ct th
ree
sam
ples
for
each
of
the
follo
win
g ty
pe:
1.Ta
ngen
t pol
e w
ith e
qual
te
nsio
n 2.
Ang
le p
ole
(bise
ctor
gu
yed
pole
) 3.
Guy
ed p
ole/
dead
end
pole
(in-
line
guye
d po
le)
4.In
-lin
e sp
an g
uyed
pol
e 5.
H-f
ram
e 6.
Brea
k-of
f R
esp
onsi
bili
ty:
�Se
an to
pro
vide
list
.
�C
hris
and
Nor
m c
an
prov
ide
prev
ious
ca
lcul
atio
n.
Dur
atio
n:
Two
wee
ks
Act
ivit
y:
•Pe
rfor
m p
ole
load
ing
calc
ulat
ion
of 1
5 sa
mpl
e on
SPI
DA
and
PLS
-C
AD
D u
sing
Ediso
n de
faul
t val
ues
Res
pon
sibi
lity
: �
Sean
’s gr
oup
will
pe
rfor
m S
PID
A
calc
ulat
ion
(rev
iew
/val
idat
e)
�N
orm
to p
erfo
rm P
LS-
CA
DD
/PO
LE
calc
ulat
ion
D
urat
ion
: Si
x w
eeks
Act
ivit
y:
•C
ondu
ct fi
eld
surv
ey
•Pe
rfor
m p
ole
load
ing
calc
ulat
ion
of 1
5 sa
mpl
e on
SPI
DA
and
PLS
-C
AD
D u
sing
field
su
rvey
ed d
ata
Res
pon
sibi
lity
: �
Mik
e H
anse
n pe
rfor
ms
field
surv
ey.
�
Sean
’s an
d N
orm
’s te
ams
perf
orm
the
seco
nd p
ass
of c
alcu
latio
n.
Dur
atio
n:
Four
wee
ks
Act
ivit
y:
•C
ompa
re re
sults
bet
wee
n SP
IDA
and
PLS
-C
AD
D/P
OLE
(pol
e ty
pes
and
safe
ty fa
ctor
s)
•Id
entif
y iss
ues,
lim
itatio
n of
SPI
DA
•
Mak
e re
com
men
datio
n
R
esp
onsi
bili
ty:
Team
to le
ad w
rap-
up
Dur
atio
n:
Four
wee
ks
07/2
5/14
09
/02/
14
09/3
0/14
12
/31/
14
We’
re h
ere!
F-4.10
11 Po
le Ty
pe
Elev
atio
n Pl
an V
iew
Tang
ent p
ole
with
equ
al
tens
ion
Ang
le P
ole
(B
i-sec
tor
Guy
ed)
Figu
re 1
El
evat
ion
and
Plan
Vie
w o
f Pol
es E
valu
ated
F-4.11
Pole
Typ
e
Elev
atio
n
Plan
Vie
w
Cor
ner
pole
(in
-lin
e gu
yed
pole
)
Dea
dend
pol
e (s
pan
guye
d po
le)
12
F-4.12
Pole
Typ
e
Elev
atio
n
Plan
Vie
w
H-F
ram
e (w
ith w
ind
guys
) D
eade
nd
Pole
(with
qu
een
post
)
13
F-4.13
Plan
ner (
Chr
is N
orm
an’s
) Not
es o
n SC
E de
faul
t fo
r SPI
DA
and
PLS-
CAD
D
14
�Ty
pica
lly c
olle
cted
dat
a in
clud
e:
�W
ire
span
leng
ths,
ang
les,
size
s, a
nd h
eigh
ts o
f att
achm
ent o
n th
e su
bjec
t pol
e �
Equi
pmen
t typ
es, s
izes
, and
hei
ghts
of a
ttac
hmen
t �
Pole
leng
th, s
peci
es, c
lass
, yea
r se
t, br
and
heig
ht, g
roun
dlin
e ci
rcum
fere
nce,
and
visu
al a
sses
smen
t of p
ole
cond
ition
(w
oodp
ecke
r da
mag
e, e
tc…
) �
Gen
eral
ass
essm
ent o
f the
con
ditio
n of
the
wor
k sit
e (c
rew
ac
cess
, sid
ewal
k re
pair,
ped
estr
ian
and
vehi
cula
r tr
affic
con
trol
re
quir
emen
ts, e
tc…
) �
Plen
ty o
f Pho
tos
F-4.14
15
Figu
re 3
SC
E D
efau
lt D
ata
Exam
ple
F-4.15
Mik
e H
anse
n’s
Not
es o
n Fi
eld
Surv
ey fo
r SPI
DA
and
PLS-
CAD
D 0
8-2
4-2
014
16
�Sp
an le
ngth
�
Ang
le o
f eac
h co
nduc
tor
span
�
Full
inve
ntor
y of
all
cond
ucto
rs
�A
ll tr
ans/
sub
tran
s pol
e da
ta h
as b
een
colle
cted
in th
e fie
ld.
�St
ill n
eed
to c
olle
ct fi
eld
data
on
dist
ribu
tion
pole
s.
�Fi
eld
data
col
lect
ion
is di
ffere
nt a
s we
use
the T
ruA
ngle
or
the T
otal
Sta
tion
surv
eyin
g to
ol to
col
lect
ang
les a
s opp
osed
to th
e Tru
Pulse
onl
y. T
his g
ives
a
muc
h m
ore
repe
atab
le a
nd a
ccur
ate
colle
ctio
n of
ang
les.
�
We
are
also
cap
turi
ng th
e ac
tual
cat
enar
y’s f
or th
e in
divi
dual
co
nduc
tors
/wir
es, a
s wel
l as t
he c
hang
e in
ele
vatio
n fr
om o
ne st
ruct
ure
to
the
next
. We
have
foun
d th
at th
is ca
n al
so b
e do
ne w
ith th
e Tru
Pulse
with
so
me
degr
ee o
f acc
urac
y. T
here
are
still
inst
ance
s whe
re th
e Tru
Pulse
will
gi
ve a
n er
rone
ous r
eadi
ng d
ue to
out
side
mag
net i
nter
fere
nce,
in th
ese
case
s th
e Tru
Ang
le o
r th
e Tot
al S
tatio
n ar
e no
t affe
cted
by
the
outs
ide
cond
ition
s. T
he ti
me
invo
lved
to c
olle
ct th
is da
ta is
long
er th
an n
orm
al d
ue to
the
colle
ctio
n an
d lo
ggin
g of
man
y m
ore
data
poi
nts t
han
wou
ld b
e co
llect
ed b
y a
typi
cal P
LP c
ontr
acto
r.
F-4.16
Figu
re 4
: Ad
vanc
ed F
ield
Sur
vey
Dat
a Ex
ampl
e
17
F-4.17
Figu
re 5
: Ad
vanc
ed F
ield
Sur
vey
Dat
a Ex
ampl
e
18
F-4.18
Tabl
e 1
: Sa
fety
Fac
tors
for W
ood
and
Ligh
t Wei
ght S
teel
(LW
S) P
oles
- N
ew a
nd In
-Ser
vice
Con
stru
ctio
n
19
F-4.19
Tabl
e 2
: Sa
fety
Fac
tors
for J
oint
-Ow
ned
and
Join
t-Use
Pol
es
20
F-4.20
Fi
gure
6:
Cat
enar
y Ex
ampl
e (T
he c
urve
that
a h
angi
ng c
able
ass
umes
und
er it
s ow
n w
eigh
t whe
n su
ppor
ted
only
at i
ts e
nds.
