2013 regional transportation authority plan report rta ballot … · 2020. 7. 8. · 36) are part...

20
2013 Regional Transportation Authority Plan Report RTA Ballot No. 36 INTERSECTION SAFETY AND CAPACITY UPGRADES

Upload: others

Post on 03-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

2013 Regional Transportation Authority Plan Report

RTA Ballot No. 36INTeRsecTIoN sAfeTy ANd cAPAcITy UPgRAdes

Page 2: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element
Page 3: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

overview

Intersection Safety and Capacity Upgrades (RTA Ballot No. 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element for intersection upgrades was allocated $100 million, or 5 percent, of the project funding identified in the plan to improve regional mobility.

The RTA plan did not identify specific intersection im-provements to be constructed as a part of this sub-ele-ment but showed in an illustrative fashion a distribution of intersection projects across the region, including intersec-tions that would be built on regional corridors listed on the ballot as Roadway Element projects.

Outreach materials of the RTA plan shared with the public prior to the vote indicated a total of 200 intersection im-provements to be built across the region.

Progress To date

Through March 2013, RTA member jurisdictions have completed102 Intersection Safety and Capacity Upgrades. Additionally, another 21 major intersections have been improved as a part of Roadway Element projects, bringing the total number of improved intersections to 123. After nearly seven years into the RTA plan, the volume of com-pleted intersection improvements compares favorably to the pre-election commitment to improve 200 intersec-tions over the life of the RTA plan.

The scope of improvements varies substantially, from the upgrade of traffic signal components to complete intersection reconstruction to add more turn lanes and drainage improvements. The costs of these improvements have been just as varied, ranging from as little as $26,000 for the installation of countdown pedestrian signals at 15 Oro Valley intersections to $7.8 million for the Grant Road and Craycroft Road intersection improvement.

While the vast majority of the completed projects funded under the sub-element have been modest in size, the costs on 14 projects exceeded $900,000, constituting 76 percent of the total funds programmed in the sub-element.

The RTA Board has approved $63,901,000 (63.9%) in project commitments out of the sub-element’s $100 mil-lion budget. To date, $48.9 million in project reimburse-ments have been made, with $44.1 million of that amount expended on projects which are now complete. Pima

2013 RTA PlAN RePoRT

Intersection safety and capacity Upgrades

County, the cities of Tucson and South Tucson, and the towns of Oro Valley, Sahuarita and Marana have received project funding. The distribution of project funding is shown on the following graph.

Programmed funding for RTA Ballot No. 36, Intersection Safety and Capacity Upgrades

Of the 102 intersection projects completed, 11 required supplemental funding due to project cost increases. Of these 11 projects, two received additional funding from the implementing jurisdiction; the remaining projects received supplemental funding by RTA Board action. The total amount added to these projects was $3.68 million. It should be noted that one project, the Wilmot/Park Place intersection, returned approximately $1.48 million which was determined to be overprogrammed. The 14 largest projects (those over $900K) included four of the projects which required supplemental funding (including both of the projects with additional jurisdictional funding). The to-tal amount of RTA funding programmed for these projects was $36 million, of which $33.4 million was expended. The remaining balance of $2.6 million represents a 7.2 percent savings from the programmed amount.

Recognizing the savings from the completed, previously programmed projects, the RTA Board programmed an ad-ditional six projects, with a combined funding amount of $3.9 million, at its January 2013 meeting.

Page 4: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

Completed RTA Intersection Improvements through February, 2013

Page 5: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

detailed Intersection Review

The following pages show the specific benefits of the 14 largest intersections (costs exceeding $900,000) funded through the Intersection Safety and Capacity Upgrades sub-element of the RTA plan.

RTA Ballot No. 36

Intersection safety and capacity Upgrades

Page 6: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

grant Road and craycroft Road Intersection

ToTal projecT cosT: $7.968 million $7.772 million pro-grammed

scope of work:Double left-turn lanes added in all directions.

Right turn lanes added in all directions.

Reconstruct Alamo Wash bridge on Cray-croft.

New median islands on Craycroft Road.

New bus pullouts on Grant Road with shelter at TMC.

