200-foot simple span bridge girder design using nu2000 v1

Upload: anthony-gravagne

Post on 08-Aug-2018

224 views

Category:

Documents


6 download

TRANSCRIPT

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    1/50

    1

    NU2000-200 ft Single Span Example

    Given:

    Span Data

    Overall Girder Length =200 FTDesign Span = 199 FT

    Girder is simply supported

    Bridge Cross Section Data

    Number of girder lines = 6Girder Spacing = 9.00 FT

    Roadway Width= 51.00 FT

    Overall Width = 53.50 FT

    Deck Thickness

    Actual = 7.5 INStructural = 7.0 IN

    Haunch thickness = 1 IN

    Girder Type

    NU 2000, with 150 mm (5.91 in.) web

    Location: Interior

    Dead Load

    Future Wearing Surface = 0.025 KSFBarrier Weight/Barrier Line = 0.27

    KLF

    Live Load

    HL-93 - Design Truck + Design Lane

    Loads

    Girder Concrete

    fc (fci/0.8) KSIfci = to be determined

    wc = normal weight aggregate concrete

    Deck Concrete

    fc = 5.0 KSI

    Prestressing Steel

    Type: 0.6-IN Diameter 270 KSI Low-Relaxation Seven-Wire Strand

    Pull: 75%

    H = 70 % (Relative Humidity)

    Use as many depression points as needed

    for design. Max. 12 strands depressed at any

    one point.

    Reinforcing Steel (Non-Prestressed)

    fy = 60 KSIEs = 29,000 KSI

    Welded Wire Reinforcement

    Use standard reinforcement sizes and

    spacing. Use 75 ksi steel for shearreinforcement

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    2/50

    2

    Proposed design steps:

    (1)Calculate gross section properties, assuming a girder concrete strength of 10 ksi.(2)Calculate live load distribution factors.(3)Calculate moments and shears at 10th points due to various limit state load combinations.

    (4)Approximate number and arrangement of strands based on Service III stress and NCHRPapproximate method. Then use detailed NCHRP 1807 (LRFD 2005) loss method to refine

    the number of strands (use spreadsheet and check by hand).

    (5)Check Strength I with strands calculated in (4), and determine concrete strength at final(use spreadsheet and check by hand).

    (6)Check if the precast section satisfies Strength IV (use spreadsheet and check by hand).(7)Determine concrete strength at release; revise concrete strength at final if needed (use

    spreadsheet and check by hand).(8)Determine the design moment diagram at 10th points and check that it is greater than the

    Mu diagram at the same points.

    (9) Check min. reinforcement limits.

    (10) Design shear reinforcement; at least the critical section must be designed by handcalculation, including longitudinal reinforcement anchorage check.

    (11) Check interface (horizontal) shear.(12) Design and detail the end zone reinforcement (splitting and confining steel).(13) Estimate midspan camber at release and at erection.(14) Estimate live load deflection.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    3/50

    3

    1.1 Section Properties

    1.1.1 Precast Girder

    The LRFD Specs allow the inclusion of transformed strand in the section propertiesfor a prestressed member (Article 5.9.1.4). For initial calculations, the reinforcementamount is not available and contribution of the strand to the section properties is

    neglected.

    Properties of NU2000:

    A = 903.8 IN2

    I = 790,592 IN4

    h = 78.7 IN

    bW = 5.9 IN

    yb = 35.7 IN

    yt = 43.0 IN

    Sb = 790,592 IN4 / 35.7 IN = 22,145 IN3

    St = 790,592 IN4 / 43.0 IN = 18,385 IN3

    1.1.2 Composite Section [spelling error on this figure Transformed

    Girder C.G.35.70"

    Deck C.G.

    83.20"

    108"Effective Width

    72.58"Transformed Width

    Figure 1.1.2-1: Cross Section of Single Girder with Composite Deck

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    4/50

    4

    Effective deck width: (LRFD 4.6.2.6.1)

    One-quarter span length = (199 FT / 4)(12) = 597 IN

    One-half flange width + (12)(deck thickness):

    (48.2 IN) / 2 + (12) (7.0 IN) = 108.1 IN

    Average spacing of adjacent girders = (9 FT) (12) = 108 IN (Controls)

    1000

    )KSI(f140.0)KCF(W

    'c+=

    KCF145.01000

    5140.0Wcd =+=

    KCF150.01000

    10140.0Wcg =+=

    n =cg

    cd

    E

    E=

    5.1

    cg

    cd

    '

    cg

    '

    cd

    W

    W

    f

    f

    =

    5.1

    150.0

    145.0

    10

    5

    = 0.6720

    Transformed deck width = (n) (effective width) = (0.672) (108 IN) = 72.58 IN

    Transformed haunch width = (n) (haunch width) = (0.672) (48.2 IN) = 32.39 IN

    Table 1.1.2-1: Composite section properties.

    Component Transformed

    Areayb A yb A(yb- ybc)

    2 Io Ic

    Girder 903.80 35.70 32,265.66 282,684.28 790,592.00 1,073,276.28Haunch 32.39 79.20 2,565.50 21,586.30 2.70 21,589.00

    Effective

    Deck508.07 83.20 42,271.26 451,627.27 2,074.61 453,701.88

    Total 1,444.26 77,102.43 1,548,567.16

    Table Section Properties Used in Design:

    ybcg = ( A yb) / A =77,102.43/ 1,444.26 = 53.39 IN

    ytcg = h ybc = 78.70 IN - 53.39 IN = 25.31IN

    ytcd = hc ybc = 78.7 IN +1 IN+ 7.0 IN - 53.39 IN = 33.31 IN

    Sbcg = Ic / ybc = 1,548,567.16 IN4 /53.39 IN = 29,004.82IN3

    Stcg = Ic / ytcg = 1,548,567.16 IN4 / 25.31 IN = 61,184.00IN3

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    5/50

    5

    Stcd = (Ic / ytcd) / n = (1,548,567.16 IN4 / 33.31 IN) / (0.6720) = 31,240.98 IN3

    Component ybcg ytcg ytcd Sbcg Stcg Stcd

    Value 53.39 25.31 33.31 29,004.82 61,184.00 31,240.98

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    6/50

    6

    2. Live Load Distribution Factor for a Typical Interior Beam

    Distribution Factors: (LRFD 4.6.2.2.1)

    To use the simplified live load distribution factor formula, the

    following conditions must be met: Width of deck is constant O.K.

    Number of girders, Nb, 4 O.K. (Nb = 6)

    Girders parallel and same stiffness O.K.

    Roadway part of overhang, de, 3.0 FTO.K.

    Curvature < 4o O.K. (Curvature = 0o)

    Bridge Type: k (LRFD Table 4.6.2.2.1-1)

    2.1 Distribution Factor for Moment(2 or more lanes loaded)

    1.0

    3s

    g2.06.0

    tL0.12

    K

    L

    S

    5.9

    S075.0DF

    += (LRFD 4.2.2.2b-1)

    Provided that: 3.5 S 16 S = 9.00 FT O.K.

    4.5 ts 12.0 ts = 7.50 IN O.K.

    20 L < 240 L = 200 FT O.K.

    Nb 4 Nb = 6 O.K.

    Kg = n (I + A eg2) (LRFD 4.6.2.2.1-1)

    n = (1/n for composite section calcs = 1/0.6720) = 1.488

    eg = yt + (ts / 2) = 43 IN + 1 IN +(7 IN / 2) = 47.50 IN

    Kg = 1.488 [790,592 IN4 + (903.8 IN2) (47.50 IN) 2 ] = 4,210,699 IN4

    ( )( )

    1.0

    3

    42.06.0

    IN7FT1990.12

    IN699,210,4

    FT199

    FT0.9

    5.9

    FT0.9075.0DF

    += = 0.689 lanes / girder

    2.2 Distribution Factor for Shear (2 or more lanes loaded)0.2

    35

    S

    12

    S2.0DF

    += (LRFD 4.6.2.2.3a-1)

    Provided that the following condition is met in addition to the conditions specified

    above:

    10,000 Kg ( = 4,210,699) 7,000,000 O.K.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    7/50

    7

    0.2

    35

    FT0.9

    12

    FT0.92.0DF

    += = 0.884 lanes / girder

    Distribution Factor for Bending Moment (DFM):

    For all limit states except Fatigue Limit State, for two or more lanes

    loaded, DFM = 0.689 lanes/beam.

    For one design lane loaded, DFM = 0.450 lanes/beam.

    Therefore, in the case of the two design lanes loaded controls, DFM = 0.689

    lanes/beam.

    Distribution Factor for Shear Force (DFV):

    For two or more lanes loaded, DFV = 0.884 lanes/beam[LRFD Table 4.6.2.2.3a-1].

    For one design lane loaded, DFV = 0.72 lanes/beam.

    Therefore, in the case of two design lanes loaded controls, DFV = 0.884.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    8/50

    8

    3. Moments and Shears

    3.1 Dead Loads

    3.1.1 Girder Dead Load at Release

    The moments for this condition are computed separately from other moments becausethe full length of the girder is used in computing these moments, rather than thedesign span (distance from center-to-center of bearings). The full length is used

    because, when the girder cambers upward in the prestressing bed after release, its

    only points of contact with the bed (and therefore its support locations) will be at theends of the girder.

    Girder Dead Load:

    w = (903.8 IN2/ 144) (0.140+10/1000 KCF) = 0.941 KLF

    Moment at x distance from end of beam due to self weight at relaese time:

    Mgdli = ( )xL2xw

    L = 200 FT (overall girder length)

    Mgdli = 0.941 (x / 2) (200 - x) = 94.1 x - 0.471 x2

    Moment due to self weight during lifting. The lifting points are at 0.1L and 0.9 L.

    w = 0.941 KLF

    188.2 K-FT 188.2 K-FT

    2823.0 K-FT

    0.1L 0.8L 0.1L

    Locations of interest at release conditions:

    1. Transfer point t = 60 db = 60 (0.6 IN) = 36.0 IN = 3.0 FT (LRFD 5.8.2.3)

    2. Depression points, yet to be determined

    3. Midspan

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    9/50

    9

    See Spreadsheet 3.3 for calculation of the moment at 10 th points. See Table 3.1 for a summary.

