2017 storm damage emergency rehabilitation...

20
2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017 Public 1 2017 Storm Damage Emergency Rehabilitation Program Summary California Department of Water Resources (DWR Rehabilitation and USACE PL 84‐99 Information) October 27, 2017

Upload: others

Post on 12-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        1 

 

 

 

 

 

2017 Storm Damage Emergency Rehabilitation 

 Program Summary 

California Department of Water Resources 

(DWR Rehabilitation and USACE PL 84‐99 Information) 

October 27, 2017 

 

 

 

 

 

   

Page 2: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        2 

Introduction: 

The storm events of January and February 2017 caused wide‐spread damage to a number of levees in the State Plan of 

Flood Control (SPFC).  As described in the Central Valley Flood Protection Plan, local maintaining agencies and DWR, along 

with the U.S. Army Corps of Engineers (USACE), are responsible for maintaining the integrity of the SPFC levees, bypasses, 

and other facilities to continue to protect California’s Central Valley.  During the course of the 2017 floods, $5 Million was 

immediately expended to repair sites.  As the flood waters receded from the Sacramento, and later the San Joaquin Basin, 

agencies responsible for maintaining the levees worked with DWR and the USACE to properly assess the recently damaged 

sites.   

*NOTE: The information below is current as of the date stated above.* 

 

ProgramOverviewBelow is a summary of the 2017 Storm Damage – DWR Emergency Rehabilitation (SDDER) and USACE PL 84‐99 efforts 

resulting from this year’s winter storms.  NOTE: These numbers are subject to change as USACE is still developing 

preliminary investigation reports (PIRs).   

Table 1: Summary of USACE PL 84‐99 Sites 

 Sacramento Area 

Delta, San Joaquin, & Other Areas

Total Number of USACE PL 84‐99 Sites  69  295 

Priority 1, 2 or 3 USACE PL 84‐99 Sites  (16 Sac Basin Sites to be repaired in 2017) 

34  16 

No Action USACE PL 84‐99 Sites (Re‐evaluated by DWR for inclusion in DWR’s efforts)

18  2 

Ineligible USACE PL 84‐99 Sites ( Re‐evaluated by DWR for inclusion in DWR’s efforts)

17  277 

     Table 2: Summary of DWR Sites (Does not include USACE Priorities 1, 2, or 3 sites)  

  Number of Sites

Number of DWR Sites   395 

Number of DWR Field Rated “Critical” Sites (30 to be repaired in 2017; 10 to be repaired in the future) 

40 

Number of DWR Field Rated “Serious” Sites 76 

Number of DWR Field Rated “Area of Concern” Sites 226

Number of Sites with “No Damage Observable” 53 

 

 

Page 3: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        3 

Table 3: Summary of Construction Efforts to Date

  Number of Sites 

DWR Sites To Be Repaired in 2017  30 

              DWR Sites – Under Construction  22 

              DWR Sites – Construction Completed  8 

   

USACE Sites to be Repaired in 2017  16 

              USACE Sites – Under Construction  16 

              USACE Sites – Construction Completed  0 

DescriptionofDWR’sPrioritizationProcess

SelectionandScreeningProcess 

Sites were compiled for screening for the 2017 Storm Damages DWR Rehabilitation from the following sources:  Flood 

Operation Center incident reports, LMA‐reported storm damage sites in response to the PL 84‐99 request letter issued by 

the CVFPB request in 2017, and critical problems in the Flood System Repair database which includes current inventory of 

known levee performance problems.  

Screening was focused on repair of storm damages that were critical, with a goal of achieving maximum flood risk 

reduction.  A two‐step prioritization process was developed. The first step focused solely on specific geotechnical factors 

and did not address levee geometry, freeboard, or overtopping deficiencies.  For this step, field teams visited the damaged 

sites and evaluated those using consistent rating criteria for the three general failure modes: erosion, stability, and 

seepage.  

The sites were then rated as “critical” or “serious”, using definitions from the DWR Flood System Repair Project (FSRP) 

Guidelines from 2012.  These definitions are noted below.  An additional category, for “areas of concern”, is meant to 

capture the remainder of the problematic sites. 

Critical:A site, if not repaired, presents a significant possibility of failure when:   Due to erosion, a) the site required a flood fight in a past high‐water event to prevent a breach, or             

b) erosion has encroached into either the waterside levee prism or extended levee prism, and as a result, 

is likely to cause a levee failure in the next high‐water event; 

Due to seepage, a) the site required a flood fight in a past high‐water event to prevent a breach, or           

b) seepage is known by historical record of past performance to have recurrent piping or boils that carry 

material, at a water stage less than design level, and as a result the site is likely to cause a levee failure in 

the next high‐water event; or, 

For stability, a) due to a slope stability issue, the site required a flood fight in a past high‐water event to 

prevent a breach, or b)  the levee embankment has slumped such that levee failure in the next high‐water 

event is likely. 

