2017 storm damage emergency rehabilitation...
TRANSCRIPT
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 1
2017 Storm Damage Emergency Rehabilitation
Program Summary
California Department of Water Resources
(DWR Rehabilitation and USACE PL 84‐99 Information)
October 27, 2017
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 2
Introduction:
The storm events of January and February 2017 caused wide‐spread damage to a number of levees in the State Plan of
Flood Control (SPFC). As described in the Central Valley Flood Protection Plan, local maintaining agencies and DWR, along
with the U.S. Army Corps of Engineers (USACE), are responsible for maintaining the integrity of the SPFC levees, bypasses,
and other facilities to continue to protect California’s Central Valley. During the course of the 2017 floods, $5 Million was
immediately expended to repair sites. As the flood waters receded from the Sacramento, and later the San Joaquin Basin,
agencies responsible for maintaining the levees worked with DWR and the USACE to properly assess the recently damaged
sites.
*NOTE: The information below is current as of the date stated above.*
ProgramOverviewBelow is a summary of the 2017 Storm Damage – DWR Emergency Rehabilitation (SDDER) and USACE PL 84‐99 efforts
resulting from this year’s winter storms. NOTE: These numbers are subject to change as USACE is still developing
preliminary investigation reports (PIRs).
Table 1: Summary of USACE PL 84‐99 Sites
Sacramento Area
Delta, San Joaquin, & Other Areas
Total Number of USACE PL 84‐99 Sites 69 295
Priority 1, 2 or 3 USACE PL 84‐99 Sites (16 Sac Basin Sites to be repaired in 2017)
34 16
No Action USACE PL 84‐99 Sites (Re‐evaluated by DWR for inclusion in DWR’s efforts)
18 2
Ineligible USACE PL 84‐99 Sites ( Re‐evaluated by DWR for inclusion in DWR’s efforts)
17 277
Table 2: Summary of DWR Sites (Does not include USACE Priorities 1, 2, or 3 sites)
Number of Sites
Number of DWR Sites 395
Number of DWR Field Rated “Critical” Sites (30 to be repaired in 2017; 10 to be repaired in the future)
40
Number of DWR Field Rated “Serious” Sites 76
Number of DWR Field Rated “Area of Concern” Sites 226
Number of Sites with “No Damage Observable” 53
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 3
Table 3: Summary of Construction Efforts to Date
Number of Sites
DWR Sites To Be Repaired in 2017 30
DWR Sites – Under Construction 22
DWR Sites – Construction Completed 8
USACE Sites to be Repaired in 2017 16
USACE Sites – Under Construction 16
USACE Sites – Construction Completed 0
DescriptionofDWR’sPrioritizationProcess
SelectionandScreeningProcess
Sites were compiled for screening for the 2017 Storm Damages DWR Rehabilitation from the following sources: Flood
Operation Center incident reports, LMA‐reported storm damage sites in response to the PL 84‐99 request letter issued by
the CVFPB request in 2017, and critical problems in the Flood System Repair database which includes current inventory of
known levee performance problems.
Screening was focused on repair of storm damages that were critical, with a goal of achieving maximum flood risk
reduction. A two‐step prioritization process was developed. The first step focused solely on specific geotechnical factors
and did not address levee geometry, freeboard, or overtopping deficiencies. For this step, field teams visited the damaged
sites and evaluated those using consistent rating criteria for the three general failure modes: erosion, stability, and
seepage.
The sites were then rated as “critical” or “serious”, using definitions from the DWR Flood System Repair Project (FSRP)
Guidelines from 2012. These definitions are noted below. An additional category, for “areas of concern”, is meant to
capture the remainder of the problematic sites.
Critical:A site, if not repaired, presents a significant possibility of failure when: Due to erosion, a) the site required a flood fight in a past high‐water event to prevent a breach, or
b) erosion has encroached into either the waterside levee prism or extended levee prism, and as a result,
is likely to cause a levee failure in the next high‐water event;
Due to seepage, a) the site required a flood fight in a past high‐water event to prevent a breach, or
b) seepage is known by historical record of past performance to have recurrent piping or boils that carry
material, at a water stage less than design level, and as a result the site is likely to cause a levee failure in
the next high‐water event; or,
For stability, a) due to a slope stability issue, the site required a flood fight in a past high‐water event to
prevent a breach, or b) the levee embankment has slumped such that levee failure in the next high‐water
event is likely.