    3.1.1.2 Girder Dead Load - Final

    For all final stress analysis, bearing-to-bearing span should be used.

    L = 199 FT (bearing to bearing)

    Mgdl = 93.63 x - 0.471 x2

    Vgdl =

    x

    2

    Lw = 93.63 - 0.941 x

    3.1.1.3 Deck Slab Loading

    Deck Thickness = 7.5 IN

    wddl = ((7.5 IN x 108 IN) /144) (0.140+5/1000 KCF) = 0.816 KLF

    L = 199 FT

    Mddl

    = 81.19 x - 0.408 x2

    Vddl = 81.19 - 0.816 x

    3.1.1.4 Haunch Weight

    wncdl = ((1.0 IN x 48.2 IN) /144) (0.145 KCF) = 0.049 KLF

    L = 199 FT

    Mncdl = 4.876 x 0.024 x2

    Vncdl = 4.876 0.049 x

    3.1.1.5 Composite Dead Load - Barriers

    Barriers: (2) (0.27 KLF / barrier) = 0.54 KLF

    wcdl = 0.54 KLF / (6 girders) = 0.09 KLF / girder (LRFD 4.6.2.2.1)

    Mcdl = 8.955 x - 0.045 x2

    Vcdl = 8.955 - 0.09x

    3.1.1.6 Composite Dead Load - Future Wearing Surface

    Future Wearing Surface: (51.00 FT) (0.025 KSF) = 1.275 KLF

    wfws = 1.275 KLF / (6 girders) = 0.213 KLF

    L = 199 FTMcdl = 21.194 x - 0.117 x

    2

    Vcdl = 21.194 - 0.106 x

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    10/50

    10

    3.2 Live load

    Bending Moment at Mid-Span

    Design truck (design tandem should be checked, but this does not govern for relatively longspans).

    Design Truck will govern over Design Tandem for this span.

    8 kips

    14 ft 14 ft

    32 kips 32 kips

    For maximum moment due to truck load at mid-span, position the rear axles 14 ft apart. Themaximum moment occurs when the section being considered is halfway between the resultant ofall three loads and the next point load. Also, the case where the 32 kip center axle load is directly

    over the midspan section should be checked.

    AR

    32 kyyx

    R32 k 8 k

    AR

    FT33.972

    2881432x =

    +=

    FT33.22

    33.914y =

    =

    KIP84.36199

    )33.22/199(72R A =

    +=

    FTK76.292,3)33.233.9(322/19984.36MTruck =+=

    Lane load (distributed load):

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    11/50

    11

    q = 0.64 klf

    RRAA

    KIP68.632

    19964.0R A =

    =

    FTK08.31682/1992/)2/19964.0(2/19968.63MLane ==

    Moment distribution factor for live load 0.689 and impact factor 1.33 for truck load,

    MLL+I = DF [Mlane + 1.33 (Mtruck)] = 0.689(3283.3961.33+3168.081 ) = 5191.6 K-FT

    The shear critical section is 5.70 ft away from the support (see section 10.1.1).1. Truck load:

    The influence line of the mid-span shear force is as follows:

    5.7/199=0.029

    5.7 ft

    0.97

    The layout of the truck load is as follows:

    32k

    R

    32k 8k

    5.7 ft

    ( ) KIP56.66)287.5199(8)147.5199(32)7.5199(32199

    1R =++=

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    12/50

    12

    66.56 K

    34.56K

    2.56 K

    5.44 K

    5.7 ft

    Vtruck= 66.56 KIPS

    3.2.3.2. Lane load

    The layout of the lane load is as follows:

    R

    0.64k/ft

    KIP08.602

    )7.5199(64.0

    199

    1RV

    2

    left =

    ==

    VLL+I = DF [Vlane + 1.33 Vtruck] = 0.896 (1.3366.56+60.08) = 133.3 KIP

    3.3 Applicable Limit States (LRFD Table 3.4.1-1)

    DCQStrengthIVu 5.1: =

    3.3.1 Service I

    This load combination is the general combination for Service Limit State stress

    checks and applies to all conditions other than Service III.

    DC5.1Q:IVStrength u =

    )(8.0)(0.1: IMLLDWDCQIIIService u +++=

    )(0.1)(0.1: IMLLDWDCQIService u +++=

    )(75.15.125.1: IMLLDWDCQIStrength u +++=

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    13/50

    13

    All load factors are equal to 1.0 for this problem.

    For moment at mid-span:

    Acting on the non-composite girder, MSLnc:

    MSLnc = 4,658.1+ 3,768.3 + 269.2 + 240.3 = 8,935.8 K-FT

    Acting on the composite girder, MSLc:MSLc = 534.6 + 1,158.3 + 5,191.5 = 6,884.4 K-FT

    3.3.2 Service III

    This load combination is a special combination for Service Limit State stress checks that

    applies only to tension in prestressed concrete structures with the objective of crack

    control.

    All load factors are equal to 1.0 for this problem, except that the live load is reduced by afactor of 0.8.

    Moments at mid-span:

    Acting on the non-composite girder, MSLnc (same as for Service I).

    Acting on the composite girder, MSLc:

    MSLc = 534.6 + 1158.3 + (0.8)(5,191.5) = 5846.1 K-FT

    3.3.3 Fatigue

    According to LRFD 5.5.3.1, Fatigue need not be checked for concrete deck slabs in multi-

    girder applications. Fatigue of the reinforcement need not be checked for fully

    prestressed components designed to have extreme fiber tensile stress due to Service III LimitState within the tensile stress limit specified in Article 5.9.4.2.2b. Fatigue of concrete is

    checked indirectly by satisfying the compression stress limit of 0.4 'cf for the load

    combination specified in LRFD 5.9.4.2.1.

    3.3.4 Strength I

    This load combination is the general combination for Strength Limit State design.Since the structure is simply supported, the maximum values for the load factors are

    used because they produce the greatest effect (see LRFD Table 3.4.1-2).

    No distinction is made between moments and shears applied to the non-composite orcomposite sections for strength computations. The factored loads are applied to the

    composite section.

    The following load factors apply:

    Dead Load - Component and Attachments 1.25 DC

    Dead Load - Wearing Surface and Utilities 1.50 DW

    Vehicular Live Load and Impact 1.75 LL and IM

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    14/50

    14

    Mu or Vu = 1.25DC + 1.50DW + 1.75(LL + IM)

    For moment at midspan, Mu:

    Mu = (1.25) [4,658.1 + 3,768.3 + 269.2 + 240.3 + 534.6] + (1.50) (1,158.3) + (1.75)

    (5,191.5)

    Mu = 22,660.6 K-FT

    For shear at the critical section for shear, Vu :

    Vu = (1.25) [88.3 + 71.4 + 5.1 + 4.6 + 10.1] +(1.50) (21.9) + (1.75) (133.3)

    Vu = 490.5 KIP

    For moment at the critical section for shear, Mu:

    Mu = (1.25) [518.4 + 419.4 + 30.0 + 26.7 + 59.5] + (1.50) (128.9) + (1.75) (577.8)

    Mu = 2,521.9 K-FT

    3.3.5 Strength IV

    This design limit state checks a precast members strength under its own weight plus the

    weight of all loads applied before composite action takes effect. If this condition is satisfied,

    there is no need to check the compressive stress limit of 0.45 'cf due to effective prestress plus

    dead load.

    The following load factors apply:

    Dead Load - Component and Attachments: DC 1.50

    Moment at mid-span should be determined for self weight, deck slab weight and haunch

    weight, Mu:

    Mu = (1.5) [4658.1 + 4037.4+ 240.3] =13,403.6 K-FT

    The bending moments and shear forces for all required limit states at 10th

    points of the span

    are shown in Tables 3.1 and 3.2:

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    15/50

    15

    Table 3.1 Bending Moments for a Typical Interior Girder

    DF 0.689 moment

    DF 0.884 shear Table of Moments, K-FT

    Location 0 critical 0.1 L 0.2 L 0.3 L 0.4 L 0.5 L 0.6 L 0.7 L

    ft 0 5.70 19.9 39.8 59.7 79.6 99.5 119.4 139.3

    Acting on Non-comp. Section

    Girder, klf 0.941 0 518.4 1676.9 2608.5 3912.8 4471.7 4658.1 4471.7 3912.8

    Deck (Structural) , klf 0.761 0 419.4 1356.6 2411.7 3165.4 3617.6 3768.3 3617.6 3165.4

    Additional Non-composite 0.054 0 30.0 96.9 172.3 226.1 258.4 269.2 258.4 226.1

    haunch, klf 0.049 0 26.7 86.5 153.8 201.8 230.6 240.3 230.6 201.8

    Subtotal: 0 994.5 3216.9 5346.2 7506.0 8578.3 8935.8 8578.3 7506.0

    Acting on Compostie section

    Barrier, KLF 0.108 0 59.5 192.5 342.2 449.1 513.2 534.6 513.2 449.1

    Future wearing Surface 0.234 0 128.9 417.0 741.3 973.0 1112.0 1158.3 1112.0 973.0

