2015 nace daytona_gsp

47
MEHAFFEY BRIDGE CONSTRUCTION Mehaffey Bridge Road Structure G-32-1 over the Iowa River at Coralville Lake Project #LFM-MEH BR--7X-52

Upload: florida-public-works-expo

Post on 07-Aug-2015

29 views

Category:

Education


0 download

TRANSCRIPT

MEHAFFEY BRIDGE CONSTRUCTIONMehaffey Bridge Road Structure G-32-1 over the Iowa River at Coralville LakeProject #LFM-MEH BR--7X-52

PRESENTATION OUTLINE

• Introductions• Project Background• Structural Highlights• Construction Challenges• Questions

INTRODUCTIONS

APWA Spring Conference March 27, 2015

YOUBrilliant, engaged professional

Your job today:◦ Actively engage in the discussion◦ Learn a little something◦ Ask questions

PROJECT BACKGROUND

APWA Spring Conference March 27, 2015

ORIGINAL RESERVOIR BRIDGE

49 years old (started 1964, completed 1966) Cost to Johnson County - $100,000

($6.55/SF) Structurally deficient (posted 10%), SR=33.3 28’ Width not suitable for current/expected

traffic levels Subject to closure during 1993/2008 level

flood events

APWA Spring Conference March 27, 2015

NEW MEHAFFEY BRIDGE DESIGNDesign Constraints/ Project Goals

Design for better flood resistance Capable of handling 4-lane traffic Include a multi-purpose trail Maintain traffic during construction (Current: 3700,

Design 5500 AADT) Open waterway by minimizing number of piers to

allow for better recreation traffic Do it all for $3M

APWA Spring Conference March 27, 2015

NEW MEHAFFEY BRIDGE DESIGNAlternatives Considered

Do nothing/repair Conventional IDOT bridge (PPCB) Hump-Back Steel Cantilevered Pre-Stressed Concrete 2-Pier

Design Cable-stay bridge (End or Center

Support) Something else???

APWA Spring Conference March 27, 2015

NEW MEHAFFEY BRIDGE DESIGNJacobsen BridgeEXTRADOSE

D

APWA Spring Conference March 27, 2015

NEW MEHAFFEY BRIDGE DESIGN

Flood resistant at 1993/2008 Levels (Elev. 717.00)

565’ x 55’ = 31075 SF 2 traffic lanes (40’ Roadway), 12’ Multi-Use Path Long span = 112’ (BTC) Traffic maintained on the old bridge throughout

sub-structure construction Only 2 piers in the water Distance from pier to pier = 224’ Contract amount = $8.9M ($286/SF)

STRUCTURAL HIGHLIGHTS

APWA Spring Conference March 27, 2015

REDUNDANCYWhen Might Sometimes Makes Right

 HAMILTON COUNTY, OH — On the night of Tuesday, May 20, 2008, a flatbed trailer carrying an old 80-ton locomotive broke free from its truck hitch. The trailer drifted forward along the southbound lane of I-275 and crashed into a pier supporting the eastbound I-74 overpass.The 32-year-old steel bridge sagged, but didn’t collapse. Eastbound traffic on I-74 traveled over the damaged bridge for about 10 minutes before officials arrived to close the bridge and reroute traffic.

APWA Spring Conference March 27, 2015

DIAGONAL SECTION

APWA Spring Conference March 27, 2015

DIAGONAL POST-TENSIONING END ANCHORAGE

APWA Spring Conference March 27, 2015

DIAGONAL AND PIER VIEW

APWA Spring Conference March 27, 2015

DIAGONAL AND PIER VIEW

APWA Spring Conference March 27, 2015

DIAGONAL AND PIER VIEW

APWA Spring Conference March 27, 2015

END OF DIAGONAL (KNUCKLE)

APWA Spring Conference March 27, 2015

KNUCKLE/SUSPENDED FLOOR BEAM

APWA Spring Conference March 27, 2015

SUBSTRUCTURE/KNUCKLES

APWA Spring Conference March 27, 2015

SUBSTRUCTURE/KNUCKLES

APWA Spring Conference March 27, 2015

FLOOR BEAM SECTION

APWA Spring Conference March 27, 2015

FLOOR BEAMS

APWA Spring Conference March 27, 2015

FLOOR BEAMS

APWA Spring Conference March 27, 2015

FLOOR BEAMS

APWA Spring Conference March 27, 2015

FLOOR BEAMS

APWA Spring Conference March 27, 2015

FLOOR BEAM POST-TENSIONING ANCHORAGE

APWA Spring Conference March 27, 2015

FLOOR BEAM POST-TENSIONING ANCHORAGE

APWA Spring Conference March 27, 2015

PUTTING IT ALL TOGETHER

APWA Spring Conference March 27, 2015

PUTTING IT ALL TOGETHER

APWA Spring Conference March 27, 2015

REDUNDANCY MET

Multiple stringers Diagonals and floor beams have multiple

rebar and two systems for reinforcing. Prestressed beams will be continuous for

extreme event and will carry in the event of loss of a diagonal or floor beam.

CONSTRUCTION CHALLENGES

It’s an expensive, unique design - what could possibly go wrong?

APWA Spring Conference March 27, 2015

DETAILS, DETAILS, DETAILS

APWA Spring Conference March 27, 2015

CONDITIONS

APWA Spring Conference March 27, 2015

TRAFFIC/THE PUBLIC

A recent count showed almost 5k AADT◦ They are not patient◦ They will not go around

The expectation is increasingly - zero delays Accelerated Bridge Construction

◦ 90 day critical closure incentive/disincentive◦ We build the new bridge, from a traffic impact

perspective, in approximately 3 months◦ Tier 5 ABC - Definitely◦ Tier 4 ABC - Most likely

How do we manage expectations???

APWA Spring Conference March 27, 2015

COMMUNICATIONSQR Code Road Signs

Website

Twitter

Dynamic Message

Signs

APWA Spring Conference March 27, 2015

COMMUNICATIONSDynamic Speed Signs

QR Code

Public Informational Meetings

Press ReleasesRadio Spots

APWA Spring Conference March 27, 2015

PROJECT STAGING

◦ Stage 1 - Construct the towers◦ Stage 2 - Construct Diagonals, Floor Beams,

Compression Struts and Knuckles◦ Stage 3 - Construct Trail portion of the deck◦ Stage 4 - Switch traffic, demo old bridge,

complete deck and paving

APWA Spring Conference March 27, 2015

STAGE 1

APWA Spring Conference March 27, 2015

STAGE 2

APWA Spring Conference March 27, 2015

STAGE 3

APWA Spring Conference March 27, 2015

STAGE 3

APWA Spring Conference March 27, 2015

STAGE 3

APWA Spring Conference March 27, 2015

STAGE 4

APWA Spring Conference March 27, 2015

THANK YOU!

A special thank you to:◦ Johnson County Board of Supervisors◦ VJ Engineering◦ Steve Jacobsen, SE◦ Iowa Bridge & Culvert, LC◦ The US Army Corps of Engineers◦ The Iowa Department of Natural Resources

APWA Spring Conference March 27, 2015

CONTACT

Greg S. Parker, PE◦ Johnson County Engineer◦ 4810 Melrose Avenue West◦ Iowa City, Iowa 52246◦ 319.356.6046◦ [email protected]

QUESTIONS?