2012 appendix l tunneling operations
TRANSCRIPT
-
8/11/2019 2012 Appendix l Tunneling Operations
1/7
CORRIBFIELDDEVELOPMENTPROJECT
OnshoreWorksConstructionofTunnel
METHODSTATEMENTRev02
TunnellingOperations
-
8/11/2019 2012 Appendix l Tunneling Operations
2/7
ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations
DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP
MethodStatement Revision:02 Page1of6
SUMMARY
Thisdocumentdescribestheconstructionofthe4.9kmsegmentlinedtunnelinwhichtheCorribOnshore
PipelinebetweenGlenagdandAughoosewillbeinstalled.
PURPOSE A4.9kmsegment linedtunnelwillbeconstructedusingaTunnelBoringMachine
(TBM)betweenAughooseandGlengad.
LOCATION The segment lined tunnelwillbe constructed from the starting shaft located at
Aughoose (approx. Chainage 88.77). From there, the pipeline route traverses
(underneath)theGlenamoyBogComplexcSACandtheBlacksodBay/Broadhaven
pSPA at Sruwaddacon Bay in a northwesterly direction towards Glengad for
approximately 4.9km, where the reception shaft (Chainage 83.88) will be
constructedinthecSAC. Thetunnelwillbeconstructedwithaminimumdepthof
coverof5.5m.
TIMESCALE It isanticipatedthatthetunnellingprocesswilltakeapproximately15monthsto
complete(atanaverageof11m/day).
Thetunnellingconstructionwillbecarriedoutona24hoursaday/7daysaweek
basis.
Otherassociatedworks,suchasmaterialtransportandtunnelarisingsdisposalwill
beexecutedbetweenthehoursof07:00and19:00weekdaysand07:00and16:00
Saturday.
CONSTRUCTION
METHODOLOGY
Thescope
of
works
for
the
construction
of
the
segment
lined
tunnel
can
be
generallydividedintothefollowingworksteps:
Constructionofthe4.9kmtunnelincludingaccessramps,startingshaftand
receptionshaft;
Installation and testing of the 20 inch gas pipeline and services in the
tunnel;and
Groutingofthetunnelandreinstatementoftheshafts.
Furtherdetailsontheconstructionofthestartandreceptionshaftsareprovidedin
othermethodstatements.
Prior to the commencement of tunnelling, the Aughoose compound is
constructedandassociatedutilitysystems,e.g.anappropriatesurfacewater
management system, are made available. A separate method statement
describestheconstructionoftheAughoosecompound.
Plantandequipmentrequiredforthetunnelling,includingtheTBM,arethen
mobilisedtosite.
AllTBMassemblyandmaterialsupplywillbemanagedfromthestartingshaft
inAughoose.
-
8/11/2019 2012 Appendix l Tunneling Operations
3/7
ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations
DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP
MethodStatement Revision:02 Page2of6
Plant
and
Equipment
Themainplantandequipmentrequiredforthetunnellingprocessinclude:
Gantrycrane;
GroutmortarSilos
Slurrytreatmentplant
Bentonitetanksandsilos
Freshwatertank
Waterstoragetanks
Filterpress
Powergenerationunits
Following the installation of all the required plant and the set up of the site
compoundandfunctiontestingthetunnellingprocesswillcommence.
Tunnelconstruction:
The tunnelwillbeconstructedusingaslurryshield tunnellingmethodwhich
involves the drilling/boring of the soil face using a TBM and then installing
precastconcretesegmentsastheTBMprogresses.
ThecuttingwheelatthefrontoftheTBMtunnelsintotheground. TheTBMis
controlledby
the
steering
cylinders
within
the
TBM
which
pushes
the
cutter
headinthedesireddirection.
Powerswitchboards,hydraulicandlogisticunitsareallinstalledneartheTBM
onanumberofbackuptrailers.Thesetrailers(typicallyof810mlength)are
interconnectedandpulledbytheTBMthroughthetunnel.
Concretesegmentsare transportedtothefrontof the tunnelonatrain that
runsontrackswithinthetunnelduringconstruction.Thesetracksareinstalled
inparalleltothetunnellingoperationononeoftheTBMbackuptrailers.
Thestacked
segments
are
transported
through
the
tunnel
to
the
tail
skin
by
a
supplysystemwithtraincarsandcranes. Anerectorunit locatedwithinthe
TBMisusedtopickupthesegmentsfromthetrainanditinstallsthesegments
into the designatedposition. Once installed they arebolted to the already
installedringandsegments.
Concrete segmentswhich are erected inside theback endof the tunnelling
machine(thetailskin)andassembledtoformacompletesegmentringwhich
isconnected,groutedandwheninpositionactsasthetunnellining.