    Live Load + Impact 0 577.8 1878.2 3367.8 4414.9 5040.8 5191.5 5040.8 4414.9

    SUBTOTAL-Service I 0 766.2 2487.7 4451.3 5837.0 6666.0 6884.4 6666.0 5837.0

    SUBTOTAL-Service III 0 650.6 2112.0 3777.7 4954.0 5657.9 5846.1 5657.9 4954.0

    Total-Strength I 0 2521.9 8174.0 14116.1 19129.5 21853.8 22660.6 21853.8 19129.5

    Total-Strength IV 0 1491.7 4825.3 8019.4 11259.1 12867.5 13403.6 12867.5 11259.1

    Moments at release, K-FT

    Location 0 transfer 0.1 L 0.2 L 0.3 L 0.4 L 0.5 L 0.6 L 0.7 L

    ft 0 1.50 20 40 60 80 100 120 140

    Girder, KLF 0.941 0 140.1 1693.8 3011.2 3952.2 4516.8 4705.0 4516.8 3952.2

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    16/50

    16

    Table 3.2 Shear Forces for a Typical Interior Girder

    Shear Force, K

    Location 0 critical 0.1 L 0.2 L 0.3 L 0.4 L 0.5 L 0.6 L 0.7 L

    ft 0 5.70 19.9 39.8 59.7 79.6 99.5 119.4 139.3

    Acting on Non-comp. Section

    Girder 0.941 93.6 88.3 74.9 56.2 37.5 18.7 0.0 -18.7 -37.5

    Deck (Structural) 0.761 75.7 71.4 60.6 45.4 30.3 15.1 0.0 -15.1 -30.3

    Additional Non-composite 0.054 5.4 5.1 4.3 3.2 2.2 1.1 0.0 -1.1 -2.2

    haunch 0.049 4.8 4.6 3.9 2.9 1.9 1.0 0.0 -1.0 -1.9

    Subtotal: 179.6 169.3 143.7 107.8 71.8 35.9 0.0 -35.9 -71.8

    Acting on Compostie section

    Barrier 0.108 10.7 10.1 8.6 6.4 4.3 2.1 0.0 -2.1 -4.3

    Future wearing Surface 0.234 23.3 21.9 18.6 14.0 9.3 4.7 0.0 -4.7 -9.3

    Live Load + Impact 138.9 133.3 119.4 101.2 84 68 53.2 -68 -84

    SUBTOTAL-Service I 172.9 165.4 146.6 121.6 97.6 74.8 53.2 -74.8 -97.6

    SUBTOTAL-Service III 145.1 138.7 122.7 101.4 80.8 61.2 42.6 -61.2 -80.8 Total-Strength I 515.9 490.5 427.2 340.8 256.1 173.6 93.1 -173.6 -256.1 Total-Strength IV 320.5 302.1 256.4 192.3 128.2 64.1 0.0 -64.1 -128.2

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    17/50

    17

    4. Total number and arrangement of strands

    4.1 Estimated Number of Strands

    The total number and arrangement of strands was estimated using service III and NCHRP 18-07

    approximate loss method. Refer to attached Excel sheet 4.1 and Tables 4.1 and 4.2. The total

    number of bottom strands can be found = 85-0.6 in. strands: 46 straight strands at the bottomflange, which is the maximum number of strands that the bottom flange can accommodate. The

    rest of the strands will be harped in three groups at 0.2L, 0.3L, and 0.4 L as shown in Figures 4-1

    and 4-2. The strands can be harped using a hold down device or steel pipes attached to theprestressing bed.

    Table 4.1 Prestress loss using NCHRP 18-07 approximate method.Sub-

    Total

    Change Net Change Net Loss

    202.5

    (1) Elastic shortening due to Pi 7.020 -38.1 164.4

    (2) Elastic shortening due to self weight -1.776 9.6 174.0Elastic, Prestress transfer, fpES 5.244 28.5

    (3) Shrinkage 12(1.7-0.01H)(5/(1+f'ci) -7.1 167.0

    (4) Creep 10(fpiApsAg)(1.7-0.01H)(5/(1+f'ci)) -24.3 142.7

    (5) Relaxation, fpR 2.5 -2.5 140.2

    Total long-term, fpLT 33.9

    (6) Elastic due to deck weight Mdecketr-fin/Ibm-tr-fin *n -1.673 7.9 148.0

    (7) Elastic due to superimposed DL (on composite section) MADLecomp-tr/Icomp-tr *n -0.487 2.3 150.3

    Elastic, Deck + SIDL -10.2

    Total Prestress Loss prior to LL, fpT 52.2

    (8) Elastic due to LL MLLecomp-net/Icomp-net *n -7.9

    Total loss including gain due to LL 44.3

    fpsfcgs

    ]I

    e

    A

    1[Af

    reltrgdr

    2

    reltr

    reltrgdr

    pspi

    + cgips fnf =

    reltrgdr

    2 reltrgdr

    I

    eM

    Table 4.2 Bottom fiber stresses (using transformed/net section properties and approximate

    NCHRP 18-07 method).Cause Initial Final

    Pi (transf. section, release) 7.735 7.735

    Mg (transf., release) -2.169 -2.169

    Loss (net section, precast) -1.594

    deck weight (transf., service) -2.039

    SIDL (transf. composite) -0.552

    LL (transf., composite) -1.910

    Net 5.566 -0.528

    Code Limit 4.500 -0.601

    '

    cf19.0

    4.2 Number of Strands Using Detailed NCHRP 18-07 Method

    Use service III and NCHRP 18-07 (LRFD 2005) detailed loss method. For this iterative process

    to be done quickly, the Loss spreadsheet is used. Refer to Spreadsheet 4.2 and Tables 4.3 and

    4.4. The total number of bottom strands can be refined to 82-0.6 in. strands: 46 straight strands at

    the bottom flange and 36 harped strands. To avoid excessive uplift force on the prestressing bed,a maximum of 12 strands will be harped at any point. Thus, the 36 strands will be harped in three

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    18/50

    18

    groups. The drape point locations will be assumed at 0.2L, 0.3L, and 0.4 L as shown in figures 5-1 and 5-2. Further design checks may require altering this arrangement. In addition, 4 straight top

    strands will be used for mild reinforcement support and for control of top cracking at prestress

    release. For the top strands, the tension will be specified at 10 ksi. The effect of the top strandson the total prestress force will be ignored.

    Table 4.3: Prestress loss using NCHRP 18-07 detailed method.Prestress Loss Using NCHRP 18-07 Detailed Method

    Project Name: PCI Handbook Page 2-19 12DT32 member with 208-D1 Strand Pattern

    Designer: MKT Date: 40407

    Prestress Loss (ksi)

    Loading Loss Components

    Combinations

    Change Net Change Net

    0 202.5

    (1) Elastic shortening due to Pi =fpiA ps 6.809 6.809 -37.0 165.5

    (2) Elastic shortening due to self weight -1.786 5.023 9.7 175.2

    Elastic, Prestress transfer, fcgp and fpES 5.023 5.023 -27.3

    (3) Shrinkage between release and deck place fpSR=bid*Ep*Kid -0.149 4.874 -3.6 171.6

    (4) Creep between release and deck place fpCR=ni*fcgp*ybid* -0.565 4.309 -13.7 157.9

    (5) Relaxation between release and deck place (assumption) fpR2 -0.049 4.260 -1.2 156.7

    Total long-term (initial to deck placemnt)id -0.763 4.260 -18.6 -18.6

    (6) Elastic due to deck weight Mdecketr-fin/Ibm-tr-fin*n -1.681 2.579 7.9 164.6

    (7) Elastic due to superimposed DL (on composite sectioMADLecomp-fin/Icomp-fin*n -0.489 2.090 2.3 166.9

    Elastic, Deck + SIDL: Dfcd and DfpED -2.170 2.090 10.2 -8.4

    (8) Shrinkage of beam bet.deck place and final fpSD=bdf*Ep*Kdf -0.406 1.684 -1.9 165.0

    (9) Creep of beam bet.deck place and final, initial loads fpCD1 =fcgp*(ybif-ybid)*Kdf*ni -1.334 0.350 -7.2 157.7

    (10) Creep of beam due to deck and SIDL fpCD2=fcd*ybdf*Kdf*n 1.399 1.749 6.6 164.3

    (11) Relaxation between deck place and final (assumption) fpR3 -0.255 1.494 -1.2 163.1

    (12) Shrinkage of deck 0.134 1.628 0.6 163.7

    Total long-term (deck placemnt to final)df -0.462 1.628 -3.1 -11.5

    (13) Elastic due to LL n*MLLecomp_tr/Icomp_tr -1.693 -0.065 8.0 -3.5

    Total loss including gain due to LL -30.8

    fcgp fps

    ]1

    [2

    reltrgdr

    reltr

    reltrgdr

    pspiI

    e

    AAf

    +cgips fnf =

    reltrgdr

    reltrgdr

    I

    eM

    2

    ( )( )

    bdfdf

    c

    dpc

    cdf

    cddddf

    c

    p

    pSS KI

    ee

    A

    EA

    E

    Ef

    7.01

    1

    7.01+

    +

    +=

    Table 4.4: Bottom fiber stresses (using transformed/net section properties and detailed

    NCHRP 18-07 method).

    Cause Final

    Pi (transf. section, release) 7.503

    Mg (transf., release) -2.180

    Loss (net section, precast) -0.841

    deck weight (transf., service) -2.047SIDL (transf. composite) -0.554

    Loss (net, composite) -0.136

    LL (transf., composite) -1.918

    Net -0.174

    70

    Code Limit -0.601

    '

    cf19.0

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    19/50

    19

    Figure 4-1: Harped strands profile

    Section at (0.5L)End Section (0.0L) Figure 4-2: Pretensioning scheme

    All strands eccentricities are shown in Table 4.5 below:

    Table 4-5: Pretensioning eccentricity at different sectionsShear critical Develop.Leng.

