2011 annual report of federal ministry of power.pdf

137
2011 Annual Report of the Federal Ministry of Power FEDERAL MINISTRY OF POWER (FMP) Federal Secretariat, Abuja 2011 ANNUAL REPORT Federal Ministry of Power Federal Secretariat Phase I, Annex III 4 th and 5 th Floors Shehu Shagari Way Abuja. July, 2012

Upload: hoanghanh

Post on 11-Feb-2017

261 views

Category:

Documents


14 download

TRANSCRIPT

Page 1: 2011 Annual Report of Federal Ministry of Power.pdf

2011 Annual Report of the Federal Ministry of Power

FEDERAL MINISTRY OF POWER (FMP) Federal Secretariat, Abuja

2011 ANNUAL REPORT

Federal Ministry of Power Federal Secretariat Phase I, Annex III 4th and 5th Floors Shehu Shagari Way

Abuja. July, 2012

Page 2: 2011 Annual Report of Federal Ministry of Power.pdf

1

Page 3: 2011 Annual Report of Federal Ministry of Power.pdf

2

TABLE OF CONTENT

FOREWARD…………………………………………………………………………..

i. Introduction…………………………………………………………………..

ii. Mandate………………………………………………………………………..

iii. Vision and Mission Statements…………………………………………..

iv. Functions of the Ministry…………………………………………………..

v. Organizational Structure…………………………………………………..

vi. Agencies under the Ministry………………………………………………

vii. Overview of the Power Sector……………………………………………

viii. Challenges in the Nigerian Power Sector……………………………..

ix. Strategic Goals / Plans…………………………………………………….

x. Major Achievements in the Power Sector…………………………….

xi. Investment Opportunities………………………………………………..

xii. Conclusion…………………………………………………………………….

Page 4: 2011 Annual Report of Federal Ministry of Power.pdf

3

FOREWORD:

President Goodluck Jonathan, GCFR, in his May 2011 inauguration speech

underscored the importance his Administration attaches to transforming the

Power Sector to provide sustainable electricity supply to the Nigerian populace.

He stated “To drive our overall economic vision, the Power Sector is at

the heart of our industrialization strategy. I call on all stakeholders to

cooperate with my Administration to ensure success of the reforms”

Arising from Mr. President‟s comment and challenge to the stakeholders in the

Power Sector, it is imperative that there has to be a paradigm shift in people‟s

minds and actions in order to improve service delivery in the sector. Every

stakeholder should therefore understand the challenges before us in terms of the

present industry position and demands and the short, medium and long term

goals. It has become public knowledge that the situation today in the Power

Sector is such that only 40% of the nation‟s populations has access to electricity

supply and in order to achieve the Nigerian Vision 20: 2020 goals, the

Distribution and Transmission networks have to grow at the rate of at least 16%

per year, rather than the current rate which is less than 1% growth rate.

We are also undoubtedly faced with the challenges of obsolete equipment, high

operating costs, high energy losses, inadequate expertise, vertically integrated

government – owned monopoly and continue increase in an already highly

suppressed demand, to mention a few. As a result of these and other challenges,

the government new drive is to proactively disaggregate the industry, develop

the market through strong regulations and cost reflective tariffs and most

importantly, utilize the private sector to lead and finance the initiative. In order

for this new drive to succeed and thrive, a series of interlocking reforms of the

current service delivery model is required to attract the large amount of

investment needed. Specifically, the ownership and control of the Power Sector

needs to move from largely Federal Government owned to modify private sector

owned, particularly in power generation and distribution. Some critical steps

need to be addressed to serve as the levers for change such as labour

agreement, a major tariff change and a bulk trader to serve as interim central

purchaser and principal contracting authority of power.

Page 5: 2011 Annual Report of Federal Ministry of Power.pdf

4

Underlying the success of the Power Sector Reform is the transformation of the

ownership and control of the Nigerian Electricity Sector. This will require

massive undertaking and supporting capital from the Federal Government to

encourage private sector involvement. However, government investment and

post reform guarantee required is not from a bottomless pit but is bounded, time

limited and crucial. The Cumulative Cost of delaying the required investment –

in terms of Cost GDP will be more than 10 times higher than the actual cost of

incurring the contingent liability. There are already key achievements such as the

stabilization of power generation to over 3500MW and a sharp reduction in

system collapses. Similarly, key reforms policy concern, investors road shows to

the pre-qualification of privatization bidders and many more. The 2011 Annual

Report of the Federal Ministry of Power is predicated on gains of the Reforms in

line with the Roadmap for the Power Sector Reforms of 2010. We are therefore

committed to implementing the reforms in a progressive manner in order to

guarantee the overall socio – economic development of the nation.

Professor Bart Nnaji, CFR Honourable Minister of Power

Page 6: 2011 Annual Report of Federal Ministry of Power.pdf

5

Preamble,

To write a preamble to a document of this magnitude with a view to

satisfying all the stakeholders in the Power Sector is humanly impossible.

However, the power sector, as we see it today, wants to get on, do more and

influence more, day - in - day - out. Thus, no stakeholder shall be left out, we

must contribute our quota for the sustainable development of the Sector.

It has been stated elsewhere that since 2002, when the Federal

Government of Nigeria adopted the National Electric Power Policy, the

comprehensive reform and reengineering of the electricity supply industry has

been central to the thinking of government. That Policy outlined, among others,

the following key objectives:-

(i) to ensure that the Power Sector attracts private investment;

(ii) to embark on a holistic principle of privatization in the Sector;

(iii) to establish an effective regulatory framework for the Power Sector;

(iv) to review and update electricity laws in line with international best

practice, etc.

No wonder, this was followed by enacting the Electric Power Sector Reform Act

in March, 2005. This Act gives effect to these policy principles which is, in part,

the subject-matter of the 2011 Annual Report. The new market development

hinges on cost reflective tariff and the presence of a strong Regulator. After all,

Prof. Barth Nnaji has ages ago observed, in his usual telling language, that “No

cost reflective tariff – No Power! And No Power – No future”. Period!

It is noted with satisfaction that the development in the Sector is going on

as expected. The Roadmap is on course. The Bulk Trader is in place. The

Market Operator is brought into existence. The Rural Electrification Agency

(REA) is back on to the scene, this time with full force. All these can be read

from the 2011 Annual Report

It remains only to be said and, to be said clearly, that my only happiness is

for the zeal and effort put into the report to broaden the nation‟s understanding

of our generation‟s opportunity to end extreme darkness in Nigeria. Going

through the report, one sees thoughts too big even for our big heads but,

nevertheless, we can make it, after all, other nations did. Clearly then, our 2011

Annual Report is not talking about hunger, diseases, squalor, poverty reduction

etc., but wealth creation via investment – great ideas, it‟s a challenge that is

Page 7: 2011 Annual Report of Federal Ministry of Power.pdf

6

hard to ignore. And when experts start talking like that perhaps we should listen

and, then act accordingly.

Happy reading.

A. J, Muhammed, mda.

Director (PRS)

Page 8: 2011 Annual Report of Federal Ministry of Power.pdf

7

Page 9: 2011 Annual Report of Federal Ministry of Power.pdf

8

Page 10: 2011 Annual Report of Federal Ministry of Power.pdf

9

I INTRODUCTION:

1.1 The development of any nation is primarily anchored on effective

generation and efficient distribution of electricity supply. For Nigeria as a

developing nation, ambitious to transform into one of the top 20 economies in

the world by 2020, sustainable power supply to drive all the critical sectors of the

economy becomes imperative and requires the cooperation and involvement of

all stakeholders. The Power Sector, undoubtedly, has witnessed long history of

neglect in terms of private sector involvement and investment. It has become an

open secret that government alone cannot bear the huge cost of salvaging the

sector, which will require over US$3.5 Billion annually. However, over the past

years, there was significant progress in attracting private sector investment in

the sector and positive indication of more in the coming years, a development

that is consistent with the present Administration‟s commitment to the

implementation of its Transformation Agenda.

II MANDATE:

2.1 The Federal Ministry of Power is the Policy making arm of the Federal

Government on matters dealing with the provision of electricity in the country.

The Ministry is mandated to develop and facilitate the implementation of policies

for the provision of adequate and reliable power supply to drive the socio –

economic development of the Nation. In discharging the mandate, the Ministry is

guided by the provisions of the National Electric Power Policy (NEPP) of 2001,

the Electric Power Sector Reforms (EPSR) Act of 2005 and the Roadmap for

Power Sector Reform of August, 2010 and the Transformation Agenda of the

present Administration on power.

III VISION AND MISSION STATEMENTS

3.1 Vision Statement:

A robust and sustainable power sector that fully supports the socio –

economic needs of the Nation and contributes to the emergence of Nigeria as

one of the top twenty economies of the world by the Year 2020.

Page 11: 2011 Annual Report of Federal Ministry of Power.pdf

10

3.2 Mission Statement:

To provide the Nation with adequate and reliable power supply by

implementing generation, transmission and distribution projects in the sector and

facilitating the emergence of a private sector led competitive and efficient electric

power industry.

IV FUNCTIONS OF THE MINISTRY

4.1 The responsibilities of the Federal Ministry of Power are as follows:

Initiating and formulating broad policies and programmes on the

development of the power sector (electricity) in general;

Initiating concessions in the power sector of the economy;

Licensing of electric generating sets of 1MW capacity and below and

electrical contractors;

Conducting investigation on electrical accidents and to ensure safety in

the electricity industry in Nigeria;

Conducting statutory tests and certification of electric poles (concrete,

wooden, steel etc) and other major electrical materials before they are

used on the grid and networks in Nigeria;

Implementing Renewable Energy progammes/initiatives (Solar, Wind,

Biomass, Small Hydro etc);

Coordinating activities of power sector;

Handling policy matters relating to research and development in the

Power Sector;

Promoting the development of hydro power plants through public

private partnership (PPP);

Participating in bilateral and multilateral relations affecting the power

sector; and

Facilitating the overall coordination of the activities of the Parastatals

under its supervision.

V ORGANISATIONAL STRUCTURE:

5.1 The Honourable Minister is the Chief Executive of the Ministry, while the

Permanent Secretary is the Accounting Officer supported by seven (7)

Departments and 5 Units, namely:

Page 12: 2011 Annual Report of Federal Ministry of Power.pdf

11

ORGANOGRAM OF THE MINISTRY OF POWER

a) Power Department

The Power Department is responsible for the initiation of policy matters in power

sector (Generation, Transmission and Distribution) and ensuring that the sectoral

policy decisions of government are implemented by the agencies of Government

under the supervision of the Ministry. The Department is responsible for the

development and supervision of some of the major publicly funded power plant

projects. It is also responsible for the supervision and monitoring of projects

under the TCN and the finalization of the privatization programme of the

successor companies of the defunct PHCN in collaboration with the Bureau of

Public Enterprises (BPE). The Department has staff strength of 25 officers,

consisting 15 engineers and 10 administrative and support staff

Honourable

Minister

Honourable

Minister of State

Permanent

Secretary

D-

Power

DPRS DEIS DISD DF&A D,PROC DHRM

Page 13: 2011 Annual Report of Federal Ministry of Power.pdf

12

The Department under review in 2011 played strategic roles in line with the

present administration resolve and determination to increase power generation

capacity to 5000MW, reinforce the transmission grid system and ensure reliable

and efficient distribution network under the National vision 20: 20: 20 set goals

and objectives.

Overview/Achievement of the Department’s Activities in 2011.

The Department‟s activities in 2011 focused on the execution of the following

projects and programs:

i. 215MW dual fired (LPFO/Natural Gas) Kaduna Power Plant Project;

ii. Development of 10MW Wind Farm Project in Katsina State;

iii. Mambilla Hydroelectric Power Project;

iv. Zungeru Hydroelectric Power Project;

v. Coal to Power Project;

vi. Other Sources of funding for Power Sector;

vii. Power Sector Reform Issues;

215MW Kaduna Power Plant Project

As part of the intervention towards resolving the acute shortage of electric power

across the country and in consideration of the persistent challenge of gas supply

to existing thermal power stations, the Ministry adopted a strategy of exploiting

alternative fuels for power generation. The primary fuel would be initially Low

Pour Fuel Oil (LPFO) but the plant is expected to switch to natural gas when the

necessary transmission infrastructure is eventually extended to Kaduna. The

selection of Kaduna for the project was based on the availability of Low Pour

Fuel Oil (LPFO) from the Kaduna refinery and the technical imperative of

balancing the national transmission grid.

A contract for the construction of a dual-fired (LPFO/Gas) power plant with an

installed capacity of 215MW (ISO) has been awarded in favour of a consortium

of GE (NuovoPignone)/Rockson Engineering Ltd with a completion period of 36

months. The contract sum is €135,840,665.71 plus N6,066,626,449.24. The

current status of implementation of the project is as follows as at December 31,

2011:

Page 14: 2011 Annual Report of Federal Ministry of Power.pdf

13

Engineering - 68%

Procurement - 60%

Construction - 49%

Overall - 59%

The projected completion date is put at December, 2013 with the first firing for

January 2013. The letters of Credit on off-shore procurement for both GE Nuovo

Pignone / Rockson Engineering Ltd have been fully funded to the tune of

135,840,665.71 Euros. It is note worthy to report that Messrs GE Nuovo

Pignonehave already delivered to Onne Port all the eights units each of gas

turbines & generators and the balance of plants has commenced the installation

/ erection works on site. However, the on-site is behind scheduled due to the

security concerns in Kaduna.

One of the challenges affecting the progress of work on the project is the on-

going rehabilitation works of the road selected to transport the heavy equipment

from Onne Port to the Kaduna Plant site. Other challenges are variations on the

contract sum arising from change in project site from an old PHCN facility to a

green field site. The VORS is being reviewed by the Project Consultant Messrs

Steag Encoted West Africa Ltd.

10MW Katsina Wind Project

In line with the Government policy of promoting renewable energy, a wind map

for the entire country has been developed, indicating numerous viable sites for

the deployment of wind turbines for power generation. A contract for the

construction of a 10MW Wind Farm at Katsina was awarded by the Federal

Government in favour of MessrsVergnet SA of France at a contract sum of

€18,500,000 plus N494,020,000 with a completion period of 24 months. The

configuration consists of 37No. 275kW wind turbine generators mounted at a

height of 55m on an inclinable tower. The Project Consultant is Terrawatt

GmbH/O. T. Otis Engineering. The project has so far been fully funded and

project implementation has progressed very smoothly despite a few challenges

relating to customs clearance at the ports. The Ministry is currently evaluating

the procurement of contractors for the erection of a 33kV transmission line/sub-

station and wire mesh fencing of the project site.

Page 15: 2011 Annual Report of Federal Ministry of Power.pdf

14

Mambilla Hydroelectric Power Project

The Mambilla HEPP is one of the major projects expected to significantly to

increase the security of supply of power to the country. The project is planned to

consist of a 2,600MW base load hydroelectric power to be implemented over a

period of 5 years. Lahmeyer International of Germany has been engaged to

undertake a detailed review of the feasibility study on the project and to prepare

a bankable report and tender documents for eventual implementation. The

completion of the report is associated with the finalization of the following

projects.

Route Surveys for Transmission lines and sub-station

Geotechnical Investigation of the project site;

Orthophoto-mapping of the area, including the transmission corridor;

Environmental and social impact assessment.

Route Surveys for Transmission lines and sub-station

Other essential studies towards the realization of the Mambilla project are the

definition of the HV transmission line for the evacuation of the generated power.

In this respect, the procurement process for the engagement of a consultant that

would undertake the Line Route Survey of the transmission corridor line routing

has been concluded. The report is expected to provide the base data for the

design of the High Voltage lines from the Abong power house to Abong and

Makurdi.

Transmission Line Route Survey: Current status of the project

Two Corridors for Transmission Lines(Corridor 1 – Abong to Makurdi, 4 x

500KV DC and Corridor 2 – Abong to Jalingo, 1 x 330KV DC)

Survey Exercise Completed December 2009

Orthophoto Mapping

The Federal Government has approved a contract for the detailed aerial mapping

of the Mambilla Power Project footprint in favour of Messrs Maps Geosystems in

December 2008 with a completion period of 9 months. The Contractor could not

mobilize before the end of February 2009 due to delays in securing flight permits

Page 16: 2011 Annual Report of Federal Ministry of Power.pdf

15

into one of the neighbouring countries. The aerial survey commenced in

November 2009 and is scheduled to be completed by December 2011

OrthoPhoto Mapping: Current status of the project

Aerial photography completed in December 2009

Results evaluated and accepted

Ground survey exercise completed August 2010

Production of Orthophotos, Digital Elevation Models in 3D and aerial

triangulation in progress

Stereo Vision / editing takes time because of the thick layer of vegetation

at the Power house area.

Expected submission date for report and maps is December, 2011

Environmental and Social Impact Assessment (EIA) : Current status of the

project

The three EIA‟s are in advance stage of progress

The draft final report for the main EIA will has been submitted for

regulatory review

The EIAs for Transmission line routes are also on going. The 1st draft EIAs

has been submitted for in-house review.

The final reports of all the EIAs after regulatory approval by FMENV are

expected in December 2011.

Geotechnical and geodetic surveys: Current status of the project

Geotechnical survey component Report submitted

Field confirmation inspection carried out in August 2010

Result required drilling at the POWER House to a depth of 350-400m and

few other areas

Outstanding Geotechnical Investigation to be carried out by selective

procurement process

A “NO Objection” for procurement for the outstanding Geotechnical

Investigation granted by BPP of either Trevi, Impregillo N. L or Fugro Nig.

Ltd.

The procurement process and completion of the investigation would be

about six months; and

Page 17: 2011 Annual Report of Federal Ministry of Power.pdf

16

RFP for the procurement at about 90% completed.

Review of Feasibility and preparation of Bankable Report

MessrsLahmeyer International has since 2006 reviewed the feasibility

Study Report

And has submitted a draft bankable Feasibility Report to the Ministry

The finalization of the study is currently constrained by the non-completion

of the geotechnical investigation of some areas of the project sites

Preparation of the detailed design and Project management

A project consultant has been procured for detail design, supervision and

Project Management

The contract sum is $37, 220, 068.72

The addendum to the contract is being finalized in the Ministry for signing

A contract for the Lot I (Civil/Hydraulic Steel Structures) of the 2,600MW

Mambilla Hydroelectric project was awarded in April 2007 by the Federal

Government, in favour of Messrs CGGC/CGC Ltd, in the sum of US$1.46billion.

The source of funding envisaged at the time of award was a combination of an

Exim Bank of China loan of US$1billion and funds from the Excess Crude Savings

Account. A tender for the electro-mechanical component was also floated in 2007

but the bids are yet to be opened. However, the contract with CGGC/CGC Ltd,

though executed, was subsequently revoked by the Federal Government on the

advice of the Ministry of Justice.

A draft bankable Feasibility Report by Lahmeyer International has since been

submitted to the Ministry but the finalisation of the study is currently constrained

by the non-completion of the geotechnical investigation of some sections of the

project site. The challenge in completing the study has been a lack of access to

the project area, particularly the proposed site of the underground power house.

In order to complete the geotechnical investigation, a request has been

submitted to the Bureau of Public Procurement seeking “No Objection” to obtain

Technical/Commercial offers based on selective tendering strategy. The short-

listed companies are Impregilo Nigeria Ltd and Fugro Nigeria Ltd.

A contract has also been awarded by the Federal Government in favour of

Messrs Coyne etBellier (Tracterbel Engineering)/DeCrown/Wadsco for the

Page 18: 2011 Annual Report of Federal Ministry of Power.pdf

17

detailed Engineering and Project Management of the Mambilla Hydroelectric

Power project with a completion period of 63 months. The contract sum is

US$37,220,068.72. The Contract Agreement has already been executed by the

Ministry and the contractor has already work on the project. However, on

account of a number of inaccuracies noted in the executed Agreement, an

Addendum to the contract is currently under consideration for the purpose of

remedying the situation.

The Mambilla project is currently a subject of litigation instituted by Messrs

Sunrise Power & Transmission Ltd. The issue in dispute is a claim by the

plaintiffs that a subsisting contract for the construction of the Mambilla

Hydroelectric Power Project on the basis of a BOT concession exists in their

favour. However, the Vice President has constituted a Committee under the

Chairmanship of the Attorney General/Minister of Justice for the resolution of all

legal encumbrances on the Mambilla project. The Committee has not met since

its inaugural meeting early this year.

The estimated cost of the Mambilla project is circa US$3billion including

transmission infrastructure. With the commencement of the detailed design

aspect of the project development, it is important to firm up on the structure of

the project finance.

Zungeru Hydroelectric Power Project

A contract for the construction of the 950MW Zungeru Hydroelectric Power

project was awarded in favour of Messrs China National Electric Equipment

Corporation (CNEEC) by the Federal Government in April 2007 with funding to be

sourced from the Excess Crude Savings Account. However, the contract was

stepped on account of the recommendations made in the updated Feasibility

Report on the project submitted by Messrs Coyne etBellier. The report

recommended that, as a consequence of declining hydrology, the optimal plant

capacity should be 525MW with the possibility of future expansion to 700MW.

Messrs Coyne etBellier has been retained by the Ministry for the conduct of due

diligence on Messrs CNEEC, preparation of EPC tender documents, evaluation of

revised offer and preparation of Contract Agreement. All the technical and

commercial negotiations have been concluded culminating in the issuance of Due

Page 19: 2011 Annual Report of Federal Ministry of Power.pdf

18

Process Certificate of No Objection in the sum of US$944,309,253.82 plus

N44,007,398,398 for the revised scope of the project.

The project is yet to be presented to the Federal Executive Council for

consideration due to an imperative to firm on the source of funding for the

project. Noting that a sum of about N87.6 billion from ECSA has been available

to the Ministry for the development of Mambilla/Zungeru since 2007, a proposal

has been made to the President to fund the project based on a debt:equity ratio

of 1:4. The debt portion is to be secured from the Exim Bank of China while the

equity is to be funded from the aforementioned ECSA funds. The financing model

is based on a financial analysis of the project indicating that revenue streams

from the completed project would be adequate to cover the prepayment

obligations over a period of 18 – 20 years.

We wish to report that ongoing discussions between the Federal Ministry of

Finance and the Exim Bank of China have recommended a loan of US$1 billion

for the Zungeru project.

