2012 appendix l tunneling operations

Upload: dante1419828327

Post on 02-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 2012 Appendix l Tunneling Operations

    1/7

    CORRIBFIELDDEVELOPMENTPROJECT

    OnshoreWorksConstructionofTunnel

    METHODSTATEMENTRev02

    TunnellingOperations

  • 8/11/2019 2012 Appendix l Tunneling Operations

    2/7

    ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations

    DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP

    MethodStatement Revision:02 Page1of6

    SUMMARY

    Thisdocumentdescribestheconstructionofthe4.9kmsegmentlinedtunnelinwhichtheCorribOnshore

    PipelinebetweenGlenagdandAughoosewillbeinstalled.

    PURPOSE A4.9kmsegment linedtunnelwillbeconstructedusingaTunnelBoringMachine

    (TBM)betweenAughooseandGlengad.

    LOCATION The segment lined tunnelwillbe constructed from the starting shaft located at

    Aughoose (approx. Chainage 88.77). From there, the pipeline route traverses

    (underneath)theGlenamoyBogComplexcSACandtheBlacksodBay/Broadhaven

    pSPA at Sruwaddacon Bay in a northwesterly direction towards Glengad for

    approximately 4.9km, where the reception shaft (Chainage 83.88) will be

    constructedinthecSAC. Thetunnelwillbeconstructedwithaminimumdepthof

    coverof5.5m.

    TIMESCALE It isanticipatedthatthetunnellingprocesswilltakeapproximately15monthsto

    complete(atanaverageof11m/day).

    Thetunnellingconstructionwillbecarriedoutona24hoursaday/7daysaweek

    basis.

    Otherassociatedworks,suchasmaterialtransportandtunnelarisingsdisposalwill

    beexecutedbetweenthehoursof07:00and19:00weekdaysand07:00and16:00

    Saturday.

    CONSTRUCTION

    METHODOLOGY

    Thescope

    of

    works

    for

    the

    construction

    of

    the

    segment

    lined

    tunnel

    can

    be

    generallydividedintothefollowingworksteps:

    Constructionofthe4.9kmtunnelincludingaccessramps,startingshaftand

    receptionshaft;

    Installation and testing of the 20 inch gas pipeline and services in the

    tunnel;and

    Groutingofthetunnelandreinstatementoftheshafts.

    Furtherdetailsontheconstructionofthestartandreceptionshaftsareprovidedin

    othermethodstatements.

    Prior to the commencement of tunnelling, the Aughoose compound is

    constructedandassociatedutilitysystems,e.g.anappropriatesurfacewater

    management system, are made available. A separate method statement

    describestheconstructionoftheAughoosecompound.

    Plantandequipmentrequiredforthetunnelling,includingtheTBM,arethen

    mobilisedtosite.

    AllTBMassemblyandmaterialsupplywillbemanagedfromthestartingshaft

    inAughoose.

  • 8/11/2019 2012 Appendix l Tunneling Operations

    3/7

    ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations

    DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP

    MethodStatement Revision:02 Page2of6

    Plant

    and

    Equipment

    Themainplantandequipmentrequiredforthetunnellingprocessinclude:

    Gantrycrane;

    GroutmortarSilos

    Slurrytreatmentplant

    Bentonitetanksandsilos

    Freshwatertank

    Waterstoragetanks

    Filterpress

    Powergenerationunits

    Following the installation of all the required plant and the set up of the site

    compoundandfunctiontestingthetunnellingprocesswillcommence.

    Tunnelconstruction:

    The tunnelwillbeconstructedusingaslurryshield tunnellingmethodwhich

    involves the drilling/boring of the soil face using a TBM and then installing

    precastconcretesegmentsastheTBMprogresses.

    ThecuttingwheelatthefrontoftheTBMtunnelsintotheground. TheTBMis

    controlledby

    the

    steering

    cylinders

    within

    the

    TBM

    which

    pushes

    the

    cutter

    headinthedesireddirection.

    Powerswitchboards,hydraulicandlogisticunitsareallinstalledneartheTBM

    onanumberofbackuptrailers.Thesetrailers(typicallyof810mlength)are

    interconnectedandpulledbytheTBMthroughthetunnel.

    Concretesegmentsare transportedtothefrontof the tunnelonatrain that

    runsontrackswithinthetunnelduringconstruction.Thesetracksareinstalled

    inparalleltothetunnellingoperationononeoftheTBMbackuptrailers.

    Thestacked

    segments

    are

    transported

    through

    the

    tunnel

    to

    the

    tail

    skin

    by

    a

    supplysystemwithtraincarsandcranes. Anerectorunit locatedwithinthe

    TBMisusedtopickupthesegmentsfromthetrainanditinstallsthesegments

    into the designatedposition. Once installed they arebolted to the already

    installedringandsegments.

    Concrete segmentswhich are erected inside theback endof the tunnelling

    machine(thetailskin)andassembledtoformacompletesegmentringwhich

    isconnected,groutedandwheninpositionactsasthetunnellining.

