2014 reliability plan - hydro ottawa · system reliability targets are set to flag where gaps exist...

28
2014 Reliability Plan Annual Planning Report

Upload: others

Post on 23-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

2014 Reliability Plan Annual Planning Report

Page 2: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

2014 Reliability Plan

2

Page 3: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

3

2014 Reliability Plan Annual Planning Report

Executive Summary Hydro Ottawa’s reliability performance in 2013 did not meet our expected targets. Interruption categories

such as defective equipment and adverse weather, or storm related have been progressively trending worse

and have exceeded the previous 3-year averages. Improvement will be needed in asset management

processes in order to prioritize end of life asset replacements. Maintenance, inspection and testing of

existing assets will continue to be essential to ensure equipment operates as expected and identify failures

before they occur. Consideration of new ways of operating to reduce system susceptibility to storm damage

and foreign interference is vital. In addition, investing in grid technologies will benefit reliability by reducing

restoration times and aid with predicting system faults.

Overall, since 2009 system

SAIFI has been steadily

increasing, due to the increase

of storms with severe wind

and rain as well as an increase

in equipment failures. Moving

forward, it is critical that

investment levels for

equipment replacement

increase in order to storm

harden the system and to get

ahead of the curve of aging

equipment.

Fundamental in Hydro

Ottawa’s approach to system

reliability is the

implementation of grid technologies. Ongoing targeted installation of automated devices is planned for the

foreseeable future to improve system reliability and operation. Currently, targeted programs are the East

44kV automation, which will deploy automatic restoration to this sub-transmission loop that supplies 3% of

Hydro Ottawa’s customers. In addition, automation plans are being deployed in the quickly growing South

Nepean/Barrhaven area, as well as targeted annual installation to address the Worst Performing Feeders.

Continued investment in the communication infrastructure will be essential to support current automation

plans while maintaining the flexibility to integrate the technologies of tomorrow.

FIGURE 0.1 - HISTORIC COMPARISON - SAIFI & SAIDI

0.41 0.53 0.44

0.41

0.68

0.17

0.31

0.30

0.42

0.28

0.30

0.50

3 Yr Avg

('09-'11)

2012 2013

SAIFI

0.41 0.54 0.45

0.310.33

0.04

0.440.35

0.54

0.66 0.420.65

3 Yr Avg

('09-'11)

2012 2013

SAIDI

Storm Related Defective Equipment Loss of Supply Other

Page 4: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

4

Contents Executive Summary .................................................................................................................................. 3

Contents .................................................................................................................................................. 4

1 Background ...................................................................................................................................... 5

1.1 Definitions ............................................................................................................................................ 6

2 Performance ..................................................................................................................................... 7

2.1 Key Measures ....................................................................................................................................... 7

2.2 System Targets ..................................................................................................................................... 8

2.2.1 SAIDI & SAIFI .................................................................................................................................... 8

2.2.2 FEMI10 ............................................................................................................................................... 8

2.3 System Reliability Performance & Analysis .......................................................................................... 9

2.3.1 Historical System Reliability Performance Measures ...................................................................... 9

2.4 Power Quality, Voltage and Waveform Performance Measures ....................................................... 11

3 Reliability Analysis .......................................................................................................................... 12

3.1 System Reliability Analysis ................................................................................................................. 12

3.1.1 Loss of Supply ................................................................................................................................. 14

3.1.2 Defective Equipment...................................................................................................................... 15

3.1.3 Adverse Weather ........................................................................................................................... 17

3.2 Major Event Days ............................................................................................................................... 18

3.3 2013 Worst Feeder Analysis ............................................................................................................... 19

3.4 Reliability Improvement Initiatives .................................................................................................... 21

4 System Automation ........................................................................................................................ 23

4.1 SCADA & Communications ................................................................................................................. 23

4.1.1 SCADA ............................................................................................................................................ 23

4.1.2 Communication Infrastructure ...................................................................................................... 23

4.2 Distribution Automation .................................................................................................................... 25

4.3 Automation Plans ............................................................................................................................... 25

4.3.1 South Nepean Automation Plan .................................................................................................... 25

4.3.2 East 28kV system ........................................................................................................................... 26

4.3.3 West 28kV system .......................................................................................................................... 26

4.3.4 44kV Sub- transmission Automation.............................................................................................. 26

4.3.5 Other Automation Plans ................................................................................................................ 26

4.4 Substation Automation ...................................................................................................................... 27

Page 5: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

5

1 Background

Hydro Ottawa continuously assesses the distribution systems service reliability. Where gaps are found, the

appropriate actions are identified to address these issues. Service reliability is integral to all work undertaken

as part of system planning and asset management. The Reliability Plan does not supersede the importance of

good Asset Management and System Capacity planning in the management of system reliability. Rather, it

provides a platform for thorough review of system reliability and identifies planned works which are designed

to directly impact system reliability.

Reliability driven projects are those which are designed to reduce outage frequency or duration regardless of

the cause. Such initiatives are almost exclusively automation projects, in general work considered as part of

the system reliability plan are:

� Deployment of remote sensors

� Deployment of remotely operable and autonomous devices

� Deployment of field devices to provide fault indications locally

� Supporting technologies to automation (i.e. communication & SCADA)

� Modifications to existing standards (i.e. animal guards)

System planning, asset management, and equipment maintenance also have direct impact on system

reliability – asset replacement prior to failure will prevent customer interruption and system planning can

reduce interruption duration through increased operability. While projects in these domains are primarily

discussed in the Asset Management, Maintenance, and System Capacity plans, their reliability impacts

discussed herein are one of the inputs to those planning processes.

Page 6: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

6

1.1 Definitions Interruption

Is a sustained loss of voltage/electrical supply on all phases to the customer’s supply point. Notwithstanding,

if the customer’s system is not able to accept electricity from Hydro Ottawa’s system, this is not considered

an outage. This does not include Partial Power (loss on some of the phases supplying a customer), or

sags/deformations, these are power quality events.