Coal to Power

One of the goals of the Federal Government in the current development effort of

the power sector is the enhancement of security of supply of electricity through

the diversification of the fuel mix. In this respect, it is planned that the nation‟s

vast resource of coal and hydropower potential would be fully exploited for the

socio-economic development of the country.

Pursuant to the above objective, an Inter-Ministerial Committee on Coal to Power

was established with a mandate to develop an Action Plan for the actualization of

coal-fired power plants. The membership of the Committee was drawn from the

following MDAs:

(i) Ministry of Mines and Steel Development;

(ii) Ministry of Power;

(iii) Ministry of Water Resources;

(iv) Ministry of Environment; and

(v) Infrastructure Concession and Regulatory Commission

Page 20: 2011 Annual Report of Federal Ministry of Power.pdf

19

The Committee has so far reviewed existing studies and literature on the

availability of coal in the country and the following fundamental issues were

noted:

(i) A significant proportion of the coal blocks in the country have

already been released on concession to the private sector but with

little or no development;

(ii) In pursuit of the privatization of the Nigeria Coal Corporation, some

of the coal blocks owned by the company have been put on

concession by the Bureau of Public Enterprises;

(iii) Most of the initiatives by the private sector towards developing coal-

fired power plants are being frustrated by lack of credible and

bankable estimate of the coal reserves;

(iv) Some of the coal blocks owned by the Nigeria Coal Corporation are

still being held by the Bureau of Public of Enterprises and may be

offered on concession.

In an effort to bridge the information gap and facilitate the development of

bankable coal to power projects, the Committee concluded that the following

studies would be needed:

(i) A bankable estimation of the coal reserves in identified blocks based

on internationally acceptable standards;

(ii) A detailed evaluation of the quality of the coal;

(iii) An assessment of the infrastructural requirement for developing

such coal-fired power plants;

(iv) A review of the transmission infrastructure in the vicinity of the

proposed site;

(v) An evaluation of the Environmental and Social Impact Assessment;

and

(vi) A determination of the optimal plant capacity that may be supported

by the identified coal blocks and/or consolidation of blocks.

In consideration of the aforementioned requirement, the Committee

recommended that the conduct of a Bankable Feasibility Study would be the

expedient means of addressing all the issues identified by the review.

Furthermore, it was concluded that the feasibility study shall be anchored on coal

blocks that are devoid of any encumbrances by third parties. In this respect, the

Page 21: 2011 Annual Report of Federal Ministry of Power.pdf

20

NCC blocks located in Enugu axis and currently under the custody of BPE

(identified as Lot I) were considered as the best candidates for such a study.

Other eligible coal blocks within the Benue/Kogi/Gombe axis were identified

through the Mining Cadastral and captured as Lot II in the procurement.

LOT I: ENUGU AXIS

(i) Ezimo Coal block: The area lies approximately 70 kilometers north

of the city of Enugu. The block lies within the coordinates long. 7º

31´E, lat. 6º 51´N. 7 º 31´E, lat. 6 º 54´ N; long. 7 º 34´E, lat 6 º

54´ N; long 7 º 34´ E, lat 6 º 51´ and covering an area of 3706.82

Hectares;

(ii) Onyeama Coal block: The area is located south of Ezimo along

the eastern flank of Anambra Basin on the foot of Enugu

Escarpment. The block lies within the coordinates long. 7º 27´E, lat.

6º 29´N. 7 º 27´E, lat. 6 º 26´ N; long. 7 º 24´E, lat 6 º 26´ N;

long 7 º 24´ E, lat 6 º 29´ and covering an area of 3,028.165

Hectares;

(iii) Okpara Coal Block:Okpara bock is located south of Onyeama

along the eastern flank of Anambra Basin on the foot of Enugu

Escarpment. The block lies within the coordinates long. º 25´E, lat.

6º 22´N. 7 º 25´E, lat. 6 º 25´ N; long. 7 º 29´E, lat 6 º 25´ N;

long 7 º 29´ E, lat 6 º 22´ and covering an area of 4,014 Hectares;

(iv) Amansidiodo Coal Block: The block lies within the coordinates

long. 7º 17´E, lat. 6º 29´N. 7 º 10´E, lat. 6 º 29´ N; long. 7 º 10´E,

lat 6 º 33´ N; long 7 º 17´ E, lat 6 º 33´ and covering an area of

12,500 Hectares; and

(v) Inyi Coal Block: The block lies within the coordinates long. 7º

17´E, lat. 6º 09´N. 7 º 17´E, lat. 6 º 06´ N; long. 7 º 15´E, lat 6 º

06´ N; long 7 º 15´ E, lat 6 º 09´ and covering an area of 2601.16

Hectares.

LOT II: BENUE/KOGI/GOMBE AXIS

Page 22: 2011 Annual Report of Federal Ministry of Power.pdf

21

(i) Abocho Coal Block (Kogi): The area is located near Abocho

Township road linked to Dekina – Emewe State Road linked to

Dekina-Anyigba Federal Road. The coordinates of the coal mine is

5km away from Latitude 7 º 38´ 45´´N, Longitude 7 º 11´ 15´´E;

(ii) Markudi Coal Block (Benue): The area is located in the outskirts

of Markudi Township on Markudi-Otukpo State Highway. The

coordinates of the coal mine is 142 km from km away from Latitude

7 º 30´N, Longitude 6 º 36´E

(iii) Gombe Coal (Gombe): The area is located in the northeast of

Nigeria in Akko LGA of Gombe State near Kumo town 34 kilometers

from Gombe on the Numan road.

The Committee therefore developed a Request for Proposal (RfP) and the Terms

of Reference contained therein designed to address the information gap outlined

in paragraph 5 above.

In line with the Public Procurement Act, an invitation for prequalification of

bidders was published in the Economist, Federal Tenders Journal, Daily Trust and

ThisDay Newspapers of March 22, 2010 and a total of fifteen (15) companies

were prequalified by a Committee established by the Ministry. The method of

selection, in line with international best practice, was Quality and Cost Based

Selection (QCBS). In order to ensure that only companies with requisite

qualification and experience were appointed for the consultancy service, Messrs

Colenco Power Engineering was retained to conduct the Technical Evaluation and

only technically qualified contractors were considered further for financial

evaluation. The Tender Evaluation Report submitted by MessrsColenco Power

Engineering Ltd had been appraised by the Bureau of Public Procurement for

compliance with the Public Procurement Act and other extant guidelines and the

under-listed Due Process Certificates of No Objection were granted by the

Bureau.

(i) Lot I: Due Process Certificate of No Objection for the award of contract

in favour of Messrs of MessrsSteagEncotec West Africa/IMC in the sum of

£2,141,096.00 plus N296,049,783.72 inclusive of 5% VAT; and

Page 23: 2011 Annual Report of Federal Ministry of Power.pdf

22

(ii) Lot II: Due Process Certificate of No Objection for the award of contract

in favour of Messrs GTA/WAPCOS in the sum of US$4,157,000.00 plus

N188,622,000.00 inclusive of 5% VAT

The Federal Executive Council had considered the procurement and approved the

award of contracts on the basis of above recommendations. The Consultants

have since commenced work on the assignment and are currently evaluating the

EOIs in respect of the geotechnical investigations under the contract.

Other Sources of funding for the Power Sector

In the light of the significant capital cost of power infrastructure, the following of

initiatives outside budget are being pursued by the Ministry:

Collaboration with the World Bank: The World Bank has in many respects

supported the Ministry towards the development of the power sector. In

particular, the ongoing National Energy Development Project through PHCN/PMU

is executing numerous capital projects and sectoral studies for the industry. The

Ministry has also finalized on a new initiative under the World Bank tagged

Nigeria Electricity & Gas Improvement Project (NEGIP). The project is designed

to provide risk mitigation measures for gas supply to the industry (Partial Risk

Guarantee (PRG) and payment for wholesale power delivered by Independent

Power Plants. The NEGIP project further seeks to provide funding for

investments towards the infrastructural bottlenecks that may arise as a result of

increased power generation arising from an improvement in gas supply.

However, the counter-indemnity Agreement between the bank and the Federal

Government is yet to be executed as the creditworthiness of the “Bulk Trader” is

anchored on the PRG. The department has also worked with the Bank to develop

an internal Carbon Finance Group that would facilitate the development of CDM

projects within the power sector. In particular, the Group is expected to package

the following investments for carbon credits:

Rehabilitation of power plants;

NIPP Power Plants

Renewable Energy Projects (Wind Farm)

Energy Efficiency Projects (e.g Compact Fluorescent Lamps)

Page 24: 2011 Annual Report of Federal Ministry of Power.pdf

23

African Development Bank: The ABD is providing a concessionary sum

US$150million in the form of budget support for the Federal Government. The

triggers for disbursement are linked to the Power Sector Reform agenda and the

National Assembly has approved the loan under the 2010 Borrowing Plan.

AfD: The French development bank, AfD, has offered a concessionary loan of

US$170 million for the projects in the power sector. The loan has also been

approved by the National Assembly under the 2010 Borrowing Plan. The Ministry

of Power has submitted a formal request to the Ministry of Finance for the facility

but the latter is yet to forward same to AfD. The AfD has indicated a deadline of

July 20, 2011 for the receipt of the request so as to meet up the timeline of its

Board of Directors. The bank has also pledged its readiness to provide US$150

million concessionary loans annually in support of the power sector.

Sellers’ Credit: A number of internationally reputable companies such as AK-AY

of Turkey are have indicated an interest to fund Transmission and Sub-station

projects with repayment spread over a period of 5 – 10 years. However, all the

proposals require a Sovereign Guarantee due to the below par credit assessment

of TCN.

b) Electrical and Inspectorate Services Department

Statutory Duties/Functions

The Electrical Inspectorate Service Department of the Ministry was

established by an Act of Parliament in 1954. It had its legal instrument of

Operation in the Electricity Act chapter 57 (Cap 57) which later became

Cap 106 of 1990 and revised and gazetted in 1996. The department is

vested with the following statutory duties and responsibilities of ensuring

safety of lives and property and security of supply in the electricity

industry:

The inspection, testing and certification of all electric power

transmission lines and distribution networks Nationwide and

Independent Power Producers Projects:

The inspection, testing and certification of Large consumers electrical

installations such as large and high rise commercial buildings,

Industries/Factories premises, breweries etc;

Page 25: 2011 Annual Report of Federal Ministry of Power.pdf

24

The inspection, testing and certification of Completed rural

electrification projects consisting of primary injection substations, 33kV

sub-transmission lines and 33/11kV distribution networks:

The licensing of privately owned generating sets which are outside the

capacity limit of the Nigerian Electricity Regulatory Commission (NERC)

i.e 1MW and below:

The issuance of electrical installation licenses to competent and

qualified electrical contractors:

The investigation of electrical accidents and electrocution for safety of

lives and property, with a view to finding out the causes and ways of

preventing future occurrences in line with the provisions of the

Regulation:

Revenue generation for Government:

The inspection, testing and certification of electric concrete poles for

use in the electricity industry:

In addition to these statutory duties, the Department

Coordinates the implementation of the Japanese grant-in-aid for rural

electrification in Nigeria:

oversees the activities of the Rural Electrification Agency: -

comments of Director, EIS needed on the matter based on

reaction from REA

Coordinates all issues relating to Renewable Energy and Energy

Efficiency:

Coordinates the implementation of small and medium hydropower

projects:

To carry out these functions the Ministry established 15 Area offices

throughout the Country located at Abeokuta, Akure, Ibadan, Lagos,

Enugu, Kaduna, Kano, Sokoto, Maiduguri, Yola, Abuja, Ilorin, Jos, Benin

and Port Harcourt

Achievements

The Electrical Inspectorate Services achieved the followings:

Page 26: 2011 Annual Report of Federal Ministry of Power.pdf

25

Main Statutory duties

A total of 650 electrical installations including generation, transmission

and distribution power projects were inspected and tested out of which

450 were certified for use:

A total of 790 electrical installation licences were issued from January

to date:

The department through its Area offices generated a total revenue of

nineteen million two hundred and seventy one thousand seven

hundred and eighty two naira ( N19, 271, 782.00) from January

2011:

A total of 50 electrical accidents/electrocutions were reported of which

a total of 36 have been investigated from January 2011 to date:

Japanese grant-in-aid rural electrification project

The project involves electrification of selected rural communities located

in difficult terrain and/or inaccessible to the national grid.

Electrification of Eburutu communities (MAP 1 & II) in Cross-rivers State

completed except map III where there was communal conflict:

Ibedu Ibiaikot communities‟ rural electrification in Akwa Ibom State

completed and energized.

Present Efforts in Renewable Energy

Due to the need to diversify energy mix, in view of the

present monopolistic type of fuelling and imbalance in the location

of the existing power stations, the use of renewable energy is

encouraged to provide alternative sources of power generation

especially in the rural areas. To this end, the Ministry is coordinating

an Inter-Ministerial Committee on Renewable Energy and

Energy Efficiency.

Solar Projects

The Ministry has completed the solar power pilot projects in Ogun and

in Cross Rivers State:

Waste-to-Power

Page 27: 2011 Annual Report of Federal Ministry of Power.pdf

26

The Ministry is collaborating with the Federal Ministry of

Environment to work on the Waste-to-Power Project and other RE

projects:

Small and Medium Hydro Power Plant

The Department had carried out consultancy studies and engineering

designs of 13 identified dams for power generation so as to produce

bankable documents which will make them executable. The ten (10)

executable dams out of the identified ones are ready/awaiting

concessioning: These are:

10MW Oyan Dam in Ogun State, 6MW Ikere Gorge in Oyo State, 3MW

Bakolori Dam in Zamfara, 7.5MW Challawa Dam in Kano, 10MW Tiga

Dam in Kano, 500KW Kampe Dam in Kogi State, 450KW Owena Dam in

Ondo State, IMW Doma Dam in Nasarawa State, 300KW Zobe Dam in

Katsina State and 4MW Jibia Dam in Katsina State.

The Ministry is liaising with Infrastructure Concessioning

Regulatory Commission (ICRC) on the Concessioning of the dams for

PPP:

The Ministry is collaborating with the Federal Ministry of Water

Resources on the concessioning of the Power components of all dams

in Nigeria:

Construction of 1.2MW hydropower plant at Amoke in Benue State.

Selection of contractor is ongoing as a tripartite project by the Ministry

of Power who is to provide the civil works, while Benue State

Government will handle all environmental issues and UNIDO to provide

the turbines.

The Federal Ministry of Water Resources is constructing a multi-purpose

dam in Kashimbila, Taraba State with a 40MW power component.

The Ministry is involved in the project component of the project being

funded by Federal Ministry of Water Resources. The Ministry will handle

the power evacuation through Transmission Company of Nigeria. (TCN)

The Ministry is also involved in the implementation of Gurara Phase I

& II being handled by Federal Ministry of Water Resources:

Page 28: 2011 Annual Report of Federal Ministry of Power.pdf

27

The Ministry on behalf of the Federal Government had signed an MoU

with the Nordic Countries on cooperation & development of energy

sector in Nigeria in particular renewable energy:

The Federal Government signed a Financial Agreement of Euro700,000

with the German KfW for Hydropower studies under the auspices of

National Energy Council :

c) Investment and Sector Development Department (ISD)

INTRODUCTION

The Department of Investment and Sector Development was created in

2008 in line with the Reform Agenda of the Federal Government in addressing

the problems of prospective power Investors who would respond to the

Government initiative in making electricity available to the citizenry.

STRUCTURE

The Department comprises two divisions as follows:

(i) Investment Division

(ii) Sector Development Division

FUNCTIONS

The Department of Investment and Sector Development is responsible for

carrying out the following functions:

Undertaking necessary investment appraisal for projects and

activities related to system expansion plan;

Coordinating all the activities of the Standing Committee on IPPs as

a way of finding out the challenges hindering the take-off of the

licensed IPPs since 2006, and to make appropriate recommendations

to the HMP for their take-off.

Promoting commercial and Technical practices in the Industry

particularly in respect of the Public Owned Enterprises;

Through the Public Private Partnership Unit, the Investment and

Sector Development Department interfaces with the Infrastructure

and Concession Regulatory Commission throughout out the lifestyle

of Projects for concessioning.

Page 29: 2011 Annual Report of Federal Ministry of Power.pdf

28

Formulating Policies, Strategies and ensuring that adequate planning

of the Electricity Industry is achieved in line with the Federal

Government set objectives: that is to make affordable and reliable

electricity available to all Nigerians, to help drive the economic

growth as well as meet the challenges that require electricity;

Developing Strategies and Appropriate Policies that will make the

Power Sector financially viable and able to facilitate economic

growth; and

Following up on Electricity Development Programmes and project

implementation.

ACTIVITIES

In a bid to carrying out the functions stated above, the Department has

undertaken the following activities amongst which are:

Programmes:

Standing Committee on Independent Power Projects:

The Department superintends over the Standing Committee on IPPs (Inter –

Ministerial Committee) which was set up by Government, to provide a one-stop

shop to investors. The Committee interacts with prospective investors on

information they need to know as well as sell out the objectives of Government

including highlights of incentives available. The membership of the Committee is

drawn from the following MDAs and Government Agencies i.e

-Power Holding Company of Nigeria (PHCN)

-Transmission Company of Nigeria (TCN)

-Nigerian Electricity Regulatory Commission (NERC)

-Central Bank of Nigeria (CBN)

-Federal Ministry of Finance (FMF)

-Federal Ministry of Power (FMP)

-Federal Ministry of Environment (FME)

The Committee, since inauguration till date had met with twelve (12) licensed

and sixty–seven (67) prospective Investors some of which were identified by the

Committee to be Engineering Procurement Contractors (EPC). In addition some

Page 30: 2011 Annual Report of Federal Ministry of Power.pdf

29

investors indicated interest in the development of the transmission aspect of the

Sector.

The Committee at the end of each meeting with the Prospective Investors

provides through the Secretariat for those that require them, Letters of

Comfort in lieu of guarantees to International Financial Institutions, Letters of

Introduction to Embassies for processing of Visas and Letters of

Commendation for presentations made which serves as a medium for fast

tracking the implementation of the Project.

Study Tour of Existing Power Stations :

The staff of the Department embarked on the study Tour of some of the existing

Power Stations in order to acquaint them with the knowledge of the operations

of the Plants and enhance the efficiency and productivity in the discharge of their

duties on issues relating to Sector Development.

Jatropha as an Alternative Source of Power Generation

An Inter-ministerial Committee on Jatropha Curcas Development in Nigeria was

inaugurated in March 2010 and held several meetings up to December, 2010.

This Committee has been dormant but with the recent change in the leadership

of Ministry, the Department has revisited the Jatropha Development programme

as other MDAs and Organisations are doing one project or the other on Jatropha

for the exploration of alternative sources of power generation. A proposal to

convene an Inter-ministerial meeting on Jathropha is in the pipeline with a view

to coming up with policies on Jathropha Projects in Nigeria and to come up with

a National Jathropha Network for mutual support , collaboration amongst the

Farmers, Researchers, Academia and the Investors.

d) Human Resources Management Department

The Human Resources Management Department is one of the Common Services

Departments of the Ministry.

Its Mandate is carried out under its two Division, namely; Appointments,

Promotion and Discipline (APD) and Staff Welfare and Training (SWT).

The APD Division is charged with matters relating to appointments, upgrading,

conversions and discipline of its staff and those of its Parastatals. The SWT

Page 31: 2011 Annual Report of Federal Ministry of Power.pdf

30

Division is charged with the general welfare of its staff especially in the areas of

accommodation, sports, cleaning, union activities, stores management etc and

the training of its staff both locally and internationally.

The Charter is an expression of the commitment and resolve of the Human

Resources Management Department to provide efficient services on Human

Resources for the entire Ministry and its Parastatals.

FUNCTIONS OF HUMAN RESOURCES DEPARTMENT

To ensure proper office management and general administration of the

Ministry;

To ensure that qualified Personnel are sourced and / or deployed

accordingly to man appropriate officers;

To ensure that qualified staff due for promotion are presented for the

exercise as and when due, thereby ensuring institutionalization of

adequate succession planning mechanisms in thee the Ministry‟

To maintain general discipline of staff in line with PSR, FR, and Extant

Circulars and Civil Service norms.

To ensure that staff are exposed to all relevant training programmes.

To ensure that welfare provisions are made available to staff in accordance

with the provisions of the PSR and extant circulars.

To ensure that office accommodation are adequately provided through

liason with OSGF and OHCSF.

To ensure that staff participate in sporting activities to maintain good

health.

To ensure that appropriate working environment and materials are

provided for all staff.

Page 32: 2011 Annual Report of Federal Ministry of Power.pdf

31

e) Planning, Research & Statistics Department

The planning, Research and Statistics Department is one of the four

(4) Common Services Departments of the Ministry. It comprises of

three Divisions namely: Planning Division, Monitoring and Evaluation

Division; and Research & Statistics Division (which also oversees the

ICT Unit and the Ministry‟s Library). The mandate of the Department

included the following:

Preparation and Submission of the Ministry‟s Federal Executive

Council (FEC) Memoranda to the Cabinet Secretariat;

Compilation and Submission of returns on implementation of

decisions of the Federal Executive Council to the Policy

Implementation and Monitoring Unit of the Presidency;

Coordination of Ministerial / Inter – Ministerial Meetings;

Coordination of the Ministry‟s participation in bilateral and

multilateral relations as well as International Joint Commission

meetings with the Ministry of Foreign Affairs (MFA) and the

National Planning Commission (NPC) respectively;

Conducting research studies into identified and approved

projects in the Power Sector of the Nigerian Economy;

Management of the Ministry‟s Energy Data Bank, computer

Services and Library;

Setting and monitoring of Performance Efficiency Targets;

Monitoring and Evaluation (M&E) of all power sector project;

Liaison with Government Agencies and other bodies outside

the Ministry;

Dissemination of information and correspondence with the

Ministry‟s Parastatals;

Preparation of progress and Annual Reports to showcase the

activities of the Ministry;

Coordinating of annual Ministerial Press Briefing;

Coverage of meetings of the Honourable Minister with CEOs of

Parastatals and Agencies and meetings of the Permanent

Secretary with the Directors and Head of Units; and

Any other duties as may be periodically assigned to the

Department.

Page 33: 2011 Annual Report of Federal Ministry of Power.pdf

32

f) Procurement Department

The Procurement Department was created with the signing into law of the Public

Procurement Act, 2007 by Mr. President, Alhaji Umar Musa Yar‟Adua on 4th June,

2007. The Federal Executive Council took steps to establish an institutional

frame work to ensure effective implementation of the Act via Circular No.

