2011_oncall_kickoff_meeting_presentation

112
2011 On-Call Kickoff Meeting North Carolina Ecosystem Enhancement Program February 9, 2011

Upload: ecosystem-enhancement-program

Post on 22-Mar-2016

212 views

Category:

Documents


0 download

DESCRIPTION

EEP's 2011 Oncall Kickoff

TRANSCRIPT

Page 1: 2011_oncall_kickoff_meeting_presentation

2011 On-Call Kickoff Meeting

North Carolina Ecosystem Enhancement Program

February 9, 2011

Page 2: 2011_oncall_kickoff_meeting_presentation

Welcome

Michael EllisonDeputy Director

Page 3: 2011_oncall_kickoff_meeting_presentation

On-call Consulting

Ed HajnosEEP Capital Projects Coordinator

Page 4: 2011_oncall_kickoff_meeting_presentation

On-call Consulting Contracts

• The EEP procedure in selecting firms for a two year open-ended agreement

• The authorization is described under rule 01 NCAC 30D .0302 (g)

• Consulting Firm Cap $700,000

• Individual Contract Cap $350,000

• Individual Project Cap $1,500,000

Page 5: 2011_oncall_kickoff_meeting_presentation

On-call Consulting Contracts

Period Firms Total Authorization

Total Contracted

Total Contracts

$8,400,000

$12,600,000

$21,700,000

$14,700,000

$15,400,000

2002 April 2002-April 2004

15 $10,500,000 $8,000,000 47

Totals $41,750,000 288

$0

$6,500,000

$7,750,000

$8,000,000

$11,500,000

2011 January 2011-January 2013

12 0

2009 January 2009-January 2011

18

31

21

22

53

2006 December 2006-December 2008

54

2005 August 2005-August 2007

55

2004 April 2004-April 2006

79

Page 6: 2011_oncall_kickoff_meeting_presentation

DBB Site Construction

Fiscal Year Projects Bid Contracted amount

June 2010 -present

11 $2,000,000

July 2009 – June 2010

24 $6,000,000

July 2007 – June 2008

12 $4,250,000

July 2006 – June 2007

19 $7,000,000

July 2005 – June 2006

12 $6,000,000

Totals 91 $29,750,000

Page 7: 2011_oncall_kickoff_meeting_presentation

On-call Consulting Contracts

Any services performed without an executed contract or contract amendment are at the risk of the firm

This is true for New Contracts, Contract amendments and Time extensions

The consulting team should know: Scope of Work, Contract language, Project Budget, Deliverable Requirements, Deliverable Schedule

This information is included in the contract prior to signature by the consulting firm

Page 8: 2011_oncall_kickoff_meeting_presentation

On-call Consulting Contracts

ScopeNarrative describing the steps involved in project development. Be specific with excluded services. Do not include assumptions.

DeliverablesList of deliverables and number to be provided (draft, final, electronic). The Deliverable Schedule is based upon weeks from contract execution.

FeeTotal fee must be in a whole dollar amount. Must display subtotal for each task. Must include direct expenses for each subtask.

Page 9: 2011_oncall_kickoff_meeting_presentation

Contracting Process

Consulting Contracts1. POC Authorization2. On-call Assignment3. Scoping Meeting4. Negotiation5. Request for Exception6. Contract Request7. Contract Execution8. Start Project

Construction Contracts1. POC Authorization2. Advertisement3. Pre-bid Meeting4. Bid Opening5. Request for Exception6. Recommendation to Award7. SCO Award Approval8. Contract Execution9. Pre-construction Meeting10. Notice to Proceed

Page 10: 2011_oncall_kickoff_meeting_presentation

Changes for the 2011 Authorization

• Post-construction monitoring services will no longer be performed on design contracts

• Designer services will conclude with the Record Drawing and Final Report

• In most cases Designer will be contracted to provide Post-construction Monitoring services

• Monitoring services will be scoped between receipt of LQ permit and Construction Bid phase

• Monitoring services contracts can include Baseline, MY1-MY5, and Closeout reports