)
21
F-4.21
Func
tiona
l Typ
es o
f Str
uctu
res
(pol
es)
22
�Ta
ngen
t str
uctu
re. T
ange
nt st
ruct
ures
are
the
type
mos
t com
mon
ly u
sed
on a
tran
smiss
ion
line
and
are
used
on
rela
tivel
y st
raig
ht p
ortio
ns o
f the
tran
smiss
ion
line.
Bec
ause
the
cond
ucto
rs a
re in
a r
elat
ivel
y st
raig
ht li
ne p
assin
g th
roug
h th
em, t
ange
nt
stru
ctur
es a
re d
esig
ned
only
to h
andl
e sm
all l
ine
angl
es (c
hang
es in
dir
ectio
n) o
f 0 to
2 d
egre
es. T
ange
nt st
ruct
ures
are
usu
ally
ch
arac
teri
zed
by su
spen
sion
(ver
tical
) ins
ulat
ors,
whi
ch su
ppor
t and
insu
late
the
cond
ucto
rs a
nd tr
ansf
er w
ind
and
wei
ght l
oads
to
the
stru
ctur
e.
�A
ngle
str
uctu
re. A
ngle
stru
ctur
es a
re u
sed
whe
re tr
ansm
issio
n lin
e co
nduc
tors
cha
nge
dire
ctio
n. T
hese
type
s of s
truc
ture
s are
de
signe
d to
with
stan
d th
e fo
rces
pla
ced
on th
em b
y th
e ch
ange
in d
irec
tion.
Ang
le st
ruct
ures
may
be:
(1) s
imila
r to
tang
ent
stru
ctur
es, u
sing
susp
ensio
n in
sula
tors
to a
ttac
h th
e co
nduc
tors
and
tran
sfer
win
d, w
eigh
t, an
d lin
e an
gle
load
s to
the
stru
ctur
e; o
r (2
) sim
ilar
to st
rain
or
dead
-end
stru
ctur
es, u
sing
insu
lato
rs in
seri
es w
ith th
e co
nduc
tors
to b
ring
win
d, w
eigh
t, an
d lin
e an
gle
load
s dir
ectly
to th
e st
ruct
ure.
�D
ead
-end
str
uctu
re. A
dea
d-en
d st
ruct
ure
is ty
pica
lly u
sed
whe
re tr
ansm
issio
n lin
e co
nduc
tors
turn
at a
wid
e an
gle
or e
nd.
Com
pare
d to
tang
ent s
truc
ture
s, a
dea
d-en
d st
ruct
ure
is de
signe
d to
be
stro
nger
and
ofte
n is
a la
rger
stru
ctur
e. T
ypic
ally,
insu
lato
rs
on a
dea
d-en
d st
ruct
ure
are
in se
ries
with
the
cond
ucto
rs (h
oriz
onta
l) to
bri
ng w
ind,
wei
ght,
and
line
angl
e lo
ads d
irec
tly to
the
stru
ctur
e. A
dea
d-en
d st
ruct
ure
is de
signe
d to
resis
t the
full
unba
lanc
ed te
nsio
n th
at w
ould
occ
ur if
all
cond
ucto
rs w
ere
rem
oved
fr
om o
ne fa
ce o
f the
stru
ctur
e.
�St
rain
str
uctu
re. A
stra
in st
ruct
ure
is sim
ilar
in a
ppea
ranc
e an
d de
sign
stre
ngth
to a
tang
ent s
truc
ture
. The
diff
eren
ce in
ap
pear
ance
is th
e co
nduc
tor a
ttac
hmen
t har
dwar
e. T
he c
ondu
ctor
att
achm
ent h
ardw
are
is th
e sa
me
as a
dea
dend
or
larg
e an
gle,
w
here
the
insu
lato
r bel
ls ar
e in
line
with
the
cond
ucto
r. W
here
as a
dea
d-en
d st
ruct
ure
is de
signe
d to
with
stan
d th
e fu
ll un
bala
nced
te
nsio
n th
at w
ould
occ
ur fr
om th
e lo
ss o
f all
cond
ucto
rs fr
om o
ne fa
ce o
f the
stru
ctur
e, a
stra
in st
ruct
ure
is de
signe
d to
with
stan
d on
ly u
nbal
ance
d te
nsio
ns a
ssoc
iate
d w
ith th
e lo
ss o
f a si
ngle
pha
se (b
undl
e of
two
cond
ucto
rs) o
n on
e fa
ce o
f the
stru
ctur
e.
F-4.22
T&
D E
ngin
eeri
ng09
/9/2
014
Engi
neer
ing
Eval
uatio
n fo
rSP
IDA
F-5
2
�O
bjec
tives
: 1.
Perf
orm
eng
inee
ring
eva
luat
ion
of S
PID
A b
y co
mpa
ring
with
PL
S-C
AD
D/P
LS-P
OLE
2.Id
entif
y an
y ga
ps w
ithin
SPI
DA
3.R
ecom
men
d pr
oces
s for
bri
dgin
g th
ose
gaps
F-6
Prop
osed
Pro
ject
Pla
n
3
Iden
tify
pole
co
nstr
uctio
n ty
pes f
or
eval
uatio
n
Com
plet
e fir
st
pass
of
calc
ulat
ion
Com
plet
e se
cond
pas
s of
calc
ulat
ion
Com
plet
e ev
alua
tion
and
mak
e re
com
men
datio
n
Act
ivit
y:Se
lect
thre
e sa
mpl
es fo
r ea
ch
of th
e fo
llow
ing
type
:1.
Tang
ent p
ole
with
equ
al
tens
ion
2.A
ngle
pol
e (b
isect
or
guye
d po
le)
3.G
uyed
pol
e/de
aden
d po
le (i
n-lin
e gu
yed
pole
)4.
In-li
ne sp
an g
uyed
pol
e5.
H-f
ram
e6.
Brea
k-of
f
Res
pon
sibi
lity
: �
Sean
to p
rovi
de li
st.
�C
hris
and
Nor
m c
an
prov
ide
prev
ious
ca
lcul
atio
n.D
urat
ion:
Tw
o w
eeks
Act
ivit
y:•
Perf
orm
pol
e lo
adin
g ca
lcul
atio
n of
15
sam
ple
on S
PID
A a
nd P
LS-
CA
DD
usin
g Ed
ison
defa
ult v
alue
s
Res
pon
sibi
lity
: �
Sean
’s gr
oup
will
pe
rfor
m S
PID
A
calc
ulat
ion
(rev
iew
/val
idat
e)�
Nor
m to
per
form
PLS
-C
AD
D/P
OLE
ca
lcul
atio
n
Dur
atio
n:
Six
wee
ks
Act
ivit
y:•
Con
duct
fiel
d su
rvey
•
Perf
orm
pol
e lo
adin
g ca
lcul
atio
n of
15
sam
ple
on S
PID
A a
nd P
LS-
CA
DD
usin
g fie
ld
surv
eyed
dat
a
Res
pon
sibi
lity
:�
Mik
e H
anse
n pe
rfor
ms
field
surv
ey.
�Se
an’s
and
Nor
m’s
team
s pe
rfor
m th
e se
cond
pas
s of
cal
cula
tion.
Dur
atio
n:
Two
wee
ks
Act
ivit
y:•
Com
pare
res
ults
bet
wee
n SP
IDA
and
PLS
-C
AD
D/P
OLE
(po
le ty
pes
and
safe
ty fa
ctor
s)•
Iden
tify
issue
s, li
mita
tion
of S
PID
A•
Mak
e re
com
men
datio
n
Res
pon
sibi
lity
:
Thu
an to
lead
the
wra
p-up
Dur
atio
n:
Two
wee
ks
07/2
5/14
09/0
2/14
09/1
6/14
09/3
0/14
?W
e’re
her
e!