Loss of Supply

Is a primary cause classification which is utilized in the outage reporting and coding. This term indicates a

situation in which the system was ready to accept energy from the bulk system, and the providers are not

supplying. The term “Loss of Supply” therefore indicates a situation where Hydro Ottawa’s system is without

power for a reason that is beyond the control of Hydro Ottawa.

System Average Interruption Frequency Index (SAIFI)

This index is designed to give information about the average frequency of sustained interruptions per

customer over a predefined area. In words, the definition is:

This index is reported both including and excluding Loss of Supply (LoS). SAIFI including LoS provides

information as to the total interruptions which are seen by the ‘average’ customer. SAIFI excluding LoS

indicates the ‘average’ customer interruptions which are the result of causes under the direct control of

Hydro Ottawa.

System Average Interruption Duration Index (SAIDI)

Designed to provide information about the average time the customers are interrupted. In words, the

definition is:

This index is reported both including and excluding Loss of Supply (LoS). As with SAIFI, the SAIDI including LoS

provides information as to the total duration of interruptions which are seen by the ‘average’ customer

whereas SAIDI excluding LoS provides an indication as to the duration which the ‘average’ customer is

interrupted as the result of causes under the control of Hydro Ottawa.

Customer Average Interruption Duration Index (CAIDI)

CAIDI represents the average time required to restore power to the average customer per sustained outage.

In words, the definition is:

Feeders Experiencing Multiple Sustained Interruptions (FEMIn)

This index represents the number of feeders experiencing outages greater than or equal to value n, current

reporting is done for n=10. It is a customer centric measure as it provides an indication as to regions which

have seen high localized issues. FEMI10 is reported excluding Scheduled Outages as well as Loss of Supply, to

more accurately track regions seeing issues, as opposed to including regions seeing multiple outages due to

maintenance, repair and upgrade activities.

Page 7: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

7

2 Performance

2.1 Key Measures System reliability in 2013 continues to see

degrading performance. Loss of Supply,

Defective Equipment, and Adverse Weather

were the main contributors to the performance

of 2013.

Improvement will be needed in asset

management processes in order to prioritize

end of life asset replacements. Maintenance,

inspection and testing of existing assets will

continue to be essential to ensure equipment

operates as expected and identify failures

before they occur.

In addition, consideration of new

ways of operating to reduce

system susceptibility to storm

damage and foreign interference is

vital. Some of the initiatives

undertaken are a review of Hydro

Ottawa’s tree trimming program,

the use of animal guards, and

review of existing maintenance

programs.

Customer Interruption

due to Storms

150% above 3-year average

Customer

Interruption due to

Defective

Equipment

130%

above average

TABLE 2.1 - SYSTEM RELIABILITY METRICS

Metric ERM

Target

2011 2012 2013

Annual SAIFI < 1.5 1.68 1.81 1.53

3-Yr Average SAIFI < 1.0 1.41 1.63 1.67

Annual SAIDI < 1.5 2.60 1.64 1.68

3-Yr Average SAIDI < 1.5 1. 8 1.86 1.96

FEMI10 ≤ 12 12 13 13

FIGURE 1.1 - HISTORICAL SAIDI & SAIFI

1.05

1.05

2.43

1.31

1.64

0.45

0.31

0.16

0.33

0.04

0.82

0.77

1.40

1.13

1.36

0.33

0.63

0.28

0.68

0.17

09

10

11

12

13

Yearly SAIDI excl LOS Yearly SAIDI due to LOS

Yearly SAIFI excl LOS Yearly SAIFI due to LOS

SAIFI SAIDI

Page 8: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

8

2.2 System Targets 2.2.1 SAIDI & SAIFI

System reliability targets are set to flag where gaps exist and attention is required. Through review of

historical performance targets shown in Table 2.2 have been approved by Hydro Ottawa’s Board of Directors.

Asset management activities will continue to strive to maximize system availability and produce best in-class

system performance.

2.2.2 FEMI10 The goal of this metric is to identify those portions of the system which are experiencing high frequency of

interruption and highlight groups of customers which may in-turn be experiencing sub-par service reliability.

FEMI is a 12 month rolling window value and can be sampled at any month to view the past 12 month’s

performance. The performance target has been set based on historical performance, and can be seen in

Table 2.2.

TABLE 2.2 - 2013 SAIDI, SAIFI & FEMI10 TARGETS

Metric / Indicator ERM Targets

Quarterly YTD

Duration of planned and unplanned interruptions

(SAIDI)

< 1.0 < 1.5

Frequency of planned and unplanned interruptions

(SAIFI)

< 1.0 < 1.5

SAIDI – 3 year moving average < 1.5 < 1.5

SAIFI – 3 year moving average < 1.0 < 1.0

FEMI10 ≤ 12 ≤ 12

Page 9: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

9

2.3 System Reliability Performance & Analysis 2.3.1 Historical System Reliability Performance Measures

Since 2009 the frequency of outages has been steadily increasing, peaking in 2012. Despite year to year

variations, the frequency increases are associated primarily with a rise in Weather related outages, Defective

Equipment, and Foreign Interference. In 2013, the largest contributor to the frequency of interruptions was

due to Defective Equipment.

In 2013, the duration of outages slightly increased in comparison to 2012 but it was still lower than 2011

which was impacted heavily by three storms resulting in widespread outages. In 2013, the largest contributor

to the duration of interruptions was Defective Equipment, followed by Adverse Weather.