    Strand type 0 L 0.031 L 0.06 L 0.1 L 0.2 L 0.3 L 0.4 L 0.5 L

    12 draped strands 32.2 27.75 23.59 17.85 3.5 3.5 3.5 3.5

    12 draped strands 50.2 45.89 41.86 36.30 22.40 8.5 8.5 8.5

    12 draped strands 68.2 63.96 60.00 54.53 40.85 27.18 13.5 13.5

    46 straight strands 4.09 4.09 4.09 4.09 4.09 4.09 4.09 4.09

    82 Bottom strands 24.33 22.43 20.65 18.20 12.06 8.03 6.03 6.03

    0 . 4 L0 . 3 L

    0 . 2 L

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    20/50

    20

    4.3 Hand Calculation of Prestressed Losses Using Detailed NCHRP 18-07 Method

    4.3.1 Shrinkage Strain

    4.3.1.1 Precast

    First period (from release to Final).

    tsthscpbif kkkkk00048.0S = 1kcp =

    One day steam curing

    038.1735

    )2.3(941064ks =

    =

    0.1)70(0143.000.2kh ==

    588.05.71

    5=

    +=fk

    61.0)588.0)(0.1)(038.1)(1(ksh ==

    ( )( )

    998.0120000)5.7(461

    120000ktd =+

    =

    6

    bif 10x292S=

    Second period (from release to deck placement).

    tsthscpbid kkkkk00048.0S = 1kcp =

    One day steam curing

    038.1735

    )2.3(941064ks =

    =

    0.1)70(0143.000.2kh == 588.0

    5.71

    5kst =

    +=

    61.0)588.0)(0.1)(038.1)(1(ksh == ( )

    ( )656.0

    160)5.7(461

    160=

    +

    =tdk

    6

    bid 10x192S=

    bidbifbdf SSS = 6

    bdf 10x100S=

    4.3.1.2 Deck Slab

    tsthscpI-di kkkkk00048.0S = 1kcp =

    for 7 days moisture curing

    0.1735

    )2/0.7(941064ks =

    =

    0.1)70(0143.000.2kh ==

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    21/50

    21

    833.051

    5kst =

    +=

    ( )( )

    998.06020000)5.7(461

    6020000ktd =

    +

    =

    at final

    6

    ddf 10x399)998.0)(833.0)(0.1)(0.1)(0.1(00048.0S==

    4.3.2 Creep Coefficient

    4.3.2.1 Precast

    First period (from release to final).

    tlahsst kkkkk9.1bif =

    955.0735

    )85.3(941064ks =

    =

    588.0

    5.71

    5=

    +

    =fk

    0.1)70(008.056.1 ==hck

    ( ) 0.1118.0 == lala tk ( )

    ( )998.0

    120000)5.7(461

    120000ktd =

    +

    =

    065.1)998.0)(0.1)(0.1)(588.0)(955.0(9.1bif ==

    Second period (release to deck placement).

    tlahsst kkkkk9.1bid =

    955.0735

    )85.3(941064ks =

    =

    588.05.71

    5=

    +=fk

    0.1)70(008.056.1 ==hck ( ) ( ) 0.11 118.0118.0 === lala tk

    ( )

    ( )656.0

    160)5.7(461

    160=

    +

    =tdk

    700.0)656.0)(0.1)(0.1)(588.0)(955.0(9.1bid ==

    Third period (deck placement to final).

    tlahsst kkkkk9.1bdf =

    955.0735

    )85.3(941064ks =

    =

    588.05.71

    5=

    +=fk

    0.1)70(008.056.1 ==hck

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    22/50

    22

    ( ) ( ) 617.060 118.0118.0 === lala tk ( )

    ( )998.0

    602000)5.7(461

    6020000=

    +

    =tdk

    657.0)998.0)(617.0)(0.1)(588.0)(955.0(9.1bdf ==

    4.3.2.2 Deck Slab

    tlahsfddf kkkkk9.1=

    0.1735

    )5.3(941064=

    =sk

    0.1)5(8.01

    5=

    +=fk

    0.1)70(008.056.1 ==hck ( ) ( ) 0.11 118.0118.0 === lala tk

    ( )( )

    998.012000)5(461

    120000 =+

    =tdk

    877.1)998.0)(0.1)(0.1)(0.1)(0.1(9.1bid ==

    4.3.3 Transformed Section Properties

    Transformed Section Properties at Release ( non-composite ):26.982)1( inAnAA pigti =+=

    inA

    AYYbi 32.33==

    4412,854 inI ti =

    Transformed Section Properties at stage II (composite):212.510,1)1( inAnAA pigt =+=

    232.51 inA

    AYYb ==

    4755,666,1 inI t =

    4.3.4 Losses at the first period

    Strand stress at service from the spreadsheet:

    ksi0.17286.02.16.62.79.13.29.72.17.136.33.275.202fs +++++=

    Bottom fiber stress at Service III:

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    23/50

    23

    =cf ti

    bg

    ti

    bp

    ti

    iI

    y*M

    I

    ye

    A

    1P

    +

    +

    i_net

    i_net_bi_net_p

    i_net

    II

    ye

    A

    1P

    [Due to time dependent losses from release to deck placement]

    tr

    trd

    I

    y*M+

    TrCom

    Tr_ComSIDL

    I

    y*M

    +

    +

    Tr_net

    Tr_net_bTr_net_p

    Tr_net

    III

    ye

    A

    1P

    [Due to time dependent losses from deck placement to final]

    Tr_Com

    Tr_ComLL

    I

    y*M

    +

    = 7.503-2.180-0.841-2.047-0.554-0.136-1.918= -0.174 KSI

    KSI601.0f19.0KSI174.0 'c ==

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    24/50

    24

    5. Strength I at Mid-Span

    The reinforcement bars in the deck slab and the top flange strands are ignored in thesecalculations. The I-beam top flange is assumed to be a rectangle of equal area to the actual flange

    area. The depth can found to be 3.93 in for the actual width of 48.2 in. of the NU I girder top

    flange shape. The strain-compatibility approach was used to calculate the mid- span section

    strength. See Table 5.1 for the results. The last cycle of the iterative analysis will be redone bylong hand below to explain the spreadsheet analysis and to check its results (See attached Excel

    Spreadsheet 5.1 for Strength I).

    Straight strands As1=460.217=9.982 IN2 y1 = 81.60 IN from top of slab

    Harped Strands As2=360.217=7.812 IN2

    y2 = 78.20 IN from top of slab

    From the spreadsheet, the value of the compression block depth, is a = 11.06 IN This indicates

    that the compression block is within the top flange of the beam: 11.07-7 (slab) 1 (haunch) =

    3.07 IN.

    According to the average beta formula source PCI BDM and LRFD,

    Deck 1 = 0.85-0.05(fc-4) = 0.85-0.05(5-4) = 0.8Girder 1 = 0.85-0.05(fc-4) = 0.85-0.05(10-4) = 0.65

    Average 1 = (Ac1fc11+ Ac2fc22)/ (Ac1fc1 + Ac2fc2) = 0.76

    c = a/ 1 = 14.55 IN

    The compression force in the deck slab and moment due to force at the top of the deck slab is

    Fc1 = 0.855(9127) = 3213.00 KIPMc1 = 3213.00 7/2 = 11245.50 K-IN

    Similarly, the compression force in the haunch and moment due to this force at the top fiber ofthe deck slab are 204.85 kips and 1536.38 kip-in; the compression force in the beam top flangeand moment due to this force at the top of the deck slab are 1259.17 kips, and 12008.27 kip- in.

    The spreadsheet is able to treat each strand layer individually. For convenience in the handcalculation check, we will assume two groups of strands, the straight strands and the harped

    strands, clustered at two points.

    Straight strands strain: 020.028500

    1721

    c

    82.61003.01 =+

    =

    Using the Power formula in PCI Bridge Design Manual Section 8.2.2.5,

    ( ){ }270

    4.1121

    27613887f36.7/136.7

    ps

    psps

    +

    +=

    fps1 = 263.21 KSI

    Fs1 = 263.219.982=2627.36 kipsMoment at top face Ms1 = 2627.36 82.61 = 217045.84 kip-IN

    Tension force in the harped strands and moment due to this force at the top of the deck slab is

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    25/50

    25

    Straight strands strain: 019.028500

    1721

    c

    2.78003.01 =+

    =

    Using Power formula fps2 = 262.37 KSI

    Fs1 = 262.37 7.182=2,049.66 kips

    Ms1 = 2,049.66 78.2 = 160,283.4 K-IN

    Sum of forces = 2,049.66 +2627.36 -204.85 -1259.17-3213.00 = 0.0

    Since strain in the extreme bottom stand layer is larger than 0.005, the resistance factor =1.

    Sum of M =1 (160,283.4 +217,045.84 -12,008.27 -1536.38 -

    11245.50)/12=29378.3 K-FT > Mu = 22393.3 K-FTThus the provided strength is about 30% larger than the required strength. This check will not

    need to be revisited unless the final number of strands has been extremely reduced. This also

    tells us that the assumed final concrete strength of 10 KSI may be too high. The Strength IV

    check should confirm this. We also have an option to try to use a lower deck strength at thistime.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    26/50

    26

    Flexural Strength Using Strain Compatibity and Mast's Variable 0.75 to 1.0

    cu

    c=

    a

    Sum of

    forces

    ANSWER:

    Mn kip-in

    kip*ft

    Units in kips and inches

    Concrete Layers f'c Width, W Thick., T Depth, dc 1 Tupper Tlower Revised T Beta1calcuation

    1 5.000 108.000 7.000 3.500 0.800 0.000 7.000 7.000 3024 3780

    2 5.000 48.200 1.000 7.500 0.800 7.000 8.000 1.000 192.8 241

    3 10.000 48.200 3.930 9.531 0.650 8.000 11.930 3.061 959.123074 1475.57396

    4 10.000 5.910 74.770 11.930 0.650 11.930 86.700 0.000 0 0

    5 86.700 0.850 86.700 86.700 0.000 0 06 86.700 0.850 86.700 86.700 0.000 0 0

    7 86.700 0.850 86.700 86.700 0.000 0 0

    Steel Layers Area Asi 4175.923074 5496.57396

    Steel Layers Area Asi Grade Effective Pr Depth dsi Es Q fpy R K so

    Gr 270 1 9.962 270 172 82.610 28500 0.031 243 7.36 1.043 0.0060

    Gr 270 2 7.812 270 172 78.200 28500 0.031 243 7.36 1.043 0.0060

    Sum of M MAXIMUM :

    W1

    W2

    W3

    W4

    T2T2 Lower

    T2Upper 1

    2

    3

    4

    dsi

    As i

    Table 5.1: Strength I Calculation at Mid-Span Section

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    27/50

    27

    6. Strength IV Limit State

    This limit state is used to check the capacity of the precast section only. The Excel strain-

    compatibility program was used to design the section. The capacity of the precast section

    without any mild reinforcement in the compression zone was estimated at:

    FTKIPMn = 0.12314 against the demand of :

    FTKIPMu = 6.13403 (from table 3-1)

    The mild reinforcement was provided in the top flange to obtain the adequate moment capacity.8 # 9 was used to satisfy this limit state. This reinforcement is extended to the 0.4 L. The 6 # 9

    are extended to the 0.3 L.