Page 11: 2011_oncall_kickoff_meeting_presentation

EEP Federal Mitigation Rule Requirements

Marc RecktenwaldWPPI Director919-715-1024

Page 12: 2011_oncall_kickoff_meeting_presentation

The Substantial Changes

• Watershed Planning based projects required instead of just emphasized

• IRT design and credit approval of all projects prior to construction

• Release schedule for all projects instituted after June 30, 2011

• Documents, procedures and guidelines updated based on new rule

• Working on DWQ/EEP Instrument

Page 13: 2011_oncall_kickoff_meeting_presentation

Amount of Work to Date

• Twenty-eight plans completed and six in progress

• All but two RBRPs updates completed• 560 EEP projects instituted• 279 DBB project – 221 in the ground• 147 FD projects – majority in the ground

Page 14: 2011_oncall_kickoff_meeting_presentation

Links

Annual Reporthttp://www.nceep.net/news/annualreport/2010/Annual2009-2010Final.pdf

Watershed Planninghttp://www.nceep.net/pages/lwplanning.htm

Instrumenthttp://www.nceep.net/pages/In_Lieu_Fee_Instrument_2010.html

Page 15: 2011_oncall_kickoff_meeting_presentation

Questions?

Page 16: 2011_oncall_kickoff_meeting_presentation

Take a Break

Page 17: 2011_oncall_kickoff_meeting_presentation

Mitigation Plan

Lin XuEnvironmental EngineerDesign and Construction Unit

Page 18: 2011_oncall_kickoff_meeting_presentation

Changes from the Last On-call

• EEP Project Implementation Manual• New EEP Mitigation Plan Template per the New

Federal RuleNew FormatWatershed Planning / Site SelectionMitigation Credit Determination

• FEMA Compliance

Page 19: 2011_oncall_kickoff_meeting_presentation

EEP Project Implementation Manual

• Mitigation template• Updates coming soon• Guidance Topics for

Development of EEP Mitigation Plan

http://www.nceep.net/abouteep/Mitigation_Plan_Guidance_Topics_Version_1.0_10-1-2010.pdf

Page 20: 2011_oncall_kickoff_meeting_presentation

New EEP Mitigation Plan Template

• Developed with USCOE• Formatted Similar to EEP

Bid Document Template

http://www.nceep.net/abouteep/NCEEP%20Mitigation%20Plan%20Template_version%202.0_1%20Oct%202010.pdf

Page 21: 2011_oncall_kickoff_meeting_presentation

New EEP Mitigation Plan Template

• Link Project Goals and Objectives to Watershed Planning

Page 22: 2011_oncall_kickoff_meeting_presentation

New EEP Mitigation Plan Template

• Credit Determination• Appendix B – Baseline

Data• Appendix C – Design Data

and Analysis• Appendix D – Plan Sheets

Page 23: 2011_oncall_kickoff_meeting_presentation

FEMA compliance

Page 24: 2011_oncall_kickoff_meeting_presentation

FEMA compliance

• Documentation of ESA Coordination with USFWS

• Fee simple ProjectsPermit from DOA (SCO)

• Conservation easement projects

Permit from NC Division of Emergency Management via local FPAsPermit from Mecklenburg County

Page 25: 2011_oncall_kickoff_meeting_presentation

Contact

Lin Xu715-7571

[email protected]

Page 26: 2011_oncall_kickoff_meeting_presentation

Elements of the EEP Baseline Monitoring Report

and the Transition from Construction

to Monitoring

Greg MeliaEEP Stream Monitoring Specialist

Page 27: 2011_oncall_kickoff_meeting_presentation

Some Terminology & Distinctions

• As-Built Survey - Refers to the survey conducted by the contractor’s PLS to document the As-built condition. The primary deliverable is the As-built drawing.

• Record Drawing Refers to the document (drawing) sealed by the designer that includes the design and As-built survey with annotation of deviations (red line markups). This document accompanies the SCO final report (financial and quantity data) and is required for acceptance of site construction.

• Monitoring Baseline - Refers to the geomorphologically relevant survey of the channel sample collected by the monitoring firm that will serve as the stability baseline for monitoring.