HCSF/PSO/150/25 dated 31st March, 2008 issued by the Head of Civil Service of

the Federation which direct the immediate take-off of Procurement Departments

in all the Ministries, Departments and Agencies (MDAs). Subsequently, through

another Circular No: HCSF/PDO/155/25 dated 9th June, 2009 directing ful

implementation of the Public Procurement Act by all MDAs. MDAs were also

advised to make arrangements to receive the Procurement Officers.

The Procurement Department is bestowed with the responsibilities of ensuring

that all procurements (both Capital and Recurrent) are administered in

compliance with the Public Procurement Act, 2007. This involves the

administration of Due Process in the Procurement of goods, works and services

and the award of all contracts in the Ministry.

The commitment of the Procurement Department is to provide efficient

procurement services by making sure that procurement processes of the Ministry

and its Parastatals are carried out according to the provisions of the Public

Procurement Act, 2007.

DUTIES AND RESPONSIBILITIES

Officers in the Cadre shall perform the following duties;

Monitoring and oversight of Public Procurement, harmonizing the existing

government policies;

Prepares an effective Procurement Plan for the Ministry (Procurement

plans of different departments or units are combined into one single plan),

identifying what needs to be procured, how project needs can best be

met, the scope of the goods, works and services required what

procurement strategies or methods to be deployed, setting the time

frames, and the responsibilities for the full procurement process. This

Procurement Plan is usually prepared during the annual budgeting

process, preferably during the last quarter of each year.

Page 34: 2011 Annual Report of Federal Ministry of Power.pdf

33

It coordinates all activities of Ministerial Tenders Board (MTB) which

include tender solicitation, analysis, selection and award of contract for

the procurement of goods, works and services within approved threshold

for the Ministry‟s projects.

It carries out supervisory functions and capacity building on the

procurement process of TCN and PHCN successor companies including the

provision of a secretariat to MTB.

It is responsible for stocks procurement and disposal, verification,

documentation and administration.

Ensuring that all procurements (both Capital and Recurrent) are

administered in compliance with the Public Procurement Act, 2007. This

involves the administration of due process in the procurement of goods

and services and the award of all contract in the Ministry, Departments

and Agencies to which they are deployed (due process here refers to the

open and competitive tendering system which includes, but not limited to,

open advertisement of proposals for suppliers and contract awards, pre-

qualification of suppliers and contractors where appropriate, submission

and open evaluation, etc.).

Maintenance of register/database of suppliers, contractors and consultants

for the Ministry/Department/Agency and the payment of appropriate fees

for tendering purposes.

Maintenance of a periodically up to – date price data base as may be

provided by the Bureau of Public Procurement for public Sector

Procurement contracts and awards and conducting independent price

verifications and independent market analysis‟ reviewing Bills of

Quantities, ensuring compliance with scope of works, schedules, etc

where necessary.

Superintending strict adherence to all extant regulations and procedures

on procurement of contract awards with emphasis on ensuring

transparency and accountability in the tendering processes.

Liaison with Bureau for Public Procurement Planning Committee (BPP) or

any other organization/agency on matters relating to contract awards;

particularly obtaining certificate of with BPP and generally attending to

queries regarding procurements and settlement of disputes.

Facilitate and Co-ordinates Procurement/Planning Committee (PPC); and

Ministerial Tenders Board (MTB) meetings Manages records and

Page 35: 2011 Annual Report of Federal Ministry of Power.pdf

34

information relating and emanating from procurement proceedings,

including obtaining necessary approvals, etc.

STRATEGIC FOCUS

The Department Planned to focus on effective procurement (Capital

and Recurrent) that meets the provisions of the public Procurement Act,

2007 and due process requirements. It also intends to reposition for

greater achievement in 2012, by monitoring all the ministry‟s projects.

g) Finance and Accounts Department

The Finance and Accounts Department is one of the common Services

departments of the Ministry. The department is divided into three divisions i.e.

Finance, Accounts and Budget with two Deputy Directors. The Department is

responsible for the preparation of the Ministry‟s Budgets through the Budget

division and the payment of the entire Ministry‟s financial transactions approved

by the Accounting officer (Permanent Secretary).

OUTLINED FUNCTIONS OF THE FINANCE AND ACCOUNTS

DEPARTMENT

Recording and updating of funds allocated into vote Books.

Processing and issuing of AIE for approved bills and claims.

Preparation of Daily, weekly and monthly balances and Returns.

Preparation of payment vouchers and Recording of AIEs.

Recording and balancing of Vote Books on daily basis.

Answering of Internal Audit Quarries.

Maintaining of cash Books and Mandate summary Registers.

Safe keeping of security Documents and writing of Payment

Mandates.

Collection of Revenue and Bank payments.

Handling Banking Transactions.

Checking and passing of payment vouchers, salary and LPCs.

Receipt and safe keeping of payment vouchers.

Page 36: 2011 Annual Report of Federal Ministry of Power.pdf

35

Batching and pre-listing of payment vouchers.

Analysis of Revenue and payments into Analysis Books.

Preparation and submission of Monthly Transcripts and ATRRS.

Reconciling Bank Statements with Cash Office Books.

Preparation and submission of Bank Reconciliation Statements

Preparation of payment Vouchers for all Advances.

Recording/Documentation of Retirement of Personal and

Non – Personal Advances

Control of Advances Ledger/Registers.

Control of Advances Vote Books.

Handling of Public Account Committee Matters.

Opening of New Personal Emolument Cards.

Receiving and processing of salary variations.

Controlling of salary payments and Group Registers.

Preparation of Staff salary deduction and summaries.

Preparation of Last Pay Certificates (LPCs)

Compilation of Nominal Roll, and Leave Roster for Accounts Staff.

Handling of Administrative matters that affect Accounts.

Other assignments as directed by Management.

h) Legal Unit

The Legal Unit of the Ministry falls under the Office of the Honourable Attorney-

General of the Federation, whose office is a constitutional creation by virtue of

Section 150 of the constitution of the Federal Republic of Nigeria 1999. Being a

Unit under the Ministry, it exercises such functions and powers that are

exercisable by the Honourable Attorney-General of the Federation pursuant to

Section 174 (2) of the Constitution.

Page 37: 2011 Annual Report of Federal Ministry of Power.pdf

36

The Unit constitutes a clearing house for all legal matters for which the Ministry

is involved. The core functioning of the Unit includes but not limited to the following:

Drafting/Vetting of Legal documents and Agreements for the

Ministry;

Rendering Legal opinion/advice on all legal matters referred;

Handling litigation matters on behalf of the Ministry;

Negotiation of contract terms and conditions on behalf of the

Ministry.

In order to effectively discharge its constitutional/administrative responsibilities

within the purview of the Ministry of Power, the Unit is guided by the provisions

of the Constitution of the Federal Republic of Nigeria, Procurement Act, National

Electric Regulatory Commission Act, Law Reports of various Courts, Electric

Power Sector Reform Act and other extant Laws.

i) Internal Audit Unit

In line with Financial Regulations 20, the Internal Audit Unit of the Ministry was

established to provide a complete and continuous audit of the Accounts records

of revenue and expenditure, plants, allocated and unallocated stores where

applicable. The Unit is directly responsible to the Accounting Officer for

comprehensive audit of all operations and activities of the Ministry. In this

regard, it carries out not only Financial Audit but also Compliance Audit,

Performance Audit and Management Audit of other areas of the Ministry with a

view to monitoring their economic efficiency and effectiveness.

The functions of the Internal Audit Unit include amongst others:

To secure the installation and maintenance of soundly based system of

control within the Ministry;

Page 38: 2011 Annual Report of Federal Ministry of Power.pdf

37

To review and where necessary make recommendations for the

improvement of systems, controls and procedures in order to ensure that

they are both efficient and effective;

To assist in protecting the assets and interests of the Ministry eg; by

carrying out continuous examination of activities in order to prevent or

promptly detect fraud, misappropriation, irregular expenditures or losses

of cash by ensuring that the rules, regulations and extant

circulars/instructions are observed;

To monitor the use of resources in the pursuit of the objectives

established by law and other authorizing bodies; and

To render monthly, quarterly, half-yearly, and special reports to

appropriate authorities.

j) Press & Public Relations Unit

The schedule of duties for the Press and Public Relations Unit are as

follows:

* Arranging press conferences, briefings, interviews for the Honourable

Minister.

* Ensure that information and facts in annual/quarterly Ministerial Briefings

are correct.

* Ensuring that the ecstatic beauty of the Ministry is guaranteed at all times

with artworks, pictures and graphics.

* Accompanying the Hon. Minister/Permanent Secretary on official assignments, in and outside Nigeria and ensuring that appropriate news

items are generated from such trips.

* Coverage of courtesy visits/meetings.

* Covering all interactive sessions of the Ministry officials/ Stakeholders and

the Media or related bodies.

Page 39: 2011 Annual Report of Federal Ministry of Power.pdf

38

* Monitoring of Local and International news reports on both Electronic and

Print Media for feedback.

* Daily compilation of Newspaper/Magazine reports/Press Clippings on

Power related matters and weekly Press Review.

* Dissemination of information through press releases, feature articles, internet etc.

* Sending Press Releases with Photographs to the Federal Ministry of Information website www.fmic.gov.ng. and all Media Houses on daily

basis.

* Populate, edict and ensure contributions for a functional, educative and

informative website for the Ministry‟s website [www.power.gov.ng].

* Responsible for the designing and placements of advertisements, and

announcements on print and electronic media.

* Covering activities/programmes of the Ministry as Master of Ceremony.

* Ensuring documentation through production of Photographs, CDs, DVD‟s,

Videotapes, VCDs, etc. for dissemination and for the archives.

* Any other duty as assigned by the Honourable Minister and the Permanent

Secretary.

k) SERVICOM Unit

The SERVICOM Unit came into being as a result of the Federal Executive Council

resolution of 10th March, 2005 that each Ministerial/Department/ Agency should

establish a Ministerial SERVICOM Unit (MSU). The MSU spearheaded the service

delivery initiative of the Ministry towards SERVICOM Compliance, thereby

ensuring the promotion of quality assurance and best practices in the

performance of its functions.

FUNCTIONS OF SERVICOM UNIT

Disseminate best practices and other tips on Service Delivery Improvement within the Ministry.

Coordination and Publication of the Ministry‟s Charters. Monitoring the implementation of each Departmental Charter.

Page 40: 2011 Annual Report of Federal Ministry of Power.pdf

39

Coordinate meetings of the stakeholders‟ Consultative Forum on service delivery.

Periodically develop and carry out sensitization programmes on effective service delivery for all segments of staff in the Ministry.

Ensuring good reception areas for customers. Ensuring condusive working environment for members of staff.

Periodically report to the Ministry‟s Management on SERVICOM activities. Institute complaints procedure including Grievance Redress Mechanism for

the Ministry and Parastatals.

Keeping records and taking actions on complaints, comments and suggestions by customers.

l) Protocol Unit

The Unit covers the entire Ministry‟s Organizational outfit and co-ordinates the

Hon. Minister‟s work by producing weekly schedule for the Minister, handling of

the protocol administration of the Honourable Minister. The unit also provided

venues for Seminars, Conferences, Investitures for the Ministry, provides and

process all travelling documents for the Honourable Minister and member of staff

travelling for official events. The Protocol Unit, besides its image – making

functions, creates the right environment for the conduct of business of

governance and diplomacy to thrive in the Ministry.

VI. AGENCIES UNDER THE MINISTRY OF POWER

6.1 Power Holding Company of Nigeria (PHCN) Successor Companies

6.1.1 Generation Companies (GENCOS)

S/N GENCOS LOCATIONS

1 Afam Rivers State

2 Egbin Ogun State

3 Jebba Niger State

4 Kainji Niger State

5 Ughelli Delta State

6 Shiroro Nigeri State

7 Sapele Delta State

8 Olorunsogo Ogun State

9 Omotosho Ondo State

10 Geregu Kogi State

Page 41: 2011 Annual Report of Federal Ministry of Power.pdf

40

The Generation companies:

GEREGU POWER PLC, AJAOKUTA

2011 ANNUAL REPORT

INTRODUCTION

Geregu power station is a simple cycle gas turbine plant, with a total installed

capacity of 414MW. It has three (3) units, with each with capacity to generate

138Mw. The station was commissioned on the 26th of February, 2007. The first

unit GT13, started commercial operation on 19th March 2007, followed by GT12

on 20th April 2007, and GT11 on 12th May, 2007. The station can still generate up

to its installed capacity. The station has just been upgraded to a CEO status,

giving us greater impetus to achieve greater heights.

GENERATION 2007 TO 2011

Page 42: 2011 Annual Report of Federal Ministry of Power.pdf

41

2007 2008 2009 2010

2011

The station generated 1,494,591MWH of energy as at end of November 2011,

surpassing the previous year‟s generation.

SERVICE LEVEL AGREMENT (SLA)

1135612 997125.4

378993.7

777622.8

1494591

1 2 3 4 5

ANNUAL TOTAL GENERATION MWH 2007 TO 2011

Series1

0

50

100

150

200

250

300

350

JAN. FEB. MAR. APR. MAY JUN. JUL. AUG. SEP. OCT. NOV. DEC.

MW

SLA PERFORMANCE 2011

Average Generation MW

SLA Commitment MW

Lower band (65%) MW

High Band (85%) MW

Page 43: 2011 Annual Report of Federal Ministry of Power.pdf

42

The station on the whole has consistently been above the lower band of the

SLA, except in May due to delayed arrival thermocouples needed for the

replacement on the units, and October arising from gas stoppage to the

station by Nigerian Gas Company.

KEY PERFORMANCE INDICATORS

The station had gas supply stoppage by NGC in October leading to a fall in

performance in the Load Factor.

INVESTMENT OPPORTUNITY

I. Re-Design of the IGV, to give it the frequency control capability, at

least for one unit.

II. Repair and upgrading of the Win-Tx. This will provide the necessary

data required from the flight recorder for the re-design of the IGV. It

will also make it possible to communicate with Siemens AG service

department, in time of technical advice during running or breakdown

and planning of maintenance. This will ultimately improve life span of

the plant, and improve generation. (760,000 euro.)

0

0.2

0.4

0.6

0.8

1

1.2

IND

EX

KPI JAN. TO AUG. 2011

Load Factor

Generation Utilization index

Capacity Utilization index

Planned Mtce Index

Breakdown Mtce Index

Station Reliability Index

Page 44: 2011 Annual Report of Federal Ministry of Power.pdf

43

III. Combine cycle. Investment in the building of a combine cycle will make

it possible to use a Heat Recovery Boiler to generate steam to produce

around 150 to 200MW. Now the hot gases from the gas turbine are just

going into the atmosphere, which is a waste.

IV. In a privatized situation supported by economic tariff structure, a

bankable PPA, operational Gas sales and transportation agreement,

Geregu Power Station will be a very profitable business especially if an

O&M or Long Term Service Agreement is negotiated with the OEM.

KAINJI HYDRO ELECTRIC PLC

Kainji Hydro Plant is an old plant with turbine generating units of between 33 and 43 years old. The original development plan for Kainji provided for the total power installation of 960MW.

At the completion of the project in 1978, the total installed capacity was 760MW with 8No units leaving the four number open pits without installation of turbine generating units. These installed units have not under gone the required statutory overhaul apart from unit 1G11 which was fully rehabilitated in 2002, but now due for overhaul. This lack of statutory overhaul has made the units susceptible to frequent faults. Kainji hydro Electric Plc was incorporated on 1st July, 2006 as one the

PHCN successor companies. This premier Hydro Power Station in Nigeria

has pursued with vigor the actualization of its mission and vision

statements above by a resolution to the maintenance of six units in

service.

This we pursued by ensuring that effective and timely routine and annual

maintenance jobs were carried out promptly. In this regard, the year 2011

took off on a fine note with units viz: 1G6, 8, 10, 11, and 12 all available

and in service with a total load capability o 405MW.

The un-available units are;

- 1G5 (10.59hrs, 08/11/2000) - Major damage on the turbine and

Generator due to failure of the governor system.

Page 45: 2011 Annual Report of Federal Ministry of Power.pdf

44

- 1G7 (20. 11hrs, 23/09/2008) - Generator Stator winding failure.

- 1G9 (23.51hrs,10/09/2010) – High water leakages from the runner

inspection door

Meanwhile, 1G9 was returned back to the Grid at 16.33hrs on 14th March,

2011 after the sealing of water leakages from the runner inspection door

with a combined capacity of 200MW, 1G5 & 1G7) await the

commencement of the planned rehabilitation by federal Government/World

Bank for their return to the National Grid.

3. ACTIVITIES CARRIED OUT DURING THE YEAR 2011. The company staff developed efficient and effective Maintenance Management System (MMS) to reduce breakdown maintenance. Hence, daily, weekly, monthly annual maintenance jobs were carried out on the available units, transformers and plant auxiliaries. Some of the units were schedule for annual maintenance with a view to ensure maximum machine availability, sustenance, hence enhanced generation. The programs were carried out at a period of low water operating head mostly between April and August. The maintenance schedules, i.e. monthly inspection, annual maintenance as carried out are as shown below; i.e. (a, b, c)

Page 46: 2011 Annual Report of Federal Ministry of Power.pdf

45

4. YEAR 2011 PROPOSED JOINT MONTHLY INSPECTION (JMI) AND ROUTINE

PREVENTIVE MAINTENANCE SCHEDULE OF UNITS.

A.

YEAR 2011 (JMI & RPM) FOR STATION TRANSFORMER

UNITS JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

1G5 - - - - - - - - - - - -

1G6 4 3 3 5 3 2 7 2 8 4 3 6

1G7 - - - - - - - - - - - -

1G8 11 8 8 12 10 7 12 9 13 11 8 8

1G9 13 10 15 14 12 13 14 11 15 13 10 13

1G10 18 15 17 19 17 16 19 16 20 18 15 15

1G11 20 17 22 21 24 21 21 18 22 20 17 20

1G12 25 22 29 26 26 28 26 23 29 25 29 29

X JAN FEB MAR APR MAY JUN JUL AU

G

SEP OCT NOV DEC

GT5 - - - - - - - - - - - -

GT6 4 5 7 4

GT7/8 8 10 9 8

GT9/1

0

15 19 16 15

GT11 22 21 22 20

GT12 29 28 29 29

Page 47: 2011 Annual Report of Federal Ministry of Power.pdf

46

5. 2011 ANNUAL MAINTENANCE

B.

UNITS

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

1G6

1G11

1G12

SUMMARY 1G6 - 25TH JULY – 29TH AUGUST, 2011 (6 WEEKS) 1G11 - 3RD MAY – 8TH JUNE, 2011 (6 WEEKS) 1G12 - 9TH SEPT – 21ST OCT, 2011 (6 WEEKS)

UNITS ACTIVE DESCRIPTION PERIOD OF

MTCE

REMARKS

1G6 Unit Annual maintenance

including welding/grouting

of throat ring/runner

chamber

25th July to 29th

August 2011

(6weeks)

To sustaining unit

availability and as well as

arrest water leakages

emanating from the

cracked throat ring metal

structure.

1G11 Unit Annual Maintenance 3rd May to 8th To sustaining unit

Page 48: 2011 Annual Report of Federal Ministry of Power.pdf

47

7. MAJOR REPAIR FOR MEGAWATT RECOVERY AND SUSTENANCE OF

PLANTS

UNI

TS

ACTIVITY DESCRIPTIONS PERIOD OF

MAINTENANCE

REMARKS

1G6 a. Annual Maintenance of

the unit.

b. Welding and

reinforcement of the

cracked areas of the

throat ring externally

and internally.

3rd October, 2011

to 31st October,

2011.

(4weeks)

Sustain unit

availability, reliability

and capability as well

as arrest serious water

leakages emanating

from the cracked

throat ring metal

structure. Job

completed, re-

commissioning in

progress.

including welding/grouting

of throat ring/runner

chamber

June, 2011

(6week)

availability and as well as

arrest water leakage

emanating from the crack

throat ring metal

structure.

1G12 Unit Annual Maintenance

including welding/grouting

of throat ring/ runner

chamber.

9th Sept to 21st

Oct, 2011

(6weeks)

To sustain unit availability

as well as arrest water

leakages coming from the

cracked portion of the

throat ring

Page 49: 2011 Annual Report of Federal Ministry of Power.pdf

48

1G1

1

a. Annual maintenance of

the unit including under

water repair works on

1G11 intake gate B

buckled guide rails of the

bulkhead/screen gates is

completed.

25th May, 2011 to

18th August, 2011.

Unit re-

commissioned to

the grid on

12/8/2011.

Unit availability to full

capacity of (100MW)

after the repair works

on intake Gate B

buckled guide rails

was completed. The

unit has been

operating on one gate

before now, with

75MW capacity.

(25MW recovered)

Sustenance of the

unit.

1G1

2

a. Annual maintenance of

the unit including

welding and

reinforcement of the

external cracks on the

throat ring and turn

buckles to be carried

out.

a. Shut down due to

punctured main bearing

cooling coil.

22nd August – 3rd

October, 2011.

The unit has been

dewatered on

28/8/11 with the

assistance of

underwater diving

service provider.

Maintenance and

welding job

completed unit-in-

service.

To sustain unit

availability and

capability as well as

arrest serious water

leakages coming from

the cracked portions

of the throat ring.

1G8 a. Repair works on the oil

head and replacement of

new jackshaft/extension

completed.

a. Trouble shooting of high

governor sump

temperature including

Cannot be

ascertained now

for the unit has to

be dewatered for

proper fault

diagnosis, before

repair.

The unit will be out till

we are able to

complete the major

repair job on 1G6,. By

then, fault diagnosis

will start.

Page 50: 2011 Annual Report of Federal Ministry of Power.pdf

49

frequent tripping of

machine on governor

fault and profuse oil

leakage to the oil head

sump is suspended till

jobs on 1G6, 1G10 and

1G12 are completed.