Serious:A site, if not repaired, has the potential to become critical when:
Due to erosion, a) erosion has encroached into either the waterside levee prism or extended levee prism
that may not cause a levee failure in the next high‐water event, or b) progressing erosion that is likely to
encroach into either the waterside levee prism or extended levee prism;
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 4
Due to stability, the levee embankment has deformed, the site may further deteriorate, may cause levee
failure in a future high‐water event or may require a flood fight in a high water event to prevent a breach;
or
Due to seepage, seepage is known by historical record of past performance to have caused recurrent
piping or boils, and the site may further deteriorate, may cause levee failure in a future high‐water event,
or may require a flood fight in a high‐water event to prevent a breach.
AreasofConcern:Areas of concern sites are the remainder of reported sites that have problems and need
periodic monitoring, but do not rise to the hazard levels of “serious” or “critical”.
The second step of the prioritization considers the hydraulic basins (leveed areas) receiving protection from SPFC
levees. The areas are ranked into three tiers considering factors including: the overall past performance of the
levees, frequency of loading, and the assets behind these levees. There are forty five leveed areas in Sacramento
River Basin and twenty nine leveed areas in San Joaquin River Basin, which were grouped into the three tiers as
follows:
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 5
Tier 1 represents the upper one‐third of levees areas with maximum assets combined with poorest
performing levees.
Tier 2 represents the middle third of the levee areas.
Tier 3 represents the least assets behind the levees combined with best performing levees.
EnvironmentalPermitting Coordination with the regulatory agencies is occurring through a Unified Command Group (UCG), comprised of
other State and Federal agencies, conference calls, or with specific agencies for specific permit issues.
Onsite vegetation plantings have followed the U.S. Army Corps of Engineers “engineering technical letter” (ETL)
standard for vegetation on levees, meaning that woody vegetation was not planted on the levee itself or 15 feet
from the levee toe.
Avoidance of impacts is the primary consideration for managing environmental impacts. Compensatory mitigation
for unavoidable impacts to endangered species will be off‐site.
First 16 critical sites:
o Permits have been issued. (One exception: biological opinion from the National Marine Fisheries Service
will be after the fact). A couple of sites had emergency notifications sent to Department of Fish and
Wildlife.
o Environmental Staff are monitoring construction to ensure compliance with permits and work windows.
o Permits are available to LMAs to download.
o Purchasing of mitigation bank credits will begin mid‐October to meet permit conditions.
Next 22 critical sites:
o Emergency permitting processes are being used for the 12 sites going to construction in November; with
emergency notifications to Department of Fish and Wildlife, Regional General Permit #8 with the U.S.
Army Corps of Engineers for Clean Water Act Section 404, and after the fact biological opinions with U.S.
Fish and Wildlife Service and National Marine Fisheries Service.
o Mitigation measures and best management practices will be incorporated into construction for sites
without current issued permits.
Tribal/CulturalUnder DWR’s policy for Tribal Engagement, we have committed to consult with tribal entities to identify and protect Tribal
Cultural Resources (TCR)’s where feasible, and to cooperate in the development of treatment and mitigation plans to
mitigate for impacts on tribal cultural resources and cultural places. We are also working to meet the standards of the CA
Natural Resources Tribal Policy. As such, we are in consultation with six tribes as we undertake construction and repair
under the emergency levee rehabilitation program on all DWR critical and serious sites. These include the Ione Band of
Miwok Indians (IBMI), The United Auburn Indian Community (UAIC), the Wilton Rancheria, The Yocha DeHe Wintun Nation
(YDWN), the Shingle Springs Band of Miwok Indians (SSBMI), and the Upper Lake Pomo Habematolel. Representatives of
select tribes are on site for assessment and monitoring as construction takes place.
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 6
DescriptionofUSACE’sSitePrioritizationProcessEvaluation factors used to rank PL84‐99 rehabilitation sites (as provided by USACE):
PL84‐99 rehabilitation sites are ranked based on severity of damages and potential consequences of a levee breech as
outlined in Table 1 and described below.
Table 4: PL84‐99 Rehabilitation Site Ranking
High Consequences
Low to Moderate Consequences
Severe Damage Order 1 Order 2
Moderate Damage Order 2 Order 3
Minor Damage Order 3 Order 4
Order 1: The damages are severe and make it very likely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect urban areas where potential consequences are high (there is a significant population at risk and / or there could be a large economic impact).