TABLE 2.3 - SYSTEM RELIABILITY PERFORMANCE

ERM

Target

2009 2010 2011 2012 2013

3 Yr Avg. SAIFI including LoS < 1 1.13 1.19 1.41 1.63 1.67

3 Yr Avg. SAIFI excluding LoS N/A 0.72 0.78 1 1.10 1.30

3 Yr Avg. SAIDI including LoS < 1.5 1.29 1.28 1.82 1.86 1.96

3 Yr Avg. SAIDI excluding LoS N/A 0.98 1.01 1.52 1.60 1.79

3 Yr Avg. CAIDI < 1.5 1.15 1.08 1.29 1.14 1.17

FEMI10 excluding LoS &

Unplanned Outages

≤ 12 9 7 12 13 13

FIGURE 2.2 - HISTORIC SYSTEM SAIFI & SAIDI

0.00

0.50

1.00

1.50

2.00

2.50

3.00

20

09

20

10

20

11

20

12

20

13

SA

IFI

0.00

0.50

1.00

1.50

2.00

2.50

3.00

20

09

20

10

20

11

20

12

20

13

SA

IDI

Yearly SAIDI or SAIFI due to LoS Yearly SAIDI or SAIFI excl LoS

3-Year Average SAIDI or SAIFI excl LoS 3-year SAIDI Average incl LOS

Page 10: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

10

The 2013 ERM targets were not met in 2013 for Annual SAIDI, 3 Year Average SAIDI and SAIFI as well as FEMI.

The contribution to the reliability performance in 2013 is discussed throughout this document, and the

missed targets cannot be attributed to one cause.

Feeders experiencing multiple interruptions were more widespread in 2013 with 13 feeders experiencing 10

or more interruptions. The primary contributors to the interruptions on these feeders are shown in Figure

2.4 and are: Defective Equipment, Foreign Interference and Adverse Weather. Six of the FEMI feeders align

with the Ten Worst Feeders (see section 3.3) and are thoroughly reviewed as part of that process for

potential improvement projects. The remaining 7 circuits will be investigated separately and any potential

improvements to reduce interruption impact identified.

FIGURE 2.3 – HISTORICAL SYSTEM FEMI10

FIGURE 2.4 - 2013 FEMI CIRCUITS SAIFI & SAIDI BY PRIMARY CAUSE

190F5249F1249F1

249F1249F2 249F2

249F2249F2

249F2

49F6

624F6

624F6

624F6

624F6

77M1

77M2

77M6

77M6

77M6

77M67F4

7F4

7F4

7F4

7F48F1

8F1

8F18F1

ALXF3BECKF2

BECKF2

BECKF2MWDF2MWDF3TB06

TB06

TB06TB15

TD01

TD01 TD01TD01TD05

TD06

TD12

TD14

TD14

TH11

TR09

TW22

TW22

TW22

TW22

0

2

4

6

8

10

12

14

2009 2010 2011 2012 2013

Nu

mb

er

of

Cir

cuit

s E

xp

eri

en

cin

g 1

0 o

r

Mo

re I

nte

rru

pti

on

s

2%

13%

34%

21%

2%

6%

2%

2%

8%10%

SAIFI

1%

26%

27%11%

0%

2%

5%

5%

21%

2%

SAIDI

Adverse Environment Adverse Weather Defective EquipmentForeign Interference Human Element LightningLoss of Supply Scheduled Outage Tree Contacts

Page 11: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

11

FIGURE 2.5 - 2013 POWER QUALITY EVENTS ITIC CURVE

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

1.8

2.0

0.001 0.01 0.1 1 10 100

RM

S V

olt

ag

e M

ag

nit

ud

e

(PU

)

Time (seconds)

2.4 Power Quality, Voltage and Waveform Performance Measures

Hydro Ottawa endeavours to operate the

voltage in the distribution system in

accordance to CSA CAN3-C235-83 in

steady state. By maintaining the voltage to

these standards, customers can expect all

of their devices, equipment and appliances

to operate as intended and expected

without damage or noticeable irritations

such as dimming or flickering lights.

Customers may however, on occasion,

experience voltage variations outside

these limits which Hydro Ottawa strives to

keep at a minimum.

Poor voltage regulation, outside ±6%, is

usually indicated by low voltage

complaints from customers. The target is to put corrective measures in place as soon as possible. The

increasing use of electronic devices is resulting in a progressive deterioration of waveform quality and it is

likely that further measures will need to be introduced and enforced in this area over the next decade.

The System Average RMS Variation Frequency Index (SARFI) is a measure of the average number of voltage

sags on the system. The ITIC curve, Figure 2.5, represents the 2013 RMS voltage variation events plotted

against the variation envelope which single phase modern devices can tolerate. Of the 2820 events recorded

in 2013, 16 fell within the prohibited region and are described in Table 2.4.

TABLE 2.4 - 2013 PROHIBITED REGION EVENTS

Date Site Cause RMS Voltage (PU) Duration (s)

16/03/2013 Casselman Loebs Unknown 1.104 1.642

12/04/2013 King Edward T1-Q Hydro One switching 1.117 0.867

King Edward T2-Z Hydro One switching 1.117 0.575

21/05/2013 Hawthorne 48M4 Unknown cause – Hydro One 1.120 97.000

Hawthorne 48M3 Unknown cause – Hydro One 1.120 97.000

18/07/2013 Albion T2-Y Hydro One Switching 1.110 24.380

20/09/2013 Marchwood T1 Unknown cause 1.101 2.833

16/10/2013 Lisgar T1-J Feeder fault 1.223 0.017

Lisgar T2-Y Feeder fault 1.224 0.017

15/11/2013 Slater T2-J2 Hydro One switching 1.120 9.575

05/12/2013 South March A9M4 Unknown cause – Hydro One 1.105 0.675

11/12/2013 Casselman Loebs Unknown 1.120 1.783

11/12/2013 Hawthorne 48M5 Unknown cause – Hydro One 1.108 90.390

18/12/2013 Hawthorne 48M3 Hydro One switching 1.114 1.350

Hawthorne 48M4 Hydro One switching 1.114 1.125

Hawthorne 48M5 Hydro One switching 1.113 0.900

No Damage Region

Prohibited Region

No Interruption

Region

Page 12: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

12

Cause of Interruption*

Unknown/Other Customer interruptions

with no apparent cause that contributed to

the outage

Scheduled Outage Customer interruptions

due to the disconnection at a selected time

for the purpose of construction or

preventive maintenance

Loss of Supply Customer interruptions due

to problems associated with assets owned

and/or operated by another party, and/or

in the bulk electricity supply system, based

upon ownership demarcation

Tree Contacts Customer interruptions

caused by faults resulting from tree contact

with energized circuits

Lightning Customer interruptions due to

lightning striking the distribution system,

resulting in an insulation breakdown

and/or flash-overs

Defective Equipment Customer

interruptions resulting from distributor

equipment failures due to deterioration

from age, incorrect maintenance, or

imminent failures detected by

maintenance

Adverse Weather Customer interruptions

resulting from rain, ice storms, snow,

winds, extreme temperatures, freezing

rain, frost, or other extreme weather

conditions (exclusive of Code 3 and Code 4

events)