Nee
d 4
Extr
asW
eeks
!
F-7
Adva
nced
Fie
ld
Surv
ey D
ata
4
�SP
IDA
and
PLS
-CA
DD
: �
Rev
ised
tens
ions
bas
ed o
n ad
vanc
ed fi
eld
stud
y an
d ad
vanc
ed fi
eldi
ng e
quip
men
t (t
otal
stat
ion)
�Sa
g, w
eath
er, a
nd c
urre
nt u
sed
to
dete
rmin
e ac
tual
max
imum
wir
e te
nsio
ns
�PL
S-C
AD
D o
nly:
�U
nlev
elsp
ans a
nd u
nequ
al sp
an
leng
ths c
onsid
ered
�SP
IDA
onl
y:�
All
span
s mod
eled
as l
evel
span
s and
sh
ort s
pan/
long
span
inte
ract
ions
ig
nore
d (c
an’t
be c
alcu
late
d in
cu
rren
t ver
sion
of to
ol)
SCE
Def
aults
�SP
IDA
and
PLS
-CA
DD
:�
Def
ault
max
imum
wir
e te
nsio
ns
from
TO
H/D
OH
�St
anda
rd fi
eldi
ng p
ract
ices
�St
anda
rd fi
eldi
ng e
quip
men
t
�PL
S-C
AD
D o
nly:
�St
anda
rd P
LS-C
AD
D d
esig
n pa
ram
eter
s for
woo
d po
les
�SP
IDA
onl
y:�
Stan
dard
SPI
DA
clie
nt fi
le (d
esig
n pa
ram
eter
s)
Sum
mar
y of
Inp
ut D
ata
to
SPID
A a
nd P
LS-C
AD
D
F-8
5
Pole
�Cl
ass
Pole
�Cl
ass
Pole
�Cl
ass
Pole
�Cl
ass
Pole
Guy
Pole
Guy
Pole
Guy
Pole
Guy
Tang
ent
1437
855E
3.56
H13.
84H1
1341
082E
3.96
H14.
00H1
1172
243E
Angl
e�Bi
sect
or21
1581
8E3.
852.
081
4.17
2.10
115
9812
2E0.
790.
864
5.20
1.45
444
7699
6E4.
252.
27H1
4.58
2.02
H1In
�line
d�gu
yed
4093
588E
4.53
2.66
H34.
442.
63H3
1840
428E
�3.
122.
151
13.3
83.
091
w/g
uy�st
ub�1
8241
23E
1.61
2.21
16.
749.
381
1240
051E
Span
�guy
ed14
3787
7E4.
606.
851
5.19
7.88
1w
/guy
�stub
�430
6191
E5.
693.
475
8.04
5.03
514
3788
0E4.
8411
.37
26.
2715
.69
2w
/guy
�stub
�143
7950
E12
.38
5.80
512
.61
7.46
516
8276
2E5.
632.
14H1
10.7
44.
60H1
w/g
uy�st
ub�1
6827
63E
see�
unde
r�que
en�p
ost
1024
970E
�(G
T951
50�&
�120
4969
E)H�
fram
e18
8208
0/18
8208
1E4.
481.
311
3.52
5.47
118
8166
8E/1
8816
69E
0.73
0.97
13.
712.
691
1881
667E
/806
447E
0.96
0.61
H13.
439.
04H1
Que
en�P
ost
2115
818E
3.85
2.08
14.
172.
101
1682
763E
3.39
2.96
14.
554.
001
1824
123E
1.61
2.21
16.
749.
381
Safe
ty�F
acto
r
SPID
APL
S�CA
DDSC
E�de
faul
tsFi
eld�
surv
eySC
E�de
faul
tsFi
eld�
surv
ey
Safe
ty�F
acto
rSa
fety
�Fac
tor
Safe
ty�F
acto
rPo
le�C
onst
ruct
ion�
Type
Results Comparison
F-9
Ref
eren
ce In
form
atio
n
6
F-10
7
Pole
Typ
eEl
evat
ion
Plan
Vie
w
Tang
ent p
ole
with
equ
al
tens
ion
Ang
le p
ole
(in-li
ne g
uyed
po
le)
Elev
atio
n an
d Pl
an V
iew
of P
oles
Eva
luat
ed
F-11
Pole
Typ
eEl
evat
ion
Plan
Vie
w
Guy
ed
pole
/dea
den
d po
le (s
pan
guye
d po
le)
H-F
ram
e(w
ith w
ind
guys
)
Ang
lePo
le
(Bi-s
ecto
r G
uyed
)
8
F-12
Det
ail I
nput
Dat
a in
to S
PID
A an
d PL
S-CA
DD
(Edi
son
defa
ult v
alue
s an
d fie
ld s
urve
yed
data
)
9
F-13
Iden
tifi
ed P
oles
for
SPID
A/P
LS-C
AD
D
10
Wor
k�O
rder
�Num
ber
Pole
�Num
ber
Que
en�P
ost
Tang
ent
Angl
e�Bi
sect
orIn
�Lin
e�G
uyed
Span
�Guy
sH
�Fra
me
TD81
1782
1437
855E
114
3787
7E1
4306
191E
1�(s
tub�
to�a
bove
)14
3795
0E2(
stub
�to�b
elow
)14
3788
0E2
TD80
5958
2115
818E
11
1882
081E
118
8166
8E2
1881
667E
347
6264
3E3�
(stu
b�to
�abo
ve)
TD72
4631
4093
588E
1�(H
�Fra
me)
1341
082E
2
TD83
7814
1682
762E
316
8276
3E2
3�(s
tub�
to�a
bove
)TD
8117
7244
7699
6E2
TD83
9055
1840
428E
218
2412
3E3
2�(s
tub�
to�a
bove
)
Dist
ribut
ion�
Onl
y�Po
les
1240
051E
311
7224
3E3
1598
122E
310
2497
0E4
GT9
5150
4��w
ill�n
eed�
for�
poin
t�loa
ds
1204
969E
4��w
ill�n
eed�
for�
poin
t�loa
ds
F-14
11
�W
hy a
re w
e d
oing
thi
s?�
Ken
Tra
inor
asks
Eng
inee
ring
to p
rovi
de a
n in
depe
nden
t eng
inee
ring
rev
iew
of
SPID
A
�W
hy d
oes
Ken
ask
us
to e
valu
ate
SPID
A?
�C
onsid
erin
g al
l im
prov
emen
ts/c
orre
ctio
ns h
ave
been
com
plet
ed o
n SP
IDA
for
prod
uctio
n w
ork,
why
doe
s SPI
DA
still
pro
duce
sign
ifica
ntly
larg
er p
oles
?
�D
id w
e be
nchm
ark
resu
lts p
rodu
ced
by S
PID
A w
ith P
LSC
AD
?
�Is
PLS
CA
D th
e ba
selin
e to
ol fo
r po
le lo
adin
g ca
lcul
atio
n?
�A
re w
e th
e on
ly u
tility
usin
g SP
IDA
for
this
mas
sive
unde
rtak
ing
(pol
e lo
adin
g 1.
5 m
illio
n po
les)
?
�D
ata
poin
ts: S
DG
&E
does
not
use
SPI
DA
for
thei
r po
le m
itiga
tion.