Page 28: 2011_oncall_kickoff_meeting_presentation

Long Profile

CAD X SectionsLODTOPODesign Alignment

Existing Alignment

As-built Alignment – with Red Line Deviations

SCO Package

As-built Record Drawing

SCO Final Report

+

As-Built - Elements

Page 29: 2011_oncall_kickoff_meeting_presentation

Functions of the Baseline Report

• Documents morphological and vegetative compliance with design.

• Describes potential implications of any deviations – e.g. sediment transport reanalysis

• Finalizes Asset Categorization and TalliesGoals and ObjectivesSuccess CriteriaMonitoring Plan

• Establishes Monitoring Baseline

Page 30: 2011_oncall_kickoff_meeting_presentation

Monitoring Baseline Elements

Monitoring Baseline Report

Baseline Photos

Long Profile

Perm Mon X SectionsBaseline

Morphology Table

Asset Map & Table

Monitoring Plan View

Background & Attribute Tables

Monitoring Plan

Baseline Vegetation Data

Success Criteria

Record Drawing

+Monit.

Features

Page 31: 2011_oncall_kickoff_meeting_presentation

A Word About Digital Drawings

• For any drawing, but the record drawing in particular:

Be aware of digital drawing formatting requirements beginning on page 13 of the EEP Project Implementation Manual

http://www.nceep.net/business/NCEEP_Project_Implementation_Manual_April%202009.pdf

Page 32: 2011_oncall_kickoff_meeting_presentation

A Word About Digital Drawings

• Includes specifications for:

GIS compatibility and geospatial referencing

File naming conventions

Features for layer distinctions

Feature shape types

Feature coding

Page 33: 2011_oncall_kickoff_meeting_presentation

More Words About Digital Drawings

• Compliant Drawings Support……

Asset verification mapse.g. Buffer Asset calcs.e.g. Buffer width assessments

Monitoring

Easement integrity verifications

Boundary marking

Stewardship needs

Page 34: 2011_oncall_kickoff_meeting_presentation

More Words About Digital Drawings

• Also…..

EEP now has a geodatabase, which was recently distributed to our monitoring firms that includes the shapes from many of our easements. They were built directly from the recorded metes and bounds. We (EEP and Designer) need to be certain that the shape in the Plan Views are spatially correct in position, size, shape, and orientation.

Page 35: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoring

• Traditional

Monitoring Features &

Baseline

As-Built Baseline

Mitigation Plan

Final SCOReport

Year – 1 Monitoring

MonitoringYears2-5

Designer

MonitoringFirm

Page 36: 2011_oncall_kickoff_meeting_presentation

• Current

Year – 1 Monitoring

MonitoringYears2-5

Designer

MonitoringFirm

As-Built Baseline

Monitoring Features &

Baseline

Mitigation Plan

Final SCOReport

Transition from Construction to Monitoring

Page 37: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoringsome key coordination points

• Challenges to Date

- EEP starting the coordination early enough.

- Variations and ambiguities in designer and contractor scopes in terms of figuring out what the monitoring firm will be provided with and therefore what they have to scope

Page 38: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoringsome key coordination points

- Given these past challenges, EEP wishes to make as clean of a break as possible in that the monitoring firm will be wholly responsible for the baseline.

- The monitoring firm will need to get some information from the designer (e.g. – the state and location of any useful benchmarks) and the e-drawings and other e-supportmaterials.

Page 39: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoringsome key coordination points

• Managing the Relationship - We don’texpect or want to have EEP staff micro-manage all interactions between the 2 firms. Handshake and go! But…..

• DATA RULE: No data or deliverable passes between consultants without it either already being in EEP’s possession or being distributed to us at the same time.

Page 40: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoringsome key coordination points

• Monitoring Contracting Needs – Upon issuance of Land Quality Permit, EEP will engage a monitoring firm for scoping.

• EEP monitoring should be in receipt of the following and will forward digital copies to monitoring firm:

- The restoration plan and its support elements

- Easement

- Categorical Exclusion

Page 41: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoringsome key coordination points

• At “SCO authorization to bid”

Construction documents (e-drawings and Project manual) will be submitted to EEP and forwarded to the monitoring consultant by EEP.

