20140908 report of findings bishop tube

Upload: thereadingshelf

Post on 07-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    1/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    1

    CLIENT: Inland DesignPROJECT: 10 Malin Road

    REQUIREMENT: PROFESSIONAL ENGINEERING SERVICES: Geotech/SWLOCATION: 10 Malin Road, West Whiteland Township

    DATE: September 8, 2014

    ATTENTION: Chuck Dobson, P.E. via Email

    Bo Erixxon, Project Manager via Email

    PURPOSE 

    The purpose of this report is to present the Findings, Conclusions and Recommendations relative

    to the physical investigation performed at the above captioned project location.

    INVESTIGATION 

    Jason Culp, P.E. and Nick Banta were present on site Friday September 5th, 2014 to conduct a

    subsurface investigation at the above mentioned project location. The investigation included

    eight (8) double ring infiltrometer tests to be conducted within proposed infiltration areas. The

    exact design of the stormwater facilities was not currently known as site data was required toprovide preliminary design. The findings and conclusions generated are to provide the initial

    broad range characteristics for design. A final more detailed investigation of the site may be

    required as the design proceeds further. In additional to information for the Stormwater relatedfacilities IES was also requested to record pertinent construction costs aspects of the site such as

    shallow groundwater, soil suitability, rock depth etc. Testing was conducted according to thePennsylvania Stormwater Best Management Guidelines’ Appendix C: Site Evaluation and Soil

    Testing Procedures. All double ring tests were presoaked for a minimum of one hour or two 30

    minute intervals prior to recording measured infiltration readings.

    FINDINGS 

    The Findings below use abbreviated nomenclature germane to soil morphology and other BMPterminology.

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    2/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    2

    Test Pit Logs:

    TP no. 1 Tested at 65”

    0-8” Topsoil Root mat

    8”-30” Lt. Brn. To Red Sandy SILT

    30”-132” Decomposed Schist 80-90% Coarse Fragments, veryfriable coarse Fragments (Channers)

    can be broken with significant hand

    pressure to rock hammer strikes

    Near vertical strikedipping towards

    the upslope side

    Limiting Zone Encountered-Rock @ 11’, lack of sufficient soil ‘medium’ will require filtering

    TP no. 2 Tested at 58”

    0-10” Topsoil Root mat

    10”-30” Reddish Gravels andChannerrs

    w/ Sandy SILT

    30”-165” Reddish Channers (schist)fragments with soil filled

    bedding/fracture planes

    Soil fill is reddish Silty SAND;coarse Fragments (Channers) can be

    broken with significant hand

    pressure to rock hammer strikes

    Near vertical strikedipping towards

    the upslope side

    No GW or Limiting Zone Encountered, lack of sufficient soil ‘medium’ will require filtering

    TP no. 3 Tested at 70”

    0-7” Topsoil Root mat

    7”-55” Reddish Brn Channery Mica SILT

    55”-168”Tan/White Mica v.f. SAND & SILT Channery Friable coarse fragmentsNo GW or Limiting Zone Encountered

    TP no. 4 Tested @ 74” BGS

    0-12” Topsoil Root mat

    12”-36” Lt. Brn Channery Sandy SILT

    36”-72” Reddish Brn Channery Mica SILT Friable coarse fragments

    72”-15’ Tan/White Mica v.f. SAND & SILT Channery Friable coarse fragments

    No GW or Limiting Zone Encountered

    TP no. 5 Tested @ 79” BGS

    0-8” Topsoil Root mat8”-89” Lt Brn Gravels/Channers & f.

    Sandy Mica SILT

    89”-111” Reddish Brn Channery Mica SILT Friable coarse fragments

    111”-168”

    Tan/White Mica v.f. SAND & SILT

    No GW or Limiting Zone Encountered

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    3/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    3

    TP no. 6 Tested @ 78” BGS

    0-3” Asphalt

    3”-8”

    Subbase 3A modified

    8”-15” Tan Sandy SILT Previous fill

    15”-96” Reddish Brn-Grey-Var v.f. Sandy Mica SILT Saprilite, very Friable CF’s

    96”-172” Grey Mica SILT, Saprolite Friable CF’s

    No GW or Limiting Zone Encountered

    TP no. 7 Tested @ 78” BGS

    0-3” Asphalt

    3”-8” Subbase 3A modified

    8”-30” Brn f. Sandy Mica SILT l/s

    Gravels

    Previous fill

    30”-168” Grey Mica SILT S Saprolite of parent formation

    96”-172” Grey Mica SILT, Saprolite Friable CF’s

    No GW or Limiting Zone Encountered

    TP no. 8 Tested @ 84” BGS

    0-3” Asphalt

    3”-8” Subbase 3A modified

    8”-65” Gravelly v.f. Sandy Mica SILT Friable CF’s, Fill

    65”-194”Grey/Tan/Var. v.f. Sandy SILT v. micaceous very steeply

    to near vertical bedding

    Very friable CF’s,

    decomposed schist

    No GW or Limiting Zone Encountered

     Infiltration Testing

    TP No. 1 4” 4” 4” 4” 4”   4” final stabilized reading with 10 minute intervals24.0 inches/hour Final Stabilized Reading @ 65 inches BGS