Adverse Environment Customer

interruptions due to distributor equipment

being subject to abnormal environments,

such as salt spray, industrial

contamination, humidity, corrosion,

vibration, fire, or flooding

Human Element Customer interruptions

due to the interface of distributor staff

with the system

Foreign Interference Customer

interruptions beyond the control of the

distributor, such as animals, vehicles, dig-

ins, vandalism, sabotage, and foreign

objects

*Definitions from OEB’s Electricity

Reporting & Record Keeping Requirements,

March 7, 2014

Unknown/Other Scheduled Outage

Loss of Supply Tree Contacts

Lightning Defective Equipment

Adverse Weather Adverse Environment

Human Element Foreign Interference

3 Reliability Analysis

3.1 System Reliability Analysis System reliability has two primary components; frequency and

duration. Frequency relates most directly to the causal aspect of

system interruption whereas duration relates most directly to

operation of the system. System Average Interruption Frequency

Index (SAIFI) can be regarded as the “cause” and System Average

Interruption Duration Index (SAIDI) regarded as the “effect”.

Additional correlation on system interruptions based on the 10

Primary Causes outlined in the Electricity Reporting and Record

Keeping Requirements provide further statistical data that can be

used as indicators of system issues where remediation should be

undertaken to improve performance. Reliability scores are

evaluated for trending and patterns as seasonal and annual

variations are not always indicative of system deficiencies.

FIGURE 3.1 - SAIFI BY PRIMARY CAUSE

FIGURE 3.2 - SAIDI BY PRIMARY CAUSE

7%

6%

11%

8%

17%27%

8%

0%6%

10%

3%

14% 2%

9%

11%

32%

19%

1% 2%

7%

Page 13: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

13

System average interruption frequency and duration indexes have been broken out by primary cause shown

in the figures below. These indicate that the leading causes for outage frequency and duration are Defective

Equipment and weather related outages which include Lighting, Tree Contacts and Adverse Weather. Foreign

Interference is on an increasing trend and also had a notable impact to both SAIFI and SAIDI in 2013.

Collectively, Defective Equipment and weather related outages account for 60% of the 2013 SAIFI score and

71% of the SAIDI score.

FIGURE 3.3 – 2013 SAIFI BY PRIMARY CAUSE COMPARED TO ’10 -‘12 AVERAGE

FIGURE 3.4 - 2013 SAIDI BY PRIMARY CAUSE COMPARED TO ’10-‘12 AVERAGE

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

1.80

2.00

2009 2010 2011 2012 2013 3 Yr Avg

('10-'12)

SA

IFI

Unknown /Other (44%)

Loss of Supply (103%)

Adverse Weather (55%)

Adverse Environment (129%)

Scheduled Outage (27%)

Tree Contacts (55%)

Lightning (131%)

Defective Equipment(26%)

Human Element (54%)

Foreign Interference (15%)

0.00

0.50

1.00

1.50

2.00

2.50

3.00

2009 2010 2011 2012 2013 3 Yr Avg

('10-'12)

SA

IDI

Unknown/Other (55%)

Loss of Supply (152%)

Tree Contacts (9%)

Adverse Weather (41%)

Adverse Environment (148%)

Foreign Interference (9%)

Schedule Outage (29%)

Lightning (112%)

Defective Equipment (25%)

Human Element (66%)

Unknown/Other Scheduled Outage Loss of Supply Tree Contacts

Lightning Defective Equipment Adverse Weather Adverse Environment

Human Element Foreign Interference

Page 14: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

14

3.1.1 Loss of Supply In 2013, Loss of Supply was the third largest contributor to frequency of interruptions; however, it was a

small contributor to the duration of interruptions. There were 18 individual interruptions recorded due to the

loss of one of nine Hydro One components. The loss of the 27 kV circuit, BECKF2, contributed to 57% of the

Loss of Supply SAIDI but only affected 2% of SAIFI score. The loss of the 115 kV circuit, C7BM, contributed to

31% of the Loss of Supply SAIDI and 80 % of the SAIFI score, as can be seen in the figures below. The C7BM

has a large contribution to the reliability indices since it is a supply to many substations in the south.

FIGURE 3.5 - CONTRIBUTION TO LOSS OF SUPPLY SAIDI BY CIRCUIT

The majority of the Loss of Supply interruptions were caused by Adverse Weather conditions in the area;

however, the interruptions due to Defective Equipment had the largest impact to the Loss of Supply SAIDI as

shown in the following figure.

FIGURE 3.6 - CONTRIBUTION TO LOSS OF SUPPLY SAIFI & SAIDI BY SECONDARY CAUSE

2%0%

14%

80%

0%

3% 1% SAIFI

57%

1%

8%

31%

0%2% 1%

SAIDI

Beckwith BECKF2 (27.6kV) Carp CARPF3 (8kV)

A9M3 (44kV) C7BM (115kV)

Greenland GNLF2 (8kV) 62M2 (44kV)

72A3RM (115kV)

14%2%

53%

31%

SAIFI

9%

57%

29%

5%SAIDI

Adverse Weather Defective Equipment Unknown / Other Lightning

Page 15: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

15

Civil Structures Customer-Owned Fusing

O/H Conductor O/H Switchgear O/H XFRM

Pole Pole Attachment Secondary/Service

Station Equipment U/G Cable U/G Cable Attachement

U/G Switchgear U/G XFRM Unknown/Other

Vault Equipment

3.1.2 Defective Equipment The largest contributor to the duration and the frequency of customer interruptions in 2013 was Defective

Equipment. The customer impact of Defective Equipment outages has exhibited an increasing trend from

2009 to 2013. The top three contributors to Defective Equipment SAIFI in 2013 were: O/H Switchgear, U/G

Cable and Station Equipment. The top three contributors to Defective Equipment SAIDI is 2013 were: Station

Equipment, U/G Cable, and U/G Cable attachment. Collectively these four equipment classes account for

more than 60% of the Defective Equipment SAIFI and SAIDI in 2013. When compared to the trend of the last

few years there was a notable increase in the impact due to Station Equipment and O/H switchgear and a

notable decrease in the impact of UG/ Cable and Pole Attachment related interruptions.