The
y us
e PL
SCA
D fo
r sm
alle
r an
d fo
cuse
d sc
ope.
F-15
12
�SP
IDA
fails
6,0
00 o
ut o
f 20,
000
�SP
IDA
doe
s wor
k on
tang
ent p
oles
, nee
d to
SPI
DA
’s ca
pabi
lity
in e
valu
atin
g on
oth
er ty
pes.
F-16
Func
tion
al Ty
pes
of S
truc
ture
s (p
oles
)
13
�Ta
ngen
t st
ruct
ure.
Tan
gent
stru
ctur
es a
re th
e ty
pe m
ost c
omm
only
use
d on
a tr
ansm
issio
n lin
e an
d ar
e us
ed o
n re
lativ
ely
stra
ight
por
tions
of t
he tr
ansm
issio
n lin
e. B
ecau
se th
e co
nduc
tors
are
in a
rel
ativ
ely
stra
ight
line
pas
sing
thro
ugh
them
, tan
gent
st
ruct
ures
are
des
igne
d on
ly to
han
dle
smal
l lin
e an
gles
(cha
nges
in d
irec
tion)
of 0
to 2
deg
rees
. Tan
gent
stru
ctur
es a
re u
sual
ly
char
acte
rize
d by
susp
ensio
n (v
ertic
al) i
nsul
ator
s, w
hich
supp
ort a
nd in
sula
te th
e co
nduc
tors
and
tran
sfer
win
d an
d w
eigh
t loa
ds to
th
e st
ruct
ure.
�A
ngle
str
uctu
re. A
ngle
stru
ctur
es a
re u
sed
whe
re tr
ansm
issio
n lin
e co
nduc
tors
cha
nge
dire
ctio
n. T
hese
type
s of s
truc
ture
s are
de
signe
d to
with
stan
d th
e fo
rces
pla
ced
on th
em b
y th
e ch
ange
in d
irec
tion.
Ang
le st
ruct
ures
may
be:
(1) s
imila
r to
tang
ent
stru
ctur
es, u
sing
susp
ensio
n in
sula
tors
to a
ttac
h th
e co
nduc
tors
and
tran
sfer
win
d, w
eigh
t, an
d lin
e an
gle
load
s to
the
stru
ctur
e; o
r (2
) sim
ilar
to st
rain
or
dead
-end
stru
ctur
es, u
sing
insu
lato
rs in
seri
es w
ith th
e co
nduc
tors
to b
ring
win
d, w
eigh
t, an
d lin
e an
gle
load
s dir
ectly
to th
e st
ruct
ure.
�D
ead
-end
str
uctu
re. A
dea
d-en
d st
ruct
ure
is ty
pica
lly u
sed
whe
re tr
ansm
issio
n lin
e co
nduc
tors
turn
at a
wid
e an
gle
or e
nd.
Com
pare
d to
tang
ent s
truc
ture
s, a
dea
d-en
d st
ruct
ure
is de
signe
d to
be
stro
nger
and
ofte
n is
a la
rger
stru
ctur
e. T
ypic
ally,
insu
lato
rs
on a
dea
d-en
d st
ruct
ure
are
in se
ries
with
the
cond
ucto
rs (h
oriz
onta
l) to
bri
ng w
ind,
wei
ght,
and
line
angl
e lo
ads d
irec
tly to
the
stru
ctur
e. A
dea
d-en
d st
ruct
ure
is de
signe
d to
res
ist th
e fu
ll un
bala
nced
tens
ion
that
wou
ld o
ccur
if a
ll co
nduc
tors
wer
e re
mov
ed
from
one
face
of t
he st
ruct
ure.
�St
rain
str
uctu
re. A
stra
in st
ruct
ure
is sim
ilar
in a
ppea
ranc
e an
d de
sign
stre
ngth
to a
tang
ent s
truc
ture
. The
diff
eren
ce in
ap
pear
ance
is th
e co
nduc
tor
atta
chm
ent h
ardw
are.
The
con
duct
or a
ttac
hmen
t har
dwar
e is
the
sam
e as
a d
eade
ndor
larg
e an
gle,
w
here
the
insu
lato
r be
lls a
re in
line
with
the
cond
ucto
r. W
here
as a
dea
d-en
d st
ruct
ure
is de
signe
d to
with
stan
d th
e fu
ll un
bala
nced
te
nsio
n th
at w
ould
occ
ur fr
om th
e lo
ss o
f all
cond
ucto
rs fr
om o
ne fa
ce o
f the
stru
ctur
e, a
stra
in st
ruct
ure
is de
signe
d to
with
stan
d on
ly u
nbal
ance
d te
nsio
ns a
ssoc
iate
d w
ith th
e lo
ss o
f a si
ngle
pha
se (b
undl
e of
two
cond
ucto
rs) o
n on
e fa
ce o
f the
stru
ctur
e.
F-17
T&
D E
ngin
eeri
ng11
/13/
2014
Engi
neer
ing
Eval
uatio
n fo
rSP
IDA
F-18
Proj
ect P
lan
2
�O
bjec
tives
: 1.
Perf
orm
eng
inee
ring
eva
luat
ion
of S
PID
A b
y co
mpa
ring
with
PL
S-C
AD
D/P
LS-P
OLE
2.Id
entif
y an
y ga
ps w
ithin
SPI
DA
3.R
ecom
men
d pr
oces
s for
bri
dgin
g th
ose
gaps
Iden
tify
pole
co
nstr
uctio
n ty
pes f
or
eval
uatio
n
Com
plet
e fir
st
pass
of
calc
ulat
ion
Com
plet
e se
cond
pas
s of
calc
ulat
ion
Com
plet
e ev
alua
tion
and
mak
e re
com
men
datio
n
Dur
atio
n:
Two
wee
ksD
urat
ion:
Si
x w
eeks
Dur
atio
n:
Eigh
t wee
ksD
urat
ion:
Fo
ur w
eeks
07/2
5/14
09/0
2/14
10/3
1/14
11/3
0/14
We’
re h
ere!
F-19
Exec
utiv
e Su
mm
ary
(Pla
ceho
lder
Thu
an)
3
�N
ine
out o
f 18
pole
s fai
led
by S
PID
A, c
ompa
red
to tw
o in
PS
-CA
DD
. m
itpo
leBr
iefd
escr
iptio
n of
the
eval
uatio
n pr
oces
s (co
nden
se v
ersio
n of
the
proj
ect p
lan)
�Su
mm
ary
of th
e be
nchm
ark
test
(fro
m th
e re
sult
com
pari
son
tabl
e):
�H
ow m
any
sam
ples
, how
SPI
DA
stat
istic
ally
com
pare
s with
PL
S-C
AD
D�
Whe
re S
PID
A d
oes w
ell,
whe
re it
falls
out
�H
ow fa
r ap
art i
s SPI
DA
from
PLS
-CA
DD
in te
rms o
f saf
ety
fact
or
�H
igh
leve
l of r
ecom
men
datio
ns to
clo
se th
e id
entif
ied
gaps
F-20
Adva
nced
Fie
ld S
urve
y D
ata
(See
Slid
es 1
6-1
8 fo
r Fie
ld S
urve
y Ex
ampl
e)
4
�SP
IDA
and
PLS
-CA
DD
: �
Rev
ised
tens
ions
bas
ed o
n ad
vanc
ed fi
eld
stud
y an
d ad
vanc
ed fi
eldi
ng e
quip
men
t (t
otal
stat
ion)
�Sa
g, w
eath
er, a
nd c
urre
nt u
sed
to
dete
rmin
e ac
tual
max
imum
wir
e te
nsio
ns
�PL
S-C
AD
D o
nly:
�U
nlev
elsp
ans a
nd u
nequ
al sp
an
leng
ths c
onsid
ered
�SP
IDA
onl
y:�
All
span
s mod
eled
as l
evel
span
s and
sh
ort s
pan/
long
span
inte
ract
ions
ig
nore
d (c
an’t
be c
alcu
late
d in
cu
rren
t ver
sion
of to
ol)
SCE
Def
aults
(See
Slid
es 1
4-1
5 fo
r SC
E D
efau
lt Ex
ampl
e)
�SP
IDA
and
PLS
-CA
DD
:�
Def
ault
max
imum
wir
e te
nsio
ns
from
TO
H/D
OH
�St
anda
rd fi
eldi
ng p
ract
ices
�St
anda
rd fi
eldi
ng e
quip
men
t
�PL
S-C
AD
D o
nly:
�St
anda
rd P
LS-C
AD
D d
esig
n pa
ram
eter
s for
woo
d po
les
�SP
IDA
onl
y:�
Stan
dard
SPI
DA
clie
nt fi
le (d
esig
n pa
ram
eter
s)
Sum
mar
y of
Inpu
t Dat
a to
SPI
DA
and
PLS-
CAD
D
F-21
5
Results Comparison For SCE Defaults(See Slides 10-12 for Pole Construction Examples)
SCE�
Defa
ult�T
ensi
ons
SPID
APL
S�CA
DD
Pole
Heig
htCl
ass
Win
dGr
ade
New
/In
�Ser
vice
�(I.