    Aftercompletionofonesegmentring,alljackingcylindersareextendedfora

    furtheradvance

    cycle.

    By

    using

    this

    method

    of

    tunnel

    lining,

    the

    already

    built

    concretetunnelremainsstationaryandservesasanabutmentfortheadvance

  • 8/11/2019 2012 Appendix l Tunneling Operations

    4/7

    ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations

    DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP

    MethodStatement Revision:02 Page3of6

    oftheTBM. Grout(annulusgrouting) is injected intotheovercutbehindthe

    installed segment rings, which is created by the cutting wheel during

    excavation.

    Slurrylines

    for

    spoil

    transport,

    air

    duct

    for

    ventilation,

    pressurised

    air

    supply

    andpower/communication cables are installed inside the tunnel to support

    thedrillingprocess.

    Drilling fluid consisting of a suspension of water and bentonite (bentonite

    slurry) is used for lubrication and cooling of the cutting head, removal of

    cuttingsandstabilisationofthecuttingface.

    Bentoniteslurrysuspensionwillbepumpedthroughthefeedingpipeintothe

    TBMworkingchamber. Itismixedwiththeexcavatedsoil/rockandpumped

    back through the slurrydischargepipe to the separationplant atAughoose

    Compound.The

    soil

    is

    separated

    and

    the

    recycled

    bentonite

    slurry

    suspension

    pumpedthroughthetunnelbackintotheTBMworkingchamber.

    Theexcavatedmaterialsfromtunnelling(tunnelarisings)isseparatedfromthe

    drilling fluid/bentoniteslurrymixtureusingaseparationplantwhereshakers

    aredeployed and stockpiled temporarilywithin theAughooseCompound in

    designatedarea.

    Thesurplusbentoniteslurrywillberemovedanddewatered ina filterpress.

    After being treated in the filter press the filter cake is dry enough for

    transportation to a licensed waste facility. The Filter Press water will be

    monitoredthen

    recycled

    /reused

    on

    site,

    where

    feasible,

    or

    transported

    off

    sitetoalicensedwatertreatmentfacility.

    MixingofGroutMortar

    Groutmortarwillbeusedforgroutingtheannulusofthetunnel(voidsbehind

    the segments). The grout mortar will also be used for filling the tunnel

    followingtheinstallationofthepipelineandservices.

    Mixing of grout will take place in a controlled and contained environment

    usingautomatedmixingtankslocatedintheAughooseCompound.Groutsilos,

    locatedadjacent

    to

    the

    mixing

    tanks,

    will

    be

    filled

    with

    dry

    cement

    brought

    in

    bycontainertruck.Thecementwillbeblown intothestoragesilosfromthe

    container truck using a sealed unit and stored there formixing as required

    duringtheworks.

    The mixing operation will involve the grouting mix and water. This is then

    pumped in containerswhich are transferred to the tunnel using the tunnel

    railway.

    Topreventingressofwaterandgrout intotheTBM,brushsealsbetweenthe

    tailskinandtheerectedsegmentsarefilledwithgrease.

  • 8/11/2019 2012 Appendix l Tunneling Operations

    5/7

    ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations

    DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP

    MethodStatement Revision:02 Page4of6

    Demobilisation

    and

    Reinstatement:

    WhentheTBMreachesthereceivingshaftinGlengad,itwillberecoveredand

    the installationof thegaspipeline and services can start. Installationof the

    pipelineandservicesisfromAughoose.

    DemobilisationoftheTBMwillbecarriedoutattheGlengadsite. Tunnelling

    equipment, such as separationplant,bentonite treatmentplant, grout silos,

    etc.attheAughooseCompoundwillbedemobilisedinstagesuponcompletion

    ofthesignificantelementsoftheworks.

    Oncetheonshorepipelineandassociatedserviceshavebeen installed inthe

    tunnelandthetunnelfullygrouted,thestartshaftandrampwillbebackfilled.

    Backfilling

    of

    the

    Tunnel

    &

    Pipeline

    Installation:

    The grout mortar will also be used for filling the tunnel following the

    installationofthepipelineandservices.

    Theequipmentassociatedwiththisbackfillingoperationwillbelocatedatthe

    Aughoosecompoundandthebackfillingoperationwillbecarriedoutfromone

    sideonlybypumpingthebackfillingmixthroughthepreinstalledgrouting.

    EQUIPMENTTunnelboringmachine(TBM) Filterpress

    TBMbackupsystem Supplysystem,feedingpipes/cables

    Tunnelsegments ControlStation

    Trackandtrainsystem Liftingandloadingdevices

    Separationplant Tanks

    Bentonitehandlingunit Gantrycrane

    Bentonite

    silos

    Mortar

    silos

    RESTRICTIONS Tunnelwillbeconstructedunderneath:

    BlacksodBay/Broadhaven pSPA

    GlenamoyBogComplexcSAC

    Noiseandvibrationlimits

    Lightingconstraints

    NonessentialactivitiesmayrequiretobesuspendedattheAughooseCompound

    on Easter Sundays during periods when Mass is taking place at the nearby

    commemorativesite.

