2010seac fall seminar welding white.ppt - · pdf fileif a joint penetration weld is ... 2g:...
TRANSCRIPT
10/19/2010
1
Schedule:Schedule:
7:30-8:15 : Breakfast8:15-8:30 : Introduction8:30-9:30 : Masonry Veneer and Cladding Systems9:30-9:45 : Break9:45-10:45 : Welding Knowledge for Structural Engineers10:45-11:00 : Break11:00-12:00 : Post-Tensioned Slab Foundations in Colorado
Gold Sponsor:p
Silver Sponsor: Bronze Sponsor:
10/19/2010
2
Welding Knowledge for Structural Engineers:
• David Weaver Project ManagerZimmerman Metals, Inc.
Zi
• Curtis Mayes, P.E.Director Preplanning / EngineeringLPR Construction
ZimmermanMetals, Inc.
Introduction to Shop Welding for Structural Engineers
10/19/2010
3
What is Arc Welding?
Lincoln Electric
Arc welding is using an electric arc to melt a base metal and a consumable such that they fuse together as they cool.
Lincoln Electric
Shielded Metal Arc Welding
SMAW (stick)•Most basic
•Slow due to downtime replacing consumables
•Not common for shop weldingp g
•Common for field welding where a small amount of weld is placed.
10/19/2010
4
“Wire Feed”
Flux Core Arc Welding (FCAW)
•With and without gas shielding
•With gas shielding is very common in shop settings.
•Without gas is very common in the field at larger welds.
Gas Metal Arc Welding (GMAW)
•Solid wire with gas shielding
Submerged Arc Welding
SAW
M t t d •More automated process
•Multiple wires feed into the welding zone
•Good for large, long welds
10/19/2010
5
Weld Access
45˚ angle
Account for Mill Tolerances
Flange reinforcing plate
PJP at column flange. Per the book the flange is 5/16” thick, but may
actually be 1/4” thick.
Flange cover plates. Plate on the left has no adjustment for mill
tolerances. Plate on the right could if it is oversized enough. Column baseplate or
cap plate.
10/19/2010
6
Welding Causes Distortion
Thermal Distortion
•The welded zone shrinks as it cools.• Double sided welds are better then single sided.
• Heat from welding can release residual stresses within the base material.
Welding Causes Distortion
Example: Flange Extension Plates
•The upper detail may result in a “pretzel”.
•The lower detail will have less distortion.
10/19/2010
7
Fillet vs. PJP vs. CJPTypically, fillet welds 3/4” or less are more economical then PJP or CJP welds of then PJP or CJP welds of similar effective throat.
PJP welds are more expensive then fillet welds due to man hours to bevel the surfaces.
CJP welds are the most expensive due to beveling the surfaces, back gouging, and inspection.
Thick Material needs to be preheated ($$$)
1/8” thru 3/4” requires no preheat.
Over ¾” thru 1 ½” ‐ preheat to 50˚
Over 1 ½” thru 2 ½” ‐ preheat to 150˚
Over 2 ½” ‐ preheat to 225˚
10/19/2010
8
What does “TYP” really mean?
What does “TYP” really mean?
10/19/2010
9
What does “TYP” really mean?
All around weld symbol
10/19/2010
10
All around weld symbol
Bad Better Best
Bad Better
Show PJP Weld Size on Drawings
If a joint penetration weld is shown without a depth then the shown without a depth then the fabricator must assume that it is
a CJP.
10/19/2010
11
Effective Throat vs. Weld Depth (PJP)The effective throat of PJP welds is dependent upon the welding position upon the welding position and the welding process used.
Therefore, the engineer should show the required effective throat for PJP welds, not the depth of the prep.
Skewed T‐Joints
At skewed T‐joints of less then 80˚ or greater then 100˚ it is best for the engineer to show the effective throat required so the fabricator can choose the most economical weld.
10/19/2010
12
Inspection ‐ FrequencyIBC Table 1704.3 uses terminology of “continuous” and “periodic”.
Section 1702:
•Continuous‐the full‐time observation of work requiring special inspection by an approved special inspector who is present in the area where the work is being performed.
•Periodic‐the part‐time or intermittent b i f k i i i l observation of work requiring special
inspection by an approved special inspector who is present in the area where the work has been or is being performed and at the completion of the work.