Aftercompletionofonesegmentring,alljackingcylindersareextendedfora
furtheradvance
cycle.
By
using
this
method
of
tunnel
lining,
the
already
built
concretetunnelremainsstationaryandservesasanabutmentfortheadvance
-
8/11/2019 2012 Appendix l Tunneling Operations
4/7
ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations
DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP
MethodStatement Revision:02 Page3of6
oftheTBM. Grout(annulusgrouting) is injected intotheovercutbehindthe
installed segment rings, which is created by the cutting wheel during
excavation.
Slurrylines
for
spoil
transport,
air
duct
for
ventilation,
pressurised
air
supply
andpower/communication cables are installed inside the tunnel to support
thedrillingprocess.
Drilling fluid consisting of a suspension of water and bentonite (bentonite
slurry) is used for lubrication and cooling of the cutting head, removal of
cuttingsandstabilisationofthecuttingface.
Bentoniteslurrysuspensionwillbepumpedthroughthefeedingpipeintothe
TBMworkingchamber. Itismixedwiththeexcavatedsoil/rockandpumped
back through the slurrydischargepipe to the separationplant atAughoose
Compound.The
soil
is
separated
and
the
recycled
bentonite
slurry
suspension
pumpedthroughthetunnelbackintotheTBMworkingchamber.
Theexcavatedmaterialsfromtunnelling(tunnelarisings)isseparatedfromthe
drilling fluid/bentoniteslurrymixtureusingaseparationplantwhereshakers
aredeployed and stockpiled temporarilywithin theAughooseCompound in
designatedarea.
Thesurplusbentoniteslurrywillberemovedanddewatered ina filterpress.
After being treated in the filter press the filter cake is dry enough for
transportation to a licensed waste facility. The Filter Press water will be
monitoredthen
recycled
/reused
on
site,
where
feasible,
or
transported
off
sitetoalicensedwatertreatmentfacility.
MixingofGroutMortar
Groutmortarwillbeusedforgroutingtheannulusofthetunnel(voidsbehind
the segments). The grout mortar will also be used for filling the tunnel
followingtheinstallationofthepipelineandservices.
Mixing of grout will take place in a controlled and contained environment
usingautomatedmixingtankslocatedintheAughooseCompound.Groutsilos,
locatedadjacent
to
the
mixing
tanks,
will
be
filled
with
dry
cement
brought
in
bycontainertruck.Thecementwillbeblown intothestoragesilosfromthe
container truck using a sealed unit and stored there formixing as required
duringtheworks.
The mixing operation will involve the grouting mix and water. This is then
pumped in containerswhich are transferred to the tunnel using the tunnel
railway.
Topreventingressofwaterandgrout intotheTBM,brushsealsbetweenthe
tailskinandtheerectedsegmentsarefilledwithgrease.
-
8/11/2019 2012 Appendix l Tunneling Operations
5/7
ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations
DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP
MethodStatement Revision:02 Page4of6
Demobilisation
and
Reinstatement:
WhentheTBMreachesthereceivingshaftinGlengad,itwillberecoveredand
the installationof thegaspipeline and services can start. Installationof the
pipelineandservicesisfromAughoose.
DemobilisationoftheTBMwillbecarriedoutattheGlengadsite. Tunnelling
equipment, such as separationplant,bentonite treatmentplant, grout silos,
etc.attheAughooseCompoundwillbedemobilisedinstagesuponcompletion
ofthesignificantelementsoftheworks.
Oncetheonshorepipelineandassociatedserviceshavebeen installed inthe
tunnelandthetunnelfullygrouted,thestartshaftandrampwillbebackfilled.
Backfilling
of
the
Tunnel
&
Pipeline
Installation:
The grout mortar will also be used for filling the tunnel following the
installationofthepipelineandservices.
Theequipmentassociatedwiththisbackfillingoperationwillbelocatedatthe
Aughoosecompoundandthebackfillingoperationwillbecarriedoutfromone
sideonlybypumpingthebackfillingmixthroughthepreinstalledgrouting.
EQUIPMENTTunnelboringmachine(TBM) Filterpress
TBMbackupsystem Supplysystem,feedingpipes/cables
Tunnelsegments ControlStation
Trackandtrainsystem Liftingandloadingdevices
Separationplant Tanks
Bentonitehandlingunit Gantrycrane
Bentonite
silos
Mortar
silos
RESTRICTIONS Tunnelwillbeconstructedunderneath:
BlacksodBay/Broadhaven pSPA
GlenamoyBogComplexcSAC
Noiseandvibrationlimits
Lightingconstraints
NonessentialactivitiesmayrequiretobesuspendedattheAughooseCompound
on Easter Sundays during periods when Mass is taking place at the nearby
commemorativesite.