Order 2: The damages are severe and make it very likely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect predominantly rural / agricultural areas where potential consequences are low to moderate. Or, the damages are moderate and the levee may breach or need significant / major emergency repairs during the next flood event. These levees protect urban areas where potential consequences are high (there is a significant population at risk and / or there could be a large economic impact). Order 3: The damages are moderate and the levee may breach or need significant / major emergency repairs during the next flood event. These levees protect predominantly rural / agricultural areas where potential consequences are low to moderate. Or, the damages are minor and it is unlikely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect urban areas where potential consequences are high (there is a significant population at risk and / or there could be a large economic impact). Order 4: The damages are minor and it is unlikely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect predominantly rural / agricultural areas where potential consequences are low to moderate. Typical evidence of severe damage for both Order 1 and 2 Sites:
Vertical or horizontal displacement in the levee crest or slopes greater than 3 feet.
Large slumps or shallow landslides on the waterside or landside levee slope close to the levee crest that may lead to progressive failure of the levee.
Evidence of sand boils indicating a significant volume of soil was removed from the levee foundation, (i.e. internal erosion was in progress).
Evidence of large deposits of soil in land side ditches or canals indicating significant material was removed from the levee foundation (i.e. internal erosion was in progress).
Significant water side erosion that threatens levee integrity / stability.
Wave wash erosion high on the levee near the crest with vertical scarps greater than 5 ft.
Widespread bulging or slumping of the levee toe due to through levee seepage. Typical evidence of moderate damage for Order 2 and 3 Sites:
Small slumps and slides with vertical or horizontal displacement of the levee slope less than 3 feet.
Waterside bank erosion that does not yet affect levee integrity, but is close.
Wave wash erosion on the upper half of the levee slope with vertical scarp less than 3 ft.
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 7
Widespread under seepage of moderate to high volume, with pervasive pin (small diameter) boils.
Isolated bulging or slumping of the levee toe due to through levee seepage Typical evidence of minor damage for Order 3 and 4 Sites:
Lateral or longitudinal tension cracks with minimal displacement indicating marginal slope stability.
Wave wash erosion on the lower half of the levee slope with vertical scarps less than 3 ft.
Localized low volume seepage with clear water not carrying material from the levee foundation or levee embankment.
Damages (rutting and loss of aggregate) to the levee patrol road that impacts access / trafficability in bad weather.
Small slides or slumps in the vicinity of the levee toe.
ContingencyPlanAs a result of many factors such as funding limitations, timing of when damaged sites were identified, and permitting
requirements not all DWR Critical sites will be rehabilitated prior to start of flood season (November 1) in 2017. Similarly,
several of the USACE PL 84‐99 Priority 2 and 3 sites will also not be repaired prior to the 2017/2018 flood season.
As part of this year’s preparation for the upcoming flood season, DWR has reached out to each of the LMAs with unrepaired
sites that have either been designated by DWR as Critical or Serious, or by the USACE as Priority 2 or 3. DWR and LMAs will
jointly develop contingency plans to assist and expedite emergency repairs during high water events. These contingency
plans could include pre‐determining quantities needed for repairs, stockpiling flood fighting materials nearby, and more.
Although detailed contingency plans will be in place, LMAs are still required to follow the Standardized Emergency
Management System (SEMS) process outlined in the letters sent to the LMAs in mid‐September 2017 (i.e., the flood fighting
effort should begin with the LMAs, and then elevate to the County Office of Emergency Services (OES), and then to theState
Flood Operations Center (FOC). For the remainder of the DWR critical sites that were not repaired in 2017, DWR will re‐
assess any potential emergency repairs completed during the 2017‐18 flood season to see what additional repairs will be
needed in future years.Note: The chart below represents the process for determining site ranking and contingency planning
for all damaged sites.