AISC –Chapter N
2010 AISC Manual of Steel Construction will include Chapter N.
Draft copy available at www.aisc.org/chapterN
Uses terminology of “observe” and “perform”.
10/19/2010
13
Ultrasonic Testing (UT)
Similar to radar.Similar to radar.
Sends out a pulse of high frequency sound and then senses for those waves to bounce off weld discontinuities back towards the sensor.
Ultrasonic Testing (UT)Sensors are commonly available in 4 different preset angles: 70˚, 60˚, 45˚, and 0˚.
Screen shows operator how much 70˚of the pulse bounces back and how far it traveled. Path of
ultrasonic pulse
Location of minorLocation of minor discontinuity in weld
Distance Pulse Traveled
10/19/2010
14
Magnetic Particle and RadiographicMagnetic Particle
•A magnetic powder is spread across the testing area The area is magnetized
Radiographic
•Essentially X-ray film process.testing area. The area is magnetized, moving the powder into a magnetic field pattern. Proper reading of the pattern can highlight discontinuities or cracks.
•Only detects cracks and discontinuities withing 0.1” of the surface
•Requires access to the back side of testing area to secure testing film or radiation source.
ZimmermanMetals, Inc.
10/19/2010
15
Introduction to Field Welding for Structural Engineers
Priority #1 Safety
W18x46
y y
W18x46
10/19/2010
16
1.Original Drawing
W18x462.Column Changed to Precast
W18x46
3.Typical temporary support selected for cantilevered beam.
4.2 A307 bolts used for support, followed by field welded flange
plates and web clip angles.
10/19/2010
17
Priority #2 Inspect What You Expect
Priority #3Empathy: the action of understanding, being aware
Imagine yourself wearing the Ironworker’s Boots.understanding, being aware
of, being sensitive to, and vicariously experiencing the feelings, thoughts, and experience of another of either the past or present without having the feelings, thoughts and experience
As well as wearing thoughts, and experience
fully communicated in an objectively explicit manner; also : the capacity for this
wearing the face shield.
10/19/2010
18
Priority #4: Position of the weld:
Initially, We Ironworkers learn how to weld on the ground…
Then, the real world sets in.
10/19/2010
19
ht S
ide
Up
Rig
hU
p SSide D
ownOK. We still weld on the ground in gthe field,
but…
10/19/2010
20
AccessAccess
AAccess
10/19/2010
21
Priority #5: Quantity of the weld:Fillet Weld Size Matters:
Fillets Welds: Production = passes5/16” is typical maximum field weld fillet size and optimum weld size.
Bump a 5/16” weld up to 3/8” and it takes almost twice along to install. Fillet Weld Cost Comparison
Load to Resist
Fillet Weld Size
Strength of Weld
Linear Inches of Weld
Required
Number of Passes Required
Total Inches to weld
Prodiction Inches per
hour
Hours to weld
Cost Per Hour
Cost to weld
$ per kip Relative Cost
100.0 kips 1/8 ” 1.9 k/in 53.9” 1 53.9” 60.0”/hr 0.898hrs $ 55.00 $ 49.38 $ 0.49 150% increase over 5/16" size100.0 kips 3/16” 2.8 k/in 35.9” 1 35.9” 60.0”/hr 0.599hrs $ 55.00 $ 32.92 $ 0.33 67% increase over 5/16" size100.0 kips 1/4 ” 3.7 k/in 26.9” 1 26.9” 60.0”/hr 0.449hrs $ 55.00 $ 24.69 $ 0.25 25% increase over 5/16" size100.0 kips 5/16” 4.6 k/in 21.5” 1 21.5” 60.0”/hr 0.359hrs $ 55.00 $ 19.75 $ 0.20 0% increase over 5/16" size100.0 kips 3/8 ” 5.6 k/in 18.0” 2 35.9” 60.0”/hr 0.599hrs $ 55.00 $ 32.92 $ 0.33 67% increase over 5/16" size100.0 kips 7/16” 6.5 k/in 15.4” 2 30.8” 60.0”/hr 0.513hrs $ 55.00 $ 28.22 $ 0.28 43% increase over 5/16" size100.0 kips 1/2 ” 7.4 k/in 13.5” 3 40.4” 60.0”/hr 0.673hrs $ 55.00 $ 37.04 $ 0.37 88% increase over 5/16" size100.0 kips 9/16” 8.4 k/in 12.0” 4 47.9” 60.0”/hr 