S.)
Pole
Guy
Clas
s+�
Guys
Pole
Guy
Clas
s+�
Guys
Tang
ent
1437
855E
70H1
12A
New
3.56
N/A
3.84
N/A
1341
082E
752
12A
New
3.06
N/A
3.17
N/A
1172
243E
404
18A
I.S.
1.71
N/A
H11.
88N
/A1
Angl
e�Bi
sect
or21
1581
8E75
212
AN
ew3.
982.
013.
712.
2415
9812
2E50
412
AI.S
.1.
140.
831
65.
832.
121
4476
996E
75H1
12A
New
3.82
2.08
6.04
2.08
3In
�line
d�gu
yed
2115
779E
752
12A
New
1.72
2.26
H25.
603.
043
1840
428E
�75
212
AN
ew3.
172.
408.
592.
461,
5w
/guy
�stub
�182
4123
E40
412
AN
ew3.
303.
754.
575.
3512
4005
1E50
312
AN
ew1.
616.
95H1
2.20
25.1
91
1,5
Span
�guy
ed14
3787
7E70
112
AN
ew4.
656.
885.
6115
.66
1w
/guy
�stub
�430
6191
E30
512
AI.S
.5.
953.
5711
.27
9.69
1437
880E
702
12A
I.S.
4.20
12.9
85.
6514
.39
w/g
uy�st
ub�1
4379
50E
405
12A
New
12.6
76.
5412
.55
6.98
1682
762E
802
12B
New
3.43
2.10
8.03
6.05
w/g
uy�st
ub�1
6827
63E
404
12B
New
2.25
2.63
23.
433.
891
H�fr
ame
1882
080/
1882
081E
701
18A
New
1.35
30.0
12
3.95
12.9
52
1881
668E
/188
1669
E70
118
AN
ew1.
601.
632
3.61
2.68
2
1881
667E
/806
447E
701
18A
New
0.95
N/A
�Guy
�St
ub2
3.43
N/A
2Q
ueen
�Pos
t21
1581
8E75
212
AN
ew3.
982.
013.
712.
2416
8276
3E40
412
BN
ew2.
252.
632
3.43
3.89
1824
123E
404
12A
New
3.30
3.75
4.57
5.35
5
SPID
A�Is
sues
Pole
�Con
stru
ctio
n�Ty
peSa
fety
�Fac
tor
Req'
d�to
�Pas
sSa
fety
�Fac
tor
Req'
d�to
�Pas
s
F-22
6
Results Comparison For Advance Field Survey(See Slide 10-12 for Pole Construction Examples)
Fiel
d�Su
rvey
�Ten
sion
sSP
IDA
PLS�
CADD
Pole
Heig
htCl
ass
Win
dGr
ade
New
/�In�
Serv
ice�
(I.S.
)Po
leGu
yCl
ass
+�Gu
ysPo
leGu
yCl
ass
+�Gu
ysTa
ngen
t14
3785
5E70
H112
AN
ew3.
56N
/A3.
81N
/A13
4108
2E75
212
AN
ew3.
06N
/A3.
13N
/A11
7224
3E40
418
AI.S
.1.
67N
/AH1
1.85
N/A
1An
gle�
Bise
ctor
2115
818E
752
12A
New
2.51
2.77
12.
612.
901
1598
122E
504
12A
I.S.
2.45
2.36
22.
332.
533
144
7699
6E75
H112
AN
ew3.
462.
553.
332.
30In
�line
d�gu
yed
2115
779E
752
12A
New
3.36
3.91
9.74
4.74
318
4042
8E�
752
12A
New
6.20
3.72
16.5
34.
681,
5w
/guy
�stub
�182
4123
E40
412
AN
ew4.
014.
525.
927.
0412
4005
1E50
312
AN
ew1.
585.
75H1
2.16
25.9
61
1,5
Span
�guy
ed14
3787
7E70
112
AN
ew4.
119.
765.
5834
.19
1w
/guy
�stub
�430
6191
E30
512
AI.S
.7.
474.
6712
.64
14.1
414
3788
0E70
212
AI.S
.3.
9213
.93
5.16
14.3
2w
/guy
�stub
�143
7950
E40
512
AN
ew12
.79
6.97
12.5
36.
9516
8276
2E80
212
BN
ew3.
016.
513.
166.
66w
/guy
�stub
�168
2763
E40
412
BN
ew2.
292.
722
3.68
4.55
1H�
fram
e18
8208
0/18
8208
1E70
118
AN
ew1.
2721
.48
24.
8010
.43
218
8166
8E/1
8816
69E
701
18A
New
1.64
1.53
23.
612.
702
1881
667E
/806
447E
701
18A
New
0.95
N/A
Guy�
Stub
23.
42N
/A2
Que
en�P
ost
2115
818E
752
12A
New
2.51
2.77
12.
612.
901
1682
763E
404
12B
New
2.29
2.72
23.
684.
5518
2412
3E40
412
AN
ew4.
014.
525.
927.
045
Spid
aIs
sues
�Re
q'd�
to�P
ass
Safe
ty�F
acto
rRe
q'd�
to�P
ass
Pole
�Con
stru
ctio
n�Ty
peSa
fety
�Fac
tor
F-23
Sum
mar
y of
Fin
ding
s an
d R
ecom
men
datio
ns
7
Iden
tifi
ed G
aps
Rec
omm
end
ed S
olut
ion
Stat
us
1W
ire T
ensio
ns d
o no
t cha
nge
with
pol
e tip
def
lect
ion.
SPID
A m
odel
need
s to
inco
rpor
ate
wir
es in
to th
e fin
ite m
odel
.Pl
anne
d to
be
inco
rpor
ated
as p
art o
f ano
n-lin
ear
anal
ysis
upda
tes.
2SP
IDA
can
not e
valu
ate
H-f
ram
e or
any
fr
ame
stru
ctur
e as
they
are
trul
y de
pict
ed.