8. THE PLANT STATUS AS AT 25TH NOVEMBER, 2011

UNIT

INSTALLED CAPACITY

PRESENT

CAPACITY

DATE OF

COMMISSIONI

NG

PRESENT

WORKING

CONDITION

PROBLEM ASSOCIATED WITH THE UNIT

DATE OF LAST

MAJOR OVERHA

UL

REHABILITATION

SCHEDULE

REMARK

1G5

120 MW

Nil 21/07/1978

Not Available

Failure of the unit was due to the Turbine Governor System failure with major damages to turbine and generator in Nov 2000

Nil To be retrofitted under NBA/World Bank Phase 1 project. Completion is 35 months from contract effectiveness

Contract awarded to Joint Venture Partners Hydro China Haudong Engineering Company & Harbin Electric Machinery Company was

signed on 27th

June, 2011.

1G6

120 MW

120MW

13/03/1978

Repair job complete Re-commissioning is in progress

Lack of statutory overhaul leading to Throat ring ruptures and excessive water leakage

Nil To be retrofitted under NBA/World Bank Phase 1 project. Completion is 42 months from

Contract awarded to Joint Venture Partners Hydro China Haudong Engineering Company & Harbin Electric Machinery Company

Page 51: 2011 Annual Report of Federal Ministry of Power.pdf

50

from turbine head cover .

contract effectiveness

signed on 27th

June, 2011.

1G7

80MW Nil 22/12/1968

Not Available

Generator stator winding insulation

failure.

Partially rehabilita

ted in 2002

First phase contract for the supply of stator

assembly coil awarded to Alstom. To be delivered in June, 2012.

Discussion with Hydro China Huadong for an offer on turbine

and auxiliary rehabilitation and the installation of the Generator stator is currently on going.

1G8

80MW NIL 23/12/1968

Unit out on governor fault. Investigation and repairs to commence at the

completion of units 1G6, repair work.

Excessive water leakage from the turbine head cover. Profuse oil leakage from the return motion tube to the oil

head sump.

Partially rehabilita

ted in 2002

Proposed for world Bank rehabilitation phase 2.

Need to be rehabilitated.

Page 52: 2011 Annual Report of Federal Ministry of Power.pdf

51

1G

9

80MW 30MW 13/02/1

969

Unit

available

and in-

service.

Derated

to

30MW

Weak and

aged stator

/ rotor

windings.

Aged

Generator

Transformer.

Old 16KV Generator

Circuit Breaker.

Nil Proposed

for World

Bank

rehabilitatio

n Phase 2.

Unit could be

decommissione

d if not

rehabilitated

soonest, as the

unit is no more

reliable.

1G

10

80MW 40MW 18/06/1

969

Unit

available

and in-

service.

Derated

to

40MW

Weak and

aged stator

/ rotor

windings.

Aged

Generator

Transformer.

Old 16KV Generator Circuit Breaker

Nil Proposed

for World

Bank

rehabilitatio

n Phase 2.

Unit could be

decommissione

d if not

rehabilitated

soonest, as the

unit is no more

reliable.

1G

11

100M

W

100M

W

29/01/1

076

Unit

available

and

In-

service.

Leaking throat ring / runner chamber.

Fully

rehabilita

ted in

May

2002.

Statutory

overhaul

required.

Unit contributes

40MW for Grid

Frequency

regulation apart

from 60MW set

entry point.

1G

12

100M

W

80MW 31/07/1

977

Unit

available

and

In-

service.

Excessive

water

leakage

from the

head cover.

Frequent

Nil 1st phase

World Bank

rehabilitatio

n.

Contract

awarded to

Contract award

signed on. 27th

June, 2011.

Page 53: 2011 Annual Report of Federal Ministry of Power.pdf

52

throat ring / runner chamber ruptures

Hydro-

China.

Completion

in 36

months

from

contract

effectivenes

s.

GT

9/1

0

13/02/1

969

Availabl

e and

de-rated

Aged Generator Transformer with high acoustic noise level.

Nil Need to

replace the

power

transformer

with a new

one

Repair carried

out to ensure

its availability

pending the

replacement.

9. PROJECT

PROPOSED REHABILITATION OF 1G7

The contract for the supply of Hydro Electric Unit 1G7 generator stator (Phase 1)

has been awarded to Alstom (OEM). Down payment of 15% has been made to

ALSTOM. Awaiting first batch of stator bars forecasts for February, 2012. Supply

is expected to be completed by the end of June, 2012.

10. RETROFITTING /REHABILITATION OF 1G5, 1G6 AND 1G12

The proposal for the first phase of rehabilitation/retrofitting of units 1G5, 1G6

and 1G12 is to be carried out through world bank/NBA (Niger Basic Authority)

(2008-2013). The due process programme of activities for this retrofitting is

under the purview of project Management Unit (PMU) division of PHCN corporate

Headquarters and it has been completed.

Contract awarded to joint venture partners Hydro China Haudong Engineering

Company & Harbin Electric Machinery Company was signed on 27th June,

2011. (USD81, 746,642.49).

Page 54: 2011 Annual Report of Federal Ministry of Power.pdf

53

The completion period for each of the units is as shown below;

1G5 - 35 months for contract

effectiveness

1G6 - 42months for contract

effectiveness

1G12 - 36months for contract

effectiveness

Auxiliary Services - 39 months for contract

effectivenes

11. PROPOSED REHILITATION/RETROFITTING OF UNITS 1G7, 1G8,

1G9 AND 1G10

The proposal for the rehabilitation / retrofitting of these units is planned

for the second phase of World Basin Authority (NBA) programme.

12. PROPOSED OVERHAUL OF 1G11

Unit 1G11 was fully rehabilitated in 2002, but now due for another

overhaul.

13. INVESTIMENT OPPORTUNITIES

There is also the possibility installing low operating head Kaplan turbine

generators in open pits 1-4 (the concrete structures are already in place)

possibly 60MW x 4 or 80MW x 3. This if done will allow for flexibility of

maintenance and also frequency regulation. The 33okV switch yard has to

be constructed for these units, if they are to be installed.

Page 55: 2011 Annual Report of Federal Ministry of Power.pdf

54

14. IMPORTANCE OF KAINJI UNITS REHABILITATION/ BENEFITS TO

THE NATION.

The generating plants will operate efficiently and reliably for many years

and contribute effectively to the power production in country, based on the

condition that the regular statutory overhaul as recommend/specified by

the manufacturer/ contractor are always done.

The station will be able to perform its statutory role fully, by Black Starting

the gird, controlling of the system frequency to achieve grid stability and

bulk power delivery, if fully rehabilitated.

15. STRATEGIC FOCUS

Costs effectively produce environmentally friendly, qualitative and

quantitative electricity.

Maintenance of adequate stock of tools and spares for rapid response to

faults.

Training and re-training of our work force on new and applicable

technology.

Minimize breakdown maintenance by application and deployment of best

practices of maintenance Management System (MMS).

Develop an effective Performance Management System.

Use the Kaplan advantage to handle frequent regulation and system

stability.

Units 1G8, 1G9, 1G10 should be considered for retrofitting/rehabilitation

as they are aged and some of the spares are no longer in production.

These units may be decommissioned as they are no longer reliable.

Timely release of budgeted money as the original equipment

manufacturer (O.E.M.) requires total sum of payment to be released

before letter of credit can be opened.

Page 56: 2011 Annual Report of Federal Ministry of Power.pdf

55

Expedite action on the proposed installation of low head Kaplan turbine

in open pits (1-4) concrete and intake structures are already in place.

16. WORK PLAN

YEAR 2012 ANNUAL MAINTENANCE PROGRAMME

SUMMARY

1G6 - 4th JUNE TO 30th JULY, 2012 (8 WEEKS)

1G11 - 2nd APRIL TO 28th MAY, 2012 (8 WEEKS)

1G12 - 1st AUGUST TO SEPT, 2012 (8 WEEKS)

MTHS JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

1G6

1G11

1G12

UNITS ACTIVE DESCRIPTION PERIOD OF MTCE REMARKS

1G6 Unit Annual maintenance

including welding/grouting

of throat ring/runner

chamber

4th June to 30th July

2012

(8weeks)

To sustaining unit

availability and as well

as arrest water

leakages emanating

from the cracked

throat ring metal

structure.

1G11 Unit Annual Maintenance

including welding/grouting

of throat ring/runner

2nd April to 28th

May, 2012

To sustaining unit

availability and as well

as arrest water leakage

04/06

to

02/04

to 28/05

01/08

to

Page 57: 2011 Annual Report of Federal Ministry of Power.pdf

56

6.1.2 Transmission Company of Nigeria (TCN)

Transmission Company of Nigeria (TCN) was incorporated in November,

2005. TCN emerged from the defunct National Electric Power Authority

(NEPA) as a product of the merger of Transmission and Operations Sectors

in April 1, 2004.

The Transmission Company of Nigeria (TCN) is one of the 18 unbundled

Business Units under the Power Holding Company of Nigeria (PHCN) and

was issued a Transmission License on 1st July, 2006.

ORGANIZATION STRUCTURE

Fig. 1 shows the organizational structure of Transmission Company Nigeria

The management team of TCN is headed by a Chief Operating Officer,

who is assisted by four Executive Directors in running the following sectors

of the company:

Finance and Administration headed by Executive Director (Finance

& Administration)

General Manager(Finance & Economic Services)

chamber

(8week)

emanating from the

crack throat ring metal

structure.

1G12 Unit Annual Maintenance

including welding/grouting

of throat ring/ runner

chamber.

1st August to 26th

September, 2012

(8weeks)

To sustain unit

availability as well as

arrest water leakages

coming from the

cracked portion of the

throat ring

Page 58: 2011 Annual Report of Federal Ministry of Power.pdf

57

Responsible for Finance & other related Services

General Manager(Corporate Services, Human Resources & Change

Management)

Responsible for Administration, Human Resources and other

Corporate Services matters

Market Operations headed by Executive Director (Market

Operations)

General Manager (Market Operations)

Responsible for coordination of Market Operations in the whole

network

Page 59: 2011 Annual Report of Federal Ministry of Power.pdf

58

MD/CEO(PHCN)

CEO(TCN)

Hon. Minister of Power

PHCNTransitional Board

TCNTechnical Monitoring

Committee

Executive Director(Transmission

Service Provider)

Executive Director(System Operator)

Executive Director(Finance & Admin)

Executive Director(Market Operations)

General Manager(Market Operations)

General Manager(Design & Construction)

General Manager(Mtce & Field Services)

General Manager(PSPR&D)

General Manager (Monitorin g /Evaluatio n)

General M anager (National Control

Center)

General Manager(Finance & Accounts)

General Manager(HR, CS & CM)

General Manager (Transmission)8No Regions

Page 60: 2011 Annual Report of Federal Ministry of Power.pdf

59

Fig. 1 The organizational structure of Transmission Company of Nigeria

System Operations Headed by ED (System Operations)

General Manager(NCC)

Responsible for coordination of Systems Operations in the whole

network

Transmission Services headed by Executive Director (Transmission

Service

Provider)

General Manager (Design & Construction)

Responsible for development of the Transmission Grid at 132kV and 330kV voltage levels with the view to increasing access to quality electricity in the country.

General Manager (Maintenance & Field Services)

Coordinates running and maintenance activities in the whole network by the eight (8) Regional Transmission Managers throughout the country

General Manager (Power System Planning, Research & Development)

Responsible for Transmission Grid planning, research and development.

General Manager (Monitoring and Evaluation)

Responsible for monitoring and evaluating Transmission projects nation-wide.

Eight(8) No. Regional Transmission Managers

These are responsible for running and maintenance of transmission and transformation facilities in their areas of operation, which are:

- Bauchi Transmission Region with Headquarters in Bauchi and covers Bauchi, Yobe, Adamawa, Taraba, Gombe and Plateau states.

Page 61: 2011 Annual Report of Federal Ministry of Power.pdf

60

- Kaduna Transmission Region with Headquarters in Kaduna and

covers Kaduna, Kano, Katsina, Jigawa and Zamfara states

- Shiroro Transmission Region with Headquarters in Shiroro and

covers Niger, Kebbi, Sokoto, Nasarawa states and the Federal

Capital Territory

- Benin Transmission Region with Headquarters in Benin and covers

Delta, Edo and Kogi states

- Lagos Transmission region with Headquarters in Ijora and covers

Lagos and Ogun states

- Osogbo Transmission Region with Headquarters in Osogbo and

covers Osogbo, Ekiti, Ondo, Oyo, Osun and Kwara states

- Enugu Transmission Region with Headquarters in Eungu and covers

Enugu, Anambra, Ebonyi and Benue states

- Port Harcourt Transmission Region with Headquarters in

PortHarcourt and covers Rivers, Cross Rivers, Bayelsa, Imo, Abia

and Akwa Ibom states.

ADAM

AW

A

GOMBE

YOBE

BORNO

BAUCHI

TARABA

PLATEAU

ZAMFARAJIGAWA

KANO

KATSINA

KADUNA

SOKOTO

KEBBI

NASS ARAWA

ABUJ

A

ONDO

NIGER

OSUN

EKITI

KWARA

OYO

DELTA

EDO

KOGI

ANAM

BRA

EN

UG

U

EBO

YI

BENUE

CRO

SS R

IVE

R

ABIA

AKWAIBOM

IMO

RIVERSBAYELSA

OGUN

Maiduguri W/C

Yola W/C

Makurdi W/C

Ajaokuta W/C

Jos W/C

Shiroro W/CKainji W/C

Jebba W/C

Abuja W/C

Dutse W/C

Kano W/C

Gusau W/C

B/Kebbi W/C

Kaduna W/CGombe W/C

New Haven W/C

Onitsha W/COwerri W/C

Calabar W/C

Ahoada W/C

Sapele W/C

Delta W/C

Papalanto W/C

Afam W/C

Ikot Ekpene W/C

Benin W/C

Benin North

Omotosho W/C

Osogbo W/C

Ilorin(Ganmo) W/C

Ayede W/C

Akangba W/C Ikeja West W/C Egbim W/C

Aja W/C

Page 62: 2011 Annual Report of Federal Ministry of Power.pdf

61

Fig. 2 Geographical Locations of the Transmission Regions.

EXISTING TRANSMISSION INFRASTRUCTURE

Two major facilities used by TCN to provide electrical service to its customers are

transmission lines and power transformers. Transmission lines can be described

as highways of electricity while power transformers are used at various points

along the way from generation to delivery and to final use. The existing

transmission system has the capacity to transmit about 6,662.3MW at 330kV and

8,238.2MW as portrayed in the following transmission network data as at 31st

October, 2011.

• 5,515.35km of 330 kV of Transmission lines

• 6,881.49km of 132kV of Transmission lines

• 33No. 330/132kV Substations with total installed transformation capacity

of 7,838 MVA (equivalent to 6,662.3MW)

• 106No. 132/33/11kV Substations with total installed transformation

capacity of 9,692 MVA (equivalent to 8,238.2MW)

• The Average Available Capacity on 330/132kV is 7,514MVA and 9,097MVA

on 132/33kV which is 95.9% and 93.7% of Installed capacity respectively

• Average Transmission Loss is 8.5%

Page 63: 2011 Annual Report of Federal Ministry of Power.pdf

62

Fig. 2. Existing National Transmission Grid

Fig. 3. Existing National Transmission Grid.

Page 64: 2011 Annual Report of Federal Ministry of Power.pdf

63

TCN HUMAN RESOURCES

SECTION DEPARTMENTS

(NUMBER)

WORK CENTRES

(NUMBER)

STAFF COUNT

(NUMBER)

CHQ 7 - 445

LAGOS REGION - 6 560

OSOGBO

REGION

- 5 321

KADUNA

REGION

- 5 327

BAUCHI

REGION

- 5 265

BENIN REGION - 5 271

SHIRORO

REGION

- 6 468

ENUGU REGION - 4 266

PH REGION - 6 267

NCC 2 - 148

TOTAL 9 32 3338

TRANSMISSION NETWORK INFRASTRUCTURAL DEVELOPMENT

Fig. 4. Transformation Capacity 2006 – 2011. Transformer capacity increased by

28.5% and 21% on the 330kV and 132kV networks respectively as a result of

replacement of lost capacities and additional capacities realized from completion

Page 65: 2011 Annual Report of Federal Ministry of Power.pdf

64

of new projects.

Fig. 5. Transmission Line Length 2006 – 2011.

330kV and 132kV Transmission Lines route length increased by 8.9% and 12.8%

respectively between 2006 and 2011 due to completion of new transmission

lines.

Page 66: 2011 Annual Report of Federal Ministry of Power.pdf

65

MAJOR ACTIVITIES

Status of Implementation of Transmission Capital Projects

802.5km of 330kV Lines are under construction out of which 779.5km are

above 50% completion stage.

625.3km of 132kV Lines are under construction out of which 316.8km are

above 50% completion stage.

1,350MVA transformer capacity at 330/132kV is presently being installed in

new substations out of which 900MVA capacity is above 50% completion

stage.

2,850MVA Capacity of 132/33KV transformers are presently being installed

in new substations out of which 810MVA are above 50% completion stage.

722km of 330kV line, 699km of 132kV line, 1,350MVA capacity at

330/132kV and 1,800MVA capacity at 132/33kV are being procured in the

2010 budget.

About 600km of overloaded 132kV transmission lines are being re-

conductored with higher capacity conductors

ACHIEVEMENTS

8.1 Transmission Projects Completed in 2011

S/N Project Title / Description Installed Capacity

Added Capacity

Date Completed

1ST QUARTER, 2011

1. Damaturu-Maiduguri 330kV line Yobe-Borno States

184kM 184kM Jan, 2011

2. Installation of a new 60MVA, 132/33KV Transformer to replace 1x12.5MVA at PH Town T.S.

60MVA 47.5MVA Mar, 2011

3. Installation of a new 60MVA, 132/33KV Transformer to replace 1x15MVA at Itu T.S.

60MVA 45MVA 14th March, 2011

Page 67: 2011 Annual Report of Federal Ministry of Power.pdf

66

2ND QUARTER, 2011

4. Katampe 1x150MVA, 330/132kV transformer

150MVA 150MVA 11th April, 2011

5. Installation of a new 60MVA, 132/33KV Transformer to replace 1x7.5MVA at Katsina T.S.

60MVA 52.5MVA 15th May, 2011

6. Installation of a new 60MVA, 132/33KV Transformer to replace

1x30MVA at Ayede T.S.

60MVA 30MVA 19th May, 2011

7. Installation of a new 60MVA, 132/33KV Transformer at Central Area T.S., Abuja

60MVA 60MVA 19th May, 2011

8. Installation of a new 60MVA, 132/33KV Transformer at Birnin Kebbi T.S.

60MVA 60MVA 24th May, 2011

9. Installation of a new 60MVA, 132/33KV Transformer to replace 1x15MVA at Abakaliki T.S.

60MVA 45MVA 25th May, 2011

10. Installation of a new 60MVA, 132/33KV Transformer to replace 1x30MVA at Kaduna Town T.S.

60MVA 30MVA 25th May, 2011

11. Installation of a new 60MVA, 132/33KV Transformer to replace 1x30MVA at Benin T.S.

60MVA 30MVA 28th May, 2011

12. Jos-Kafanchan 80kM, 132kV Lines 80kM 80kM 3rd June,

2011

3RD QUARTER, 2011

13. Installation of a new 60MVA, 132/33KV Transformer at Ikorodu T.S. (LEEC, mfd 2010)

60MVA 60MVA 9th August, 2011

14. Installation of a new 60MVA, 132/33KV Transformer to replace a defective 45MVA at PH(Town) T.S.

60MVA 45MVA 21st August, 2011

Page 68: 2011 Annual Report of Federal Ministry of Power.pdf

67

(LEEC, mfd 2010)

15. Installation of a new 60MVA, 132/33KV Transformer at Kumbotso T.S. (Cropton Greeves, NIPP)

60MVA 60MVA September, 2011

The above transmission network expansion and reinforcement projects aimed at

substantial improvement in the wheeling of electricity and increased capacity to

the grid were completed in year 2011.

Table 10.1 Transmission projects planned for completion in 2012

S/N

PROJECTS

Date

Award

ed

Estimated

Completion

Date

330kV

Line/km

132kV Line/km

330kV /MVA

132kV /MVA

1 Mbalano-Okigwe

132kv SC line Abia 2001 2012

20.3

2

Okigwe 2x30/40MVA

132/33kV Substation,

Imo

2001 2012 60

3

Mbalano

2x30/40MVA

132/33kV substation.

Abia

2001 2012 60

4

Makere - Pankshin

132KV DC Line

Plateau State

2007 2012 122

5

Kano- Walalanbe

132KV Line (Turn in

and out of Dan

agundi-Dakata

132KV single Cct

Line) and 2 x

30/40MVA S/S at

Walalambe Kano

2007 2012 60

Page 69: 2011 Annual Report of Federal Ministry of Power.pdf

68

State

6

3rd Benin - Onitsha

330KV DC Line Edo

- Anambra States

2007 2012 141

7

2x30/40MVA

132/33kV S/S at

Ogoja Cross

River State

2007 2012 60

8

Rehabilitation of

Sokoto - Talatmafara

132KV DC line

2007 2012 235

9 132//33kV at Aboh -

Mbaise S/S 2009 2012 120

10

Transmission &

Supply of Substation

at Tamburawa Water

Facility

2009 2012 60

11

2x60 MVA, 132/33

kV substation at

Ideato and 2 x132KV

Line Bays at Okigwe

2009 2012 120

12

1X30 MVA 132/33 KV

SS at Kwanar

Dangora

2009 2012 30

13

Afam - PH 132kv DC

turning in and out at

PH main TS

2009 2012 10

14

2nd Benin-Onitsha

330kV SC line Edo-

Delta-Anambra

States

2008 2012 132.8

Page 70: 2011 Annual Report of Federal Ministry of Power.pdf

69

15

Onitsha 150MVA

330/132/33kV T/F

and 330kV bays at

Onitsha and Benin.

Anambra / Edo

States

2008 2012 150

16

Calabar 2x150MVA,

330/132/33kV

Substations and line

bay at Alaoji

Substations. Cross

River States

2006 2012 300

17

Damaturu 330/132kV

Substation Yobe

State

2006 2012 150 60

18

132/33KV S/S at

Ayangba Kogi

State

2007 2012 120

19

2 x 30MVA

132/33KV S/S at

Pankshin and Makeri

2007 2012 120

20

Daura 2 x 30/40MVA S/S and 2x

132kv line bay ext. at Katsina

Katsina State

2007 2012 60

21

1x60MVA Substation at Ughelli

Power Plant and 1x30/40MVA

substation reinforcement at Amukpe

2008 2012 90

22 Kukwaba 2x60MVA, 132/33kV

substation 2007 2012 120

23 2 x60MVA 132/33kV S/S at 2007 2012 120

Page 71: 2011 Annual Report of Federal Ministry of Power.pdf

70

Ogbomosho 1no. 132kV Bay

Extension at Ganmo:Oyo &Kwara

States

24

2x60 MVA, 132/33 kV substation at

Oba and 2 x132KV Line Bays at

Nnewi

2009 2012 120

25 1X30MVA, 132/33 kV Substation at

Wudil, Kano State 2010 2012 30

Total Expected Capacity

273.8 387.3 600 1,410

Grid Operations

An interconnected grid was maintained in year 2011. A peak generation of

4,054.2 MW occurred on the 4th October, 2011 while 90,315.27MWH is the peak

to date daily energy generation recorded in April 16th 2011.

