2014 road show - master electricians, electrical ... 3012 construction and demolition sites as/nzs...
TRANSCRIPT
![Page 1: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/1.jpg)
Department for Manufacturing, Innovation, Trade, Resources and Energy
Office of theTechnical RegulatorTechnical Regulator
2014 Road show
www.sa.gov.au/otr
DISCLAIMER : The views presented in this presentation are not necessarily those of the Government of South
Australia. The slides in this presentation are the property of the Government of South Australia, and may not be
copied or reproduced in any way. In developing this presentation, every effort has been made to ensure that
information reflects the requirements of the legislation, and any examples are intended to be of assistance in
outlining the application of the legislation. The information contained in this presentation does not constitute legal
advice or professional advice of any kind. It is your responsibility to seek independent legal and professional advice
on matters addressed in this presentation. The Crown will not be liable for any injury, damage or loss of any kind
sustained by any person that arises from reliance upon any information contained within this presentation.
![Page 2: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/2.jpg)
Topics• Standards updates
AS/NZS 3000 Wiring Rules
AS/NZS 3003 Patient Areas
AS/NZS 3010 Generator sets
AS/NZS 3012 Construction and demolition sites
AS/NZS 4777 Grid connection of solar systems via inverter
2014 Road Show
Office of the
Technical Regulator
AS/NZS 4777 Grid connection of solar systems via inverter
AS/NZS 5033 Installation of PV arrays
• Soft wiring systems – licensing requirements
• Existing/dangerous electrical work
• Electrical Certificates of Compliance – Proving your work
• Shocks
• AS/NZS 3000 Part 1 clarification
![Page 3: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/3.jpg)
AS/NZS 3000Electrical Installations –Wiring Rules
Standards committee EL 001 is currently rewriting AS/NZS 3000.
The new edition will:
• Look at FAQs and rewrite those clauses
that need rewording for better
Office of the
Technical Regulator
that need rewording for better
interpretation
• Include additional requirements for RCDs
The new edition may go to print in late 2015
![Page 4: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/4.jpg)
AS/NZS 3000Electrical Installations –Wiring Rules
Part 1
FundamentalPrinciples
Compliance by
Part 2
Deemed to comply Sections 2 – 8
Compliance by specific design Sections 2 – 8
and Appendices
AS/NZS 3000 Companion Standards deemed to
comply
AS/NZS 3000 Companion Standards. Alternative
Arrangement
![Page 5: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/5.jpg)
AS/NZS 3003Electrical Installations – Patient Areas
Standards committee HT-021 is currently reviewing AS/NZS 3003.
The industry has raised issues about interpreting the clauses.
Major areas of concern are:
• Home dialysis (new clause already written)
Office of the
Technical Regulator
• Home dialysis (new clause already written)
• Align terminology, definitions and layout with other standards
• Better definition of patient and cardio areas
• EPAS (Enterprise Patient Administration System)
![Page 6: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/6.jpg)
AS/NZS 3003Electrical Installations – Patient Areas
EPAS
Enterprise Enterprise
Patient
Administration
System
![Page 7: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/7.jpg)
AS/NZS 3010Electrical Installations - Generating Sets
Standards committee EL 001-24 is currently reviewing AS/NZS 3010.
A new edition is being written that will
Office of the
Technical Regulator
A new edition is being written that will clarify generator installations.
A draft for public comments should be available mid 2014.
Previously one of the main concerns was :
When
do I
switch
the
neutral ?
![Page 8: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/8.jpg)
AS/NZS 3010Electrical Installations - Generating Sets
Drawings have been revised
showing neutrals NOT being
switched.
That is because you don’t have to
Office of the
Technical Regulator
That is because you don’t have to
switch the neutral, and the
protective earth neutral (PEN)
conductor shall not be switched
or isolated.
![Page 9: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/9.jpg)
AS/NZS 3010Electrical Installations - Generating Sets
Three phase electrical
installation – connected to
three phase generator
Office of the
Technical Regulator
Neutral is
not
switched
![Page 10: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/10.jpg)
AS/NZS 3010Electrical Installations - Generating Sets
Active
and
neutral
switched
Single phase electrical
installations – connected to
portable gen set via inlet
Office of the
Technical Regulator
Isolated Generator
![Page 11: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/11.jpg)
AS/NZS 3012Electrical Installations – Construction and
Demolition SitesStandards committee EL001-17 is currently reviewing AS/NZS 3012Issues of concern include:
• 1.4.2 Portable Socket- Outlet Assemblies (PSOA’s) Definition for those allowed for use on construction sites
• 1.4.2 Portable Socket- Outlet Assemblies (PSOA’s) Definition for those allowed for use on construction sites
• 2.5.3 Protection against mechanical damage –cables installed on fences
• 2.7.3 Emergency Evacuation Lighting - minimum 20lux
These issues will be addresses in an amendment which should be available mid 2014
![Page 12: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/12.jpg)
AS/NZS 4777 Grid connection of energy systems via
inverters.
