STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 20.04.13
1.Ground Floor slab 4 Flats Completed,5th Flat Planning Today 2.First Floor 1 & 2 flats Bar Bending Work In Progress
![Page 2: 20 04-2013](https://reader036.vdocuments.us/reader036/viewer/2022062523/58f1f8cb1a28ab935b8b4571/html5/thumbnails/2.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 20.04.13
1.Ground Floor slab 4 Flats Completed,5th Flat Planning Today 2.First Floor slab flat no 01 & 02 completed remain columns work in
progress
![Page 3: 20 04-2013](https://reader036.vdocuments.us/reader036/viewer/2022062523/58f1f8cb1a28ab935b8b4571/html5/thumbnails/3.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 20.04.13
1.Basement I slab Completed2.Ground Floor Flat No 01Beam Bottom Shuttering work in progress
![Page 4: 20 04-2013](https://reader036.vdocuments.us/reader036/viewer/2022062523/58f1f8cb1a28ab935b8b4571/html5/thumbnails/4.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 20.04.13
1.Ground Floor slab Completed2.First Floor Slab Shuttering work in progress for flat no 1 & 2
![Page 5: 20 04-2013](https://reader036.vdocuments.us/reader036/viewer/2022062523/58f1f8cb1a28ab935b8b4571/html5/thumbnails/5.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 20.04.13
1.Ground Floor slab 1 & 2 flats completed remaining flats bar bending work in progress
![Page 6: 20 04-2013](https://reader036.vdocuments.us/reader036/viewer/2022062523/58f1f8cb1a28ab935b8b4571/html5/thumbnails/6.jpg)
STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 20.04.131.Total Site Ground Floor slab Tower : A Completed Today
Tower : B Completed Today Tower: D Completed
2.Total Site First Floor slab Tower : B 2 Flats Completed