This will also trigger coordination between the EEP PM and Mon Specialist to initiate the “handshake” between the design firm and the monitoring firm.

Page 42: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoringsome key coordination points

• Scheduling Second element of coordination will be to get the monitoring firm clear and “in the loop” on the scheduling for attendance of the Pre-con meeting.

• Priorities and Needs – Mon firm’s needs at that meeting will obviously be subordinate to main business, but at the end of that meeting after they walk the site, they may need to have some questions addressed concerning boundaries and benchmarks.

Page 43: 2011_oncall_kickoff_meeting_presentation

Transition from Construction to Monitoring

• Key Items in Design Scoping to Facilitate Monitoring

- Compliance with Digital Drawings Requirements.

- The location and status of survey benchmarks.

- Required digital formats of other design support materials

IMPORTANT SLIDE

Page 44: 2011_oncall_kickoff_meeting_presentation

Contact

Greg Melia715-1659

[email protected]

Page 45: 2011_oncall_kickoff_meeting_presentation

Annual Monitoring

Zack Mondry715-6933

[email protected]

Page 46: 2011_oncall_kickoff_meeting_presentation

Annual Monitoring-Outline• 2011 Monitoring

– Vegetation & Stream Visual Assessment Tables

– Current Condition Maps– Summary Status Table– Field Training Day

• 2012 Monitoring– USACE Guidelines Revision– Stream Geomorphic Database– Version 1.4 Monitoring Template

Page 47: 2011_oncall_kickoff_meeting_presentation

2011 Monitoring-Vegetation Visual Assessment

• From Template Version 1.3• First used in 2010• Corresponding GIS file with closed

polygons

Page 48: 2011_oncall_kickoff_meeting_presentation

2011 Monitoring-Vegetation Plot Data/Reporting• Need to verify that tables/narrative

state success for specific resource types

• Stream/Wetland criteria: MY5 260 native woody (trees, shrubs) stems/acre (total stems)

• Buffer Restoration criteria: MY5 320 planted native hardwood (exclude shrubs?) stems/acre

Page 49: 2011_oncall_kickoff_meeting_presentation

2011 Monitoring-Vegetation Plot Data/Reporting

• Format Table 7 and 9 (Template Version 1.3) specifically for stream, wetland, buffer resource types.

Page 50: 2011_oncall_kickoff_meeting_presentation

2011 Monitoring-Stream Visual Assessment

• From Template Version 1.3• Corresponding GIS file with lines,

points

Page 51: 2011_oncall_kickoff_meeting_presentation

• Use same terminology as in tables;• Bare, low density, invasives,

encroachment• Bar formation, degradation,

scoured, undercut, mass wasting, piping

2011 Monitoring-Current Condition Maps

Page 52: 2011_oncall_kickoff_meeting_presentation

2011 Monitoring-Summary Status TableVegetation Data

CVS Veg Plot Protocol? Number of Plots

Number of Plots >320

Total Stems/Acre

Number of plots >260

Total Stems/Acre

% of plots making 320

stems

% of plots making 260

stemsCurrent Total Mean Density

Current Planted Mean

Density

Y/N # # # # #

Hydrologic Data

Number of Wetland Gauges

Number of Gauges Meeting Criteria

% of gauges meeting success criteria

Are Failed Gauges

Clustered?

Number of Repeat Gauge

Failures

Data Gaps Due To Gauge

Malfunction Reported?

Monitoring Year Rainfall

Deficits Reported?

# # Y/N # Y/N Y/N

Geomorphic Data--Visual AssessmentVisual Survey Reach

Footage From Top Of

Table 8

Bed Visual % Stable

Bank Visual % Stable

Vane Structures

Visual % Stable

Feet From E.2 From FFormula, From G.4

Other Asset Impacts

Beaver Reported?

Encroachment Reported?

Boundary Demarcation

(bollards, fencing) or

Repair Need Reported?

Boundary Signage Needed?