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 Public 8
Figure 1: Contingency Planning Flow Chart
2018 Rehabilitation
(After 2017/2018 Flood Season)
Contract Flood Fight Final Repair
Done 2018 Monitor Site Performance
2017/2018 FloodSeason
Action Needed/Contingency Plan
Final RepairDone 2017 –Monitor Site Performance
Yes No
MonitorNo
Traditional Flood Fight (Flood Threat Mitigation Process)
DWR Critical or USACE PL84‐99,P1, P2 & P3
DWR SeriousSites
Repair to be completed in2017
Action Needed/Contingency Plan
Yes
Yes No
Evaluation of Known & Reported Sites Damaged in 2016/2017 Flood Season
Sites Determined to Fail next Flood Season
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 9
SiteListBelow is a table of the sites that will be repaired in 2017 or are part of DWR’s Contingency Planning Efforts.
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
LMA‐21 RD 1001 Bear River Erosion 38.946751 ‐121.563825 DWR Construction Complete
USACE_CESPK_FAIR_ 2010_p_0044
RD 787 Colusa Basin Drain
Stability 38.80101 ‐121.74838 DWR Construction In Process
LMA‐71 Tehama County Flood Control and Water Conservation District
Deer Creek – Unit 1
Erosion 39.9469 ‐122.0515 DWR Construction Complete
LMA‐3 Lake County Watershed Protection District
Middle Creek Erosion 39.179715 ‐122.896926 DWR Construction Complete
LMA‐53 Sacramento Bypass Sacramento Bypass
Stability 38.60133826 ‐121.5820263 DWR Construction In Process
LMA‐52 Sacramento Bypass Sacramento Bypass
Stability 38.60159656 ‐121.5811883 DWR Construction In Process
LMA‐54 Sacramento Bypass Sacramento Bypass
Erosion 38.59683065 ‐121.5792158 DWR Construction In Process
RD 827‐03 RD827 ‐ Elkhorn Sacramento River
Erosion 38.674042 ‐121.642986 DWR Construction In Process
ST20‐01 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 39.171211 ‐121.730135 DWR Construction Complete
ST11‐U4‐01 West Levee Yolo Bypass Yolo Bypass Erosion 38.53598014 ‐121.63143 DWR Construction Complete
LMA‐74 SBFCA Feather River Seepage 39.15594 ‐121.61664 SBFCA Construction In Process
313‐14 RD2098 ‐ Cache & Haas Slough
Cache Slough Stability 38.28303742 ‐121.7110735 DWR Construction In Process
386‐32 RD150 ‐ Merrit Island Elk Slough Erosion 38.391054 ‐121.539214 DWR Construction In Process
LMA‐73 RD2098 ‐ Cache & Haas Slough
Hass Slough Erosion 38.29297 ‐121.72317 DWR Construction Complete
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 10
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
DWR_RD2098_01_s_2012_12
RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.283868 ‐121.693627 DWR Construction Complete
LMA – 245 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2965 ‐121.6935 DWR Construction In Process
LMA – 247 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2962 ‐121.6935 DWR Construction In Process
LMA – 251 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2931 ‐121.6935 DWR Construction In Process
LMA – 252 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2929 ‐121.6935 DWR Construction In Process
LMA – 253 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2923 ‐121.6934 DWR Construction In Process
LMA – 254 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2919 ‐121.6935 DWR Construction In Process
LMA – 255 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2916 ‐121.6935 DWR Construction In Process
LMA – 265 RD2098 ‐ Cache & Haas Slough