0.798hrs $ 55.00 $ 43.90 $ 0.44 122% increase over 5/16" size100.0 kips 5/8 ” 9.3 k/in 10.8” 5 53.9” 60.0”/hr 0.898hrs $ 55.00 $ 49.38 $ 0.49 150% increase over 5/16" size100.0 kips 11/16” 10.2 k/in 9.8” 5 49.0” 60.0”/hr 0.816hrs $ 55.00 $ 44.89 $ 0.45 127% increase over 5/16" size100.0 kips 3/4 ” 11.1 k/in 9.0” 6 53.9” 60.0”/hr 0.898hrs $ 55.00 $ 49.38 $ 0.49 150% increase over 5/16" size100.0 kips 13/16” 12.1 k/in 8.3” 7 58.0” 60.0”/hr 0.967hrs $ 55.00 $ 53.18 $ 0.53 169% increase over 5/16" size100.0 kips 7/8 ” 13.0 k/in 7.7” 8 61.6” 60.0”/hr 1.026hrs $ 55.00 $ 56.44 $ 0.56 186% increase over 5/16" size100.0 kips 15/16” 13.9 k/in 7.2” 10 71.8” 60.0”/hr 1.197hrs $ 55.00 $ 65.84 $ 0.66 233% increase over 5/16" size100.0 kips 1” 14.9 k/in 6.7” 11 74.1” 60.0”/hr 1.235hrs $ 55.00 $ 67.90 $ 0.68 244% increase over 5/16" size
Priority #6: Be Specific
Field Weld flags must be specific and intentional
Specs need to address backup bars, runoff tabs, etc…
How much weld is REALLY required? Don’t need any here? Great!
10/19/2010
22
Four Basic Welding Positions1G: Plates horizontal, flat weld
2G: Plates vertical, axis of weld horizontal2G: Plates vertical, axis of weld horizontal
3G: Plates vertical, axis of weld vertical
4G: Plates horizontal, overhead weld
Three Basic Welding Joints1. Fillet
2. Partial Penetration
3. Full Penetration
Three Basic Welding Joints
Two Basic Field Welding Processes
1: SMAW for less welding at a single location1: SMAW for less welding at a single location
2: FCAW for more welding at a single location
There are several other processes available for the field, but they are all
rarely used
10/19/2010
23
Now: Let’s Get to Work
Connection Design
Bolts areBolts are great, but
sometimes weld is better.
10/19/2010
24
AESS welding?
Get a sample and review from the proper distance. Don’t perfect a
Backer Bars?Leave them on if
you can.
Run-off tabs?Don t perfect a finish that can’t be
seen.
Run off tabs? Leave them on if
you can.
Field welding on galvanized material?
Doesn’t that ruin the corrosion protection? Avoid field welding by
Need to fill a rat hole for p g y
design if possible.
If you must do this, avoid the fumes. E6011 is more forgiving for a less
experienced welder. E7018 is OK as long as the machine settings are
correct.
architectural reasons?
Read about tri-axial stresses, then decide.
OK. This talk Is about welding, but don’t
weld if you don’t need to… OK?
STEEL ERECTORSCONSTRUCTION
10/19/2010
25
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
26
STEEL ERECTORSCONSTRUCTION
10/19/2010
27
OK. But this is a really tough weld. Is there
another way?
STEEL ERECTORSCONSTRUCTION
10/19/2010
28
STEEL ERECTORSCONSTRUCTION
10/19/2010
29
STEEL ERECTORSCONSTRUCTION
10/19/2010
30
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
31
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
32
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
33
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
34
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
35
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
36
STEEL ERECTORSCONSTRUCTION
STEEL ERECTORSCONSTRUCTION
10/19/2010
37
Priority #1: SafetyPriority #2: Inspect What You Expect
Priority #3: Be Empathetic to the IronworkerPriority #3: Be Empathetic to the IronworkerPriority #4: Position, Position, Position
Priority #5: QuantityPriority #6: Be Specific
P i it #7Priority #7:
Get Plenty of Rest
10/19/2010
38
Questions?
Welding Knowledge for Structural Engineers:
• David Weaver Project ManagerZimmerman Metals, Inc.
Zi• Curtis Mayes, P.E.
Director Preplanning / EngineeringLPR Construction
ZimmermanMetals, Inc.