SPID
Ato
mod
el m
ulti-
pole
st
ruct
ures
as t
hey
trul
y ap
pear
. Pl
anne
rs to
use
the
curr
ent j
ob a
id.
On
SPID
A r
oadm
ap fo
r Po
LAR
rel
ease
.
3SC
E us
es a
hig
hly
inac
cura
te p
ole
buck
ling
form
ula
in S
PID
A w
hich
is n
ot
nece
ssar
y sin
ce th
e FE
ana
lysis
de
term
ines
pol
e st
abili
ty.
Pole
buc
klin
g in
SPI
DA
shou
ld b
e re
mov
ed to
pro
vide
mor
e ac
cura
te
pole
load
ing
resu
lts.
SCE
to u
pdat
e re
quir
emen
ts w
ithin
the
SPID
A c
lient
file
to r
emov
e po
le b
uckl
ing.
4Ve
ry lo
ng sp
an g
uys n
eed
a la
rge
pre-
stre
ss to
kee
p th
e po
le p
lum
b. S
PID
A
does
not
allo
w p
re-t
ensio
n.
Plan
ners
to b
e al
low
edto
use
a
tens
ion
adju
stm
ent f
acto
r or
SPI
DA
to
be
upda
ted
to sh
ow tr
ue p
re-
tens
ion
inst
ead
of h
avin
g th
e op
tions
fo
r fu
ll or
slac
k te
nsio
n on
ly.
On
the
road
map
for
incl
usio
n in
to S
PID
ACal
c v5
.4.S
CE
will
be
heav
ily in
volv
ed in
ass
istin
g w
ith th
e de
sign
and
calc
ulat
ion
logi
c.
5W
ire T
ensio
ns in
SPI
DA
rem
ain
cons
tant
re
gard
less
of w
ind
angl
eSP
IDA
mod
elne
eds t
o in
corp
orat
e w
ires
into
the
finite
mod
el.
Plan
ned
to b
e in
corp
orat
ed a
s par
t of a
non-
linea
r an
alys
is up
date
s. `
6T
he p
rogr
am a
ssum
es a
fixe
d po
le
grou
nd li
ne.
Thi
s ite
mis
addr
esse
d as
oth
er
anal
ysis
is ad
just
ed w
ithin
the
prog
ram
.
SPID
A is
wor
king
to in
corp
orat
e fo
unda
tiona
l an
alys
is in
to S
PID
ACal
c.
F-24
Ref
eren
ce In
form
atio
n
8
F-25
Proj
ect P
lan
9
Iden
tify
pole
co
nstr
uctio
n ty
pes f
or
eval
uatio
n
Com
plet
e fir
st
pass
of
calc
ulat
ion
Com
plet
e se
cond
pas
s of
calc
ulat
ion
Com
plet
e ev
alua
tion
and
mak
e re
com
men
datio
n
Act
ivit
y:Se
lect
thre
e sa
mpl
es fo
r ea
ch
of th
e fo
llow
ing
type
:1.
Tang
ent p
ole
with
equ
al
tens
ion
2.A
ngle
pol
e (b
isect
or
guye
d po
le)
3.G
uyed
pol
e/de
aden
d po
le (i
n-lin
e gu
yed
pole
)4.
In-li
ne sp
an g
uyed
pol
e5.
H-f
ram
e6.
Brea
k-of
f
Res
pon
sibi
lity
: �
Sean
to p
rovi
de li
st.
�C
hris
and
Nor
m c
an
prov
ide
prev
ious
ca
lcul
atio
n.D
urat
ion:
Tw
o w
eeks
Act
ivit
y:•
Perf
orm
pol
e lo
adin
g ca
lcul
atio
n of
15
sam
ple
on S
PID
A a
nd P
LS-
CA
DD
usin
g Ed
ison
defa
ult v
alue
s
Res
pon
sibi
lity
: �
Sean
’s gr
oup
will
pe
rfor
m S
PID
A
calc
ulat
ion
(rev
iew
/val
idat
e)�
Nor
m to
per
form
PLS
-C
AD
D/P
OLE
ca
lcul
atio
n
Dur
atio
n:
Six
wee
ks
Act
ivit
y:•
Con
duct
fiel
d su
rvey
•
Perf
orm
pol
e lo
adin
g ca
lcul
atio
n of
15
sam
ple
on S
PID
A a
nd P
LS-
CA
DD
usin
g fie
ld
surv
eyed
dat
a
Res
pon
sibi
lity
:�
Mik
e H
anse
n pe
rfor
ms
field
surv
ey.
�Se
an’s
and
Nor
m’s
team
s pe
rfor
m th
e se
cond
pas
s of
cal
cula
tion.
Dur
atio
n:
Four
wee
ks
Act
ivit
y:•
Com
pare
res
ults
bet
wee
n SP
IDA
and
PLS
-C
AD
D/P
OLE
(po
le ty
pes
and
safe
ty fa
ctor
s)•
Iden
tify
issue
s, li
mita
tion
of S
PID
A•
Mak
e re
com
men
datio
n
Res
pon
sibi
lity
:
Team
to le
ad w
rap-
up
Dur
atio
n:
Four
wee
ks
07/2
5/14
09/0
2/14
09/3
0/14
12/3
1/14
We’
re h
ere!
F-26
10
Pole
Typ
eEl
evat
ion
Plan
Vie
w
Tang
ent p
ole
with
equ
al
tens
ion
Ang
lePo
le
(Bi-s
ecto
r G
uyed
)
Figu
re 1
Elev
atio
n an
d Pl
an V
iew
of P
oles
Eva
luat
ed
F-27
Pole
Typ
eEl
evat
ion
Plan
Vie
w
Ang
le p
ole
(in-li
ne g
uyed
po
le)
Guy
ed
pole
/dea
dend
po
le (s
pan
guye
d po
le)
11
F-28
Pole
Typ
eEl
evat
ion
Plan
Vie
w
H-F
ram
e(w
ith w
ind
guys
)
Dea
dend
(w
ith q
ueen
po
st)
12
F-29
Figu
re 2
Iden
tifie
d Po
les
for S
PID
A/PL
S-CA
DD
13
Wor
k�O
rder
�Num
ber
Pole
�Num
ber
Que
en�P
ost
Tang
ent
Angl
e�Bi
sect
orIn
�Lin
e�G
uyed
Span
�Guy
sH
�Fra
me
TD81
1782
1437
855E
114
3787
7E1
4306
191E
1�(s
tub�
to�a
bove
)14
3795
0E2(
stub
�to�b
elow
)14
3788
0E2
TD80
5958
2115
818E
11
1882
081E
118
8166
8E2
1881
667E
347
6264
3E3�
(stu
b�to
�abo
ve)
TD72
4631
4093
588E
1�(H
�Fra
me)
1341
082E
2
TD83
7814
1682
762E
316
8276
3E2
3�(s
tub�
to�a
bove
)TD
8117
7244
7699
6E2
TD83
9055
1840
428E
218
2412
3E3
2�(s
tub�
to�a
bove
)
Dist
ribut
ion�
Onl
y�Po
les
1240
051E
311
7224
3E3
1598
122E
310
2497
0E4
GT9
5150
4��w
ill�n
eed�
for�
poin
t�loa
ds
1204
969E
4��w
ill�n
eed�
for�
poin
t�loa
ds
F-30
Plan
ner (
Chris
Nor
man
’s) N
otes
on
SCE
defa
ult
for S
PID
A an
d PL
S-CA
DD
14
�Ty
pica
lly c
olle
cted
dat
a in
clud
e:�
Wir
e sp
an le
ngth
s, a
ngle
s, si
zes,
and
hei
ghts
of a
ttac
hmen
t on
the
subj
ect p
ole
�Eq
uipm
ent t
ypes
, siz
es, a
nd h
eigh
ts o
f att
achm
ent
�Po
le le
ngth
, spe
cies
, cla
ss, y
ear
set,
bran
d he
ight
, gro
undl
ine
circ
umfe
renc
e, a
nd v
isual
ass
essm
ent o
f pol
e co
nditi
on
(woo
dpec
ker
dam
age,
etc
…)
�G
ener
al a
sses
smen
t of t
he c
ondi
tion
of th
e w
ork
site
(cre
w
acce
ss, s
idew
alk
repa
ir, p
edes
tria
n an
d ve
hicu
lar
traf
fic c
ontr
ol
requ
irem
ents
, etc
…)
�Pl
enty
of P
hoto
s
F-31
15
Figu
re 3
SCE
Def
ault
Dat
a Ex
ampl
e
F-32
Mik
e H
anse
n’s
Not
es o
n Fi
eld
Surv
ey fo
r SPI
DA
and
PLS-
CAD
D 0
8-2
4-2
014
16
�Sp
an le
ngth
�A
ngle
of e
ach
cond
ucto
r sp
an�
Full
inve
ntor
y of
all
cond
ucto
rs�
All
tran
s/su
b tr
ans p
ole
data
has
bee
n co
llect
ed in
the
field
.�
Still
nee
d to
col
lect
fiel
d da
ta o
n di
stri
butio
n po
les.
