2013 - 2014 CONSTRUCTION ENGINEERING SERVICES FOR WISDOT SOUTHEAST REGION – LOCAL PROGRAM CONSULTANT PACKAGE SE 60L Project I.D. #1 2722-10-70 Highway/Street: Coffee Road Termini/Location: Calhoun Rd To National Ave County: Waukesha Length: 1.32 miles Project Type: Reconstruction Urban and/or Rural: Urban & Rural Traffic Control: Closed to thru traffic Letting Date: January 14, 2014 Field Rate Accounting Required: No Anticipated Construction Cost: $3,000,000 - $3,999,999 Major Items of Work: Roadway items, HMA, Electrical Complexity Level: High Restrictions: Holidays, Snakes, Contaminated Soils Construction Leader Required: Yes Construction Support Staff Required: Yes Anticipated Number of Support Staff: 2-3 Required Certification: Aggregate sampling and PCCTEC-1 Duties: Construction administration, inspection, materials sampling and testing, and construction surveys. Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals For more information, contact: Sandra Villiesse , Contract Specialist SE Region Local Program, 2013-14 Packages

Upload: phunganh

Post on 11-May-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

2013 - 2014 CONSTRUCTION ENGINEERING SERVICES FOR WISDOT

SOUTHEAST REGION – LOCAL PROGRAM

CONSULTANT PACKAGE SE 60L

Project I.D. #1 2722-10-70Highway/Street: Coffee RoadTermini/Location: Calhoun Rd To National AveCounty: WaukeshaLength: 1.32 milesProject Type: ReconstructionUrban and/or Rural: Urban & RuralTraffic Control: Closed to thru traffic

Letting Date: January 14, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $3,000,000 - $3,999,999

Major Items of Work: Roadway items, HMA, ElectricalComplexity Level: HighRestrictions: Holidays, Snakes, Contaminated Soils

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 2-3

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region Local Program, 2013-14 Packages

Page 2: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 61L

Project I.D. #1 2722-11-70Highway/Street: Lincoln AvenueTermini/Location: Calhoun Rd To CTH O (Moorland Rd)County: WaukeshaLength: 0.93 milesProject Type: ReconstructionUrban and/or Rural: Urban & RuralTraffic Control: Open to thru traffic

Letting Date: January 14, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $5,000,000 - $7,499,999

Major Items of Work: Roadway items, HMA, BioswalesComplexity Level: HighRestrictions: Holidays, Contaminated Soils, In-stream Disturbance, Railroad

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 3

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 14 Packages

Page 3: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 62L

Project I.D. #1 2160-10-70Highway/Street: S 76th Street (CTH U)Termini/Location: 600 Ft N Of W High St-Carter BlvdCounty: MilwaukeeLength: 1.975 milesProject Type: ReconstructionUrban and/or Rural: UrbanTraffic Control: Open to thru traffic

Letting Date: February 11, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $7,500,000 - $9,999,999

Major Items of Work: Roadway items, Concrete pavement, HMA pavement, Traffic signals, Box culvert extension

Complexity Level: HighAssociated Contracts: NoneRestrictions: Holidays, Swallows, In-stream Disturbance, Ash Borer

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number: 3-4

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 4: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 63L

Project I.D. #1 2370-00-73Highway/Street: CTH F (Redford Blvd)Termini/Location: Busse Road To STH 190 (South Ramp)County: WaukeshaLength: 2.613 milesProject Type: ReconditionUrban and/or Rural: Urban & RuralTraffic Control: Open to thru traffic, Staging

Letting Date: February 11, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $3,000,000 - $3,999,999

Major Items of Work: Roadway items, Pavement milling & grinding, Concrete pavement repair, HMA, Traffic signals

Complexity Level: HighRestrictions: Holidays, Contaminated Soils

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 2

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 5: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 64L

Project I.D. #1 2718-00-74Highway/Street: Summit AvenueTermini/Location: 2nd Street To Thackery TrailCounty: WaukeshaLength: 1.08 milesProject Type: ReconstructionUrban and/or Rural: UrbanTraffic Control: Some Open to thru traffic, Some Closed to thru traffic, Alternate Route

Provided

Letting Date: February 11, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $1,000,000 - $1,999,999

Major Items of Work: Roadway items, HMA, Mill & overlay & reconstructionComplexity Level: HighRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 6: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 65L

Project I.D. #1 2984-39-72Highway/Street: North 45th StreetTermini/Location: Bridge Over Menomonee Rvr & ApproachesCounty: MilwaukeeLength: 0.02 milesProject Type: Bridge RehabUrban and/or Rural: UrbanTraffic Control: Closed, Temp Bridge