Serious:A site, if not repaired, has the potential to become critical when:  

Due to erosion, a) erosion has encroached into either the waterside levee prism or extended levee prism 

that may not cause a levee failure in the next high‐water event, or b) progressing erosion that is likely to 

encroach into either the waterside levee prism or extended levee prism;  

Page 4: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        4 

Due to stability, the levee embankment has deformed, the site may further deteriorate, may cause levee 

failure in a future high‐water event or may require a flood fight in a high water event to prevent a breach; 

or 

Due to seepage, seepage is known by historical record of past performance to have caused recurrent 

piping or boils, and the site may further deteriorate, may cause levee failure in a future high‐water event, 

or may require a flood fight in a high‐water event to prevent a breach. 

AreasofConcern:Areas of concern sites are the remainder of reported sites that have problems and need 

periodic monitoring, but do not rise to the hazard levels of “serious” or “critical”.  

 

The second step of the prioritization considers the hydraulic basins (leveed areas) receiving protection from SPFC 

levees. The areas are ranked into three tiers considering factors including: the overall past performance of the 

levees, frequency of loading, and the assets behind these levees. There are forty five leveed areas in Sacramento 

River Basin and twenty nine leveed areas in San Joaquin River Basin, which were grouped into the three tiers as 

follows:  

Page 5: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        5 

 Tier 1 represents the upper one‐third of levees areas with maximum assets combined with poorest 

performing levees.  

Tier 2 represents the middle third of the levee areas. 

Tier 3 represents the least assets behind the levees combined with best performing levees. 

EnvironmentalPermitting Coordination with the regulatory agencies is occurring through a Unified Command Group (UCG), comprised of 

other State and Federal agencies, conference calls, or with specific agencies for specific permit issues. 

Onsite vegetation plantings have followed the U.S. Army Corps of Engineers “engineering  technical letter” (ETL) 

standard for vegetation on levees, meaning that woody vegetation was not planted on the levee itself or 15 feet 

from the levee toe.  

Avoidance of impacts is the primary consideration for managing environmental impacts. Compensatory mitigation 

for unavoidable impacts to endangered species will be off‐site. 

First 16 critical sites: 

o Permits have been issued. (One exception: biological opinion from the National Marine Fisheries Service 

will be after the fact). A couple of sites had emergency notifications sent to Department of Fish and 

Wildlife. 

o Environmental Staff are monitoring construction to ensure compliance with permits and work windows.  

o Permits are available to LMAs to download. 

o Purchasing of mitigation bank credits will begin mid‐October to meet permit conditions. 

Next 22 critical sites: 

o Emergency permitting processes are being used for the 12 sites going to construction in November; with 

emergency notifications to Department of Fish and Wildlife, Regional General Permit #8 with the U.S. 

Army Corps of Engineers for Clean Water Act Section 404, and after the fact biological opinions with U.S. 

Fish and Wildlife Service and National Marine Fisheries Service.  

o Mitigation measures and best management practices will be incorporated into construction for sites 

without current issued permits. 

Tribal/CulturalUnder DWR’s policy for Tribal Engagement, we have committed to consult with tribal entities to identify and protect Tribal 

Cultural Resources (TCR)’s where feasible, and to cooperate in the development of treatment and mitigation plans to 

mitigate for impacts on tribal cultural resources and cultural places.  We are also working to meet the standards of the CA 

Natural Resources Tribal Policy.  As such, we are in consultation with six tribes as we undertake construction and repair 

under the emergency levee rehabilitation program on all DWR critical and serious sites.  These include the Ione Band of 

Miwok Indians (IBMI), The United Auburn Indian Community (UAIC), the Wilton Rancheria, The Yocha DeHe Wintun Nation 

(YDWN), the Shingle Springs Band of Miwok Indians (SSBMI), and the Upper Lake Pomo Habematolel.   Representatives of 

select tribes are on site for assessment and monitoring as construction takes place. 

 

 

Page 6: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        6 

DescriptionofUSACE’sSitePrioritizationProcessEvaluation factors used to rank PL84‐99 rehabilitation sites (as provided by USACE): 

PL84‐99 rehabilitation sites are ranked based on severity of damages and potential consequences of a levee breech as 

outlined in Table 1 and described below.  