    The section at point 0.4L with 6 # 9 in the top flange has capacity of

    FTKIPMn

    = 0.12922 > FTKIPMu = 5.12867 . OK

    The section at 0.3L without any top reinforcement has a capacity of

    FTKIPMn

    = 0.11774 > FTKIPMu = 51.11259 . OK

    For brevity, the hand calculation for the last iteration only is shown below (mid-span).

    '

    cf =10,000 psi 1 =0.65

    c = 55.34 IN

    a = 1c = 0.65(55.34) = 35.97 IN

    +

    =

    p

    pepps

    Ef

    cd 1003.0

    We can combine prestressing strand into the clusters:

    1. 46 straight strands

    INdp 61.7409.47.78 ==

    INxps310187.7

    28500

    0.1721

    34.55

    61.74003.0 =

    +

    =

    2. 12 draped strands- First Cluster

    INdp 2.755.37.78 ==

    INxps310219.7

    28500

    0.1721

    34.55

    2.75003.0

    =

    +

    =

    3. 12 draped strands- Second Cluster

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    28/50

    28

    INdp 2.705.87.78 ==

    INxps310948.6

    28500

    0.1721

    34.55

    2.70003.0 =

    +

    =

    4. 12 draped strandsThird Cluster

    INdp 2.655.137.78 ==

    INxps310678.6

    28500

    0.1721

    34.55

    2.65003.0 =

    +

    =

    5. 4 partially tensioned straight strands in the top flange

    INdp 0.2=

    INxps310541.2

    28500

    10

    34.55

    234.55003.0 =

    =

    Strain in compression steel is found from the ratio:

    d = 2.0 IN

    INxs3' 10892.2

    34.55

    234.55003.0 =

    =

    KSIfEf ysss 60==

    KSIfKSIxf ys 6087.83)29000(10892.23 ===

    Thus, take KSIfs 60= .

    Find the stress of the prestressing strands using the Power formula:

    ( )( )KSIf

    ps

    psps 270

    4.1121

    613,27887

    36.7

    136.7

    +

    +=

    1. 46 Straight strands

    ( )( )KSI

    x

    xfps 80.199

    )10187.7(4.1121

    613,2788710187.7

    36.7

    136.73

    3 =

    +

    +=

    2. 12 Draped strands- First Cluster

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    29/50

    29

    ( )( )KSI

    x

    xfps 54.200

    )10219.7(4.1121

    613,2788710219.7

    36.7

    136.73

    3 =

    +

    +=

    3. 12 Draped strands- Second Cluster

    ( )( )KSI

    x

    xfps 14.194

    )10948.6(4.1121

    613,2788710948.6

    36.7

    136.73

    3 =

    +

    +=

    4. 12 Draped strands Third Cluster

    ( )( )KSI

    x

    xfps 48.187

    )10678.6(4.1121

    613,2788710678.6

    36.7

    136.73

    3 =

    +

    +=

    5. 4 Partially tensioned straight strands

    ( )( )KSI

    x

    xfps 41.72

    )10541.2(4.1121

    613,2788710541.2

    36.7

    136.73

    3 =

    +

    +=

    Assume the compression flange is divided into separate sections.

    The rectangular shape was used to substitute the trapezoidal form of the top flange. The width of

    the rectangular shape b is as follows:

    b = (48.2 + 5.9)/2=27.05 IN

    Compression forces:

    KIPAfC cc 8.1048)10(56.2)2.48(85.085.0'

    1 ===

    KIPAfC cc 0.407)10(77.1)05.27(85.085.0'

    2 ===

    KIPAfC cc 8.1586)10)(77.156.297.35)(9.5(85.085.0'

    3 ===

    KIPffAC cpsPS 5.55))10(85.041.72)(217.0(4)85.0('

    4 ===

    KIPffAC csS 2.366))10(85.00.60)(79.0(9)85.0('

    5 ===

    Tension forces:

    KIPfAT psps 4.19948.199)217.0(461 ===

    KIPfAT psps 2.52254.200)217.0(122 ===

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    30/50

    30

    KIPfAT psps 5.50514.194)217.0(123 ===

    KIPfAT psps 2.48848.187)217.0(123 ===

    To derive the moment capacity of the section, we can take the sum of the moments around any

    point.

    Summing the moments around the bottom of the compression block:

    jcj

    j

    cscsspscpspstop

    psipsipsi

    i

    n yAfyffAyffAyfAM ==

    +++=3

    1

    '''4

    1

    85.0)85.0()85.0( =

    =1,994.4(38.64) + 522.2(39.23) + 505.5(34.23) + 488.3(29.23) + 1,048.8(34.69)

    + 407.0(32.53) + 1,586.8(15.82) + (55.5+366.2)33.97 =

    =77,063.6 + 20,485.9 +17,303.3 + 14,273.0 + 36,382.9 + 13,239.7 + 25,103.2 + 14,325 =

    218,176.7 KIP*IN = 18,181.4 KIP*FT

    The resistance factor shall be taken according to LRFD 5.5.4.1.

    For flexure and tension of prestressed concrete, it is equal to 1.

    For the unified design method, the following formula for calculation will be used:

    00.13/)25075.1(75.0 += extreme

    Proposed for LRFD by Seguirant et al. (PCI Journal 2004):

    INxextreme310158.11

    34.55

    27.78003.0 =

    =

    68.03/)10158.1(25075.1( 3 =+= x Thus take 75.0=

    0.636,13)4.181,18(75.0 ==nM KIP-FT

    From Table 3-1, the factored moment for Strength IV is equal to:

    6.403,13=uM KIP-FT OK

    The Excel program treats each layer of strands individually and provides more accurate results.

    Refer to Figure 6-2 and the attached Excel program for Strength IV, cell M17.

    Its output for INKIPMn = 7.505,13 , which is greater than INKIPMu = 6.403,13

    The precast section has a sufficient capacity to resist the ultimate load during the construction

    stages.

    OK

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    31/50

    31

    Flexural Strength Using Strain Compatibity and Mast's Variable = = = = 0.75 to 1.0))))

    c=

    a

    Sum of

    forces

    Units in kips and inches ANSWE

    kip*ft

    Concrete Layers f'c Width, W Thick., T Depth, dc 1 Tupper Tlower Revised T Beta1calcuation

    1 10.000 48.200 2.560 1.280 0.650 0.000 2.560 2.560 802.048 123

    2 10.000 27.050 1.770 3.445 0.650 2.560 4.330 1.770 311.21025 4783 10.000 5.900 74.370 20.152 0.650 4.330 78.700 31.643 1213.5186 1866

    Total: 78.700 2330.214 3584

    Steel Layers Area Asi Grade Effective Pre Depth dsi Es Q fpy R K eso Grade 60 Bars 1 7.11 60 0.0 2.000 29000 0 60 100 1.096

    Gr 270 1 3.472 270 172 76.700 28500 0.031 243.00 7.36 1.043 0

    Gr 270 2 3.472 270 172 74.700 28500 0.031 243 7.36 1.043 0Gr 270 3 2.17 270 172 72.700 28500 0.031 243 7.36 1.043 0Gr 270 4 0.868 270 172 70.700 28500 0.031 243 7.36 1.043 0

    5 0.868 270 10 2.000 28500 0.031 243 7.36 1.043 06 2.604 270 172 75.200 28500 0.031 243 7.36 1.043 07 2.604 270 172 70.200 28500 0.031 243 7.36 1.043 08 2.604 270 172 65.200 28500 0.031 243 7.36 1.043 0

    W1

    W2

    W3

    W4

    T2T2Lower

    T2Upper 1

    2

    3

    4

    dsi

    Asi

    Figure 6.1: Strength IV Calculations for Mid-span

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    32/50

    32

    7. Required Concrete Strength at Release

    Because of the extreme length of this beam, it is necessary to set the lifting points some distance

    away from the beams ends to help resist buckling of the top flange. We will assume that a careful

    lifting analysis has resulted in identifying the lifting points at 20 feet from each end.

    Based on NDOR Policy and January-February 2001 PCI paper by Tadros et al., Strength Design

    of Pretensioned Flexural Concrete Members at Prestress Transfer, the prestressed member canbe treated as a reinforced concreted column subjected to moment combined with axial

    compression force equal to the force in the prestressing steel just before prestress transfer.

    Therefore, we can solve for the neutral axis location c and 'cif by using the equilibrium

    equations.