Average Power Stations MWH/H Generation On The Peak

Day(4054.2 MW) of

4th October 2011

S/N STATION

AVERAGE GEN/STATION

(MWH/H)

1 KAINJI 272

2 JEBBA 453

3 SHIRORO 396

4 EGBIN 875

5 TRANS AMADI 6.3

6 AES 120.5

7 SAPELE 130

8 SAPELE NIPP 0.0

Page 72: 2011 Annual Report of Federal Ministry of Power.pdf

71

9 IBOM POWER 25.6

10 OKPAI 459

11 AFAM 1-5 60

12 AFAM VI 544

13 DELTA 232

14 GEREGU 190

15 OMOKU 0.0

16 OMOTOSHO 65

17 OLORUNSOGO I 108

18 OLORUNSOGO II 117.8

Total Hydros 1121

Total Thermals 2933.2

HYDRO + THERMAL 4054.2

Stations Contribution To Energy Generated On The Peak

Energy Day of

April 16, 2011

Page 73: 2011 Annual Report of Federal Ministry of Power.pdf

72

STATION TYPE OF TURBINE

MWH

KAINJI HYDRO 8282.00

JEBBA HYDRO 10230.00

SHIRORO HYDRO 9383.00

EGBIN STEAM 19816.00

TRANS AMADI GAS 418.80

AES GAS 5326.80

SAPELE STEAM 3733.27

IBOM POWER GAS ----

OKPAI GAS 10283.00

AFAM 1 – 5 GAS 1465.50

AFAM VI GAS 2001.60

DELTA GAS 5687.20

GEREGU GAS 5454.80

OMOKU GAS ----

OMOTOSHO GAS 514.00

OLORUNSOGO PHASE I

GAS ----

OLORUNSOGO PHASE II

GAS 2719.30

TOTAL 90315.27

Forecast Of Stations For The Next Six Months Starting From

September, 2011

Are as follows:

Station Sept

(MW)

Oct

(MW)

Nov

(MW)

Dec

(MW)

Jan

(MW)

Feb

(MW)

Kainji 200 165 270 270 280 280

Page 74: 2011 Annual Report of Federal Ministry of Power.pdf

73

Jebba 240 360 320 270 225 240

Shiroro 300 300 300 300 300 300

Egbin 860 860 860 1080 1080 1080

Geregu 220 220 220 330 330 220

Omotosho 70 105 105 105 105 105

Olorunsogo

I

21.5 21.5 21.5 21.5 21.5 21.5

Olorunsogo

II

240 240 365 365 365 365

Delta 320 340 380 480 500 500

Sapele 90 170 220 260 260 170

Afam I – V 65 65 65 117 117 117

Sapele

NIPP

112 224 224 224 336 336

Okpai 470 451 451 470 470 429

AES 160 160 188 215 215 240

Afam VI 424 562 562 513 525 510

Transamadi 80 80 80 80 80 80

Omoku 40 60 80 100 100 100

Ibom 75 75 75 75 75 75

TOTAL 3987.5 4458.5 4786.5 5275.5 5384.5 5168.5

Page 75: 2011 Annual Report of Federal Ministry of Power.pdf

74

CHALLENGES

The major challenges to the performance of TCN are as follows:

Radial Lines with no redundancies

Obsolete Substation Equipment

Overloaded transmission lines and Substations

The network is still largely manually operated (not fully automated)

Inadequate Coverage of Infrastructure

Limited Funds for Development projects

High Technical loss

Menace of Erosion of Towers

Hostile Communities(i.e. way-leave issues)

Delay in the release of approved Budget

Downward amendment of approved budget on projects

Frequent system disturbances resulting in partial/total collapse.

Operational Problems (Voltage and Frequency controls): Absence of free

governors to manage allocated load effectively.

Challenges of opening L/C

Lengthy Procurement Process

Challenges during clearing of materials/ equipment at the Port

Delay in the release of approved Budget

Vandalism of Transmission lines

Delay in the release of MYTO subsidy

Lack of adequate technical manpower at various work centres

Ways to mitigate the challenges:

Vandalism: Police together with the host communities are partnering with

the various regions to secure the transmission lines.

Page 76: 2011 Annual Report of Federal Ministry of Power.pdf

75

Erosion menace: Erosion control measures are employed in the affected

areas.

Lack of adequate manpower: Casual workers are used to close the gap.

Fast tracking the procurement process

Procurement of work tools and test equipment.

Completion of on-going capital and in-house projects

Reinforcement of existing network

Timely release of approved funds for project execution and maintenance

activities.

Acquisition and development of adequate human capacity to cope with the

ageing work force.

Completion of projects targeted at closing the loop in the transmission

grid.

STRATEGIC FOCUS

Our Vision:

A transmission company with a solid reputation for delivering reliable,

cost-effective electric power to end users in Nigeria and West African Sub-

Region.

Our mission:

To cost effectively provide, operate and maintain the required assets,

equipment and transmission grid network for evacuating and dispatching

high quality and reliable electricity with minimal technical losses.

Our Strategies:

• Build Transmission Grid that can efficiently evacuate all generated

power

• Create adequate network redundancies to ensure at least 99.9%

reliability

• Reduce transmission loss to less than 5%

Page 77: 2011 Annual Report of Federal Ministry of Power.pdf

76

• Pursue Inter connection with neighboring countries for power exchange

• Improve TCN‟s revenue base to ensure a self sufficient and self

sustaining company

Implementation of Strategy

All power stations to have alternative evacuation routes

All State capitals to have 330/132kV TS

All major towns, Local Govt. Headquarters and State Capitals to be on

dual source of supply at 132kV

All Transmission Stations to have at least 2 transformers that are less

than 75% loaded at any time

All Transmission Stations to be rehabilitated for automation operation

Implementation of Plan will be primarily from IGR, Contractor

Financing, Foreign Loans

Expected Revenue

The total expected revenue to settle the Market for January to September

2011 transactions was N198.92bn. The sum was made up of the

settlement invoices to the Discos and the Disco income based on the

MYTO of 2008.

Whereas the sum of the Market Operator‟s invoices was N158.07bn, the

sum of Disco incomes for the period was N40.85bn (including N1.58bn

over absorbed equalization amount).

Actual Revenue

Out of the N198.92bn expected in the Market during January to September

2011, actual revenue collected was N146.47, implying a revenue gap of

N52.45bn during the period.

The sum of N140.98bn came from the Disco collections (N110.98 collected

directly from consumers and N30b paid to DISCOs by FGN as MYTO

Subsidy) while N5.2bn was paid by CEB (Togo & Benin Republics) and

NIGELEC of Niger Republic. Also, the three Independent Larger Power

Consumers paid N0.294bn

Page 78: 2011 Annual Report of Federal Ministry of Power.pdf

77

Required Vs Actual Market Settlement

The sum required to settle the Market January to September 2011 was

N198.92bn. Out of this, the Discos were expected to earn N40.85bn.

while the Federal Government generating plants were expected to receive

the total sum of N42.13bn. The IPPs were expected to be paid N51.43bn,

while Transmission Company of Nigeria (TCN) was required to be paid

N23.2bn. For gas supplied to the Thermal Plants (including AES - an IPP),

NGC and Shell were required to be paid the total sum of N17.62bn.

Due to the fact that actual revenue was lower than the expected revenue,

the actual Market Settlement during the period was short of the required

settlement. The situation was further compounded by the fact that the

Discos received N55.81bn instead of the N40.85bn provided in the MYTO.

The extra N14.95bn spent on Discos was due to the high Disco staff cost

and the inadequate provision for Disco Opex in the Tariff Order of 2008.

Also, the PHCN Corporate Headquarters is taking more responsibilities than

was provided for in the Tariff Order. Therefore, it took more payment

than required during the settlement period.

Consequently, the Gencos received N19.18bn instead of the required

N42.13bn; the IPPs were paid N23.5bn instead of the required N51.43bn.

The gas companies were paid N13.71bn instead of N17.62bn required for

the period, while the TCN was paid N14.18bn instead of N23.23bn.

Revenue Gap Vs Actual Settlement Gap

Ordinarily, the actual settlement gap should be equal to the revenue gap,

but due to the fact that some participants‟ receipts were not consistent

with their MYTO provisions, the actual settlement gap for the period 2011

was more than the revenue gap established.

Consequently, whereas the revenue gap was N52.45bn the actual

settlement gap was N82.3bn. This means that an extra sum of N82.3bn

was required for the Nigerian Electricity Market to achieve settlement

equilibrium during the period, January to September 2011.

Page 79: 2011 Annual Report of Federal Ministry of Power.pdf

78

6.1.3 Distribution Companies (DISCOS)

S/N DISCOS AREAS COVERED (STATES)

1 Abuja Electricity Distribution Company Plc

FCT, Niger, Kogi, Nassarawa

2 Benin Electricity Distribution Company Plc

Edo, Delta, Ondo, Ekiti

3 Eko Electricity Distribution Company Plc

Lagos South

4 Enugu Electricity Distribution Company Plc

Enugu, Imo, Anambra, Abia, Ebonyi

5 Ibadan Electricity Distribution Company Plc

Oyo, Ogun, Osun, Kwara

6 Ikeja Electricity Distribution Company Plc

Lagos North

7 Jos Electricity Distribution Company Plc Plateau, Benue, Bauchi, Gombe

8 Kaduna Electricity Distribution Company Plc

Kaduna, Kebbi, Sokoto, Zamfara

9 Kano Electricity Distribution Company Plc

Kano, Jigawa, Katsina

10 Port Harcourt Electricity Distribution Company Plc

Akwa-Ibom, Cross River, Rivers, Bayelsa

11 Yola Electricity Distribution Company Plc

Adamawa, Borno, Taraba, Yobe

In consonance with the Roadmap unveiled by the President of the

Federal Republic of Nigeria on Thursday, 26th August, 2010 to

ensure modest but genuinely realizable improvements in the amount

and quality of electricity supplied to customers in the country all

Distribution Companies are expected to be privatized based on a

core investor sale of a minimum of 51% of the Government‟s equity

in the companies.

Page 80: 2011 Annual Report of Federal Ministry of Power.pdf

79

6.1.4 NIGERIA BULK ELECTRICITY TRADING COMPANY PLC (NBET) –

The Electric Power Sector Reform Act of 2005 (EPSRA or the Act) provides for the bulk

trading licensee that will buy electric power (capacity, energy and ancillary services) from

generation companies for resale to distribution companies and eligible customers. This

entity, the bulk trader, will procure power through the Transitional Stage of the market

during which it is expected that the distribution companies would have reached a stage

where they can procure power on the strength of their operations at which point the bulk

trader will cease to procure new capacity.

In fulfillment of the requirements of EPSRA, and in line with the Roadmap to Power Sector

Reform, Nigerian Bulk Electricity Trading Plc (NBET aka the Bulk Trader) was incorporated

on July 29, 2010, with 100% Federal Government on Nigeria (FGN) shareholding. The

shareholding is split between the Bureau of Public Enterprises (BPE) and Ministry of Finance

Incorporated (MOFI), in a ratio of 80% and 20% percent, respectively.

Upon incorporation, the BPE and the Presidential Task Force on Power (PTFP) began to

midwife the activities of the company on two major fronts: 1) Engaging potential

Independent Power Producers (IPPs) in discussions for power purchase agreements (PPA),

to be backed by the World Bank‟s Partial Risk Guarantee (PRG) instruments; and 2)

Operationalizing the Bulk Trader by identifying the requisite functions and designing a

structure that will enable NBET effectively play its role.

On August 23, 2011, the President, Dr. Goodluck Jonathan inaugurated a nine-person

Board of Directors that included the Chief Executive Officer (CEO) for NBET. The board

members are;

Dr. Ngozi Okonjo-Iweala, (Coordinating Minister for the Economy and Hon Minister

of Finance) Chairman

Prof. Bart Nnaji Hon. Minister of Power

Page 81: 2011 Annual Report of Federal Ministry of Power.pdf

80

Mr. Rumundaka Wonodi, Chief Executive Officer

Mr. Saka Abimbola Isau SAN, Vice Chairman

Ms. Bolanle Onagoruwa Director-General, Bureau of Public Enterprises

Mr Haruna Sambo Mohammed

Hon. Mohammed Kumalia

Mr. Paul Usoro, SAN

Engr. Abdulganiyu Umar

PURPOSE OF THE BULK TRADER

During the Transitional Stage of the Nigerian electricity market reforms, NBET will be

responsible for buying power from IPPs and reselling the power to the distribution

companies (DisCos). It will not be the sole authorized or designated buyer, as other

entities, such as DisCos that have attained commercial viability, will be able to procure

power directly from GenCos as well. Accordingly, NBET will not be a monopoly but will,

in a sense, compete with other qualified buyers. Qualified companies are welcome to

enter bilateral contracts for sale or purchase of power.

Page 82: 2011 Annual Report of Federal Ministry of Power.pdf

81

PRIMARY RESPONSIBILITIES

Sign PPAs with privatized generation companies

Assume PHCN obligations in existing PPAs with IPPs (outstanding liabilities

transferred to NELMCO)

Negotiate and enter into PPAs with potential IPPs

Sign Vesting Contracts with Distribution Companies

Sign power sale agreements (PSA) with eligible customers

Values

Integrity

Transparency

Professionalism

Social Responsibility

GenCo1

GenCo2

GenCo3

GenCo4

GenCo5

GenCo6

DisCo 1 DisCo 2 DisCo 3 DisCo 4 DisCo 5

DisCo 6 DisCo 7

DisCo 8 DisCo 9 DisCo 10 DisCo 11

BULK TRADER

Existing

Existing

Existing

New IPPs

POWER PURCHASE

VESTING CONTRACTS

Additional

Eligible Customers

PPA

Page 83: 2011 Annual Report of Federal Ministry of Power.pdf

82

Teamwork

OBJECTIVES

To put in place an effective transaction environment which minimizes risk and allocates it

fairly to the parties best able to manage it

To implement a procurement process that is transparent and will result in the economic

procurement of needed power

To have all existing and new power capacity under contract by 2016, although the

commercial operation date when this capacity comes on line may be latter

To ensure efficient settlement in the short term until this function is subsumed under the

Market Operator

To become sustaining as soon as practical thereby minimizing the cost to the FGN

To be ready to novate contracts and wind up as soon as the suppliers are ready to take

on their own procurement

To enter into contracts that are well structured and managed in a manner that precludes

recourse to any credit guarantee instrument

ACHIEVEMENTS

The Electric Power Department of BPE and the Regulatory & Transaction Monitoring

(RTM) unit of the PTFP, have over the past year and since the incorporation of NBET,

been responsible for conducting the activities of NBET. The major milestones attained

during this period include:

Secured the commitment of World Bank for the provision of Partial Risk

Guarantee (PRG) for potential IPP contracts. Once the power sector reform was

formally restarted with launch of the Road map to Power Sector Reform and with

Page 84: 2011 Annual Report of Federal Ministry of Power.pdf

83

the determination that a Bulk Trading entity with a credible payment guarantee

needed to be established, the question became what form and type of guarantee

that will be used to back the bulk trader. After due considerations, the FGN

government decided to approach the World Bank for support through the Partial

Risk Guarantee instrument. World‟s Bank commitment for provision of PRG in

support of new capacity was obtained in the fourth quarter of 2010. Earlier this

year, the World Bank expressed interest to provide same in the privatization of

the PHCN Successor Generating Companies (GenCos).

Reviewed proposals from various IPP projects from which 14 qualifying projects

were nominated to the World Bank to qualify for PRG backed Power Purchase

Agreements (PPA) with the Bulk Trader.

The World Bank‟s energy team has undertaken 2 missions to the country. The

primary objectives of the mission are to engage all stakeholders in the reforming

industry both in the public and private sectors. Workshops on Environmental and

Social Impact Assessment Studies were held by the mission together with

representatives of the bulk trader. There were also visits to the nominated IPP

project sites and one-on-one sessions held with the project developers where

progress reports were given.

Procurement of legal advisory services for NBET. In the fourth quarter of 2010,

BPE conducted a procurement exercise for legal services. The bid for legal

advisory services was won by G. Elias & Co in association with Hunton & Williams.

In June 2011, BPE, on behalf of NBET, entered into contract with G. Elias & Co for

the provision. As a result, NBET was able to provide draft PPAs and

vesting contracts for inclusion in the data room for privatization of

PHCN successor companies. Also developed was a draft PPA for new

Independent Power Projects.

Page 85: 2011 Annual Report of Federal Ministry of Power.pdf

84

NBET finalized its licensing terms with Nigerian Electricity Regulatory Commission

(NERC) and has made the necessary payments required to obtain its license.

NBET has completed procurement of office accommodation for its operations

GOING FORWARD

Since the inauguration of its board, the management of NBET has been focused

on making the company operational. NBET will look to resolve key issues such as

o Set up a functional office location

o Hire key staff

o Finalize an organized process for engaging potential IPP developers in a

manner that provides the best value to the country

NBET will continue to be a key participant in the on-going privatization of the

PHCN successor companies and will work to fully embody its role as described

within the EPSRA 2005 and as required to develop the Nigerian Electricity Supply

Industry.

6.2.2 Nigerian Electricity Regulatory Commission (NERC) – is an

independent regulatory body saddled with the regulation of the electric power

industry in Nigeria. NERC was formed in 2005 for formation and review of

electricity tariffs, transparent policies regarding subsidies, promotion of policies

that are efficient and environmentally friendly, and also including forming and

enforcing of standards in the creation and use of electricity in Nigeria. NERC was

instituted primarily to regulate the tariff of Power Generating companies owned

or controlled by the government, and any other generating company which has

license for power generation and transmission of energy, and distribution of

electricity.

Page 86: 2011 Annual Report of Federal Ministry of Power.pdf

85

Powers and Duties of NERC

The Commission‟s powers and duties are solely provided for in the EPSR Act

2005, and effectively ushered the privatization of electric power services in

Nigeria unbundling of the defunct National Electricity Power Authority

(NEPA)/Power Holding Company of Nigeria to operates/investors, set and review

electricity tariffs and where possible promote competition. The Commission‟s

main objective is to protect existing and future consumers‟ interests in relation to

electricity generated and that conveyed by distribution or transmission systems.

Consumers‟ interests are their interests taken as a whole including their interests

in affordable tariffs and safe, reliable and available electricity supply, and the

reduction of greenhouse gases to them.

Structure of NERC

The Nigerian Electricity Regulatory Commission is governed by a tenured Board

of Commissioners, headed by a Chairman. The Nigerian President nominated

one nominee Commissioner to represent his/her geopolitical zone in the country

for a fixed tenure of 4 years, renewable once only. The Chairman/CEO, however

has period of 5 years, also renewable once only. The nominees are duly

screened by the Nigerian Senate. The Board of Commission of NERC issues

orders on electricity matters in Nigeria. It makes regulatory decisions and issues

final license to investors/operators. It also settles industrial dispute through its

ADR mechanism in an open hearing. NERC is divided into seven Divisions:

Office of the Chairman/CEO,

Engineering, Standard and Safety Division,

Finance and Management Services Division,

Government and Consumer Affairs Division,

Legal Licensing and Enforcement Division,

Market Competition and Rates Division, and the

Renewable energy/Research and Development Division.

Page 87: 2011 Annual Report of Federal Ministry of Power.pdf

86

6.2.3 National Power Training Institute of Nigeria (NAPTIN) –

The National Power Training Institute of Nigeria (NAPTIN) which was established

on March 23rd, 2009 commenced full operation in September, 2009. The primary

purpose for its establishment is to provide training for power sector personnel

and coordinate training activities in the sector. In pursuit of this mandate,

NAPTIN has taken over the management of the existing seven regional training

centers of PHCN.

The core values of NAPTIN are as follows:

Creativity and Innovation

Ethical Behaviour

Accountability

Business Objectives / Goals:

To create a strong, dynamic and World – Class Power Tarining Institutes

called NAPTIN;

Create a cadre of experts and professional trainers;

Develop partnership, affiliations and linkages with Local and International

Training Institutes and Universities;

To develop a marketing strategy to market the values of training in Power

Utilities in Nigeria.

NAPTIN's Organizational Structure

Page 89: 2011 Annual Report of Federal Ministry of Power.pdf

88

6.2.4 Nigeria Electricity Liability Management LTD/GTE –

The Nigerian Electricity Liability Management Limited/gte (NELMCO) are one of

the “other transferees” companies envisaged under S.22(1) EPSR Act.2005 the

EPSR Act 2005. The National Council on Privatisation (NCP) approved the set up

as one of the successor companies from the reform of PHCN. They were

incorporated under the Companies and Allied Matters Act, 1999 in August, 2006

as a company limited by guarantee, with registration RC664658. The

shareholders are the Federal Ministry of Finance Incorporated (MOFI) and the

Bureau of Public Enterprise (BPE), providing guarantees to the extent of 90%

and 10% respectfully.

THE MANDATE

To assume and administer the stranded debts and assets of PHCN

pursuant to the provisions of EPSR Act 2005

To assume and manage pension liabilities of employees of PHCN

To hold the non-core assets of PHCN, sell or dispose off or deal in any

manner for the purpose of financing the payment of debts or other related

matters.

Page 90: 2011 Annual Report of Federal Ministry of Power.pdf

89

To take over the management and settlement of PHCN‟s Power Purchase

Agreement (PPA) debts as may be determined by the National Council On

Privatisation from time to time.

To sell, mortgage, dispose off, deal in any manner of the property or

assets of the company as may be expedient with a view to promoting its

objects.

To do all such other things as are incidental or may be thought conducive

to the attainment of the above objects or any of them.

STAKEHOLDERS ENGAGEMENT STRATEGY

• Engage the Union of PHCN Pensioners to negotiated buy out.