Y/N Y/N Y/N Y/N/U

Page 53: 2011_oncall_kickoff_meeting_presentation

2011 Monitoring-Field Training DayLooking at Last Week of March

• What is a “problem area”?• Stream Visual Assessment

– Banks, Structures, Bed

• Vegetation Visual Assessment– Bare, Low Density, Invasives

Page 54: 2011_oncall_kickoff_meeting_presentation

2012 Monitoring-USACE Guidelines Revision

• Stream-still use XS, LP, Ptx surveys, but tailored to site characteristics

• Some site types/years only use visual assessment and photo monitoring?

• > 5 year monitoring period, but maybe alternate-year surveys, consideration of channel-forming flow events?

• Vegetation-fixed plots and use of transect method?

• Planted/Total stems, Woody/Hardwood

Page 55: 2011_oncall_kickoff_meeting_presentation

2012 Monitoring-Geomorphic Database

• EEP starting to develop a database for geomorphic, hydrologic, and project tracking data.

• Looking at web-entry format similar to the CVS database.

Page 56: 2011_oncall_kickoff_meeting_presentation

2012 Monitoring-New EEP Documents

• New documentation will be needed to meet anticipated changes:– USACE Stream Guidelines Revision– Use of EEP Summary Status Table– Stream Geomorphic Database

Page 57: 2011_oncall_kickoff_meeting_presentation

Thank You! Questions?

Page 58: 2011_oncall_kickoff_meeting_presentation

Your EEP Contact for Hydro Gauges is Heather Smith!

Page 59: 2011_oncall_kickoff_meeting_presentation

Carolina Vegetative Survey (CVS)Protocol

Mac HauptMonitoring Supervisor

Page 60: 2011_oncall_kickoff_meeting_presentation

Outline

• Why CVS ?• Reducing Vegetation Problems at Closeout• CVS Level Selection• CVS-EEP Process Flow Charts• CVS Resources

Page 61: 2011_oncall_kickoff_meeting_presentation

Why CVS?

• Based on 6000 + reference plots• Consistent method• Data is usable in a database

– Analysis- within project– Analysis- among population of projects

• Restoration target community trends over long term (greater than 5 years)

• And many other reasons…

Page 62: 2011_oncall_kickoff_meeting_presentation
Page 63: 2011_oncall_kickoff_meeting_presentation

• Data summarized with click of a button• Multiple configuration options available

– Reports based on a single year or multiple years

– Reports based on a single project or multiple projects

Page 64: 2011_oncall_kickoff_meeting_presentation
Page 65: 2011_oncall_kickoff_meeting_presentation
Page 66: 2011_oncall_kickoff_meeting_presentation

• EEP contractors can use plot & NVC data to establish site-specific restoration targets.

• Cheaper and better than the traditional approach

• Growers can better predict material needs.

• EEP can better evaluate plans and anticipate significantly higher success.

Page 67: 2011_oncall_kickoff_meeting_presentation

http://www.nceep.net/business/monitoring/veg/Vegetation_Related_Resources.htm

Page 68: 2011_oncall_kickoff_meeting_presentation

Reducing Vegetation Problemsat Close-out

• Improving Vegetation Success– training EEP staff and contractors

• exotic invasive species• project evaluation• species identification• planting plan development

• Improving Planting Plans– training and resources intended to

• increase project manager capability• produce better planting plans• facilitate buffer maintenance and repair contracts• increase contractor/designer accountability

Page 69: 2011_oncall_kickoff_meeting_presentation

CVS Level Selection• Level 1

– Planted stems only-Year 1• Level 2

– Planted stems and volunteers- Year 2+• Level 3- leaf cover for most common species

(currently we have only one project (marsh) using this level)

• Level 4 – we do not use for typical mitigation monitoring (same as #3 but cover for all species)

• Level 5 - we do not use for typical mitigation monitoring (same as #4 but spatial structure as well)

Page 70: 2011_oncall_kickoff_meeting_presentation

CVS-EEP Process Flow Charts

• Describe data management process for both baseline and subsequent years’ data

• Everyone scoping, collecting and delivering CVS-EEP monitoring data should be familiar with and follow the flow charts.