FIGURE 3.7 - DEFECTIVE EQUIPMENT SAIFI & SAIDI BY ASSET

FIGURE 3.8 – 2013 DEFECTIVE EQUIPMENT SAIFI & SAIDI BY ASSET

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

0.45

2009 2010 2011 2012 2013

SA

IFI

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

2009 2010 2011 2012 2013

SA

IDI

0%

0%

0%2%

16% 4%

9%

6%

0%

14%16%

12%

0%7%

12%

0%

SAIFI

0%

2%0%

4%

12%1%

6%

4%

0%30%

17%

14%

1% 4%

7%

0%SAIDI

Page 16: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

16

O/H Switchgear – In 2013, there were 74 interruptions caused by the failure of overhead switchgear. This

includes failures to single and three-phase reclosers, fused cutouts, inline switches and solid blade switches.

Of the 74 interruptions, 4 failures to inline switches, 1 failure to a simple solid switch, 1 failure to a Vega

switch and 1 failure to a load break switch had the largest impact to both the Defective Equipment SAIDI and

SAIFI. There were no obvious trends in the causes for the failures found.

U/G Cable – Cable continues to appreciably contribute to annual customer interruptions. In 2013, there were

55 outages attributed to the failure of U/G cable. Of the 55 interruptions, 10 U/G cable failures had over 60%

impact to the U/G cable SAIFI and SAIDI. The main contributors to this category where single faults on trunk

lines affecting a large number of customers.

Station Equipment – In 2013, there were 21 Station Equipment related interruptions. The increase in the

contribution of station equipment failures is due primarily to the TO49 breaker failure at the indoor

Overbrook Station (See Figure 3.9). This breaker failure caused an outage to two buses at the Overbrook

Station (approximately half the 13kV station) and the 4kV Dagmar Station.

U/G Cable Attachment – In 2013, there were 21 interruptions attributed to the failure of U/G cable

attachments. The increase in contribution due to cable attachments is due primarily to two events: a

termination failure on the ALEXF3 feeder and a blown pothead on the TO3UT feeder which was partially

carrying TO2UT at the time of failure. These outages contributed to 40% of the U/G cable attachment SAIFI

and 71% of the U/G cable attachment SAIDI.

FIGURE 3.9 - TO49 BREAKER FAILURE

Page 17: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

17

3.1.3 Adverse Weather In 2013, Adverse Weather did not have a large contribution to the duration of interruptions and the

frequency of customer interruptions as it has been observed in previous years. However, when outages due

to Tree Contacts, Lightning and Adverse Weather are combined as “Storm Related Outages” they jointly have

the second largest contribution to the duration, and the largest contributor to frequency of customer

interruptions in 2013. The frequency of outages caused by storms increased significantly in 2013 when

compared to 2012, but the duration of these outages only had slight increased. In 2013, there were two

Major Event Days, one of them was caused by a storm involving lightning and high winds on July 19th

. Hydro

Ottawa continually tries to mitigate storm damage by including provisions in system design and identifying

assets for replacement that have degraded below the required design strength.

FIGURE 3.10 - STORM RELATED OUTAGES CONTRIBUTION TO SAIFI & SAIDI

FIGURE 3.11 – 2013 STORM RELATED OUTAGES CONTRIBUTION TO SAIFI & SAIDI

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

2009 2010 2011 2012 2013

SA

IFI

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

2009 2010 2011 2012 2013

SA

IDI

23%

53%

24%

SAIFI

60%

36%

4%SAIDI

Tree Contacts Lightning Adverse Weather

Page 18: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

18

3.2 Major Event Days Hydro Ottawa follows the “Beta Method” outlined in section 4.5 of IEEE Standard 1366-2003 “IEEE Guide for

Electric Power Distribution Reliability Indices” to determine Major Event Days.

TABLE 3.1 - MAJOR EVENT DAYS

Year Number Date Primary Cause

2011 4 April 24th

June 8th

July 17th

July 18th

Adverse Weather

Adverse Weather

Adverse Weather

2012 2 May 4th

July 23rd

Loss of Supply – Defective Equipment

Adverse Weather & Loss of Supply

2013 2 July 19th

Aug 22nd

Adverse Weather

Defective Equipment-

Dagmar/Overbrook

The daily system SAIDI threshold is calculated based on the

historical daily SAIDI values from the previous five years; this means

that the 2013 TMED was calculated based on the performance of

2008 through 2012. The 2013 TMED, calculated as per IEEE 1366-

2003 came to a daily SAIDI threshold of 0.114.

The following chart shows the daily system SAIDI graphically with

the calculated threshold value, TMED. It can clearly be seen that only

2 days in 2013 exceeded the threshold: July 19th

and August 22nd

.

On July 19th

, the Ottawa area experienced a lightning storm with

high winds which caused a number of interruptions. On August 22nd

,

the TO3UT breaker at the Overbrook Station failed causing an

outage on two busses of 13kV station and at the 4kV Dagmar

station.

FIGURE 3.12 - 2013 DAILY SYSTEM SAIDI

0

0.05

0.1

0.15

0.2

0.25

SAIDI tMed

Standard 1366-2003 defines a

Major Event Day as:

A day in which the daily system

SAIDI exceeds a threshold value,

TMED. For the purposes of

calculating daily system SAIDI,

any interruption that spans

multiple calendar days is

accrued to the day on which the

interruption began. Statistically,

days having a daily system SAIDI

greater than TMED are days on

which the energy delivery

system experienced stresses

beyond that normally expected

(such as severe weather).