�Fi
eld
data
col
lect
ion
is di
ffere
nt a
s we
use
the T
ruan
gle
or th
e Tot
al S
tatio
n su
rvey
ing
tool
to c
olle
ct a
ngle
s as o
ppos
ed to
the T
ruPu
lse o
nly.
Thi
s giv
es a
m
uch
mor
e re
peat
able
and
acc
urat
e co
llect
ion
of a
ngle
s. �
We
are
also
cap
turi
ng th
e ac
tual
cat
enar
y’s f
or th
e in
divi
dual
co
nduc
tors
/wir
es, a
s wel
l as t
he c
hang
e in
ele
vatio
n fr
om o
ne st
ruct
ure
to
the
next
. We
have
foun
d th
at th
is ca
n al
so b
e do
ne w
ith th
e Tru
pulse
with
so
me
degr
ee o
f acc
urac
y. T
here
are
still
inst
ance
s whe
re th
e Tru
pulse
will
gi
ve a
n er
rone
ous r
eadi
ng d
ue to
out
side
mag
net i
nter
fere
nce,
in th
ese
case
s th
e Tru
angl
eor
the T
otal
Sta
tion
are
not a
ffect
ed b
y th
e ou
tsid
e co
nditi
ons.
The
tim
e in
volv
ed to
col
lect
this
data
is lo
nger
than
nor
mal
due
to th
e co
llect
ion
and
logg
ing
of m
any
mor
e da
ta p
oint
s tha
n w
ould
be
colle
cted
by
a ty
pica
l PLP
con
trac
tor.
F-33
Figu
re 4
:Ad
vanc
ed F
ield
Sur
vey
Dat
a Ex
ampl
e
17
F-34
Figu
re 5
:Ad
vanc
ed F
ield
Sur
vey
Dat
a Ex
ampl
e
18
F-35
Tabl
e 1
: Sa
fety
Fac
tors
for W
ood
and
Ligh
t Wei
ght S
teel
(LW
S) P
oles
-N
ew a
nd In
-Ser
vice
Con
stru
ctio
n
19
F-36
Tabl
e 2
: Sa
fety
Fac
tors
for J
oint
-Ow
ned
and
Join
t-Use
Pol
es
20
F-37
Figu
re 6
:Ca
tena
ry E
xam
ple
(The
curv
eth
at a
han
ging
cab
leas
sum
es u
nder
its
own
wei
ghtw
hen
supp
orte
d on
ly a
t its
end
s.)
21
F-38
22
�SP
IDA
fails
6,0
00 o
ut o
f 20,
000
�SP
IDA
doe
s wor
k on
tang
ent p
oles
, nee
d to
SPI
DA
’s ca
pabi
lity
in e
valu
atin
g on
oth
er ty
pes.
F-39
Func
tiona
l Typ
es o
f Str
uctu
res
(pol
es)
23
�Ta
ngen
t st
ruct
ure.
Tan
gent
stru
ctur
es a
re th
e ty
pe m
ost c
omm
only
use
d on
a tr
ansm
issio
n lin
e an
d ar
e us
ed o
n re
lativ
ely
stra
ight
por
tions
of t
he tr
ansm
issio
n lin
e. B
ecau
se th
e co
nduc
tors
are
in a
rel
ativ
ely
stra
ight
line
pas
sing
thro
ugh
them
, tan
gent
st
ruct
ures
are
des
igne
d on
ly to
han
dle
smal
l lin
e an
gles
(cha
nges
in d
irec
tion)
of 0
to 2
deg
rees
. Tan
gent
stru
ctur
es a
re u
sual
ly
char
acte
rize
d by
susp
ensio
n (v
ertic
al) i
nsul
ator
s, w
hich
supp
ort a
nd in
sula
te th
e co
nduc
tors
and
tran
sfer
win
d an
d w
eigh
t loa
ds to
th
e st
ruct
ure.
�A
ngle
str
uctu
re. A
ngle
stru
ctur
es a
re u
sed
whe
re tr
ansm
issio
n lin
e co
nduc
tors
cha
nge
dire
ctio
n. T
hese
type
s of s
truc
ture
s are
de
signe
d to
with
stan
d th
e fo
rces
pla
ced
on th
em b
y th
e ch
ange
in d
irec
tion.
Ang
le st
ruct
ures
may
be:
(1) s
imila
r to
tang
ent
stru
ctur
es, u
sing
susp
ensio
n in
sula
tors
to a
ttac
h th
e co
nduc
tors
and
tran
sfer
win
d, w
eigh
t, an
d lin
e an
gle
load
s to
the
stru
ctur
e; o
r (2
) sim
ilar
to st
rain
or
dead
-end
stru
ctur
es, u
sing
insu
lato
rs in
seri
es w
ith th
e co
nduc
tors
to b
ring
win
d, w
eigh
t, an
d lin
e an
gle
load
s dir
ectly
to th
e st
ruct
ure.
�D
ead
-end
str
uctu
re. A
dea
d-en
d st
ruct
ure
is ty
pica
lly u
sed
whe
re tr
ansm
issio
n lin
e co
nduc
tors
turn
at a
wid
e an
gle
or e
nd.
Com
pare
d to
tang
ent s
truc
ture
s, a
dea
d-en
d st
ruct
ure
is de
signe
d to
be
stro
nger
and
ofte
n is
a la
rger
stru
ctur
e. T
ypic
ally,
insu
lato
rs
on a
dea
d-en
d st
ruct
ure
are
in se
ries
with
the
cond
ucto
rs (h
oriz
onta
l) to
bri
ng w
ind,
wei
ght,
and
line
angl
e lo
ads d
irec
tly to
the
stru
ctur
e. A
dea
d-en
d st
ruct
ure
is de
signe
d to
res
ist th
e fu
ll un
bala
nced
tens
ion
that
wou
ld o
ccur
if a
ll co
nduc
tors
wer
e re
mov
ed
from
one
face
of t
he st
ruct
ure.