Page 71: 2011_oncall_kickoff_meeting_presentation
Page 72: 2011_oncall_kickoff_meeting_presentation
Page 73: 2011_oncall_kickoff_meeting_presentation
Page 74: 2011_oncall_kickoff_meeting_presentation
Page 75: 2011_oncall_kickoff_meeting_presentation

Prototype tool predicts target vegetation type based on site data.

Planting lists could be automatically generated from community data.

Page 76: 2011_oncall_kickoff_meeting_presentation

Mitigation Project Closeout

Mac HauptMonitoring Supervisor

Page 77: 2011_oncall_kickoff_meeting_presentation

Closeouts

• Previously created separate report

• Now….Incorporate in the project’s last monitoring report

• Will modify scoping table to include additional components when needed

Page 78: 2011_oncall_kickoff_meeting_presentation

Closeouts

• Primary Data components needed:– Asset table– Asset Map– Current Plan view showing veg plots, gauges, cross

sections (already in report)– Summary Veg Table (already in report)– Summary Hydro Table (wetland-ground water gauges)– Project summary of goals and objectives including the

watershed plan context -How did the project perform? Trends?

Page 79: 2011_oncall_kickoff_meeting_presentation

Role for EEP Monitoring Firms

• Project Closeout - Aspects of the Process & Format. -Detailed Asset Breakdown:

Table 1. Project Restoration Components and Mitigation AssetsStream

Drainage/Hydrology Component Restoration Component Asset RatioMap # Approach Level Ratio Multip Feet SMU Acres WMU

Jumping Run Upper (Above Henry Road) Segment 1 1 P1/P2 R 0.75 1.33 4377 5821 - -Jumping Run Lower Segment 1 (Down to confluence) 2 P2 R 1.00 1.00 800 800 - -(Below Payne Store Road) Segment 2 (Confl to Pres segm) 3 P2 EI 1.50 0.67 380 253 - -

Segment 3 (Preserv - one side) 4 - - - 0.00 1450 0 - -Tributary Segment 1 (Upper ) 5 Fence/Plan EII 2.00 0.50 1350 675 - -

Segment 2 (Lower 90 feet) 6 P2 EI 1.50 0.67 90 60 - -Wetland

Jumping Run Upper (Above Henry Road) Wetland 1 7 - E 2.00 0.50 - - 2.360 1.180Wetland 2 8 - R 1.00 1.00 - - 0.030 0.030Wetland 3 9 - R 1.00 1.00 - - 0.260 0.260Wetland 4 10 - R 1.00 1.00 - - 0.300 0.300Wetland 5 11 - E 2.00 0.50 - - 1.870 0.935

Tributary Wetland 6 12 - P 5.00 0.20 - - 0.010 0.002Wetland 7 13 - P 5.00 0.20 - - 0.100 0.020Wetland 8 14 - P 5.00 0.20 - - 0.070 0.014

Jumping Run Lower (Below Payne Rd)) Wetland 9 15 - P 5.00 0.20 - - 1.400 0.280

Asset Data

Page 80: 2011_oncall_kickoff_meeting_presentation

Role for EEP Monitoring Firms• Project Closeout - Aspects of the Process & Format.

-Coupled with linked detailed asset map including buffer polygons

Page 81: 2011_oncall_kickoff_meeting_presentation

Role for EEP Monitoring Firms

- Representative photos of the change that the site underwent

Photo point #3, view upstream at pool X-section.

As-built (2000) Monitoring Year 5 (2005)

Photo point #40, view downstream near Henry Road.

Page 82: 2011_oncall_kickoff_meeting_presentation

Role for EEP Monitoring Firms

• Project Closeout – Project Summary Aspects Examples:- Re-establishing bankfull, recalculation of CA’s and trending

them etc.- Was there a stable pattern of variation over the 5 years?

- Watershed plan context?

- Were certain key variables maintained within intended bounds?

BHR% Bank instability etc.Bedform diversityGauge performance percentages

Page 83: 2011_oncall_kickoff_meeting_presentation

Role for EEP Monitoring Firms• Project Closeout – Project Summary Aspects

- Asset Verification (Examples).