    Asi

    ysi

    b j

    j=2

    j=1

    j=3j=4

    j=5

    j=6

    j=8

    j=9

    j=7

    d c jTj

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    33/50

    33

    Table 7.1 Excel program for calculating'

    cif

    Directions:

    1 Input Output

    2 Sign convention: compressive stress

    in concrete and tensile stress in steelare considered positive. Prestress force

    is always positive. Moment in the same

    sense as prestress force moment is negtive.

    3 Units in kips and inches

    4 Make sure the compression fibre.

    dc & ys based on compressed concrete edge

    5 Functions are used below

    Output f'c Top Steel Stress

    8.468 -14.28

    MExt

    -35.2875 1.15 0.75 1.15 0.003

    CONCRETE LAYERS

    Width , b Thick ., T Sum of T Compr . T Depth, dc

    1 38.4 5.3 5.3 5.3 2.65 203.52 1464.896 3881.975

    2 22.15 5.5 10.8 5.5 8.05 121.825 876.872 7058.819

    3 5.9 63.59 74.39 49.24668 35.42334 290.5554 2091.36 74082.95

    4 27.05 1.75 76.14 0 0 0 0 048.2 2.56 78.7 0 0 0 0 0

    78.7 4433.128 85023.74

    STEEL LAYERSInitial Prest fpi Depth ys Stress Grade

    Gr 270 1 9.982 202.5 4.09 28500 -0.002867 -81.71194 1 2355.611 9634.449 270 243 1.04 0.031 7.36

    2 7.812 202.5 36.3 28500 -0.001821 -51.9032 1 2076.387 75372.86 270 243 1.04 0.031 7.363 0.868 10 76.95 28500 -0.000501 -14.28047 0 0.913884 70.32338 270 243 1.04 0.031 7.36

    4432.912 85077.63

    0.65 92.38 60.05 0.2158243 0.215824

    STRENGTH DESIGN PROGRAM FOR PRESTRESS TRANSFER

    DATA FOR CONTROLING

    cA cMcF

    c

    m p

    a

    K Q R

    F M

    sEsA s sf sF sMiw pyf

    cu

    The equations that were used in the analysis are as follows:

    1. Strain calculation:

    =

    cy1003.0 sisi

    2. Force equilibrium:

    ==

    +

    +=

    0way

    1way0wf85.0ffAAf85.0F

    isi

    isi

    i

    icsi

    p

    sisi

    j

    cjc

    3. Moment equilibrium:

    ==

    +

    +=

    0way

    1way0Mywf85.0ffAyAf85.0M

    isi

    isim

    i

    siicsi

    p

    sisi

    j

    cjcjc

    4. Power formula to get strand stress:

    +

    +=

    R/1R

    py

    ssi

    ssisi

    kf

    E1

    Q1QEf

    By solving the two equilibrium equations, the two variables c and 'cif can be obtained. The

    analysis can be done by trying c and 'cif and checking the equilibrium equations.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    34/50

    34

    The following table shows the results for several critical sections.

    Table 7.2: Prestress Member Strength at Release

    Sections Moment (Kips-IN) fci (KSI.) Top fiber stress (KSI.)

    Transfer length 60d=0.015L 3336.786 7.318 -25.36

    0.1L 20325.6 7.449 -24.08

    0.2L 36134.4 7.712 -20.09

    0.3L 47426.4 8.159 -13.06

    0.4L 54201.6 7.456 -20.85

    lifting point 0.1L -50.8 8.469 -14.27

    Max. 'cif 8.469

    Note that prestress loss calculation needs to be redone using 8.5 KSI for concrete strength atrelease.

    Note:

    The following is the check by hand at 0.1L span and the last trial of the analysis.c= 92.38 IN., fci = 8.468 ksi

    = 0.85-0.05(fc-4) = 0.85-0.05(8.468 -4) = 0.7

    a = c = 60.91 IN.Divide NU2000 into 5 layers:

    Table 7.3: Concrete layers

    Concrete Layer Width Thickness

    1 38.4 5.3

    2 22.15 5.5

    3 5.9 63.59

    4 27.05 1.75

    5 48.2 2.56

    The force at each concrete layer, and the corresponding bending moment at the edge of thebottom flange for the final trial, are as follows:

    1. Concrete layer1Fc1 = 0.858.468 ( 38.45.3)= 1464.896 KipsMc1 = 1464.896 5.3/2 = 3881.975 Kips-IN

    2. Concrete layer2Fc2 = 0.858.468 ( 22.155.5) = 876.872 Kips

    Mc2 = 876.872(5.5/2+5.3) = 7058.819 Kips-IN

    3. Concrete layer 3Fc3 = 0.858.468 ( 5.963.59) = 2091.36 Kips

    Mc3 = 2091.36 [(60.91-5.3-5.5)/2+5.3+5.5] = 74082.95 Kips-IN

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    35/50

    35

    4. Concrete layer 4Fc4 = 0 Kips

    Mc4 = 0 Kips-IN

    5. Concrete layer 5

    Fc5 = 0 Kips

    Mc5 = 0 Kips-IN

    Adding them together, F = 1464.896 +876.872 +2091.36 = 4433.128 Kips

    M = 3881.975+7058.819+74082.95=85023.74 Kips-IN

    Use

    =

    c

    y1003.0 sisi

    Top steel:

    00287.097.86

    09.41003.0 1s =

    =

    KS-81.71

    27004.1

    2850000287.01

    031.01031.02850000287.0

    kf

    E1

    Q1QEf

    36.7/136.7

    R/1R

    py

    ssi

    s1s1s =

    +

    +=

    +

    +=

    If the strands are within the compression block height, the compression force of the concreteshould be 0.85fc (Ac-As)=0.85 fcAc-0.85 fc As.

    0.85fcAs is considered when we calculate force of strands in order to avoid the calculation of

    centroid of the concrete area.

    externaleriorint FF =

    pips

    p

    sc fA

    FF =

    pips

    p

    sisscc fA

    fA)AA(f85.0 =

    Rearranging the items in the equation, we get

    ==

    ++=

    0way

    1way0wf85.0f

    fAAfF

    isi

    isi

    iicsi

    p

    sisij

    cjc

    Hence, Fs=9.982(-81.71+1.15/0.75202.5+0.858.468) = 2355.611 Kips.

    Ms = 2355.611 4.09=9634.45 Kips-IN

    The force calculations of the other strands are the same way. Therefore the total force and

    moment of strands are:

    Kips4432.90.9142076.42355.61Fs =++=

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    36/50

    36

    IN-K85077.6370.3275372.869634.45Ms =++= 04432.9-4433.128FF sc =

    0)-35.2875(0.75

    1.15-85077.63-85023.74M

    MM ext

    msc =

    Thus, the assumptions of fci

    and the neutral axis location c are OK.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    37/50

    37

    8. Design moment diagram nM and factored moment Mu at 10th

    Points

    The flexural moment capacities were estimated at 10th

    points of the span. For the end section, themoment capacity was based on 8 bottom strands bent in the end diaphragm. The embedment of

    those strands was assumed to be equal to 36 inches, which allowed us to develop puf8.0 .

    The moment capacity of the section located at the distance equal to the development length wasalso estimated. The development length of prestressing strands was calculated using the formula:

    bpepsd dffkL )3

    2( = ( LRFD 5.11.4.2-1)

    where k= 1.6 for precast , prestressed beams

    and KSIfps 21.263= , see section 5.

    FTINLd 88.116.1426.0)1723

    221.263(6.1 ===

    The appropriate eccentricities of the strands were used to estimate the capacity of the sections at

    different points of the span (see Table 4-5). The strain-compatibility approach was used for thesecalculations. (See attached files)

    0

    5000

    10000

    15000

    20000

    25000

    30000

    0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

    Girder Sections X/L

    BendingMoment(K-Ft)

    Mu

    Mn

    Figure 8.1: Design moment diagram and the factored moment along the girder line

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    38/50

    38

    9. Minimum Reinforcement Calculations

    nM the lesser of 1.2 crM or 1.33 uM (LRFD 5.7.3.3.2)

    Compute Mcr using Std. Specs Article 9.18.2.1

    ( ) rcbcnc/dcpercr fS1SSMSffM += (LRFD Eq. 5.7.3.3.2-1)where

    cr ff = 37.0 = KSI00.1037.0 = 1.170 KSI (LRFD revision 2004)

    pef = compressive stress in concrete due to effective prestress forces only (after

    losses) at the extreme fiber of the section where tensile stress is caused by externallyapplied loads.

    Prestressing force is KIPP 6.30600.172)217.0(82 ==

    pef = 7.35

    592,790

    )03.67.35(6.3060

    8.903

    6.3060 +=+

    nc

    nc

    y

    I

    Pe

    A

    P= 7.487 KSI

    ncdM / = the non-composite dead load moment

    ncdM / = 8,935.8 K-FT (Refer to Table 4-1)

    cS = bcgS = composite section modulus for the tension face

    bS = non-composite section modulus for the tension face

    ( )( ) ( )

    += 1

    145,22

    004,29)12(935,8004,29487.7170.1

    3

    33

    IN

    INFTKINKSIKSIMcr

    = 251,087.6 33,212.4 = 217,875.2 KIP-IN = 18,156.3KIP FT. CONTROLS

    rcfS = 29,004(0.759) = 22,014.0 KIP-FT

    1.2 Mcr = 1.2 (18,156.3) = 21,787.5 K-FT GOVERNS since 1.2 Mcr< 1.33 Mu

    1.33 Mu = 1.33 (22,660.6) = 30,138.6 K-FT

    Moment capacity of the composite section at mid-span is:

    FTKIPMn = 5.728,29

    (See attached Excel program Strength I mid-span, cell M17)

    nM = 29,728.5 K-FT > 1.2Mcr = 21,787.5 K-FT 0.K

    The requirement of minimum reinforcement has been met.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    39/50

    39

    10. Shear Design

    10.1 Transverse Shear Reinforcement

    In this example, the girder will be designed for vertical shear at the critical section for shear.In a full design, other sections along the length of the girder would have to be designed as

    well.