Activities that occur on major

event days should be separately

analyzed and reported.

August 22nd

July 19th

Page 19: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

19

3.3 2013 Worst Feeder Analysis In 2011, a standard method to determine the “Worst Feeders” was defined. This method takes into

consideration the duration, frequency and number of sustained outages as well as the number of momentary

(duration < 1min) interruptions a feeder experiences.

Based on the Worst Feeder Methodology the 10 worst feeders were evaluated and potential improvements

to the feeders were proposed. The table below summarizes the findings from the detailed study completed

for each of the 10 feeders.

TABLE 3.2 - 2013 WORST FEEDER IMPROVEMENT PROPOSALS

Rank Feeder Issue 2013 Proposal

1 249F1 • Feeder Exposure

• Susceptible to animal and

tree contacts

• An additional feeder, 249F4, is being brought

out of the station to split the load on the

249F1. In particular, Findlay Creek will be

supplied from the new feeder limiting the

exposure from the existing circuitry north of

the neighbourhood.

• Spot trimming above and beyond the normal

vegetation management three year cycle was

performed late 2013 to reduce the probability

of tree contacts.

• Animal guards were installed on portions of the

circuit in 2013 to reduce the possibility of

animal contacts.

• A second station transformer is planned for

Leitrim in 2017, to provide redundancy, allow

for maintenance and additional capacity.

2 77M6 • Underground cable faults • More cable testing in this area to identify

potential for replacement or injection

• A new feeder purchased from Hydro One’s

Orleans TS will become available to support

the area in 2015.

3 7F4 • Feeder Exposure

• Susceptible to animal and

tree contacts

• A new station transformer is being energized at

Limebank in 2015.

• The 7F4 circuit will be split by the new 7F5 in

2015.

4 A9M3 • Radial line

• Feeder exposure

• Relocation of backyard O/H line in Stittsville.

Construction to start in 2014.

• In 2013, poles and insulators in critical

condition were replaced.

• Automation of two VBM switches at the

intersection of Fallowfield and Shea in 2013.

• Construction of a 44kV line to tie A9M3 with

22M25 will commence in 2015 and conclude in

2017. A fully automated VBM will allow for

quick supply transfer.

• New 44kV tie a VBM will be installed on

Johnwoods & Hazeldean for further

Page 20: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

20

Rank Feeder Issue 2013 Proposal

sectionalizing under contingency.

5 TB06 • Overhead switch failures • Failed switches have been replaced, continue

to monitor.

6 624F6 • Feeder exposure

• Susceptible to animal and

tree contact caused

interruptions

• Crews are encouraged to install animal guards

when completing construction on this circuit.

• The tree trimming crew worked in this area in

late 2013 as part of 3 year program.

7 249F2 • Feeder exposure

• Susceptible to animal and

tree contacts

• A second station transformer is planned for

Leitrim in 2017, to provide redundancy, allow

for maintenance and additional capacity.

• An additional feeder, 249F3, will egress once

the transformer is in place. This will allow the

load on 29F2 to be split.

8 77M2 • Largest interruption due

to pole insulator failure

• Porcelain insulators are being replaced

• A new feeder purchased from Hydro One’s

Orleans TS will become available to support

the area in 2015.

9 MWDF2 • • New second supply to the Marchwood DS

station will allow for load transfer at the

station without an interruption.

10 7F1 • Feeder exposure

• Susceptible to animal and

tree contacts

• A new station transformer is being energized in

2015 to allow for better load distribution and

less feeder exposure.

The Worst Feeder Methodology recommends tracking the worst feeders over a three year period to allow

time for the improvements to be seen. The following figure outlines the 10 worst feeders for 2013 and where

they sit in regards to Score versus Trend. Note that feeders that have a trend below 0.5 are seeing an

improvement in reliability (1 feeder in 2013 – 249F2). Moving forward, the feeders will need to be continually

tracked to determine whether the improvements made in the distribution have had an impact on improving

the feeder’s reliability, it is believed that there will be at least a three year lag in seeing the improvements on

the feeder – 1 year for the improvement to be implemented and the two following years to develop a new

trend.

FIGURE 3.13 - 2013 TOP 10 WORST FEEDERS SCORE VS. 3-YEAR TREND

0

0.5

1

0 0.5 1 1.5 2 2.5 3

Tre

nd

Score

249F1

77M6

7F4

A9M3

TB06

624F6

249F2

77M2

Imp

rov

ing

Re

lia

bil

ity

De

teri

ora

tin

g

Re

lia

bil

ity

Page 21: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

21

3.4 Reliability Improvement Initiatives In support of the HOL Customer Value and improving customer experience, Hydro Ottawa continually

implements projects to improve reliability in areas with known problems. The following works have been or

are planned to address the identified reliability issues.

Loss of Supply

The reliability and redundancy of system supply is continuously evaluated as part of the Capacity Planning

exercise. Where feasible, contingency plans are developed to expedite restoration and reduce the impact of

the loss of any one supply. As well, the installation of remotely operable devices are considered when

evaluating restoration and isolation scenarios to reduce the number of customers affected by a loss of supply

and to quickly be able to resupply the affected region.

Defective Equipment

U/G Cable – Replacement of end-of-life underground cable is an on-going program, which requires significant

investment. New cable condition information available from the U/G cable testing program started in late

2010, is being used to help identify end-of-life cable and prioritize these replacements to have maximum

impact. Also, the use of cable injection is being trialed to prolong the life of ageing cable, this technology may

allow areas of concern to be addressed more rapidly than traditional replacement.

U/G Switchgear – Replacement of end-of-life underground switchgear is an on-going program. In 2013, 5

switchgear were replaced. Switchgear are prioritized for replacement by condition and their criticality to

system operation. It is anticipated that by 2014 all 6-way gear that have become a non-stock item and are all

at end-of-life will be replaced.