One final verification that treatments applied to restoration components (assets) meet regulatory definitions.

Verification that the regulatory buffer limits are being met for each restoration component.

Isolation of under performing components.

Page 84: 2011_oncall_kickoff_meeting_presentation

Role for EEP Monitoring Firms

• Project Closeout – Project Summary Aspects

- Asset Mining (Examples).

Some assets may have been overlooked such as:Surplus BufferComponents that classify as preservation

opportunitiesWetland features or their extent

Determination of whether component attributes might justify ratio adjustments :

BMPsHeadwater drainage captureStressor removal

Page 85: 2011_oncall_kickoff_meeting_presentation

Begin with the End in Mind

• Close-out!• Close-out!• Close-out!

Page 86: 2011_oncall_kickoff_meeting_presentation

Questions?

Mac Haupt919 715-1070

[email protected]

Page 87: 2011_oncall_kickoff_meeting_presentation

Take a Break

Page 88: 2011_oncall_kickoff_meeting_presentation

Construction Documents

Ed HajnosCapital Projects Coordinator

Page 89: 2011_oncall_kickoff_meeting_presentation

Construction Documents

What constitutes a Construction Document submittal?

Initial Submittal for EEP Review must be PE-sealedPlan SheetsProject Manual Engineer’s Opinion of Probable Cost

Revised Submittal for Permitting and Bid Authorization must be PE-sealed

Plan Sheets CADD/Microstation filesProject ManualEngineer’s Opinion of Probable Cost

Page 90: 2011_oncall_kickoff_meeting_presentation

Construction Documents

Plan SheetsTitle PageLegends and SymbolsGeneral Notes and Construction SequenceCross-sectionsDetail PagesStructure DataGrading Plans – Plan and Profile on the SAME PLAN SHEETSite Stabilization Plan – Limits of Disturbance, Access, Erosion & Sedimentation Control Measures, Seeding, Mulching, etc.Planting Plan – Planting Zones, Species, and Type(s)Boundary Marking Plan – Type and Location

Page 91: 2011_oncall_kickoff_meeting_presentation

Construction Documents

Project ManualSection Source Notes

Cover EEP Fill in the Blank

Notice to Bidders SCO Fill in the Blank

Table of Contents EEP As is

Instructions to Bidders SCO Fill in the Blank

General Conditions SCO As is

Supplementary Instructions to Bidders EEP As is

Supplementary General Conditions EEP Fill in the Blank

MBE Recruitment Guidelines SCO As is

Technical Specifications Designer/EEP Custom to the project

Schedule of Units Designer Custom to the project

Contract Forms SCO As is

Appendices Designer/EEP Permits, Historical Rainfall data, etc

Page 92: 2011_oncall_kickoff_meeting_presentation

Supplementary General Conditions

Article 1 Definitions As is

Article 2 Intent and Execution of Documents Fill in the blank

Article 10 Permits, Inspections, Fees, Regulations As is

Article 11 Protection of Work, Property, and the Public As is

Article 12 Sedimentation Pollution Control Act of 1973 As is

Article 14 Construction Supervision As is

Article 16 Subcontracts and Subcontractors As is

Article 18 Designer’s Status As is

Article 23 Time of Completion, Delays, Extension of Time Fill in the blank

Article 24 Partial Utilization Beneficial Occupancy As is

Article 25 Final Inspection and Acceptance As is

Article 31 Request for Payment As is

Article 34 Minimum Insurance Requirements As is

Article 40 Utilities, Structures, Signs As is

Article 41 Cleaning Up As is

Page 93: 2011_oncall_kickoff_meeting_presentation

Construction Documents

Engineer’s Opinion of Probable Cost

Must be PE-sealedMust have credibility Must be within construction budgetMust use Schedule of Units in Project ManualEstimate accuracy will be judged by comparing the estimate against the bid results

Page 94: 2011_oncall_kickoff_meeting_presentation

Construction Documents

• Links for more infoEEP designer information:

http://www.nceep.net/pages/designer_info.htm

State Construction Office:http://www.nc-sco.com

NC Land Quality sectionhttp://www.dlr.enr.state.nc.us/pages/sedimentation_new.h

tml

Page 95: 2011_oncall_kickoff_meeting_presentation

Questions?