    10.1.1 Critical Section for Shear

    Critical section for shear is located at distance dv from the support:

    dv = Effective shear depth (LRFD revision 2004)

    = Distance between the resultants of tensile and compressive forces

    The depth of the compression block, a, was computed in determining the moment

    capacity of the section (see Section 3.1.4.5). You can also use the output of Excelprogram Strength I, Strain-Compatibility Approach AASHTO LRFD @ critical

    section (cell M8).

    ( )2

    [email protected]

    ationcriticalgchh

    add fgev +== = (78.7 + 7.0 + 1 -22.19) - (10.05/2)

    = 59.49 IN

    But dv need not be taken less than the greater of (LRFD 5.8.2.7)

    0.9 de = (0.9) (78.7 + 7 + 1 22.19) = (0.9) (64.51) = 58.06 IN

    0.72 h = (0.72) (78.7 + 7 + 1) = 62.42 IN GOVERNS

    Therefore, use dv = 62.42 IN.

    The critical section for shear is then

    0.50 FT + 62.42 IN / 12 = 5.70 FT from centerline of support.

    At the critical section for shear, Vu = 490.5 KIPS.

    10.1.2 Component of Shear Resistance from Prestress, Vp

    Pf= 82 (0.217)172.0 = 3060.6 KIP

    The angle of the center of gravity of the strand profile with respect to horizontal is

    = tan-1 [(eCL - eend) / (distance to depression point)]

    = tan-1 [((24.33 IN 18.20 IN) / 12) / (0.1(200)) FT] = 1.463o

    Vp = Pfsin (1.463o) = (3060.6 KIP) [sin (1.463o)] = 78.2 KIPS

    10.1.3 Governing Equations for Shear

    Vu Vr = Vn (LRFD 5.8.2.1-2)

    = 0.90 for shear (LRFD 5.5.4.2.1)

    Vn = Vc + Vs + Vp (LRFD 5.8.3.3-1)

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    40/50

    40

    Compute maximum shear capacity of the section:

    Vn max = pvvc Vdbf25.0 + (LRFD 5.8.3.3-2)

    Vn max = (0.25) (10.00 KSI) (5.9 IN) (62.42 IN) + 78.2 KIP = 998.9 KIPS

    Vn max = (0.90) (985.1) = 998.9 KIPS > Vu = 485.0 KIPS O.K.

    10.1.4 Concrete Contribution to Shear Resistance, Vc

    vvcc dbf.V = 03160 (LRFD 5.8.3.3-3)

    To use this equation, the quantity must be determined. This quantity is a factor that

    represents the efficiency of shear transfer by concrete. Note that ( )KSIf0316.0 c =

    ( )PSIf0.1 c , so a value of 2 would provide a concrete contribution similar to the

    familiar simplified value of ( )PSIf2V cc = bd.

    To obtain , the quantitiescf

    v

    and X are needed, where

    cf

    v

    is a relative shear stress

    and X is the largest longitudinal strain which occurs within the web of the member.

    ( )

    ( ) ( )IN42.62IN9.59.0

    KIP2.789.0KIP490.5

    db

    VVv

    vv

    pu =

    = = 1.265 KSI (LRFD 5.8.3.4.2-1)

    cf

    v

    = KSI

    KSI

    0.10

    25.1= 0.127

    We can begin iterations using the initially assumed value of in the formula below.

    ( )pspss

    popspuu

    v

    u

    xAEAE

    fAVVNd

    M

    +

    ++

    =2

    cot)(5.05.0

    0.002 (LRFD 5.8.3.4.2-2)

    New Commentary allows us to avoid an iterative process by simplifying the formula

    above to the form of

    ( )pspss

    popspuu

    v

    u

    xAEAE

    fAVVNd

    M

    +

    ++

    =2

    )(5.0

    0.002

    Mu = 2,521.9 K-FT = 30,262.8 K-IN (Summary of Dead and Live Load Effects)

    Moment in this formula is not supposed to be taken less than Vu dv (LRFD C5.8.3.3)

    0.617,30)42.62(5.490 ==vu dV K-IN Controls

    Nu = 0 - no applied axial loads

    fpo = 0.7 (270) = 189.0 KSI (LRFD C5.8.3.4.2)

    Aps = area of prestressing steel on the flexural tension side of the member,

    i.e., the straight strands

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    41/50

    41

    Aps = 46(0.217) = 9.982 IN2

    ( ) ( )( )

    ( ) ( )[ ]982.9500,282

    0.189982.92.785.49042.62

    617,30+

    =x 0.002

    ( ) 974,5681.984

    487,2842

    6.886,14125.490 =

    +=x = - 0.00173

    Because x is negative, use Eq. 5.8.3.4.2-3:

    ( )pspsscc

    popspuu

    v

    u

    xAEAEAE

    fAVVNd

    M

    ++

    ++

    =2

    cot)(5.05.0

    (LRFD 5.8.3.4.2-3)

    or simplify this formula to:

    ( )pspsscc

    popspuuv

    u

    xAEAEAE

    fAVVNd

    M

    ++

    ++

    =2

    )(5.0

    Ac = Area of concrete on flexural tension side

    = Area of girder below h/2 = (78.7+7+1)/2 = 43.35 IN

    = (38.4)(5.3) + (5.5)(38.4+5.9)/2 + (43.35-5.3-5.9)(5.9) = 517.4 IN2

    ( )( )[ ] 932,841,61.984

    487,2844.51760622

    6.18864125.490 =

    +

    +=x = -1.44x10-4

    From Table 5.8.3.4.2-1, with x = -1.44x10-4

    & cf

    v

    = 0.127, find = 3.05 and

    22.21=

    With these values, the concrete contribution, cV , can now be computed.

    ( ) ( ) ( )ININKSIVC 42.629.50.1005.30316.0= = 112.2 KIPS

    Another check was added by AASHTO LRFD revision 2004 to ensure that web concrete does

    not crack (mostly necessary for box girders):

    LDcw VVV +

    From the Summary of Dead and Live Load Effects, we can find:

    KIPVV LD 3.3343.1339.211.103.169 =+++=+

    cwV can be found using ACI formula

    ( )pwpcccw VdbffV ++= 3.05.3

    ' Eq.(11-12)

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    42/50

    42

    where pcf is the resultant compressive stress at the centroid of the composite section due to both

    prestress and moments resisted by the precast member acting alone, and dis a distance from the

    extreme compression fiber to the centroid of prestressed reinforcement or 0.8h , whichever isgreater.

    d= 78.7 + 7 + 1 - 22.19 = 64.51 IN0.8h = (78.7 + 7 + 1)0.8 = 69.36 IN CONTROLS

    ( ) ( )nccnc

    ncd

    ncc

    nc

    pc yyI

    Myy

    I

    Pe

    A

    Pf += / =

    =ncdM / 994.5 KIP-FT = 11934 KIP-IN from Summary of Dead and Live Load Effects

    P = 82(172)0.217 = 3060.6 KIPS

    Section properties can be found in Table 1.1.2-1:

    ( ) ( )7.3539.53592,790

    119347.3539.53

    592,790

    )19.22(6.3060

    8.903

    6.3060+=pcf =

    3.386 -1.520 + 0.267 = 2.133 KSI

    ( ) =++= 2.78)36.69(9.5)133.2(3.01000/10005.3cwV 307.2 + 78.2 = 385.4 KIPS > 334.3 KIPSO.K.

    10.1.5 Required Shear Reinforcement, Vs

    Required Vs = Vu / - Vc Vp = 490.5 / 0.9 112.2 78.2 = 354.6 KIPS

    Assuming vertical stirrups,

    s

    cotdfAV

    vyvs

    = (LRFD C5.8.3.3-1)

    Compute Av on an IN2/FT basis (s = 12 IN):

    =

    cotdf

    V12A

    vy

    sv

    ( )( )

    ( ) ( ) ( )=

    22.21cot42.6275

    354.612

    INKSI

    KIPINA

    v = 0.353 IN2/FT

    Check minimum transverse reinforcement:

    y

    vcv

    f

    sbf0316.0A = (LRFD 5.8.2.5)

    ( ) ( )

    KSI

    ININKSIAv

    75

    1290.500.100316.0= = 0.094 IN2/FT < 0.352 IN2/FT O.K.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    43/50

    43

    Check maximum stirrup spacing: (LRFD 5.8.2.7-2)

    Vu = 490.5 KIP > 0.1 fc bv dv = (0.1) (5.9) (10.00) (62.42) = 368.3 KIPS

    Therefore, maximum WWR spacing is 12 IN.

    For D18 WWR, maximum spacing is

    s = 0.18*2*12/0.352 = 12.27 INUse D18 WWR @ 12 IN

    Av,provd = 0.18(2)12/12 = 0.36 IN2/FT

    The design of the other sections is in the attached spreadsheet.

    10.2 Longitudinal Reinforcement Requirement

    In this example, the longitudinal reinforcement requirement will be checked at the

    critical section for shear. The Specifications require that this requirement be satisfiedat each section of the girder. Therefore, in a full design, other sections along the

    length of the girder would also have to be checked.

    10.2.1 Required Longitudinal Force

    Required Longitudinal Force:

    Treqd =

    +

    +

    cotVV5.0

    VN5.0

    d

    Mps

    uu

    v

    u (LRFD 5.8.3.5-1)

    However, at the inside edge of the bearing at simply-supported ends,

    Treqd =

    cotVV5.0

    Vps

    u

    (LRFD 5.8.3.5)

    whereVs = shear resistance provided by transverse reinforcement, not to exceed Vu /.