Table 4: PL84‐99 Rehabilitation Site Ranking

  High Consequences

Low to Moderate Consequences 

Severe Damage  Order 1 Order 2 

Moderate Damage  Order 2  Order 3 

Minor Damage  Order 3  Order 4 

 

Order 1: The damages are severe and make it very likely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect urban areas where potential consequences are high (there is a significant population at risk and / or there could be a large economic impact). 

 Order 2: The damages are severe and make it very likely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect predominantly rural / agricultural areas where potential consequences are low to moderate.  Or, the damages are moderate and the levee may breach or need significant / major emergency repairs during the next flood event. These levees protect urban areas where potential consequences are high (there is a significant population at risk and / or there could be a large economic impact).  Order 3: The damages are moderate and the levee may breach or need significant / major emergency repairs during the next flood event. These levees protect predominantly rural / agricultural areas where potential consequences are low to moderate. Or, the damages are minor and it is unlikely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect urban areas where potential consequences are high (there is a significant population at risk and / or there could be a large economic impact). Order 4: The damages are minor and it is unlikely the levee would breach or need significant / major emergency repairs during the next flood event. These levees protect predominantly rural / agricultural areas where potential consequences are low to moderate.  Typical evidence of severe damage for both Order 1 and 2 Sites: 

Vertical or horizontal displacement in the levee crest or slopes greater than 3 feet.  

Large slumps or shallow landslides on the waterside or landside levee slope close to the levee crest that may lead to progressive failure of the levee. 

Evidence of sand boils indicating a significant volume of soil was removed from the levee foundation, (i.e. internal erosion was in progress). 

Evidence of large deposits of soil in land side ditches or canals indicating significant material was removed from the levee foundation (i.e. internal erosion was in progress). 

Significant water side erosion that threatens levee integrity / stability. 

Wave wash erosion high on the levee near the crest with vertical scarps greater than 5 ft. 

Widespread bulging or slumping of the levee toe due to through levee seepage.  Typical evidence of moderate damage for Order 2 and 3 Sites: 

Small slumps and slides with vertical or horizontal displacement of the levee slope less than 3 feet. 

Waterside bank erosion that does not yet affect levee integrity, but is close. 

Wave wash erosion on the upper half of the levee slope with vertical scarp less than 3 ft. 

Page 7: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        7 

Widespread under seepage of moderate to high volume, with pervasive pin (small diameter) boils. 

Isolated bulging or slumping of the levee toe due to through levee seepage  Typical evidence of minor damage for Order 3 and 4 Sites: 

Lateral or longitudinal tension cracks with minimal displacement indicating marginal slope stability. 

Wave wash erosion on the lower half of the levee slope with vertical scarps less than 3 ft. 

Localized low volume seepage with clear water not carrying material from the levee foundation or levee embankment. 

Damages (rutting and loss of aggregate) to the levee patrol road that impacts access / trafficability in bad weather. 

Small slides or slumps in the vicinity of the levee toe. 

ContingencyPlanAs a result of many factors such as funding limitations, timing of when damaged sites were identified, and permitting 

requirements not all DWR Critical sites will be rehabilitated prior to start of flood season (November 1) in 2017.  Similarly, 

several of the USACE PL 84‐99 Priority 2 and 3 sites will also not be repaired prior to the 2017/2018 flood season.   

As part of this year’s preparation for the upcoming flood season, DWR has reached out to each of the LMAs with unrepaired 

sites that have either been designated by DWR as Critical or Serious, or by the USACE as Priority 2 or 3.  DWR and LMAs will 

jointly develop contingency plans to assist and expedite emergency repairs during high water events.  These contingency 

plans could include pre‐determining quantities needed for repairs, stockpiling flood fighting materials nearby, and more.  

Although detailed contingency plans will be in place, LMAs are still required to follow the Standardized Emergency 

Management System (SEMS) process outlined in the letters sent to the LMAs in mid‐September 2017 (i.e., the flood fighting 

effort should begin with the LMAs, and then elevate to the County Office of Emergency Services (OES), and then to theState 

Flood Operations Center (FOC).  For the remainder of the DWR critical sites that were not repaired in 2017, DWR will re‐

assess any potential emergency repairs completed during the 2017‐18 flood season to see what additional repairs will be 

needed in future years.Note: The chart below represents the process for determining site ranking and contingency planning 

for all damaged sites. 