    TP No. 2 3 ½” 3 ½” 3 ½” 3 ½” 3 ½” 3 ½”  3 ½” final stabilized reading with 10 minuteintervals

    21.0 inches/hour Final Stabilized Reading @ 58 inches BGS

    TP No. 3 ⅝” ¼” ¼” ¼”  ¼” final stabilized reading with 30 minute intervals

    0.25 inches/hour Final Stabilized Reading @ 70 inches BGS

    TP No. 4 ½” ½” ½” 3/8” 3/8”   3/8” final stabilized reading with 30 minute intervals0.75inches/hour Final Stabilized Reading @ 74 inches BGS

    TP No. 5 1” 1” ⅝” ½” ½” ½”  ½” final stabilized reading with 30 minute intervals

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    4/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    4

    1.0 inches/hour Final Stabilized Reading @ 79 inches BGS

    TP No. 6 1” 1” 1” 1”  1” final stabilized reading with 30 minute intervals

    2.0 

    inches/hour Final Stabilized Reading @ 78 inches BGS

    TP No. 7 ¼” ¼” ¼” ¼”  ¼” final stabilized reading with 30 minute intervals

    0.5inches/hour Final Stabilized Reading @ 78 inches BGS

    TP No. 8 2” 1¼” 1¼” 1¼” 1¼”   1¼” final stabilized reading with 30 minute intervals

    2.5inches/hour Final Stabilized Reading @ 84 inches BGS

    CONCLUSIONS 

    1. 

    The Design Engineer is recommended to use the above information for sizing the

    Proposed Stormwater Management Facilities with a slight rate reduction for

    subsurface infiltration facilities to ensure the longevity of the systems given the

    presence of fine grain soils and cohesive soil content.

    2.  The saprolite to residium strata that all tests were conducted within is highly variable

    both vertically and laterally. The majority of test areas with well draining tests wasdue to the near vertical bedding planes of the decomposed parent material (schist).

    The rapidly draining areas of test pits 1 and 2 is composed of decomposed parent

    rock, in this case Micaceous Schist to Gneiss. The material is highly decomposedhowever is in a platy, vertical orientation which promotes infiltration through the

    macropores of the soil/rock medium. In this area a filter layer of concrete sand will

    be necessary to ensure the proper filtering of pollutants to ensure water quality

    requirements are met.

    3.  We strongly recommends that a qualified Soil Engineer or representative thereof be

    present during infiltration facility installation to ensure the stone facility-sand-soilinterface is placed at an appropriate depth to maximize recharge. Facility bottom

    elevation often varies as overlying soils are not uniform thus requiring over

    excavation in localized areas of the facility to maximize infiltration potential.

    4. 

    The geotextile fabric is recommended to not be utilized at the bottom of any

    infiltration facility as the liner is serving too often as a hydraulically restrictive

    material and creating a ‘bath tub’ effect, ergo – only utilize the geotextile on thesides and top of the trench.

    5.  Test Pit no. 1 is the only area which exhibited somewhat shallow rock refusal. Allother test pits were excavated down to the maximum reach of the excavator. Most of

    the material is fractured and decomposed and therefore rippable, especially in a

    larger excavation.

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    5/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    5

    6.  The soils encountered are fine grained soils that are very moisture sensitive. Areasthat achieve compaction will be susceptible to breakdown with repeated construction

    traffic on top of those areas. Additionally, the coarse fragments throughout the site

    are easily fractured and broken down and therefore will have similar negative effectwith repeated traffic.

    7.  The site topography and open rapidly draining strata encountered at the upslopeportion of the site may result in areas downslope receiving intermittent seepage in

    localized areas. This should be considered for design of retaining walls and for

    mitigation in any construction activities.

    8. 

    Refer to the attached laboratory data for additional information regarding the

    findings above.

    9. 

    Test Pit locations were provided in the field by Inland Design. Please refer to theattached image of then plan provided to IES for test pit locations.

    10. 

    Please contact IES should questions/concerns relative to subsurface geology arise

    during planning or construction phases of this project as actual field conditions are

    expected to vary and this report does not speak to all possible issues that might arise.

    Very Truly Yours,

    Jason Culp, P.E.Project Manager

    Ingram Engineering Services, Inc.

    484.947.5549 office

    610.431.7015 fax [email protected] 

    Chadd W. Ingram, P.E.(DE, MD, NJ, PA), S.E.O.

    Principal & CEO

    Ingram Engineering Services, Inc.484.947.5549 office

    610.431.7015 fax

    [email protected] 

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    6/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    6

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    7/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    7

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    8/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    8

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    9/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    9

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    10/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    10

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    11/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    11

  • 8/20/2019 20140908 Report of Findings Bishop Tube

    12/12

      Ingram Engineering Services, Inc.16 Hagerty Blvd. Suite 400

    West Chester PA 19382

    Office 484-947-5549 Fax 610-431-7015 

    12