Jamaica Bay Jamaica Bay Task Force Meeting Task Force Meeting Update on Jamaica Bay Update on Jamaica Bay Biological Nutrient Reduction Program Biological Nutrient Reduction Program March 19, 2015 March 19, 2015

Upload: ecowatchers

Post on 15-Jul-2015

124 views

Category:

Environment


1 download

TRANSCRIPT

Page 1: 2015 3-19 jamaica bay bnr update 2

Jamaica Bay Jamaica Bay Task Force MeetingTask Force Meeting

Update on Jamaica Bay Update on Jamaica Bay Biological Nutrient Reduction ProgramBiological Nutrient Reduction Program

March 19, 2015March 19, 2015

Page 2: 2015 3-19 jamaica bay bnr update 2

2

Overview of Jamaica Bay Jamaica Bay is designated for primary contact

and it’s tributaries are designated for secondary contact

Water quality in Jamaica Bay is better than its been in 100 years and supports a wide variety of wildlife but there are still impairments:

Waters tend to be eutrophic Seasonal low DO levels

These water quality impairments are linked to high nutrient loadings in conjunction with man-made physical alterations

DEP is upgrading all for of it’s WWTP that discharge into Jamaica Bay for Step Feed BNR

Loss of the marsh islands is another critical issue within Jamaica Bay

DEP has partnered with ACOE to restore many of these marsh islands ($13M funded)

Page 3: 2015 3-19 jamaica bay bnr update 2

3

Historical Water Quality

Page 4: 2015 3-19 jamaica bay bnr update 2

Additional Water Quality Studies

In 1995/96 DEP conducted comprehensive water quality and ecological studies to calibrate JEM

Subsequent comprehensive water quality, ecological, and finfish studies were conducted in 2005/2006

Ongoing Jamaica Bay Science & Resiliency Institute will be refining JEM

DEP to conduct a comprehensive Post Construction Monitoring Plan from 2016 thru 2019

4

Water QualityWater Quality MarshlandMarshland

UlvaUlva PhytoplanktonPhytoplankton

Page 5: 2015 3-19 jamaica bay bnr update 2

5

Jamaica Bay Restoration Projects

Page 6: 2015 3-19 jamaica bay bnr update 2

6

CSO Projects

Page 7: 2015 3-19 jamaica bay bnr update 2

FANCJ BNR Requirements for JB

7

26W Step Feed BNR Construction Completion: July 2010

26W Commence Operation of Interim Carbon: December 2011

26W Commence Operation of Permanent Chemical Feed Systems: December 2015

JA Step Feed Operations: December 2014

JA Step BNR Construction Completion: June 2015

RK BNR Construction Completion: December 2019

CI BNR Construction Completion: December 2020

Page 8: 2015 3-19 jamaica bay bnr update 2

26th Ward WWTP (26W-12)

8

26W: FANCJ Milestones:

Step Feed BNR Construction Completion Milestone: July 31, 2010

Commence Operation of Interim Carbon: December 31, 2011

Commence Operation of Permanent Supplemental Chemical Feed Systems: December 31, 2015

Page 9: 2015 3-19 jamaica bay bnr update 2

26th Ward WWTP (26W-12)

9

z

26W-12: Step Feed BNR26W-12: Step Feed BNRSeparate Centrate Separate Centrate

Treatment + Interim Treatment + Interim CarbonCarbon

New Permanent New Permanent Chemical FacilitiesChemical Facilities

Page 10: 2015 3-19 jamaica bay bnr update 2

26th Ward WWTP Performance

15

Page 11: 2015 3-19 jamaica bay bnr update 2

1111

Jamaica WWTP (JA-2)

JA: FANCJ Milestones:Step Feed BNR Commence BNR Operation Milestone: December 31, 2014

Step Feed BNR Construction Completion Milestone: June 30, 2015

Commence Operation of Permanent Supplemental Chemical Feed Systems: June 30, 2016

Page 12: 2015 3-19 jamaica bay bnr update 2

1212

Jamaica WWTP (JA-2)

z

JA-2: Step Feed BNRJA-2: Step Feed BNR

New Carbon FacilitiesNew Carbon Facilities

Page 13: 2015 3-19 jamaica bay bnr update 2

Jamaica WWTP Performance

13

Page 14: 2015 3-19 jamaica bay bnr update 2

1414

Current Jamaica Bay TN Discharges

Page 15: 2015 3-19 jamaica bay bnr update 2

15

Supplemental Carbon Facilities Carbon Operation Milestone:

• 26th Ward – December 31, 2013

• Jamaica – June 30, 2016

Construction Completion Milestone:

• Jamaica Bay – December 31, 2016

Projected TN Reduction = 4.700 lbs/d

Page 16: 2015 3-19 jamaica bay bnr update 2

Coney Island BNR Upgrade

Design Completion: December 2015 Construction Completion: December 2020 Projected to remove an additional 1,200 lbs/d of nitrogen

16

Page 17: 2015 3-19 jamaica bay bnr update 2

Rockaway BNR Upgrade

17

Design Completion: December 2015 Construction Completion: December 2019 Projected to remove an additional 3,300 lbs/d of nitrogen