 

  

Page 8: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017 Public        8 

Figure 1: Contingency Planning Flow Chart

2018 Rehabilitation 

(After 2017/2018 Flood Season)

Contract Flood Fight Final Repair

Done 2018 Monitor Site Performance

2017/2018 FloodSeason

Action Needed/Contingency Plan

Final RepairDone 2017 –Monitor Site Performance

Yes No

MonitorNo

Traditional Flood Fight (Flood Threat Mitigation Process)

DWR Critical or USACE PL84‐99,P1, P2 & P3

DWR SeriousSites

Repair to be completed in2017

Action Needed/Contingency Plan

Yes

Yes No

Evaluation of Known & Reported Sites Damaged in 2016/2017 Flood Season

Sites Determined to Fail next Flood Season 

Page 9: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                9 

SiteListBelow is a table of the sites that will be repaired in 2017 or are part of DWR’s Contingency Planning Efforts. 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status 

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

LMA‐21  RD 1001  Bear River  Erosion  38.946751  ‐121.563825  DWR Construction Complete

USACE_CESPK_FAIR_ 2010_p_0044 

RD 787 Colusa Basin Drain

Stability  38.80101  ‐121.74838  DWR Construction In Process

LMA‐71 Tehama County Flood Control and Water Conservation District

Deer Creek – Unit 1 

Erosion  39.9469  ‐122.0515  DWR Construction Complete 

LMA‐3 Lake County Watershed Protection District

Middle Creek  Erosion  39.179715  ‐122.896926  DWR Construction Complete

LMA‐53  Sacramento Bypass Sacramento Bypass 

Stability  38.60133826  ‐121.5820263  DWR Construction In Process 

LMA‐52  Sacramento Bypass Sacramento Bypass 

Stability  38.60159656  ‐121.5811883  DWR Construction In Process 

LMA‐54  Sacramento Bypass Sacramento Bypass

Erosion  38.59683065  ‐121.5792158  DWR Construction In Process

RD 827‐03  RD827 ‐ Elkhorn Sacramento River

Erosion  38.674042  ‐121.642986  DWR Construction In Process

ST20‐01 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  39.171211  ‐121.730135  DWR Construction Complete 

ST11‐U4‐01  West Levee Yolo Bypass  Yolo Bypass  Erosion  38.53598014  ‐121.63143  DWR Construction Complete 

LMA‐74  SBFCA  Feather River  Seepage  39.15594  ‐121.61664  SBFCA Construction In Process

313‐14 RD2098 ‐ Cache & Haas Slough 

Cache Slough  Stability  38.28303742  ‐121.7110735  DWR Construction In Process

386‐32  RD150 ‐ Merrit Island  Elk Slough  Erosion  38.391054  ‐121.539214  DWR Construction In Process

LMA‐73 RD2098 ‐ Cache & Haas Slough 

Hass Slough  Erosion  38.29297  ‐121.72317  DWR Construction Complete 

Page 10: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                10 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

DWR_RD2098_01_s_2012_12 

RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.283868  ‐121.693627  DWR Construction Complete 

LMA – 245 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2965  ‐121.6935  DWR Construction In Process 

LMA – 247 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2962  ‐121.6935  DWR Construction In Process

LMA – 251 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2931  ‐121.6935  DWR Construction In Process

LMA – 252 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2929  ‐121.6935  DWR Construction In Process 

LMA – 253 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2923  ‐121.6934  DWR Construction In Process 

LMA – 254 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2919  ‐121.6935  DWR Construction In Process

LMA – 255 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2916  ‐121.6935  DWR Construction In Process

LMA – 265 RD2098 ‐ Cache & Haas Slough 

Cache Slough  Erosion  38.2837  ‐121.7134  DWR Construction In Process 

LMA – 266  RD2098 ‐ Cache & Haas Slough 

Cache Slough  Erosion  38.2872  ‐121.716  DWR Construction In Process 

LMA – 132  RD150 ‐ Merrit Island  Elk Slough  Stability  38.35623056  ‐121.5619167  DWR Construction In Process

LMA – 133  RD150 ‐ Merrit Island  Elk Slough  Erosion  38.37511389  ‐121.5446917  DWR Construction In Process

LMA – 134  RD150 ‐ Merrit Island  Elk Slough  Erosion  38.37721667  ‐121.5420583  DWR Construction In Process

DWR_RD2101_01_s_2012_1 

RD2101 ‐ Blewett San Joaquin River 

Erosion  37.65055  ‐121.22957  DWR Construction In Process 

DWR_RD2085_01_R_2012_01 

RD2085 ‐ Kasson San Joaquin River

Erosion  37.68662  ‐121.27679  DWR Construction In Process

DWR_RD0524_01_s_2012_21 

RD524 ‐ Middle Robert's Island 

San Joaquin River 

Erosion  37.93186  ‐121.32831  DWR Construction Complete  

Page 11: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                11 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