�St
rain
str
uctu
re. A
stra
in st
ruct
ure
is sim
ilar
in a
ppea
ranc
e an
d de
sign
stre
ngth
to a
tang
ent s
truc
ture
. The
diff
eren
ce in
ap
pear
ance
is th
e co
nduc
tor
atta
chm
ent h
ardw
are.
The
con
duct
or a
ttac
hmen
t har
dwar
e is
the
sam
e as
a d
eade
ndor
larg
e an
gle,
w
here
the
insu
lato
r be
lls a
re in
line
with
the
cond
ucto
r. W
here
as a
dea
d-en
d st
ruct
ure
is de
signe
d to
with
stan
d th
e fu
ll un
bala
nced
te
nsio
n th
at w
ould
occ
ur fr
om th
e lo
ss o
f all
cond
ucto
rs fr
om o
ne fa
ce o
f the
stru
ctur
e, a
stra
in st
ruct
ure
is de
signe
d to
with
stan
d on
ly u
nbal
ance
d te
nsio
ns a
ssoc
iate
d w
ith th
e lo
ss o
f a si
ngle
pha
se (b
undl
e of
two
cond
ucto
rs) o
n on
e fa
ce o
f the
stru
ctur
e.
F-40
Meeting Notes for September 9, 2014
SPIDA evaluation progress updates
The next team meeting will be scheduled for the end of September.
Discussion Notes � Approximately 800 -1000 poles are evaluated each day by planners using SPIDA. � As limitations are identified within SPIDA, information needs to be communicated to the
planners via the Design Support Updates (DSU) to ensure each pole is assessed correctly. � Work with the Polar Project team to schedule a meeting with the SPIDA program
developers to address limitations within SPIDA, make program adjustments and make updates to the client files.
o Conductor tension/Pre-tensiono Guyingo H-frameso Angle Bi-Sector
Project Action Items
Team Objectives � Provide a high level executive summary of the objectives.
o A detailed summary of the purpose for this evaluation o Plans for resolving any gaps identified between SPIDA and PLS-
CADD/PLS_POLE� Project time line will be extended 4 weeks. � Final results will be presented the last week of October.
Calibration Expectation � Create a matrix to evaluate the gaps/limitations identified with in SPIDA.
o Provide detailed description of the identified gaps/limitations with the program o Provide recommendations for resolving gapso Work with the Technical Change Committee (TCC) on concerns which have been
identified in the program and in the field � Expand on the results comparison to include differences identified within SPIDA vs PLS-
CADD/PLS-POLE for the SCE default data: o Safety factoro Change in pole class needed pass within SPIDA vs PLS-CADD/PLS-POLE for
the SCE default data.� Expand on the results comparison to include differences identified within SPIDA vs PLS-
CADD/PLS-POLE for the SCE advance field data: o Safety factoro Change in pole class needed pass within SPIDA vs PLS-CADD/PLS-POLE for
the SCE default data.
References and supporting documents
F-41
� Include a sketch of the plan and elevation view for queen post example � Detailed description of each sketch
F-42
Engi
neer
ing
Eval
uati
on f
orSP
IDA
T&D
Eng
inee
ring
07/1
8/20
14
F-43
•O
bjec
tive
s:
1.Pe
rfor
m e
ngin
eeri
ng e
valu
atio
n of
SPI
DA
to v
alid
ate
its
resu
lts
by c
ompa
ring
wit
h PL
S-C
AD
D/P
LS-P
OLE
2.C
lari
fy li
mit
atio
n or
gap
of S
PID
A o
n po
le lo
adin
g ca
lcul
atio
n3.
Rec
omm
end
proc
ess
for
gap
clos
ure
•O
n th
is r
epor
t (07
-18-
2014
):
�Pr
opos
ed p
roje
ct p
lan
that
def
ines
the
scop
e an
d ti
me
line
•Pr
ojec
t del
iver
able
(09-
12-2
014)
:�
Fina
l rec
omm
enda
tion
.
F-44
Prop
osed
Pro
ject
Pla
nId
enti
fy p
ole
cons
truc
tion
ty
pes
for
eval
uati
on
Com
plet
e fir
st
pass
of
calc
ulat
ion
Com
plet
e se
cond
pa
ss o
f ca
lcul
atio
n
Com
plet
e ev
alua
tion
and
m
ake
reco
mm
enda
tion
Sele
ct th
ree
sam
ples
for
each
of t
he fo
llow
ing
type
:1.
Tang
ent p
ole
wit
h eq
ual
tens
ion
2.A
ngle
pol
e (b
isec
tor
guye
d po
le)
3.G
uyed
pol
e/de
aden
dpo
le (i
n-lin
e gu
yed
pole
)4.
In-l
ine
span
guy
ed p
ole
5.H
-fra
me
Res
pons
ibili
ty:
Sean
Wild
er to
pro
vide
list
. C
hris
Nor
man
and
Nor
man
ca
n pr
ovid
e pr
evio
us
calc
ulat
ion.
Dur
atio
n: tw
o w
eeks
Perf
orm
pol
e lo
adin
g ca
lcul
atio
n of
15
sam
ple
on S
PID
A a
nd
PLS-
CA
DD
usi
ng
Edi
son’
s st
anda
rd
valu
es/a
ssum
ptio
ns
Res
pons
ibili
ty:
•Se
an W
ilder
’s g
roup
w
ill p
erfo
rm S
PID
A
calc
ulat
ion
•N
orm
Juf
fer
and
Chr
is N
orm
an to
pe
rfor
m P
LS-
CA
DD
/PO
LE
calc
ulat
ion
Dur
atio
n: tw
o w
eeks
Con
duct
fiel
d su
rvey
an
d pe
rfor
m p
ole
load
ing
calc
ulat
ion
of
15 s
ampl
e on
SPI
DA
an
d PL
S-C
AD
D u
sing
fie
ld s
urve
yed
data
Res
pons
ibili
ty:
Mik
e H
anse
n st
arts
pe
rfor
min
g fie
ld
surv
ey a
fter
rec
eivi
ng
the
pole
can
dida
te li
st
from
Sea
n.
Sean
’s te
am, N
orm
and
C
hris
to p
erfo
rm th
e se
cond
pas
s of
ca
lcul
atio
n.
Dur
atio
n: th
ree
wee
ks
•C
ompa
re r
esul
ts
betw
een
SPID
A a
nd
PLS-
CA
DD
/PO
LE•
Iden
tify
issu
es,
limit
atio
n of
SPI
DA
•M
ake
reco
mm
enda
tion
Res
pons
ibili
ty:
Thua
n to
lead
the
wra
p-up
Dur
atio
n: tw
o w
eeks
07/2
5/14
08/0
8/14
08/2
9/14
09/1
2/14
F-45
Back
grou
nd In
form
atio
n
Not
e fr
om T
huan
Tran
7/1
8/20
14
Ken/
Bill/
Phil,
Plea
se f
ind
atta
ched
the
pro
pose
d pr
ojec
t pl
an f
or y
our
pre-
read
and
co
mm
ents
. T
his
plan
has
bee
n pu
t to
geth
er b
y th
e te
am in
clud
ing
Deb
ra
Broo
ks,
Sean
Wild
er,
Mik
e H
anse
n, N
orm
Juf
er,
Chri
s N
orm
an a
nd m
ysel
f. I
al
so h
ave
had
thre
e co
nver
sati
ons
wit
h An
dy S
tew
art.
He
has
been
ver
y he
lpfu
l and
I w
ill c
onti
nue
to u
se h
im a
s m
y re
sour
ce.
I will
fol
low
up
a m
eeti
ng s
oon.
F-46