Cache Slough Erosion 38.2837 ‐121.7134 DWR Construction In Process
LMA – 266 RD2098 ‐ Cache & Haas Slough
Cache Slough Erosion 38.2872 ‐121.716 DWR Construction In Process
LMA – 132 RD150 ‐ Merrit Island Elk Slough Stability 38.35623056 ‐121.5619167 DWR Construction In Process
LMA – 133 RD150 ‐ Merrit Island Elk Slough Erosion 38.37511389 ‐121.5446917 DWR Construction In Process
LMA – 134 RD150 ‐ Merrit Island Elk Slough Erosion 38.37721667 ‐121.5420583 DWR Construction In Process
DWR_RD2101_01_s_2012_1
RD2101 ‐ Blewett San Joaquin River
Erosion 37.65055 ‐121.22957 DWR Construction In Process
DWR_RD2085_01_R_2012_01
RD2085 ‐ Kasson San Joaquin River
Erosion 37.68662 ‐121.27679 DWR Construction In Process
DWR_RD0524_01_s_2012_21
RD524 ‐ Middle Robert's Island
San Joaquin River
Erosion 37.93186 ‐121.32831 DWR Construction Complete
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 11
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
MA16‐01 Maintenance Area 16 Feather River Waterside Erosion
39.258105 ‐121.636314 USACE Construction In Process
MA12‐01 Maintenance Area 12 Colusa Basin Drain
Waterside Slope Slip
39.13392 ‐122.02277 USACE Construction In Process
RD1001‐01 RD 1001 Feather River Boils 38.78383 ‐121.61224 USACE Construction In Process
RD1001‐02 RD 1001 Natomas Cross Canal
Boils 38.81141 ‐121.56291 USACE Construction In Process
RD 108‐01 RD 108 Colusa Basin Drain
Landside Slope Slip
38.99577167 ‐121.9606167 USACE Construction In Process
RD 108‐02 RD 108 Colusa Basin Drain
Landside Slope Slip
38.96777 ‐121.9241783 USACE Construction In Process
RD 108‐03 RD 108 Colusa Basin Drain
Landside Slope Slip
38.94571667 ‐121.9067167 USACE Construction In Process
RD 108‐04 RD 108 Colusa Basin Drain
Waterside Slope Slip
38.89758333 ‐121.9146883 USACE Construction In Process
RD 108‐05 RD 108 Colusa Basin Drain
Waterside Slope Slip
38.89614167 ‐121.914445 USACE Construction In Process
RD 2035‐01 RD 2035 Yolo Bypass Landside Slope Slip
38.63979 ‐121.66129 USACE Construction In Process
RD 2035‐02 RD 2035 Yolo Bypass Landside Slope Slip
38.63703 ‐121.6593 USACE Construction In Process
RD 2035‐03 RD 2035 Yolo Bypass Landside Slope Slip
38.63645 ‐121.65888 USACE Construction In Process
RD 2035‐04 RD 2035 Yolo Bypass Landside Slope Slip
38.63609 ‐121.65863 USACE Construction In Process
RD 2035‐05 RD 2035 Yolo Bypass Landside Slope Slip
38.63443 ‐121.65738 USACE Construction In Process
RD 2035‐06 RD 2035 Yolo Bypass Landside Slope Slip
38.63242 ‐121.65592 USACE Construction In Process
RD 2035‐07 RD 2035 Yolo Bypass Landside Slope Slip
38.63104 ‐121.65491 USACE Construction In Process
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 12
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
SRWLD‐01 Sacramento River West Side Levee District
Sacramento River
Seepage 38.85186944 ‐121.7255694 N/A Contingency Plan
RD 2035‐08 RD2035 ‐ Conway Yolo Bypass Erosion 38.59284 ‐121.63134 N/A Contingency Plan
SCDU‐03 City of Sacramento Sacramento River
Erosion 38.571397 ‐121.513797 N/A Contingency Plan
MA9‐01 Maintenance Area 9 Sacramento River
Erosion 38.53135368 ‐121.5272856 N/A Contingency Plan
MA9‐03 Maintenance Area 9 Sacramento River
Erosion 38.47482751 ‐121.5354548 N/A Contingency Plan
LD1‐S‐02 Levee District 1 ‐ Sutter County
Feather River Erosion 39.018322 ‐121.610275 N/A Contingency Plan
RD 70‐01 RD70 ‐ Meridian Sacramento River