MA16‐01  Maintenance Area 16  Feather River Waterside Erosion 

39.258105  ‐121.636314  USACE Construction In Process 

MA12‐01  Maintenance Area 12 Colusa Basin Drain 

Waterside Slope Slip 

39.13392  ‐122.02277  USACE Construction In Process 

RD1001‐01  RD 1001  Feather River  Boils  38.78383  ‐121.61224  USACE Construction In Process

RD1001‐02  RD 1001 Natomas Cross Canal

Boils  38.81141  ‐121.56291  USACE Construction In Process

RD 108‐01  RD 108 Colusa Basin Drain 

Landside Slope Slip 

38.99577167  ‐121.9606167  USACE Construction In Process 

RD 108‐02  RD 108 Colusa Basin Drain 

Landside Slope Slip 

38.96777  ‐121.9241783  USACE Construction In Process 

RD 108‐03  RD 108 Colusa Basin Drain

Landside Slope Slip

38.94571667  ‐121.9067167  USACE Construction In Process

RD 108‐04  RD 108 Colusa Basin Drain

Waterside Slope Slip

38.89758333  ‐121.9146883  USACE Construction In Process

RD 108‐05  RD 108 Colusa Basin Drain 

Waterside Slope Slip 

38.89614167  ‐121.914445  USACE Construction In Process 

RD 2035‐01  RD 2035  Yolo Bypass Landside Slope Slip 

38.63979  ‐121.66129  USACE Construction In Process 

RD 2035‐02  RD 2035  Yolo Bypass Landside Slope Slip

38.63703  ‐121.6593  USACE Construction In Process

RD 2035‐03  RD 2035  Yolo Bypass Landside Slope Slip

38.63645  ‐121.65888  USACE Construction In Process

RD 2035‐04  RD 2035  Yolo Bypass Landside Slope Slip

38.63609  ‐121.65863  USACE Construction In Process

RD 2035‐05  RD 2035  Yolo Bypass Landside Slope Slip 

38.63443  ‐121.65738  USACE Construction In Process 

RD 2035‐06  RD 2035  Yolo Bypass Landside Slope Slip

38.63242  ‐121.65592  USACE Construction In Process

RD 2035‐07  RD 2035  Yolo Bypass Landside Slope Slip 

38.63104  ‐121.65491  USACE Construction In Process  

Page 12: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                12 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

SRWLD‐01 Sacramento River West Side Levee District 

Sacramento River 

Seepage  38.85186944  ‐121.7255694  N/A Contingency Plan 

RD 2035‐08  RD2035 ‐ Conway  Yolo Bypass  Erosion  38.59284  ‐121.63134  N/A Contingency Plan 

SCDU‐03  City of Sacramento Sacramento River

Erosion  38.571397  ‐121.513797  N/A Contingency Plan

MA9‐01  Maintenance Area 9 Sacramento River

Erosion  38.53135368  ‐121.5272856  N/A Contingency Plan

MA9‐03  Maintenance Area 9 Sacramento River 

Erosion  38.47482751  ‐121.5354548  N/A Contingency Plan 

LD1‐S‐02 Levee District 1 ‐ Sutter County 

Feather River  Erosion  39.018322  ‐121.610275  N/A Contingency Plan 

RD 70‐01  RD70 ‐ Meridian Sacramento River

Erosion  39.06819  ‐121.8627  N/A Contingency Plan

RD 70‐03  RD70 ‐ Meridian Sacramento River

Erosion  39.14524  ‐121.84265  N/A Contingency Plan

SRWLD‐02 Sacramento River West Side Levee District 

Sacramento River 

Seepage  39.09558889  ‐121.8974  N/A Contingency Plan 

SRWLD‐03 Sacramento River West Side Levee District 

Sacramento River 

Seepage  39.09496667  ‐121.8948583  N/A Contingency Plan 

SRWLD‐04 Sacramento River West Side Levee District

Sacramento River

Seepage  39.19933  ‐121.9881967  N/A Contingency Plan

SRWLD‐05 Sacramento River West Side Levee District

Sacramento River

Seepage  39.192405  ‐121.98732  N/A Contingency Plan

RD 2035‐09  RD2035 ‐ Conway  Yolo Bypass  Erosion  38.647061  ‐121.666439  N/A Contingency Plan

ST11‐U1‐01  West Levee Yolo Bypass  Yolo Bypass  Erosion  38.72724961  ‐121.660234  N/A Contingency Plan 