• Engage inherited third party Creditors to negotiated settlement.

• Engage professionals to provide consultancy and advisory services.

• Engage relevant MDA‟s for support and concessions.

OPERATIONAL STRATEGY

The company‟s operational strategy during the Transitional Stage of the electricity market development will be to:

1. Engage professionals to provide consultancy advisory and due diligence services over stranded Debts and non - core Assets.

2. Engage in transparent and competitive bidding process in the disposal of the non-core assets

3. Engage the Union of PHCN Pensioners and negotiate Pension buy out 4. Engage PHCN Creditors and negotiate settlement modalities 5. Engage DMO and MOFI on foreign debt relief and swaps.

BUSINESS STRATEGY

• Regularly liaise with NERC and Market Operators for funds to:

– Settle Inherited PPA liabilities, Pay monthly pensions of PHCN

Pensioners.

• Use of reputable professional and consulting firms to provide advisory

services in the areas of:

– Actuarial valuation, Property valuation, Legal search, Negotiation

skills and Capacity development

Page 91: 2011 Annual Report of Federal Ministry of Power.pdf

90

• Regularly liaise with appropriate FGN MDA‟s to:

– Fund shortfalls to inherited liabilities e.g, PENCOM, To agree

possible debt swaps and forgiven and cancelled foreign debts

• Use of Financial Institutions for short - medium term bridging facilities.

– To take advantage of negotiated discounts due to delay in fund FGN

releases

– To leverage on financial instruments such as bonds, etc

GUARANTEE HOLDERS

The guarantors to NELMCO as per the Articles and Memorandum of

Incorporation provided guarantees in the following proportions:

a. Ministry of Finance Incorporated (MOFI). 90% b. Bureau of Public Enterprises (BPE). 10%

OPPORTUNITIES

NELMCO will avail itself of the under listed opportunities in the facilitation of its liability management responsibilities in the transition:

1. Raise finance from disposable non-core assets of PHCN 2. Liaise with PENCON with a view to accessing finance to deal with the

shortfall in the Staff Pension fund. 3. Access to FGN treasury to fund inherited Legacy debts and third party

liabilities. 4. Access to privatization proceeds from sale of PHCN successor companies. 5. Access to NERC MYTO fund for contribution to legacy debt settlement. 6. Collaborate with relevant government Agencies to access the Capital Market

for the issuance of financial instruments such as bonds, etc

FUNDING

The fund flow that will accrue to the company in the transitional period will be from the following sources:

1. Industry Receivables in respect of Federal, States and Local Governments. 2. Sales proceed of non-core assets

Page 92: 2011 Annual Report of Federal Ministry of Power.pdf

91

3. Ministry of Finance retained source deductions from Lagos State Government in respect of AES IPP counter-part contribution

4. Industry Levy by NERC on successor companies customers bill as pass-through operating cost in the form of “Reform charge”

5. FGN budget appropriation to fund shortfalls

TRANSFERRABLE NON-CORE ASSETS – 1 LAND & PROPERTIES

• PHCN London Office and Staff quarters

• PHCN HQ Building at Maitama, Abuja.

• PHCN HQ Annex at Wuse 2, Abuja.

• PHCN HQ Annex Building at Marina, Lagos

• PHCN HQ Annex Building at Awolowo Road, Ikoyi Lagos.

• PHCN Zonal Office Buildings at Ikeja, Ibadan (W.I.P), Enugu, Kaduna

(W.I.P), Jos, Kano, and Yola

• PHCN Golf Courses at Shiroro and Kainji.

• PHCN Bonded Custom Warehouse at Apapa, Lagos.

• PHCN Workshop at Ijora

• PHCN Undeveloped Plots of Land across the country.

• PHCN Medical Centres at Abuja, Ijora, and Oshodi and others.

• PHCN Unsold staff quarters

TRANSFERRABLE NON-CORE ASSETS – 2 CURRENT ASSETS (REVENUE)

• Receivables from government accounts country-wide of PHCN Successor

Distribution Companies. This should accrue to NELMCO for application in

the settlement of inherited IPP‟s liabilities.

These are accumulated debts arising from unpaid consumption of

generated and distributed electricity prior to the Bulk Trader executed

Contracts. The proceeds from these outstanding debts

• Proceeds from the sale of staff quarters to PHCN staff under the FGN

policy on government quarters and houses that is escrowed in some

banks.

• All Properties, Investments and monies owned and accruable to the PHCN

Superannuation Fund.

Page 93: 2011 Annual Report of Federal Ministry of Power.pdf

92

• The balance of unremitted deductions made on behalf of PHCN at source

in the vault of the Federal Ministry of Finance, from Lagos State

Government as counterpart contribution to AES PPA payment obligation.

(this may have constitutional implication)

CHALLENGES

Liquidation of PHJCN and facilitation of the transfers of files, Agreements,

Contracts documents, Schedules, Title Deeds, Litigations, etc

Seed Money of =N=30billion to take advantage of payment on discounted

debts.

Budgetary provision to offset legacy debts, PPA unpaid bills, other

obligations.

Procurement of Consultants and Advisers to facilitate NELMCO‟s operation

Negotiation with Creditors and stakeholders for discounts on verified

liabilities

Domiciliation of current payment to PHCN in respect of monthly pensions,

gas bills, etc to NELMCO. This will facilitate continuation of on-going

payment obligations.

Capacity to meet Monthly =N=803m Pension payment of Pensioners.

Liquidation of PHCN and facilitation of transfers of Files, Agree UN-

CRYSTALIZED BURDEN – CONTINGENT LIABILITIES

1. Environmental Liabilities- (Possible worries of Investors from western

countries)

Asbestos-related liabilities

Realised on a massive scale in western economy in the last two

decades. Investor will require government commitment to their

settlement post-privatisation.

2. Polychlorinated Biphenyls (PCBs)

Contaminant in electrical equipments in the form of dielectric fluids in

transformers and capacitors. Studies have confirmed significant

percentage in PHCN transformers.

Contamination in open environment/sites that have been used to house

or maintain transformers.

Page 94: 2011 Annual Report of Federal Ministry of Power.pdf

93

3. Emissions to the atmosphere and discharges into water, management of

solid waste, etc

4. Third Parties Liabilities from States Government and Local Governments,

Communities, Corporate Institutions and Individuals arising from

investment in infrastructure valued along with PHCN networks

(These will crystallise pre or post -privatisation negotiations,

conduct of due diligence and upon transfer of ownership to

Investors)

TOTAL 2011 2012 2013 2014 2015=N=(m) =N=(m) =N=(m) =N=(m) =N=(m) =N=(m)

INFLOWS:

Proceed from sale of Non-Core Assets 19,500,000 - 9,500,000 10,000,000 - -Proceed from Receiveables on Government account 12,000,000 5,000,000 5,000,000 2,000,000 - -

Source Deductions from FGN/STATES/LGA’s ?? - - - - -Industry contribution to legacy debt payments 14,000,000 2,000,000 3,000,000 3,000,000 3,000,000 3,000,000

Proceed of sale of Staff Quarters 200,000 - 100,000 100,000 - -

Balance on Superannuation Fund ?? - - - - -Total (A) 45,700,000 7,000,000 17,600,000 15,100,000 3,000,000 3,000,000

OUTFLOWS:

IPP’sEnergy liabilities 64,999,297 4,999,297 20,000,000 20,000,000 20,000,000 0

Pensioners Buy-out 34,800,000 0 17,400,000 17,400,000

Foreign loans on Power Plants 40,469,087 0 10,469,087 10,000,000 10,000,000 10,000,000

FGN Foreign Loans 30,025,532 ? ? ? ? ?

Legacy debts and other liabilities 19,928,903 0 7,928,903 6,000,000 6,000,000 0

Local Bank Loans 2,064,117 1,000,000 1,064,117 0 0 0

World Bank/ADB Loans 43,774,339 0 15,774,339 14,000,000 14,000,000

Operations costs- Monthly Pension costs- Personnel Costs- Overheads- Fixed Assets

8,120,000588,730682,000255,000

4,640,000117,746187,000255,000

3,480,000117,746165,000

0

-117,746130,000

0

-117,746100,000

0

-117,746100,000

0

Total (B) 245,707,005 11,199,043 76,399,192 67,647,746 50,217,746 10,217,746

SHORTFALL = (A-B) (FGN APPROPRIATION PROVISION) 200,007,005(30,025,532)

4,199,043 58,799,192 52,547,746 47,217,746 7,217,746

Our Business Plan (Projected)

Page 95: 2011 Annual Report of Federal Ministry of Power.pdf

94

6.2.5 Rural Electrification Agency (REA)

The mission of REA is to provide access to reliable and affordable electricity

supply for the rural dwellers irrespective of where they live and what they do, in

a way that would allow for reasonable return on investment through

economically responsive tariff which is supportive of the average rural customer

The Rural Electrification Agency was established in accordance with Section

88 of Electric Power Sector Reform Act (EPSR) 2005 with the Corporate

Headquarters in Abuja and six (6) zonal offices in Oshogbo (South West Zone),

Enugu (South East Zone), Lokoja (North Central Zone), Dutse (North West

Zone), Bauchi (North East Zone), and Calabar (South South Zone) and a liaison

office in Lagos. It was inaugurated on 16th March, 2006 in accordance with the

provisions of Section 88 of the Electric Power Sector Reform Act. The Agency

was established to perform three essential functions namely:

To promote Rural Electrification in the country, so that each Nigerian shall

see the light of the day.

To set up and manage Rural Electrification Fund

To co-ordinate Rural Electrification activities in the country

The Rural Electrification Agency inherited a total of 2,269Nos Rural

Electrification projects from the Federal Ministry of Power.

The Agency also awarded a total of 153Nos Grid Extension and Off-

grid Extension projects in Year 2008.

Achievements of the Agency

Since the establishment of the Agency, some of the giant strides taken are

follows:

Creation of six functional zonal offices across the country and a liaison

office as follows:

Page 96: 2011 Annual Report of Federal Ministry of Power.pdf

95

Dutse - North West Zone

Bauchi - North East Zone

Lokoja - North Central Zone

Enugu - South East Zone

Calabar - South South Zone

Osogbo - South West Zone

Lagos – Lagos liaison office

Setting up a Rural Electrification Fund as required by the EPSR Act, 2005.

Verifying and appraising on-going projects taken over from the Ministry for

continued execution and completion

Liaising with the various stakeholders including States and Local

Governments on existing plans and strategies for Rural Electrification in

their respective territories

Initiated the conduct of studies for development of baseline data on

National Rural Electrification

Developing prototype rural electrification network designs and review of

existing on-going projects for expedited completion

Exploring fuel/energy saving options in power generation using renewable

energy technologies and the conversion of flared gas (where available) to

electricity

Promotional activities to mobilize rural communities preparatory to the

initiation of the Agency‟s off-grid/renewable energy programme

Many communities where on-going projects had substantially advanced

were also sensitized towards formation of Rural Electricity Users

Cooperative Societies (REUCS)

To date a total of 323Nos of the on-going projects have been completed

leaving a balance of 1,946Nos at different levels of completion

Page 97: 2011 Annual Report of Federal Ministry of Power.pdf

96

A total of 106No of the grid and off-grid projects awarded by the Agency

in Year 2008 have been completed leaving a balance of 47Nos. at

difference stages of completion

Plans, Strategies and Targets of REA Activities

The Agency has mapped out plans to ensure that its mandate on delivery

of rural electrification is accomplished. As a result, it is embarking on the

following:

Completion of the 1,946Nos. on-going rural electrification

projects nationwide through aggressive pursuit of strategies for

raising funds

Completion of 47Nos Grid and Off-grid projects awarded by the

Agency in Y2008.

Execution of the second phase of the off-grid renewable energy

programme of the Agency

Completion of the legal processes; institutional framework and

formation of Rural Electricity Users Cooperative Societies in target

communities where completed Federal Government rural

electrification projects are located

Growing the Rural Electrification Fund by sourcing for more

contributors to the fund and investing available principal in low

risk financial ventures

Aggressive promotion of projects to seek partners with the

Agency on identified projects under the Public Private Partnership

arrangement as contained in the Act

Page 98: 2011 Annual Report of Federal Ministry of Power.pdf

97

Extensive dialogue with Chief Executives of successor companies

of PHCN on improved services delivery to rural customers on

terms and conditions that are mutually favourable.

Dialogue with NERC on prompt establishment of the Power

Consumers Assistance Fund to support the underprivileged.

Completing the development of a Rural Electrification Master Plan

for Nigeria in conjunction with Japanese International Co-

operation Agency (JICA).

Building capacity (through education and training) on efficient

and productive uses of electricity; sensitizing promoters on

investment potentials in rural electrification as an engine for

driving small and medium scale industries.

THE CHALLENGES OF THE RURAL ELECTRIFICATION AGENCY

Insufficient project vehicles for monitoring and

supervision of over 2,000 rural electrification projects

across the country.

A total of N40.5b is required to complete our on-going

rural electrification projects.

Yearly Insufficient appropriation to complete on-going

projects.

Page 99: 2011 Annual Report of Federal Ministry of Power.pdf

98

Page 100: 2011 Annual Report of Federal Ministry of Power.pdf

99

Page 101: 2011 Annual Report of Federal Ministry of Power.pdf

100

Page 102: 2011 Annual Report of Federal Ministry of Power.pdf

101

PRESIDENTIAL TASK FORCE ON POWER:

The Mandate of the Presidential Task Force on Power (PTFP) is to • Fast-track improvement and predictability in electricity availability to Nigerian homes and businesses. • Take irreversible steps to promote medium to long term sustainable growth of the Nigerian electricity supply industry. • Restore the consumers‟ confidence in the Nigerian Electricity Supply Industry

• Establish and implement an effective consumer protection system • Make every Nigerian electricity consumer a customer that is responsible and complies with tariff and service obligations • Establish a competitive power procurement framework that delivers increased generation to meet increasing customer demand • Identify all sources of available excess captive generation in the country and develop a fast-track framework for making such accessible to consumers • Establish and sustain effective communication with power stakeholders and the Nigerian public across the entire span of the Action Plan COMPOSITION OF PTFP The PTFP is headed by a Coordinator, Engr. Ottih John Ottih and comprises of the following units: (A) Performance Monitoring Team on Fuel-to-Power (B) Performance Monitoring Team on Generation (C) Performance Monitoring Team on Transmission & System Operations (D) Performance Monitoring Team on Distribution & Market Operations (E) Performance Monitoring Team on National Integrated Power Project

(F) Performance Monitoring Team on Regulatory & Transaction Monitoring (G) Performance Monitoring Team on Labour (H) Institutional Continuity, Finance and Administration Unit (I) MIS/Technical Support Unit (J) Project Monitoring Unit Unit

Page 103: 2011 Annual Report of Federal Ministry of Power.pdf

102

OPERATIONS OF PTFP The various units of the Presidential Task Force on Power are integrated multi-disciplinary team of experts assembled to monitor, analyze, recommend and facilitate ways to ensure improvement on power sector demand on short, medium and long term basis. The various units have Senior Performance Monitors (SPM) and Heads as team leaders to ensure that tasks and targets of each team are delivered.

(A) FUEL-TO-POWER (FTP) TEAM To guide the team in achieving the PTFP objectives, the mandate of the FTP team and related targets are: · To establish current status of gas supply and pipeline transmission network including ongoing projects and planned activities related to gas-to-power sector. · Interact with NNPC Gas and Power Directorate, Gas Aggregation Company of Nigeria (GACN), gas supply companies (IOCs and NPDC) and NAPIMS to collate and analyse data. · To gather, collate and analyse daily demand and production data from Power Holding Company of Nigeria (PHCN) and Nigeria Gas Company (NGC) with a view to establishing gas availability and areas of potential shortfall. · To identify issues relating to meeting the immediate gas demand need of PHCN and undertake effective monitoring of the supply and demand chain. · To develop a plan of action to mitigate gas shortages if any, resulting from increased demand from rehabilitation of PHCN power plants and commissioning of NIPP‟s. · To review ongoing power projects and their impact on the gas supply chain and recommend areas of improvement that will ensure the availability and sustainability of Gas supply to Power. · To report to the PTFP on key project risks and issues relating to gas

supply and infrastructure plans and implementation as well as identify and recommend measures to ensure that the network has sufficient capacity to meet current generation demands and ensure stable and secure supply of fuel in the medium and long term. · To explore and recommend alternative fuels/energy including but not limited to coal, solar, wind and nuclear, for medium and long term power needs of Nigeria. · To establish a clear understanding of the dependencies between fuel, generation, transmission and distribution and the other links in the electric power supply chain.

Page 104: 2011 Annual Report of Federal Ministry of Power.pdf

103

· Provide the PTFP with timely and accurate reports on the information gathered and activities conducted above, with clear recommendations on interventions required in order to meet the objectives of the Presidential Action Plan on Power; and · Work with and support other Teams within the Presidential Task Forceto ensure that the objectives of the PACP are met. (B) GENERATION TEAM The principal role of the Performance Monitoring Unit on Generation is to: · Gather and collate information on all power generation projects (in both

the public and private sectors) particularly as they concern planned or new generation, rehabilitation and maintenance activities. · Track the ongoing activities of the power generating companies, monitor the activities and associated work plans of the management of the generating companies and monitor the inspection of generation projects and related project activities conducted by the Ministry of Power and PHCN. · Be responsible for ensuring that generation projects, including those pertaining to new generation, rehabilitation and maintenance, are executed to time and quality. While the detailed monitoring and control will be undertaken by the Ministry of Power and PHCN, the Performance Monitoring Unit (Generation) has a planning oversight role related to the efficient execution of the PTFP plan and, more specifically, to critical path projects designated as such for the attainment of the Plan‟s objectives. · Submit recommendations to the PTFP on rewards, incentives and sanctions for the management of generation companies. · Provide the PTFP with timely, accurate, and ongoing reports on the information gathered and activities conducted in the power generation area, with clear recommendations on which projects, maintenance and rehabilitation and other activities should be prioritized or not, and which intervening actions should be taken by the PTFP and PACP, in order to meet the objectives of the

Presidential Action Plan on Power. · Report on key project issues that are escalated from the Ministry of Power and PHCN relating to plans and implementation and key risks and issues that might affect the implementation of projects. This will involve ensuring that linkages and dependencies are managed effectively, that procurement and finance challenges are addressed and that options for resolution/mitigation in the short and longer term are identified. · Obtain a clear understanding of the dependencies between the generation sub-sector and the other links in the electric power supply chain.

Page 105: 2011 Annual Report of Federal Ministry of Power.pdf

104

· Work with and support other Performance Monitoring Units, particularly the Performance Monitoring Unit (National Integrated Power Projects), to ensure that the objectives of the Presidential Action Plan on Power are met, and · Help to communicate the priorities of the PTFP to the key stakeholders in the generation sub-sector. (C) TRANSMISSION TEAM The responsibilities of the transmission team of PTFP are as follows: · Qualitative service to customers (Gencos, DisCos) · Good corporate governance

· Provision of accessible, reliable, stable and affordable service. · Evolve ideas in operating the transmission grid optimally, collate and analyse transmission system data. · Monitoring of all on-going transmission projects and the performance of Transmission and System Operations. · Analyse and advance recommendations to enhanced grid structure. · Make inputs to budgetary allocation and engage with TCN management to resolve issues hindering their output. · Escalate all transmission and system operations roadblocks to PTFP and PACP. · Evolve ways to improve Transmission and System Operations performance and also drive and monitor the transmission targets on the Presidential Road Map on Power. · Make inputs to appropriate system reinforcement projects through concise gap analysis. · Engage TCN in resolving power issues escalated by distribution companies. · Interface with the Distribution team in PTFP to smoothen out all Transmission Distribution interface issues (D) DISTRIBUTION TEAM The PTFP distribution team has the responsibility of developing programs and

strategies that will assist in: · Bridging distribution gaps to improve the overall distribution network capability, reliability and supply predictability. · Ensuring that every Kwh distributed is sold and the associated revenue collected, thereby increasing collection efficiency to set targets. · Ensure that all power generated and transmitted from the grid to the various distribution zones are distributed seamlessly in an effective and efficient manner.

Page 106: 2011 Annual Report of Federal Ministry of Power.pdf

105

· Reducing aggregate distribution losses (technical & non-technical) and improving customer care service delivery and take customer satisfaction to the next level. · Identify the revenue gap, develop strategies for improvement in revenue collection and monitor and evaluate performances in revenue generation and collection. · The baseline for the Distribution team therefore was to establish the bottlenecks, challenges and the associated gaps on the distribution network (Technical & Commercial) to be addressed within the short and medium terms while, long term issues were expected to be handled at the post privatization

stage. (E) NIPP TEAM The activities of this Unit include the following: · Monitor the progress and performance of each Project very closely and follow-through to their commissioning on schedule. · Observe, investigate and report all process and system gaps in the management of each project and take actions to improve performance. · Engage with other interface agencies to resolve all roadblocks and bottlenecks and facilitate project progress. · Report and escalate all identified risks that can work against scheduled project delivery and take actions to mitigate their impact. · Carry out any other assignments which would assist the NDPHC/NIPP to deliver the projects on schedule. (F) REGULATORY & TRANSACTION MONITORING TEAM the Team‟s mandate was to work primarily with BPE and other agencies on the following: · Prepare a Power Sector Reform programme working paper that sets out its appreciation of the entire divestiture process,

relevant players, cross-cutting issues and their priority and critical actions and timelines for their completion; · Prepare a Divestiture Transaction Strategy for the approval of the relevant authorities and Shortlist and procure Transaction Advisers to put in place a Management Contract for the Transmission Company of Nigeria; · Undertake pre-transaction processes with its external Advisers, the PHCN successor companies and other stakeholders (essentially these would be mostly regulatory, corporate, technical and commercial actions in the various Successor Companies to be divested, e.g., the

Page 107: 2011 Annual Report of Federal Ministry of Power.pdf

106

implementation of a workable deal on pensions and severance liabilities and the establishment of Successor Company boards of directors); The unit also worked with NERC on the issues of; producing and gazetting regulatory documents that were fundamental to the commercial success of any transaction and a viable future of the industry itself, being essentially the financial model for the entire sector, must be effective in taking account all economic and commercial indices that drive the sector. It should therefore be enforceable, sustainable and conducive to the commercial viability of the sector; while the Bulk Trader‟s license must enable it to enter into vesting contracts and PPAs that

give certainty to counterparties as well as minimize risk and are fully enforceable. · Considering other regulatory matters such as the Market Rules, Grid Codes, arbitration rules, licenses to be issued to successor companies, etc and determine whether they need to be modified at this Stage (G) LABOUR The team was set up to consult and discuss with PHCN management and labour union of PHCN on a proper working relationship with the privatization process. The team's mandate is as follows: · Ensure that issues and challenges with PHCN management and PHCN staff are treated. · Proposed securing funds to settle severance. · Set up 1st round of negotiations with relevant bodies. · Engagement of HR, biometric, payroll, and actuarial consultants. · Identification and disengagement of excess PHCN staff. · Set up 2nd concluding round of negotiations with relevant bodies. · Payment of severance and transfer of retained staff · Handover to successor companies.

