2012 Educational Facilities Master Plan

Presentation to the Board of Education

June 25, 2012

Harford County Public Schools Serving Youth

Page 2: 2012 Educational Facilities Master Plan Presentation to the Board of Education June 25, 2012 Harford County Public Schools Serving Youth

Educational Facilities Master Plan

Section I: Mission, Standards, and Guidelines Educational Programs and Policies

Section II: Community Analysis Growth and Demographics Information

Section III: Facilities Inventory Building Assessment and Inventory of Facilities

Section IV: Enrollment Projections 2011 Enrollment Projections

Section V: Facility Utilization and Needs Long-Range Planning and Timeline of Capital Projects

Section VI: Letters of Approval State /County Enrollment and Master Plan Approval Letters

Page 3: 2012 Educational Facilities Master Plan Presentation to the Board of Education June 25, 2012 Harford County Public Schools Serving Youth

Project Categories

C = Capacity Projects

M = Modernization Projects

B = Building/Program Improvement Projects

S = Site/Program Improvement Projects

Evaluation of existing buildings and sites to both modernize and expand

Master planning to maximize the land we own

Page 4: 2012 Educational Facilities Master Plan Presentation to the Board of Education June 25, 2012 Harford County Public Schools Serving Youth

Parameters For Decision Making State and Local Funding Approvals

Educational Facilities Master Plan

Balancing Enrollment

Capacity, Infrastructure, & Program Projects

Comprehensive Facilities Master Plan (CFMP)

Projects have been placed on hold pending the completion of the CFMP & Local Funding Commitment

Page 5: 2012 Educational Facilities Master Plan Presentation to the Board of Education June 25, 2012 Harford County Public Schools Serving Youth

Capital Project Status Homestead/Wakefield ES – The BOE approved the Scope Study.

Local Planning was approved by the State in FY12. This Local Planning approval from the State will expire in FY14.

John Archer School – The BOE approved the Scope Study.

Youth’s Benefit ES – The construction documents are 95%complete.

William Paca/Old Post ES – The BOE approved the Scope Study.

Joppatowne HS – The BOE approved the Scope Study.

Campus Hills ES - The construction documents are 65% complete.

Havre de Grace HS – The Scope Study is currently in progress.

Page 6: 2012 Educational Facilities Master Plan Presentation to the Board of Education June 25, 2012 Harford County Public Schools Serving Youth

FACILITIES PLANNING & MASTER PLAN 2012Construction Timeline - Capacity, Modernization and Addition Projects

  FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23PROJECTS - STATE/LOCAL 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22 22-23

Homestead/Wakefield ES Addition / Modernization (SRC= 1029)

  

On Hold Pending the Completion of the Harford County Comprehensive Facilities Master Plan  

 

New John Archer School Facility at Bel Air Campus (SRC = 200)

  

On Hold Pending the Completion of the Harford County Comprehensive Facilities Master Plan  

 

Youth's Benefit ES Replacement School(SRC = 1130)

On Hold Pending the Completion of the Harford County Comprehensive Facilities Master Plan  

 

William Paca/Old Post ES Replacement School(SRC = 1154)

  

On Hold Pending the Completion of the Harford County Comprehensive Facilities Master Plan  

 

Page 7: 2012 Educational Facilities Master Plan Presentation to the Board of Education June 25, 2012 Harford County Public Schools Serving Youth

FACILITIES PLANNING & MASTER PLAN 2012Construction Timeline - Capacity, Modernization and Addition Projects

  FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23PROJECTS - STATE/LOCAL 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22 22-23

Joppatowne HSAddition & Modernization (SRC = 1475)

  

On Hold Pending the Completion of the Harford County Comprehensive Facilities Master Plan  

 

New Campus Hills Elementary School (SRC = 696)

 To Be Determined 

Existing John Archer School Building Modernization /Renovation (SRC=TBD)

 To Be Determined 

New Middle School (SRC = TBD)

 To Be Determined 

Page 8: 2012 Educational Facilities Master Plan Presentation to the Board of Education June 25, 2012 Harford County Public Schools Serving Youth

FACILITIES PLANNING & MASTER PLAN 2012Construction Timeline - Capacity, Modernization and Addition Projects

  FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23PROJECTS - STATE/LOCAL

12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22 22--23

Riverside ES (SRC=TBD)

 To Be Determined 

Bel Air MS (SRC=TBD)

 To Be Determined 

Magnolia ES (SRC=TBD)

 To Be Determined 

GD Lisby ES (SRC=TBD)

 To Be Determined 

WS James ES (SRC= TBD)

 To Be Determined 

Prospect Mill ES (SRC = TBD)

 To Be Determined 

Aberdeen MS (SRC= TBD)

 To Be Determined 

Edgewood MS (SRC=TBD)

 To Be Determined 

Abbreviation Key - SS = Scope Study, FS = State Required Feasibility Study, P = Planning and Design, C = Construction, O = Occupancy, SFR = State Funding Reimbursement, SRC = State Rated Capacity