Standards committee EL 42 has released a two part
‘draft’ of the AS/NZS 4777 standard :
• Part 1: Installation requirements
Office of the
Technical Regulator
• Part 1: Installation requirements
• Part 2: Inverter requirements
The draft includes numerous safety enhancements and
is available for public comment now.
A new edition is expected to go to print in late 2014
![Page 13: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/13.jpg)
AS/NZS 5033 Installation and safety requirements for
photovoltaic (PV) arrays
Standards committee EL 42 will release amendment 3 for
AS/NZS 5033:2012 to address numerous issues such as:
Office of the
Technical Regulator
• PV strings using d.c. conditioning units
• D.C. wiring installation & segregation requirements
• Small micro inverter installations
The following slides cover a few examples of the revision
![Page 14: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/14.jpg)
Installations* above 600 V shall have restricted access: *not permitted for domestic
AS/NZS 5033 Installation and safety requirements for
photovoltaic (PV) arrays
Office of the
Technical Regulator
*not permitted for domestic
• Restricted access can be achieved by barriers or by
location
![Page 15: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/15.jpg)
AS/NZS 5033 Installation and safety requirements for
photovoltaic (PV) arrays
Restricted access by barrier
Awww, I wanna
touch the solar
Office of the
Technical Regulator
touch the solar
panels
![Page 16: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/16.jpg)
AS/NZS 5033 Installation and safety requirements for
photovoltaic (PV) arrays
Restricted access by location
Office of the
Technical Regulator
![Page 17: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/17.jpg)
Installations* above 600 V shall have restricted access: *not permitted for domestic
AS/NZS 5033 Installation and safety requirements for
photovoltaic (PV) arrays
Office of the
Technical Regulator
• Restricted access applies to PV modules, switch-
disconnectors and all d.c. wiring up to input of
inverter
• D.c. wiring installed within a conduit is considered
restricted access
![Page 18: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/18.jpg)
AS/NZS 5033 Installation and safety requirements for
photovoltaic (PV) arrays
Exposed metal module frames and array mounting
frames shall be earthed. This applies to all grid
connected PV arrays, including:
Office of the
Technical Regulator
connected PV arrays, including:
• ELV PV arrays (i.e. less than 120 V d.c.); and
• A.C. modules; and
• PV arrays connected to micro inverters
![Page 19: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/19.jpg)
Electrical Standards
If you have ideas for improvement in the next edition of
AS/NZS 3000 or any other standard mentioned particularly
with the interpretation of clauses,
be involved and let us know.
Office of the
Technical Regulator
Email your suggestions to dmitre.otrmail.com.au
YOUR INPUT IS APPRECIATED.
![Page 20: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/20.jpg)
Soft Wiring Systems
The wiring of demountable
office partitions and work
stations, that are assembled
on site, is considered to be
electrical installation work.
Office of the
Technical Regulator
Regardless of how the systems are connected to other
parts of the electrical installation, this work must be
carried out by suitably licensed electricians.
electrical installation work.
![Page 21: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/21.jpg)
Soft Wiring SystemsPortable screens and partitions are
regarded as portable equipment.
The insertion of a plug into a
socket outlet to provide supply
to the prewired equipment is
not electrical installation work.
Office of the
Technical Regulator
not electrical installation work.
However it would be expected that
these partitions would have
ongoing tag and testing to ensure
their electrical integrity fff
![Page 22: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/22.jpg)
Dangerous Electrical
Installations
Use section “B” of your Electrical Certificate of Compliance to
advise your customers of all substandard installation wiring.
Section 60 of The Electricity Act 1996. The Owner/Occupier is
responsible for their electrical installation.