(H) INSTITUTIONAL CONTINUITY, FINANCE & ADMINISTRATION The activities of this Unit include : · To ensure effective transition of the activities and achievements of the Task Force to the designated institutions of the Federal Government at the end of the tenure of the Task Force. Ensure sequential reports submitted to PACP meetings, considering the performance and identified outstanding issues as related to the Task Force. · Ensure that activities of the Task Force are in full compliance with all Federal Government policies and practices.

Page 108: 2011 Annual Report of Federal Ministry of Power.pdf

107

Objective and target in terms of performance and challenges of the task force. · To ensure consistent adherence to administrative policies and procedures as stipulated by the civil service rules. · To ensure that accurate and measurable value is received for all expenditures made by PTFP by evolving and working out the variable templates and metrics. · To monitor all procurement activities to ensure compliance with stipulated quality, timeliness and cost. Budget performance and spending pattern of funds.

· To provide Secretariat support to the PTFP, i.e. activities of all units, considering staff performance, challenges, mitigation and recommendations. The Unit which was led by a Head had its day to day activities carried out by three sub-unit (Administration, Finance and Institutional Continuity). (I) MIS/TECHNICAL SUPPORT UNIT The Unit is responsible for the following: · Manage the total IT infrastructure of the PTFP and ensure internet services availability. · To provide first line of end user support services and to train and support PTFP staff in the use of ICTS. · Provide database management systems to track status of power sector road map projects and ensure the PTFP‟s website is up-to-date and design, develop and deploy web based solutions and technologies. · To secure all PTFP information assets are managed with relevant data and statistics software. · To specify and recommend a procurement of all PTFP ICT assets.

(J) PROJECT MONITORING UNIT The PMU was set up to: · Facilitate the timely and well-structured flow of information between the various teams. · Ensure that the strategies, priorities, and implementation plans prepared by the sector teams are properly collated. · Review the quality and assure the strategies, priorities and implementation plans prepared by the various team.

Page 109: 2011 Annual Report of Federal Ministry of Power.pdf

108

· Identify and highlight interdependencies between the work plans of all the sector teams. · Combine and synthesise the work plans of the seven (7) Sector team into a composite “Statement of Strategic Priorities‟‟. · Identify key risks which will have a bearing on the success of the overall programme of activities and develop appropriate risk resolution and risk mitigation strategies. · Provide strategic advice on a range of issues including but not restricted to: issues management and media relations; investor relations; and relations with donor agencies and development finance institutions.

VII OVERVIEW OF THE POWER SECTOR

7.1 Providing access to affordable and reliable electricity to all citizens of

Nigeria is a critical national goal of the Federal Government of Nigeria. This is in

view of the fact that without adequate and reliable electricity supply, our socio-

economic goals of alleviating poverty, creating jobs and wealth as envisaged in

the Transformation Agenda cannot be achieved.

7.2 Historically, electricity supply in Nigeria dates back to 1886 when two

generation sets were installed to serve the colony of Lagos. By 1951, the Act

establishing the Electricity Corporation of Nigeria (ECN) was enacted. This was

followed by another Act establishing the Niger Dams Authority (NDA) in 1962 to

develop hydro electric power. The merger of the two organizations in 1972 gave

birth to what was known as the National Electric Power Authority (NEPA).

Between 2001 and 2005, changes to the erstwhile Electricity and National

Electric Power Act removed the monopoly status granted NEPA over generation,

transmission, distribution and marketing of electricity. The reason for the

amendments was to pave the way for liberalization and in effect, introduce

competition and hence efficiency. However, this did not materialize.

Page 110: 2011 Annual Report of Federal Ministry of Power.pdf

109

7.3 A comprehensive review of the policy, legal and regulatory framework led

to the formulation and drafting of the National Electric Power Policy (NEPP) and

the Electric Power Sector Reform (EPSR) Act, which were adopted and enacted in

2011 and 2005 respectively. The latter provided the basis for the transformation

of NEPA into Power Holding Company of Nigeria (PHCN), and the unbundling of

PHCN into eighteen (18) successor companies, six (6) generation companies as

Kainji and Jebba Hydro Electric Power Plants were incorporated as a single

entity; One (1) transmission and eleven (11) distribution companies. The

unbundling of PHCN was a strategic step towards creating a competitive

electricity market.

7.4 In pursuit of Government‟s goal to develop a sustainable power sector that

will support the socio-economic needs of the nation and the quest for the

emergence of Nigeria as one of the 20 most developed economies of the world

by the year 2020, the Federal Ministry of Power is focused on its mandate to

ensure that the Nation is supplied reliable and adequate power to achieve our

vision as a country. This will be achieved through earmarked projects currently

being implemented by the various Agencies under the supervision of the Ministry

across the power value chain-generation, transmission, and distribution as

attracting private investment in the sector.

7.5 A strategic plan was vigorously pursued in 2009 which benefited from an

emergency funding intervention by all tiers of Government in addition to the

Budgetary Appropriation to make good the primary objective of increasing

electricity supply and its reliability to drive National socio-economic aspirations of

job creation and increase welfare of the Nigeria citizenry. Other objectives the

Federal Government set to achieve with the intervention include:

Page 111: 2011 Annual Report of Federal Ministry of Power.pdf

110

Diversification of generation beyond gas and hydro, which are presently

the dominant sources of power generation;

Improved security and reliability of electricity services;

Improved operational efficiency and sector viability; and

Increasing access to electricity.

VIII. CHALLENGES IN THE NIGERIAN POWER SECTOR

8.1 The key challenges militating against the efficient delivery of adequate and

reliable electricity supply in Nigeria are as follows:

Highly Capital Intensive – nature of power sector projects: In this

regard, public sector funding is inadequate due to competing demands.

Inadequate Power Generation Capacity: In comparison with other

countries, Nigeria‟s average daily generation of 3,700MW is grossly

inadequate for a population of over 160 million people. Factors affecting

the generation capacity include old/ageing power plants (3 hydro & 3

thermal plants are over 20 years old, 1 thermal plant is 10 -20

years, while only 3 thermal plants are less than 10 years old),

vandalization of existing power infrastructure, gas supply constraints and

inadequate maintenance of equipments that stem from procurement

bottlenecks, dearth of skilled maintenance personnel in the sector and the

dependence on imports of parts and foreign experts to effect repairs and

overhauls.

Transmissions and Distribution Networks: are currently inadequate

and inefficient in wheeling and distributing generated power, with high

transmission losses.

Page 112: 2011 Annual Report of Federal Ministry of Power.pdf

111

Inefficient Billing and Metering System: One of the major challenges

facing the Nigerian Power sector is the low efficiency in billing and revenue

collection by the Distribution Companies (DISCOS).

Sector Reforms: Areas of focus include strengthening industry

regulations, industry and market structure appropriate electricity pricing

development of commercial framework to support private investments,

effective setting of competition amongst the successor companies, and

efficiency improvement in reducing technical and non technical issues.

8.2 It is gratifying to note that the present Administration has put the

necessary machinery in place to address all the above challenges. The

plans/strategies in that respect are provided below:

IX. STRATEGIC GOALS / PLANS

9.1 The strategic priorities for the power sector to address the critical issues

and challenges identified in the Nigerian electricity industry are as follow:

a. Optimization of Existing Assets (Rehabilitation): Overhaul and

rehabilitation of existing power generating plants as well as rehabilitation

and expansion of transmission and distribution infrastructure.

b. Building New Capacity (On – going Projects): Completion of the on-

going National Integrated Power Project (NIPP) and encouraging

Independent Power Producers (IPP) to increase capacity.

c. Energy Security: Achieving energy supply security by utilizing the

Nation‟s other energy resources (including coal, crude oil, wind, solar,

small & medium hydro, biomass and nuclear) to diversify the energy

generation mix.

d. Attracting Private Investments in the Sector: The EPSR Act, 2005

provides for the deregulation of the Power sector to attract private

Page 113: 2011 Annual Report of Federal Ministry of Power.pdf

112

investors in generation and distribution. In order to catalyze the inflow into

the industry of private sector investments and accompanying managerial

and technical expertise, the following steps are being taken:

Establishment of an Appropriate Pricing Regime;

Establishment of the Nigerian Bulk Electricity Trading Company PLC

(NBETC) as Bulk Purchaser;

Provision of Government Credit Enhancement;

Operationalising the Nigerian Electricity Liability Management

Company (NELMCO); and

Reaching Agreement on all Outstanding Labour Issues

e. Consolidating On-going Reforms Process: Efforts are being made to

consolidate the on-going structural and economic reforms targeted at

establishing effective institutional and regulatory frameworks in the power

sector.

f. Promoting Energy Efficiency: Introducing demand side management

principles, embarking on public enlightenment campaigns, as well as

advocating for the use of energy saving equipment to reduce power

demand at home and industry

X. MAJOR ACHIEVMENTS IN THE POWER SECTOR.

10.1 Institutional Framework

In order to deliver on the promise of Mr. President “to improve

electricity availability to Nigerian homes and businesses within a short time

frame”, the Federal Government established a Presidential Action

Committee on Power (PACP) and a Presidential Task Force on Power

(PTFP). PACP, under the Chairmanship of Mr. President, has been

providing leadership and guidance for the Power Sector development as

Page 114: 2011 Annual Report of Federal Ministry of Power.pdf

113

well as determining the general policy directions and strategic focus of the

power reforms. The Presidential Task Force, under the Chairmanship of

the Special Adviser to the President on Power, has been developing and

driving forward the Action Plan for the Nigerian Power Sector with

achievable targets within the lifespan of this Administration. The Task

Force reports to Mr. President and the PACP on a weekly basis.

10.2 GENERATION:

A total of 1,494,590.6MWH of energy has been generated as at

November 2011, surpassing those recorded in previous years. (See the

histogram above).

Load factor average of 0.674, signifying that 67.4% of the available

capacity was actually sent to the consumers.

Generation Utilization Index average of 0.647 for the year, showing that

64.7% of the available capacity was actual generation.

Capacity Utilization index averaging at 0.615 implies that the station made

available 61.5% of the installed capacity.

Station Reliability Index at an average of 0.648 for the year, shows that

the three (3) units in the station ran for 64.8% of the time in 2011.

Planned Maintenance Index average of 1.0 shows that all the routine

preventive maintenance activities were carried out.

Breakdown Maintenance Index average of 0.599, had the implication that

59.9% of the breakdown/defects were rectified.

Service Level Commitment: The station on the whole meets up with its

service level contractual obligation.

Minor Inspection GT11, GT12, and GT13: This was completed this year, by

Siemens the OEM, ensuring the plant availability for the next 4000 to

8000EOH.

Training of staff both locally and foreign. This has equipped the staff on

Technical and managerial capability but further plant specific trainings are

Page 115: 2011 Annual Report of Federal Ministry of Power.pdf

114

required to improve diagnostic skills in plant maintenance. In liaison with

the OEM identified skill gaps have been passed on to NAPTIN for

coordination and funding.

Computerized Maintenance Management System (CMMS) was installed to

improve on the former MMS which was manual based. This has ensured

the availability and reliability of the plant. This also, has improved the

management and the early commencement of work. With the CMMS, the

daily routine inspection and planned maintenance Inspection (weekly,

monthly, quarterly, bi-annual, and annually) and implementation of the

manufacturers maintenance specification has helped to sustain availability

and efficiency of the plant.

In tandem with the CMMS is the computerization of the store which will

improve our inventory management. The two systems will later be

connected to broaden the scope of the CMMS;

Annual maintenance, repair of water leakages from the head cover

assembly, exciter flash over repair work were all carried out on 1G12

thereby restoring the unit back to service.

Repair of unit 1G9 runner inspection door, installation of main guide

bearing and repair of 16KV circuit breaker were all carried out.

Welding of the cracked throat ring/ runner chamber, repair of the head

cover assembly and annual maintenance were carried out on unit 1G6 in

order to restored the unit back after being shut down on emergency due

to excessive water leakage from the runner throat ring.

Enhanced plant maintenance activities were carried out by the application

of effective maintenance management system (MMS) for plant sustenance.

Improved company asset base as a result of infrastructural rehabilitation

carried out.

Provision of incentive, innovation and human capacity development for the

company staff thus enhancing good management/staff relationship.

Page 116: 2011 Annual Report of Federal Ministry of Power.pdf

115

10.3 Reform Programme

In consonance with the Roadmap unveiled by the President of the Republic of

Nigeria on Thursday, 26th August, 2010 “to ensure modest but genuinely

realizable improvements in the amount and quality of electricity supplied to

consumers in the country”, all the Distribution Companies are being

privatized based on a core investor sale of a minimum of 51% of the

Government‟s equity in the companies. The PHCN successor thermal plants are

also being privatized via the sale of a minimum of 51% of the Government‟s

equity in the companies. The PHCN successor thermal plants are also being

privatized via the sale of a minimum of 51% equity to core investors that clearly

demonstrate the technical and financial ability to operate and expand each plant;

while concessions are to be granted for the operation of the hydropower

generating plants at Jebba, Kainji and Shiroro. In addition, necessary steps are

being taken to hand – over the Transmission Company of Nigeria (TCN) to a

credible private sector Company under a five – year management contract.

10.3 Optimization of Existing Assets

In order to recover lost capacity and sustain the running Units, the existing

power generating plants are being overhauled and rehabilitated prior to their

privaitisation. Also, the rehabilitation and expansion of some transmission and

distribution infrastructure have been completed while some others are on –going

10.4 Building New Capacity

Concerted efforts are being made to complete the on – going National

Inatergrated Power Projects (NIPP) at Alaoji, Calabar, Egbema, Ihovbor, Gbarain,

Page 117: 2011 Annual Report of Federal Ministry of Power.pdf

116

Sapele, Omoku, Geregu, Omotosho and Olorunsogo. In addition, the

Independent Power Producers (IPP) are being encouraged to increase capacity.

Energy Security

One of the strategic priorities of the present Administration is the achievement of

energy supply security by utilizing the Nation‟s other energy resources (including

coal, crude oil, wind, solar, small & medium hydro, biomass and nuclear) to

diversify the energy generation mix. To enhance energy security, given that the

power industry in Nigeria is predominantly driven by gas, the Federal Ministry of

Power identified the following projects for implementation, which commenced in

2009 and are currently at various stages of completion.

i) Coal – Fired Power Plants: Detailed studies by Consultants are in the

process of being completed to ascertain the commercial quantity of coal

available for the development of such a plant at any of the potential sites in

Enugu, Benue, Kogi and Gombe States.

ii) Small and Medium Scale Hydro Power Plants: Feasibility studies and

Environmental Impact Assessment (EIA) for the development of 12 identified

sites for small & medium hydro power projects for both on – grid and off –

grid generation are on – going. The projects will include the installation of

turbines and generators in existing dams to generate electricity [e.g.

Dadinkowa (34MW), Oyan (9MW), Ikere Gorge Dam (6MW) and Bakolori

(3MW)]

iii) Kaduna Power Plants Projects (21.5MW): As part of the intervention

towards resolving the acute shortage of electric power across the country

and in consideration of the persistent challenges of gas supply to existing

thermal power stations, the Federal Government adopted a strategy of

exploiting alternative fuels for power generation. In this respect,

Page 118: 2011 Annual Report of Federal Ministry of Power.pdf

117

Government awarded a contarct in favour of a consortium of GE / Rockson

Engineering Ltd for the establishment of a 215MW (ISO) power plant in

Kaduna. The primary fuel would be initially Low Pour Fuel Oil (LPFO) but the

plant is expected to switch to natural gas when the necessary gas

transmission infrastructure is eventually extended to Kaduna. The selection

of Kaduna for the project was based on the availability of Low Pour Fuel Oil

(LPFO) from Kaduna refinery and the technical imperative of balancing the

national transmission grid. The project was awarded to the consortium on

EPC basis and the Work Plan indicates that the project would be completed

in 2011.

iv) 10MW Katsina Wind Farm Project: In line with the Government policy of

promoting renewable energy, a wind resources mapping for the entire

country was undertaken by Messrs Lahmeyer International in the year

2006. The final Report indicated numerous viable sites for the deployment of

wind turbines for power generation. In order to flag off the exploitation of

the Nation‟s resource forpower generation, a contract was awarded for the

establishment of the Nation‟s first wind farm to be located at Katsina in

favour of Messrs Vergnet SA of France. With an installed capacity of 10MW,

the completed plant is expected to supplement the electric power supply

available to the community and showcase the wind technology for potential

investors. The project is scheduled for completion in 2011

v) Mambilla (2, 600MW) Hydroelectric Power Project: The Mambilla

HEPP is one of the major projects expected to significantly increase the

security of supply of power in the country. The project is planned to consist

of a 2,600MW base load hydroelectric power plant with a completion period

of 5years. Lahmeyer International was engaged to undertake a detailed

review of the feasibility study on the project and to prepare a bankable

Page 119: 2011 Annual Report of Federal Ministry of Power.pdf

118

report and tender documents for eventual implementation. Another essential

study towards the realization of the Mambilla project is the definition of the

HV Transmission Line for the generated power. The project, which was

undertaken by Messrs Colemnco Power Engineering Ltd has been

completed on scheduled and is expected to provide the base data for the

design of the High Voltage lines from the Mambilla power house to be

located at Abong to Jalingo and Makurdi. The Policy direction of Government

is to vacate all existing contractual commitments on the projects and

complete all the on – going preliminary studies by the 1st Quarter of 2011.

(i) Zungeru (700MW) Hydroelectric Power Project: The Zungeru

Hydroelectric Power Project was conceived as a 950 MW power plant

on the basis of feasibility studies conducted in the 1980s. In view of

the passage of time, Messrs Coyne Et Bellier was engaged to review

1983 feasibility study earlier prepared by Messrs Chas T. Main

International. Messrs Coyne Et Bellier has since submitted the

review report indicating that the optimal capacity of the project shall

be 525MW with the possibility of future expansion to 700MW Though a

contract for the implementation of the 950MW project was awarded in

April 2007 in favour of Messrs CNEEC, the Ministry is in the process

of re-negotiating the contract in line with the revised scope and

recommendation of Messrs Coyne Et Bellier. The Consultant has

since prepared technical specifications and EPC tender documents for

the project and it is currently being reviewed by the Ministry. The

Ministry has also initiated the process of procuring a Consultant for the

conduct of an Environmental Impact Assessment (EIA) for the project.

10.3 Attracting Private Investments in the Sector

The EPSR Act, 2005 provides for the deregulation of the power sector to

attract private investors in generation and distribution. In order to

catalyze the inflow of private sector investments and accompanying

managerial and technical expertise into the industry, the following steps

have been taken:

Page 120: 2011 Annual Report of Federal Ministry of Power.pdf

119

(i) Establishment of an Appropriate Pricing Regime: It is

noteworthy that for the sector to be financially viable throughout

the value chain, the end-user tariff (which is currently significantly

below what is necessary for the sector) must at least be at a cost-

reflective level. Consequently, the Nigerian Electricity Regulatory

Commission (NERC) embarked on a major review of the Multi-Year

Tariff Order (MYTO) with a view to developing an appropriate Tariff

Structure taken into consideration the need for cost recovery in the

industry.

(ii) Establishment of the Nigerian Bulk Electricity Trading

Company PLC (NBETC) as a Bulk Purchaser: The Company

was incorporated to carry out contract management and bulk

trading (on behalf of the Distribution Companies). NBETC is a

transitional entity until the DISCOs attain credibility and credit

worthiness.

(iii) Provision of Government Credit Enhancement: In entering

into Power Purchase Agreements (PPAs), Independent Power

Producers (IPPs) will require that there is a creditworthy

counterparty at the other side of the table. In this regard, the

Federal Ministry of Finance is reviewing a set of options through

which the Federal Government may provide credit enhancement to

the bulk purchaser that will enter into PPAs with the successor

generation companies and IPPs.

(iv) Operationalising the Nigerian Electricity Liability

Management Company (NELMCO): Efforts are being made to

fully operationalize NELMCO which was established as a special

purpose vehicle to assume and manage extant assets, liabilities and

other obligations that could not be easily transferred from the

Power Holding Company of Nigeria (PHCN) to any of the Successor

Companies.

Page 121: 2011 Annual Report of Federal Ministry of Power.pdf

120

(v) Reaching Agreement on all Outstanding Labour Issues: The

Federal Government recently engaged in active dialogue with the

leaders of the Labour Unions on the settlement of outstanding

monetization arrears and severance pay. Other outstanding labour

issues are currently being addressed by an inter-Ministerial

Committee, under the Chairmanship of the Honourable Minister of

Labour and Productivity.

10.4 Capacity Building in the Power Sector

The growth of the power sector and the introduction of new technologies

have necessitated an urgent need to develop the human capital that would

efficiently operate, maintain and manage the power sector. In this regard,

the National Power Training Institute of Nigeria (NAPTIN) was developed

to address the manpower needs of the sector, with the existing seven (7)

Regional Training Centres (RTCs) forming the core of the take-off facilities.

Two (2) additional RTCs are currently being developed at Oji and Kano.

Between June 2009 when NAPTIN commenced training and December

2010, NAPTIN has succeeded in providing capacity building training

programmes for 2,716 PHCN personnel in various areas of electricity

production chain.

10.5 Operational Performance

Generation

It is gratifying to note that power generation in the country stabilised over

the past one year. Also, the highest Peak Generation of 3,804.3MW

in the history of the power sector was achieved on 5th August,

2010.

Transmission

The power sector has witnessed improved transmission capacity and

reliability. In the last year, capacity of the system was increased, the

amount of power that moved through the system increased by 25%, and

the number of system collapses was reduced from 17 to 13. Large scale

improvements in the infrastructure include:

986.5km of 330kV lines out of which most have been 50% completed.