Construct continuous sidewalks.

Upgrade traffic signals.

Reconstruct or overlay existing pavement through project limits.

compleTed: FY 2010

The Grant Road and Craycroft Road intersection was one of the first major intersection projects completed with RTA funding and is the most expensive intersection project to date. The project received an initial $4.5 million funding allocation, which was increased to $7.772 million due to escalating costs. The project was originally bid in 2007, but the bids were rejected due to the bids exceeding available funding. The project was downscaled to reduce

costs and additional funding was programmed.

The completed project substantially improved intersection performance, with significant reductions in overall delay. The project has reduced delay at the intersection by 24 percent during the morning rush hour, with the evening rush hour delay reduced by 37 percent.

Before reconstruction

After reconstruction

Page 7: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

ToTal projecT cosT: $4.77 million $4.997 million pro-grammed.

scope of work:Right turn lanes added in all directions.

New bus pullouts on Campbell (north of intersection) and Ft. Lowell Road (east & west of intersection) with shelters.

Construct continuous sidewalks.

Upgrade traffic signals.

Drainage improve-ments.

Reconstruct or overlay existing pavement through project limits.

compleTed: FY 2011

ft. lowell Road and campbell Avenue Intersection

The Ft. Lowell Road and Campbell Avenue intersection improvements were completed at a cost of $426,000 below the programmed amount. Additional funds will be returned as a result of the sale of the remnant parcel at the northwest corner of the intersection. The improve-

ments are estimated to reduce the average intersection delay (per entering vehicle) in the evening peak period from 50.9 seconds to 35.9 seconds, a reduction of nearly 30 percent.

Before reconstruction

After reconstruction

Page 8: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

starr Pass Blvd. and Mission Road Intersection

ToTal projecT cosT: $3.878 million $4.65 million pro-grammed.

scope of work:Reconstruct ramp from northbound Mission to eastbound Starr Pass.

Reconfigure intersec-tion to have Mission Road tee into Starr Pass, with Grande Street tee into Mission Road.

Construct continuous sidewalks.

Reconstruct traffic signal.

Reconstruct or overlay existing pavement through project limits.

compleTed: FY 2011

Before reconstruction

After reconstruction

The Starr Pass Boulevard and Mission Road intersection improvements were designed to simplify operations at the intersection and favor the heaviest traffic movements with improved geometry. The changes also helped to reduce

traffic through the adjacent neighborhood. The final project costs were over $700,000 below the programmed amount. The improvements are estimated to reduce delay per vehicle by 9 percent in the evening peak hour.

Page 9: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

ToTal projecT cosT: $1.475 million $1.7 million pro-grammed (after $1.48 million released).

scope of work:Reconstruct continuous flow Tee intersection (Florida Tee) to provide three lanes of continu-ous northbound travel.

Add southbound right turn lane to improve safety.

Reconfigure median island.

Construct continuous sidewalks.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2010

Park Place and Wilmot Road Intersection

Before reconstruction

After reconstruction

The Park Place and Wilmot Road intersection improve-ments established a continuous flow intersection. Prior to the project, two of the three northbound lanes were con-tinuous flow. However, the 3rd, inside lane was subject to

signal operations. This created driver confusion and delay. Total vehicle delay has been reduced during the evening peak hour by 15 percent.

Page 10: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

golf links Road and Wilmot Road Intersection

ToTAL PRojeCT CoST:

$1.627 million $1.95 million originally programmed.

SCoPe oF WoRk:

Right turn lanes.

Construct continuous sidewalks.

Upgrade traffic signals.

Reconstruct or overlay existing pavement through project limits.

Drainage improve-ments.

CoMPLeTeD:

FY 2010

Before reconstruction

After reconstruction

This project was delivered more than 16 percent under the programmed amount. The intersection improvements

are estimated to reduce evening peak-hour delay by more than 28 percent.

Page 11: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

ToTAL PRojeCT CoST:

$3.25 million $4 million originally programmed.

SCoPe oF WoRk:

Dual left turn lanes in all directions.

Reconfigure median island.

Construct continuous sidewalks.