![Page 23: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/23.jpg)
Dangerous Electrical
Installations
If the Owner/Occupier refuses to approve repairs
And
the installation is immediately dangerous
OrOr
it is in a public area phone the OTR on
8226 5518
after hours 1800 558 811
![Page 24: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/24.jpg)
Reporting dangerous electrical work
We often receive
calls from
contractors
regarding
Office of the
Technical Regulator
regarding
dangerous
electrical work that
they have found.
![Page 25: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/25.jpg)
Reporting dangerous electrical work
We would
encourage you
to contact the
OTR to report an
unsafe
installation if the installation if the
owner/occupier
refuses to rectify
the issue
![Page 26: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/26.jpg)
Reporting dangerous electrical work
![Page 27: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/27.jpg)
Reporting dangerous electrical work
![Page 28: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/28.jpg)
Reporting dangerous electrical work
![Page 29: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/29.jpg)
Reporting
dangerous
electrical work
![Page 30: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/30.jpg)
Reporting dangerous electrical work
![Page 31: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/31.jpg)
Reporting dangerous electrical work
Earth pit less
than 12 months
old.
Presumed that Presumed that
acid wash used
on “pebble” path
caused severe
corrosion.
![Page 32: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/32.jpg)
Reporting dangerous electrical work
![Page 33: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/33.jpg)
Reporting dangerous electrical work
![Page 34: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/34.jpg)
Recall NoticesCLIPSAL 413 SURFACE SOCKET
Sold through wholesalers between
9th January 2014 and 21st February 2014
![Page 35: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/35.jpg)
The OTR are currently considering developing an
electronic ECC system, thoughts so far:
• iPhone/Android app
• Drop down menu’s where practical
• Copies emailed to client, OTR and SAPN as
required
Electrical Certificates of Compliance
required
• Ability to print hard copy
Please give us your comments/feedback etc.
![Page 36: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/36.jpg)
An Authorised Person cannot
sign off their own work, you
cannot supervise your own
work.
The only person who can sign
off on their own work is the
Electrical Certificates of Compliance
off on their own work is the
Contractor.
Remember to register your
book.
![Page 37: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/37.jpg)
Electrical Certificates of Compliance
Sufficient detail so that the work
done can be identified for 5 years
Must have street number and address
Date started and finished
Other electrical work ie “foreignies
List defects observed,
or write
‘No defects observed’
Must be signed by the worker carrying
out the examination and tests
Signed in section 3 by the contractor /
authorized person / supervisor
Before the installation is
energized
![Page 38: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/38.jpg)
Electric Shocks (M.E.N)
Correct
service:
Office of the
Technical Regulator
service:
Current returns
to network
through
customers
neutral (low
resistance
path).
![Page 39: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/39.jpg)
Electric Shocks (M.E.N)
Correct
service: Open circuit
Office of the
Technical Regulator
service:
Current returns
to network
through
customers
neutral (low
resistance
path).
Open circuit
neutral:
Current now
returns to
Network through
general mass of
earth .
(high resistance)
![Page 40: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/40.jpg)
Accident Reporting
• Deaths immediately
• Injuries requiring medical
assistance within 24 hours
Office of the
Technical Regulator
• All other accidents within 10
working days
Regulation 70 of the Electricity (General) Regulations 2012
![Page 41: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/41.jpg)
Rescue & Resuscitation
A reminder……..
It will be a mandatory requirement from 1st June 2014
that persons who carry out, or help carry out electrical
work be suitably trained in Rescue & Resuscitation.
All Electrical Workers and apprentices will be required to All Electrical Workers and apprentices will be required to
maintain a 12 month’s competency in Rescue &
Resuscitation from this date.
![Page 42: 2014 Road show - Master Electricians, Electrical ... 3012 Construction and demolition sites AS/NZS 4777 Grid connection of solar systems via inverter 2014 Road Show ... AS/NZS 3012](https://reader033.vdocuments.us/reader033/viewer/2022051508/5ab814bb7f8b9ad5338c68ea/html5/thumbnails/42.jpg)
Department for Manufacturing, Innovation, Trade, Resources and Energy
OTR Office hours 8am to 4:30pm
Monday to Friday Ph – 8226 5518
www.dmitre.sa.gov.au
Monday to Friday Ph – 8226 5518
www.sa.gov.au/otrwww.sa.gov.au/otrwww.sa.gov.au/otrwww.sa.gov.au/otr
- Download past issues of Reg Roundup
- Download shock/incident report forms
- Download Test and Verification sheets
- Online ECC registration