RD 1001‐03  RD1001 ‐ Nicolaus Natomas Cross Canal

Erosion  38.8281  ‐121.53474  N/A Contingency Plan

LMA‐119  RD150 ‐ Merrit Island  Elk Slough  Erosion  38.34814167  ‐121.5723194  N/A Contingency Plan  

Page 13: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                13 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

LMA‐122  RD150 ‐ Merrit Island  Elk Slough  Stability  38.35623056  ‐121.5619167  N/A Contingency Plan 

LMA‐139  RD150 ‐ Merrit Island  Elk Slough  Stability  38.39583333  ‐121.53715  N/A Contingency Plan 

LMA‐140  RD150 ‐ Merrit Island  Elk Slough  Stability  38.39623333  ‐121.5360639  N/A Contingency Plan

LMA‐147  RD349 ‐ Sutter Island Steamboat Slough

Erosion  38.30221667  ‐121.5798472  N/A Contingency Plan

LMA‐191  RD2060 ‐ Hastings Lindsey Slough 

Erosion  38.25118611  ‐121.7171139  N/A Contingency Plan 

LMA‐216  RD2060 ‐ Hastings  Cache Slough  Erosion  38.29053889  ‐121.7316028  N/A Contingency Plan 

LMA‐304 San Joaquin County Flood Control District 

Mormon Slough

Erosion  38.04593  ‐121.023021  N/A Contingency Plan

LMA‐417  RD2089 ‐ Stark  Old River  Erosion  37.8056  ‐121.4019  N/A Contingency Plan

LMA‐439 RD524 ‐ Middle Robert's Island 

San Joaquin  Erosion  37.9317  ‐121.3283  N/A Contingency Plan 

DWR_NA0016_01_s_2012_2 

Sacramento River West Side Levee District 

Sacramento River 

Erosion  38.95405988  ‐121.8405597  N/A Contingency Plan 

DWR_LD0003_01_s_2012_52 

Levee District 3 Sacramento River

Erosion  39.50438815  ‐121.9853009  N/A Contingency Plan

DWR_RD0003_01_R_2012_03 

RD3 ‐ Grand Island Steamboat Slough

Erosion  38.18381  ‐121.64878  N/A Contingency Plan

LMA‐34  RD2075 ‐ McMullin San Joaquin River

Seepage  37.728038  ‐121.274353  N/A Contingency Plan

FSRP‐13‐55  RD2085 ‐ Kasson San Joaquin River 

Erosion  37.703094  ‐121.274894  N/A Contingency Plan 

LMA‐15  RD1001 ‐ Nicolaus Yankee Slough

Erosion  38.975019  ‐121.481066  N/A Contingency Plan

LMA‐20  RD1001 ‐ Nicolaus  Feather River  Seepage  38.838  ‐121.633051  N/A Contingency Plan  

Page 14: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                14 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

RD 70‐02  RD70 ‐ Meridian Sacramento River 

Seepage (B)  39.15748  ‐121.87925  N/A Contingency Plan 

DWR_NA0019_04_s_2012_9 

Tehema County Flood Control and Water Conservation District

Elder Creek  Erosion  40.05159551  ‐122.1641788  N/A Contingency Plan 

RD 900‐01  RD900 ‐ West Sacramento

Deep Water Shipping Canal

Erosion  38.50896944  ‐121.5816806  N/A Contingency Plan 

ST11‐U4‐02  West Levee Yolo Bypass  Yolo Bypass  Erosion  38.56328942  ‐121.6383671  N/A Contingency Plan

LMA‐29 Marysville Levee Commission 

Feather River  Erosion  39.129715  ‐121.596819  N/A Contingency Plan 

MA5‐N‐01  Maintenance Area 5 Butte Creek  Erosion  39.676298  ‐121.778272  N/A 

Contingency Plan 

LMA‐72 

Tehama County Flood Control and Water Conservation District

Deer Creek ‐ Unit 1 

Erosion  39.964869  ‐122.029  N/A Contingency Plan 

LMA‐100  RD3 ‐ Grand Island Steamboat Slough 

Erosion  38.302981  ‐121.577336  N/A Contingency Plan 

LMA‐101  RD3 ‐ Grand Island Steamboat Slough 

Erosion  38.293381  ‐121.58245  N/A Contingency Plan 

LMA‐113  RD150 ‐ Merrit IslandSacramento River

Erosion  38.357183  ‐121.528547  N/A Contingency Plan

LMA‐130  RD150 ‐ Merrit IslandElk Slough  Erosion  38.37427778  ‐121.5491667  N/A 