Page 122: 2011 Annual Report of Federal Ministry of Power.pdf

121

705.3km of 132kV lines out of which 396.8km are above 50% completion.

1350MVA transformer capacity at 330/132kV are being installed in new substations of which some 900MVA are more than 50% completed.

3000MVA capacity of 132/33KV transformers are being installed in new substations of which 960 MVA are more than 50% completed.

Distribution

There has been a marginal increase in the distribution capacity. By 31st

December, 2010 it was over 19,163.89MVA (16,289.31MW).

10.6 Investors’ Comfort Framework

In line with the vision of a private sector-led electricity industry in Nigeria,

the Nigerian Electricity Regulatory Commission (NERC) earlier in the year

instituted a major review of the Multi-Year Tariff Order (MYTO). The intent

was to bring commercial viability to the sector by introducing economic

pricing for power. The MYTO major review is continuing, and is expected

to be completed in the first quarter of 2011. On completion, consumers

will be required to pay tariffs which actually reflect the costs of the

electricity they use. This in turn, will allow the private sector, operating at

reasonable levels of efficiency, to realise the returns on investment

required to attract investments in the sector.

10.7 Renewable Energy The deployment of renewable energy technologies for electricity

generation in Nigeria had been low. However, the Government in 2010

started to pay more attention to these energy sources, particularly in

smaller urban centres and rural areas. Projects included:

15kW solar pilot project at OGD farm settlement in Idekan, Ogun State was completed and handed-over on 19th March, 2010;

15.79kW Kindigi solar project in Katsina State is 60% completed; 17.5kW Gaza solar project in Shira LGA of Bauchi State is about

to start producing power; and

17.5kW solar electrification of Esham Community in Ogoja LGA of

Cross-River State is 85% completed.

10.8 Private Investments

The activities of the Standing Committee (which was established by the

Ministry in November 2009 to facilitate the coordination, licensing and

Page 123: 2011 Annual Report of Federal Ministry of Power.pdf

122

review of the business models of private sector investors in the power

sector) were intensified in 2010. Private sector participation in power

generation in the country has been in geometric progression. Between

2006 and 2009, a total of 34 Companies had been licensed as

Independent Power Producers (IPPs). Of this, eight have commenced

commercial operation as follows:

On-Grid Generation. (1,876MW Installed Capacity)

Okpai – 480MW

AES – 270MW

Omoku – 150MW

Afam VI (Shell) – 650MW

Ibom Power – 190MW

Trans-Amadi – 136MW

Off-Grid Generation. (114.82MW Installed Capacity)

Notore Power – 25MW

Energy Company of Nigeria (ENCON) – 89.82MW

In 2010, more than 40 prospective investors had made presentations to

the Ministry and several have started the process to obtain licenses. With

the establishment of the Bulk Purchaser, the signing of Power Purchase

Agreements, the N300 billion in loans being made available by the Central

Bank of Nigeria and the securitization arrangement being made by the

Federal Government, many companies are being encouraged to invest in

the sector.

10.9 Power Purchase Agreements

A number of Power Purchase Agreements (PPAs) were being discussed

between some IPPs and the Federal Government. These included:

Shell Petroleum Development Joint Venture (650MW plant at Afam VI).

Ibom Power PLC (691MW out of which 190MW is already producing commercially).

Chevron Nigeria PLC Joint Venture (500MW plant at Apura). Exxon Mobil Joint Venture (350MW plant at Qua Iboe).

Page 124: 2011 Annual Report of Federal Ministry of Power.pdf

123

Total Elf Petroleum Nigeria Limited Joint Venture (500MW plant at Obite).

First Independent Power Limited (150MW plant at Omoku, 136MW plant at Trans Amadi, and 75MW plant at Eleme).

10.10 Labour Issues

The Government is committed to settling all legitimate workforce

entitlements and negotiates the position of workers under the newly

reformed power system. As a demonstration of Government‟s commitment

and sincerity to the reform process, payment of monetization arrears to

the staff of PHCN progressed as follows:

1 No. of Staff for Verification 46,108

2 No. of Staff Processed and Paid 43,226 (93.75%)

3 No. of Staff Cleared with Pending Issues

971

4 No. of Staff Cleared but being Reviewed

198

5 No. of Staff Yet to be Cleared 1,713

6 Amount Disbursed to Date N52.915 billion (94.43%)

7 Closing Balance N3.120 billion

10.14 US$100 Million Indian Line of Credit

The Government of India approved a US$100 million line of credit (2009-

2010) to Nigeria for the execution of the following projects:

Supply and commissioning of transmission line, 33KVA 330/415kV

distribution transformers and associated accessories for 96 Communities in the three Senatorial Districts of Enugu State (US$40 million);

Provision of 132/33kV Substation, Solar Mini-Grid electrification and solar street lighting in Kaduna State (US$29.85 million); and

Construction of 2x26MW gas-based power plant in Cross River State (US$30 million).

Page 125: 2011 Annual Report of Federal Ministry of Power.pdf

124

10.11 Gas Supply Mechanism

The Ministry collaborated with the Ministry of Petroleum Resources, the Nigerian

National Petroleum Corporation (NNPC), and the International Oil Companies

(IOCs) to institutionalize the commercial framework for gas supply to PHCN

legacy plants. The Gas Supply Agreement (GSA) and the Gas Transportation

Agreement (GTA) were finalised. The following Gas Supply Aggregation

Agreements have either been signed or negotiations were concluded in 2010:

Pan Ocean (60 mmscf/day).

Shell Petroleum Development Company Joint Venture (350 mmscf/day). Chevron Nigeria Limited Joint Venture (550 mmscf/day).

10.12 Power Projects Completed in 2010

The following major projects were either commissioned or due for

commissioning in 2010:

650MW Afam VI Power Plant.

37 Japanese Grant-in-Aid Rural Electrification Projects (23 in Cross-River & 14 in Akwa-Ibom States).

367.5km of 330kv Transmission Line Connecting Jalingo, Taraba State to the National Grid.

2x30MVA 132/33kV Substation at Jalingo, Taraba State.

2x30/40MVA 132/33kV Substation in Talata-Mafara, Zamfara State.

1x150MVA 330/132/33kV Substation at Kumbotso, Kano.

1x150MVA, 330/132/33kV Substation at Mando Road, Kaduna.

2x60MVA 132/33kV Substation in Kubwa, Abuja.

60MVA, 132/33kV Transformer at Apo, Abuja.

2x30/40MVA 132/33kV Substation at Ado-Ekiti.

Ikot Ekong 2.5MVA 33/11kV Injection Substation in Ika LGA, Akwa-Ibom

State.

Page 126: 2011 Annual Report of Federal Ministry of Power.pdf

125

10.13 Project Management Unit (PMU) The Project Management Unit in the Ministry is responsible for implementing projects financed by the World Bank. The PMU is currently managing three projects, all under implementation. These are:

a. National Energy Development Project (NEDP): The NEDP was

designed to strengthen the transmission and distribution systems and

initiate renewable energy pilots. The US$172 million project became

effective in November 2005 and will close in June 2012. It has

components for: Transmission, Distribution, Rural Access, Technical

Assistance, and NERC.

Among other projects, it has completed:

Supply of Instrument Transformers;

Substation Rehabilitation and Reinforcement;

Grid Metering;

Rehabilitation of Jos- Makeri 132 KV line;

Supply of Cables, Termination Kits, HT concrete pole, ring main units,

distribution boxes and fuses and150 mm2 Aluminum Conductors;

Supply and Installation of HT Metering Panels;

Supply of Primary and Secondary Injection Test Kits;

Supply of Surge Arresters & Transition Joints;

Feasibility Studies and Design of Off-Grid Solar PV Site;

Screening Study to Assess SHP Potential in Nigeria;

Solar Power Electrification of Fadama Communities in Ogun State; and

Conversion of LVDS to HVDS- Karu Feeder 1 Contract No: NCB 10 Lot 3.

b. Nigeria Electricity and Gas Improvement Project (NEGIP):

This US$600 million project was approved in June 2009 and became

effective in July 2010. The project aims to improve the availability

and reliability of electric power in Nigeria mainly by supporting gas

supply contracts through US$400 million in Partial Risk Guarantees

(PRGs) and US$200 million in complementary investments in

transmission and distribution systems. The project will assist the

Government of Nigeria (GON) in delivering more reliable power and

creating a healthier power sector. The proposed project will result in

Page 127: 2011 Annual Report of Federal Ministry of Power.pdf

126

five distinct economic benefits: 1) incremental, reliable and improved

quality of gas supply; 2) reduction of power losses from generation,

distribution and the electrical grid; 3) improved power quality and

reliability, 4) improved financial health of the sector by helping

increased generation and income, and 5) enhance customer

satisfaction.

During the period under review, the project resulted in:

Rehabilitation and reinforcement of old 330/132kV and 132/33kV Transmission Sub-stations;

Reinforcement and rehabilitation of 33/11kV injection Sub-stations in all the 11 electricity Distribution Companies; and

Installation of 11kV Sectionalizers in Karu, Kubwa, LUTH, Ogba, Agege and Challenge HVDs Clusters.

c. Niger Basin Water Resources Development and Ecosystem

Management Programme: The main purpose of the project is to

rehabilitate the hydroelectric units at Kainji and undertake civil works at

Jebba dams. It became effective in December 2007 and on-going up to

2010. The project involved five countries along the River Niger. The

Nigerian portion of the Credit was US$135 million. In 2010, the project

had:

Commenced bidding for the rehabilitation of the power plants 5, 6 and 12 and the common systems at Kainji;

Commenced bidding for the supply and installation of hydrological equipment at Kainji and Jebba;

Awarded bids and started other processes for the supply of battery packs, machine tools and machines, the supply of spare parts, computer equipment and flood warning equipment;

Established teams to execute carbon finance initiatives at Kainji and Jebba; and

Awarded consultancy contracts for engineering supervision of the spillway at Jebba, the environmental action plan for Jebba and Kainji, and various other projects needed in conjunction with the upgrading for the two facilities.

Page 128: 2011 Annual Report of Federal Ministry of Power.pdf

127

XI. PROSPECTS AND INVESTMENT OPPORTUNITIES IN NIGERIA

The Power Sector has been formally opened to investors to participate in the

generation and distribution of electrical energy in Nigeria, since the enactment

into Law, the Electric Power Sector Reform Act in 2005.

Government has further demonstrated its commitment to a stable, reliable and

affordable power supply to all Nigerians in Government pronouncements,

institutional and regulatory reforms programs, and has even gone further to

publish a Road Map towards the achievement of the said objectives.

One of the Key objectives and targets is the involvement of the private sector in

the overall development of power infrastructure, operations and maintenance.

To this end, various initiatives have been put in place, through regulation and

institutional reforms, which culminated in the request for Expression of Interest

(EOI) from investors willing to participate in power generation and distribution,

based on equity participation in existing assets as well as new infrastructure.

To this end, a lot of investment fora had been created by the Federal

Government through the Bureau for Public Enterprises, Road shows,

publications and the establishment of a One-stop-shop committee for IPPs in

the Federal Ministry of Power to amongst others:-

a) Provide the necessary information to investors on the institutional and

regulatory, Financial, Environmental issues and the steps required by

would-be-investors in establishing Independent Power Production in

Nigeria.

b) Provide linkage and contact persons in the various entities that will

interface with investors in the power sector.

c) To help investors to fast track processes and procedures required in the

licensing processes.

d) To perform other functions as may be required in ensuring a total

information flow to the investors is achieved as well as fast-track entry

Visas to Nigeria for the purpose of investors‟ access to Nigeria.

The „One-Stop-Shop‟ Committee for IPPS draws membership from Federal

Ministry of Power, Power Holding Company of Nigeria (PHCN), Federal Ministry of

Page 129: 2011 Annual Report of Federal Ministry of Power.pdf

128

Finance, Federal Ministry of Environment, Central Bank of Nigeria and the

Nigerian Electricity Regulatory Commission (NERC).

NECESSARY STEPS REQUIRED FOR INVESTORS IN THE POWER

SECTOR.

The following steps are necessary for potential investors in the Power

Sector, especially in Generation.

i. Identify the type of generation that is; gas fired (thermal), Coal fired

Plat, Hydro, and/or Renewable Energy, including small and Medium

Hydro.

ii. Investors are required to perform a search and identify sources of

generation, e.g. Hydro site requires identification of suitable river

flows, Gas fired thermal Units must locate and confirm sources of

gas and be able to firm up this source via Gas Aggregation Company

of Nigeria or to other sources. Coal fired power plants must identify

coal sources and firm up supply.

iii. Investors must locate their plant on a land already acquired or

capable of acquiring with no encumbrances.

iv. Investors must perform Environmental Impact Assessment (EIA)

studies and be fully certified by the Federal Ministry of Environment

for environmental compliance and during the period, it is expected

that the issues of land acquisition and ownership, Community

related issues would have been solved.

v. Investors will perform power evacuation studies in liaison with the

Transmission Company of Nigeria (TCN) to ensure that there is

adequate power evacuation infrastructure as well as resolve issues

bothering on Common point of connection to the grid.

vi. Investors will be required to firm up and prepare their Business plan,

to include Capital investment, Operation & Maintenance cost

including fuel costs, etc. and come up with a total financial model

for their plant.

vii. There are various forms of waivers available for prospective

investors in Nigeria. The Nigerian Investment Promotion Council is

to provide the details of these waivers whenever they are required.

viii. Investors will commence a Power Purchase Agreement (PPA)

negotiation of identified off-taker, or the Bulk Electricity Trading

Page 130: 2011 Annual Report of Federal Ministry of Power.pdf

129

Company of Nigeria where a total package on a PPA will be

negotiated and signed.

ix. Investors can now engage the Nigeria Electricity Regulatory

Commission (NERC) for the issuance of licenses which are site

specific. Licenses can be for grid operation or off-grid depending on

the off taker involved.

x. Investor Builds its plant, and Commissions in line with the licensing

conditions.

So far Seventy-nine (79) prospective Investors presented project Proposals to

the IPPs Standing Committee according to the table below:

DISTRIBUTION OF COMPANIES’ AREAS OF INTEREST

Interest Number of Companies

Gas 25

Hydro 8

Coal 6

Wind 8

Solar 5

Renewable( Not Specific) 3

Waste 5

Heat 3

LPFO 1

Fuel Cell 2

EPC 13

Page 131: 2011 Annual Report of Federal Ministry of Power.pdf

130

ENERGY RESOURCES IN NIGERIA:

Nigeria is endowed with reasonably large quantities of various energy resources.

The Country is endowed with both the Conventional and the non-conventional

Energy resources. The Conventional comprise mostly of the non- renewable

energy resources such as crude petroleum oil, natural gas, coal, tar sand and

uranium. The country has the tenth largest oil and gas reserves in the world.

Nigeria‟s near equatorial location, extensive and diverse vegetation, prevailing

trade winds and many rivers endow her with high quantities and quality of

renewable energy resources. These include solar radiation, hydro power, wind

and biomass energy. The table below illustrates the energy resources in the

Country.

0

5

10

15

20

25

30

Companies and their Areas of Interest

Areas of Interest

No. of Companies

Page 132: 2011 Annual Report of Federal Ministry of Power.pdf

131

Table I

Current Nigeria’s Energy Resource

Energy Type Resource Estimate

Crude Oil 35 billion barrels

Natural Gas 183 Trillion cubic feet (1ft=0.048m)

Hydro power 14750 MW

Coal 2.75 billion Metric tons.

Solar Radiation 3.5 – 7.0 KWh/m2-day

Wind Energy 2.0 – 4.0 m/s( 10 metres in height)

Nuclear Lot (Not yet Quantified)

Biomass 144 million tonnes/yr

Wave and Tidal Energy 150,000 TJ/yr (16.6 x 106 toe/yr)

Geothermal Energy 37 and above 100oC (Not yet expl.)

2.1 CONVENTIONAL ENERGY RESOURCES:

i. Oil And Gas (Petroleum Resources)

ii. Coal

iii. Hydro

Table II

Small and Medium Hydro Power Potentials in 10 locations Nigeria

Location Dams Exploitable Capacity,

Ogun State Oyan 10MW

Oyo State Ikere 6 MW

Page 133: 2011 Annual Report of Federal Ministry of Power.pdf

132

Zamfara Bakolori 3 MW

Kano Challawa 7.5 MW

Kano Tiga 10 MW

Kogi Kampe 500KW

Ondo Owena 450KW

Nasarawa Doma 1MW

Katsina Zobe 300KW

Katsina Jibia 4MW

2.2 NON-CONVENTIONAL ENERGY RESOURCES

The following are the various non-conventional energy resources available in the

country that can be harnessed for power generation.

i. Nuclear

ii. Solar

iii. Wind Power

iv. Biomass Energy

v. Wave And Tidal

vi. Geothermal Energy

Table III

Summary of geothermal potentials in Nigeria

S/N State Location Geothermal

Resource

Primary outputs/Source

1. Adamawa Lamurde

LGA

Lamurde hot

spring

Steam/hot water above 100oC.

Hot dry rock and normal temp.

2. Bauchi Yankari Park Wikki Warm

Spring

Warm water up to 40oC Hot dry

rock and normal temperature

gradient

Page 134: 2011 Annual Report of Federal Ministry of Power.pdf

133

3. Benue Okpoga Enemabia warm

spring

Warm water at 38oC. Hot dry

rock and normal temperature

gradient.

4. Ekiti Ikogosi Ikogosi warm

spring

Warm water at 37oC. Hot dry

rock and normal temperature

gradient.

5. Nasarawa Awe LGA Akiri Warm

Spring

Warm water at 40oC. Hot dry

rock and normal temperature

gradient.

Source: On-going studies at the University of Ado-Ekiti, Mechanical Engineering

Dept.

ENTRY OPTIONS FOR INVESTORS

Potential Investors can consider the following options in the development of the

Power Sector in Nigeria:

Independent Power Producer

Acquisition of Existing Thermal Power Plants

Concessioning of Existing Hydropower Plants in the Country

Local Production of Equipment and Components used in the Power

Sector

Manufacture of Energy saving appliances

Provision of gas supply and transportation infrastructure

INVESTORS’S COMFORT FRAMEWORK

Independent Electricity Regulator Tariff review on fast track

Creditworthy off-taker Established- Nigeria Bulk Electricity Trading PLC Credit enhancement

Liability Management Co. (NELMCO) set-up

Government‟s Reforms Policy Trust

Political will

Page 135: 2011 Annual Report of Federal Ministry of Power.pdf

134

TACKLING SECURITY IN NIGERIA

An unfriendly security climate precludes both external and internal investment in

the Country. Thus security is seen by the present Administration as necessary for

the development of the Power Sector. It has put in place measures to tackle the

Niger Delta Security challenges and the recent spurs of terrorism unleashed in

the Country with physical policing, military intelligence, security and the

installation of closed circuit televisions in strategic locations in the Country.

In addition, efforts are on-going to put an end to the challenges of insecurity in

the Country by the Federal Government with the setting up of Committees on

security with a view to investigating the underlying cause (s) of the acts of

violence experienced in the Country and dealing with them in a decisive manner.

Potential investors are hereby assured that investments made in the Power

Sector are secured.

Nigeria‟s membership in multilateral organizations such as the following is

another guarantee to potential investors:

(i) Multilateral Investment Guarantee Agency (MIGA) guarantees offer

much more than just the assurance that losses will be recovered. The

insurance also benefits investors and lenders.

(ii) International Development Associations (IDA) aims to reduce poverty

by providing interest-free credits and grants for programs that boost

economic growth, reduce inequalities and improve people‟s living

conditions.

(iii) International Finance Corporation (IFC) positioned to help countries in Sub-Saharan Africa develop model projects that can support private investment, thus allowing government spending to focus on areas where it can be more effective.

Page 136: 2011 Annual Report of Federal Ministry of Power.pdf

135

XII. CONCLUSION

12.1 The year 2011 was considered as a pivotal year for the consolidation of the work needed to both provide reliable power to the people of Nigeria and pave the way for the future. During the past year, the Federal Ministry of Power made strong progress in three (3) main areas: (i) Fixing the current system in order to deliver the maximum amount of power. Today, Nigerians are receiving more reliable power than they have had in the past years. Generation is achieving record amounts of power and we have delivered it to the people. Polls tell us that 90 percent of people who have seen a change in their power supply

have seen a positive change; (ii) Consolidating the reform programme in the power sector. The Ministry is rapidly moving towards winding down the Power Holding Company of Nigeria (PHCN) within the next few months, and moving towards more private sector participation in our current generation, transmission and distribution companies; and (iii) Building the enabling environment that will drive the billions of dollars of private sector investment needed for future power projects in Nigeria. (iv) From January 2012, state governments in Nigeria had the rights to generate and distribute electricity power in their domain.

This was made possible by the new set of regulations by the Nigerian Electricity Regulatory Commission (NERC) guiding Independent Electricity Distribution Network Operators and Embedded Power Generators.

Embedded Generation is when a power plant is built in a particular locality and not connected to the national grid for transmission. The generated capacity is connected directly to the distribution network.

Prior to this initiative, the Federal Government had held on to the exclusive right of electricity power generation and distribution for commercial purposes apart from some big industries that were given the license to produce limited units for industrial use.

Federal Ministry of Power

Abuja.

Page 137: 2011 Annual Report of Federal Ministry of Power.pdf

136

ACRONYMS

GCFR - Grand Commander Federal Republic

LPFO - Low Pour Fuel Oil

PHCN - Power Holding Company of Nigeria

HEPP - Hydro Electric Power Project

NPPP - Nationwide Independent Power Producers

Project

NERC - Nigeria Electricity Regulatory Commission

OSGF - Office of the Secretary to the Government

Of the Federation

OHCSF - Office of the Head of Civil Service of the

Federation

TCN - Transmission Company of Nigeria

GENCO - Generation Company

CDs - Compact Disk

DVD - Digital Versatile Disk

VCD - Video Compact Disk

GT - Generator

SLM - Service Level Agreement

MMS - Maintenance Management System

OEM - Original Equipment Manufacturer

LC - Letter of Credit

MYTO - Multi-Year Tariff Order

EIA - Environmental Impact Assessment

NIPP - National Integrated Power Project

IPP - Independent Power Producers

NEPP - National Electric Power Policy

EPSR - Electric Power Sector Reform

REA - Rural Electrification Agency