Bus pullout and shelter.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2012

golf links Road and Kolb Road Intersection

Before reconstruction

After reconstruction

Improvements to the intersection of Golf Links Road and Kolb Road consisted of dual left turn lanes in all directions, bus pullouts, access control measures and upgraded pe-destrian facilities. The project was completed 18 percent

below the programmed amount. The new intersection reduces entering vehicle delay during the evening peak by more than 34 percent

Page 12: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

la cholla Blvd and overton Road Intersection

ToTAL PRojeCT CoST:

$0.981 million $1.04 million originally programmed.

SCoPe oF WoRk:

Widen intersection add-ing left turn lanes and right turn lanes.

Drainage improve-ments.

Added pedestrian ramps and curbs.

Install new traffic signal, including video detection, safety light-ing and pre-emption capabilities.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2008

Before reconstruction

After reconstruction

This was one of the first intersection projects completed. The original amount programmed for the project was $780,000. However, additional funding was provided by RTA Board action, bringing the total funding programmed

to $1,040,000. The intersection was raised above the floodplain of the nearby Cañada del Oro wash to elimi-nate flooding. New left turn lanes and traffic signals were installed.

Page 13: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

ToTAL PRojeCT CoST:

$1.184 million $1.1 million originally programmed.

SCoPe oF WoRk:

Widened intersection to add dual left turns on River Road.

Reconfigure median islands.

Construct continuous sidewalks.

Bus pullout and shelter.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2009

la cholla Blvd and River Road Intersection

Before reconstruction

After reconstruction

The La Cholla and River Road intersection improvements will yield delay reductions of 28 percent during p.m. peak hour operations. Transit users were provided a shelter

south of River on La Cholla (not shown in photo). Project costs went 7 percent over the programmed amount.

Page 14: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

la cholla Blvd and lambert lane Intersection

ToTAL PRojeCT CoST:

$0.855 million; $0.9 million originally pro-grammed.

SCoPe oF WoRk:

Reconstruct and widen intersection adding 4 left turn lanes.

New traffic signals, in-cluding video detection, safety lighting and pre-emption capabilities.

Added pedestrian ramps.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2008

Before reconstruction

After reconstruction

This was a considerable upgrade of a four-way stop in-tersection into a fully functional signal-controlled inter-

section with turning lanes. This project was completed 5 percent under the programmed budget amount.

Page 15: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

ToTAL PRojeCT CoST:

$4.5 million; $2.5 mil-lion programmed. ($2 million Pima County development impact fees)

SCoPe oF WoRk:

Widen intersection to include left and right turn lanes and two flow lanes in all directions.

Add median islands.

Upgrade traffic signals from 4-way stop.

Added pedestrian ramps and curbs through intersection.

New traffic signal in-cluding video detection, and safety lighting.

Bicycle lanes.

Drainage improve-ments.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2009

Houghton Road and sahuarita Road Intersection

Before reconstruction

After reconstruction

This project reduced congestion and enhanced safety. It included replacing the stop sign controlled intersec-tion with traffic signals, removing the existing median and adding turn lanes on the approaches; adding a westbound and southbound right turn lane; construct-ing drainage improvements such as culverts, pipes and

ditches, and adding bicycle lanes, pedestrian access ramps and crosswalks for pedestrians. The project was completed at the programmed amount. However, local funds were required to fully fund the improvements. The project re-duces delay by 13 percent in afternoon peak, and address-es a number of safety deficiencies previously identified.

Page 16: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

Alvernon Way and Valencia Road Intersection

ToTAL PRojeCT CoST:

$2.55 million $2.5 million pro-grammed.

SCoPe oF WoRk:

Widen Valencia to three flow lanes with double left turn lanes.

Reconfigure median islands.

Construct continuous sidewalks.

Upgrade traffic signals.

Add bus pullout.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2012

Before reconstruction

After reconstruction

This project has reduced delay by 15 percent during the afternoon peak and was completed with a cost of 2 percent over the programmed amount. It included the

widening of Valencia Road and added sidewalks and a bus pullout.

Page 17: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

ToTAL PRojeCT CoST:

$0.582 million $0.9 million pro-grammed.