Contingency Plan

LMA‐131  RD150 ‐ Merrit Island Elk Slough  Erosion  38.37431389  ‐121.5477528  N/A 

Contingency Plan 

LMA‐136  RD150 ‐ Merrit Island Elk Slough  Erosion  38.38216944  ‐121.5445972  N/A 

Contingency Plan 

LMA‐142  RD150 ‐ Merrit IslandElk Slough  Erosion  38.40922778  ‐121.5393889  N/A 

Contingency Plan

LMA‐143  RD150 ‐ Merrit IslandElk Slough  Erosion  38.40798333  ‐121.5343222  N/A 

Contingency Plan

Page 15: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                15 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

LMA‐151  RD349 ‐ Sutter Island Steamboat Slough 

Erosion  38.27903889  ‐121.5896639  N/A Contingency Plan 

LMA‐156  RD755 ‐ Randall Sacramento River 

Erosion  38.33775833  ‐121.5638556  N/A Contingency Plan 

LMA‐169  RD551 ‐ Pearson Sacramento River

Erosion  38.27459167  ‐121.5389583  N/A Contingency Plan

LMA‐178  RD551 ‐ Pearson Sacramento River

Erosion  38.26443611  ‐121.5254722  N/A Contingency Plan

LMA‐184  RD999 ‐ Netherlands Sacramento River 

Erosion  38.41531944  ‐121.5237167  N/A Contingency Plan 

LMA‐192  RD2060 ‐ Hastings Lindsey Slough 

Erosion  38.25188611  ‐121.7199333  N/A Contingency Plan 

LMA‐193  RD2060 ‐ Hastings Lindsey Slough

Erosion  38.25597222  ‐121.7241972  N/A Contingency Plan

LMA‐195  RD2060 ‐ Hastings Lindsey Slough

Erosion  38.25931667  ‐121.7263139  N/A Contingency Plan

LMA‐197  RD2060 ‐ Hastings Lindsey Slough 

Erosion  38.26077222  ‐121.7408167  N/A Contingency Plan 

LMA‐205  RD2060 ‐ Hastings Lindsey Slough 

Erosion  38.26015  ‐121.7635556  N/A Contingency Plan 

LMA‐206  RD2060 ‐ Hastings Lindsey Slough

Erosion  38.26071389  ‐121.7679722  N/A Contingency Plan

LMA‐220  RD2060 ‐ Hastings Cache Slough  Erosion  38.28733611  ‐121.7243639  N/A 

Contingency Plan

LMA‐224  RD2060 ‐ Hastings Cache Slough  Erosion  38.28273333  ‐121.7176833  N/A 

Contingency Plan

LMA‐225  RD2060 ‐ Hastings Cache Slough  Erosion  38.28183889  ‐121.7169639  N/A 

Contingency Plan 

LMA‐230  RD2060 ‐ Hastings  Cache Slough  Erosion  38.27785  ‐121.7126389  N/A Contingency Plan

LMA‐232  RD2060 ‐ Hastings  Cache Slough  Erosion  38.27660833  ‐121.7108111  N/A Contingency Plan  

Page 16: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                16 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

LMA‐237  RD2060 ‐ Hastings  Cache Slough  Erosion  38.26400556  ‐121.6988111  N/A Contingency Plan 

LMA‐238  RD2060 ‐ Hastings  Cache Slough  Erosion  38.26211389  ‐121.6979778  N/A Contingency Plan 

LMA‐239  RD2060 ‐ Hastings  Cache Slough  Erosion  38.26078889  ‐121.6969639  N/A Contingency Plan

LMA‐243 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2971  ‐121.6933  N/A Contingency Plan

LMA‐248 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2959  ‐121.6935  N/A Contingency Plan 

LMA‐256 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2892  ‐121.6935  N/A Contingency Plan 

LMA‐257 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2888  ‐121.6935  N/A Contingency Plan

LMA‐258 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2869  ‐121.6935  N/A Contingency Plan

LMA‐259 RD2098 ‐ Cache & Haas Slough 

Shag Slough  Erosion  38.2857  ‐121.6935  N/A Contingency Plan 

LMA‐269 RD2098 ‐ Cache & Haas Slough 

Cache Slough  Erosion  38.2913  ‐121.7161  N/A Contingency Plan 

LMA‐281  RD2068 ‐ Yolano Shag Slough  Stability  38.36234  ‐121.69406  N/A 

Contingency Plan

LMA‐284  RD2068 ‐ Yolano Shag Slough  Stability  38.3607  ‐121.6942  N/A 

Contingency Plan

LMA‐287  RD2068 ‐ Yolano Shag Slough  Stability  38.3595  ‐121.6942  N/A 

Contingency Plan

LMA‐289  RD2068 ‐ Yolano  Shag Slough  Stability  38.3545  ‐121.694  N/A Contingency Plan 