-
8/11/2019 2012 Appendix l Tunneling Operations
6/7
ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations
DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP
MethodStatement Revision:02 Page5of6
POTENTIAL
ENVIRONMENTAL
IMPACT
MITIGATION
Release
of
bentonite
to
environment
Thecompositionofslurryisdesignedtosuitthegeotechnicalconditions.
Bentonitepressureandrateofusagewillbemonitoredconstantly. Inthe
eventofbentonitereleasethebentoniteoperatingpressurewillbereduced
immediatelytoreducebentoniteloss.
Bentonitesensorswillbeinstalledintheexcavationchamber. Thechamber
canbeseparatedfromtheslurrysystem.
TheTBMspeedwillbealteredtosuitthegroundconditions.
Intheunlikelyeventofabentonitereleasethedesignandoperationofthe
TBM
will
limit
the
volume
to
7m
3
.
Measureswill be implemented atAughoose andGlengad to prevent any
egressofbentonite intowatercourses leading intothecSAC/pSPA.Ahard
standingareaforbentonitehandlingplantwillbe located intheAughoose
Compound. There is a separate drainage system where the runoff is
collectedandpumpedintoausedbentonitetank.
During removalof theTBMatGlengad, theshaftwillbepartially flooded.
This water will be contained within the shaft and removed offsite for
treatment at an appropriate licensed water treatment facility. Robust
measureswillbe taken toensurethere isnobentonite releaseduring the
loading,handlingandtransportoftheTBMinGlengad.
Noise,vibrationand
lighting
disturbance.
Noise and vibration will be minimised through design, and appropriate
selectionofplantandequipment.
Proactivemaintenanceofmachinery.
Claddingofstationarymachinerysuchasgeneratorsandseparationplant.
Acousticscreening&fencing.
Siteand
mobile
lighting
will
be
designed
to
limit
light
spillage.
-
8/11/2019 2012 Appendix l Tunneling Operations
7/7
ShellExplorationandProductionIrelandLtd. Title: TunnellingOperations
DraftEnvironmental ManagementPlan DocumentNo: COR14OP0000_SEPILEMP
MethodStatement Revision:02 Page6of6
POTENTIAL
ENVIRONMENTAL
IMPACT
MITIGATION
Disturbance
to
birds
in
the
adjacent
pSPA
and
birds
on
migration
Acoustic screening barriers will be installed on the temporary perimeter
palisadefencing.
Solidacousticfencingwillbeusedwithinthecompoundtominimisenoise.
Lighting will be designed to minimise light leakage into the pSPA (light
intensitynomorethan0.3luxattheshoreline).
Green (beacon) lightingwillbe installedon tall structuresanduprights to
reducecollisionrisk.
Settlementpondswillbecoveredbyasuitablebirddeterrentmaterial.
Robustsedimentandpollutioncontrolmeasurestopreventimpactonprey
speciesintheBay(benthicmacrofaunaandfishspecies).
See LVI, Glengad Compounds and Access RoadMS for details of further
mitigation.
Potentialforindirect
impact
on
habitats
and
species
in
the
adjacent
cSAC
/pSPA
Robustmeasures (see below andAughoose Compound ConstructionMS)
willbeimplementedtopreventsedimentationandpollutionoftheadjacent
Annex I estuarine and interidal habitats in Sruwaddacon Bay and species
whichdependuponthem,includingsalmon.
Pollution
of
Land/Water/cSACand
pSPA
habitats
&
species
due
spillage
or
leaks
of
oil/dieselfromplant
and
equipment.
Machineryandplantwillbeinspectedpriortomobilisationtosite.
Refuellingofplant/machinerywilltakeplaceindesignatedareasonly.
Spillkitswillbeavailableonsite.
Releaseofsuspended
solids
from
the
works
could
have
negative
impactonwaterquality
Asurfacewatermanagementsystemwillbeutilised toensure removalof
suspended solids prior to discharge to receiving waters at an agreed
location.
Pumpedwaterwillbesubjecttosedimentcontrolmeasures.
Earthworks
may
disturb
archaeologicalremains
A licensed archaeologistwill be on site tomonitor all excavations of the
tunnelstartandreceptionshafts.
Intheeventofanarchaeologicalfindthearchaeologistmayhaveworkon
thesite
stopped,
pending
adecision
as
to
how
best
to
deal
with
the
archaeology by the Department of Arts, Heritage and Gaeltacht Affairs
(DAHGA)(previouslyassignedtotheDepartmentofEnvironment,Heritage
andLocalGovernment(DoEHLG).