Erosion 39.06819 ‐121.8627 N/A Contingency Plan
RD 70‐03 RD70 ‐ Meridian Sacramento River
Erosion 39.14524 ‐121.84265 N/A Contingency Plan
SRWLD‐02 Sacramento River West Side Levee District
Sacramento River
Seepage 39.09558889 ‐121.8974 N/A Contingency Plan
SRWLD‐03 Sacramento River West Side Levee District
Sacramento River
Seepage 39.09496667 ‐121.8948583 N/A Contingency Plan
SRWLD‐04 Sacramento River West Side Levee District
Sacramento River
Seepage 39.19933 ‐121.9881967 N/A Contingency Plan
SRWLD‐05 Sacramento River West Side Levee District
Sacramento River
Seepage 39.192405 ‐121.98732 N/A Contingency Plan
RD 2035‐09 RD2035 ‐ Conway Yolo Bypass Erosion 38.647061 ‐121.666439 N/A Contingency Plan
ST11‐U1‐01 West Levee Yolo Bypass Yolo Bypass Erosion 38.72724961 ‐121.660234 N/A Contingency Plan
RD 1001‐03 RD1001 ‐ Nicolaus Natomas Cross Canal
Erosion 38.8281 ‐121.53474 N/A Contingency Plan
LMA‐119 RD150 ‐ Merrit Island Elk Slough Erosion 38.34814167 ‐121.5723194 N/A Contingency Plan
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 13
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
LMA‐122 RD150 ‐ Merrit Island Elk Slough Stability 38.35623056 ‐121.5619167 N/A Contingency Plan
LMA‐139 RD150 ‐ Merrit Island Elk Slough Stability 38.39583333 ‐121.53715 N/A Contingency Plan
LMA‐140 RD150 ‐ Merrit Island Elk Slough Stability 38.39623333 ‐121.5360639 N/A Contingency Plan
LMA‐147 RD349 ‐ Sutter Island Steamboat Slough
Erosion 38.30221667 ‐121.5798472 N/A Contingency Plan
LMA‐191 RD2060 ‐ Hastings Lindsey Slough
Erosion 38.25118611 ‐121.7171139 N/A Contingency Plan
LMA‐216 RD2060 ‐ Hastings Cache Slough Erosion 38.29053889 ‐121.7316028 N/A Contingency Plan
LMA‐304 San Joaquin County Flood Control District
Mormon Slough
Erosion 38.04593 ‐121.023021 N/A Contingency Plan
LMA‐417 RD2089 ‐ Stark Old River Erosion 37.8056 ‐121.4019 N/A Contingency Plan
LMA‐439 RD524 ‐ Middle Robert's Island
San Joaquin Erosion 37.9317 ‐121.3283 N/A Contingency Plan
DWR_NA0016_01_s_2012_2
Sacramento River West Side Levee District
Sacramento River
Erosion 38.95405988 ‐121.8405597 N/A Contingency Plan
DWR_LD0003_01_s_2012_52
Levee District 3 Sacramento River
Erosion 39.50438815 ‐121.9853009 N/A Contingency Plan
DWR_RD0003_01_R_2012_03
RD3 ‐ Grand Island Steamboat Slough
Erosion 38.18381 ‐121.64878 N/A Contingency Plan
LMA‐34 RD2075 ‐ McMullin San Joaquin River
Seepage 37.728038 ‐121.274353 N/A Contingency Plan
FSRP‐13‐55 RD2085 ‐ Kasson San Joaquin River
Erosion 37.703094 ‐121.274894 N/A Contingency Plan
LMA‐15 RD1001 ‐ Nicolaus Yankee Slough
Erosion 38.975019 ‐121.481066 N/A Contingency Plan
LMA‐20 RD1001 ‐ Nicolaus Feather River Seepage 38.838 ‐121.633051 N/A Contingency Plan
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 14
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
RD 70‐02 RD70 ‐ Meridian Sacramento River
Seepage (B) 39.15748 ‐121.87925 N/A Contingency Plan
DWR_NA0019_04_s_2012_9
Tehema County Flood Control and Water Conservation District
Elder Creek Erosion 40.05159551 ‐122.1641788 N/A Contingency Plan
RD 900‐01 RD900 ‐ West Sacramento
Deep Water Shipping Canal
Erosion 38.50896944 ‐121.5816806 N/A Contingency Plan
ST11‐U4‐02 West Levee Yolo Bypass Yolo Bypass Erosion 38.56328942 ‐121.6383671 N/A Contingency Plan
LMA‐29 Marysville Levee Commission
Feather River Erosion 39.129715 ‐121.596819 N/A Contingency Plan
MA5‐N‐01 Maintenance Area 5 Butte Creek Erosion 39.676298 ‐121.778272 N/A