SCoPe oF WoRk:

Widen Valencia to add left turn lane eastbound and right turn lane westbound. Widen Camino Verde to provide for left and right turn lanes.

Added a traffic signal.

Add pedestrian ramps and curbs.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2010

camino Verde and Valencia Road Intersection

Before reconstruction

After reconstruction

This project replaced the stop signs with a traffic signal, and added dedicated lanes for all turning movements.

The project was completed at a cost of 35 percent under the programmed amount.

Page 18: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

Ina Road and silverbell Road Intersection

ToTAL PRojeCT CoST:

$1 million; $1 million programmed.

SCoPe oF WoRk:

Realign and widen intersection adding left and right turn lanes.

Reconfigure or add median islands.

Construct continuous sidewalks.

Upgrade traffic signals.

Drainage improve-ments.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2009

Before reconstruction

After reconstruction

This project included realignment of the intersection along with widening both roads from two to four lanes. Turn lanes and multi-use lanes also were added to miti-gate congestion and improve safety. The project was

delivered for the programmed amount (in conjunction with Silverbell Road improvements) and has reduced peak hour intersection delay by 48 percent.

Page 19: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

ToTAL PRojeCT CoST:

$0.859 million; $0.998 million programmed.

SCoPe oF WoRk:

Reconstruct intersection with traffic circle.

Reconfigure median islands.

Add pedestrian ramps and curbs.

Reconstruct or overlay existing pavement through project limits.

CoMPLeTeD:

FY 2010

camino del sol and continental Road Intersection

Before reconstruction

After reconstruction

This Green Valley project was completed for a cost of 14 percent under the programmed amount. Adding the traffic circle provides traffic calming for safer intersection operation and avoids the need for a traffic signal. This

project was coordinated with Continental Road bicycle lane improvements funded under the Bikeways, Green-ways, Pathways and Sidewalks sub-element (RTA Ballot No. 41).

Page 20: 2013 Regional Transportation Authority Plan Report RTA Ballot … · 2020. 7. 8. · 36) are part of the Safety Element of the RTA plan adopted by voters in May 2006. The sub-element

cost summary for the 14 largest completed Intersection safety and capacity Upgrades, RTA Ballot No. 36

Safety - Intersection Improvements Sponsor

Construction Bid Amount

RTA Cost (000's)

Expended (000's)

Balance (000's)

% +/- Budget

Grant/Craycroft City of Tucson $6,368,888 $7,772 $7,906 ($134) 1.72%

Golf Links/Wilmot City of Tucson $1,219,314 $1,950 $1,627 $323 -16.56%

Ft. Lowell/Campbell City of Tucson $209,944 $4,997 $4,770 $227 -4.54%

Starr Pass/Mission City of Tucson $2,987,187 $4,650 $3,878 $772 -16.60%

Wilmot/Park Place City of Tucson $1,120,473 $1,700 $1,475 $225 -13.24%

Golf Links/Kolb City of Tucson $2,711,580 $4,000 $3,250 $750 -18.75%

La Cholla/Overton Pima County $899,412 $1,040 $981 $59 -5.67%

Houghton/Sahuarita Pima County $3,222,159 $2,500 $2,500 $0 0.00%

Alvernon Way/Valencia Pima County $1,854,734 $2,500 $2,550 ($50) 2.00%

La Cholla/River Pima County $818,080 $1,100 $1,184 ($84) 7.64%

Camino Verde/Valencia Pima County $422,824 $900 $582 $318 -35.33%

Continental/Camino del Sol Pima County $546,400 $998 $859 $139 -13.93%

Lambert Lane/La Cholla Oro Valley $885,793 $900 $855 $45 -5.00%

Silverbell/Ina Marana $1,041,770 $1,000 $1,000 $0 0.00%

$36,007 $33,417 $2,590 -7.19%

% +/- RTA Cost Expended Balance Budget

Projects Over 900,000 36,007 33,417 2,590 -7.19%All Intersections 47,511 44,082 3,429 7.22%

Unexpended % +/– RTA Cost Expended Balance Budget Projects Over $900,000 $36,007 $33,417 $2,590 –7.19% All Intersections $47,511 $44,082 $3,429 –7.22%