  • 8/11/2019 2012 Appendix l Tunneling Operations

    6/7

    ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations

    DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP

    MethodStatement Revision:02 Page5of6

    POTENTIAL

    ENVIRONMENTAL

    IMPACT

    MITIGATION

    Release

    of

    bentonite

    to

    environment

    Thecompositionofslurryisdesignedtosuitthegeotechnicalconditions.

    Bentonitepressureandrateofusagewillbemonitoredconstantly. Inthe

    eventofbentonitereleasethebentoniteoperatingpressurewillbereduced

    immediatelytoreducebentoniteloss.

    Bentonitesensorswillbeinstalledintheexcavationchamber. Thechamber

    canbeseparatedfromtheslurrysystem.

    TheTBMspeedwillbealteredtosuitthegroundconditions.

    Intheunlikelyeventofabentonitereleasethedesignandoperationofthe

    TBM

    will

    limit

    the

    volume

    to

    7m

    3

    .

    Measureswill be implemented atAughoose andGlengad to prevent any

    egressofbentonite intowatercourses leading intothecSAC/pSPA.Ahard

    standingareaforbentonitehandlingplantwillbe located intheAughoose

    Compound. There is a separate drainage system where the runoff is

    collectedandpumpedintoausedbentonitetank.

    During removalof theTBMatGlengad, theshaftwillbepartially flooded.

    This water will be contained within the shaft and removed offsite for

    treatment at an appropriate licensed water treatment facility. Robust

    measureswillbe taken toensurethere isnobentonite releaseduring the

    loading,handlingandtransportoftheTBMinGlengad.

    Noise,vibrationand

    lighting

    disturbance.

    Noise and vibration will be minimised through design, and appropriate

    selectionofplantandequipment.

    Proactivemaintenanceofmachinery.

    Claddingofstationarymachinerysuchasgeneratorsandseparationplant.

    Acousticscreening&fencing.

    Siteand

    mobile

    lighting

    will

    be

    designed

    to

    limit

    light

    spillage.

  • 8/11/2019 2012 Appendix l Tunneling Operations

    7/7

    ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations

    DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP

    MethodStatement Revision:02 Page6of6

    POTENTIAL

    ENVIRONMENTAL

    IMPACT

    MITIGATION

    Disturbance

    to

    birds

    in

    the

    adjacent

    pSPA

    and

    birds

    on

    migration

    Acoustic screening barriers will be installed on the temporary perimeter

    palisadefencing.

    Solidacousticfencingwillbeusedwithinthecompoundtominimisenoise.

    Lighting will be designed to minimise light leakage into the pSPA (light

    intensitynomorethan0.3luxattheshoreline).

    Green (beacon) lightingwillbe installedon tall structuresanduprights to

    reducecollisionrisk.

    Settlementpondswillbecoveredbyasuitablebirddeterrentmaterial.

    Robustsedimentandpollutioncontrolmeasurestopreventimpactonprey

    speciesintheBay(benthicmacrofaunaandfishspecies).

    See LVI, Glengad Compounds and Access RoadMS for details of further

    mitigation.

    Potentialforindirect

    impact

    on

    habitats

    and

    species

    in

    the

    adjacent

    cSAC

    /pSPA

    Robustmeasures (see below andAughoose Compound ConstructionMS)

    willbeimplementedtopreventsedimentationandpollutionoftheadjacent

    Annex I estuarine and interidal habitats in Sruwaddacon Bay and species

    whichdependuponthem,includingsalmon.

    Pollution

    of

    Land/Water/cSACand

    pSPA

    habitats

    &

    species

    due

    spillage

    or

    leaks

    of

    oil/dieselfromplant

    and

    equipment.

    Machineryandplantwillbeinspectedpriortomobilisationtosite.

    Refuellingofplant/machinerywilltakeplaceindesignatedareasonly.

    Spillkitswillbeavailableonsite.

    Releaseofsuspended

    solids

    from

    the

    works

    could

    have

    negative

    impactonwaterquality

    Asurfacewatermanagementsystemwillbeutilised toensure removalof

    suspended solids prior to discharge to receiving waters at an agreed

    location.

    Pumpedwaterwillbesubjecttosedimentcontrolmeasures.

    Earthworks

    may

    disturb

    archaeologicalremains

    A licensed archaeologistwill be on site tomonitor all excavations of the

    tunnelstartandreceptionshafts.

    Intheeventofanarchaeologicalfindthearchaeologistmayhaveworkon

    thesite

    stopped,

    pending

    adecision

    as

    to

    how

    best

    to

    deal

    with

    the

    archaeology by the Department of Arts, Heritage and Gaeltacht Affairs

    (DAHGA)(previouslyassignedtotheDepartmentofEnvironment,Heritage

    andLocalGovernment(DoEHLG).