Contingency Plan
LMA‐72
Tehama County Flood Control and Water Conservation District
Deer Creek ‐ Unit 1
Erosion 39.964869 ‐122.029 N/A Contingency Plan
LMA‐100 RD3 ‐ Grand Island Steamboat Slough
Erosion 38.302981 ‐121.577336 N/A Contingency Plan
LMA‐101 RD3 ‐ Grand Island Steamboat Slough
Erosion 38.293381 ‐121.58245 N/A Contingency Plan
LMA‐113 RD150 ‐ Merrit IslandSacramento River
Erosion 38.357183 ‐121.528547 N/A Contingency Plan
LMA‐130 RD150 ‐ Merrit IslandElk Slough Erosion 38.37427778 ‐121.5491667 N/A
Contingency Plan
LMA‐131 RD150 ‐ Merrit Island Elk Slough Erosion 38.37431389 ‐121.5477528 N/A
Contingency Plan
LMA‐136 RD150 ‐ Merrit Island Elk Slough Erosion 38.38216944 ‐121.5445972 N/A
Contingency Plan
LMA‐142 RD150 ‐ Merrit IslandElk Slough Erosion 38.40922778 ‐121.5393889 N/A
Contingency Plan
LMA‐143 RD150 ‐ Merrit IslandElk Slough Erosion 38.40798333 ‐121.5343222 N/A
Contingency Plan
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 15
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
LMA‐151 RD349 ‐ Sutter Island Steamboat Slough
Erosion 38.27903889 ‐121.5896639 N/A Contingency Plan
LMA‐156 RD755 ‐ Randall Sacramento River
Erosion 38.33775833 ‐121.5638556 N/A Contingency Plan
LMA‐169 RD551 ‐ Pearson Sacramento River
Erosion 38.27459167 ‐121.5389583 N/A Contingency Plan
LMA‐178 RD551 ‐ Pearson Sacramento River
Erosion 38.26443611 ‐121.5254722 N/A Contingency Plan
LMA‐184 RD999 ‐ Netherlands Sacramento River
Erosion 38.41531944 ‐121.5237167 N/A Contingency Plan
LMA‐192 RD2060 ‐ Hastings Lindsey Slough
Erosion 38.25188611 ‐121.7199333 N/A Contingency Plan
LMA‐193 RD2060 ‐ Hastings Lindsey Slough
Erosion 38.25597222 ‐121.7241972 N/A Contingency Plan
LMA‐195 RD2060 ‐ Hastings Lindsey Slough
Erosion 38.25931667 ‐121.7263139 N/A Contingency Plan
LMA‐197 RD2060 ‐ Hastings Lindsey Slough
Erosion 38.26077222 ‐121.7408167 N/A Contingency Plan
LMA‐205 RD2060 ‐ Hastings Lindsey Slough
Erosion 38.26015 ‐121.7635556 N/A Contingency Plan
LMA‐206 RD2060 ‐ Hastings Lindsey Slough
Erosion 38.26071389 ‐121.7679722 N/A Contingency Plan
LMA‐220 RD2060 ‐ Hastings Cache Slough Erosion 38.28733611 ‐121.7243639 N/A
Contingency Plan
LMA‐224 RD2060 ‐ Hastings Cache Slough Erosion 38.28273333 ‐121.7176833 N/A
Contingency Plan
LMA‐225 RD2060 ‐ Hastings Cache Slough Erosion 38.28183889 ‐121.7169639 N/A
Contingency Plan
LMA‐230 RD2060 ‐ Hastings Cache Slough Erosion 38.27785 ‐121.7126389 N/A Contingency Plan
LMA‐232 RD2060 ‐ Hastings Cache Slough Erosion 38.27660833 ‐121.7108111 N/A Contingency Plan
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 16
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
LMA‐237 RD2060 ‐ Hastings Cache Slough Erosion 38.26400556 ‐121.6988111 N/A Contingency Plan
LMA‐238 RD2060 ‐ Hastings Cache Slough Erosion 38.26211389 ‐121.6979778 N/A Contingency Plan
LMA‐239 RD2060 ‐ Hastings Cache Slough Erosion 38.26078889 ‐121.6969639 N/A Contingency Plan
LMA‐243 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2971 ‐121.6933 N/A Contingency Plan
LMA‐248 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2959 ‐121.6935 N/A Contingency Plan
LMA‐256 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2892 ‐121.6935 N/A Contingency Plan
LMA‐257 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2888 ‐121.6935 N/A Contingency Plan