    =s

    cotdfA vyv (Use final values from shear design above) (LRFD C5.8.3.3-1)

    =( )( )( ) ( )

    IN

    INKSIIN

    0.12

    22.21cot42.627536.0 2 = 361.7 KIPS

    Treqd = ( ) ( )

    22.21cot2.787.3615.0

    9.0

    5.490= (545.0 180.9 78.2) cot (21.22)

    = (285.9) (2.58) = 736.5 KIPS

    10.2.2 Available Longitudinal Force

    The force to resist Treqd must be supplied by the reinforcement on the flexural tension

    side of the member. In this case, the available reinforcement consists of the straight

    strands. The available force that can be provided by these strands at the critical

    section for shear must be determined considering the lack of full development due tothe proximity to the end of the girder.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    44/50

    44

    The location at which T must be provided is where the failure crack is assumed forthis analysis, which radiates from the inside face of the support and crosses the

    centroid of the straight strands. The angle determined during shear design at thislocation is used here. The inside face of the support is 12 IN from the end of the

    girder.

    Figure 10.1: Assumed failure crack and location where

    crack crosses straight strands.

    The total effective prestress force for the straight strands is

    Pes = Aps fpe = 9.982 IN2 (172.0 KSI) = 1716.9 KIPS.

    The distance from the bottom of the girder to the centroid of these strands is

    dg = c.g. straight strands = 4.09 IN.

    Measured from the end of the girder, the crack crosses the centroid of the straightstrands at

    x = + cotdgb = 12 IN + 4.09 IN (cot 21.22) = 22.53 IN.

    This location is within the transfer length, t , so the available stress is less than the

    effective prestress force for the straight strands. The available prestress force, Tavail,at x is therefore computed assuming a linear variation in stress from the end of the

    girder to the transfer length. The transfer length, t , is 60 db or 36 IN. (LRFD 5.11.4.1.)

    Tavail = Pes ( )tx = 1716.9 KIPS (22.53 IN / 36 IN) = 1,074.1 KIPS.

    Since Tavail = 1074.1 KIP > Treqd = 736.5 KIPS, the straight strands are adequate to

    resist the required longitudinal force at this location, and no additional reinforcement

    is required.

    If the strands had not been adequate to resist the force, additional mild reinforcement

    would have been added to provide the remainder of the required force.

    It is good practice to bend at least 8 strands from the bottom layer of the strands.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    45/50

    45

    11. Interface Shear Reinforcement

    The girder will be designed for interface shear at the initial critical section for shear.

    The width of the shear interface is equal to the width of the top flange of the girder,which is 48.20 IN. Therefore, bv = 48.20 IN.

    Assume that the top surface of the girder is intentionally roughened to an amplitude

    of 0.25 IN and cleaned prior to placement of the deck concrete. The requirement for

    intentional roughening of the top of the girder should be indicated on the plans.

    Compute the factored horizontal shear, Vh:

    Vh = Vu/ de (LRFD C5.8.4.1-1)

    The definition for de given for this equation is the same as dv.

    Therefore use dv as computed above.

    Vh = Vu/ dv = 490.5/ 62.42 = 7.858 KIPS/IN.

    Since Vh Vn and = 0.9,

    Vn reqd = Vh/ = 7.858 / 0.9 = 9.702 KIPS/IN.

    Check limits on Vn:

    Vn 0.2 fc Acv or 0.8 Acv :0.8 Acv is controlling the design

    Acv = area of concrete engaged in shear transfer

    = vb = (48.2 IN) (1.0 IN) = 48.2 IN2

    Use = 1.0 IN to compute Vh on a per inch basis.

    Vn reqd = 7.858 KIPS/IN 0.2 fc Acv = (0.8) (48.2) = 38.56 KIPS / IN. O.K.

    Compute the nominal interface shear resistance, Vn:

    cyvfcvn PfAAcV ++= (LRFD 5.8.4.1-1)

    where

    c = 0.100 KSI and = 1.000 for an intentionally roughened surface (LRFD 5.8.4.2)

    Avf= area of shear reinforcement crossing the shear plane

    Pc = permanent net compressive force normal to the shear plane

    = 0

    Solve for the required Avf:

    y

    cvreqdnvf

    f

    AcVA

    =

    ( ) ( )

    ( )( )6000.1

    2.48100.0702.9 =vfA = 0.081 IN2/IN or 0.98 IN2/FT. CONTROLS

    Minimum steel requirement:

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    46/50

    46

    yvvf

    f

    sb05.0A (LRFD 5.8.4.1-4)

    Avf= (0.05) (48.2 IN) (12 IN) / 60 KSI = 0.482 IN2/ FT

    Use 2 # 5 @ 7 IN (Av provd = 1.06 IN2/FT Say OK Note that this limit depends directly

    on the width of the interface more steel is required for a wider interface)

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    47/50

    47

    12. Design and detail the end zone reinforcement

    12.1 Anchorage Zone Reinforcement

    LRFD 5.10.10.1 requires that the factored bursting resistance of a pretensioned

    anchorage zone be at least 4.0% of the total prestressing force. This resistance isprovided by vertical reinforcement close to the ends of pretensioned girders.

    The factored bursting resistance is given by

    Pr = fs As , (LRFD 5.10.10.1-1)

    where

    Pr = (0.04) Po = (0.04) [(0.75) (270 KSI) (17.794IN2)] = 144.13 KIP

    Note: The total jacking force prior to any losses is used as the total prestressing

    force Po in this calculation:

    fs is the working stress in the reinforcement, not to exceed 20 KSI.

    Solving for the required area of reinforcement, As:

    ( )KSI20

    KIP13.144

    f

    PA

    s

    rs == = 7.20IN

    2

    Therefore, at least 7.20 IN2 of vertical reinforcement must be placed within h/5 =

    78.7 IN / 5 = 15.7 IN from the end of the member. Stirrups placed for vertical or

    interface shear can also be used to satisfy this requirement since this reinforcement is

    only required to resist forces at release.

    Take # 7 stirrups @ 3 inch spacing

    2provided

    s IN20.76.0)2(6A ==

    Note: The first spacing from the end of the girder to the first stirrup is 3 inches as

    well.

    12.2 Confinement Reinforcement

    In accordance with LRFD 5.10.10.2, confinement reinforcement of not less than # 3

    bars at a spacing of not more than 6.0 IN shall be placed within 1.5 d (say 1.5 h =

    9.00 FT) from the end of the girder. These bars shall be shaped to enclose thestrands.

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    48/50

    48

    13 and 14. Mid-Span Camber at release and erection and live load deflection

    Curvature Values at mid-span

    Due to Initial prestressinitialci

    initialpspi

    IE

    eAf

    = = 2.08E-05

    Due to member weightinitialci

    gdr

    IE

    M

    = = -1.18E-05

    Due to loss (from initial to erection)finalci

    finalpsps

    IE

    eAf

    = = -1.97E-06

    Due to dead load on precast girderfinalc

    deck

    IE

    M

    = = -1.00E-05

    Due to dead load on composite sectioncompositefinalc

    dl

    IEM

    = = -1.76E-06

    Due to prestress loss (erection to final)compositelfinalc

    compositefinalps2ps

    IE

    eAf

    = = -1.91E-07

    Due to live loadcompositefinalc

    ll

    IE

    M

    = = -6.08E-06

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    49/50

    49

    Approximate Curvature Integration

    It is valid fMidspan End and two-po

    Initial prestress 2.08E-05 8.49E-06 13.79 13.79 23.85339714

    Member weight -1.18E-05 0 -6.99 -6.99 -12.08981378 due to pres

    Loss (initial to erection) -1.97E-06 -7.81E-07 -1.30 ------ -1.967053642

    Dead load on precast -1.00E-05 0 -5.95 ------ ------ Where

    Dead load on composite -1.76E-06 0 -1.04 ------ ------

    Loss (erection to final) -1.91E-07 -4.75E-07 -0.14 ------ ------ a = distancLive load -6.08E-06 0 ------ ------ ------

    Total 6.80 9.80 due to selfw

    Accurate Curvature Integration

    End 0.1L 0.2L 0.3L 0.4L Midspan

    Initial prestress 8.49E-06 1.29E-05 1.70E-05 1.96E-05 2.08E-05 2.08E-05

    Member weight 0 -4.44E-06 -6.76E-06 -9.97E-06 -1.13E-05 -1.18E-05

    Loss (initial to erection) -7.81E-07 -1.20E-06 -1.65E-06 -1.88E-06 -1.99E-06 -1.97E-06Dead load on precast 0 -3.77E-06 -6.57E-06 -8.49E-06 -9.62E-06 -1.00E-05

    Dead load on composite 0 -6.57E-07 -1.15E-06 -1.49E-06 -1.69E-06 -1.76E-06

    Loss (erection to final) -4.75E-07 -4.62E-07 -4.02E-07 -2.93E-07 -2.17E-07 -1.91E-07

    Live load 0 -2.29E-06 -4.03E-06 -5.21E-06 -5.90E-06 -6.08E-06Total

    The formula for deflection at midspan as a function of curvatures at (span/10) points, for simple spans and for interior spans.

    It may be used for end spans without much loss of accuracy. Symmetrical moment diagram about midspan is assumed) .

    ElasticCurvature

    Elastic CurvatureElastic Initial Erection

    )3

    7432

    6

    1(L01.0 543210

    2+++++=

    The live load deflection is 3.64 IN. The detailed calculations are shown in the attached Excel spreadsheet

  • 8/22/2019 200-Foot Simple Span Bridge Girder Design Using NU2000 V1

    50/50

    Calculating deflection by the elastic weight or moment-area method,

    Curvature

    Moment

    Load M

    !"!

    Figure 13.1: Deflection Calculation

    The equation in the Excel spreadsheet was developed by calculating the deflection at the

    mid-span section by taking the moment of the elastic loads at the mid-span. Assume that

    the curvature is symmetrical. Refer to Figure 13.1.