LMA‐290  RD2068 ‐ Yolano  Shag Slough  Stability  38.3462  ‐121.694  N/A Contingency Plan

LMA‐291  RD2068 ‐ Yolano  Shag Slough  Stability  38.3449  ‐121.694  N/A Contingency Plan  

Page 17: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                17 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

LMA‐295 RD524 ‐ Middle Robert's Island 

San Joaquin River 

Erosion  37.8922  ‐121.328  N/A Contingency Plan 

LMA‐296  RD2095 ‐ Paradise Cut San Joaquin River 

Erosion  37.740196  ‐121.297662  N/A Contingency Plan 

LMA‐328  West Levee Yolo Bypass Sacramento River

Erosion  38.7591  ‐121.667964  N/A Contingency Plan

SCDU‐07  City of Sacramento Sacramento River

Erosion  38.56207  ‐121.51577  N/A Contingency Plan

LMA‐407  RD307 ‐ Lisbon Sacramento River 

Erosion  38.43165  ‐121.533367  N/A Contingency Plan 

LMA‐408  RD307 ‐ Lisbon Sacramento River 

Erosion  38.431219  ‐121.533411  N/A Contingency Plan 

LMA‐409  RD307 ‐ Lisbon Sacramento River

Erosion  38.430958  ‐121.533364  N/A Contingency Plan

LMA‐410  RD307 ‐ Lisbon Sacramento River

Erosion  38.430572  ‐121.533372  N/A Contingency Plan

LMA‐411  RD307 ‐ Lisbon Sacramento River 

Erosion  38.430447  ‐121.533336  N/A Contingency Plan 

LMA‐412  RD307 ‐ Lisbon Sacramento River 

Erosion  38.430367  ‐121.533306  N/A Contingency Plan 

LMA‐413  RD2089 ‐ Stark  Old River  Erosion  37.8121  ‐121.4159  N/A Contingency Plan

LMA‐414  RD2089 ‐ Stark  Old River  Erosion  37.81027  ‐121.41324  N/A Contingency Plan

LMA‐418  RD2089 ‐ Stark  Old River  Erosion  37.8097  ‐121.3964  N/A Contingency Plan

LMA‐440 RD524 ‐ Middle Robert's Island 

San Joaquin  Erosion  37.9319  ‐121.3284  N/A Contingency Plan 

LMA‐443 RD524 ‐ Middle Robert's Island 

San Joaquin  Erosion  37.9353  ‐121.3332  N/A Contingency Plan

LMA‐457 RD544 ‐ Upper Robert's Island 

Old River  Erosion  37.8203  ‐121.3457  N/A Contingency Plan  

Page 18: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                18 

Table 5: 2017 Storm Damage – DWR Emergency Rehabilitation Repair Site Status

Site Designation  LMA  Waterway  Damage  Latitude  Longitude Constructing 

AgencyConstruction 

Status

LMA‐464 RD544 ‐ Upper Robert's Island 

Old River  Erosion  37.8135  ‐121.3194  N/A Contingency Plan 

LMA‐465 RD544 ‐ Upper Robert's Island 

Old River  Erosion  37.8184  ‐121.319  N/A Contingency Plan 

LMA‐468 RD544 ‐ Upper Robert's Island 

Old River  Erosion  37.8294  ‐121.312  N/A Contingency Plan

LMA‐469 RD544 ‐ Upper Robert's Island 

Old River  Erosion  37.8296  ‐121.3121  N/A Contingency Plan

LMA‐488  RD2064 ‐ River Junction San Joaquin River 

Erosion  37.6778  ‐121.2644  N/A Contingency Plan 

LMA‐500 Tehama County Flood Control and Water Conservation District

Deer Creek ‐ Unit 1 

Erosion  39.96925  ‐122.008681  N/A Contingency Plan 

 

Page 19: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                19 

Figure 2: Site Location Map – Sacramento Basin   

 

Page 20: 2017 Storm Damage Emergency Rehabilitation …cvfpb.ca.gov/wp-content/uploads/2017/10/SDDER_PUBLIC...2017 Storm Damage – DWR Emergency Rehabilitation October 27, 2017 10/26/2017

2017StormDamage–DWREmergencyRehabilitationOctober27,2017

10/26/2017                20 

Figure 3: Site Location Map – San Joaquin Basin