LMA‐258 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2869 ‐121.6935 N/A Contingency Plan
LMA‐259 RD2098 ‐ Cache & Haas Slough
Shag Slough Erosion 38.2857 ‐121.6935 N/A Contingency Plan
LMA‐269 RD2098 ‐ Cache & Haas Slough
Cache Slough Erosion 38.2913 ‐121.7161 N/A Contingency Plan
LMA‐281 RD2068 ‐ Yolano Shag Slough Stability 38.36234 ‐121.69406 N/A
Contingency Plan
LMA‐284 RD2068 ‐ Yolano Shag Slough Stability 38.3607 ‐121.6942 N/A
Contingency Plan
LMA‐287 RD2068 ‐ Yolano Shag Slough Stability 38.3595 ‐121.6942 N/A
Contingency Plan
LMA‐289 RD2068 ‐ Yolano Shag Slough Stability 38.3545 ‐121.694 N/A Contingency Plan
LMA‐290 RD2068 ‐ Yolano Shag Slough Stability 38.3462 ‐121.694 N/A Contingency Plan
LMA‐291 RD2068 ‐ Yolano Shag Slough Stability 38.3449 ‐121.694 N/A Contingency Plan
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 17
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
LMA‐295 RD524 ‐ Middle Robert's Island
San Joaquin River
Erosion 37.8922 ‐121.328 N/A Contingency Plan
LMA‐296 RD2095 ‐ Paradise Cut San Joaquin River
Erosion 37.740196 ‐121.297662 N/A Contingency Plan
LMA‐328 West Levee Yolo Bypass Sacramento River
Erosion 38.7591 ‐121.667964 N/A Contingency Plan
SCDU‐07 City of Sacramento Sacramento River
Erosion 38.56207 ‐121.51577 N/A Contingency Plan
LMA‐407 RD307 ‐ Lisbon Sacramento River
Erosion 38.43165 ‐121.533367 N/A Contingency Plan
LMA‐408 RD307 ‐ Lisbon Sacramento River
Erosion 38.431219 ‐121.533411 N/A Contingency Plan
LMA‐409 RD307 ‐ Lisbon Sacramento River
Erosion 38.430958 ‐121.533364 N/A Contingency Plan
LMA‐410 RD307 ‐ Lisbon Sacramento River
Erosion 38.430572 ‐121.533372 N/A Contingency Plan
LMA‐411 RD307 ‐ Lisbon Sacramento River
Erosion 38.430447 ‐121.533336 N/A Contingency Plan
LMA‐412 RD307 ‐ Lisbon Sacramento River
Erosion 38.430367 ‐121.533306 N/A Contingency Plan
LMA‐413 RD2089 ‐ Stark Old River Erosion 37.8121 ‐121.4159 N/A Contingency Plan
LMA‐414 RD2089 ‐ Stark Old River Erosion 37.81027 ‐121.41324 N/A Contingency Plan
LMA‐418 RD2089 ‐ Stark Old River Erosion 37.8097 ‐121.3964 N/A Contingency Plan
LMA‐440 RD524 ‐ Middle Robert's Island
San Joaquin Erosion 37.9319 ‐121.3284 N/A Contingency Plan
LMA‐443 RD524 ‐ Middle Robert's Island
San Joaquin Erosion 37.9353 ‐121.3332 N/A Contingency Plan
LMA‐457 RD544 ‐ Upper Robert's Island
Old River Erosion 37.8203 ‐121.3457 N/A Contingency Plan
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 18
Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status
Site Designation LMA Waterway Damage Latitude Longitude Constructing
AgencyConstruction
Status
LMA‐464 RD544 ‐ Upper Robert's Island
Old River Erosion 37.8135 ‐121.3194 N/A Contingency Plan
LMA‐465 RD544 ‐ Upper Robert's Island
Old River Erosion 37.8184 ‐121.319 N/A Contingency Plan
LMA‐468 RD544 ‐ Upper Robert's Island
Old River Erosion 37.8294 ‐121.312 N/A Contingency Plan
LMA‐469 RD544 ‐ Upper Robert's Island
Old River Erosion 37.8296 ‐121.3121 N/A Contingency Plan
LMA‐488 RD2064 ‐ River Junction San Joaquin River
Erosion 37.6778 ‐121.2644 N/A Contingency Plan
LMA‐500 Tehama County Flood Control and Water Conservation District
Deer Creek ‐ Unit 1
Erosion 39.96925 ‐122.008681 N/A Contingency Plan
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 19
Figure 2: Site Location Map – Sacramento Basin
2017StormDamage–DWREmergencyRehabilitationOctober27,2017
10/26/2017 20
Figure 3: Site Location Map – San Joaquin Basin