O/H Switchgear – Overhead Switchgear are inspected as part of the Critical Switch program with the purpose

of maintain and inspecting switches that are deemed a higher priority. These switches are selected based on

the requirements to interrupt higher loads, supply many customers, or supply critical customers. The cyclic

three-year inspection program will ensure all areas (urban, rural and difficult access) will be visited, and aid in

detecting problems before they fail.

U/G Transformers – Currently, our underground transformer replacement program has been targeting the

removal of PCB containing units. Once all of the PCB transformers have been replaced a proactive

underground transformer replacement program will be evaluated to start targeting end-of-life units.

Station Equipment – Station transformers and switchgear/reclosers are being continually replaced based on

age and condition, as well monthly station maintenance and inspections take place to track and identify

potential issues with equipment and connections. The type and mechanism of station equipment failures will

continue to be monitored to identify any trends and possible solutions that could be implemented system

wide.

Adverse Weather

Continued enhancements are being made to the system to improve the withstand capabilities during storms

and to reduce the impact of individual outages. There are three initiatives/programs which address this need:

Pole Replacement – The condition of poles is evaluated on an ongoing basis. From the condition assessment a

review is conducted to determine the areas which are in the poorest condition so they can be targeted for

Page 22: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

22

planned replacement. By eliminating poles in poor condition and upgrading the attached hardware, the

ability of the system to operate through adverse weather without interruption is improved.

Vegetation Management – Updates to the vegetation management program currently underway are

anticipated to reduce tree contacts during wind storms. Changes to the program which are being

implemented include targeted tree trimming cycle and clearance distance from lines based on tree species

and their rate of growth. In addition ‘smart’ tree removals are being considered. ‘Smart’ removals would

target trees near overhead lines that either are near end of life and at risk of falling into the line or would

require excess trimming (i.e. trimming would be required too frequently or would negatively impact the

health of the tree) to maintain an appropriate clearance.

System Protection – Where appropriate, distribution reclosers are installed on the system. While these

reclosers will not completely eliminate outages, they do sectionalize the distribution circuit, minimizing the

number of customer interruptions for a given fault.

Worst Feeders

The worst feeder program is designed to address short term reliability issues in an immediate time-frame. All

work identified in the 2013 review will be carried out in the 2014 budget year, with targeted completion

before the beginning of storm season. In the Fall of 2014, identification and assessment of the worst feeders

will again be carried out and appropriate actions will be undertaken to improve performance of the identified

circuits.

System Activity Investigation Reporting Criteria

The Asset Planning Group has been engaged in producing System Activity Investigation Reports with the goal

of providing clarity into issues with the configuration and operation of the distribution system. System

activity investigation reports provide insight into the root cause of an event, identify issues with standard

process and procedures, and provide recommendations to mitigate re-occurring events. The Asset Planning

Group has developed a set of criteria to initiate system activity reports. These criteria will attempt to capture

events that can lead to corrective actions to further better the system and operating procedures.

Any of the following criteria can initiate a System Activity Investigation Report:

1- ≥ 1000 Customers and ≥ 1 Minute (Unplanned)

2- ≥ 8 Hours and ≥ 1 Customer (Unplanned)

3- Equipment/Protection mis-operation (HOL, HONI, or other).

4- Incidents where equipment failure, protection mis-operation, or system operation (i.e. switching)

have or are suspected to have caused or contributed to Health & Safety incidents (Public or

Employee) or property damage (i.e. catastrophic vault equipment failure).

5- Re-occurring incidents of supply quality falling outside tolerances for voltage, current, frequency and

harmonic distortion as specified in ECG0008, that are suspected to have originated from the

distribution system.

6- As circumstances require.

Page 23: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

23

4 System Automation Automation projects targeted to improve reliability performance cannot function without a strong

communication infrastructure. Ongoing investment over the next 20 years will be required to create a

communication network which is strong enough to support system automation plans, yet flexible enough to

integrate the quickly evolving technologies involved.

4.1 SCADA & Communications 4.1.1 SCADA

The automation class of assets is usually designated as

the SCADA (Supervisory Control and Data Acquisition)

system in substations and in distribution. Hydro

Ottawa Limited’s SCADA asset class system is used to

monitor and control station and distribution system

equipment.

SCADA supports system reliability by providing system

operators with real-time access to system status and

control, reducing time required to identify service disruptions, locate system faults, and operate the system

to restore customers. As more and more distribution assets are connected to the SCADA system, the

Operator’s situational awareness improves, resulting in a more focused and effective restoration effort.

The HOL SCADA system was installed in 2006 and has not received any significant updates since that time.

While the system has been maintained with vendor support, it is coming to the end of its useful service life.

Therefore, the Grid Technology group is planning on replacing the SCADA system during the Real Estate

Rationalization (starting 2015 with completion of installation in 2018) project as it will provide an opportune

time to transition to a new system.

4.1.2 Communication Infrastructure Communications are fundamental to all HOLs distribution automation plans. HOL communications

infrastructure includes a dark fiber network that Hydro Ottawa Ltd currently leases from Rogers

Communications Inc. (formerly Atria Networks), radio communications in both the licensed and unlicensed

900MHz spectrum, and phone based communication (both leased lines and cellular including LTE).

In early 2014, Hydro Ottawa Ltd. initiated a pilot project to deploy a small WiMAX network using the 1800 –

1830MHz band that has been reserved by Industry Canada for use in the management of the electricity

system. It is the goal of this project to evaluate the technology for use in distribution automation as well as

SCADA and metering applications. While the WiMAX network will not provide the throughput of 3G/LTE

systems, it does provide lower latency and a cost structure that will be more compatible with a utility

budgetary framework.

Hydro Ottawa continues to evaluate the best mix of these technologies to support increased communication

distribution and substation equipment in the future. Current challenges include the ongoing costs of leasing

fiber optic communications, as well as saturation of available radio communication primarily in the east area

of the city. As part of this evaluation, HOL has engaged a consulting firm to develop a telecommunications

master plan with their final report anticipated May 2014. With this plan, HOL intends to create a roadmap for

investment in communications infrastructure that will make efficient use of budget dollars as well as having a

maximum impact on device connectivity.