Letting Date: March 11, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $1,000,000 - $1,999,999

Major Items of Work: Bridge redeck, ApproachesComplexity Level: MediumRestrictions: Holidays, Railroad coordination, Contaminated soild, Archeolgical

monitoring

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 0-1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 7: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 66L

Project I.D. #1 3849-00-71Highway/Street: Sheridan Springs RdTermini/Location: Bridge Over White River (P-64-0074)County: WalworthLength: 0.07 milesProject Type: Bridge ReplacementUrban and/or Rural: RuralTraffic Control: Closed to thru traffic

Letting Date: March 11, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Major Items of Work: Roadway items, Bridge items, HMA, Slab on prestressed girdersComplexity Level: MediumRestrictions: Holidays, In-stream disturbance, Wetlands, Swallows

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 0-1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 8: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 67L

Project I.D. #1 2670-00-71Highway/Street: Green Tree RoadTermini/Location: River Road To Jean Nicolet RoadCounty: MilwaukeeLength: 0.64 milesProject Type: ResurfacingUrban and/or Rural: Urban & RuralTraffic Control: Open to thru traffic

Letting Date: April 8, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $100,000 - $249,999

Major Items of Work: Roadway items, ADA rampsComplexity Level: Low/MediumRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 0-1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 9: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 68L

Project I.D. #1 2704-00-73Highway/Street: Ohio StreetTermini/Location: 16th St To Washington Ave (STH 20)County: RacineLength: 0.38 milesProject Type: Pavement ReplacementUrban and/or Rural: UrbanTraffic Control: Staging, Road Closed/Detour

Letting Date: April 8, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $1,000,000 - $1,999,999

Major Items of Work: Roadway items, Concrete, Pavement marking, Storm sewer, ADA rampsComplexity Level: Medium/HighRestrictions: Holidays, Ash borer

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 10: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 69L

Project I.D. #1 2155-03-71Highway/Street: W. Fond Du Lac Ave (STH 145)Termini/Location: Intersection With ShermanCounty: MilwaukeeLength: 0.10 milesProject Type: MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to thru traffic

Letting Date: May 13, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $100,000 - $249,999

Major Items of Work: Roadway items, Concrete, Traffic SignalsComplexity Level: MediumRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 0-1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 11: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 70L

Project I.D. #1 2160-15-70Highway/Street: S 76th StreetTermini/Location: Intersection With Edgerton & Layton AveCounty: MilwaukeeLength: 0.10 milesProject Type: MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to thru traffic

Letting Date: May 13, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $500,000 - $749,999

Major Items of Work: Roadway items, Concrete, Traffic SignalsComplexity Level: MediumRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 0-1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 12: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 71L

Project I.D. #1 2967-16-70Highway/Street: Pedestrian Countdown Signal HeadTermini/Location: 49 Various IntersectionsCounty: MilwaukeeLength: 0.00 milesProject Type: MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: July 8, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Major Items of Work: Countdown pedestrian signal headsComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 0-1

Required Certification: NoneDuties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 13: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 72L

Project I.D. #1 3853-00-72Highway/Street: West Lake DriveTermini/Location: CTH P To Road BCounty: WaukeshaLength: 0.966 milesProject Type: ResurfacingUrban and/or Rural: Urban & RuralTraffic Control: Road closed to thru traffic

Letting Date: July 8, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Major Items of Work: HMA, Curb & gutter, Pavement marking, Grading, Adjust MH rimsComplexity Level: Low/MediumRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: YesAnticipated Number of Support Staff: 0-1

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 14: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 73L

Project I.D. #1 2984-08-75Highway/Street: City Of Milwaukee Various LocationsTermini/Location: 10 Local IntersectionsCounty: MilwaukeeLength: 0.00 milesProject Type: MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: August 12, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $500,000 - $749,999

Major Items of Work: Monotube mast arms, Median nose modifications, Detectable warning fields

Complexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 15: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 74L

Project I.D. #1 2265-17-90Highway/Street: 27th StreetTermini/Location: West Highland Blvd To St Paul AveCounty: MilwaukeeLength: 0.86 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: October 25, 2013

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Major Items of Work: Sidewalks, Stamped colored concrete, Crosswalks, LightingComplexity Level: LowAssociated Contracts: NoneRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 16: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 75L

Project I.D. #1 1693-44-70Highway/Street: Bicycle Lane InstallationsTermini/Location: Various Roadways City Of MilwaukeeCounty: MilwaukeeLength: 20-30 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: January 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Major Items of Work: Pavement marking, SigningComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: NoneDuties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 17: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 76L