Ed Hajnos919 715-1953

[email protected]

Page 96: 2011_oncall_kickoff_meeting_presentation

Construction Management and Administration

Jeff SchafferEastern Operations Supervisor

Page 97: 2011_oncall_kickoff_meeting_presentation

Involved Parties

• EEP

• State Construction Office

• Contractor

• Designer/Consultant

Page 98: 2011_oncall_kickoff_meeting_presentation

Designer/Consultant

• Description of Status & Responsibilities 01 NCAC 30A .403 (SCO Contract Law)

Contract

Construction Contract General Conditions (Form OC-15)

SCO Manual

Definitions Section of EEP Project Implementation Manual

Page 99: 2011_oncall_kickoff_meeting_presentation

Designer/Consultant

• Designer is the EEP’s agent

• Designer shall provide:General administration of construction performanceInspections to ensure complianceDirection to contractor

• Designer has authority to:Stop workOrder work removedOrder corrections of work

Page 100: 2011_oncall_kickoff_meeting_presentation

Designer’s Responsibilities• Plans & specifications

• Project schedule

• Claims avoidance

• Monthly/weekly construction progress meetings

• Inspections

• Pay requests

• Changes in work Field ordersChange orders

• Project Close-Out

Page 101: 2011_oncall_kickoff_meeting_presentation

REMEMBER• You represent EEP.

• You are EEP’s eyes and ears at the site.

• Your design, ensure that’s what is built.

• Address problems early to reduce them.

• Specific recommendations

• Communication is key to success!

Page 102: 2011_oncall_kickoff_meeting_presentation

Questions?

Refer to:Project Implementation Manual

www.nceep.net

Page 103: 2011_oncall_kickoff_meeting_presentation

Construction Practices andPermit Compliance

Wyatt Brown, LSS, CPESC919-716-1616

Page 104: 2011_oncall_kickoff_meeting_presentation

Maintain Permit Compliance

• 401• 404• Erosion & Sedimentation• NPDES• Trout Waiver• CAMA

Page 105: 2011_oncall_kickoff_meeting_presentation

Sediment & Erosion Control

1) Self Inspection Form_ Financial Responsibility Party or agent– After every stage of construction– Notations on field copy (red line)– In addition to NPDES– Must be doing now– Land Quality Website

2) Trout streams--- 5 ac. Pump around

Page 106: 2011_oncall_kickoff_meeting_presentation
Page 107: 2011_oncall_kickoff_meeting_presentation

Problems I’ve Seen

• 1) Proofreading Mitigation Plan• 2) Up to date Notice to Bidders other SCO

forms• 3) SCO Monitor not in loop• 4) Pre-Bids for old sites• 5) Matting weight• 6) Project Constraints

Page 108: 2011_oncall_kickoff_meeting_presentation

For The Future

• 1) Invite Land Quality to Pre-Con• 2) New turbidity rules

– August– 14 days for ground cover– Skimmer basins (no stone filters)– Turbidity rules > 20 acres

• 3) 5 cfs base flow/pump around– Diversion– Project Constraints

Page 109: 2011_oncall_kickoff_meeting_presentation

For Future Continued

• 4) Bonding of sites• 5) Reclamation

Page 110: 2011_oncall_kickoff_meeting_presentation

Questions?

Wyatt Brown919 715-1616

[email protected]

Page 111: 2011_oncall_kickoff_meeting_presentation

Upcoming Trainings

March 30th FHWA Categorical Exclusion

April 7th FHWA Categorical Exclusion

Spring 2011 Claims Avoidance Workshop

Spring 2011 CVS Protocols

Summer 2011 CVS Pulse

Fall 2011 Construction Administration

Date TBD Construction Practices for Stream Restoration

Page 112: 2011_oncall_kickoff_meeting_presentation

Closing Remarks

Jeff JurekProject Control and Research Director