Page 24: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

24

FIGURE 4.1 - EXISTING FIBER NETWORK

Page 25: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

25

4.2 Distribution Automation Distribution automation supports improved reliability through reduced outage duration, and reduced

customer interruption. Outage duration is reduced through the addition of remotely operable device which

allow system operators to quickly restore customers following interruptions, as well as increased speed of

fault location through system monitoring. Customer interruptions are reduced by deploying autonomous

devices such as reclosers, which isolate faulted sections of the system and reduce the total customers

interrupted for a given fault.

4.3 Automation Plans 4.3.1 South Nepean Automation Plan

The South Nepean 28kV system is supplied by three 28kV stations, each with single source supplies.

Installation of automated switches will reduce outage duration. With rapid growth in this area, load transfers

are often required to maintain system loading within equipment ratings. With the addition of remotely

operable switches, load transfers can be executed faster in response to system loading.

There are 4 automated switches remaining to be installed to complete current plans in this area following

2012. These switches will be installed between 2013 and 2016. The switch locations are existing normal open

points between Fallowfield DS, Longfields DS and Limebank MS, or are strategic locations to allow for

sectionalizing of the feeders in south Nepean. The proposed locations for automated devices are shown in

Figure 4.2.

FIGURE 4.2 - EXISTING AND PROPOSED LOCATIONS FOR REMOTELY OPERATED SWITCHES

7F1

7F2

606F1

606F2

210F1

210F2

Existing Switch

2011 Installation

2012 Installation

Future Installation

Page 26: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

26

4.3.2 East 28kV system Hydro Ottawa’s East end 28kV system is modern, containing several remotely operable switching points.

Future automation projects in this area will focus on sustainment of existing automated switches and

additions as identified to improve functionality.

4.3.3 West 28kV system Planned addition of remotely operable devices on the west 28kV system is planned for 2013 and beyond.

Locations currently identified include installation of remotely operable tie switches between feeders to

reduce outage duration and increase speed at which circuits can be sectionalized in the Stittsville area.

4.3.4 44kV Sub- transmission Automation Hydro Ottawa 44kV sub transmission system supplies some large customers directly but is primarily the

supply network for a number of 8kV and a handful of 28kV substations. While interconnections exist, the

44kV system operate largely in isolation, with the East supplied from Hawthorne TS, South by Nepean TS and

West By South March TS.

East End 44kV

This project includes the plan to modernize and deploy automatic restoration on the 44kV loop in the east

end which is created by the 48M3, 48M4, and 48M5. These sub transmission circuits supply power to roughly

3% of Hydro Ottawa’s Customer base. This project includes the installation of station and distribution circuit

breakers as well as some minor system reconfiguration, and station reconfiguration.

This scheme will enable restoration of most customers without operator intervention and will eliminate the

need to dispatch crews. This scheme will improve supply reliability by eliminating sustained customer

interruptions at the existing 44/8kv stations for most sub transmission interruptions on the 44kV system.

West 44kV

The 44kV system in the west of the city is radial with predominately manually operated switches, many of

which are non-load break. Starting in 2012, deployment of remotely operable devices on this part of the

system is planned to improve operability and reliability.

2012 projects included the replacement of two existing manual non-load break switches on the A9M3 with

remotely operable switches. This will allow for sectionalizing and partial restoration without dispatching

crews. In 2013, three additional devices are planned to be installed on the A9M3 and A9M1 to further

improve operability of the system

4.3.5 Other Automation Plans CPP Padmount Control Improvement

Automated CPP padmount switchgear have had past issues with going out of calibration, resulting in failure

in remote operation. This project includes both engaging CPP to develop a solution as well as deploying the

solution in the field. This project is currently planned to be carried out in 2015.

FCI Program

Continuing on the success of the recent FCI trials of the last two years, 2010 saw the deployment of more

FCIs throughout the service area. In 2011 Hydro Ottawa has developed a comprehensive FCI deployment

plan. The plan will be broken into phases and will be implemented over the next several years. FCI indication

is an essential pillar in the effort to improve situational awareness and improve System Office’s ability to limit

the outage durations for customers on the large 27kV distribution systems. This technology is also valuable

as a key element in developing automated load restoration schemes.

Page 27: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

20

14

Re

lia

bil

ity

Pla

n

27

4.4 Substation Automation New station construction and station upgrades are incorporating the latest technologies and network

communication infrastructure. These stations will take advantage of the latest developments in

communication technology and in new electronic protection relaying, metering, and equipment monitoring.

These upgrades will also make use of newer and more advanced security features, thereby ensuring that the

enhanced connectivity does not come with enhanced risk. Along with this endeavour, existing substation

intelligent devices will be incorporated into the existing SCADA system to capture the real-time monitoring

data and providing this data to HOL’s Asset Management department through back office database links that

already exist. In 2010, all existing transformer oil analysis devices were connected to substation RTUs.

Substation automation work will be focused on the addition of online oil monitoring to aged transformers, at

a rate of 4 per year in 2012 and 2013, then decreasing to 2 per year beyond. In addition, work is planned for

continued deployment of Power Quality metering with the development of a real time link in 2014. With the

goal of reducing distribution losses a trial of closed loop line voltage control is planned to be initiated in 2014,

to enable lower operating voltage while maintaining customer voltage within the appropriate range. Another

significant benefit of the additional Power Quality metering will be the ability to capture waveform data from

system faults. This data can be processed using power quality software (PQView) in order to determine

approximate locations for faults (in conjunction with the FCI data). While there will be some additional effort

involved in calibrating this system, it is expected that it will eventually lead to a significant reduction in the

time spent investigating a fault and therefore reduce response time.

Page 28: 2014 Reliability Plan - Hydro Ottawa · System reliability targets are set to flag where gaps exist and attention is required. Through review of historical performance targets shown

2014 Reliability Plan

28