Project I.D. #1 2265-00-93Highway/Street: Layton Blvd Street ScapeTermini/Location: W Oklahoma Ave To National AveCounty: MilwaukeeLength: 2.35 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: February 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Major Items of Work: Lighting, Colored concrete crosswalks, Decorative trash containers and planters

Complexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 18: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 77L

Project I.D. #1 1693-35-93Highway/Street: Installation Of Transit PriorityTermini/Location: Express Bus/Trolley Circulator RtesCounty: MilwaukeeLength: 0.00 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: February 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $750,000 - $999,999

Major Items of Work: Detection and Controller EquipmentComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 19: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 78L

Project I.D. #1 1693-35-98Highway/Street: Install Semi-Actuated OperationTermini/Location: 32 Local Intersections CitywideCounty: MilwaukeeLength: 0.00 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: March 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Project I.D. #2 1693-35-99Highway/Street: Install Semi-Actuated OperationTermini/Location: 10 Connecting Highway IntersectionsCounty: MilwaukeeLength: 0.00 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: March 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $100,000 - $249,999

Major Items of Work: Traffic Signal Improvements: Pedestrian pushbuttons, Vehicle detection loops

Complexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 20: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 79L

Project I.D. #1 1693-48-91Highway/Street: Traffic Adaptive Signal SystemTermini/Location: 22 Signalized IntersectionsCounty: MilwaukeeLength: 0.00 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: March 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $500,000 - $749,999

Major Items of Work: Computer controlled traffic signalsComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: NoneDuties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 21: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 80L

Project I.D. #1 2545-03-91Highway/Street: West Hampton AvenueTermini/Location: N Teutonia Ave To N Green Bay AveCounty: MilwaukeeLength: 0.758 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: April 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $100,000 - $249,999

Major Items of Work: Signals and SignsComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 22: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 81L

Project I.D. #1 2697-03-71Highway/Street: Pioneer Rd (CTH C)Termini/Location: Intersection Granville Rd (CTH Y)County: OzaukeeLength: 0.00 milesProject Type: LFA - MiscellaneousUrban and/or Rural: RuralTraffic Control: Open to Thru Traffic

Letting Date: April 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $0 - $99,999

Project I.D. #2 4822-05-70Highway/Street: Trail Improvement ProjectTermini/Location: Ozaukee Interurban TrailCounty: OzaukeeLength: 0.511 miles off road & 0.398 miles shoulder wideningProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: April 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $100,000 - $249,999

Major Items of Work: Overhead signs, Grading, HMAComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 23: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 82L

Project I.D. #1 2100-02-91Highway/Street: South 35th StreetTermini/Location: W Burnham Ave To W Greenfield AveCounty: MilwaukeeLength: 0.56 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: May 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $100,000 - $249,999

Major Items of Work: Signals and SignsComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

Page 24: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 83L

Project I.D. #1 2155-03-91Highway/Street: W. Fond Du Lave Ave (STH 145)Termini/Location: Intersection With ShermanCounty: MilwaukeeLength: 0.00 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: May 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $0 - $99,999

Project I.D. #2 2984-16-91Highway/Street: West Lloyd StreetTermini/Location: N 60th St To W Lisbon AveCounty: MilwaukeeLength: 1.10 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: August 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $0 - $99,999

Major Items of Work: Monotube mast arms, Signals and SignsComplexity Level: LowAssociated Contracts: 2155-03-91 & 2984-16-91 tied as Construction Package onlyRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 15 Packages

Page 25: 2013-14 Construction Engineering Solicitation - …wisconsindot.gov/.../slicitations/13con/selpack13.docx · Web viewTraffic Control:Closed, Temp Bridge Letting Date:March 11, 2014

CONSULTANT PACKAGE SE 84L

Project I.D. #1 2984-08-95Highway/Street: City Of Milwaukee Various LocationsTermini/Location: 10 Local IntersectionsCounty: MilwaukeeLength: 0.00 milesProject Type: LFA - MiscellaneousUrban and/or Rural: UrbanTraffic Control: Open to Thru Traffic

Letting Date: August 25, 2014

Field Rate Accounting Required: NoAnticipated Construction Cost: $250,000 - $499,999

Major Items of Work: Signs, Signals & LightingComplexity Level: LowRestrictions: Holidays

Construction Leader Required: YesConstruction Support Staff Required: NoAnticipated Number of Support Staff: 0

Required Certification: Aggregate sampling and PCCTEC-1Duties: Construction administration, inspection, materials sampling and testing,

and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact: Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages