2012-2013 fund - all entry
TRANSCRIPT
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE1 CONSTRUCTION OF
BLOOD BANK IN KHATRA
S.D. HOSPITAL COMPLEX
EXECUTIVE ENGINEER,
PUBLIC WORKS
DEPARTMENT, BANKURA
DIVISION-II AND EXECUTIVE
ENGINEER, PUBLIC WORKS
DEPARTMENT, MIDNAPORE
ELECTRICAL DIVISION
62/PM(F)/P/
1B-68/2012
03-05-2012 75.86656 75.86656 31-05-2013 CIVIL WORK
COMPLETE;
PROBLEM IN
CONSTRUCTIO
N OF
PARTITION
WALL
2 DEVELOPMENT AND
REPAIRING OF DAMAGED
CONDITION OF SCHOOL
BUILDINGS WITH
ELECTRIFICATION OF
LOUPARA HIGH SCHOOL
UNDER RAIPUR BLOCK
BLOCK DEVELOPMENT
OFFICER, RAIPUR BLOCK
85/PM(F)/P/
1B-71/2012
& 321
09-05-2012 &
26-09-2012
4.50000 4.50000 100% 15-12-2012 4.50000 COMPLETE
3.1 RENOVATION OF CANAL
FOR RESTORATION OF
IRRIGATION POTENTIAL IN
BETWEEN CH. 55.00 & CH.
92.00 INCLUDING CANAL
STRUCTURES AT CH. 1.50
& CH. 63.00 UNDER ONDA
BLOCK
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
98/PM(F)/P/
1B-67/2012
&
173/PM(F)/P
/1B-67/2012
DATED 13-
07-2012
31-05-2012 26.75799 26.75799 100% COMPLETE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
76.26716
PUA DEPT.'S SANCTION
ORDER
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
3.2 RENOVATION OF CANAL
FOR RESTORATION OF
IRRIGATION POTENTIAL IN
BETWEEN CH. 92.00 & CH.
120.00 INCLUDING CANAL
STRUCTURES AT CH.
101.00 UNDER ONDA
BLOCK
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
98/PM(F)/P/
1B-67/2012
&
173/PM(F)/P
/1B-67/2012
DATED 13-
07-2013
31-05-2012 25.76252 25.76252 100% COMPLETE
3.3 RENOVATION OF CANAL
FOR RESTORATION OF
IRRIGATION POTENTIAL IN
BETWEEN CH. 204.10 &
CH. 232.00 INCLUDING
CANAL STRUCTURES AT
CH. 198.00 UNDER ONDA
BLOCK
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
98/PM(F)/P/
1B-67/2012
&
173/PM(F)/P
/1B-67/2012
DATED 13-
07-2014
31-05-2012 27.14059 27.14059 100% COMPLETE
4 228 UNITS OF
PISICULTURE SCHEME
WITHIN 14 BLOCKS OF
BANKURA AND KHATRA
SUB-DIVISION
ASSISTANT DIRECTOR OF
FISHERIES, BANKURA
105/PM(F)/P
/1B-79/2012
05-06-2012 11.85600 11.85600 100% 11.85600 COMPLETE
76.26716
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
5 EXCAVATION OF WATER
HARVESTING TANK,
BOULDER PITCHING WORK
WITH TOE WALL,
CONSTRUCTION OF GHAT,
PLANTATION AND ECO-
DEVELOPMENT AT PUP
ADMINISTRATIVE
BUILDING PREMISES
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
106/PM(F)/P
/1B-88/2012
05-06-2012 55.12595 36.15924 85% 30-09-2013 36.15924 PLANTATION,
BORING
COMPLETE,
TANK AND
ALLIED WORK
TO BE
COMPLETED
VERY SHORTLY
6.1 SINKING OF MEDIUM
DUTY TUBE-WELL FOR
IRRIGATION IN MURAKATI
(KALARA) VILLAGE,
SALTORA GP, TALDANGRA
PS
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
110/PM(F)/P
/1B-77/2012
07-06-2012 3.03000 3.03000 100% 28-02-2013 COMPLETE
6.2 SINKING OF MEDIUM
DUTY TUBE-WELL FOR
IRRIGATION IN SATBAR
VILLAGE, SALTORA GP,
TALDANGRA PS
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
110/PM(F)/P
/1B-77/2012
07-06-2012 3.03000 3.03000 SITE NOT
AVAILABLE
6.3 SINKING OF MEDIUM
DUTY TUBE-WELL FOR
IRRIGATION IN KARANDIHI
VILLAGE, SALTORA GP,
TALDANGRA PS
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
110/PM(F)/P
/1B-77/2012
07-06-2012 3.03000 3.03000 SITE NOT
AVAILABLE
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
7 CONSTRUCTION OF SC/ST
GIRLS HOSTEL BUILDING
OF BIRSHA MUNDA
MEMORIAL COLLEGE,
PIRRA, RAIPUR BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
RAIPUR
157/PM(F)/P
/1B-93/2012
06-07-2012 92.27288 68.30214 80% 30-05-2013 68.30214 WORK IN
PROGRESS
8 CONSTRUCTION OF
BOUNDARY WALL AT
P.R.M.S.
MAHAVIDYALAYA,
BARAGARI, JAMBONI
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
SARENGA
160/PM(F)/P
/1B-
130/2012
11-07-2012 48.84000 15-06-2013 WORK
STARTED
9 BORING OF A 200 x 150
MM. DIA TUBE-WELL OF
DEPTH 200 MT. AT
BHARAT SEVASHRAM
SANGHA, KENDUADIHI
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
161/PM(F)/P
/1B-
133/2012
11-07-2012 3.76948 1.77078 100% 15-04-2013 1.77078 COMPLETE
10 SINKING OF A DEEP TUBE-
WELL OF 200 MT. DEPTH
AND INSTALLATION OF
SUBMERSIBLE PUMP SET
AND NECESSARY WATER
DISTRIBUTION LINE OF
AMADER HASPATAL
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
171/PM(F)/P
/1B-
52/2011(PT.-
I)
13-07-2012 5.00819 3.51613 100% 15-04-2013 3.51613 COMPLETE
11 CONSTRUCTION OF
BRIDGE AT EKCHALA
(MARAKANALI),
GANGAJALGHATI P.S.
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
178/PM(F)/P
/1B-
116/2012
17-07-2012 25.00000 21.67155 85% 30-09-2013 21.67155 WORK IN
PROGRESS
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
12.1 INFRASTRUCTURE
DEVELOPMENT WORKS AT
BANSIDI HIGH SCHOOL,
INDPUR
BLOCK DEVELOPMENT
OFFICER, INDPUR BLOCK
179/PM(F)/P
/1B-
150/2012
18-07-2012 20.77653 REVISED
ESTIMATE AS
SUBMITTED BY
BDO VETTED
FROM PUP ON
29/07/2013
12.2 REPAIRING AND
RENOVATION WORK OF
SCHOOL BUILDING AT
CHHATNA CHANDIDAS
VIDYAPITH, CHHATNA
BLOCK DEVELOPMENT
OFFICER, CHHATNA BLOCK
179/PM(F)/P
/1B-
150/2012
18-07-2012 14.48700 13.75664 100% 10-05-2013 13.75664 COMPLETE
13.1 CONSTRUCTION OF
CONCRETE ROAD FROM
BIKNA UPOR PARA TO
NAMO PARA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
181/PM(F)/P
/1B-20/2012
23-07-2012 16.45132 100% 30-04-2013 COMPLETE
13.2 CONSTRUCTION OF BRICK
WORK DRAIN FROM
BIKNA UPOR PARA TO
NAMO PARA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
181/PM(F)/P
/1B-20/2012
23-07-2012 10.18784 100% 30-06-2013 COMPLETE
13.3 CONSTRUCTION OF
CONCRETE ROAD FROM
RAMSAGAR BUS STAND
TO RAMSAGAR RLY.
STATION
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
181/PM(F)/P
/1B-20/2012
23-07-2012 23.58344 COMPLETE
13.4 CONSTRUCTION OF BRICK
WORK DRAIN FROM
RAMSAGAR BUS STAND
TO RAMSAGAR RLY.
STATION
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
181/PM(F)/P
/1B-20/2012
23-07-2012 20.26142 WORK IN
PROGRESS
36.16744 36.1674480% 30-09-2013
23.30520 23.30520
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
14 CONSTRUCTION OF 15KM
BITUMINOUS ROAD FROM
DHANJHAR MORE TO
KARAPARA (BANSIDIHA)
AT RANIBANDH
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
187/PM(F)/P
/1B-
143/2012
25-07-2012 170.00000 170.00000 100% 31-07-2013 170.00000 COMPLETE
15 CONSTRUCTION OF ROAD
FROM RATANPUR TO
KRISHNAGAR AT ONDA
BLOCK
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
189/PM(F)/P
/1B-
144/2012
25-07-2012 117.61524 117.61524 45% 30-11-2013 117.36727 WORK IN
PROGRESS
16 CULTIVATION OF KHARIFF
ONION IN BANKURA
DISTRICT
DIRECTOR OF RESEARCH,
BIDHAN CHANDRA KRISHI
VISWAVIDYALAYA, P.O. -
KALYANI, DIST. - NADIA
190/PM(F)/P
/1B-
148/2012
25-07-2012 9.00000 9.00000 100% 2.16169 COMPLETE
17.1 ROY BUNDH SURFACE
FLOW MINOR IRRIGATION
SCHEME, BHABRIGORA
MOUZA, INDPUR BLOCK
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 80.80050 80.80050 100% 26-04-2013 COMPLETE
17.2 PONDA BUNDH SURFACE
FLOW MINOR IRRIGATION
SCHEME, RADHANAGAR
MOUZA, INDPUR BLOCK
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 56.01009 56.01009 100% 26-04-2013 COMPLETE
17.3 UPAR BUNDH SURFACE
FLOW MINOR IRRIGATION
SCHEME, SAYERDI
MOUZA, INDPUR BLOCK
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 27.27898 27.27898 100% 26-04-2013 COMPLETE
13.49815
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
17.4 KAMALYA BELGORIA
SURFACE FLOW MINOR
IRRIGATION SCHEME,
KAJALKURA MOUZA,
INDPUR BLOCK
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 21.81970 21.81970 100% 26-04-2013 COMPLETE
17.5 NATUN BUNDH SURFACE
FLOW MINOR IRRIGATION
SCHEME, LEDAPALASH
MOUZA, INDPUR BLOCK
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 35.54999 35.54999 100% 01-01-2013 COMPLETE
17.6 LAYEK BUNDH SURFACE
FLOW MINOR IRRIGATION
SCHEME, KAJALKURA
MOUZA, INDPUR BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 43.58450 31.82655 100% 30-06-2013 31.82655 COMPLETE
17.7 ARALDIHI SCHOOL BUNDH
SURFACE FLOW MINOR
IRRIGATION SCHEME,
ARALDIHI MOUZA,
INDPUR BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 20.11056 11.76998 100% 30-06-2013 11.76998 COMPLETE
17.8 HURHURA BUNDH
SURFACE FLOW MINOR
IRRIGATION SCHEME,
MADHABPUR MOUZA,
GANGAJALGHATI BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 35.27534 25.03379 100% 30-06-2013 25.03379 COMPLETE
13.49815
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
17.9 CONSTRUCTION OF CHECK
DAM AND
AUGMENTATION OF
RESERVOIR, MAHESNA
MOUZA, CHHATNA BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
191/PM(F)/P
/1B-
137/2012
25-07-2012 38.72656 65% 30-11-2013 WORK IN
PROGRESS
18.1 BANER BUNDH MINOR
IRRIGATION SCHEME IN
CHHATNA BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
192/PM(F)/P
/1B-
149/2012
26-07-2012 47.69337 25.98405 100% 30-05-2013 25.98405 COMPLETE
18.2 RESHER PUKUR MINOR
IRRIGATION SCHEME IN
CHHATNA BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
192/PM(F)/P
/1B-
149/2012
26-07-2012 37.88384 21.49535 100% 30-05-2013 21.49535 COMPLETE
18.3 DHOBAGORA SOLER
BUNDH IN INDPUR BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
192/PM(F)/P
/1B-
149/2012
26-07-2012 61.77828 35.49425 90% 30-11-2013 35.49425 WORK IN
PROGRESS
18.4 BARABUNDH MINOR
IRRIGATION SCHEME IN
INDPUR BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
192/PM(F)/P
/1B-
149/2012
26-07-2012 29.12293 13.55864 100% 30-05-2013 13.55864 COMPLETE
19 CONSTRUCTION OF A
VOCATIONAL TRAINING
CENTRE AND HOSTEL
BUILDING AT AMADER
HASPATAL, CHHATNA
FOUNDATION FOR HEALTH
ACTION
226/PM(F)/P
/1B-52/2011
16-08-2012 60.00607 60.00607 100% 30-06-2013 39.49217 COMPLETE
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
20 CONSTRUCTION OF
BITUMINOUS ROAD FROM
KHATRA KANGSABATI
SISHU VIDYALAYA TO
BANTILLA VILLAGE,
KHATRA BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
284/PM(F)/P
/1B-
178/2012
07-09-2012 72.61834 27.30297 85% 30-09-2013 27.30297 WORK IN
PROGRESS
21 CONSTRUCTION OF
INCOMPLETE TOURIST
COTTAGE AND
INCOMPLETE TOURIST
HUT AT ENDOGENOUS
TOURISM PROJECT,
BARAGHUTU,
MUKUTMANIPUR, KHATRA
PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH EO,
KHATRA
292/PM(F)/P
/1B-
187/2012
12-09-2012 19.63154 10.41345 60% 10.41345 WORK IN
PROGRESS
22.1 CEMENT CONCRETE ROAD
AT PALAJURIA VILLAGE
FROM ASTHIR BUNDH TO
EXISTING CONCRETE
ROAD, GANGAJALGHATI
PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
304/PM(F)/P
/1B-
116/2012
(PT.-I)
17-09-2012 15.68943 15.55921 100% 15-05-2013 15.55921 COMPLETE
22.2 CEMENT CONCRETE ROAD
AT RAJARAMPUR VILLAGE,
GANGAJALGHATI PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
304/PM(F)/P
/1B-
116/2012
(PT.-I)
17-09-2012 22.33824 13.55160 100% 15-05-2013 13.55160 COMPLETE
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
22.3 IMPROVEMENT OF
MORRUM ROAD FROM
JAMBEDIA JORE TO
VIRINGI MORE VIA VIRINGI
VILLAGE, GANGAJALGHATI
PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
304/PM(F)/P
/1B-
116/2012
(PT.-I)
17-09-2012 23.89221 50% 31-10-2013 WORK IN
PROGRESS
22.4 IMPROVEMENT OF
MORRUM ROAD FROM
EKCHALA MORE TO
MORAKANALI MORE VIA
EKCHALA VILLAGE,
GANGAJALGHATI PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
304/PM(F)/P
/1B-
116/2012
(PT.-I)
17-09-2012 24.37135 9.56597 80% 30-09-2013 9.56597 WORK IN
PROGRESS
23 CONSTRUCTION OF
BOUNDARY WALL AT
VIVEKANANDA SIKSHA
MANDIR (JR. HIGH
SCHOOL) AT MOLEBONA,
BANKURA-I BLOCK
SCHOOL AUTHORITY,
VIVEKANANDA SIKSHA
MANDIR (JR. HIGH SCHOOL)
313/PM(F)/P
/1B-
186/2012
24-09-2012 25.97403 25.97403 100% 20-04-2013 25.97403 COMPLETE
24 DISEMINATION OF AGRO
TECHNIQUES FOR
GROWING AND
PROCESSING OF
TURMERIC IN NON-
TRADITIONAL AREAS OF
PASCHIMANCHAL FOR
LIVELIHOOD
DIRECTOR OF RESEARCH,
BIDHAN CHANDRA KRISHI
VISWAVIDYALAYA, P.O. -
KALYANI, DIST. - NADIA
322/PM(F)/P
/1B-
188/2012
26-09-2012 19.50000 19.50000 6.96604 ONGOING,
PROJECT HAS 3
YRS. DURATION
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
25.1 CONSTRUCTION OF
BOUNDARY WALL AT
BARIKUL UDAY BHARATI
HIGH SCHOOL (HS),
BARIKUL
BLOCK DEVELOPMENT
OFFICER, RANIBUNDH
BLOCK
323/PM(F)/P
/1B-
193/2012
27-09-2012 21.23786 20.21763 100% 30-04-2013 20.21763 COMPLETE
25.2 UPGRADATION TO
BITUMINOUS ROAD FROM
AHANDA PIYARSEE GIRLS
HIGH SCHOOL TO NH-60A,
INDPUR PS
BLOCK DEVELOPMENT
OFFICER, INDPUR BLOCK
323/PM(F)/P
/1B-
193/2012
27-09-2012 50.95586 17.77060 25% 31-05-2013 16.78116 WORK IN
PROGRESS
26.1 RENOVATION OF CANAL
IN THE FORM OF
RESTORING & LINING IN
BETWEEN CH. 126.70 AND
CH. 160.00 OF DY-4 OF
B.B.C. FOR RESTORATION
OF DISTRESSED
IRRIGATION POTENTIAL
WITHIN ONDA BLOCK,
DIST. BANKURA UNDER
BANKURA IRRIGATION
DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
342/PM(F)/P
/1B-
167/2012
09-10-2012 31.75000 31.75000 100% 30-04-2013 COMPLETE120.94868
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
26.2 RENOVATION OF CANAL
IN THE FORM OF
RESECTIONING & LINING
IN BETWEEN CH. 160.00
AND CH. 198.80 OF DY-4
OF B.B.C. FOR
RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL WITHIN ONDA
BLOCK, DIST. BANKURA
UNDER BANKURA
IRRIGATION DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
342/PM(F)/P
/1B-
167/2012
09-10-2012 38.95000 38.95000 100% 30-04-2013 COMPLETE
26.3 RENOVATION OF CANAL
IN THE FORM OF
RESECTIONING & LINING
IN BETWEEN CH.198.80
AND CH. 257.50 OF DY-4
OF B.B.C. FOR
RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL WITHIN ONDA
BLOCK, DIST. BANKURA
UNDER BANKURA
IRRIGATION DIVISION.
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
342/PM(F)/P
/1B-
167/2012
09-10-2012 49.98000 49.98000 85% 31-12-2013 WORK IN
PROGRESS
120.94868
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
26.4 RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL IN THE FORM
OF RE-SECTIONING OF
CANAL INCLUDING
CEMENT CONCRETE
LINING IN BETWEEN CH.
836.00 & CH 980.22 OF
SIMLAPAL BRANCH CANAL
WITHIN SIMLAPAL BLOCK,
DIST. BANKURA UNDER
BANKURA IRRIGATION
DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
342/PM(F)/P
/1B-
167/2012
09-10-2012 49.91000 49.91000 30% 31-12-2013 WORK IN
PROGRESS
26.5 RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL IN THE FORM
OF RE-SECTIONING OF
CANAL INCLUDING
CEMENT CONCRETE
LINING & REPAIR OF
STRUCTURES IN
DISTRIBUTORY CANAL NO.
15, 16, 17, 18 OF
SIMLAPAL BRANCH CANAL
WITHIN SIMLAPAL BLOCK,
DIST. BANKURA UNDER
BANKURA IRRIGATION
DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
342/PM(F)/P
/1B-
167/2012
09-10-2012 49.89000 49.89000 70% 31-12-2013 WORK IN
PROGRESS
120.94868
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
26.6 RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL IN THE FORM
OF CANAL INCLUDING
CEMENT CONCRETE
LINING & REPAIR OF
STRUCTURES IN
DISTRIBUTARY CANAL NO.
13 OF SIMLAPAL BRANCH
CANAL WITHIN SIMLAPAL
BLOCK, DIST. BANKURA
UNDER BANKURA
IRRIGATION DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
342/PM(F)/P
/1B-
167/2012
09-10-2012 31.85000 31.85000 70% 31-12-2013 WORK IN
PROGRESS
27.1 WORK OF SANITATION AT
AMDANGA HOSTEL,
SIMLAPAL BLOCK
SECRETARY, YUGACHARYA
VIVEKANANDA SEVA SAMITY
362/PM(F)/P
/1B-
217/2012
30-10-2012 2.99893 2.99893 100% 30-06-2013 2.99893 COMPLETE
27.2 SINKING OF SUBMERSIBLE
PUMP AND PIPELINE AT
AMDANGA HOSTEL,
SIMLAPAL BLOCK
SECRETARY, YUGACHARYA
VIVEKANANDA SEVA SAMITY
362/PM(F)/P
/1B-
217/2012
30-10-2012 2.81251 2.81251 100% 30-06-2013 2.81251 COMPLETE
120.94868
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
28 COMPLETION OF
DEVELOPMENT OF TRIBAL
TANK ADJUNCTION TO
SUSUNIA HILL INCLUDING
BOATING CLUB AND
PISICULTURE, CHHATNA
BLOCK
BLOCK DEVELOPMENT
OFFICER, CHHATNA BLOCK
366/PM(F)/P
/1B-
219/2012
06-11-2012 57.50786 27.07305 60% 30-06-2013 27.07305 TANK
EXCAVATION IS
IN PROGRESS
29.1 CONSTRUCTION OF
BOUNDARY WALL AT
BHARAT SEVASHRAM
SANGHA, KHATRA PS
SECRETARY, BHARAT
SEVASHRAM SANGHA,
KHATRA
375/PM(F)/P
/1B-
231/2012
20-11-2012 21.07423 21.07423 100% 21.07423 COMPLETE
29.2 CONSTRUCTION OF
FENCING AT BHARAT
SEVASHRAM SANGHA,
KHATRA PS
SECRETARY, BHARAT
SEVASHRAM SANGHA,
KHATRA
375/PM(F)/P
/1B-
231/2012
20-11-2012 5.25124 5.25124 100% 5.25124 COMPLETE
30 CONSTRUCTION OF
HOSTEL BUILDING,
KITCHEN STORE, DINING
AND WATER CLOSET BATH
OF SALDAHA JUNIOR HIGH
SCHOOL, SALDAHA
VILLAGE, TALDANGRA
BLOCK
SCHOOL AUTHORITY,
SALDAHA JUNIOR HIGH
SCHOOL
377/PM(F)/P
/1B-
186/2012
21-11-2012 14.39078 14.39078 100% 14.39078 COMPLETE
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
31 CONSTRUCTION OF
BOUNDARY WALL OF
JYOTI PRATIBANDHI
PUNARBASAN KENDRA,
BANKURA (SADAR) SUB-
DIVISION
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
378/PM(F)/P
/1B-
227/2012
21-11-2012 18.78989 18.21910 100% 31-05-2013 18.21910 COMPLETE
32 RE-EXCAVATION AND
CONSTRUCTION OF
BATHING GHAT, GUARD
WALL ETC. OF BHARAT
SEVASHRAM SANGHA
POND, KHATRA BLOCK
SECRETARY, BHARAT
SEVASHRAM SANGHA,
KHATRA
379/PM(F)/P
/1B-
216/2012
21-11-2012 23.57070 23.57070 100% 31-05-2013 23.57070 COMPLETE
33 CONSTRUCTION OF
BOUNDARY WALL AT
PAIRASOLE DUBURIA
JUNIOR HIGH SCHOOL,
MEJIA BLOCK
SCHOOL AUTHORITY,
PAIRASOLE DUBURIA
JUNIOR HIGH SCHOOL
387/PM(F)/P
/1B-
223/2012
23-11-2012 10.26511 10.26511 50% 5.05142 WORK IN
PROGRESS
34.1 CONSTRUCTION OF SIDE
DRAIN FROM
PANCHMURA SABRAKONE
ROAD TO PANCHMURA
KUMARPARA, TALDANGRA
BLOCK
EXECUTIVE OFFICER,
TALDANGRA PANCHAYAT
SAMITY
402/PM(F)/P
/1B-
189/2012
05-12-2012 22.64636 22.64636 50% 31-05-2013 10.00000 WORK IN
PROGRESS
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
34.2 CONSTRUCTION OF PCC
ROAD FROM PANCHMURA
SABRAKONE ROAD TO
PANCHMURA
KUMARPARA, TALDANGRA
BLOCK
EXECUTIVE OFFICER,
TALDANGRA PANCHAYAT
SAMITY
402/PM(F)/P
/1B-
189/2012
05-12-2012 24.86973 24.86973 100% 23.20588 COMPLETE
34.3 CONSTRUCTION OF PCC
ROAD OVER EXISTING
VILLAGE ROAD AT
PANCHMURA
KUMARPARA, TALDANGRA
BLOCK
EXECUTIVE OFFICER,
TALDANGRA PANCHAYAT
SAMITY
402/PM(F)/P
/1B-
189/2012
05-12-2012 12.49113 12.49113 100% 31-05-2013 11.86479 COMPLETE
35 RE-EXCAVATION OF NAGRI
SAHEB BUNDH, KHATRA
P.S.
EXECUTIVE OFFICER,
KHATRA PANCHAYAT
SAMITY
410/PM(F)/P
/1B-
235/2012
11-12-2012 37.55526 37.55526 100% 30-04-2013 37.37119 COMPLETE
36 CONSTRUCTION OF
CONCRETE ROAD FROM
KARAPARA CHOWMATHA
TO NAMOPARA IN
PURUSHOTTAMPUR
VILLAGE,
PURUSHOTTAMPUR
MAUZA, INDPUR BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
415/PM(F)/P
/1B-
238/2012
13-12-2012 37.12752 18.76838 50% 30-09-2013 18.76838 WORK IN
PROGRESS
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
37 CONSTRUCTION OF 3 NOS.
OF COTTAGE AND ALLIED
WORKS FOR COMPLETION
OF MURUTHBAHA ECO
PARK AT SUSUNIA,
BANKURA
BLOCK DEVELOPMENT
OFFICER, CHHATNA BLOCK
434/PM(F)/P
/1B-
192/2012
20-12-2012 58.10722 17.58357 30% 30-06-2013 17.58357 CONST. OF
COTTAGE
RUNNING
UPTO PLINTH
LEVEL
38 CONSTRUCTION OF EXTRA
FOUNDATION FOR
ADDITIONAL CLASSROOMS
ON 1ST FLOOR OF
PUNISOLE NASRUL ULLOM
SIDDQUIA M.S.K. (SR.
MADRASAH TYPE), ONDA
PS
EXECUTIVE OFFICER, ONDA
PANCHAYAT SAMITY
437/PM(F)/P
/1B-
254/2012
21-12-2012 7.35000 7.35000 NO
INFORMATION
RECEIVED
39 DEVELOPMENT OF
TECHNOLOGY FOR
PRODUCTION OF WINE
GRAPES IN DROUGHT
PRONE AREA OF BANKURA
DISTRICT (TOTAL 41.24000
LAC)
BIDHAN CHANDRA KRISHI
VISWAVIDYALAYA,
MOHANPUR, NADIA
439/PM(F)/P
/1B-
236/2012
24-12-2012 16.30400 16.30400 40% PROJECT IS
ONGOING
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
40.1 RENOVATION OF CANAL
IN THE FORM OF
RESECTIONING & LINING
IN BETWEEN CH. 258.09
AND CH. 286.112 OF DY-4
OF B.B.C. FOR
RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL WITHIN ONDA
BLOCK, DIST. – BANKURA
UNDER BANKURA
IRRIGATION DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
01/PM(F)/P/
1B-67/2012
04-01-2013 32.78000 32.78000 15% 31-12-2013 WORK IN
PROGRESS
40.2 RENOVATION OF CANAL
IN THE FORM OF
RESECTIONING & LINING
IN BETWEEN CH. 287.506
AND CH. 323.936 OF DY-4
OF B.B.C. FOR
RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL WITHIN ONDA
BLOCK, DIST. – BANKURA
UNDER BANKURA
IRIGATION DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
01/PM(F)/P/
1B-67/2012
04-01-2013 44.89000 44.89000 15% 31-12-2013 WORK IN
PROGRESS
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
40.3 RENOVATION OF CANAL
IN THE FORM OF
RESECTIONING & LINING
IN BETWEEN CH. 324.609
AND CH. 368.00 OF DY-4
OF B.B.C. FOR
RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL WITHIN ONDA
BLOCK, DIST. – BANKURA
UNDER BANKURA
IRRIGATION DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
01/PM(F)/P/
1B-67/2012
04-01-2013 49.98000 49.98000 15% 31-12-2013 WORK IN
PROGRESS
40.4 RENOVATION OF CANAL
IN THE FORM OF
RESECTIONING & LINING
IN BETWEEN CH. 368.886
AND CH. 411.00 OF DY-4
OF B.B.C. FOR
RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL WITHIN ONDA
BLOCK, DIST. – BANKURA
UNDER BANKURA
IRRIGATION DIVISION
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION, 03242-254934
01/PM(F)/P/
1B-67/2012
04-01-2013 49.20000 49.20000 15% 15-07-2013 WORK IN
PROGRESS
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
41.1 RESTORATION OF LOST
IRRIGATION POTENTIAL BY
M/R TO CAST IN SITU
CEMENT CONCRETE
LINING IN BETWEEN CH.
14.00 TO CH. 18.00, CH.
38.00 TO CH. 42.00 ETC.
OF DY-03 OF R.M.B.C.,
MUKUTMONIPUR,
KHATRA BLOCK
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION - II, KHATRA,
BANKURA
02/PM(F)/P/
1B-188/2012
04-01-2013 23.82127 23.82127 100% 30-06-2013 COMPLETE
41.2 IMPROVEMENT OF
IRRIGATION POTENTIAL
AND CANAL SYSTEM BY
RESECTIONING &
CONSTRUCTION OF
CONCRETE LINING FROM
CH. 344.00 TO CH. 359.00
OF MR-3 OF DY-08 OF
R.M.B.C. WITHIN RAIPUR
BLOCK
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION - II, KHATRA,
BANKURA
02/PM(F)/P/
1B-188/2012
04-01-2013 24.23655 24.23655 100% COMPLETE
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
41.3 IMPROVEMENT OF
IRRIGATION POTENTIAL
AND CANAL SYSTEM BY
RESECTIONING &
CONSTRUCTION OF
CONCRETE LINING FROM
CH. 328.00 TO CH.343.00
OF MR-3 OF DY-8 OF
R.M.B.C. WITHIN RAIPUR
BLOCK
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION - II, KHATRA,
BANKURA
02/PM(F)/P/
1B-188/2012
04-01-2013 24.37774 24.37774 100% COMPLETE
41.4 RESTORATION OF LOST
IRRIGATION POTENTIAL OF
DY-06 OF K.M.C.(U) FROM
CH. 128.00 TO CH.132.0O
AND 135.00 TO CH. 138.00
WITHIN SIMLAPAL BLOCK
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION - II, KHATRA,
BANKURA
02/PM(F)/P/
1B-188/2012
04-01-2013 7.72585 7.72585 100% COMPLETE
41.5 RESTORATION OF LOST
IRRIGATION POTENTIAL OF
DY-08 OF S.M.C.(U) FROM
CH. 288.00 TO CH. 231.50,
CH. 233.50 TO CH. 238.50
ETC. WITHIN KHATRA
BLOCK
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION - II, KHATRA,
BANKURA
02/PM(F)/P/
1B-188/2012
04-01-2013 10.01345 10.01345 85% 31-12-2013 WORK IN
PROGRESS
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
41.6 RESTORATION OF LOST
IRRIGATION POTENTIAL OF
DY-08 OF S.M.C.(U) FROM
CH. 88.00 TO CH. 207.00
WITHIN KHATRA BLOCK
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION - II, KHATRA,
BANKURA
02/PM(F)/P/
1B-188/2012
04-01-2013 10.16305 10.16305 85% 31-12-2013 WORK IN
PROGRESS
42.1 IMPROVEMENT OF RIDING
QUALITY OF BANKURA-
SALTORA ROAD FROM
18.60 KMP TO 19.20 KMP
(KHARBONA BAZAR) IN
THE DISTRICT OF
BANKURA
EXECUTIVE ENGINEER, PWD,
BANKURA DIVISION
13/PM(F)/P/
1B-247/2012
24-01-2013 18.13512 36.27023
42.2 IMPROVEMENT OF RIDING
QUALITY OF BANKURA-
SALTORA ROAD FROM
12.31 KMP TO 14.20 KMP
(CHHATNA BAZAR) IN THE
DISTRICT OF BANKURA
EXECUTIVE ENGINEER, PWD,
BANKURA DIVISION
13/PM(F)/P/
1B-247/2012
24-01-2013 40.67724 81.35448
43.1 CONSTRUCTION OF
LIBRARY BUILDING AT
RAMCHANDRA TARUN
PALLY, MEJIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
19/PM(F)/P/
1B-253/2012
24-01-2013 13.38992 9.51356 60% 30-11-2013 9.51356 WORK IN
PROGRESS
*FULL
AMOUNT
RELEASED BY
MISTAKE, BUT
AS OTHER
SOURCE OF
FUND
RECEIVED BY
EE, PWD
ENTIRE
AMOUNT WILL
BE REFUNDED
TO PUP
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
43.2 CONSTRUCTION OF
CEMENT CONCRETE ROAD
FROM LALBAZAR PRIMARY
SCHOOL TO LALBAZAR
MASJID (IN 3 PART),
ARDHAGRAM GP, MEJIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
19/PM(F)/P/
1B-253/2012
24-01-2013 24.43413 16.95020 100% 16.95020 COMPLETE
44 REPAIRING OF CENTRAL
LABORATORY OF PMGSY
CELL OF BANKURA
DIVISION
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
23/PM(F)/P/
1B-259/2012
30-01-2013 6.21360 6.21360 NOT STARTED
45.1 RENOVATION OF
DILAPIDATED ROAD FROM
MAIN ROAD OF
NABAJIBANPUR VILLAGE
(SAMABAY BANK) TO
BORO POOL (TANTKANALI)
BLOCK DEVELOPMENT
OFFICER, BANKURA-II BLOCK
71/PM(F)/P/
1B-25/2013
11-03-2013 4.00000 15-07-2013 COMPLETE
OUT OF NREGS
FUND
45.2 RENOVATION OF
DILAPIDATED ROAD FROM
BADRA MORE TO
NADIGHAT
BLOCK DEVELOPMENT
OFFICER, BANKURA-II BLOCK
71/PM(F)/P/
1B-25/2013
11-03-2013 5.00000 15-07-2013 STARTED SOON
REPORT AS ON 10/02/2014 ` IN LAC
NO. DATE
DISTRICT: BANKURADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
UC RECEIVED REMARKSSANCTIONED
AMOUNT
EXPECTED DATE
OF
COMPLETION
SL. NO. IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
46.1 CONSTRUCTION OF SC/ ST
HOSTEL BUILDING AT
DUMURTORE BAGBADINI
HIGH SCHOOL, RAIPUR
BLOCK
SCHOOL AUTHORITY,
DUMURTORE BAGBADINI
HIGH SCHOOL
99/PM(F)/P/
1B-24/2013
18-03-2013 20.78564 20.78564 50% 12.19032 WORK IN
PROGRESS
46.2 SINKING OF DEEP TUBE-
WELL AT DUMURTORE
BAGBADINI HIGH SCHOOL,
RAIPUR BLOCK
SCHOOL AUTHORITY,
DUMURTORE BAGBADINI
HIGH SCHOOL
99/PM(F)/P/
1B-24/2013
18-03-2013 3.59500 3.59500 100% 3.59500 COMPLETE
TOTAL: 2744.06355 2276.14612 1353.71976
` IN LAC
NO. DATE1 IMPLEMENTATION OF 69
(SIXTY NINE) NOS. OF
SCHEMES IN RESPECT OF
RAJNAGAR BLOCK
EXECUTIVE OFFICER,
RAJNAGAR PANCHAYAT
SAMITY
256/PM(F)/P
/1B-31/2012
24-08-2012 123.37000 123.37000 99% 123.36673 WORK IN
PROGRESS
2 IMPLEMENTATION OF 23
(TWENTY THREE) NOS. OF
SCHEMES IN RESPECT OF
MD. BAZAR BLOCK
EXECUTIVE OFFICER, MD.
BAZAR PANCHAYAT SAMITY
257/PM(F)/P
/1B-32/2012
24-08-2012 120.32000 120.32000 100% 120.32000 COMPLETE
3 IMPLEMENTATION OF 5
(FIVE) NOS. OF SCHEMES
IN RESPECT OF NALHATI-I
BLOCK
EXECUTIVE OFFICER,
NALHATI-I PANCHAYAT
SAMITY; 03465-255236;
9474766664;
259/PM(F)/P
/1B-34/2012
24-08-2012 37.01500 37.01500 100% 37.01500 COMPLETE
4 IMPLEMENTATION OF 8
(EIGHT) NOS. OF SCHEMES
IN RESPECT OF
ILLAMBAZAR BLOCK
EXECUTIVE OFFICER,
ILLAMBAZAR PANCHAYAT
SAMITY
260/PM(F)/P
/1B-35/2012
24-08-2012 28.06500 28.06500 100% 28.06500 COMPLETE
5 IMPLEMENTATION OF 29
(TWENTY NINE) NOS. OF
SCHEMES IN RESPECT OF
BOLPUR-SRINIKETAN
BLOCK
EXECUTIVE OFFICER,
BOLPUR-SRINIKETAN
PANCHAYAT SAMITY; 03463-
264280/ 264172/
9434040654,
261/PM(F)/P
/1B-36/2012
24-08-2012 100.72500 100.72500 100% 100.72500 COMPLETE
DISTRICT: BIRBHUMDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
SANCTIONED
AMOUNT
RELEASED
AMOUNT
` IN LAC
NO. DATE
DISTRICT: BIRBHUMDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
SANCTIONED
AMOUNT
RELEASED
AMOUNT
6 IMPLEMENTATION OF 61
(SIXTY ONE) NOS. OF
SCHEMES IN RESPECT OF
SURI-I BLOCK
EXECUTIVE OFFICER, SURI-I
PANCHAYAT SAMITY, 03462-
225409/ 9434004880
262/PM(F)/P
/1B-41/2012
24-08-2012 124.53500 124.53500 100% 113.35277 COMPLETE
7 IMPLEMENTATION OF 35
(THIRTY FIVE) NOS. OF
SCHEMES IN RESPECT OF
DUBRAJPUR BLOCK
EXECUTIVE OFFICER,
DUBRAJPUR PANCHAYAT
SAMITY
266/PM(F)/P
/1B-29/2012
27-08-2012 103.29000 103.29000 95% 100.89902 WORK IN
PROGRESS
8 IMPLEMENTATION OF 60
(SIXTY) NOS. OF SCHEMES
IN RESPECT OF MURARAI-I
BLOCK
EXECUTIVE OFFICER,
MURARAI-I PANCHAYAT
SAMITY
267/PM(F)/P
/1B-28/2012
27-08-2012 76.24000 76.24000 100% 76.24000 COMPLETE
9 IMPLEMENTATION OF 8
(EIGHT) NOS. OF SCHEMES
IN RESPECT OF
KHOYRASOLE BLOCK
EXECUTIVE OFFICER,
KHOYRASOLE PANCHAYAT
SAMITY
268/PM(F)/P
/1B-30/2012
27-08-2012 29.53500 29.53500 90% 26.53500 WORK IN
PROGRESS
10 IMPLEMENTATION OF 48
(FORTY EIGHT) NOS. OF
SCHEMES IN RESPECT OF
RAMPURHAT-I BLOCK
EXECUTIVE OFFICER,
RAMPURHAT-I PANCHAYAT
SAMITY
269/PM(F)/P
/1B-33/2012
27-08-2012 58.50000 58.50000 100% 58.50000 COMPLETE
11 CONSTRUCTION OF MINI
BARRAGE OVER KANA
AJOY AT UPARKHARA
MOUZA, BOLPUR-
SRINIKETAN PS (5TH
INSTALMENT)
DISTRICT MAGISTRATE,
BIRBHUM
329/PM(F)/P
/1B-89/2008
(PT.-I)
28-09-2012 144.68000 144.68000 CIVIL PART
COMPLETE
` IN LAC
NO. DATE
DISTRICT: BIRBHUMDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
SANCTIONED
AMOUNT
RELEASED
AMOUNT
12.1 IMPROVEMENT OF RIDING
QUALITY AND
STRENGTHENING OF S/R
TO RAMPURHAT —
DUMKA ROAD FROM 0.0
KM TO 3.00 KM AND 9.00
KM TO 12.30 KM UNDER
RAMPURHAT SUB-
DIVISION
EXECUTIVE ENGINEER,
P.W.D., BIRBHUM DIVISION,
03462-255261, 9830149949,
351/PM(F)/P
/1B-
133/2011
12-10-2012 101.96240 101.96240 100% 31-03-2013 76.51008 COMPLETE
12.2 IMPROVEMENT OF RIDING
QUALITY AND
STRENGTHENING OF S/R
TO SURI — MD. BAZAR
ROAD FROM 0.0 KM TO
1.00 KM AND 3.81 KM TO
5.60 UNDER SURI SUB-
DIVISION
EXECUTIVE ENGINEER,
P.W.D., BIRBHUM DIVISION,
03462-255261, 9830149949,
351/PM(F)/P
/1B-
133/2011
12-10-2012 47.70926 47.70926 100% 31-03-2013 24.35613 COMPLETE
12.3 IMPROVEMENT &
STRENGTHENING OF
KHAGRA — JOYDEV ROAD
FROM 0.0 KM TO 8.00 KM
UNDER BOLPUR SUB-
DIVISION
EXECUTIVE ENGINEER,
P.W.D., BIRBHUM DIVISION,
03462-255261, 9830149949,
351/PM(F)/P
/1B-
133/2011
12-10-2012 171.52255 171.52255 100% 31-03-2013 137.10440 COMPLETE
` IN LAC
NO. DATE
DISTRICT: BIRBHUMDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
SANCTIONED
AMOUNT
RELEASED
AMOUNT
12.4 IMPROVEMENT &
STRENGTHENING OF
BOLPUR — ILLAMBAZAR
ROAD FROM 1.0 KM TO
9.40 KM EXCLUDING 3.0
KM TO 5.20 KM UNDER
BOLPUR SUB-DIVISION
EXECUTIVE ENGINEER,
P.W.D., BIRBHUM DIVISION,
03462-255261, 9830149949,
351/PM(F)/P
/1B-
133/2011
12-10-2012 131.89738 131.89738 95% 31-08-2013 131.89738 WORK IN
PROGRESS,
2012-13 FUND
UTILISED
12.5 IMPROVEMENT OF RIDING
QUALITY AND
STRENGTHENING OF SURI
RAJNAGAR ROAD (SH-13)
FROM 0.0 KM TO 4.00 KM
UNDER BIRBHUM
HIGHWAY DIVISION
EXECUTIVE ENGINEER,
P.W.D. (ROADS)
DIRECTORATE, BIRBHUM
HIGHWAY DIVISION,
9434173015, 03462-255381
351/PM(F)/P
/1B-
133/2011
12-10-2012 102.00000 102.00000 95% 31-10-2013 89.96072 WORK IN
PROGRESS
13 IMPROVEMENT OF ROAD
FROM ROYPUR TO
DHOLKATA AT PANCHAMI
AREA OF MD. BAZAR
BLOCK
DISTRICT MAGISTRATE,
BIRBHUM
367/PM(F)/P
/1B-
117/2012
12-11-2012 272.02011 272.02011 20% 50.28169 WORK IN
PROGRESS
14 CONSTRUCTION OF
BUILDING FOR A PUBLIC
HEALTH TRAINING CENTRE
AND HEALTH CARE
COMPLEX, BIRBHUM
SECRETARY, LIVER
FOUNDATION, 53 GOPAL
BANERJEE LANE, HOWRAH
414/PM(F)/P
/1B-99/2008
13-12-2012 20.00000 20.00000 100% 20.00000 COMPLETE
` IN LAC
NO. DATE
DISTRICT: BIRBHUMDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
SANCTIONED
AMOUNT
RELEASED
AMOUNT
15 IMPROVEMENT &
STRENGTHENING OF
BOLPUR — ILLAMBAZAR
ROAD FROM 1.0 KMP TO
9.40 KMP EXCLUDING 3.0
KMP TO 5.20 KMP UNDER
BOLPUR SUB-DIVISION
(ADDITIONAL SANCTION)
EXECUTIVE ENGINEER,
P.W.D., BIRBHUM DIVISION,
03462-255261, 9830149949,
438/PM(F)/P
/1B-
133/2011
24-12-2012 137.30196 137.30196 95% 31-08-2013 137.30196 WORK IN
PROGRESS,
2012-13 FUND
UTILISED
TOTAL: 1,930.68866 1,930.68866 1,452.43088
` IN LAC
NO. DATE1.1 RESECTIONING OF
DURGAPUR BRANCH
CANAL FROM CH. 0.00 TO
CH. 268.00 IN KANKSA
BLOCK UNDER DAMODAR
HEAD WORKS DIVISION
DISTRICT MAGISTRATE,
BURDWAN
180/PM(F)/P
/1B-
151/2012
20-07-2012 184.92185 184.92185
1.2 RESECTIONING OF
DURGAPUR BRANCH
CANAL FROM CH. 268.65
TO CH. 757.00 IN KANKSA
AND AUSGRAM-II BLOCK
UNDER DAMODAR HEAD
WORKS DIVISION
DISTRICT MAGISTRATE,
BURDWAN
180/PM(F)/P
/1B-
151/2012
20-07-2012 221.96128 221.96128
1.3 UPGRADATION AND
IMPROVEMENT OF
PANDAVESWAR -
NATUNDANGA ROAD
FROM 0.00 KMP TO 1.00
KMP UNDER ASANSOL SUB-
DIVISION
DISTRICT MAGISTRATE,
BURDWAN
180/PM(F)/P
/1B-
151/2012
20-07-2012 127.99466 127.99466
1.4 GROUND WATER BASED
WATER SUPPLY SCHEME
AT ALEFNAGAR IN
AUSGRAM - I BLOCK
DISTRICT MAGISTRATE,
BURDWAN
180/PM(F)/P
/1B-
151/2012
20-07-2012 68.97442 68.97442
DISTRICT: BURDWANDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSSANCTIONED
AMOUNT
289.08098
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
` IN LAC
NO. DATE
DISTRICT: BURDWANDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
1.5 GROUND WATER BASED
WATER SUPPLY SCHEME
AT SHYAMSUNDARPUR IN
AUSGRAM - II BLOCK
DISTRICT MAGISTRATE,
BURDWAN
180/PM(F)/P
/1B-
151/2012
20-07-2012 68.79944 68.79944
2 CONSTRUCTION OF RIG
BORE TUBE WELL IN 10
BLOCKS AND RIVERBED
TUBE WELL IN RANIGUNG
BLOCK (150 NOS. TUBE-
WELLS)
EXECUTIVE ENGINEER,
CENTRAL MECHANICAL
DIVISION, P.H.E.
DIRECTORATE, BURDWAN;
0342-2644048,
273/PM(F)/P
/1B-46/2012
29-08-2012 141.36138 141.36138 100% 141.36138 COMPLETE
3 CONSTRUCTION OF ICDS
CENTRES, ADDITIONAL
CLASSROOMS & SUPPLY
OF DRINKING WATER IN
10 BLOCKS
DISTRICT MAGISTRATE,
BURDWAN
274/PM(F)/P
/1B-
170/2011
29-08-2012 342.53710 342.53710
4 CONTINGENT FUND FOR
SMOOTH RUNNING OF
PUP SCHEMES
IMPLEMENTED DURING
2012-13
DISTRICT MAGISTRATE,
BURDWAN
406/PM(F)/P
/1B-85/2010
10-12-2012 5.68000 5.68000
289.08098
` IN LAC
NO. DATE
DISTRICT: BURDWANDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
5.1 RESTORATION OF CANAL
BED AND SLOPES
INCLUDING LINING
WORKS WITH PCC FROM
CH. 472.00 TO CH. 488.00
IN KANKSA BLOCK,
BURDWAN IRRIGATION
SUB-DIVN. NO. III
DISTRICT MAGISTRATE,
BURDWAN
22/PM(F)/P/
1B-258/2012
30-01-2013 22.44526 22.44526 100% 22.44526 COMPLETE
(50% WORK
SANCTIONED
IN THIS F.Y.)
5.2 RESTORATION OF CANAL
BED AND SLOPES
INCLUDING LINING
WORKS WITH PCC FROM
CH. 488.00 TO CH. 506.00
IN KANKSA & AUSGRAM-II
BLOCK, BURDWAN
IRRIGATION SUB-DIVN.
NO. III
DISTRICT MAGISTRATE,
BURDWAN
22/PM(F)/P/
1B-258/2012
30-01-2013 22.28023 22.28023 100% 22.28023 COMPLETE
(50% WORK
SANCTIONED
IN THIS F.Y.)
5.3 RESTORATION OF CANAL
BED AND SLOPES
INCLUDING LINING
WORKS WITH PCC FROM
CH. 528.00 TO CH. 544.00
IN AUSGRAM-II BLOCK,
BURDWAN IRRIGATION
SUB-DIVN. NO. III
DISTRICT MAGISTRATE,
BURDWAN
22/PM(F)/P/
1B-258/2012
30-01-2013 22.34318 22.34318 100% 22.34318 COMPLETE
(50% WORK
SANCTIONED
IN THIS F.Y.)
TOTAL: 1,229.29880 1,229.29880 497.51103
` IN LAC
NO. DATE1 CONSTRUCTION OF
CLASSROOMS, HOSTEL
BUILDING AND LADIES
TOILET OF TENTULMURI
RAMKRISHNA
SIKSHANIKETAN UNDER
KHARAGPUR-II BLOCK
BLOCK DEVELOPMENT
OFFICER, KHARAGPUR-II
BLOCK
89/PM(F)/P/
1B-19/2012
11-05-2012 10.19855 9.18504 100% 9.18504 COMPLETE
2 CONSTRUCTION OF
COMMUNITY CENTRE AT
KANKRAJHORE WITHIN
BINPUR-II PANCHAYAT
SAMITY (POST FACTO
APPROVAL)
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
93/PM(F)/P/
1B-66/2011
15-05-2012 4.35997 4.35997 100% 4.35997 COMPLETE
3 CONSTRUCTION OF RCC
BOX CULVERT OVER
MAHULIA KHAL IN
BETWEEN BANSIABHOL
AND SINGDHUI VILLAGE
UNDER NAYAGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
94/PM(F)/P/
1B-82/2012
30-05-2012 22.50588 21.25718 100% 21.25718 COMPLETE
4 CONSTRUCTION OF ROAD
FROM ASUI TO NURSOLE
UNDER GOPIBALLAVPUR-I
BLOCK
CHIEF ENGINEER,
P.W.D.(ROADS)
96/PM(F)/P/
1B-69/2012
31-05-2012 217.81620
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
5.1 EXCAVATION OF NUNIA
PUCCA PUKUR UNDER
JAMBONI BLOCK
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
100/PM(F)/P
/1B-78/2012
01-06-2012 24.63672 23.70242 100% 23.70242 COMPLETE
5.2 RE-EXCAVATION OF BARA
BANKATA MUCHIR BUNDH
UNDER JAMBONI BLOCK
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
100/PM(F)/P
/1B-78/2012
01-06-2012 18.79900 NIT ISSUED ON
30/05/2012
5.3 RE-EXCAVATION OF
ALAMPUR KATHUA
BUNDH UNDER JAMBONI
BLOCK
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
100/PM(F)/P
/1B-78/2012
01-06-2012 18.79900 18.69857 100% 18.69857 COMPLETE
5.4 EXCAVATION OF
DUMURIA PANRUA
BUNDH UNDER JAMBONI
BLOCK
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
100/PM(F)/P
/1B-78/2012
01-06-2012 24.63672 23.78753 100% 23.78753 COMPLETE
6 CONSTRUCTION OF
NURSING TRAINING
SCHOOL AT LALGARH
WITHIN PHC CAMPUS
UNDER BINPUR-I BLOCK
WEST BENGAL MEDICAL
SERVICE CORPORATION
LIMITED
102/PM(F)/P
/1B-84/2012
04-06-2012 600.00000 300.00000 75% WORK IN
PROGRESS
UPTO PILE CAP
LEVEL, PILING
WORK
COMPLETE
7 CONSTRUCTION OF
HOSTEL BUILDING AT
ASANDA SIKSHA NIKETAN,
P.O. LALNAGAR
HEADMASTER, ASANDA
SIKSHA NIKETAN
108/PM(F)/P
/1B-
124/2011
07-06-2012 22.86835 22.86835 60% 11.43418 WORK IN
PROGRESS
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
8.1 CONSTRUCTION OF CLASS
'A' SINGLE LANE ROAD
BRIDGE AT CH. 1233.26 OF
TSMC(N) IN MOUZA-
JARALATA, PS-JHARGRAM
ALONG KESIA-NATUNDIHI
ROAD UNDER
KANGSABATI CANALS
DIVISION NO. V,
JHARGRAM
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION NO. V, JHARGRAM,
PASCHIM MEDINIPUR
109/PM(F)/P
/1B-85/2012
07-06-2012 49.92400 49.92400 50% WORK IN
PROGRESS,
W.O. ISSUED
ON 01-11-2012,
NIT ISSUED ON
03-08-2012
8.2 CONSTRUCTION OF CLASS
'A' SINGLE LANE ROAD
BRIDGE AT CH. 12.00 OF
DY-12L OF TSMC(N) IN
MOUZA-JARALATA, PS-
JHARGRAM ALONG KESIA-
NATUNDIHI ROAD
INCLUDING
CONSTRUCTION OF LINING
FROM CH. 0.00 TO CH.
20.00 OF DY-12L/ TSMC(N)
UNDER KANGSABATI
CANALS DIVISION NO. V,
JHARGRAM
EXECUTIVE ENGINEER,
KANGSABATI CANALS
DIVISION NO. V, JHARGRAM,
PASCHIM MEDINIPUR
109/PM(F)/P
/1B-85/2012
07-06-2012 32.95807 32.95807 50% WORK IN
PROGRESS,
W.O. ISSUED
ON 01-11-2012,
NIT ISSUED ON
03-08-2012
26.19818
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
9 IMPROVEMENT OF ROAD
FROM BARAPENIA TO
NARAYANPUR VILLAGE IN
BANDHGORA G.P.,
JHARGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
111/PM(F)/P
/1B-94/2012
11-06-2012 18.53949 17.91910 100% 15-01-2013 17.91910 COMPLETE
10 CONSTRUCTION OF GR.
FLOOR SCHOOL BUILDING
OF TENTULMURI PRIMARY
SCHOOL, KHARAGPUR-II
BLOCK DEVELOPMENT
OFFICER, KHARAGPUR-II
BLOCK
117/PM(F)/P
/1B-81/2012
12-06-2012 21.72171 19.83684 100% 19.50345 COMPLETE
11 ANTI-EROSION WORK
ALONG THE LEFT BANK OF
RIVER KANGSABATI AT
DHERUA MOUZA,
MEDINIPUR(SADAR)
EXECUTIVE ENGINEER
(I&W), WEST MEDINIPUR
DIVISION
118/PM(F)/P
/1B-86/2012
12-06-2012 51.55656 51.55656
12 CONSTRUCTION OF
BOUNDARY WALL OF A
MUSLIM GRAVEYARD AT
DAHIJURI UNDER BINPUR-I
P.S.
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
119/PM(F)/P
/1B-02/2012
12-06-2012 11.21914 9.81355 100% 9.81355 COMPLETE
13 CONSTRUCTION OF
SCHOOL BUILDING OF
BINPUR HIGH SCHOOL,
BINPUR
HEADMASTER, BINPUR HIGH
SCHOOL
131/PM(F)/P
/1B-87/2012
15-06-2012 24.81233 24.81233 75% 12.16511 ROOF LEVEL
WORK
CONTINUING
14.1 IMPROVEMENT OF ROAD
FROM GHUTIA TO BANKRA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 8.35429 8.27154 100% 8.27154 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
14.2 IMPROVEMENT OF ROAD
FROM BHTURO TO ASTI
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 11.30479 11.17554 100% 11.17554 COMPLETE
14.3 IMPROVEMENT OF ROAD
FROM SARENGA TO
KURARIA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 3.30447 3.27012 100% 3.27012 COMPLETE
14.4 IMPROVEMENT OF ROAD
FROM KENDUA TO
BAGHUA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 4.95668 4.82411 100% 4.82411 COMPLETE
14.5 IMPROVEMENT OF ROAD
FROM AMLATORA TO
SARAKATA VIA BURISOLE
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 4.50958 4.45041 100% 4.45041 COMPLETE
14.6 IMPROVEMENT OF ROAD
FROM SALTALA TO ENATA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 9.68982 9.31803 100% 9.31803 COMPLETE
14.7 IMPROVEMENT OF ROAD
FROM KHATKURA TO
BANNAGAJAR
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 3.75797 3.72468 100% 3.72468 COMPLETE
14.8 IMPROVEMENT OF ROAD
FROM BALIBANDH TO
JAMUNASOLE
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 3.11874 2.47165 100% 2.47165 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
14.9 IMPROVEMENT OF ROAD
FROM KANIMOHULI RAIL
STATION TO GAIDA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 5.01257 4.95333 100% 4.95333 COMPLETE
14.10 IMPROVEMENT OF ROAD
FROM PARIHATI TO
GUIARA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 8.26114 8.17730 100% 8.17730 COMPLETE
14.11 IMPROVEMENT OF ROAD
FROM ORO TO
BARABANKATA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 7.43503 7.32278 100% 7.32278 COMPLETE
14.12 IMPROVEMENT OF ROAD
FROM GAGNASULI TO
BENASULI
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 7.70226 7.60226 100% 7.60226 COMPLETE
14.13 IMPROVEMENT OF ROAD
FROM PASCHIM
PURNAPANI TO
KENDUASULI
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 4.50958 4.46414 100% 4.46414 COMPLETE
14.14 IMPROVEMENT OF ROAD
FROM HIZLI TO
SONAMUKHI
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 4.22372 4.17257 100% 4.17257 COMPLETE
14.15 IMPROVEMENT OF ROAD
FROM BAGGHORI TO
BADAKATA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 7.99756 7.90758 100% 7.90758 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
14.16 IMPROVEMENT OF ROAD
FROM GIDHNI ADIBASI
PARA TO SALPATHRA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012
15-06-2012 4.48954 4.44426 100% 4.44426 COMPLETE
14.17 IMPROVEMENT OF ROAD
WITH MORRUM &
BOULDER FROM
KASAFALIA TO
RANGAMETIA VIA
BHALUKKHULIA
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012 &
396
15-06-2012 &
29-11-2012
10.77334 10.62233 100% 10.62233 COMPLETE
14.18 CONSTRUCTION OF RCC
SLAB CULVERT AT
BHALUKKHULIA ON
BHALUKKHULIA TO
KASAFALIA ROAD
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012 &
396
15-06-2012 &
29-11-2012
6.15000 6.15000 100% 6.15000 COMPLETE
14.19 CONSTRUCTION OF RCC
SLAB CULVERT AT
BHALUKKHULIA ON
KASAFALIA TO
BHALUKKHULIA ROAD
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012 &
396
15-06-2012 &
29-11-2012
6.15000 6.14823 100% 6.14823 COMPLETE
14.20 CONSTRUCTION OF RCC
BRIDGE OVER KASAFALIA
KHAL ON THE ROAD OF
BHALUKKHULIA TO
KASAFALIA ROAD
BLOCK DEVELOPMENT
OFFICER, JAMBONI BLOCK
132/PM(F)/P
/1B-
100/2012 &
396
15-06-2012 &
29-11-2012
8.00000 8.00000 100% 8.00000 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
15.1 IMPROVEMENT OF ROAD
FROM ANDHARIA PITCH
ROAD TO JAMDA IN
ANDHARIA AND BELATIKRI
GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 18.12171 17.46736 100% 15-12-2012 17.46736 COMPLETE
15.2 IMPROVEMENT OF ROAD
FROM BELATIKRI TO
LAGHATA NADIGHAT IN
BELATIKRI AND NEPURA
GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 21.91741 15.79283 55% 15-12-2012 15.79283 WORK IN
PROGRESS
15.3 IMPROVEMENT OF ROAD
FROM KANSINA MORE TO
RATHBERA CHAWK IN
ANDHARIA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 13.55118 12.81494 100% 15-12-2012 12.81494 COMPLETE
15.4 IMPROVEMENT OF ROAD
FROM CHHOTO JAMDA TO
AMAINAGAR PITCH ROAD
IN BELATIKRI AND
ANDHARIA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 18.12171 17.54448 100% 15-12-2012 17.54448 COMPLETE
15.5 IMPROVEMENT OF ROAD
FROM GOHOMIDANGA TO
BHULKA IN BAITA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 13.55118 5.34015 50% 15-12-2012 1ST RA BILL
DRAWN
15.6 IMPROVEMENT OF ROAD
FROM GUJISOLE MORE TO
PANPURIA IN SIJUA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 8.65624 8.32007 100% 15-12-2012 8.32007 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
15.7 IMPROVEMENT OF ROAD
FROM TANTISOLE
RAJBUNDH BRIDGE TO
DUMURIA PRIMARY
SCHOOL IN SIJUA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 8.65624 8.29046 100% 15-12-2012 8.29046 COMPLETE
15.8 IMPROVEMENT OF ROAD
FROM LALGARH BAZAR TO
KANGSABATI NADIGHAT
IN LALGARH GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.13970 1.50460 100% 15-12-2012 1.50460 COMPLETE
15.9 IMPROVEMENT OF ROAD
FROM DUBRAJPUR TO
POLICE PHARI IN
RAMGARH GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 8.65624 8.31675 100% 15-12-2012 8.31675 COMPLETE
15.10 IMPROVEMENT OF ROAD
FROM KUMIRKATA PITCH
ROAD TO PANCHIARA IN
DAHIJURI GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 8.98066 7.95503 100% 15-12-2012 7.95503 COMPLETE
15.11 IMPROVEMENT OF ROAD
FROM MAGURA TO
ANKRO IN BINPUR
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 7.95368 2.61440 100% 15-12-2012 2.61440 COMPLETE
15.12 IMPROVEMENT OF ROAD
FROM FULBERI MORE TO
BANDARBONI IN DAHIJURI
GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 13.55118 9.98461 100% 15-12-2012 9.98461 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
15.13 IMPROVEMENT OF ROAD
FROM BAHADURPUR
PITCH ROAD TO
NACHHIPUR NADIGHAT IN
NEPURA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 17.70938 13.26923 100% 15-12-2012 13.26923 COMPLETE
15.14 IMPROVEMENT OF ROAD
FROM LALGARH BURA
BABA THAN (PITCH ROAD)
TO PODIHA VILLAGE IN
LALGARH GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 7.79544 7.49121 100% 15-12-2012 7.49121 COMPLETE
15.15 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT LAGHATA PHC IN
NEPURA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.50000 20% 15-12-2012 WORK IN
PROGRESS
15.16 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT NACHHIPUR HIGH
SCHOOL IN NEPURA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.50000 20% 15-12-2012 WORK IN
PROGRESS
15.17 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT LALGARH PHC IN
LALGARH GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.50000 1.68492 50% 15-12-2012 1.68492 WORK IN
PROGRESS
15.18 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT LALGARH
SARADAMONI PRIMARY
SCHOOL IN LALGARH GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.50000 1.59973 50% 15-12-2012 1.59973 WORK IN
PROGRESS
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
15.19 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT BAITA SRIGOPAL H.S.
SCHOOL, JASHPUR IN
BAITA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.50000 15-12-2012 PENDING FOR
CHANGING OF
SITE
15.20 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT DHARAMPUR PHC IN
DHARAMPUR GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.50000 1.87039 100% 1.87039 COMPLETE
15.21 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT ANDHARIA CHAWK IN
ANDHARIA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.49943 2.05069 100% COMPLETE
15.22 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT BINPUR CHAWK IN
BINPUR GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.49943 1.83324 100% 15-12-2012 1.83324 COMPLETE
15.23 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT AMAINAGAR IN
ANDHARIA GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.49943 2.09192 60% 15-12-2012 2.09192 WORK IN
PROGRESS
15.24 SINKING OF TUBE WELL
WITH SUBMERSIBLE PUMP
AT MURAR GARAI PARA IN
RAMGARH GP
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
133/PM(F)/P
/1B-98/2012
15-06-2012 2.49943 1.60526 100% 15-12-2012 1.60526 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
16.1 IMPROVEMENT OF ROAD
FROM AMLASOLE
BIRSARMUNDA MORE TO
JHARKHAND
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 6.78290 6.23312 100% 6.23312 COMPLETE
16.2 IMPROVEMENT OF ROAD
FROM DHOBAJAN COLONY
TO SUKNAPAHARI VIA
KHAMAR
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 20.29578 19.80897 100% 19.80897 COMPLETE
16.3 IMPROVEMENT OF ROAD
FROM SILDA SATIGHAT TO
RAGHUNATHPUR
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 23.77921 22.17645 100% 15-01-2013 22.17645 COMPLETE
16.4 IMPROVEMENT OF ROAD
FROM JARDA TO
RANGAMETIA,
SANDAPARA
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 20.99840 15.40325 100% 01-01-2013 15.40325 COMPLETE
16.5 IMPROVEMENT OF ROAD
FROM DHULIPARA TO
RAJDAHA IN BHELAIDIHA
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 5.80462 5.24106 100% 5.24106 COMPLETE
16.6 IMPROVEMENT OF ROAD
FROM LEDASAL TO
PANCHTAKARPAL, KANKO
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 19.55550 16.16900 100% 25-01-2013 16.16900 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
16.7 IMPROVEMENT OF ROAD
FROM GORAMTHAN TO
GADRASINI ASHRAM,
BELPAHARI
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 9.52460 8.71126 100% 01-01-2013 8.71126 COMPLETE
16.8 IMPROVEMENT OF ROAD
FROM DOMSOLE HIGH
SCHOOL TO BANKATI,
HARDA
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 9.67280 9.00553 100% 01-01-2013 9.00553 COMPLETE
16.9 IMPROVEMENT OF ROAD
FROM BELPAHARI TO
SANDAPARA IN
BELPAHARI
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 8.38352 7.46288 40% 01-01-2013 7.46288 WORK IN
PROGRESS
16.10 IMPROVEMENT OF ROAD
FROM RAGHUNATHPUR
TO ERGODA, ERGODA
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 13.29110 11.62628 100% 11.62628 COMPLETE
16.11 IMPROVEMENT OF ROAD
FROM MAHULBONI TO
ODOLCHUA IN SIMULPAL
BLOCK DEVELOPMENT
OFFICER, BINPUR-II BLOCK
134/PM(F)/P
/1B-99/2012
15-06-2012 10.05575 8.73974 100% 01-01-2013 8.73974 COMPLETE
17.1 IMPROVEMENT OF ROAD
FROM BAHARAKOTA TO
DURGAPUR
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.23219 3.67959 100% 25-01-2013 3.67959 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
17.2 IMPROVEMENT OF ROAD
FROM NH-6 TO
CHANDIPUR VIA GP
OFFICE
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.23219 5.23219 100% 30-01-2013 5.23219 COMPLETE
17.3 IMPROVEMENT OF ROAD
FROM CHANDRI TO
MADHABPUR VIA ASTI IN
CHANDRI GP
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 3.02559 2.84712 100% 30-05-2013 2.84712 COMPLETE
17.4 IMPROVEMENT OF ROAD
FROM KANYADUBA TO
MURGIDIHI
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 3.02559 2.09073 100% 31-01-2013 2.09073 COMPLETE
17.5 IMPROVEMENT OF ROAD
FROM PHASITALA TO
PATHRI VIA DHANGRI
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.23219 5.23219 100% 5.23219 COMPLETE
17.6 IMPROVEMENT OF ROAD
FROM AMDIHA TO
CHHANAPARA
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.23219 3.94241 100% 30-04-2013 3.94241 COMPLETE
17.7 IMPROVEMENT OF ROAD
FROM KALABONI TO
JARULIA
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 14.55227 14.54627 100% 15-01-2013 14.54627 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
17.8 IMPROVEMENT OF ROAD
FROM BIRIDANGA (NAHAR
KHAL CULVERT) TO
BETKUNDRI MPS GATE
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 6.57273 5.46283 100% 31-01-2013 5.46283 COMPLETE
17.9 IMPROVEMENT OF ROAD
FROM BARDANGA TO
SANKARBONI VIA
SAGARBHANGA
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.85139 3.91160 100% 30-05-2013 3.91160 COMPLETE
17.10 IMPROVEMENT OF ROAD
FROM KHALSHEULI TO
PAKURIAPAL VIA
RADHANAGAR
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.85139 5.47965 100% 15-01-2013 5.47965 COMPLETE
17.11 IMPROVEMENT OF ROAD
FROM AUSHPAL TO
TALDANGA
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 6.57273 6.31699 100% 31-01-2013 6.31699 COMPLETE
17.12 IMPROVEMENT OF ROAD
FROM BRINDABANPUR TO
ANDHARIASOLE IN
NEDABAHARA G.P.
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 10.51140 10.50614 100% 31-01-2013 10.50614 COMPLETE
17.13 IMPROVEMENT OF ROAD
FROM MADHUPUR TO
PHASITALA
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 14.55227 14.40258 100% 31-01-2013 14.40258 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
17.14 IMPROVEMENT OF ROAD
FROM DEBI CHAK TO
PATASIMUL
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 10.51140 10.51140 100% 31-01-2013 10.51140 COMPLETE
17.15 IMPROVEMENT OF ROAD
FROM JAMSOLA TO
KULDIHA
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 6.66189 6.51742 100% 31-01-2013 6.51742 COMPLETE
17.16 IMPROVEMENT OF ROAD
FROM BARDANGA CHAK
TO METAL
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.69089 5.67048 100% 31-01-2013 5.67048 COMPLETE
17.17 IMPROVEMENT OF ROAD
FROM GOLAGHUTIA TO
CHANDRI MORE
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.69089 5.08448 100% 30-05-2013 5.08448 COMPLETE
17.18 IMPROVEMENT OF ROAD
FROM KUNDALDIHA TO
TENGIA
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.69089 4.65118 85% 30-05-2013 4.65118 WORK IN
PROGRESS
17.19 IMPROVEMENT OF ROAD
FROM NETURA BUS
STAND (NH-6) TO
MATALSOLE
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 3.02559 2.80420 100% 30-05-2013 2.80420 COMPLETE
17.20 IMPROVEMENT OF ROAD
FROM KHALSEULI TO
DAMRASOLE VIA
KALABONI
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 5.69089 5.22085 100% 15-01-2013 5.22085 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
17.21 IMPROVEMENT OF ROAD
FROM PANCHAMI TO
PIPRI
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 3.02559 2.03420 90% 30-05-2013 2.03420 WORK IN
PROGRESS
17.22 IMPROVEMENT OF ROAD
FROM JABNIKATA TO DEER
PARK VIA KHARIKASULI
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
135/PM(F)/P
/1B-97/2012
15-06-2012 10.51140 9.28310 100% 30-04-2013 9.28310 COMPLETE
18 WATER SUPLY SCHEME
FOR R.G.T.S. SCHOOL AT
BELPAHARI, BINPUR-II
EXECUTIVE ENGINEER,
MIDNAPORE DIVISION,
P.H.E. DIRECTORATE
138/PM(F)/P
/1B-
111/2012
22-06-2012 13.70584 13.70584
19 SINKING OF 350 NOS.
INDIAN MARK-II TUBE-
WELL IN 7 PUP BLOCKS
EXECUTIVE ENGINEER,
MIDNAPORE DIVISION,
P.H.E. DIRECTORATE
139/PM(F)/P
/1B-
112/2012
22-06-2012 313.91000 313.91000 85% 156.95500 311 TUBE-WELL
COMPLETE
20 CONSTRUCTION OF
BOUNDARY WALL AT
LALGARH PHC, BINPUR-I
BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
BINPUR-I
152/PM(F)/P
/1B-
115/2011
04-07-2012 38.01873 NIT ISSUED ON
10-10-2013
21 CONSTRUCTION OF
SCHOOL BUILDING OF
CHHAY HAZARI SCHOOL,
GOPIBALLAVPUR-I
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
GOPIBALLAVPUR-I
154/PM(F)/P
/1B-
160/2011
04-07-2012 22.64728 WORK ORDER
ISSUED ON 29-
01-2013
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
22 CONSTRUCTION OF NEW
SCHOOL BUILDING AT
MURABONI NETAJI HIGH
SCHOOL, MURABONI,
BINPUR-I
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
BINPUR-I
167/PM(F)/P
/1B-
140/2011
13-07-2012 24.69324 11.52803 55% 11.08708 WORK IN
PROGRESS
23 REPAIRING OF BITUMEN
ROAD FROM BINPUR TO
PAPATPUR NODIGHAT
AND BOXI VIA HARDA AND
MURGIMORE, BINPUR-I
BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
175/PM(F)/P
/1B-
141/2012 &
06/PM(F)/P/
1B-141/2012
16-07-2012 &
14-01-2013
517.42392 372.89069 60% 30-11-2013 372.89069 WORK ORDER
ISSUED IN 3
PARTS; WORK
IN PROGRESS
24.1 CONSTRUCTION OF
ADDITIONAL CLASS ROOM
OF KENDIJAMBANI ICDS
CENTRE, GARHBETA-III
BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
GARHBETA-III
194/PM(F)/P
/1B-
153/2012
27-07-2012 4.09890 4.09890 100% 4.09890 COMPLETE
24.2 CONSTRUCTION OF
BOUNDARY WALL AND
OTHER WORK OF
KADAMDIHA PRIMARY
SCHOOL
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
GARHBETA-III
194/PM(F)/P
/1B-
153/2012
27-07-2012 20.64973
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
25 REPAIRING OF
KADAMKANALI TO
RADHANAGAR ROAD,
JHARGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
196/PM(F)/P
/1B-
161/2012
27-07-2012 7.74436 7.51782 100% 25-05-2013 7.51782 COMPLETE
26 CONSTRUCTION OF 6 NOS.
OF CLASSROOMS AT
RANTUA HIGH SCHOOL,
JHARGRAM
HEADMASTER, RANTUA
HIGH SCHOOL
198/PM(F)/P
/1B-17/2012
& 305
30-07-2012 &
19-09-2012
36.82552 36.82552 60% 18.41276 WORK IN
PROGRESS
27 CONSTRUCTION OF
CLASSROOMS AT SALJORA
PRIMARY SCHOOL,
NARAYANGARH PS
HEAD TEACHER, SALJORA
PRIMARY SCHOOL
200/PM(F)/P
/1B-
129/2012
31-07-2012 12.01479 12.01479 100% 12.01479 COMPLETE
28 EXCAVATION OF POND ON
BRWS LAND, BELPAHARI
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
203/PM(F)/P
/1B-
155/2012
01-08-2012 3.52199 1.22058 100% 1.22058 COMPLETE
29 PLANT AND MACHINERY
OF MILK PROCESSING
UNIT AT KESHIARY AND
CHANDRAKONA ROAD
MILK CHILLING PLANT,
GARHBETA-III BLOCK
MANAGING DIRECTOR,
MIMUL, PASCHIM
MEDINIPUR
205/PM(F)/P
/1B-
152/2012
01-08-2012 69.51000 34.75500 50% 10.34000 M.P.U. AT
KESHIARY IS
PROPOSED FOR
SHIFTING AT
MIDNAPUR
SADAR,
CHILLING
PLANT
COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
30.1 INSTALLATION OF MINI
DEEP TUBE-WELL AT
HARTORA MOUZA, J.L. NO.
– 130, SALBONI BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
210/PM(F)/P
/1B-
160/2012
03-08-2012 2.13945 SENT TO
DEPTT. FOR
ADDL.
SANCTION
30.2 INSTALLATION OF MINI
DEEP TUBE-WELL AT
JOYPUR MOUZA, J.L. NO. –
46, SALBONI BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
210/PM(F)/P
/1B-
160/2012
03-08-2012 2.13945 SENT TO
DEPTT. FOR
ADDL.
SANCTION
30.3 INSTALLATION OF MINI
DEEP TUBE-WELL AT
BARAMESHA MOUZA, J.L.
NO. – 271, PLOT NO. - 49,
SALBONI BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
210/PM(F)/P
/1B-
160/2012
03-08-2012 2.13945 2.13945 100% 2.13945 COMPLETE
30.4 INSTALLATION OF MINI
DEEP TUBE-WELL AT
BHEDUA MOUZA, J.L. NO.
– 435, PLOT NO. – 59, 7
NO. GP, GARHBETA-III PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
210/PM(F)/P
/1B-
160/2012
03-08-2012 3.79870 3.79328 100% 3.79328 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
30.5 CONST. OF PUCCA DRAIN
WITH COVER SLAB AT
GUIADAHA MOUZA, J.L.
NO. – 713, PLOT NO. –
370, KARSA GP,
GARHBETA-III PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
210/PM(F)/P
/1B-
160/2012
03-08-2012 15.84989 10.24387 85% 10.24387 WORK IN
PROGRESS
30.6 CONSTRUCTION OF
SCHOOL BUILDING AT
DABCHA NABKOLA SISHU
NIKETAN, J.L. NO. – 672,
PLOT NO. – 26,
SATBANKURA GP
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
GARHBETA-III
210/PM(F)/P
/1B-
160/2012
03-08-2012 7.48394
30.7 CONSTRUCTION OF
INDOOR BADMINTON
COURT AT GARHBETA-I
BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
GARHBETA-I
210/PM(F)/P
/1B-
160/2012
03-08-2012 5.53052
30.8 CONSTRUCTION OF
BOUNDARY WALL WITH
M.S. SHEET GATE OF
KIABONI HIGH SCHOOL,
GARHBETA-III BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
GARHBETA-III
210/PM(F)/P
/1B-
160/2012
03-08-2012 9.94051
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
30.9 CONSTRUCTION OF STAGE
WITH GREEN ROOM OF
KIABONI HIGH SCHOOL,
GARHBETA-III BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
GARHBETA-III
210/PM(F)/P
/1B-
160/2012
03-08-2012 4.02888
31 CONSTRUCTION OF
SCHOOL HOSTEL BUILDING
AT ARJUNI DESHBANDHU
VIDYAPITH,
NARAYANGARH BLOCK
HEADMASTER, ARJUNI
DESBANDHU VIDYAPITH,
P.O.-THAKURCHAK,
PASCHIM MEDINIPUR, PIN-
721424
130/PM(F)/P
/1B-
120/2011
23-05-2013 24.50248 12.25124 TENDER
INVITED ON 14-
02-2013
32 CONSTRUCTION OF
HOSTEL BUILDING AT
KHALSEULI HIGH SCHOOL
(H.S.), JHARGRAM SUB-
DIVISION
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
JHARGRAM
221/PM(F)/P
/1B-
175/2012
14-08-2012 24.79534 11.27231 50% 01-06-2013 11.27231 WORK IN
PROGRESS
33 ELECTRICAL INSTALLATION
WORK AT BAITA SRI
GOPAL HIGH SCHOOL,
BINPUR-I BLOCK
EXECUTIVE ENGINEER,
P.W.D., MIDNAPORE
ELECTRICAL DIVISION
222/PM(F)/P
/1B-
172/2012
14-08-2012 3.85001 3.85001 100% 3.85001 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
34 REPAIRING OF ASUI-
NURISOLE ROAD BY
PATCHING POTHOLES BY
JHAMA METAL
CONSOLIDATION,
GOPIBALLAVPUR-I BLOCK
EXECUTIVE ENGINEER,
MIDNAPORE HIGHWAY
DIVISION-II, P.W.D.(ROADS)
DIRECTORATE
223/PM(F)/P
/1B-69/2011
14-08-2012 8.22649 8.22649 100% 8.20037 COMPLETE
35 CONSTRUCTION OF
BOUNDARY WALL AT
MADHUPUR BINAPANI
HIGH SCHOOL (H.S.),
MADHUPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
SALBONI
225/PM(F)/P
/1B-
171/2012
14-08-2012 16.76151
36 EXCAVATION/ RE-
EXCAVATION OF 5 NOS.
OF WHS AND DHALL
BANDHS AT LOGDICHALK,
GARBERIA, MARCHI AND
LOCHANGARH MOUZAS,
GARHBETA-III BLOCK
ASSISTANT DIRECTOR OF
AGRICULTURE (ADMN.),
SOIL CONSERVATION,
MEDINIPUR
228/PM(F)/P
/1B-
165/2012
17-08-2012 27.64158 27.37148 100% 27.37148 COMPLETE,
BALANCE
REFUNDED
37.1 CONSTRUCTION OF
GROUND FLOOR OF
GAJASHIMUL K.C.M. HIGH
SCHOOL BUILDING
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
JHARGRAM
229/PM(F)/P
/1B-
170/2012
17-08-2012 24.69324 17.88513 01-07-2013 17.88513 WORK IN
PROGRESS
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
37.2 CONSTRUCTION OF
BOUNDARY WALL OF
GAJASHIMUL K.C.M. HIGH
SCHOOL
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
JHARGRAM
229/PM(F)/P
/1B-
170/2012
17-08-2012 9.96994 4.77381 60% 30-04-2013 4.77381 WORK IN
PROGRESS,
DELAYED DUE
TO LAND
DISPUTE
37.3 CONSTRUCTION OF FIRST
FLOOR OF GAJASHIMUL
K.C.M. HIGH SCHOOL
BUILDING
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO,
JHARGRAM
229/PM(F)/P
/1B-
170/2012
17-08-2012 7.96313 01-06-2013 NOT STARTED
38 SINKING OF 9 INDIA MARK-
II TUBE WELL AND 124
MDTW WITH
SUBMERSIBLE PUMPS IN
JHARGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
230/PM(F)/P
/1B-
112/2012
17-08-2012 174.93129 129.92006 85% 25-05-2013 129.92006 9 INDIA MARK-
II TUBEWELLS
& 114 MDTW
COMPLETE
39.1 REPAIRING OF BITUMEN
ROAD FROM BINPUR TO
PAPATPUR NODIGHAT
AND BOXI VIA HARDA AND
MURGIMORE, BINPUR-I
BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
265/PM(F)/P
/1B-
141/2012
27-08-2012 9.87435 9.21765 100% 9.21765 COMPLETE
39.2 REPAIR OF BITUMEN
ROAD FROM MURGI
MORE TO BOXI, BINPUR-I
BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
265/PM(F)/P
/1B-
141/2012
27-08-2012 9.52170 7.46780 100% 7.46780 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
40 CONSTRUCTION OF
HOSTEL BUILDING AT
JOYPUR ST, SC & BC HIGH
SCHOOL (HS), SALBONI
BLOCK
BLOCK DEVELOPMENT
OFFICER, SALBONI BLOCK
271/PM(F)/P
/1B-
181/2012
28-08-2012 24.41466 22.04488 80% 22.04488 WORK IN
PROGRESS
41 CONSTRAUCTION OF
BOUNDARY WALL AT
ANDHARIA RAJBALLAV
HIGH SCHOOL AT
ANDHARIA
SCHOOL AUTHORITY,
ANDHARIA RAJBALLAV HIGH
SCHOOL
300/PM(F)/P
/1B-
139/2011
14-09-2012 24.98108 12.49054
42 SINKING OF 2 (TWO) DEEP
TUBE-WELL IN NUYASAI
AND BORADANGA
VILLAGE, NAYAGRAM
DEVELOPMENT BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
307/PM(F)/P
/1B-82/2012
19-09-2012 10.00000
43.1 CONSTRUCTION OF
CONCRETE ROAD WITH
GUARD WALL FROM
JHARBONI TO RAJABUNDH
(447.50 MTR.)
DISTRICT MAGISTRATE,
PASCHIM MEDINIPUR
308/PM(F)/P
/1B-
191/2012
19-09-2012 25.00411 25.00411 DM HAS ASKED
BDO,
NAYAGRAM TO
INITIATE
TENDER
PROCESS
43.2 CONSTRUCTION OF
CONCRETE ROAD WITH
PUCCA DRAIN IN THE
VILLAGE NEMAINAGAR
DISTRICT MAGISTRATE,
PASCHIM MEDINIPUR
308/PM(F)/P
/1B-
191/2012
19-09-2012 24.95039 24.95039 DM HAS ASKED
BDO,
NAYAGRAM TO
INITIATE
TENDER
PROCESS
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
44 CONSTRUCTION OF
BOUNDARY WALL AT
BARUA MSK, SIROMONI
GRAM PANCHAYAT,
MIDNAPUR SADAR
PANCHAYAT SAMITY
BLOCK DEVELOPMENT
OFFICER, MIDNAPUR SADAR
BLOCK
309/PM(F)/P
/1B-
190/2012
19-09-2012 9.50534 9.50534 100% 9.50534 COMPLETE
45.1 INSTALLATION OF MINI
DEEP TUBE-WELL FOR
IRRIGATION WATER
SUPPLY WITHIN
GARHBETA-III BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
311/PM(F)/P
/1B-85/2012
21-09-2012 4.25000 WORK ORDER
NOT YET
ISSUED
45.2 CONSTRUCTION OF
MODEL PUMP HOUSE IN
GARHBETA-III PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
311/PM(F)/P
/1B-85/2012
21-09-2012 0.43965 NIT ISSUED ON
10/10/2012
45.3 CONSTRUCTION OF
PROPOSED GROUND
FLOOR OF NEW BUILDING
OF KIABONI HIGH
SCHOOL, GARHBETA-III PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
311/PM(F)/P
/1B-85/2012
21-09-2012 24.83621 10% 30-11-2013 WORK
STARTED
45.4 CONSTRUCTION OF
PROPOSED FIRST FLOOR
OF NEW BUILDING OF
KIABONI HIGH SCHOOL,
GARHBETA-III PS
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
311/PM(F)/P
/1B-85/2012
21-09-2012 16.90667 10% 30-11-2013 WORK
STARTED
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
46.1 CONSTRUCTION OF
BUILDING OF CIRCLE LEVEL
TRAINING HALL AT
CHANDRAKONA ROAD
WITHIN GARHBETA-III PS
BLOCK DEVELOPMENT
OFFICER, GARHBETA-III
BLOCK
314/PM(F)/P
/1B-
174/2012
24-09-2012 11.50839
46.2 SUBMERSIBLE PUMP FOR
DRINKING WATER SUPPLY
PURPOSE AT
CHANDRAKONA ROAD S.I.
OF SCHOOL, GARHBETA
SOUTH CIRCLE, GARHBETA-
III PS
BLOCK DEVELOPMENT
OFFICER, GARHBETA-III
BLOCK
314/PM(F)/P
/1B-
174/2012
24-09-2012 2.31251
47 CONSTRUCTION OF FIRST
FLOOR SCHOOL BUILDING
AT BAGHPICHLA MSK,
SALBONI BLOCK
BLOCK DEVELOPMENT
OFFICER, SALBONI BLOCK
316/PM(F)/P
/1B-
173/2012
25-09-2012 11.09307 10.75146 100% 10.75146 COMPLETE
48 CONSTRUCTION OF
SINGLE STORIED
CLASSROOM WITH
STAIRCASE AND
BOUNDARY WALL OF
ORGANJA SHRI
RAMKRISHNA SARADA
VIDYANIKETAN
SCHOOL AUTHORITY,
ORGANJA SHRI
RAMKRISHNA SARADA
VIDYANIKETAN
317/PM(F)/P
/1B-16/2010
25-09-2012 8.32500 4.16250
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
49 RENOVATION OF AGRO
INDUSTRIAL TRAINING
CENTRE, JHARGRAM
BLOCK
BLOCK DEVELOPMENT
OFFICER, JHARGRAM BLOCK
331/PM(F)/P
/1B-
195/2012
01-10-2012 4.68177 4.68177 100% 15-01-2013 4.68177 COMPLETE
50 CONSTRUCTION OF
BUILDING AT
KANCHADAHARI-
GUIADAHA HIGH
MADRASAH (10,57,801/-)
& SINKING OF 6 NOS. OF
DEEP TUBE-WELLS
(12,00,000/-) IN
DIFFERENT PLACES
WITHIN GARHBETA-III PS
BLOCK DEVELOPMENT
OFFICER, GARHBETA-III
BLOCK
332/PM(F)/P
/1B-
194/2012
01-10-2012 22.57801 9.68232 50% 9.68232 MADRASAH'S
WORK
COMPLETE
51 REPAIRING THE PUCCA
ROAD (8.4 KM) FROM
KHALSEULI TO MALANCHA
(KHARAGPUR), BINPUR-I
BLOCK
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
335/PM(F)/P
/1B-
196/2012
04-10-2012 199.99948 20% WORK IN
PROGRESS
52.1 CONSTRUCTION OF
BOUNDARY WALL OF
NETAI JUNIOR HIGH
SCHOOL
SCHOOL AUTHORITY, NETAI
JUNIOR HIGH SCHOOL
341/PM(F)/P
/1B-49/2012
09-10-2012 8.71574 8.71574 50% 4.35787 WORK IN
PROGRESS
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
52.2 CONSTRUCTION OF
GOUND FLOOR OF
SCHOOL BUILDING OF
NETAI JUNIOR HIGH
SCHOOL
SCHOOL AUTHORITY, NETAI
JUNIOR HIGH SCHOOL
341/PM(F)/P
/1B-49/2012
09-10-2012 13.02039 13.02039 50% 6.51020 WORK IN
PROGRESS
53 SPECIAL REPAIRING IN
DAMAGED STEEL FRAMED
BRIDGE ON NAHARKHAL,
JHARGRAM BLOCK
DISTRICT MAGISTRATE,
PASCHIM MEDINIPUR
354/PM(F)/P
/1B-
212/2012
17-10-2012 7.88511 7.88511
54 CONSTRUCTION OF
HOSTEL BUILDING AT
SATRANGI VIVEKANANDA
HIGH SCHOOL,
KHARAGPUR-II BLOCK
TEACHER-IN-CHARGE,
SATRANGI VIVEKANANDA
HIGH SCHOOL
356/PM(F)/P
/1B-
213/2012
18-10-2012 17.73412 17.73412 100% 17.73412 COMPLETE
55 CONSTRUCTION OF FOUR
CLASSROOMS AT
MALANCHA HIGH
SCHOOL, GOPIBALLAVPUR-
II BLOCK
TEACHER-IN-CHARGE,
MALANCHA HIGH SCHOOL
361/PM(F)/P
/1B-
169/2012
30-10-2012 28.32338 28.32338 55% 14.16169 WORK IN
PROGRESS
56 CONSTRUCTION OF
CLASSROOM IN
MIDNAPORE TOWN
WELFARE SOCIETY WITHIN
SOCIETY TRAINING
CENTRE (VIKASH)
COMPOUND, MEDINIPUR
SADAR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
380/PM(F)/P
/1B-
232/2012
21-11-2012 16.33982 10.14014 80% 10.14014 WORK IN
PROGRESS
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
57 CONSTRUCTION OF
INSTITUTIONAL BUILDING
(GROUND FLOOR) FOR
SATSOLE KIRANMOYEE
HIGH SCHOOL (H.S.),
PHASE-I, ANANDAPUR
P.S., KESHPUR
SCHOOL AUTHORITY,
SATSOLE KIRANMOYEE HIGH
SCHOOL (H.S.)
388/PM(F)/P
/1B-
226/2012
23-11-2012 24.54446 24.54446 50% 12.27223 WORK IN
PROGRESS
58 ARRANGEMENT OF
FOOTBALL TOURNAMENT
AND ARCHERY
TOURNAMENT IN
AMLASOLE AND ITS
SURROUNDING AREA,
PASCHIM MEDINIPUR
SECRETARY, DURBAR
MAHILA SAMANWAYA
COMMITTEE
399/PM(F)/P
/1B-53/2012
04-12-2012 1.69125 1.69125 100% 1.69125 COMPLETE
59 CONSTRUCTION OF
GROUND FLOOR SCHOOL
BUILDING AT TALNANNA
MADRASAH SIKSHA
KENDRA, MUGBASAN GP,
KESHPUR BLOCK
BLOCK DEVELOPMENT
OFFICER, KESHPUR BLOCK
400/PM(F)/P
/1B-
131/2012
04-12-2012 18.11025 15.38467 75% 15.38467 WORK IN
PROGRESS
60 CONSTRUCTION OF
BOUNDARY WALL AT
SEVAYATAN SIKSHAN
MAHAVIDYALAYA AT
JHARGRAM (IN 3 PART,
TOTAL 580 METRE)
EXECUTIVE ENGINEER,
VIDYASAGAR UNIVERSITY
DIVISION, P.W.(C.B.) DTE.,
P.W.DEPTT.
404/PM(F)/P
/1B-
184/2012
06-12-2012 34.95322 34.95322
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
61 CONSTRUCTION OF
BOUNDARY WALL AND
EXTENSION AND
RENOVATION WORK OF
SCHOOL BUILDING AT
CHAKMAKRAMPPUR HIGH
SCHOOL
HEADMASTER,
CHAKMAKRAMPUR HIGH
SCHOOL, P.O. -
CHAKMAKRAMPUR, DIST. -
PASCHIM MEDINIPUR,
721149
408/PM(F)/P
/1B-
218/2012
11-12-2012 29.21601 29.21601 55% 14.60801 WORK IN
PROGRESS
62 INSTALLATION/ SINKING
OF 7 NOS. OF MINI DEEP
TUBE-WELLS IN DIFFERENT
MOUZAS (DUKI,
DWARIGERIA(NORTH),
BHOGISOLE,
GHOSHKHIRA, GUIADAHA,
NABKOLA AND AT
GURAHARA, GUJRAT &
KENDERISOLE MOUZA)
WITHIN GARHBETA-III
BLOCK
BLOCK DEVELOPMENT
OFFICER, GARHBETA-III
BLOCK
419/PM(F)/P
/1B-
239/2012
13-12-2012 32.87133 21.35992 65% 21.35992 4 SCHEME AT
DUKI,
DWARIGERIA(N
ORTH),
GHOSHKHIRA &
GUIADAHA
COMPLETE
63 SINKING OF ONE MINI
DEEP TUBE-WELL AT
MOHASOLE MOUZA
WITHIN SALBONI BLOCK
BLOCK DEVELOPMENT
OFFICER, SALBONI BLOCK
420/PM(F)/P
/1B-
239/2012
13-12-2012 4.14910 4.03005 100% 4.03005 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
64 SINKING OF 8 NOS. (@
`8.64647 LAC) MINI DEEP
TUBE-WELLS IN DIFFERENT
MOUZAS (UMRAPATA,
JAMSOLE, BHURUBONI,
DUMURIA,
CHHOTONAKDONA,
BATHANTORE,
HAMARGORA,
GANGDUARI), GARHBETA-
II BLOCK
BLOCK DEVELOPMENT
OFFICER, GARHBETA-II
BLOCK
421/PM(F)/P
/1B-
239/2012
13-12-2012 69.17176 45.90722 100% 45.90722 COMPLETE
65 DISTRIBUTION OF SPORTS
KITS TO 75 NOS. OF
CLUBS/ YOUTH
ORGANIZATIONS WITHIN
FIVE ASSEMBLY
CONSTITUENCIES OF
JHARGRAM SUB-DIVISION
422/PM(F)/P
/1B-
257/2012
14-12-2012 16.50000 15.28800 100% 15.28800 COMPLETE
66 CONSTRUCTION OF
BRIDGE OVER BAGDIHA
KHAL, GOPIBALLAVPUR-I
BLOCK
BLOCK DEVELOPMENT
OFFICER, GOPIBALLAVPUR-I
BLOCK
425/PM(F)/P
/1B-90/2012
18-12-2012 22.61065
67 CONSTRUCTION OF RCC
BOX BRIDGE AT
KAMALPUR SAKAMUHI
KHAL, NAYAGRAM
PANCHAYAT SAMITY
EXECUTIVE OFFICER,
NAYAGRAM PANCHAYAT
SAMITY
428/PM(F)/P
/1B-
251/2012
18-12-2012 23.03097 23.03097
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
68 CONSTRUCTION OF
OLDAGE HOME OF RED
CROSS SOCIETY AT
JHARGRAM
SECRETARY, RED CROSS
SOCIETY, JHARGRAM SUB-
DIVISIONAL BRANCH
433/PM(F)/P
/1B-
113/2012
18-12-2012 4.84250 4.84250
69 FITTING & INSTALLATION
FOR SUPPLYING SAFE
PURIFIED RURAL
COMMUNITY DRINKING
WATER FOR 9 NOS.
PHC/BPHC/RH AT AN
ESTIMATED COST OF
27.56771 LAC EACH
NAMELY LALGARH PHC
(BINPUR-I), CHINCHIRA
PHC (JAMBONI),
CHILKIGARH BPHC
(JAMBONI), BINPUR RH
(BINPUR-I), BELPAHARI RH
(BINPUR-II),
GOPIBALLAVPUR RH
(GOPIBALLAVPUR-I),
TOPSIA RH
(GOPIBALLAVPUR-II),
KHARIKAMATHANI RH
(NAYAGRAM),
BHANGAGARH RH
(SANKRAIL) WITHIN
JHARGRAM SUB-DIVISION
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
440/PM(F)/P
/1B-
264/2012
28-12-2012 248.10939 247.99388 100% 30-06-2013 247.99388 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
70 CONSTRUCTION OF
BOUNDARY WALL AT
DEBAGRAM MAHADEV
HIGH SCHOOL UNDER
SALBONI BLOCK
SCHOOL AUTHORITY,
DEBAGRAM MAHADEV HIGH
SCHOOL
04/PM(F)/P/
1B-263/2012
10-01-2013 14.84400 14.84400 55% 7.42200 WORK IN
PROGRESS
71 INFRASTRUCTURAL
DEVELOPMENT OF SILDA
CHANDRA SEKHAR
COLLEGE
EXECUTIVE ENGINEER-I,
P.W.D., KHARAGPUR
DIVISION
08/PM(F)/P/
1B-
67/2008(Par
t-IV)
15-01-2013 100.00000 100.00000
72.1 CONSTRUCTION OF
HOSTEL BUILDING AT
GARHBETA HIGH SCHOOL,
GARHBETA-I BLOCK
BLOCK DEVELOPMENT
OFFICER, GARHBETA-I
BLOCK
14/PM(F)/P/
1B-262/2012
24-01-2013 28.17772 16.59022 60% 16.59022 WORK IN
PROGRESS
72.2 CONSTRUCTION OF
SCHOOL BUILDING AT
GARHBETA HIGH SCHOOL,
GARHBETA-I BLOCK
BLOCK DEVELOPMENT
OFFICER, GARHBETA-I
BLOCK
14/PM(F)/P/
1B-262/2012
24-01-2013 24.95645 18.55971 60% 18.55971 WORK IN
PROGRESS
73 CONSTRUCTION OF
BOUNDARY WALL AT
JANARDANPUR HIGH
SCHOOL, KHARAGPUR-II
PS
SCHOOL AUTHORITY,
JANARDANPUR HIGH
SCHOOL
15/PM(F)/P/
1B-261/2012
24-01-2013 3.63184 3.63184 100% 3.63184 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
74 CONSTRUCTION OF 10
NOS. OF RAIN WATER
HARVESTING TANK
(RWHT) IN DIFF. BLOCKS
DM THROUGH EE(AI),
JHARGRAM (AI) DIVISION
21/PM(F)/P/
1B-05/2013
30-01-2013 75.10019 75.10019
75 SINKING OF 10 NOS. OF
MINI DEEP TUBE-WELLS
(6.34440 EACH),
NAYAGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
24/PM(F)/P/
1B-03/2013
30-01-2013 63.44400
76 ADDITIONAL FUND FOR
AWARDING 1888 NOS. OF
BICYCLES TO TRIBAL GIRL
STUDENTS OF CLASS X, XI
& XII OF PASCHIM
MEDINIPUR
DISTRICT MAGISTRATE,
PASCHIM MEDINIPUR
31/PM(F)/P/
1B-02/2011
05-02-2013 20.80120 20.80120
77.1 CONSTRUCTION OF RCC
BOX CULVERT AT
JAMSOLA OVER MAHULIA
KHAL, NAYAGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
33/PM(F)/P/
1B-243/2012
07-02-2013 22.51000 BDO
REQUESTED
VIDE NO.
379/PUP/BNK/
1A-04/12 DT.
20-02-2013
77.2 CONSTRUCTION OF BOX
CULVERT AT JARKA OVER
NAYAGRAM-ATMAJHIA
ROAD , NAYAGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
33/PM(F)/P/
1B-243/2012
07-02-2013 23.03000 22.91880 100% 22.91880 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
77.3 CONSTRUCTION OF
BANSPAT BOX CULVERT AT
BANSPAT, NAYAGRAM
BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
33/PM(F)/P/
1B-243/2012
07-02-2013 7.00000 BDO
REQUESTED
VIDE NO.
379/PUP/BNK/
1A-04/12 DT.
20-02-2013
77.4 CONSTRUCTION OF RCC
BOX CULVERT AT
BARSOLE, NAYAGRAM
BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
33/PM(F)/P/
1B-243/2012
07-02-2013 7.83000 BDO
REQUESTED
VIDE NO.
379/PUP/BNK/
1A-04/12 DT.
20-02-2013
77.5 CONSTRUCTION OF BOX
CULVERT AT TOPOBAN
OVER TOPOBAN BARSULI
ROAD, NAYAGRAM BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
33/PM(F)/P/
1B-243/2012
07-02-2013 7.00000 BDO
REQUESTED
VIDE NO.
379/PUP/BNK/
1A-04/12 DT.
20-02-2013
77.6 CONSTRUCTION OF RCC
BOX CULVERT OVER
SITALANA KHAL AT
KEYAJHARIA, NAYAGRAM
BLOCK
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
33/PM(F)/P/
1B-243/2012
07-02-2013 14.59000 BDO
REQUESTED
VIDE NO.
379/PUP/BNK/
1A-04/12 DT.
20-02-2013
78.1 PIPE LINE WATER SUPPLY
AT MURAKATI JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
78.2 PIPE LINE WATER SUPPLY
AT KHAMARMOHULI JR.
HIGH SCHOOL, SANKRAIL
BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
78.3 PIPE LINE WATER SUPPLY
AT KUKURAKHUPI JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
78.4 PIPE LINE WATER SUPPLY
AT SIMULIA JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
78.5 PIPE LINE WATER SUPPLY
AT DURGAPUR JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
78.6 PIPE LINE WATER SUPPLY
AT BAHARADANRI JR.
HIGH SCHOOL, SANKRAIL
BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
78.7 PIPE LINE WATER SUPPLY
AT HARIPURA JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
78.8 PIPE LINE WATER SUPPLY
AT ANDHARI JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
78.9 PIPE LINE WATER SUPPLY
AT KASHIDANGA JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 TENDER
INVITED ON 20-
02-2013
78.10 PIPE LINE WATER SUPPLY
AT CHHATRI JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 2.34185 100% 2.34185 COMPLETE
78.11 PIPE LINE WATER SUPPLY
AT BAKRA JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 1.81459 100% 1.81459 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
78.12 PIPE LINE WATER SUPPLY
AT CHUNPARA JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 1.79130 100% 1.79130 COMPLETE
78.13 PIPE LINE WATER SUPPLY
AT NEKRASULI JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 1.99820 100% 1.99820 COMPLETE
78.14 PIPE LINE WATER SUPPLY
AT BANKATI JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 2.02123 100% 2.02123 COMPLETE
78.15 PIPE LINE WATER SUPPLY
AT BHAMAL JR. HIGH
SCHOOL, SANKRAIL BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 1.52722 100% 1.52722 COMPLETE
78.16 PIPE LINE WATER SUPPLY
AT PECHABINDHYA JR.
HIGH SCHOOL, SANKRAIL
BLOCK
BLOCK DEVELOPMENT
OFFICER, SANKRAIL BLOCK
34/PM(F)/P/
1B-243/2012
07-02-2013 2.50000 1.74802 100% 1.74802 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
79.1 CONSTRUCTION OF
CONCRETE ROAD FROM
GOPIBALLAVPUR THANA
CHOWK TO GOBINDA
MANDIR, GOPIBALLAVPUR-
I BLOCK
BLOCK DEVELOPMENT
OFFICER, GOPIBALLAVPUR-I
BLOCK
35/PM(F)/P/
1B-243/2012
07-02-2013 19.36000 19.36000 100% 19.36000 COMPLETE
79.2 CONSTRUCTION OF
CAUSEWAY AT
CHUTARPATA,
GOPIBALLAVPUR-I BLOCK
BLOCK DEVELOPMENT
OFFICER, GOPIBALLAVPUR-I
BLOCK
35/PM(F)/P/
1B-243/2012
07-02-2013 7.12000 7.01092 100% 7.01092 COMPLETE
79.3 CHECK DAM AT
ANDHARKULI,
GOPIBALLAVPUR-I BLOCK
BLOCK DEVELOPMENT
OFFICER, GOPIBALLAVPUR-I
BLOCK
35/PM(F)/P/
1B-243/2012
07-02-2013 7.74000 TENDER
INVITED ON 25-
02-2013
80.1 CONSTRUCTION OF
GUARD WALL AT
BAKULTALA TO PAIKUIBAR
AT MAHULI,
GOPIBALLAVPUR-II BLOCK
BLOCK DEVELOPMENT
OFFICER, GOPIBALLAVPUR-II
BLOCK
36/PM(F)/P/
1B-243/2012
07-02-2013 3.00000 3.00000 100% 3.00000 COMPLETE
80.2 CONSTRUCTION OF
CULVERT AT EKDAL
VILLAGE, GOPIBALLAVPUR-
II BLOCK
BLOCK DEVELOPMENT
OFFICER, GOPIBALLAVPUR-II
BLOCK
36/PM(F)/P/
1B-243/2012
07-02-2013 2.11000 BDO
REQUESTED
VIDE NO.
378/PUP/BNK/
1A-04/12 DT.
20-02-2013
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
80.3 CONSTRUCTION OF
CULVERT NEAR EKUR PRY.
SCHOOL, GOPIBALLAVPUR-
II BLOCK
BLOCK DEVELOPMENT
OFFICER, GOPIBALLAVPUR-II
BLOCK
36/PM(F)/P/
1B-243/2012
07-02-2013 3.46000 3.43955 100% 3.43955 COMPLETE
81 EXCAVATION OF DINHI
BUNDH, GARHBETA-III
PANCHAYAT SAMITY
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
64/PM(F)/1B-
204/2012
05-03-2013 49.67589 100% COMPLETE
82 CONSTRUCTION OF
ADDITIONAL CLASSROOMS
OF KENDIJAMBANI ICDS
CENTRE, GARHBETA-III
BLOCK (ADDL. AMOUNT)
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD THROUGH BDO
65/PM(F)/P/
1B-153/2012
05-03-2013 0.54882 0.41300 100% 0.41300 COMPLETE
83 INFRASTRUCTURAL
DEVELOPMENT
(BOUNDARY WALL
12,91,449/- & SCHOOL
BUILDING 24,74,328/-) OF
SIJUA MSK, BINPUR-I PS
SECRETARY, SIJUA MSK 66/PM(F)/P/
1B-18/2013
05-03-2013 37.65777 37.65777
84 INSTALLATION OF MINI
DEEP TUBE-WELL AT
BARAMESHA MOUZA,
SALBONI BLOCK (ADDL.
SANCTION)
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
70/PM(F)/P/
1B-160/2012
08-03-2013 2.68887 2.17864 100% 2.17864 COMPLETE
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
85 RENOVATION WORK OF
CLASSROOMS AT
JHARGRAM BANITIRTHA
HIGH SCHOOL (HS)
SCHOOL AUTHORITY,
JHARGRAM BANITIRTHA
HIGH SCHOOL (HS)
76/PM(F)/P/
1B-19/2013
14-03-2013 8.21248 8.21248
86.1 CONSTRUCTION OF BORE
WELL AND BOUNDARY
WALL AROUND TRIBAL
HOSTEL ATTACHED AT
KAPGARI SEVA BHARATI
MAHAVIDYALAYA,
KAPGARI MOUZA
TEACHER-IN-CHARGE,
KAPGARI SEVA BHARATI
MAHAVIDYALAYA
78/PM(F)/P/
1B-31/2013
18-03-2013 6.93129 6.93129
86.2 ADDITION AND
ALTERATION OF GROUND
FLOOR AND FIRST FLOOR
OF TRIBAL HOSTEL
BUILDING AT KAPGARI
SEVA BHARATI
MAHAVIDYALAYA,
KAPGARI MOUZA
TEACHER-IN-CHARGE,
KAPGARI SEVA BHARATI
MAHAVIDYALAYA
78/PM(F)/P/
1B-31/2013
18-03-2013 44.67335 44.67335 55% WORK IN
PROGRESS
87 DEVELOPMENT OF PLAY
GROUND AT AMLASOLE
UNDER BINPUR-II BLOCK
(TOTAL SANCTION -
1,02,452/-)
DURBAR MAHILA
SAMANWAYA COMMITTEE,
KOLKATA
79/PM(F)/P/
1B-32/2013
19-03-2013 0.14860 0.14860
` IN LAC
NO. DATE
DISTRICT: PASCHIM MEDINIPURDETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED REMARKSPHYSICAL
PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
EXPECTED DATE
OF
COMPLETION
88 CONSTRUCTION OF RCC
SLAB CULVERT OVER
BAJUDIHA KHAL UNDER
BERAJAL GRAM
PANCHAYAT, NAYAGRAM
PANCHAYAT SAMITY
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
96/PM(F)/P/
1B-91/2012
18-03-2013 27.20384 26.60348 100% 26.60348 COMPLETE
89.1 NERAKOPA MINI PIPED
WATER SUPPLY SCHEME,
GARHBETA-III PANCHAYAT
SAMITY
EXECUTIVE ENGINEER,
MIDNAPORE MECHANICAL
DIVISION, PHE DTE.,
PASCHIM MEDINIPUR
97/PM(F)/P/
1B-125/2012
18-03-2013 18.67077 18.67077
89.2 DWARIGERIA MINI PIPED
WATER SUPPLY SCHEME,
GARHBETA-III PANCHAYAT
SAMITY
EXECUTIVE ENGINEER,
MIDNAPORE MECHANICAL
DIVISION, PHE DTE.,
PASCHIM MEDINIPUR
97/PM(F)/P/
1B-125/2012
18-03-2013 17.95473 17.95473
90 CONSTRUCTION OF
HOSTEL BUILDING
ATTACHED TO SALANGA
GOPINATHPUR
VIVEKANANDA VIDYAPITH
(HIGH SCHOOL), KESHPUR
BLOCK
SCHOOL AUTHORITY,
SALANGA GOPINATHPUR
VIVEKANANDA VIDYAPITH
(HIGH SCHOOL)
101/PM(F)/P
/1B-20/2013
26-03-2013 24.99440 24.99440 60% 12.49720 WORK IN
PROGRESS
TOTAL: 5058.71832 3414.74922 2209.19734
` IN LAC
NO. DATE1.1 CONST. OF GARDIH
VILLAGE ROAD P.C.C. AT
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 2.86800 2.70086 100% 12-11-2012 2.70086 COMPLETED
1.2 IMPROVEMENT OF ROAD
FROM HELIPAD TO TURGA
FALLS IN BAGHMUNDI
GRAM PANCHAYAT (PART-
I)
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 24.02200 17.16683 100% 28-11-2012 17.16683 COMPLETED
1.3 CONST. OF SOPARAMBERA
NICHPARA TO UPAR PARA
P.C.C. ROAD IN AJODHYA
GRAM PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 9.03500 7.52028 100% 15-10-2012 7.52028 COMPLETED
1.4 CONST. OF KULTAR
VILLAGE ROAD P.C.C. AT
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 5.72000 5.72000 100% 5.72000 COMPLETED
1.5 CONST. OF SIMULBERA
VILLAGE ROAD P.C.C. AT
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 2.61000 2.61000 100% 25-11-2012 2.61000 COMPLETED
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
1.6 CONST. OF PUNIASASAN
UP ROAD P.C.C. AT
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 6.00000 6.00000 100% 15-11-2012 6.00000 COMPLETED
1.7 CONST. OF JAMGHUTU
GRAMIN ROAD P.C.C. AT
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 2.61000 2.61000 100% 24-08-2012 2.61000 COMPLETE
1.8 CONST. OF KENDGUTU TO
BHURSABERA P.C.C. ROAD
AT AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 3.04000 3.01176 100% 3.01176 COMPLETE
1.9 CONST. OF DUNGRI
VILLAGE P.C.C. ROAD IN
BURDA-KALIMATI GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 15.04900 13.27616 100% 13.27616 COMPLETE
1.10 CONST. OF ICHHAKOTO
VILLAGE P.C.C. ROAD IN
BURDA-KALIMATI GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 15.04900 13.47469 100% 13.47469 COMPLETE
1.11 CONST. OF BASARE TO
DUNGRIDIH ROAD IN
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 6.17200 6.17200 100% 30-08-2012 6.17200 COMPLETE
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
1.12 CONST. OF SONAHARA
VILLAGE P.C.C. ROAD IN
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 2.91900 2.91900 100% 31-08-2012 2.91900 COMPLETE
1.13 CONST. OF BHUINGHORA
VILLAGE P.C.C. ROAD IN
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 5.82300 5.57933 100% 19-10-2012 5.57933 COMPLETED
1.14 CONST. OF HATINADA
VILLAGE P.C.C. ROAD IN
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 5.85700 5.70125 100% 18-08-2012 5.70125 COMPLETED
1.15 CONST. OF DARUDIH
VILLAGE P.C.C. ROAD IN
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 5.89000 5.89000 100% 11-10-2012 5.89000 COMPLETED
1.16 CONST. OF BONGADA
(SANTAL PARA) VILLAGE
P.C.C. ROAD IN AJODHYA
GRAM PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 5.79000 5.79000 100% 14-02-2013 5.79000 COMPLETED
1.17 CONST. OF KAMLABAHAL
VILLAGE P.C.C. ROAD IN
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 5.84000 5.84000 100% 5.84000 COMPLETED
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
1.18 CONST. OF KUCHRIRAKHA
VILLAGE P.C.C. ROAD IN
AJODHYA GRAM
PANCHAYAT
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
82/PM(F)/P/
1B-69/2012
03-05-2012 5.75500 5.75500 100% 08-11-2012 5.75500 COMPLETED
2 CONSTRUCTION OF SMALL
CULVERTS AND GUARD
WALL ON PUCCA ROAD
ALONG WITH PCC TO
PROPOSED BAGHMUNDI
POLYTECHNIC SITE IN
BAGHMUNDI BLOCK
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
97/PM(F)/P/
1B-83/2012
31-05-2012 20.21388 10.97533 10.68147 WORK
COMPLETE FOR
CULVERT &
GUARD WALL;
ROAD NOT
STARTED AS
ESTIMATE
REVISED
3.1 CONSTRUCTION OF
INCOMPLETE ROAD AT
KALIMELA UNDER
SALTORE G.P.
BLOCK DEVELOPMENT
OFFICER, NETURIA BLOCK
112/PM/P/1
B-101/2012
11-06-2012 2.00000 BDO HAS BEEN
REQUESTED TO
SUBMIT
ALTERNATIVE
SCHEME AS
THE
SANCTIONED
SCHEME
ALREADY
COMPLETED
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
3.2 CONSTRUCTION OF ROAD
AT NABAGRAM,
KHAWASPARA
BLOCK DEVELOPMENT
OFFICER, NETURIA BLOCK
112/PM/P/1
B-101/2012
11-06-2012 2.50000 BDO HAS BEEN
REQUESTED TO
TAKE UP THE
SCHEME VIDE
NO.
807/PUP/BNK/
1S-116/12
DATED 18-07-
2012
4 CONSTRUCTION OF
GROUND FLOOR OF
KOTSHILA
MAHAVIDYALAYA AT
KOTSHILA, P.O.-JIUDARU
BLOCK DEVELOPMENT
OFFICER, JHALDA-II BLOCK
113/PM(F)/P
/1B-96/2012
11-06-2012 114.88371 59.54367 50% 59.54367 WORK IN
PROGRESS
5 CONSTRUCTION OF
COMMUNITY HALL AT
TUNTURI
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
114/PM(F)/P
/1B-
110/2012
12-06-2012 13.35423 6.54633 40% 6.54633 WORK IN
PROGRESS
6 CONSTRUCTION OF
JHALDA SATYABHAMA
VIDYAPITH HOSTEL
BUILDING
BLOCK DEVELOPMENT
OFFICER, JHALDA-I BLOCK
115/PM(F)/P
/1B-
110/2012
12-06-2012 16.90770 10.92300 80% 10.92300 NIT ISSUED ON
25/07/2012
7 CONSTRUCTION OF 3 NOS.
CLASSROOM AND
BOUNDARY WALL AT
KASHIDIH C.R.C.G.
VIDYAPITH
HEADMASTER, KASHIDIH
C.R.C.G. VIDYAPITH
120/PM(F)/P
/1B-
107/2012
12-06-2012 39.31213 39.31213 50% 30.55910 WORK IN
PROGRESS
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
8 CONSTRUCTION OF
SCHOOL BUILDING OF
JITUJURI DEBASISH HIGH
SCHOOL (H.S.)
HEADMASTER, JITUJURI
DEBASISH HIGH SCHOOL
(H.S.)
121/PM(F)/P
/1B-
108/2012
12-06-2012 21.66977 10.83488
9 CONSTRUCTION OF
HOSTEL BUILDING AND
SCHOOL BOUNDARY WALL
AT TATARI-KENDADIH
HIGH SCHOOL
HEADMASTER, TATARI-
KENDADIH HIGH SCHOOL
122/PM(F)/P
/1B-
109/2012
12-06-2012 25.13340 25.13340 100% 25.13340 COMPLETE
10 CONSTRUCTION OF TWO
CLASS ROOM AT
BADALDIH HIGH SCHOOL,
BARABAZAR BLOCK
BLOCK DEVELOPMENT
OFFICER, BARABAZAR BLOCK
123/PM(F)/P
/1B-
103/2012
12-06-2012 14.13534 11.41001 100% 11.41001 COMPLETE
11 IMPROVEMENT OF ROAD
FROM ANARA SHIV
MANDIR TO ANARA BUS
STAND (1.60 KM), PARA
BLOCK DEVELOPMENT
OFFICER, PARA BLOCK
124/PM(F)/P
/1B-
114/2012
12-06-2012 14.28769 14.28769 100% 14.28769 COMPLETE
12 CONSTRUCTION OF TWO
CLASS ROOM AT
KHARIDURA HIGH
SCHOOL, MANBAZAR-II
BLOCK DEVELOPMENT
OFFICER, MANBAZAR-II
BLOCK
127/PM(F)/P
/1B-
104/2012
12-06-2012 14.13534 11.99356 100% 15-02-2012 11.78770 COMPLETE
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
13 CONSTRUCTION OF
BOUNDARY WALL, REPAIR
AND RENOVATION OF
BUILDING OF MUDALI
R.N.M. HIGH SCHOOL,
ARSHA
BLOCK DEVELOPMENT
OFFICER, ARSHA BLOCK
128/PM(F)/P
/1B-
102/2012
13-06-2012 26.42877 25.86574 100% 25.86574 COMPLETE
14 EXCAVATION OF A SILTED
POND AT KHUKRAMURA
VILLAGE, ARSHA
SECRETARY, RAMAKRISHNA
MISSION VIDYAPITH,
PURULIA
141/PM(F)/P
/1B-
122/2012
25-06-2012 24.99686 24.99686 100% 23.47824 COMPLETE
15 PIPED LINE DRINKING
WATER SUPPLY FOR 97
NOS. ANGANWADI
CENTRES AT KASHIPUR &
NETURIA BLOCKS
DISTRICT MAGISTRATE,
PURULIA
144/PM(F)/P
/1B-
121/2012
25-06-2012 9.26611 9.26611 100% COMPLETE
16 CONSTRUCTION OF A
LIBRARY AND READING
ROOM CUM COMMUNITY
HALL AT RAMAKRISHNA
MATH, BAGDA
ADHYAKSHA, RAMAKRISHNA
MATH, BAGDA, PURULIA
145/PM(F)/P
/1B-
123/2012
25-06-2012 25.00000 25.00000 65% 23.25967 WORK IN
PROGRESS
17 CONSTRUCTION OF
BIDHAKATA JORE-CUM-
CULVERT
BLOCK DEVELOPMENT
OFFICER, SANTURI BLOCK
159/PM(F)/P
/1B-
136/2012
11-07-2012 24.86748 WORK ORDER
ISSUED ON 19-
10-2012
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
18.1 CONSTRUCTION OF
CLASSROOMS AT
GHATBERA KEROWA H.S.
SCHOOL
BLOCK DEVELOPMENT
OFFICER, BALARAMPUR
BLOCK
165/PM(F)/P
/1B-
128/2012
12-07-2012 16.94634 16.10281 100% 16.10281 COMPLETE
18.2 DEVELOPMENT OF PLAY
FIELD OF LAGDA HIGH
SCHOOL (H.S.)
BLOCK DEVELOPMENT
OFFICER, PURULIA-I BLOCK
165/PM(F)/P
/1B-
128/2012
12-07-2012 14.17509 11.26578 100% MAY'2013 11.26578 COMPLETE
18.3 UPGRADATION OF
LALMATI GIRLS HIGH
SCHOOL BUILDING
BLOCK DEVELOPMENT
OFFICER, BALARAMPUR
BLOCK
165/PM(F)/P
/1B-
128/2012
12-07-2012 15.15221
18.4 CONSTRUCTION OF ROAD
BRIDGE AT ARABAID JORE
BLOCK DEVELOPMENT
OFFICER, BARABAZAR BLOCK
165/PM(F)/P
/1B-
128/2012
12-07-2012 24.56084
18.5 CONSTRUCTION OF
SAPUJORA CULVERT
UNDER BELA GP
BLOCK DEVELOPMENT
OFFICER, BALARAMPUR
BLOCK
165/PM(F)/P
/1B-
128/2012
12-07-2012 15.81713 WORK ORDER
ISSUED,
SCHEME
RUNNING
18.6 CONSTRUCTION OF
CULVERT WITH
GUARDWALL AT CHITAHA
VILLAGE
BLOCK DEVELOPMENT
OFFICER, BALARAMPUR
BLOCK
165/PM(F)/P
/1B-
128/2012
12-07-2012 6.15369 WORK ORDER
ISSUED,
SCHEME
RUNNING
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
19 CONSTRUCTION OF 1ST
FLOOR BUILDING WITHIN
GARHJOYPUR SHRI SHRI
RAMKRISHNA
VIVEKANANDA ASHRAM
HEADMASTER, GARHJOYPUR
SHRI SHRI RAMKRISHNA
VIVEKANANDA ASHRAM
174/PM(F)/P
/1B-
135/2012
16-07-2012 17.06713 17.06713
20 CONSTRUCTION OF
GROUND FLOOR (PHASE-I:
24.84568 LAC & PHASE-II:
12.32675 LAC) OF A
HOSTEL BUILDING FOR SC,
ST AND OBC STUDENTS AT
THE AJODHYA HILL TOP,
BAGHMUNDI P.S.
SECRETARY, BHARAT
SEVASHRAM SANGHA,
PURULIA
176/PM(F)/P
/1B-
147/2012
16-07-2012 37.17243 37.17243 13.51339 WORK IN
PROGRESS
21.1 EXTENSION OF HOSPITAL
BUILDING AND CONST. OF
STAFF QUARTERS OF
LOKESWARANANDA EYE
FOUNDATION, PARA (50%
OF REMAINING AMOUNT)
SECRETARY, NANRITAM 182/PM(F)/P
/1B-09/2012
24-07-2012 56.56642 56.56642 95% 26.11229
21.2 PURCHASING OF
EQUIPMENTS, INCLUDING
SURGICAL EQUIPMENT,
2ND PHASE OF
LOKESWARANANDA EYE
FOUNDATION, PARA (FULL
REMAINING AMOUNT)
SECRETARY, NANRITAM 182/PM(F)/P
/1B-09/2012
24-07-2012 91.28300 91.28300 95% 85.01005
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
21.3 MOBILE VAN OF
LOKESWARANANDA EYE
FOUNDATION, PARA (FULL
REMAINING AMOUNT)
SECRETARY, NANRITAM 182/PM(F)/P
/1B-09/2012
24-07-2012 1.67708 1.67708 100% 1.67708
22.1 CONSTRUCTION OF PCC
ROAD FROM BAGHRA TO
KOLABANDH, PURULIA-II
BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
207/PM(F)/P
/1B-
163/2012
01-08-2012 19.99650 BDO HAS BEEN
REQUESTED TO
TAKE UP THE
SCHEME VIDE
NO.
988/PUP/BNK/
1S-152/12
DATED 17-08-
2012
22.2 CONSTRUCTION OF PCC
ROAD FROM ARITA TO
DESHRA, PURULIA-II
BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
207/PM(F)/P
/1B-
163/2012
01-08-2012 19.99304 13.84730 100% 13.84730 COMPLETE
22.3 CONSTRUCTION OF PIPE-
CAUSEWAY AT HUTMURA,
PURULIA-II BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
207/PM(F)/P
/1B-
163/2012
01-08-2012 14.77170 14.29116 100% 14.29116 COMPLETE
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
22.4 CONSTRUCTION OF LOW
LEVEL BRIDGE OR
CAUSEWAY AT LALBAZAR-
PURDA, PURULIA-II BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
207/PM(F)/P
/1B-
163/2012
01-08-2012 15.31920 14.86673 100% 14.86673 COMPLETE
23 CONSTRUCTION OF 1ST
FLOOR OF COMMUNITY
HALL AT LALPUR, HURA
BLOCK
BLOCK DEVELOPMENT
OFFICER, HURA BLOCK
270/PM(F)/P
/1B-
182/2012
28-08-2012 48.86409 26.24129 50% 26.04705 WORK IN
PROGRESS
24 CONSTRUCTION OF
SCHOOL BUILDING OF
SIMAKANALI SIDDIKA
MADRASAH SHIKSHA
KENDRA, PUNCHA PS
EXECUTIVE OFFICER,
PUNCHA PS
136/PM(F)/P
/1B-
176/2012
28-05-2013 23.51743 12.10120 50% 12.10120 ONGOING
25 IMPROVEMENT OF ROAD
FROM ANARA SHIV
MANDIR TO ANARA BUS
STAND (PART-B, C, & D),
PARA
BLOCK DEVELOPMENT
OFFICER, PARA BLOCK
277/PM(F)/P
/1B-
114/2012
30-08-2012 75.10098 65.79291 70% 65.79291 WORK IN
PROGRESS
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
26 CONSTRUCTION OF 2ND
FLOOR FOR GYNAE,
PEDIATRIC WARD,
ELECTRICAL INSTALLATION
AND ALLIED WORKS AT
DEBEN MAHATO (SADAR)
HOSPITAL
EXECUTIVE ENGINEER,
P.W.D., WESTERN ELECTICAL
DIVISION NO. - II
279/PM(F)/P
/1B-85/2011
30-08-2012 15.27580 15.27580
27 CONSTRUCTION OF
CLASSROOMS AT BERADA
HIGHER SECONDARY
SCHOOL, BARABAZAR
BLOCK
BLOCK DEVELOPMENT
OFFICER, BARABAZAR BLOCK
280/PM(F)/P
/1B-
179/2012
31-08-2012 24.44847 24.09003 100% 23.73399 COMPLETE
28 CONSTRUCTION OF
BRIDGE ON RIVER
THAKURCHATANI NEAR
GURRABERA, JHALDA-II
BLOCK (ADDITIONAL
FUND)
BLOCK DEVELOPMENT
OFFICER, JHALDA-II BLOCK
324/PM(F)/P
/1B-
166/2011
27-09-2012 7.77867 WORK IN
PROGRESS
29 RE-CONSTRUCTION WITH
REPAIRING OF APPROACH
ROAD OF RANGANITARD
CULVERT UNDER
UPARKAHAN GP
BLOCK DEVELOPMENT
OFFICER, JOYPUR BLOCK
325/PM(F)/P
/1B-
199/2012
27-09-2012 5.13605 4.89772 100% 4.89772 COMPLETE
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
30 CONSTRUCTION OF ROAD
FROM GOPALPUR BUS-
STAND TO BAGDA BUS-
STAND VIA RASUDI (4 KM),
PUNCHA BLOCK (PHASE-I
& PHASE-II)
DISTRICT MAGISTRATE,
PURULIA
326/PM(F)/P
/1B-
198/2012
27-09-2012 52.92606 52.92606 80% 31-05-2013 TENDER
INVITED ON 26-
12-2012
31 CONSTRUCTION OF
BOUNDARY WALL OF
MAIN BUILDING AT
PATHARDIH BPHC,
BAGHMUNDI BLOCK
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
327/PM(F)/P
/1B-
201/2012
27-09-2012 33.32000 15.52902 70% 15.52902 WORK IN
PROGRESS
32 CONSTRUCTION OF CHECK
DAM AT DHANSURA,
BELMA, CHAKIRBAN AND
SENERA AMRA VILLAGE,
PURULIA-II PS
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
338/PM(F)/P
/1B-
162/2012
05-10-2012 34.71569 14.34387 14.34387 BDO HAS BEEN
REQUESTED TO
TAKE UP THE
SCHEME VIDE
NO.
1424/PUP/BNK
/1S-198/12
DATED
12/10/2012
33 ADDITIONAL
EXPENDITURE FOR
CONSTRUCTION OF 18
(EIGHTEEN) NOS. OF PCC
ROAD IN BAGHMUNDI
BLOCK
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
339/PM(F)/P
/1B-69/2012
08-10-2012 10.36500 8.23995 8.23995
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
34.1 CONSTRUCTION OF
CULVERT ON SALDAHA
RIVER AT GOKULNAGAR
MOUZA UNDER JHALDA-I
BLOCK
BLOCK DEVELOPMENT
OFFICER, JHALDA-I BLOCK
346/PM(F)/P
/1B-
205/2012
10-10-2012 24.59000 12.15688 12.15688 WORK IN
PROGRESS
34.2 CONSTRUCTION OF BLACK
TOP ROAD ON BOTH SIDE
OF SALDAHA CULVERT IN
GOKULNAGAR
BLOCK DEVELOPMENT
OFFICER, JHALDA-I BLOCK
346/PM(F)/P
/1B-
205/2012
10-10-2012 12.46029 TENDER
INVITED ON 26-
11-2012
35 CONSTRUCTION OF MAIN
GATE AND TWO NOS. OF
SECURITY ROOMS AT
PURULIA POLYTECHNIC
PRINCIPAL, PURULIA
POLYTECHNIC
350/PM(F)/P
/1B-
207/2012
12-10-2012 5.50742 5.50742 100% 5.50742 COMPLETE
36 CONSTRUCTION OF
CLASSROOMS AT
CHANDRA HIGH SCHOOL
(HS) (ADDITIONAL
AMOUNT)
BLOCK DEVELOPMENT
OFFICER, MANBAZAR-I
BLOCK
352/PM(F)/P
/1B-
134/2011
16-10-2012 3.05053
37 CONSTRUCTION OF A
PATIENT WAITING HALL IN
PHASE-I & PHASE-II AT
BHARAT SEVASHRAM
SANGHA CHARITABLE
DISPENSARIES , PURULIA
SECRETARY, BHARAT
SEVASHRAM SANGHA,
PURULIA
353/PM(F)/P
/1B-
210/2012
17-10-2012 40.43369 40.43369 15.30247
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
38 CONSTRUCTION OF
BOUNDARY WALL &
SCHOOL BUILDING OF
RAMAKRISHNA
VIVEKANANDA MISSION
AT BELKURI
SECRETARY, RAMAKRISHNA
VIVEKANANDA MISSION,
PURULIA
355/PM(F)/P
/1B-
211/2012
18-10-2012 31.07141 31.07141 65% 20.47293 WORK IN
PROGRESS
39 CONSTRUCTION OF
BRIDGE ON TULIN MAGHA
ROAD ON SALDAH RIVER,
JHALDA-I BLOCK
DISTRICT MAGISTRATE,
PURULIA
359/PM(F)/P
/1B-
110/2012 &
364/PM/201
2
19-10-2012 &
02-11-2012
154.81423 154.81423 2% 31-03-2015 TENDER
INVITED ON 26-
12-2012
40.1 CONSTRUCTION OF
CLASSROOMS AT
GENGARA HIGH SCHOOL,
PURULIA-II BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
369/PM(F)/P
/1B-
202/2012
09-11-2012 5.00000 BDO HAS BEEN
REQUESTED TO
TAKE UP THE
SCHEME VIDE
NO.
1688/PUP/BNK
/1S-210/12
DATED
05/12/2012
40.2 CONSTRUCTION OF
CLASSROOMS AT
KHUDIBANDH HIGH
SCHOOL, PURULIA-II
BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
369/PM(F)/P
/1B-
202/2012
09-11-2012 9.95945 9.94479 100% 9.94479 COMPLETE
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
41 CONSTRUCTION OF
GALLERY OF THE STADIUM
FOR TWO BLOCKS AT
MANBHUM VICTORIA
INSTITUTION IN TWO
PHASE
DISTRICT MAGISTRATE,
PURULIA
371/PM(F)/P
/1B-
220/2012
20-11-2012 39.31756 39.31756 55% 31-07-2013 19.65878 WORK IN
PROGRESS
42 CONSTRUCTION WORK OF
EXISTING SCHOOL
BUILDING AT
KUKRUDABAR PRIMARY
SCHOOL, BANDWAN
BLOCK
HEADMASTER,
KUKRUDABAR PRIMARY
SCHOOL, BANDWAN
389/PM(F)/P
/1B-
214/2012
27-11-2012 2.80000 2.80000 2.80000 CONSTRUCTIO
N WORK
COMPLETE
43.1 CONSTRUCTION OF PCC
ROAD FROM BILTORA
DEOGHORIA PARA TO
BAURI BANDH, PURULIA-II
BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
391/PM(F)/P
/1B-
215/2012
27-11-2012 3.50000 0.08436
43.2 CONSTRUCTION OF PCC
ROAD FROM NADIHA
ROAD TO PURANDIH VIA
MALTHORE, BELMA,
PURULIA-II BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
391/PM(F)/P
/1B-
215/2012
27-11-2012 10.50000 9.85288 100% 9.85288 COMPLETE
44.1 CONSTRUCTION OF ROAD
FROM GARAFUSRO
SHIVAMANDIR TO
GARAFUSRO JORE,
PURULIA-I BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-I BLOCK
392/PM(F)/P
/1B-
127/2012
27-11-2012 24.64165 24.31300 100% MAY'2013 23.85706 COMPLETE
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
44.2 CONSTRUCTION OF
CONCRETE ROAD FROM
BALIAGARA SHIVAMANDIR
TO BOSTOMTUPA JORE,
PURULIA-I BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-I BLOCK
392/PM(F)/P
/1B-
127/2012
27-11-2012 10.01256 8.19331 100% MAY'2013 8.01139 COMPLETE
44.3 CONSTRUCTION OF ROAD
FROM GHARJURI TO
GARAFUSRO VILLAGE,
PURULIA-I BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-I BLOCK
392/PM(F)/P
/1B-
127/2012
27-11-2012 19.80377 0.36760 MAY'2013 WORK ORDER
ISSUED
44.4 CONSTRUCTION OF ROAD
FROM DULMI 40 QUARTER
TO RAIBUNDH MORE,
PURULIA-I BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-I BLOCK
392/PM(F)/P
/1B-
127/2012
27-11-2012 19.80377 18.47510 100% MAY'2013 18.47510 COMPLETE
44.5 CONSTRUCTION OF
CONCRETE ROAD FROM
MANGURIA SHIVAMANDIR
TO OLD BEGUNKODAR
ROAD, PURULIA-I BLOCK
BLOCK DEVELOPMENT
OFFICER, PURULIA-I BLOCK
392/PM(F)/P
/1B-
127/2012
27-11-2012 10.72774 8.89049 100% MAY'2013 8.89049 COMPLETE
45 CONSTRUCTION OF
BOUNDARY WALL AT PARA
SHIB NARAYAN HIGH
SCHOOL (H.S.), PARA
BLOCK
HEADMASTER, PARA SHIB
NARAYAN HIGH SCHOOL
(H.S.)
409/PM(F)/P
/1B-
234/2012
11-12-2012 23.51551 23.51551 100% 23.51551 COMPLETE
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
46 CONSTRUCTION OF
CLASSROOM AT
CHELYAMA B.P. HIGH
SCHOOL, RAGHUNATHPUR-
II BLOCK
SCHOOL AUTHORITY,
CHELYAMA B.P. HIGH
SCHOOL
413/PM(F)/P
/1B-01/2012
13-12-2012 17.22960 8.61480 WORK ORDER
ISSUED,
DELAYED DUE
TO RAIN
47.1 CONSTRUCTION OF
CULVERT AT KALIMATI
MORE TO BIDDRI ROAD IN
SERENGHDIH G.P.,
BAGHMUNDI BLOCK
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
417/PM(F)/P
/1B-
233/2012
13-12-2012 24.91970 24.05276 100% 24.05276 COMPLETE
47.2 CONSTRUCTION OF
CULVERT ON BUKHADIH
TO SARAMCHAKI ROAD IN
BURDA-KALIMATI G.P.,
BAGHMUNDI BLOCK
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
417/PM(F)/P
/1B-
233/2012
13-12-2012 24.91970 0.54360 0.54360 WORK IN
PROGRESS
47.3 CONSTRUCTION OF
CULVERT ON THE ROAD
SURJANDIH TO
KAMALBAHAL ROAD IN
AJODHYA G.P.,
BAGHMUNDI BLOCK
BLOCK DEVELOPMENT
OFFICER, BAGHMUNDI
BLOCK
417/PM(F)/P
/1B-
233/2012
13-12-2012 24.91970 0.54360 0.54360 WORK IN
PROGRESS
48 SUPPLYING OF DRINKING
WATER BY LAYING PIPE
LINE TO 9 (NINE) NOS. OF
ANGANWARI CENTRES IN
PARA ICDS PROJECT
EE, CIVIL, PHE DTE., PURULIA 418/PM(F)/P
/1B-
237/2012
13-12-2012 0.97038 0.97038
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
49 RENOVATION AND
FURNISHING OF
LABORATORIES AT
CHITTARANJAN GIRLS'
HIGH SCHOOL
HEADMISTRESS,
CHITTARANJAN GIRLS' HIGH
SCHOOL
423/PM(F)/P
/1B-
248/2012
14-12-2012 3.35674 3.35674 100% 3.35674 COMPLETE
50 CONSTRUCTION OF PCC
ROAD FROM SATNALA
STREAM TO MAMUDIH
VILLAGE (3.0 KM) WITHIN
JHALDA-II BLOCK
DISTRICT MAGISTRATE,
PURULIA
424/PM(F)/P
/1B-70/2012
18-12-2012 119.22956 119.22956 25% 30-09-2013
51 CONSTRUCTION OF OFFICE
BUILDINGS OF R.B.B. HIGH
SCHOOL (H.S.) AT
GARHJOYPUR
HEADMASTER, R.B.B. HIGH
SCHOOL (H.S.)
426/PM(F)/P
/1B-
249/2012
18-12-2012 19.30177 19.30177 50% 9.65088 WORK IN
PROGRESS
52 CONSTRUCTION OF 2 NOS.
OF CLASSROOMS
INCLUDING STAIRCASE AT
MANIPUR SWAMI
VIVEKANANDA HIGH
SCHOOL (H.S.)
HEADMASTER, MANIPUR
SWAMI VIVEKANANDA HIGH
SCHOOL (H.S.)
435/PM(F)/P
/1B-
256/2012
20-12-2012 16.36239 16.36239 8.18100
53 CONSTRUCTION OF
BRIDGE ON SATNALA,
JHALDA-II BLOCK
DISTRICT MAGISTRATE,
PURULIA
17/PM(F)/P/
1B-70/2012
24-01-2013 4.45262
` IN LAC
NO. DATE
REMARKSSANCTIONED
AMOUNT
RELEASED
AMOUNT
PHYSICAL
PROGRESS
EXPECTED DATE
OF
COMPLETION
DISTRICT: PURULIADETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2012-13
SL. NO. NAME OF THE SCHEME IMPLEMENTING AGENCY
WITH CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
UC RECEIVED
54 CONSTRUCTION OF PUCCA
ROAD FROM TELEKOCHA
TO JAMUNA BANDH (5.70
KM), MANBAZAR-II BLOCK
DISTRICT MAGISTRATE,
PURULIA
29/PM(F)/P/
1B-143/2012
04-02-2013 149.72598 149.72598 20% 30-09-2013
55 CONSTRUCTION OF A
LIBRARY AND READING
ROOM CUM COMMUNITY
HALL AT RAMAKRISHNA
MATH, BAGDA (ADDL.
FUND)
ADHYAKSHA, RAMAKRISHNA
MATH, BAGDA, PURULIA
74/PM(F)/P/
1B-123/2012
13-03-2013 19.52958 19.52958
56 CONSTRUCTION OF
ADDITIONAL CLASSROOMS
AT BALARAMPUR PHOOL
CHAND HIGH SCHOOL,
BALARAMPUR BLOCK
BLOCK DEVELOPMENT
OFFICER, BALARAMPUR
BLOCK
95/PM(F)/P/
1B-22/2013
18-03-2013 14.88602 BDO
REQUESTED
VIDE NO.
640/PUP/BNK/
1S-278/12 DT.
22-03-2013
TOTAL: 2128.55477 1669.37295 963.35976